1.0 Detailed Definition of Alternatives

Size: px
Start display at page:

Download "1.0 Detailed Definition of Alternatives"

Transcription

1 1.0 Detailed Definition of Alternatives 1.1 Introduction This chapter provides supplemental information on the four alternatives, including both physical and operational characteristics (e.g. service plans) as well as additional route network and facility maps. The chapter also provides a comparative matrix of the four alternatives. The chapter contains the following information: Maps of route network and station stops for each alternative; Number of trips by end terminal for each alternative; Summary table of the station stops for all alternatives; Two comparative matrixes of the physical and operational characteristics of the four alternatives; Additional alignment and physical characteristics of the Streetcar Build Alternative; and Conceptual site plan for the streetcar s Operations and Maintenance (O&M) Facility in Pentagon City. The chapter is organized as followed: Table 1-3: Streetcar Build Alternative: Number of Trips by End Terminal Table 1-4: Streetcar Build Alternative: Streetcar Alignment Information Table 1-5: Streetcar Build Alternative: Streetcar Facility Information Table 1-6: Streetcar Build Alternative: Pentagon City O&M Facility Information Figure 1-5: Streetcar Build Alternative: Pentagon City Operation and Maintenance Facility Plan 1.5 Comparison of Alternatives This section provides one figure and three tables that compare the operational and physical characteristics of each alternative. The following tables and figures are provided: Figure 1-6: TSM 1, TSM 2, and Streetcar Build Alternatives: Route Network Table 1-7: Stop Locations by Alternative Table 1-8: Physical and Operational Characteristics for each Alternative Table 1-9: Additional Transit Attributes by Alternative 1.2 No Build Alternative This section provides operational information regarding the No Build Alternative. The following figures and tables are provided: Figure 1-1: No Build Alternative: Route Network Table 1-1: No Build Alternative: Number of Trips by End Terminal 1.3 TSM Alternatives This section provides operational information regarding the two TSM Alternatives. The following figures and tables are provided: Figure 1-2: TSM Alternatives: Route Network Table 1-2: TSM Alternatives: Number of Trips by End Terminal 1.4 Streetcar Build Alternative This section provides information on both the operational and physical characteristics, including information on the proposed Operations & Maintenance (O&M) facility, of the Streetcar Build Alternative. The following figures and tables are provided: Figure 1-3: Streetcar Alignment and and Background Bus Service Route Network Figure 1-4: Streetcar Build Alternative: Streetcar Alignment and Stop Locations May

2 Figure 1-1: No Build Alternative: Route Network 1-2 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

3 Table 1-1: No Build Alternative: Number of Trips by End Terminal Route Terminal points Hours of Service Pentagon Peak Vehicles Per Hour Eastbound Mid-Day Vehicles Per Hour - Eastbound 16A Annandale to Pentagon Metro Station Weekday - all day B Culmore to Pentagon Metro Station (weekend service to Annandale) Peak period, evenings, and weekends D Annandale to Pentagon Metro Station Weekday - all day E Culmore to Pentagon Metro Station via Pentagon City Evenings each day n/a n/a 16F Culmore to Pentagon and then into DC Limited Stop Peak period, peak direction J Culmore to Pentagon Metro Station All Day, Weekdays, Saturdays K Columbia Heights West to Pentagon Metro Station Weekend mornings only n/a n/a 16L Annandale to Pentagon Metro Express (via I-395) Weekday peak period/direction P Culmore to Pentagon Metro Station via Pentagon City Sunday - all day n/a n/a ART 42 Ballston to Pentagon Metro Station All day, Weekdays and Saturdays 3 2 Subtotal Pentagon (Note: 16L not included in schematic diagram - next slide does not run on Columbia Pike) 15 6 Pentagon City 16G Columbia Heights West to Pentagon City Metro Station All Day, 7 days per week H Skyline to Pentagon City Metro Station and then to Crystal City Peak period, peak direction only H/ Skyline to Pentagon City Metro Station Peak period, peak direction only 3 0 Subtotal Pentagon City 11 4 Other Routes 16Y Four Mile Run Road to Farragut Square Peak period, peak direction only 7 0 ART 41 Columbia Heights West to Court House All day, 7 days per week 4 4 ART 45 Four Mile Run Drive to Rosslyn All Day weekdays only 2 2 Streetcar No service in No-Build No service in No-Build n/a n/a May

