Feasibility Update. RMRA Feasibility Study Steering Committee. Study Work Schedule: Tasks 1 thru February 27, 2009.

Size: px
Start display at page:

Download "Feasibility Update. RMRA Feasibility Study Steering Committee. Study Work Schedule: Tasks 1 thru February 27, 2009."

Transcription

1 Presentation To RMRA Feasibility Study Steering Committee Feasibility Update February 7, 9 TEMS, Inc. / Quandel Consultants, LLC 1 Study Work Schedule: Tasks 1 thru 4.4.

2 Study Work Schedule: Tasks 4.5 thru February Public Involvement Update Finalized and attained approval on stakeholder blast Distributed on /5 to nearly 1, contacts Community Partnership Program Materials Newsletter Article Station Map Alternatives Fact Sheet Distributed Community Partnership Program Materials to 1+ organizations on /5 Continued coordination w/ I-7 Coalition and other studies (e.g. Gaming Area EIS) 4

3 Engineering Segments: Unconstrained Rail Network 5 Engineering Segments: Constrained Rail and Maglev Network 6

4 Operations: I-5 I South Joint Line Rail Corridor Consists of two tracks former DRGW (UP) and ATSF (BNSF) alignment Proposing to undo USRA-era mix and match that has been in place since 1918 This becomes the starting point for a further program of curve easements Almost completely separate freight from passenger operations DRGW ATSF DRGW Denver ATSF Sedalia DRGW Spruce ATSF North Colorado Springs Passenger Alignment Freight Alignment Buttes to Fountain section, issue of which track segment to use DRGW ATSF ATSF DRGW South Colorado Springs DRGW Buttes DRGW Pueblo 7 Joint Line: Nixon Power Plant Former ATSF Alignment paralleling I-5I 8

5 Joint Line and Spanish Peak Lines Joint Line, Littleton to Pueblo With RC - ATSF alignment used for passengers; DRGW for freight. Equip DRGW with bi-directional Traffic Control and mile passing sidings at 1 mile intervals (same as parallel RC line freight configuration.) Without RC Fully replace the ATSF track by double tracking the DRGW alignment for freight with universal crossovers every 8-1 miles (except possibly from Palmer Lake to Colorado Springs where the passenger system builds it own track on the abandoned ATSF grade.) Spanish Peaks Line, Pueblo to Trinidad With RC Spanish Peaks line will lose most of its freight traffic (Empty coal trains) as a result of RC diversion. Upgrade one of the two tracks from Pueblo to Walsenburg to 11-mph, and single track from Walsenburg to Trinidad to best available speed based on curvature. Without RC Upgrade one of the two tracks Pueblo to Walsenburg to 11-mph and co-mingle with freight (empty coal trains) at 79-mph from Walsenburg to Trinidad. 9 Joint Line: Littleton to DUS The Trench Crestline Ave Prop Freight Prop Psgr South Suburban Sta Shift LRT west onto siding to make Room for 4 th Trk KEY W/ RC W/O RC In these areas, some freight tracks on 14 center to Light Rail. Shift freight track to make room and widen track centers to LRT 1

6 Joint Line Bridges over C-47C 11 Rail Tracks Converging South of LRT 1

7 End of LRT South of Mineral Station 13 Littleton Trench 14

8 LRT Flyover Looking South 15 Four Tracks South of LRT Flyover Four Tracks Here already! 16

9 Freight on 14 Center to LRT Track 17 Parked Freights at Mississippi Ave Trains awaiting Crew Change, also showing room to add track on bridgeb 18

10 View South of CML at Curtis Street This area will be reconfigured by RTD West Light Rail 19 Arriving DUS on Joint Line

11 Alternative Denver Station Sites To Golden/I-7 via Arvada To DIA via Brush Line To DIA via Pullman Yard BROADWAY SITE 16 th Street SITE DUS Broadway Site provides through movement from DIA to Golden Line (Via Arvada) but requires movement through Pullman Yard as well as new track connections at Prospect Jct. To Pueblo and I-7 via US-6 1 Joint Line and CML Joint Line and CML, Denver to Littleton With RC - Detailed capacity simulation will be required to finalize freight requirements and ultimately determine the necessity of capital improvements through the area: - Tentatively, plan to add a track for bypassing the freight train staging area between South Denver and Englewood. The passenger track would buffer between the freight and LRT tracks and would extend 9 miles, all the way from the LRT flyover to DUS. Without RC In addition to above improvements: - Maximally extend the length of the freight train staging area to the north end of the Littleton trench by adding switches at Crestline Avenue. Adding a fourth track here may require shifting the LRT tracks onto the Electron Lead to make room. - Additionally, based on the result of the line capacity simulation, if necessary to mitigate freight capacity needs, construct an aerial rail structure to carry the passenger line through. (An alternative may be either to tunnel, or else to displace LRT out of the trench to surface running.)

