1 Ohio Passenger Rail Development Northwest Ohio Passenger Rail Association Ohio Rail Development Commission June 11, 2010
2 Ohio Strategy Establish the Market Grow the Market Capture the Value of the Market
3 3C Market Strengths Cleveland Columbus Cincinnati Large end-point population centers Many intermediate cities Mid-point Capitol City Lacks air service Serves strong business market Potential to serve commuter markets Potential to stand-alone Serves 60% of Ohio Population
4 Establish the Market 3C Quick Start
5 Ohio s 3C Quick Start Application for ARRA funding SUCCESS: $400 million award. Among the largest awards. Other applicants couldn t meet the requirements. ODOT/ORDC staff worked tirelessly to submit a comprehensive application.
6 3C Quick Start Service Characteristics Three trains per day in each direction 79-mph top speed Fares approx. 15 cents/mile On-board Food Service 478,000 Annual Trips Compares favorably to other Amtrak corridors
7 3C Quick Start Tier One Environmental Assessment and Alternatives Analysis Completed in 8 weeks Purpose and Need 33 Route Alternatives Three Levels of Screening Public Involvement FONSI
8 3C Quick Start Capital Improvements Capacity additions Track upgrades Train maintenance facilities 8 Passenger Stations Highway/Rail grade crossing improvements Train fleet
9 Proposal to Project Next Steps Finalize FRA Statement of Work Complete Capacity Analysis Select Operator Procure Equipment Strategy Initiate Railroad Negotiations Conduct Preliminary Engineering Complete Tier Two Environmental Assessment
10 The Ohio Hub Growing the Market Ohio Hub MWRRS Trips in million 13.6 million
11 The Ohio Hub Service Characteristics: Expanded system Increased speeds More frequencies Improved Fast Frequent services Reliable Competitive with automobile times Same-day round trips
12 Ohio Hub Feasibility Study Combined 72 stations the - 10 Ohio corridors Hub and 33 million MWRRS people (east) in into 6 States a single and 2,300-mile Ontario, Canada passenger rail network
13 Ohio Hub Optimized Train Frequencies Toledo Hub: 76 Trains/Day 38 Arrivals 38 Departures Columbus Hub: 80 Trains/Day 40 Arrivals 40 Departures Cleveland Hub: 64 Trains/Day 32 Arrivals 32 Departures
14 The Toledo Hub Strategically Positioned for Growth Station Activity in 2025: 76 trains per day 786,000 annual trips 5 th highest ridership among Ohio Hub stations Destination/Travel Time: To Chicago: 3 :18 To Cleveland: 1 :25 To Columbus: 2: 12 To Detroit 1: 15 To Pittsburgh: 3 :45 To Toronto: 6 :30
15 Ohio Hub PEIS Programmatic Environmental Impact Statement Kick-off on Monday
16 Toledo Rail Corridors PEIS Alternatives Analysis
17 Chicago - Toledo PEIS Alternatives Analysis
18 Toledo - Cleveland PEIS Alternatives Analysis
19 Ohio Hub Study Feasibility Analysis Criteria FRA Commercial Feasibility Report to Congress set criteria for establishing project feasibility: 1. The ratio of operating revenues to operating costs; and 2. The ratio of total project benefits to total project costs
20 Ohio Hub Study Ridership, Revenue and Operating Cost Data Corridor Revenue Cost Rev/TM Cost/TM Surplus Op Ratio Riders Psgr Miles Load Fctr Trip Len Yield Chicago-Michigan $136 $97 $47.73 $34.12 $ $0.22 Chicago-FTW-Toledo $99 $64 $53.72 $34.81 $ $0.27 Chicago-Cincinnati $60 $40 $51.44 $34.42 $ $0.29 Total MWRRS Eastern $295 $202 $50.36 $34.40 $ $0.25 Cleveland-Cincinnati $100 $55 $78.01 $42.88 $ $0.38 Cleveland-Detroit $51 $36 $46.44 $32.82 $ $0.25 Cleveland-Niagara Falls $45 $25 $69.49 $38.32 $ $0.39 Cleveland-Pittsburgh $30 $22 $43.17 $31.24 $ $0.32 Subtotal OHIO Base $226 $138 $60.74 $36.96 $ $0.33 Pittsburgh-Columbus $25 $20 $41.22 $32.98 $ $0.27 Columbus-Ft Wayne $36 $26 $45.40 $33.04 $ $0.25 Columbus-Toledo $24 $18 $42.85 $31.83 $ $0.25 Subtotal OHIO Incremental $85 $64 $43.39 $32.67 $ $0.26 TOTAL OHIO HUB $311 $202 $54.76 $35.48 $ $0.31