4 Figure 1-2: TSM Alternatives: Route Network 1-4 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

5 Table 1-2: TSM Alternatives: Number of Trips by End Terminal (TSM 1 and TSM 2 Alternative have the same service pattern) Route Terminal points Hours of Service Peak Vehicles Per Mid-Day Vehicles Per Hour Eastbound Hour - Eastbound Pentagon 16A Annandale to Pentagon Metro Station (will run as limited stop) Weekday - all day B Culmore to Pentagon Metro Station (weekend Peak period, evenings, and service to Annandale) weekends D Annandale to Pentagon Metro Station (will run as limited stop) Weekday - all day E Culmore to Pentagon Metro Station via Pentagon City Evenings each day n/a n/a 16F Culmore to Federal Triangle via Pentagon (will remain as Limited Stop) Peak period, peak direction J Culmore to Pentagon Metro Station All Day, Weekdays, Saturdays K Columbia Heights West to Pentagon Metro Station Weekend mornings only n/a n/a 16L 16P Annandale to Pentagon Express (via I-395) Culmore to Pentagon Metro Station via Pentagon City Weekday peak period, peak direction 2 0 Sunday - all day n/a n/a ART 42 Ballston to Pentagon Metro Station All day, Weekdays and Saturdays 3 2 Subtotal Pentagon 15 6 Pentagon City 16G* Skyline (TSM 2)/NOVA (TSM 1) to 12th Street South (Conference Center) All Day, 7 days per week H* Skyline (TSM 2)/NOVA (TSM 1) to Pentagon City and then to Crystal City Weekday, All Day H/* Skyline (TSM 2)/NOVA (TSM 1) to 12th Street South (Conference Center) Weekday, All Day 4 3 Subtotal Pentagon City Other Routes 16Y Four Mile Run Road to Farragut Square Peak period, peak direction only 7 0 ART 41 Columbia Heights West to Court House All day, 7 days per week 8 8 ART 45 Four Mile Run Drive to Rosslyn All Day weekdays only 2 2 Streetcar No service in TSM No service in TSM n/a n/a May

6 Figure 1-3: Streetcar Build Alternative: Streetcar Alignment and Background Bus Service Route Network 1-6 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

7 Figure 1-4: Streetcar Build Alternative: Streetcar Alignment and Stop Locations May

8 1-8 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

9 Table 1-3: Streetcar Build Alternative: Number of Trips by End Terminal Route Terminal points Hours of Service Peak Vehicles Per Hour Eastbound Mid-Day Vehicles Per Hour - Eastbound Pentagon 16A Annandale to Pentagon Metro Station (will run as limited stop) Weekday - all day B Culmore to Pentagon Metro Station weekend Peak Periods, evenings and service to Annandale) weekends D Annandale to Pentagon Metro Station (will run as limited stop) Weekday - all day E Culmore to Pentagon Metro Station via Pentagon City Evenings each day n/a n/a 16F Culmore to Federal Triangle via Pentagon Remains Limited Stop Peak period J Culmore to Pentagon Metro Station All Day weekdays, Saturdays K 16L 16P Columbia Heights West to Pentagon Metro Station Annandale to Pentagon Express (via I-395) Culmore to Pentagon Metro Station via Pentagon City Weekend mornings only n/a n/a Weekday peak period, peak direction 2 0 Sunday - all day n/a n/a ART 42 Ballston to Pentagon Metro Station All day, Weekdays and Saturdays 3 2 Pentagon Subtotal 15 6 Pentagon City Streetcar Skyline to 12 th Street South (Conference Center) All Day, 7 days per week J (PC) Culmore to Pentagon City Metro Station Peak Period Only G Removed in Build Removed in Build n/a n/a 16H Removed in Build Removed in Build n/a n/a 16H/ Removed in Build Removed in Build n/a n/a Pentagon City Subtotal Other Routes 16Y Four Mile Run Road to Farragut Square Peak period, peak direction only 7 0 ART 41 Columbia Heights West to Court House All day, 7 days per week 8 8 ART 45 Four Mile Run Drive to Rosslyn All Day weekdays only 2 2 May

10 Table 1-4: Streetcar Build Alternative: Streetcar Alignment Information Alignment Eastern Terminus Pentagon City (12 th Street/South Eads Street) Design Options for Design Option: Skyline - Jefferson Street Western Terminus Transit Center Design Option: Skyline Central Plaza Design Option: Skyline at Route 7 Design Options for Roadway Alignment Areas of Median Running Alignment Length Non-Revenue Length Track Current Columbia Pike alignment between the Navy Annex and Joyce Street Realigned Columbia Pike between the Navy Annex and Joyce Street (Contingent upon land swap with DOD) Median running segments: Jefferson Street between Leesburg Pike and Columbia Pike (0.51 miles); exclusive guideway along a portion of Jefferson Street for Design Option Skyline- Jefferson Street Transit Center (approximately 400 feet) South Joyce Street between Army Navy Drive and Columbia Pike (0.30 miles) South Hayes Street/Army Navy Drive to 12 th Street/South Eads Street (0.42 miles); exclusive guideway along a portion of 12 th Street between Fern and Eads (approximately 300 feet) 4.71 miles (Design Option: Jefferson Street Transit Center) 4.94 miles (Design Option: Skyline Central Plaza) 4.91 miles (Design Option: Skyline at Route 7) 160 feet Table 1-5: Streetcar Build Alternative: Streetcar Facility Information Facilities Stops 18 stop locations in each direction (Design Option: Skyline - Jefferson Street Transit Center); 19 stop locations in each direction (Design Options Skyline Central Plaza and Skyline at Route 7). (Note: Some stop improvements implemented under the No Build Alternative.) See Table 6 for list of stops Operations and Pentagon City (along Eads Street between 12 th Maintenance Facility Street and Army Navy Drive) Transit Center Jefferson Street (Baileys Crossroads): at-grade offstreet bus bays and approximately 200 surface park-and-ride spaces. Construction Staging and Equipment Storage Facility Traction Power Substations Along Columbia Pike near Navy Annex Army Navy Drive/I-395 ramp Washington Boulevard interchange Oakland Street Randolph Street/George Mason Drive Jefferson Street Transit Center Table 1-6: Streetcar Build: Pentagon City O&M Facility Information Pentagon City O&M facility Shop Building (sf.): 12,000 Fleet Size (no. of cars): 13 Rail Vehicle Storage: 13 Turnouts: 4 Access: 12th street Traction Power Substations: 1 Duties Performed Daily maintenance, inspections, running repair, wheel truing, component change-out/cyclical maintenance 1-10 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