12 Base Rail Route-79mph/15mph 79-mph 11-mph 15-mph 3 Base Rail Route-mph/3mph 15-mph 15-mph 3-mph 4

13 Speed/Frequency Ridership Scenarios for Typical High Speed Corridors Trains / day mph mph 15 mph mph 3 mph 5 Market Analysis: Winter Surveys Goals Three Distinct Survey Types Abstract Mode surveys quantify how much travelers value time (VOT) Transfer surveys evaluate penalty associated with changing trains/modes Bias surveys evaluate modal bias Air vs. Rail and Auto vs. Rail Approach Quota Surveys with individual Sample Frame Targets by Sub-Group (e.g. Trip Length, Mode, Trip Purpose). Survey Implementation Fall Survey was targeted Primarily at Colorado Resident and non-seasonal tourism. Winter Survey (completed) focused on Resort tourism: - DIA Survey of Colorado intra-state flights (VOT, Bias and Transfer survey versions) - Ski Resort surveys at Copper Mountain and Vail (VOT, Bias and Transfer survey versions) - Casino surveys at Central City (VOT version only) 6

14 Fall and Winter Survey Objectives Location Fall Winter Denver Int l Airport Buses (RTD/FRE/Greyhound) Ski Resorts Gaming Resorts Amtrak DMV 7 Final Survey Locations and Dates SURVEY DATES SUMMER WINTER BOTH 8

15 Winter Survey Actual Deployment DIA Airport Survey Vail Resorts Pilot Central City Gaming Survey Vail and Copper Mountain Survey Team Actual Deployment Thu Fri Sat Sun Mon Tue Wed /1 /13 /14 /15 /16 /17 /18 Survey Tallies Location Results Fall Survey...,88 Winter DIA 34 Central City 74 Ski Resorts 499 Subtotal 915 TOTAL 3,73 9 Differences in Fall vs. Winter Surveys Besides the three different survey versions administered (VOT, Bias, Transfer) the target populations were different: DIA Surveys - The Fall DIA Survey targeted local Colorado Residents and screened out connecting passengers. - The Winter DIA Survey targeted all resort travelers on intrastate flights, including both local and connecting passengers. Urban and Resort Surveys - The Fall Surveys at DMV, Rail and Bus stations targeted local Colorado Residents. - The Winter resort surveys targeted both Day Trip and Destination resort travelers. 3

16 Winter Resort Survey Questionnaire Classification Questions on Left Tradeoff Questions on Right 31 Winter Survey Anecdotes Flier on Aspen air connection Felt that flying to Aspen was cheaper than renting a car for 1 days, and not needing the car Copper Mountain destination traveler Staying in a time-share at Silverthorne, needs a car to get to and from the house. Wanted to know about availability of local rental cars at the train station Day tripper on Season Pass Not particularly time sensitive, since they have a season pass to the ski slopes and don t care if they have all day on the slopes. Central City casino visitor Comes to gamble several times a week; enjoys the scenery and considers the ride up to be a part of the outing. 3

17 Demand Update: COMPASS Model Structure Four-Mode Four-Mode Base Base Year Year Transport Transport Socio- Socio- Network Network Economics Economics Stated Stated Preference Preference Demand Demand Trip Trip Model Model Base Base Year Year Survey Survey Matrices Matrices Calibration Calibration Matrix Matrix Origin- Origin- Destination Destination Data Data Economic Economic Scenarios Scenarios Rail Rail Strategies Strategies Travel Travel Demand Demand Model Model Run Run Forecast Forecast Year Year Trip Trip Matrices Matrices Revenue Revenue Analysis Analysis Financial Financial Analysis Analysis User User Benefit Benefit Analysis Analysis Economic Economic Rent Rent Analysis Analysis 33 Zone System 34

18 Colorado Economic Scenarios: State Demography Office & TEMS High, Central and Low Case Population Growth High Case Central Case (SDO, BEA and MPOs combined) Low Case (BEA) Average Annual Growth Rates (%): Millions High-Low Range - 9% Colorado Economic Scenarios: High, Central and Low Cases Real Average Household Income Growth Thousands 7$ Average Annual Growth Rates (%): 1. Low Case Central Case High Case

