A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. - Transmission & Distribution

Size: px
Start display at page:

Download "A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. - Transmission & Distribution"

Transcription

1 A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Muskrat Falls Project - Exhibit 114 Page 1 of 47 Electrical Mechanical /''.., Civil Protection & Control - Transmission & Distribution Telecontrol System Planning UPGRADE TRANSMISSION LINE CORRIDOR Bay d'espoir to Western Avalon September 2011 newfoundland labrador hydro a nalcor energy company

2 Page 2 of 47 Table of Contents 1 INTRODUCTION PROJECT DESCRIPTION EXISTING SYSTEM Age of Equipment or System Major Work and/or Upgrades Anticipated Useful life Maintenance History Outage Statistics Industry Experience Maintenance or Support Arrangements Vendor Recommendations Availability of Replacement Parts Retirements Safety Performance Environmental Performance Operating Regime JUSTIFICATION Net Present Value Levelized Cost of Energy Cost Benefit Analysis Legislative or Regulatory Requirements Historical Information Forecast Customer Growth Energy Efficiency Benefits Losses During Construction Status Quo Alternatives CONCLUSION Project Schedule Newfoundland and Labrador Hydro i

3 Page 3 of 47 1 INTRODUCTION Newfoundland and Labrador Hydro (Hydro) owns and operates eleven 230 kv lines totaling 627 km in length connecting the Bay d Espoir Generating Station to the major load centers and generation in the eastern portion of the province. Figure 1 provides a diagram of the Bay d Espoir East 230 kv transmission system. Holyrood TL202 Sunnyside TL203 Western Avalon TL217 TL242 TL218 Bay d'espoir TL206 TL207 TL237 TL201 TL236 Come By Chance Transmission line crossings removed for clarity Hardwoods Oxen Pond Figure 1 Bay d Espoir East 230 kv Transmission System The Bay d Espoir East 230 kv transmission system is characterized as being a heavily loaded system. Conversely, the 230 kv transmission system west of Bay d Espoir is characterized as being a more lightly loaded system. Table 1 provides a summary of east and west loads at the time of system peaks for the period By comparison the 230 kv transmission system east of Bay d Espoir is loaded to approximately twice the loading of the 230 kv transmission system west of Bay d Espoir. The heavy loading on the eastern portion of the system is coupled with the incentive to provide least cost power to customers by minimizing Holyrood production and maximizing production from hydroelectric resources located in Bay d Espoir and west. Constant monitoring of the load on the eastern portion of the system is therefore required. Thermal load limits on the lines must be strictly enforced to avoid unacceptable line sag and/or potential conductor damage. Further loading pressures will be placed upon the Bay d Espoir East system with the addition of the Vale processing plant at Long Harbour and has already occurred due to the loss of load and net hydroelectric generation increase attributed to the closure of the Abitibi Bowater paper mill Newfoundland and Labrador Hydro Page 1

4 Page 4 of 47 in Grand Falls Windsor. Table 1 Bay d Espoir East and West 230 kv Transmission System Peak Loads 2006 to 2010 Year Bay d Espoir East 1 Bay d Espoir West Notes 1 Bay d Espoir East load equal to TL202 and TL206 flow plus Paradise River, Holyrood and Hardwoods generation at time of peak. 2 Bay d Espoir West load equal to TL204 and TL231 flow plus Cat Arm, Hinds Lake, Stephenville, Hawke s Bay, St. Anthony Diesel Plant generation and Non Utility Generation purchases at time of peak. 3 Connaigre Peninsula loads not included 4 Values based on the Hydro Energy Management System (EMS) hourly data and not weather adjusted Lower Churchill Impacts Given that the Lower Churchill Project has yet to receive final project sanction, analysis of the Bay d Espoir East 230 kv transmission system must consider both the continued Isolated Island Scenario and the Labrador Infeed Scenario. In effect, the proposed project must be appropriate to either an Isolated Island or Labrador Interconnected future. To accomplish this, the Bay d Espoir East 230 kv transmission system was split into two sections Bay d Espoir to Western Avalon and Western Avalon to St. John s. This project considers only the upgrade requirements for the Bay d Espoir to Western Avalon section of the Bay d Espoir East 230 kv transmission system. The Western Avalon to St. John s section can only be considered once the decision on the Lower Churchill Project and subsequent need for the Soldiers Pond Terminal Station is made. With the final decision on the Lower Churchill Project scheduled for late 2011 or early 2012, Hydro intends to submit any necessary upgrade projects for the Western Avalon to St. John s section of the Bay d Espoir East 230 kv transmission system associated with the proposed Lower Churchill Project to The Board as part of its 2013 capital budget application. Newfoundland and Labrador Hydro Page 2