11 Figure 1-5: Streetcar Build Alternative: Pentagon City Operation and Maintenance Facility Concept Plan May

12 Figure 1-6: TSM 1, TSM 2, and Build Alternatives: Route Network 1-12 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

13 Table 1-7: Stop Locations by Alternative Station ID General Location No Build Streetcar Build (incl. TSM Alternatives (existing) platform location) Local Pentagon City (varies by route) Background bus service A 12th St/Eads St center B Pentagon City Metro/S. Hayes St center C Army Navy Drive/S. Joyce St curbside D S. Joyce St center Local Southgate Rd - - E Heritage Center (Oak St) curbside Local S. Orme St - - Local Rolfe St - - F Scott St curbside G S. Courthouse Rd curbside H S. Barton St curbside I Walter Reed Drive curbside Local S. Highland St - - J S. Glebe Rd curbside K S. Monroe St - curbside Local S. Oakland St - Local S. Quincy St - - L George Mason Drive curbside M S. Thomas St curbside N S. Buchanan/Four Mile Run Dr curbside O Arlington Mill (Dinwiddie St) curbside Local Frederick St - - P Greenbrier St curbside Local Wildwood Park/Windsor Towers - - Local Jefferson St near Columbia Pike (westbound only) - - Q Jefferson St - Goodwin House center* R Jefferson St near Leesburg Pike S Skyline Complex Various locations (TSM 1) At transit center (TSM 2) At George Mason Dr (TSM 1) In Skyline Complex (TSM 2) At transit center curbside May

14 Physical Characteristics Table 1-8: Physical and Operational Characteristics for each Alternative Transit vehicles Transit alignments Stop locations Assumed street improvements Station configuration and boarding Station attributespassenger info, shelter, etc. Park-and-ride, transfer facilities No Build TSM 1 TSM 2 Streetcar Build 60-foot articulated buses on 66-foot electric tram, routes 16G, 16H (capacity of capacity of 44 seated 60 seated passengers/34 passengers/71 standees. standees) Metrobus: 40-foot compressed natural gas (CNG) buses (capacity for 41 seated passengers/22 standees). ART: 31- or 35-foot CNG buses with capacity for 25 seated/10 standing Metrobus 16 Line and coordinated ART service ( PikeRide ) Stops located at most intersections, approximately 1/8- mile apart Ongoing roadway reconstruction projects, see Table for a detailed description Implementation of Super Stops with raised boarding areas along Columbia Pike; boarding through front door Ongoing stop improvements program to add basic shelters and schedule information; Super Stops have enhanced shelters and display real-time information Small park-and-ride at Columbia Pike and Four Mile Run Drive Same as No Build Alternative Enhanced bus network along project corridor with a focus on providing improved service to Skyline Consolidate selected bus stops; ¼ to ½ mile spacing to support high activity locations and provide efficient transit operations Same as No Build Alternative Continued implementation of the Super Stops program along Columbia Pike at consolidated stops; boarding through front door Ongoing stop improvements program to add basic shelters and schedule information; Super Stops have enhanced shelters and display real-time information Same as No Build Alternative 40-foot CNG buses on remaining Metrobus routes. 31- or 35-foot CNG buses on ART routes Same as TSM 1 Alternative Same as TSM 1 Alternative All projects included under No Build; Minimum street improvements required for implementation of transit improvements (set curb and median to accommodate vehicular left turns, pedestrian movements, etc.) Implementation of Super Stops with raised boarding areas along full ~5 mile alignment (Skyline to Pentagon City); boarding and alighting through all doors Consolidated stops that have not been upgraded through the Super Stops program will have enhanced shelters and display real-time information, similar in design of the Super Stops. Same as No Build; Plus, a parking and intermodal transfer facility on Jefferson Street near Baileys Crossroads. 40-foot CNG buses on complementary Metrobus service. 31- or 35-foot CNG buses on ART routes Streetcar service along 5- mile alignment between Skyline and Pentagon City with complementary bus network Same as TSM 1 Alternative All projects included under No Build; Minimum street improvements required for implementation of streetcar (set curb and median to accommodate vehicular left turns, pedestrian movements, etc.) Same as TSM 2 Alternative Same as TSM 2 Alternative Same as TSM 2 Alternative 1-14 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