19 Colorado Economic Scenarios: High, Central and Low Case Employment Growth Average Annual Growth Rates (%): Millions Central Case (SDO, BEA and MPOs combined) Low Case (SDO and BEA) High Case Base Highway Network 38

20 Future Rail Network 39 Generalized Cost Components Time Costs Reliability Schedule Public Modes In-vehicle Time Access/Egress Time Number of Interchanges Connection Wait Times Terminal Wait Times Fare Access/Egress Costs On Time Performance Frequency of Service Convenience of Times Travel Time Auto Operating Costs Tolls Parking (all divided by occupancy) 4

21 VOT and VOF are needed to define Travel Utility Equation for the Networks U ijp = ƒ(gcijp) Where GC ijp = Generalized cost of travel between zones i and j for purpose p GC ijmp = TT ijm + TC ijmp VOF mp x OH + VOT mp VOT mp x F ijm Where TT ijm = Travel time between zones i and j for mode m (in-vehicle time + waiting time + delay time + connect time + access/egress time + interchange penalty), with waiting, delay, connect and access/egress time multiplied by two to account for the additional disutility felt by travelers for these activities TC ijmp = Travel cost between zones i and j for mode m and purpose p (fare + access/egress cost for public modes, operating costs for auto) VOT mp = Value of Time for mode m and purpose p VOF mp = Value of Frequency for mode m and purpose p F ijm = Frequency in departures per week between zones i and j for mode m OH = Operating hours per week 41 Values of Time $/hr Modes Trip Purposes Business Commuter Tourist Other Transit $13. $1.9 $11.39 $11.6 Rail $16.7 $17.5 $17.65 $15.9 Auto $18.91 $18.95 $18.86 $17.69 Air $48.69 $35.73 $33.34 $

22 Coverage of Existing Colorado Data Intercity Trips (greater than 55 miles) 1 Destination Origination 159 Data Available Data Unavailable 178 Data Unavailable Total Existing Data Percentage Covered Zones % Population 4.9 Million 4.6 Million 93.7% Trips per year 1 Million 98 Million 95.5% 43 Base Year Trip Summary Intercity Trips (greater than 55 miles) Mode Car Bus Air Rail Trips 1,,,96, 15,53 831,98 Market Share 96.1%.84%.14%.8% 44

23 Preliminary Base Year Rail Ridership 45 3, Railroad Station Traffic: Passenger Volumes (trips greater than 55 miles) 5, Amtrak Service: trains per day, Station Pas s enger Volume s 15, 1, 5, DIA Denver CBD North Suburban South Suburban Colorado Springs North Front Range Black Hawk Golden Breckenridge Pueblo Vail As pe n FortCollins Copper MT. Avon Ke ystone Steamboat Springs Grand Jct. Cheyenne, WY Monument Glenwood Springs Castle Rock Founta in Trinidad Georgetown Eagle (Airport) Walsenburg Gypsum Rifle Mid Valley Idaho Springs Craig Hayden Airport Parachute Phippsburg Stations 46

24 Total Demand α β 1 β R Coef t Stat Coef t Stat Coef t Stat Business Commuter Tourist Other where U U U U Ln ( Trip) α + β Ln( SE + β Total Total Total Total = 1 ) U Total * U.397* Auto ( Public GC = Ln e + e ) for Business * U.44539* Auto ( Public GC = Ln e + e ) for Commuter * U.14755* Auto ( Public GC = Ln e + e ) for Tourist * U.7576* Auto ( Public GC = Ln e + e ) for Other 47 Mode Split Base Hierarchy: Slow Speed Total Demand Public Modes Auto Mode Air Mode Surface Modes Rail Mode Bus Mode 48

25 Rail Mode vs Bus Mode Level 1 α β 1 β R Coef t Stat Coef t Stat Coef t Stat Business Commuter Tourist Other Ln ( P / P ) β GC Rail Bus = α + β1 GC Rail Bus 49 Surface Modes vs Air Mode Level α β 1 β R Coef t Stat Coef t Stat Coef t Stat Business Commuter Tourist Other where Ln ( P / P ) β GC U U U U Surface Surface Surface Surface Surface Air = α + β1 U Surface * GC.14473* Bus ( Rail GC = Ln e + e ) for Business * GC.8183* Bus ( Rail GC = Ln e + e ) for Commuter * GC.1347* Bus ( Rail GC = Ln e + e ) for Tourist * GC.3674* Bus ( Rail GC = Ln e + e ) for Other Air 5