21 Capturing the Value of the Market Ohio s Passenger Rail Stations
22 Ohio Hub Economic Impact Study Two Study Teams Two Parallel Study Efforts Provided third party validation Applied alternative methodologies Provided real estate expertise for assessing land use impacts
23 Ohio Hub Short-term Construction Impacts MSA Capital ($ Millions) Economic Benefit (Output in $ Millions) Increase in Household Earnings ($ Millions) Annual Construction Jobs Created Cleveland $653 $1,418 $414 1,245 Cincinnati $240 $554 $ Columbus $361 $829 $ Dayton $120 $236 $ Toledo $190 $373 $ Ohio Total $2,380 $5,993 $1,846 6,060
24 Ohio Hub The Value of the Market Long-term Economic Impacts Annual Ridership Ohio Hub + MWRRI Long-term Jobs Created Increase in Household Income ($ Millions) Increase in Property Value ($ Millions) Cleveland 1,155, $115 $160 $370 $520 Cincinnati 1,074, $95 $135 $330 $470 Columbus 1,110, $85 $115 $250 $340 Dayton 787, $75 $105 $210 $285 Toledo 786, $25 $55 $115 $160 Springfield 69, $7 $10 $20 $30 SYSTEM TOTAL 6,560,000 16,700 $1 Billion $3 Billion
25 Ohio Hub Return on Investment Development Impact on Cleveland $370 to $520 Million
26 Ohio Hub The Value of the Market Potential Development Impact on Toledo $115 to $160 Million
27 Ohio Hub Economic Impact Study Results 5,550-6,060 annual construction jobs 49,900 total construction jobs over 9 years 16,700 permanent jobs $1 billion increase in the region s income $3 billion in station-area development $80 million impact on state tourism 320,000 new overnight trips 5% increase in Cleveland Hopkins air traffic $3 - $6 billion in potential freight rail benefit 9.4 million gallons of fuel saved each year
28 Ohio Hub Economic Impact Study Conclusions Construction of high-speed passenger rail is economically feasible and justifiable assuming an 80% federal construction match. By feasible, we believe the economic benefits justify the investment and the project will not be a burden on the State biennial budget. If, as in the case of highway projects, Ohio provides just 20% of the capital costs, a $1 billion investment will achieve a $17 billion return.
29 Quick Start Station-Area Planning is Underway
30 3C Quick Start Cleveland and SW Cleveland Station Connections 3C Connects to GCRTA at the Lakefront Amtrak Station at West 150 th Street
31 3C Quick Start City of Riverside Wright-Patterson Train Station
32
33 Questions?
Program. presented by: September 22, 2010
Minnesota s s High Speed Passenger Rail Program presented by: Minnesota Department of Transportation September 22, 2010 Presentation Overview State Rail Plan National High Speed Rail Initiatives Passenger
More informationNEW HAVEN-HARTFORD-SPRINGFIELD LINE HIGH SPEED INTERCITY RAIL PROJECT
NEW HAVEN-HARTFORD-SPRINGFIELD LINE HIGH SPEED INTERCITY RAIL PROJECT Ralph F. Trepal, P.E. CDM Smith Sr. Project Manager Cleveland, OH John E. Bernick, P.E. Connecticut Department of Transportation Supervising
More informationMetropolitan Council Budget Overview SFY
Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows
More informationTime (secs) Distance (feet) Accel (mphps) , , , , ,388 0.