5 Page 5 of 47 2 PROJECT DESCRIPTION The project will consist of a new 230 kv transmission line, 188 km in length connecting Bay d Espoir and Western Avalon Terminal Stations. This includes construction of a 230 kv steel tower transmission line complete with overhead ground wire over its entire length. A minimum conductor size of 795 kcmil, 26/7 ACSR DRAKE with a 75 C conductor temperature rating or 804 kcmil 54/19 AACSR/TW with an 80 C conductor temperature is required to provide the necessary thermal rating for the new circuit. At Bay d Espoir Terminal Station, three 230 kv circuit breakers, six 230 kv motor operated disconnect switches and associated control panels will be added to complete the breaker and one half arrangement on the first two legs of the station layout and accommodate the new 230 kv transmission line termination on a third leg. Figure 2 provides a single line diagram with the proposed additions in red. Newfoundland and Labrador Hydro Page 3

6 Page 6 of 47 Figure 2 Bay d Espoir Terminal Station #2 Additions for New 230 kv Transmission Line At Western Avalon Terminal Station a new 230 kv ring bus consisting of four 230 kv circuit breakers is proposed for the southern end of the terminal station. Rather than construct the new ring bus using traditional gas filled, air insulated circuit breakers and motor operated disconnect switches, Hydro is proposing to use a compact gas insulated switchgear (GIS) ring bus configuration. The rationale for the use of the GIS equipment is to limit the civil works for the ring bus addition. The Western Avalon Terminal Station is situated on the side of a hill near Chapel Arm. The land to the west of the terminal station consists of an upward sloping steep embankment which has had drainage issues in the past. Excavation to the west would to be extremely costly as it would require additional slope Newfoundland and Labrador Hydro Page 4

7 Page 7 of 47 stability and drainage work along with relocation of the existing access road. The land to the east consists of a downward sloping steep embankment to Route 201. Expansion in this direction would require extensive amounts of fill. If acquisition of building lots for private homes in the area of the Western Avalon Terminal Station were to be pursued, a minimal extension to the south side of the station can be accommodated to permit installation of the compact GIS and access road realignment. As part of the GIS ring bus addition, TL208 will be re terminated in the new ring along with the new 230 kv transmission line to Bay d Espoir. This will improve the reliability of the TL208 supply as it will no longer be tripped due to an outage to 230 kv bus B1 or 230/66 kv transformers T1 or T2. Figure 3 provides a single line diagram of the Western Avalon Terminal Station with the proposed additions shown in red. The GIS ring bus addition will contain one spare line termination for a future 230 kv transmission line to the east, if/when it may be required. Hydro has secured the land in the area to permit the future line termination. TL208 to Long Harbour TL237 to Come By Chance TL201 to Hardwoods B3 230 kv B1 230 kv Outdoor GIS Module New to Bay d'espoir Future Line Termination B4 138 kv 230/138 kv T3 & T4 25/33.3/41.7 MVA T5 75/100/125 MVA B2 66 kv T1 & T2 230/66 kv 15/20/25 MVA TL217 to Holyrood TL203 to Sunnyside Figure 3 Western Avalon Terminal Station Additions for New 230 kv Transmission Line It should also be noted that this project also includes a study to investigate suspension insulators on TL206 (Bay d Espoir to Sunnyside). These are original insulators manufactured by NEMA and are of the same vintage as the Canadian Porcelain/Canadian Ohio Brass Newfoundland and Labrador Hydro Page 5