26 Public Modes vs Auto Mode Level 3 α β 1 β R Coef t Stat Coef t Stat Coef t Stat Business Commuter Tourist Other where Ln ( P / P ) β GC U U U U Public Public Public Public Public Auto = α + β1 U Public * U Surface GC Air Auto.16375* = Ln( e + e ) for Business * U Surface GCAir.8473* = Ln( e + e ) for Commuter * U Surface GCAir.1385* = Ln( e + e ) for Tourist * U Surface GC Air.4794* = Ln( e + e ) for Other 51 Transport Strategies Highway I-7 PEIS: No Action/Collaborative Recommendations I-5 N PEIS: No Action I-5 S PEIS: No Action Other Public Modes Air System grows with traffic Fares constant in real terms Bus System grows with traffic Fares constant in real terms Schedule impacted by congestion 5

27 U.S. Crude Oil Composite Acquisition Cost by Refiners Historic Data and the Forecasts 8$ per Barrel Low Case Central Case High Case Year Source: Energy Information Administration and TEMS, Inc. 53 U.S. Retail Gasoline Prices as a Function of Crude Oil Prices (1993 8) 4 Gasoline Price (8 Cents per Gallon) y =.598x R =.979 Each $38 increase in Crude Oil = $1 on gas Crude Oil Composite Acquisition Cost (8 $ per Barrel) Source: TEMS, Inc and Energy Information Administration. 54

28 U.S. Retail Gasoline Prices - Historic Data and the Forecasts 6 5 8$ per Gallon Low Case Central Case High Case Year Source: TEMS, Inc and Energy Information Administration. 55 Highway Congestion: I-7 Segments (I-7 PEIS) 56

29 I-7 AADT and Segment Locations Seg 1 Seg 6 Seg 1 Source: CDOT, 57 I-7 Hourly Traffic Volumes: Segment 1 Eastbound and Westbound Weekday Traffic Volumes Traffic Volumes EB Weekday_Seg Hours of Day Capacity WB Weekday_Seg Hours of Day Capacity 58

30 I-7 Hourly Traffic Volumes: Segment 1 Eastbound and Westbound Weekend Traffic Volumes Traffic Volumes EB Weekend_Seg Hours of Day Capacity WB Weekend_Seg Hours of Day Capacity 59 I-7 Hourly Traffic Volumes: Segment 6 Eastbound and Westbound Weekday Traffic Volumes Traffic Volumes EB Weekday_Seg Hours of Day Capacity WB Weekday_Seg Hours of Day Capacity 6

31 I-7 Hourly Traffic Volumes: Segment 6 Eastbound and Westbound Weekend Traffic Volumes Traffic Volumes EB Weekend_Seg Hours of Day Capacity WB Weekend_Seg Hours of Day Capacity 61 I-7 Hourly Traffic Volumes: Segment 1 Eastbound and Westbound Typical Day Traffic Volumes Traffic Volumes EB _Seg Hours of Day Capacity WB _Seg Hours of Day Capacity 6

32 I-7 Hours of Congestion: Segments 1 thru 1 Eastbound and Westbound Weekday Hours Hours EB We ek day Years Segments on I 7 WB Weekday Years Segm ents on I 7 63 I-7 Hours of Congestion: Segments 1 thru 1 Eastbound and Westbound Weekend Hours Hours EB Weekend Years Segments on I 7 WB Weekend Years Segments on I 7 64

33 I-5 AADT and Segment Locations Seg 1: Castle Rock Seg : Johnstown Source: CDOT, 65 I-5 Hourly Traffic Volumes: Segment 1 Northbound and Southbound Typical Day Traffic Volumes Traffic Volumes NB _Seg Hours of Day Capacity SB _Seg Hours of Day Capacity 66

34 I-5 Hourly Traffic Volumes: Segment Northbound and Southbound Typical Day Traffic Volumes Traffic Volumes NB _Seg Hours of Day Capacity SB _Seg Hours of Day Capacity 67 I-5 Hours of Congestion: Segments 1 and Northbound and Southbound Typical Day Hours Hours Northbound Segm ents on I 5 Southbound Years 5 Years Segments on I 5 68

35 Thank You. 69

RMRA Feasibility Study Steering Committee

RMRA Feasibility Study Steering Committee Presentation To RMRA Feasibility Study Steering Committee Feasibility Study Update October 24, 2008 TEMS, Inc. / Quandel Consultants, LLC 1 Study Work Schedule: Tasks 1 thru 4.3.3 2 Study Work Schedule:

More information

Development of the Preferred Option and Implementation Plan

Development of the Preferred Option and Implementation Plan Presentation To RMRA Peer Panel Day #1 Preferred Option and Risk Assessment August 25, 2009 TEMS, Inc. / Quandel Consultants, LLC 0 Development of the Preferred Option and Implementation Plan 1 1 Results