EQUIPMENT Locomotive Hauled vs. Diesel Multiple Units Ohio Rail Development Commission November 19, 2009 Presentation Outline Typical Characteristics Locomotive-hauled equipment DMU Performance Performance
More informationUpdate of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI
Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative
More informationNeeds and Community Characteristics
Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by
More informationEconomic Impacts. Midwest Regional Rail System. of the. A Transportation Network for the 21st Century
For more information, please contact: Midwest Regional Rail Initiative c/o Wisconsin Department of Transportation Railroads and Harbors Section 4802 Sheboygan Avenue, Room 701 P. O. Box 7914 Madison, WI
More informationNew Haven Hartford Springfield Rail
New Haven Hartford Springfield Rail Opportunities for Economic Growth NHHS Rail Conference, October 25, 2011 NHHSrail.com Tom Maziarz, CT DOT, Bureau of Policy & Planning Thomas.Maziarz@ct.gov New Haven
More informationKANSAS CITY STREETCAR
KANSAS CITY STREETCAR KAREN CLAWSON MID-AMERICA REGIONAL COUNCIL KANSAS CITY STREETCAR Regional Context Alternatives Analysis Kansas City Streetcar Project KANSAS CITY REGION KANSAS CITY REGION KANSAS
More informationAn Overview of High Speed Rail. David Randall Peterman Congressional Research Service
An Overview of High Speed Rail David Randall Peterman Congressional Research Service 1 Defining High Speed Rail in the U.S. What is High Speed Rail? Allusions to world-class European and Asian systems
More informationHigh-Speed Intercity Passenger Rail
September 13, 2011 LTRC Seminar Series: Congestion Management Baton Rouge New Orleans High-Speed Intercity Passenger Rail AGENDA LTRC Seminar Series: Congestion Management Baton Rouge, Louisiana Project
More informationNew Haven-Hartford-Springfield Rail Project Gateway to New England. Program Update March 14, 2011 Revised & Updated March 31, 2011
New Haven-Hartford-Springfield Rail Project Gateway to New England Program Update March 14, 2011 Revised & Updated March 31, 2011 1 New Haven-Hartford-Springfield Rail Corridor Glory Days: 1925-1955 22
More informationThe Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland
The Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland Chesapeake Science & Security Corridor Regional Rail Committee Meeting October 20, 2010 Drew Galloway
More informationThe Preferred Alternative: a Vision for Growth on the Northeast Corridor
A Long-Term Vision is Needed The Preferred Alternative: a Vision for Growth on the Northeast Corridor The Federal Railroad Administration (FRA) has released the Tier 1 Final Environmental Impact Statement
More informationGeorgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at
Overview Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at www.garail.com Commuter rail service between Lovejoy and Atlanta is ready for implementation:
More informationChicago Milwaukee Intercity Passenger Rail Corridor
Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department
More informationDRAFT Subject to modifications
TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The
More informationAMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)
FOR IMMEDIATE RELEASE September 28, 2010 ATK-10-130a Contact: Media Relations 202 906.3860 AMTRAK ENVISIONS WORLD CLASS HIGH-SPEED RAIL Washington to Boston in about three hours at up to 220 mph (354 kph)
More informationWhoWhatWhenWhereWhy. (lists only those in proposed Midwest-Northeast HSR Corridor) SOURCE: America 2050
WhoWhatWhenWhereWhy Linking populous regions more than 500 miles apart with high-speed rail once seemed unthinkable. That was before China deployed new advances in technology for its 818-mile Jinghu high-speed
More informationKenosha-Racine-Milwaukee (KRM)
Kenosha-Racine-Milwaukee (KRM) Commuter Rail #147925 November 6, 2009 1 Guidance of KRM Commuter Rail Studies Intergovernmental Partnership Technical Steering Committee Temporary and Limited Authority
More information2012 MULTIMODAL OPERATIONS WORKSHOP
New Haven-Hartford-Springfield Rail Program Gateway to New England Jeffrey T. Schultz, PMP Senior Principal Technical Specialist Parsons Brinckerhoff Glastonbury, CT July 31, 2012 2012 MULTIMODAL OPERATIONS
More informationLeadership NC. November 8, 2018
v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationBedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015
Bedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015 SUBJECT: Bedford Amtrak Station Why an Amtrak station in Bedford makes sense. I. BACKGROUND: In January
More informationScope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station
203 North LaSalle Street, Suite 2100 Chicago, IL 60601 (312) 558-1345 Fax: (312) 346-9603 E-Mail: cquandel@quandelconsultants.com www.quandel.com Scope of Services January 26, 2010 Project Development
More informationThe City of Toronto s Transportation Strategy July 2007
The City of Toronto s Transportation Strategy July 2007 Presentation Outline Transportation Statistics Transportation Building Blocks Toronto s Official Plan Transportation and City Building Vision Projects
More informationValley Metro Overview. ITE/IMSA Spring Conference March 6, 2014
Valley Metro Overview ITE/IMSA Spring Conference March 6, 2014 Valley Metro Who Are We? Operate Regional Transit Services Valley Metro and Phoenix are region s primary service providers Light Rail and
More informationDevelopment of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation
Development of 220 mph High Speed Rail Service for Illinois Mark C. Walbrun, PE TranSystems Corporation 1 Study Purpose Worldwide Use of High Speed Rail Technology Japan, France, Italy, Germany, Spain,