15 Storage and maintenance facilities Vehicle propulsion Background bus service Intelligent Transportation Systems (ITS) Service Frequency Fare Policy and Pricing Operating speed and travel time (peakhour, peak-direction 2016 and 2030) Service hours No Build TSM 1 TSM 2 Streetcar Build Existing bus maintenance and storage facility at Four Mile Run. ART buses will be stored and maintained at the Art House facility Internal combustion engines powered by CNG Metrobus 16 Line and coordinated ART services, DASH buses serving NOVA; additional Metrobus service crossing Columbia Pike Real-time passenger information available via internet and phone and at some stops; transit signal priority No expected change: 2-3 minutes in the peak along trunk (4-6 minutes to both the Pentagon and Pentagon City); 6-minute offpeak headways along trunk (10-15 minutes to both the Pentagon and Pentagon City) On-board fare collection, with SmarTrip, cash, day pass, and flash pass Vehicles travel at posted speed limits; peak travel time 28 mins (2016) and 20 mins (2030) Weekday 5:00 am to 1:30 am (Friday until 3:30 am); Saturday 5:30 am to 3:30 am; Sunday 6:00 am to 12:30 am Same as No Build Alternative Same as No Build Alternative Adjust No Build corridor bus service to better serve Skyline and provide more frequent midday service along Columbia Pike Same as No Build. However, articulated buses would be stored and maintained at WMATA s Cinder Bed Road facility Same as No Build Alternative Same as TSM 1 Alternative Same as No Build. Plus, the addition of a new streetcar O&M facility at Pentagon City. Overhead electric contact wire and traction power substations to power streetcars; CNG buses Adjust bus network to supplement proposed streetcar service Same as No Build Alternative Same as No Build Alternative Same as No Build Alternative 2-3 minute peak headways along trunk to match current Columbia Pike service. Includes 6-minute off-peak headways along trunk (10-15 minutes to both the Pentagon and Pentagon City) Same as No Build Alternative Vehicles travel at posted speed limits; peak travel time 26 mins (2016) and 28 mins (2030) Same as TSM 1 Alternative Off-board fare collection with proof of payment Vehicles travel at posted speed limits; peak travel time 23 mins (2016) and 25 mins (2030) Same as TSM 1 Alternative Same as TSM 2 Alternative Vehicles travel at posted speed limits; peak travel time 22 mins (2016) and 23 mins (2030) Match Metro service hours Same as TSM 1 Alternative Same as TSM 1 Alternative May

16 Table 1-9: Additional Transit Attributes by Alternative No Build TSM 1 TSM 2 Streetcar Build Vehicles- standard, articulated buses, streetcars Branding- signage Standard buses Continuation of ART local bus branding; PikeRide branding Same as No Build Continuation of ART local bus branding; Special branding for Pentagon City trunk line: 16G, 16H, 16J; Metro Extra branding for: Pentagon 16A, 16B, 16D Express to Downtown Washington 16Y, 16F Fare collection SmarTrip and cash on-vehicle Same as No Build Station configuration and boarding Station attributespassenger info, shelter, etc. Implementation of Super Stops with raised boarding areas along Columbia Pike Ongoing stop improvements program to add basic shelters and schedule information; Super Stops have enhanced shelters and display of realtime information Same as No Build Ongoing stop improvements program to add basic shelters and schedule information; Super Stops have enhanced shelters and display of realtime information Articulated buses on selected routes: 16G, 16H, Continuation of ART local bus branding; Special branding for Pentagon City trunk line: 16G, 16H, 16J; Metro Extra branding for: Pentagon 16A, 16B, 16D Express to Downtown Washington 16Y, 16F Off-vehicle payment and validation; on-board random inspections Implementation of Enhanced Stops (similar in design to Super Stops) with raised boarding areas along full ~5 mile alignment (Skyline to Pentagon City); boarding and alighting through all doors All stops have enhanced shelters and display of realtime information Streetcars and standard buses Continuation of ART local bus branding; Streetcar branding for Pentagon City service; Metro Extra branding for: Pentagon 16A, 16B, 16D Express to Downtown Washington 16Y, 16F Same as TSM 2 Same as TSM 2 All stops have enhanced shelters and display of realtime information 1-16 Columbia Pike Transit Initiative Alternatives Analysis/Environmental Assessment Volume II