More information

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

METRO Light Rail Update

METRO Light Rail Update American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

TEXAS CITY PARK & RIDE RIDERSHIP ANALYSIS

TEXAS CITY PARK & RIDE RIDERSHIP ANALYSIS TEXAS CITY PARK & RIDE RIDERSHIP ANALYSIS This document reviews the methodologies and tools used to calculate the projected ridership and parking space needs from the proposed Texas City Park & Ride to

More information

Feasibility Study Update and Workshop Introduction

Feasibility Study Update and Workshop Introduction Alternatives Analysis Workshop Preliminary Results Feasibility Study Update and Workshop Introduction April 24, 2009 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda 1. MORNING 1. Opening Comments and Today

More information

RTID Travel Demand Modeling: Assumptions and Method of Analysis

RTID Travel Demand Modeling: Assumptions and Method of Analysis RTID Travel Demand Modeling: Assumptions and Method of Analysis Overall Model and Scenario Assumptions The Puget Sound Regional Council s (PSRC) regional travel demand model was used to forecast travel

More information

Stakeholder Meeting #3. August 22, 2018

Stakeholder Meeting #3. August 22, 2018 Stakeholder Meeting #3 August 22, 2018 Good Afternoon Stakeholder Introductions Name and Affiliation Ground Rules Agenda Climate Action Plan Process Overview Vision Statements Overarching vision of what

More information

Valley Metro Overview. ITE/IMSA Spring Conference March 6, 2014

Valley Metro Overview. ITE/IMSA Spring Conference March 6, 2014 Valley Metro Overview ITE/IMSA Spring Conference March 6, 2014 Valley Metro Who Are We? Operate Regional Transit Services Valley Metro and Phoenix are region s primary service providers Light Rail and

More information

HRTPO Strategic Campaign. Passenger Rail. Agenda Item #11. Presentation To. May 19, Presentation By

HRTPO Strategic Campaign. Passenger Rail. Agenda Item #11. Presentation To. May 19, Presentation By Presentation To HRTPO Board Meeting Agenda Item #11 HRTPO Strategic Campaign and Vision Plan for Passenger Rail Presentation By May 19, 2010 Transportation Economics & Management Systems, Inc. Study Timeline

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional

More information

Central Park Drives Traffic Management Overview

Central Park Drives Traffic Management Overview Central Park Drives Traffic Management Overview Spring 2015 New York City Department of Transportation Existing Traffic Management From Labor Day thru Last Day of NYC Public School: 8-10 AM weekdays (Southbound)

More information

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Output

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Output NDSU Dept #2880 PO Box 6050 Fargo, ND 58108-6050 Tel 701-231-8058 Fax 701-231-6265 www.ugpti.org www.atacenter.org Interstate Operations Study: Fargo-Moorhead Metropolitan Area 2015 Simulation Output Technical

More information

Travel Demand Modeling at NCTCOG

Travel Demand Modeling at NCTCOG Travel Demand Modeling at NCTCOG Arash Mirzaei North Central Texas Council Of Governments for Southern Methodist University The ASCE Student Chapter October 24, 2005 Contents NCTCOG DFW Regional Model

More information

Summit County Greenhouse Gas Emissions Summary, 2017

Summit County Greenhouse Gas Emissions Summary, 2017 Summit County Greenhouse Gas Emissions Summary, 2017 In 2018, Summit County completed its first greenhouse gas inventory to better understand its emissions profile and to give insight to policies and programs

More information

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS February 2018 Highway & Bridge Project PIN 6754.12 Route 13 Connector Road Chemung County February 2018 Appendix

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Colorado Association of Ski Towns August 26, 2016

Colorado Association of Ski Towns August 26, 2016 Colorado Association of Ski Towns August 26, 2016 1 Presentation RFTA Overview Long Range Forecast Integrated Transportation System Plan Questions Roaring Fork Transportation Authority (RFTA) RFTA Overview

More information

Travel Time Savings Memorandum

Travel Time Savings Memorandum 04-05-2018 TABLE OF CONTENTS 1 Background 3 Methodology 3 Inputs and Calculation 3 Assumptions 4 Light Rail Transit (LRT) Travel Times 5 Auto Travel Times 5 Bus Travel Times 6 Findings 7 Generalized Cost

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

RTSP Phase II Update

RTSP Phase II Update Washington Metropolitan Area Transit Authority RTSP Phase II Update Presentation to the Technical Advisory Group July 18, 2013 Meeting 1 Presentation Outline RTSP Integration with Momentum RTSP Process