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationStatus of Plans March Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS
Status of Plans March 2011 Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS Transit project update Project rationale The system New Britain Hartford Busway New Haven/Hartford/ Springfield Passenger Rail
More informationGreater Cleveland Regional Transit Authority
Greater Cleveland Regional Transit Authority Summary of Proposed Award Vanpool Program Presented to: Operations Committee August 2, 2016 What is a Vanpool? A vanpool is a group of people (larger than 5)
More informationCaltrain Modernization EMU Procurement
Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting
More informationKRM Corridor Transit Service Options: Frequently Asked Questions
December 2008 KRM Corridor Transit Service Options: Frequently Asked Questions by Thomas A. Rubin and Robert W. Poole, Jr. FREQUENTLY ASKED QUESTIONS 1 2 3 4 5 6 7 8 How many net new transit riders would
More informationGreater Cleveland Regional Transit Authority. Joe Calabrese CEO/General Manager
Greater Cleveland Regional Transit Authority Joe Calabrese CEO/General Manager Greater Cleveland RTA Overview Service Area Population of 1.5 million Customers Served 200,000 on a typical weekday 1.6 million
More informationSales and Use Transportation Tax Implementation Plan
Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,
More informationProposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta
Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Overview Commuter rail service between Lovejoy and Atlanta is ready for implementation: $87.08 Million is in
More informationTRANSFORMING THE WAY OUR REGION MOVES
TRANSFORMING THE WAY OUR REGION MOVES Judy Pfeifer, Chief Communications and Public Affairs Officer Gord Troughton, Director, Corridor Infrastructure Chris Burke, Director, Service Planning GRIDLOCK COSTS
More informationConverting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada
Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population
More informationMississauga Transit 2009 Budget
Mississauga Transit 2009 Budget Budget Committee Presentation December 2, 2008 Revenue Ridership Forecasted 2008 Total Rides Including transfers 11% growth in the last 24 months Transit Service Area Business
More informationExpanding Capacity for the Northeast Corridor The Gateway Program
Expanding Capacity for the Northeast Corridor The Gateway Program Petra Todorovich Messick March 4, 2013 Raritan Valley Rail Coalition Somerville, NJ The Northeast Corridor Mainline and Branches 899 Route-miles
More informationContents. Executive Summary...1 Introduction...2 Operating Plan...4 System Connectivity...5
Contents Executive Summary...1 Introduction...2 Operating Plan...4 System Connectivity...5 Project Benefits...6 Economic Growth...7 Infrastructure Improvements...9 Quality of Life... 11 Next Steps... 12
More informationU.S. System Summary: ARIZONA/SOUTHWEST
U.S. System Summary: ARIZONA/SOUTHWEST Arizona/Southwest High-Speed Rail System (Source: Texas A&M Transportation Institute) The Arizona/Southwest high-speed rail system described in this summary groups
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationThe Smart Growth Countywide Transit Master Plan
Choose the Future The Smart Growth Transit Master Plan What is the Transit Master Plan? A robust and integrated plan to establish countywide public transportation priorities over the next thirty years
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationDowntown Transit Connector. Making Transit Work for Rhode Island
Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project
More informationMr. Vince Mauceri General Manager Transportation Operations and Technology
Mr. Vince Mauceri General Manager Transportation Operations and Technology METROLINX OVERVIEW AND MANDATE Established in 2006 to address the significant transportation challenges in the Greater Toronto
More informationGO Transit s deliverable: the 2020 Service Plan
GO Transit s deliverable: the 2020 Service Plan GO Transit s 2020 Service Plan describes GO s commitment to customers, existing and new, to provide a dramatically expanded interregional transit option
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationMeeting the Transportation Challenge in the Northeast
Meeting the Transportation Challenge in the Northeast Corridor Frank VACCA Chief Engineer, Amtrak, United States Drew GALLOWAY AVP, NEC Infrastructure and Investment Development, Amtrak, United States
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationNOACA Planning and Programming Committee February 14, 2014
NOACA Planning and Programming Committee February 14, 2014 1 Ohio's four busiest train stations Toledo, Cleveland, Sandusky, Elyria Each has 28 passenger trains arriving/departing each week Ridership is
More informationRocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC
Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview
More informationIssues Facing the Panel
Issues Facing the Panel Choice of technology for Sheppard Avenue (not for every corridor every where for all time!): subway vs. LRT Budget implications I would argue that procurement, construction management
More informationComprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS
Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS Annie Nam Southern California Association of Governments September 24, 2012 The Goods Movement
More informationExecutive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.
Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections
More informationPresentation A Blue Slides 1-5.
Presentation A Blue Slides 1-5. 1 Presentation A Blue Slides 1-5. 2 Presentation A Blue Slides 1-5. 3 Presentation A Blue Slides 1-5. 4 Presentation A Blue Slides 1-5. 5 Transit Service right. service
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationTransportation 2040: Plan Performance. Transportation Policy Board September 14, 2017
Transportation 2040: Plan Performance Transportation Policy Board September 14, 2017 Today Background Plan Performance Today s Meeting Background Board and Committee Direction 2016-2017 Transportation
More informationUTA Transportation Equity Study and Staff Analysis. Board Workshop January 6, 2018
UTA Transportation Equity Study and Staff Analysis Board Workshop January 6, 2018 1 Executive Summary UTA ranks DART 6 th out of top 20 Transit Agencies in the country for ridership. UTA Study confirms
More informationGreen Line Long-Term Investments
Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect
More informationHigh Speed Rail Conference
High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationUNION STATION MASTER PLAN STUDY
UNION STATION MASTER PLAN STUDY The Chicago Department of Transportation has begun a comprehensive study of issues related to Chicago s Union Station, the Union Station Master Plan. Opened in 1925, Union
More informationThe Case for. Business. investment. in Public Transportation
The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend
More informationHalifax Commuter Rail: A Fresh Concept
Building Owners & Managers Association (BOMA) Nova Scotia PO Box 1597, Halifax NS B3J 2Y3 902-425-3717 info@bomanovascotia.com bomanovascotia.com Halifax Commuter Rail: A Fresh Concept The Green Interconnected
More informationMemorandum. To: The Arlington County Board Date: June 29, 2018 From: Subject:
OFFICE OF THE COUNTY MANAGER 2100 Clarendon Boulevard, Suite 302, Arlington, VA 22201 TEL 703.228.3120 FAX 703.228.3218 TTY 703.228.4611 www.arlingtonva.us Memorandum To: The Arlington County Board Date:
More informationPlanning of the HSR Network
Engineering Services Department A Global Solution in Public Works Project China s High Speed Rail Network Susan Pan, P.E., Manager of Engineering County of Ventura, Planning of the HSR Network Planning
More informationThe Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix
The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationThe Screening and Selection of Regionally Significant Projects
The Screening and Selection of Regionally Significant Projects UTC 2018 Seminar Series March 15, 2018 Claire Bozic Martin Menninger ON TO 2050 CMAP is the Region s MPO, seven county region Land use and
More informationMass Transit in Charlotte and San Antonio. Keith T. Parker, AICP
Mass Transit in Charlotte and San Antonio Keith T. Parker, AICP President/CEO Presentation Overview Charlotte Agency and Customer Profile San Antonio Agency and Customer Profile Attracting New Customers
More informationChicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015
Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In
More informationMARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018
MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline
More informationFeasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study
Feasibility Study Community Meeting March, 2017 1 Agenda 1. Welcome / Introductions 2. Background / Meeting Purpose 3. Progress to Date Options Evaluated Capital/Operating Costs Ridership 4. Financial
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More informationNew Haven-Hartford-Springfield Rail Project Gateway to New England. Public Hearing June
New Haven-Hartford-Springfield Rail Project Gateway to New England Public Hearing June 2012 1 New Haven-Hartford-Springfield Rail Corridor Glory Days: 1925-1955 22 trains/day in 1947 Bankers Ltd 3-hour
More informationDeveloping Toronto s Transit Network Plan to Public Information Meeting June 21, 2016
Developing Toronto s Transit Network Plan to 2031 Public Information Meeting June 21, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration options
More informationSuccessful Passenger Rail in the State of California