14.0 Capital Cost Estimate Methodology

14.0 Capital Cost Estimate Methodology 14.0 Capital Cost Estimate Methodology 14.1 Purpose of the Memorandum This memorandum documents the major assumptions that inform the conceptual capital cost estimates for the transit improvement alternatives

More information

COLUMBIA PIKE TRANSIT INITIATIVE

COLUMBIA PIKE TRANSIT INITIATIVE COLUMBIA PIKE TRANSIT INITIATIVE Engineering Report October 2012 COLUMBIA PIKE TRANSIT INITIATIVE Engineering Report Table of Contents PART A: GENERAL 1 PART B: ACTION ITEMS LIST 1 PART 1 - SYSTEM DEFINITION

More information

Riding Metrobus 16H from GHBC to Pentagon City (last update Oct )

Riding Metrobus 16H from GHBC to Pentagon City (last update Oct ) Riding Metrobus 16H from GHBC to Pentagon City (last update Oct-17-2018) WMATA s Metrobus 16H is a very convenient, low-cost way for GHBC residents to get to/from Pentagon City for: o o Shopping trips

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period 8. Operating Plans The following Section presents the operating plans for the Short-List Alternatives. The modern streetcar operating plans are presented for Alternatives 2 and 3, followed by bus rapid

More information

Background Information about the Metrobus 29 Lines Study

Background Information about the Metrobus 29 Lines Study Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area. DRAFT Project Summaries

Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area. DRAFT Project Summaries Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area DRAFT Project Summaries May 2009 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROJECTS... 3 2.1

More information

West Rosslyn Development

West Rosslyn Development Traffic Impact Study and Transportation Management Plan West Rosslyn Development Arlington County, VA Revised: January 11, 2017 May 10, 2016 Prepared for: Penzance 2400 N Street, NW, Suite 600 Washington,

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

HISTORIC TRAFFIC COUNT DATA ( )

HISTORIC TRAFFIC COUNT DATA ( ) HISTORIC TRAFFIC COUNT DATA (1980 2015) Highlights The traffic trends for 25 locations in the 22202 zip code area have decreased by 20 percent (on average) since 2000, when traffic peaked. Currently, average

More information

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014 TBARTA USF to Wesley Chapel Express Bus Service Operating Plan Draft 3/25/2014 March 2014 Table of Contents 1.0 Introduction... 1 2.0 Study Area... 1 3.0 Existing Available Service... 3 4.0 Proposed Service...

More information

DETAILED DEFINITION OF ALTERNATIVES. July 2014 FINAL

DETAILED DEFINITION OF ALTERNATIVES. July 2014 FINAL DETAILED DEFINITION OF ALTERNATIVES July 2014 Table of Contents 1.0 Introduction... 1 1.1 Detailed Mode Alternatives... 1 1.2 Detailed Alignment Alternatives... 1 1.3 Key Physical and Service Elements...

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

State Avenue Corridor Bus Rapid Transit (BRT)

State Avenue Corridor Bus Rapid Transit (BRT) State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!

More information

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report REVISIONS 1. Table 39: New Public Investments for Operation and Maintenance Costs 2. Appendix A-10: Passenger Rail Service - Operations

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Metro Transit Arterial Transitway Corridors Study

Metro Transit Arterial Transitway Corridors Study Metro Transit Arterial Transitway Corridors Study Technical Memorandum #3 Corridor Mode Development 2/1/2012 Prepared by the SRF Consulting Group Team Table of Contents Introduction... 1 Concept Plans...

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Detailed Definition of Alternatives

Detailed Definition of Alternatives West Broadway Transit Study Detailed Definition of Alternatives 9/4/2015 DRAFT Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 2040 No-Build Alternative... 1 Build Alternatives...

More information

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis

More information

Appendix B. Tier 2 Final Environmental Assessment I-66 Transit/TDM Technical Report

Appendix B. Tier 2 Final Environmental Assessment I-66 Transit/TDM Technical Report Tier 2 Final Environmental Assessment I-66 Transit/TDM Technical Report Appendix B Bus Bay, Maintenance, and Storage Capacity Analysis Technical Memorandum FINAL MAY 2016 INTRODUCTION This technical memorandum

More information

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...

More information

GLEBE 672 TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA. Section 1 INTRODUCTION 1

GLEBE 672 TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA. Section 1 INTRODUCTION 1 GLEBE 672 TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA TABLE OF CONTENTS Page Section 1 INTRODUCTION 1 Section 2 BACKGROUND INFORMATION 6 Public Road Network... 6 Non Auto Facilities and Services...