More information

Metropolitan Freeway System 2007 Congestion Report

Metropolitan Freeway System 2007 Congestion Report Metropolitan Freeway System 2007 Congestion Report Minnesota Department of Transportation Office of Traffic, Safety and Operations Freeway Operations Section Regional Transportation Management Center March

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

Ohio Passenger Rail Development. Northwest Ohio Passenger Rail Association

Ohio Passenger Rail Development. Northwest Ohio Passenger Rail Association Ohio Passenger Rail Development Northwest Ohio Passenger Rail Association Ohio Rail Development Commission June 11, 2010 Ohio Strategy Establish the Market Grow the Market Capture the Value of the Market

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

The Jack A. Markell Trail Delaware s Bicycle Highway New England Bike- Walk Summit

The Jack A. Markell Trail Delaware s Bicycle Highway New England Bike- Walk Summit The Jack A. Markell Trail Delaware s Bicycle Highway 2018 New England Bike- Walk Summit The Jack A. Markell Trail Sometimes a very difficult project, including significant investment and perseverance,

More information

BCA Benefits and Assumptions Summary

BCA Benefits and Assumptions Summary 2016 TIGER Application - Plymouth Multimodal BCA Benefits and Assumptions Summary The Plymouth Multimodal generates a variety of benefits, ranging from monetary such as increased transit fare revenue,

More information

A Transit Plan for the Future. Draft Network Plan

A Transit Plan for the Future. Draft Network Plan A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year

More information

TRAVEL DEMAND FORECASTS

TRAVEL DEMAND FORECASTS Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) TRAVEL DEMAND FORECASTS A. Introduction 1. The purpose of the travel demand forecasts is to assess the impact of the project components

More information

Kenosha-Racine-Milwaukee (KRM)

Kenosha-Racine-Milwaukee (KRM) Kenosha-Racine-Milwaukee (KRM) Commuter Rail #147925 November 6, 2009 1 Guidance of KRM Commuter Rail Studies Intergovernmental Partnership Technical Steering Committee Temporary and Limited Authority

More information

Transit Access Study

Transit Access Study West of Hudson Regional Transit Access Study Open House presentation July 20, 2010 1 Agenda Progress To date Summary of Level 2 Alternatives and Screening Service Plans Bus and Rail Operating and Capital

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Mountain Area Transportation Study Model Methodology and Assumptions Final

Mountain Area Transportation Study Model Methodology and Assumptions Final Model Methodology and Assumptions Final February 19, 2017 Submitted to: 17J17-1768.17 Prepared by Iteris, Inc. Innovating Through Informatics TABLE OF CONTENTS 1.0 OVERVIEW... 1 1.1 Project Objective and

More information

TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury

TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

2016 Congestion Report

2016 Congestion Report 2016 Congestion Report Metropolitan Freeway System May 2017 2016 Congestion Report 1 Table of Contents Purpose and Need...3 Introduction...3 Methodology...4 2016 Results...5 Explanation of Percentage Miles

More information

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &

More information

Traffic and Toll Revenue Estimates

Traffic and Toll Revenue Estimates The results of WSA s assessment of traffic and toll revenue characteristics of the proposed LBJ (MLs) are presented in this chapter. As discussed in Chapter 1, Alternatives 2 and 6 were selected as the

More information

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project

More information

Metropolitan Council Budget Overview SFY

Metropolitan Council Budget Overview SFY Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows

More information

Chicago Milwaukee Intercity Passenger Rail Corridor

Chicago Milwaukee Intercity Passenger Rail Corridor Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department

More information

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The

More information

SERVICE DESIGN GUIDELINES

SERVICE DESIGN GUIDELINES VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Results

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Results NDSU Dept #2880 PO Box 6050 Fargo, ND 58108-6050 Tel 701-231-8058 Fax 701-231-6265 www.ugpti.org www.atacenter.org Interstate Operations Study: Fargo-Moorhead Metropolitan Area 2025 Simulation Results

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005

Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Public Transit District Utah Transit Authority Linear Geographic Area - 130 miles by

More information

Presentation To: HRTPO Passenger Rail Task Force

Presentation To: HRTPO Passenger Rail Task Force Presentation To: HRTPO Passenger Rail Task Force HRTPO Norfolk-Richmond Passenger Rail Ridership and Revenue Forecasts Presentation By December 17, 2013 Transportation Economics & Management Systems, Inc.