8 Page 8 of 47 insulators that have experienced significant cement growth and mechanical failure over time. However, there is little industry information on the long term mechanical and electrical performance of the NEMA insulators. It is suspected that the NEMA insulators on TL206 do not meet Hydro s existing suspension insulator specification. To confirm the residual mechanical strength of the NEMA insulators following 43 years in service, Hydro is proposing to remove sample strings from service and complete laboratory testing. Cost of this component is estimated at $50,000. Following testing Hydro will be in a better position to report the condition of the TL206 insulators to the Board with a recommendation on a replacement program for the NEMA insulators. As discussed in the Justification Section below, analysis indicates that this new 230 kv transmission line is required to increase firm system capacity in both the continued Isolated Island Scenario and the Labrador Interconnected Scenario. Newfoundland and Labrador Hydro Page 6

9 Page 9 of 47 3 EXISTING SYSTEM The existing Bay d Espoir to Western Avalon transmission corridor consists of five 230 kv transmission lines including: TL202 Bay d Espoir to Western Avalon; TL203 Sunnyside to Western Avalon; TL206 Bay d Espoir to Western Avalon; TL207 Sunnyside to Come By Chance; and TL237 Come By Chance to Western Avalon. Table 2 provides the rating of each transmission line for varying ambient temperature. Table 2 Bay d Espoir to Western Avalon Transmission Corridor Line Ratings TL # MVA Rating for an Ambient Temperature of 30 C 25 C 15 C 0 C TL TL TL TL TL Of these transmission lines, TL202 and TL206 are the most heavily loaded lines during the late spring to early fall time period when the Holyrood Thermal Generating Station is shut down or operating at minimal levels. This is due to the fact that they carry the loads of both the Burin and Avalon Peninsulas along with a portion of the load on the 138 kv transmission loop between Stony Brook and Sunnyside. Load relief to TL202 and TL206 is provided by the Paradise River Hydroelectric Generating Station and the St. Lawrence and Fermeuse wind farms when in operation. Under a line outage contingency Hydro will start its combustion Newfoundland and Labrador Hydro Page 7

10 Page 10 of 47 turbines at Holyrood (10 MW) and Hardwoods (46 MW) to reduce the loading on the transmission corridor. Given a thermal rating of MVA on a 15 C day (i.e. spring/fall) Hydro must limit the loading on TL202 and TL206 to approximately 353 MW ( = 353.7) to ensure that TL202 or TL206 does not become overloaded should TL206 or TL202 trip. Consequently for Bay d Espoir East loads in excess of 353 MW on a 15 C day, Hydro must operate generation at its Holyrood Thermal Generating Station. This inefficiency is further illustrated in Table 3, which includes the triggers used by System Operations to determine when generators at Holyrood Thermal Generating Station are to be brought online. In an optimal situation, the generators at Holyrood would only be dispatched after all hydroelectric generators on the island are brought online (while maintaining sufficient reserve to withstand the loss of the largest unit). These optimal thresholds are indicated in Table 3. Due to the existing thermal limitations, generators at Holyrood must be brought online at load levels that are much lower than the optimal values. The Holyrood units are therefore required to operate much earlier in the fall and later in the spring than would otherwise be required. This problem is compounded as the generators are often dispatched to produce a minimal output power (approximately 70 MW), resulting in a highly inefficient use of fuel. Number of Holyrood Generators In Service Table 3 Thresholds for Bringing Generators Online at Holyrood Thermal Generating Station Optimal Threshold to Bring an Additional Holyrood Generator Online (MW of System Generation) Threshold to Bring an Additional Holyrood Generator Online (MW of System Generation) Threshold/ Optimal Threshold 0* % 1* % % * Holyrood Unit Three online as a Synchronous Condenser Newfoundland and Labrador Hydro Page 8