More information

Update on Bus Stop Enhancements

Update on Bus Stop Enhancements Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Figure 2-14: Existing Bus Routing at Irwindale Station

Figure 2-14: Existing Bus Routing at Irwindale Station 494 W oothill Blvd 69 N Irwindale Ave 185 Irwindale E 1st St 3 6 feet igure 2-14: Existing Bus Routing at Irwindale 39 Proposed Bus Route 494 W oothill Blvd Proposed Discontinued Bus Route Proposed New

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Service Quality: Higher Ridership: Very Affordable: Image:

Service Quality: Higher Ridership: Very Affordable: Image: Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to

More information

FACT SHEET. US 192 Alternatives Analysis Modal Technologies. Alternative Description/Overview

FACT SHEET. US 192 Alternatives Analysis Modal Technologies. Alternative Description/Overview FACT SHEET US 192 Alternatives Analysis Modal Technologies Bus Alternative Description/Overview Bus systems typically operate in mixed traffic and have minimal station infrastructure. Bus service typically

More information

2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS

2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS 2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS In the Study Area, as in most of the Metro Transit network, there are two distinct route structures. The base service structure operates all day and the peak

More information

Proposed FY2015 Budget and Fare Increase

Proposed FY2015 Budget and Fare Increase Washington Metropolitan Area Transit Authority Proposed FY2015 Budget and Fare Increase Riders Advisory Council January 8, 2014 1 Washington Metropolitan Area Transit Authority What will riders see from

More information

Central Maryland Transit Development Plan

Central Maryland Transit Development Plan Central Maryland Transit Development Plan Planning the Future of Transit in Our Region Anne Arundel County Transportation Commission December 13, 2017 Anne Arundel County Howard County Prince George s

More information

Reston Transportation Strategy July 9, 2018

Reston Transportation Strategy July 9, 2018 Reston Transportation Strategy July 9, 2018 Background: On February 11, 2014, the Board of Supervisors adopted the Reston Phase I Comprehensive Plan Amendment for the core areas of Reston between Sunset

More information

JOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm

JOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm ART and APS Bus Parking Informational Session July 27, 2017 7 8:30 pm 2 Agenda Introductions & overview APS Bus Parking APS Bus Facts APS Bus Operations ART Bus Parking Story of ART and its role in County

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

NVTA SIX YEAR PLAN PROJECTS BY MODE

NVTA SIX YEAR PLAN PROJECTS BY MODE NVTA SIX YEAR PLAN PROJECTS BY MODE FINAL Rebuild the King Street Metro Parking Lot and Bus Loading Area This project will reconfigure the existing Metrorail station parking lot, maximize bus bay capacity

More information

EAST-WEST BUS RAPID TRANSIT Service Plan and Operations and Maintenance (O&M) Cost Memo

EAST-WEST BUS RAPID TRANSIT Service Plan and Operations and Maintenance (O&M) Cost Memo EAST-WEST BUS RAPID TRANSIT Service Plan and Operations and Maintenance (O&M) Cost Memo This memo documents the proposed service plan, operating statistics, and O&M cost for the East-West BRT and background

More information

Community Outreach Meetings

Community Outreach Meetings Community Outreach Meetings BCT At A Glance 410 square miles service area More than 41.5 million annual trips 327 fixed-route buses 44 bus routes 78 Community Buses in 19 Municipalities BCT At A Glance

More information

TRANSPORTATION EFFECTS

TRANSPORTATION EFFECTS 6 TRANSPORTATION EFFECTS This chapter describes the long-term and construction effects of the No Build Alternative, the Wiehle Avenue, and the full LPA on the local and regional transportation network.

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

Where will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run?

Where will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run? Where will 32 65 87 223 Rosedale Transit Center 225 227 264 801 ROSEVILLE 65 Snelling & County Road B BRT run? Snelling & Roselawn FALCON HEIGHTS BRT will serve 20 stations along the line, connecting to

More information

1.0 INTRODUCTION Organization of this Report Study Area EXISTING CONDITIONS CTA Rail Forest Park Branch...

1.0 INTRODUCTION Organization of this Report Study Area EXISTING CONDITIONS CTA Rail Forest Park Branch... Table of Contents 1.0 INTRODUCTION... 4 1.1 Organization of this Report... 4 1.2 Study Area... 4 2.0 EXISTING CONDITIONS... 5 2.1 CTA Rail Forest Park Branch... 5 3.0 SERVICE PATTERNS... 6 3.1 Car Requirements...