More information

Metropolitan Freeway System 2013 Congestion Report

Metropolitan Freeway System 2013 Congestion Report Metropolitan Freeway System 2013 Congestion Report Metro District Office of Operations and Maintenance Regional Transportation Management Center May 2014 Table of Contents PURPOSE AND NEED... 1 INTRODUCTION...

More information

Development of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation

Development of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation Development of 220 mph High Speed Rail Service for Illinois Mark C. Walbrun, PE TranSystems Corporation 1 Study Purpose Worldwide Use of High Speed Rail Technology Japan, France, Italy, Germany, Spain,

More information

DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY

DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY APPENDIX 1 DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY INTRODUCTION: This Appendix presents a general description of the analysis method used in forecasting

More information

TPB CLRP Aspirations Scenario

TPB CLRP Aspirations Scenario TPB CLRP Aspirations Scenario Streamlined Variably Priced Lane Network Sensitivity Test Ron Kirby Erin Morrow Department of Transportation Planning Presentation to the Transportation Planning Board October

More information

UTA Transportation Equity Study and Staff Analysis. Board Workshop January 6, 2018

UTA Transportation Equity Study and Staff Analysis. Board Workshop January 6, 2018 UTA Transportation Equity Study and Staff Analysis Board Workshop January 6, 2018 1 Executive Summary UTA ranks DART 6 th out of top 20 Transit Agencies in the country for ridership. UTA Study confirms

More information

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014 Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

Appendix B: Travel Demand Forecasts July 2017

Appendix B: Travel Demand Forecasts July 2017 Appendix B: Travel Demand Forecasts July 2017 Table of Contents 1 Introduction... 2 2 Model Review and Updates... 2 2.1 Overview of Smart Moves Model ( City of London Model )... 2 2.1.1 Network and Zone

More information

Public Transportation Problems and Solutions in the Historical Center of Quito

Public Transportation Problems and Solutions in the Historical Center of Quito TRANSPORTATION RESEARCH RECORD 1266 205 Public Transportation Problems and Solutions in the Historical Center of Quito JACOB GREENSTEIN, Lours BERGER, AND AMIRAM STRULOV Quito, the capital of Ecuador,

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Halifax Commuter Rail Feasibility Study

Halifax Commuter Rail Feasibility Study Halifax Commuter Rail Feasibility Study Open House Halifax Regional Municipality February 26, 2015 Study Team The team is led by CPCS: A global management consulting firm (formerly the consulting arm of

More information

The Engineering Department recommends Council receive this report for information.

The Engineering Department recommends Council receive this report for information. CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Contents. Executive Summary...1 Introduction...2 Operating Plan...4 System Connectivity...5

Contents. Executive Summary...1 Introduction...2 Operating Plan...4 System Connectivity...5 Contents Executive Summary...1 Introduction...2 Operating Plan...4 System Connectivity...5 Project Benefits...6 Economic Growth...7 Infrastructure Improvements...9 Quality of Life... 11 Next Steps... 12

More information

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA Tube Counts Type of report: Tube Count - Volume Data LOCATION: Scotts Valley Dr QC JOB #: 245667 SPECIFIC LOCATION: ft from Tabor St DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA DATE: Mar 2 24 - Mar

More information

SEPULVEDA PASS CORRIDOR

SEPULVEDA PASS CORRIDOR SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000

More information

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Annual growth rate is 3.8% By 2020 population growth would

More information

Caltrain Downtown Extension Study Ridership Forecast Summary

Caltrain Downtown Extension Study Ridership Forecast Summary Caltrain Downtown Extension Study Ridership Forecast Summary presented to Transbay Joint Powers Authority presented by Cambridge Systematics date: March 12, 2009 Transportation leadership you can trust.

More information

3.1 Introduction Transportation Elements and Study Area Meeting the Need for the Project

3.1 Introduction Transportation Elements and Study Area Meeting the Need for the Project Chapter 3 Transportation Environment and Consequences 3. Introduction This chapter summarizes the characteristics of the transportation system in the East Link Project vicinity and discusses potential

More information

North Shore Alternatives Analysis. May 2012

North Shore Alternatives Analysis. May 2012 North Shore Alternatives Analysis May 2012 Agenda Study Process and Progress to Date Short List Alternatives Screening Traffic Analysis Conceptual Engineering Ridership Forecasts Refinement of Service

More information

Rocky Mountain Rail Authority High Speed Rail Feasibility Study Summary 9/16/10

Rocky Mountain Rail Authority High Speed Rail Feasibility Study Summary 9/16/10 Rocky Mountain Rail Authority High Speed Rail Feasibility Study Summary 9/16/10 By Harry Dale Chairman, Rocky Mountain Rail Authority 303-250-6181 Hjd173@wispertel.net http://rockymountainrail.org The