11 Page 11 of 47 While these factors demonstrate significant restrictions in the operational flexibility of the existing transmission system east of Bay d Espoir, there is a much greater concern relating to transfer capacity. In the event of the loss of a unit at Holyrood, the existing transmission system would be unable to supply system loads above 1280 MW. While this analysis is described in detail in Section 4, it may be noted that the peak load for 2012 is forecasted to exceed 1350 MW. The loss of a unit at Holyrood would therefore result in a significant exposure for unsupplied load. 3.1 Age of Equipment or System The 230 kv transmission lines in the Bay d Espoir to Western Avalon corridor were built between 1965 and The original in service dates of the transmission lines are as follows: TL202 Bay d Espoir to Sunnyside 1966 TL203 Sunnyside to Western Avalon 1965 TL206 Bay d Espoir to Sunnyside 1968 TL207 Sunnyside to Come By Chance 1968 TL237 Sunnyside to Come By Chance Major Work and/or Upgrades The following upgrades have occurred along the Bay d Espoir to Western Avalon transmission corridor since installation: Newfoundland and Labrador Hydro Page 9

12 Page 12 of 47 Table 4 Major Work or Upgrades Year Major Work/Upgrade Comments 2003 TL203 Thermal Uprate The thermal rating of TL203 was increased to meet system loading requirements 2002 TL237 Rebuild Following 1994 ice storm TL237 was rebuilt for a 3 in ice load as part of the Avalon Transmission Upgrade Project 2002 TL207 Rebuild Following 1994 ice storm TL207 was rebuilt for a 3 in ice load as part of the Avalon Transmission Upgrade Project 2001 TL206 Lightning arrester additions Poor lightning performance of TL202 and TL206 resulted in a significant number of simultaneous outages and loss of supply to Avalon Peninsula 1993 to TL202 insulator replacements TL203 line upgraded with high strength kcmil conductor Canadian Ohio Brass insulators replaced Ice storms resulted in failure of TL203 structures and outages to customers. A high strength kcmil conductor was added to 22 km along the two inch ice zones 3.3 Anticipated Useful life The proposed 230 kv transmission line has an estimated service life of 50 years. Newfoundland and Labrador Hydro Page 10

13 Page 13 of Maintenance History As the proposed 230 kv transmission line between Bay d Espoir and Western Avalon is a new asset, there is no maintenance history. 3.5 Outage Statistics As the proposed 230 kv transmission line between Bay d Espoir and Western Avalon is a new asset, there are no available outage statistics. Given the application of an overhead ground wire along its entire length, it is anticipated that the lightning performance of the new line will be very similar to that of TL206 which is equipped with lightning arresters. The mechanical and structural performance of the proposed line will be very similar to that of TL202, TL206, TL207 and TL237 as it will be designed withstand comparable meteorological loading. Outage statistics for existing 230 kv transmission lines in the Bay d Espoir to Western Avalon corridor are as follows: Newfoundland and Labrador Hydro Page 11

14 Page 14 of 47 Table 5 Listing of Transmission Line Terminal Equipment Performance Bay d Espoir to Western Avalon Corridor Transmission Line Frequency (per terminal year) Unavailability (%) TL202 ( ) TL203 ( ) TL206 ( ) TL207 ( ) TL237 ( ) Hydro 230 kv ( ) CEA 230 kv ( ) Frequency (per terminal year) is the number of line outages per line terminal. Unavailability is amount of time the line is not available for terminal related causes. 3.6 Industry Experience As discussed in Section 4, when the load or power transfer requirements of a portion of the transmission system exceed the original rating of the transmission lines, several alternatives are considered in the industry. One alternative is to investigate the potential to increase the rating of the existing transmission lines either through re conductoring or a combination of conductor changes (replacement or re tensioning) and structure modifications (increases in structure height or mid span structures). The second alternative is to consider the addition of new transmission lines at the same or higher voltage to the corridor. A third alternative is to increase the voltage rating of the existing lines. When power system stability becomes an issue along a portion of the transmission system due to changes in the system topology, generation dispatch or load patterns, the two prominent alternatives used in industry include series compensation and the construction of new transmission lines. Newfoundland and Labrador Hydro Page 12