Successful Passenger Rail in the State of California Texas Transportation Forum Austin, Texas Eugene K. Skoropowski, Managing Director Capitol Corridor Joint Powers Authority (CCJPA) Oakland, California
More information2030 Multimodal Transportation Study
2030 Multimodal Transportation Study City of Jacksonville Planning and Development Department Prepared by Ghyabi & Associates April 29,2010 Introduction Presentation Components 1. Study Basis 2. Study
More informationIntegrating HSR Into Existing Regional Transportation Systems
Integrating HSR Into Existing Regional Transportation Systems Anthony Perl aperl@sfu.ca 2 Questions hold the key to successful integration of HSR into US mobility How fast will highspeed trains run in
More informationSMART INVESTMENTS IN INTERCITY PASSENGER TRAVEL FACILITIES: A BALANCED MULTI-MODAL APPROACH
SMART INVESTMENTS IN INTERCITY PASSENGER TRAVEL FACILITIES: A BALANCED MULTI-MODAL APPROACH International Workshop on High-Speed Rail Planning and Operations George List, NC State Re-Growth, not Expansion
More informationSan Francisco to San Jose Preliminary Alternatives Analysis
San Francisco to San Jose High-Speed Train Project EIR/EIS San Francisco to San Jose Preliminary Alternatives Analysis April 15, 2010 Page 1 Largest Public Transportation Project in U.S. History 800 miles
More informationCharlotte-Mecklenburg Region Rapid Transit and Land-Use Integration
Charlotte-Mecklenburg Region Rapid Transit and Land-Use Integration Legislative Committee on Urban Growth and Infrastructure Carolyn Flowers CEO Charlotte Area Transit System March 23, 2010 Charlotte Region
More informationSEPULVEDA PASS CORRIDOR
SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000
More informationTIER TWO SCREENING REPORT
TIER TWO SCREENING REPORT November 2012 Parsons Brinckerhoff DRAFT November 2012 1 Parsons Brinckerhoff DRAFT November 2012-2 TABLE OF CONTENTS Table of Contents...3 List of Tables...4 List of Figures...5
More informationTRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury
TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based
More informationTHE PARTNERSHIP OF RAIL & COAL MOVING AHEAD 2014 RMCMI ANNUAL MEETING SEPTEMBER 19, 2014
THE PARTNERSHIP OF RAIL & COAL MOVING AHEAD 2014 RMCMI ANNUAL MEETING SEPTEMBER 19, 2014 1 BNSF is a Leading U.S. Railroad A Berkshire Hathaway company 32,500 route miles in 28 states and two Canadian
More informationPurple Line Light Rail P3 Project
Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationClick to edit Master title style
P3s Come In All Shapes And Sizes Mr. Greg Slater, Administrator 7/26/2018 1 1 Customer-Driven Customer First TODAY S DISCUSSION Introduction to MDOT MDOT P3 Experience Full Delivery Stream Restoration
More informationHRTPO Strategic Campaign. Passenger Rail. Agenda Item #11. Presentation To. May 19, Presentation By
Presentation To HRTPO Board Meeting Agenda Item #11 HRTPO Strategic Campaign and Vision Plan for Passenger Rail Presentation By May 19, 2010 Transportation Economics & Management Systems, Inc. Study Timeline
More informationDeutsche Bank 5 th Annual Global Industrials and Basic Materials Conference
Deutsche Bank 5 th Annual Global Industrials and Basic Materials Conference Marta R. Stewart Executive Vice President Finance & Chief Financial Officer June 05, 2014 1 Norfolk Southern Update First Quarter
More informationU.S. System Summary: CALIFORNIA
U.S. System Summary: CALIFORNIA California High-Speed Rail System (Source: CHSRA) The California high-speed rail system is a proposed system containing 798 miles of routes in nine segments wholly contained
More informationStifel Transportation and Logistics Conference. Marta R. Stewart Executive Vice President Chief Financial Officer February 11, 2014
Stifel Transportation and Logistics Conference Marta R. Stewart Executive Vice President Chief Financial Officer February 11, 2014 1 Norfolk Southern Update 2013 Overview First Quarter Update Business
More informationMETRO TRANSIT a n n ua l re p o r t. madison, wisconsin // mymetrobus.com
METRO TRANSIT 2016 a n n ua l re p o r t madison, wisconsin // mymetrobus.com metro transit In 2016, Metro Transit took steps to address capacity issues both on and off the road. Off the road, Metro began
More informationREPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES
TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who
More information