More information

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis Durham-Orange Light Rail Transit Project July 25, 218 ROMF Transportation Impact Analysis Version

More information

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle

Chapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

I-26 Fixed Guideway Alternatives Analysis

I-26 Fixed Guideway Alternatives Analysis I-26 Fixed Guideway Alternatives Analysis Steering & Technical Advisory Committees Joint Meeting January 15, 2016 @ 10:00 AM SC/TAC Meeting Winter 2016 Agenda I. Welcome & Introductions II. III. Project

More information

Trunk Highway 13 Corridor Study Update Existing and No-Build Conditions Technical Memo #2B: Traffic Forecasts and Operations Analysis SEH No.

Trunk Highway 13 Corridor Study Update Existing and No-Build Conditions Technical Memo #2B: Traffic Forecasts and Operations Analysis SEH No. TECHNICAL MEMORANDUM TO: FROM: Molly McCartney MnDOT Project Manager Haifeng Xiao, PE Tom Sohrweide, PE, PTOE DATE: November 27, 2012 RE: Trunk Highway 13 Corridor Study Update Existing and No-Build Conditions

More information

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station 203 North LaSalle Street, Suite 2100 Chicago, IL 60601 (312) 558-1345 Fax: (312) 346-9603 E-Mail: cquandel@quandelconsultants.com www.quandel.com Scope of Services January 26, 2010 Project Development

More information

A Light Rail, Group Rapid Transit, Personal Rapid Transit Comparison Peter J. Muller, P.E., MASCE 1 Ingmar J. Andreasson, PhD, Prof. Em.

A Light Rail, Group Rapid Transit, Personal Rapid Transit Comparison Peter J. Muller, P.E., MASCE 1 Ingmar J. Andreasson, PhD, Prof. Em. A Light Rail, Group Rapid Transit, Personal Rapid Transit Comparison Peter J. Muller, P.E., MASCE 1 Ingmar J. Andreasson, PhD, Prof. Em. 2 Submitted to ASCE Automated People Movers Conference 2018 1 President,

More information

Maryland Gets to Work

Maryland Gets to Work I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast

More information

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

Appendix B CTA Transit Data Supporting Documentation

Appendix B CTA Transit Data Supporting Documentation RED ED-PURPLE BYPASS PROJECT ENVIRONMENTAL ASSESSMENT AND SECTION 4(F) EVALUATION Appendix B CTA Transit Data Supporting Documentation 4( Memorandum Date: May 14, 2015 Subject: Chicago Transit Authority

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS

BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS Prepared for: City of Berkeley Prepared by: REVISED JANUARY 9, 2009 Berkeley Downtown Area Plan Program EIR Traffic

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

AECOM 30 Leek Cres., 4 th Floor Richmond Hill, ON L4B 4N4 Canada

AECOM 30 Leek Cres., 4 th Floor Richmond Hill, ON L4B 4N4 Canada \ AECOM 30 Leek Cres., 4 th Floor Richmond Hill, ON L4B 4N4 Canada www.aecom.com 905-882-4401 tel 905-882-4399 fax Memorandum To CC Subject Peter Dorton (MTO), Eric Terro (MTO) Olga Garces (MTO) Page 1

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

Expansion Projects Description

Expansion Projects Description Expansion Projects Description The Turnpike expansion program was authorized by the Florida Legislature in 1990 to meet the State s backlog of needed highway facilities. The Legislature set environmental

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Executive Summary. Phase 2 Evaluation Report. Introduction

Executive Summary. Phase 2 Evaluation Report. Introduction , Executive Summary Executive Summary Introduction TransLink and the Province of British Columbia sponsored a multi-phase study to evaluate alternatives for rapid transit service in the Broadway corridor

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND Prepared for: Department of Public Works Anne Arundel County Prepared by: URS Corporation 4 North Park Drive, Suite 3 Hunt Valley,

More information

Sean P. McBride, Executive Director Kalamazoo Metro Transit. Presentation to Michigan Transportation Planning Association July 13, 2016

Sean P. McBride, Executive Director Kalamazoo Metro Transit. Presentation to Michigan Transportation Planning Association July 13, 2016 Sean P. McBride, Executive Director Kalamazoo Metro Transit Presentation to Michigan Transportation Planning Association July 13, 2016 Metro Transit in Kalamazoo County Square Miles = 132 Urbanized Population:

More information