More information

Basic Project Information

Basic Project Information FY 2015-16 PROJECT DESCRIPTION FORM (9F) Submitting Agency: Arlington County Basic Project Information Project Title: Glebe Road Corridor Intelligent Transportation Systems (9F) Project Type (check one):

More information

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project

More information

Streetcar and Light Rail Design Differences. March 2015

Streetcar and Light Rail Design Differences. March 2015 Streetcar and Light Rail Design Differences March 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets served

More information

1 On Time Performance

1 On Time Performance MEMORANDUM: US 29 Travel Time & OTP To: From: Joana Conklin, Montgomery County DOT James A. Bunch, SWAI Subject: US 29 Travel Time and On Time Performance Analysis Date: This memorandum documents the US

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) A: 2014 SFMTA TRANSIT SERVICE INFORMATION B: SFMTA TRAFFIC COUNT DATA C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) E: LAND USE AND VALUE

More information

METRO Light Rail Update

METRO Light Rail Update American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations

More information

SERVICE DESIGN GUIDELINES

SERVICE DESIGN GUIDELINES VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative PRELIMINARY ORDER OF MAGNITUDE CAPITAL COST ESTIMATING METHODOLOGY Technical Memorandum December 2011 Prepared for: Metropolitan Atlanta Rapid Transit Authority Atlanta, GA

More information

SERVICE IMPROVEMENT GUIDE

SERVICE IMPROVEMENT GUIDE SOUTH COOK COUNTY / WILL COUNTY RESTRUCTURING INITIATIVE SERVICE IMPROVEMENT GUIDE Working to Improve Your Commute Change has arrived for residents of south and southwest Cook County, in the form of improved

More information

Minutes (Approved, with edit, July 12, 2017)

Minutes (Approved, with edit, July 12, 2017) Arlington Pedestrian Advisory Committee (PAC) Wednesday, June 14, 2017 Joint Transit Advisory Committee (TAC) Pedestrian Advisory Committee (PAC) Bus Tour Minutes (Approved, with edit, July 12, 2017) Present

More information

Chicago Transit Authority Service Standards and Policies

Chicago Transit Authority Service Standards and Policies Chicago Transit Authority Service Standards and Policies Overview and Objectives The Chicago Transit Authority (CTA) has revised its Service Standards and Policies in accordance with Federal Transit Administration

More information

Transit Access Study

Transit Access Study West of Hudson Regional Transit Access Study Open House presentation July 20, 2010 1 Agenda Progress To date Summary of Level 2 Alternatives and Screening Service Plans Bus and Rail Operating and Capital

More information

Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan. Virginia Square Site

Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan. Virginia Square Site Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan Virginia Square Site Staff Presentation October 1, 2013 Meeting Agenda Introductions Analysis of Office Uses in Virginia Square

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

VAN NESS AVENUE BUS RAPID TRANSIT

VAN NESS AVENUE BUS RAPID TRANSIT VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running

More information

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited.

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited. RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Guycoki (Eastern) Limited June 16, 2016 116-638 Brief_1.doc D. J. Halpenny & Associates Ltd. Consulting

More information

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016 Clifton Corridor Transit Initiative Briefing to Great Lakes Community February 11, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project What are the different

More information

MTA New York City Transit Service Guidelines Manual

MTA New York City Transit Service Guidelines Manual MTA New York City Transit Service Guidelines Manual Thomas F. Prendergast, President Robert Bergen, Executive Vice President Division of Operations Planning Peter G. Cafiero, Chief August 2010 Table of

More information

2010 Virginia Department of Transportation Daily Traffic Volume Estimates Including Vehicle Classification Estimates. Jurisdiction Report 00

2010 Virginia Department of Transportation Daily Traffic Volume Estimates Including Vehicle Classification Estimates. Jurisdiction Report 00 Daily Traffic Volume Estimates Including Vehicle Classification Estimates where available Jurisdiction Report 00 Arlington County City of Alexandria Prepared By In Cooperation With U.S. Department of Transportation

More information

VIRGINIA HOSPITAL CENTER MULTIMODAL TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA TABLE OF CONTENTS

VIRGINIA HOSPITAL CENTER MULTIMODAL TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA TABLE OF CONTENTS VIRGINIA HOSPITAL CENTER MULTIMODAL TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA TABLE OF CONTENTS Section INTRODUCTION Introduction... Study Scope... 2 Section 2 BACKGROUND INFORMATION Existing

More information

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1 Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule

More information

Leesburg Dulles Greenway BRT Feasibility

Leesburg Dulles Greenway BRT Feasibility Leesburg Dulles Greenway BRT Feasibility May 28, 2008 Introduction Increase the use of public transit service by local residents, employees, and visitors alike to help reduce motor vehicle use and traffic

More information

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP

More information

Expansion Projects Description

Expansion Projects Description Expansion Projects Description The Turnpike expansion program was authorized by the Florida Legislature in 1990 to meet the State s backlog of needed highway facilities. The Legislature set environmental

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

Click to edit Master title style

Click to edit Master title style Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment

More information

Midtown Corridor Alternatives Analysis Key Issues Memo

Midtown Corridor Alternatives Analysis Key Issues Memo Midtown Corridor Alternatives Analysis Key Issues Memo 1/4/2013 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 1. Markets... 1 External Markets... 1 Intra-Corridor Travel...

More information

3.0 TRANSPORTATION ISSUES AND ANALYSIS

3.0 TRANSPORTATION ISSUES AND ANALYSIS 3.0 TRANSPORTATION ISSUES AND ANALYSIS 3.1 Transit Analysis The following sections address the anticipated transit service levels under each of the alternatives considered in the detailed screening as

More information

DRAFT BUS TRANSFORMATION PROJECT

DRAFT BUS TRANSFORMATION PROJECT BUS TRANSFORMATION PROJECT Bus System Today October 2018 The current regional system includes nine bus service providers: WMATA Loudoun County Transit The Bus Fairfax County Connector RideOn ART DASH CUE

More information

Highway Transitway Corridor Study

Highway Transitway Corridor Study Highway Transitway Corridor Study Technical Memorandum 3: Corridor Concepts and Evaluation Prepared for: Metropolitan Council May 2014 SRF No. 7994 Table of Contents Introduction... 1 Concept Development...

More information

WAKE TRANSIT PLAN Summer 2018

WAKE TRANSIT PLAN Summer 2018 WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.

More information

Service Planning Open House

Service Planning Open House Service Planning Open House Presentation to Community RTA Board Room July 17, 2018 575 EYES See Something, Text Something Transit App RTA CLE Mobile Ticketing Bus Stop Consolidation/Safety Improvement

More information

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012 Station Evaluation Durham-Orange Light Rail Transit Project Spring 2012 Key Ingredients for Station Development Platform Designs UNC Hospitals Station The UNC Hospitals Station Option D would be the westerly

More information

Stakeholders Advisory Working Group Traffic and Transit Group Meeting #4, October 10, 2007

Stakeholders Advisory Working Group Traffic and Transit Group Meeting #4, October 10, 2007 Contact Us FAQs Search + HOME + ABOUT THE STUDY + ALTERNATIVES + PUBLIC INVOLVEMENT + WORKING GROUPS + PRESS RELEASES + LIBRARY Stakeholders Advisory Working Group Traffic and Transit Group Meeting #4,

More information

Trip Generation and Parking Study New Californian Apartments, Berkeley

Trip Generation and Parking Study New Californian Apartments, Berkeley Trip Generation and Parking Study New Californian Apartments, Berkeley Institute of Transportation Engineers University of California, Berkeley Student Chapter Spring 2012 Background The ITE Student Chapter

More information

Sound Transit East Link: Bus/LRT System Integration Study

Sound Transit East Link: Bus/LRT System Integration Study Sound Transit East Link: Bus/LRT System Integration Study Prepared For: Sound Transit King County Metro Mercer Island WSDOT Prepared By: CH2M HILL July, 2014 1 SOUND TRANSIT EAST LINK: BUS/LRT SYSTEMES

More information

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville

Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville 1. Introduction During the stakeholder input sessions of Charlottesville Area Transit s (CAT) Transit Development

More information

Countywide Transit Corridors Functional Master Plan. Appendix 9 Travel Demand Forecasting Model Documentation

Countywide Transit Corridors Functional Master Plan. Appendix 9 Travel Demand Forecasting Model Documentation Countywide Transit Corridors Functional Master Plan Appendix 9 Travel Demand Forecasting Model Documentation Tower 1, 10 th Floor 100 S. Charles Street Baltimore, MD 21201-2727 (410) 727-5050 Memorandum

More information

Master Transportation Plan. Transit Element

Master Transportation Plan. Transit Element Transit Element March, 2009 1 Table of Contents I. Introduction...1 II. Summary...2 III. Policies, Implementation Actions and Performance Measures.4 IV. The Primary and Secondary Transit Networks....13

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

NVR AT BALLSTON TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA

NVR AT BALLSTON TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA NVR AT BALLSTON TRAFFIC IMPACT ANALYSIS ARLINGTON COUNTY, VIRGINIA Prepared for: NVR, Incorporated Prepared by: Wells + Associates, Inc. Michael Workosky, PTP, TOPS, TSOS John Cavan, P.E., PTOE 703.917.6620

More information

MEMORANDUM. WMATA Service Evaluation Study BService Routes City Staff Recommendation

MEMORANDUM. WMATA Service Evaluation Study BService Routes City Staff Recommendation A r 4 i9ul Hvcalibiir tload 916 I3o rie 1larvl Z11716 j KA MEMORANDUM TO FROM SUBJECT City Council David J Deutsch City Manager WMATA Service Evaluation Study BService Routes City Staff Recommendation

More information

Increase Rail Service to the Mid City Green Line Stations

Increase Rail Service to the Mid City Green Line Stations Washington Metropolitan Area Transit Authority Increase Rail Service to the Mid City Green Line Stations P D E C Presented to the Board of Directors: Planning and Development Committee by Planning, Development,

More information

Metrorail Line Load Application

Metrorail Line Load Application Metrorail Line Load Application Presented to Travel Demand Forecasting Subcommittee Wendy Jia & Tom Harrington, WMATA Bassel Younan & Jeff Bruggeman, AECOM November 20, 2009 Metrorail Line Load Application

More information