15 Page 15 of 47 Series compensation involves the addition of a capacitor bank in series with the transmission line to effectively reduce its impedance. This reduction allows for the stiffening of the transmission network and improves stability. This technique is used extensively by Hydro Québec TransÉnergie to increase the transmission capacity of their 735 kv network. Series compensation on the 735 kv network ranges from 16% to 50%. The other alternative to improve power system stability is to increase the number of transmission lines and/or voltage levels in a corridor. Like series compensation, the construction of parallel lines allow reduces the overall transmission corridor impedance and thereby stiffens the transmission network so that it is no longer susceptible to instability. When both transmission line ratings and power system stability issues occur along the same transmission corridor, series compensation, in and of itself, is not an effective solution on its own. 3.7 Maintenance or Support Arrangements Normal routine maintenance work for the proposed 230 kv transmission line and associated terminal station equipment will be performed by Hydro personnel. 3.8 Vendor Recommendations This project includes the purchase and installation of new terminal station equipment and the design and construction of a new 230 kv transmission line. Therefore vendor recommendation with respect to repair or replacement is not pertinent. 3.9 Availability of Replacement Parts Required spare parts for terminal station equipment and transmission structure Newfoundland and Labrador Hydro Page 13

16 Page 16 of 47 components will be purchased at the time of the equipment purchases Retirements There will be no retirements as part of this project Safety Performance This project is not required to comply with any specific safety regulation Environmental Performance This project is not required to address any non compliance issues pertaining to environmental regulations Operating Regime The proposed 230 kv transmission line and associated terminal station equipment will be placed in service on a continuous basis, being removed only for regularly scheduled maintenance. Newfoundland and Labrador Hydro Page 14

17 Page 17 of 47 4 JUSTIFICATION As indicated in Section 1, significant development east of Bay d Espoir, particularly on the Avalon Peninsula has resulted in a shift in the province s load distribution. As a result of this shift, the limited transmission capacity east of Bay d Espoir has become the governing factor for determining the total firm capacity of the Newfoundland and Labrador Hydro Transmission System. This limitation is demonstrated in a contingency scenario involving the loss of a unit at Holyrood over peak. As indicated in the load flow analyses below, this worst case scenario would put a significant strain on the Bay d Espoir East transmission system. It should also be noted that the duration of the contingency could be quite extensive if a unit at Holyrood were to be damaged or otherwise out of service. Existing System For the existing system, the contingency involving the loss of a unit a Holyrood is illustrated in Figure 4 where a limit of approximately 854 MW is delivered to loads east of Bay d Espoir. As indicated in the figure, the absolute limit of the transmission system is reached in this case with gas turbines at Holyrood, Hardwoods, and the Newfoundland Power unit at Greenhill brought online for support. It should be noted that the loss of the Holyrood unit does not result in the overloading of transmission lines in this case. Rather, the loss of the unit results in a lack of reactive power support on the Avalon Peninsula. As illustrated, Holyrood Units 2 and 3 are generating 94.8 Mvar and Mvar, respectively, which equals their reactive power limits. If system load were to increase, these units would no longer be able to meet the reactive power consumption of the load, and the system would experience a voltage collapse. Newfoundland and Labrador Hydro Page 15

18 Page 18 of 47 Figure 4 Existing Transmission System Loss of Unit 1 at Holyrood As a result, the transmission system would only have a firm capacity of 1280 MW. As the forecasted system peak for 2012 is 1353 MW (as indicated in Section 4.6), this would result in a significant exposure for unsupplied load. This result would indicate that there is an immediate need for enhancements to the transmission system east of Bay d Espoir. By comparison, analysis performed in indicated that this violation in the firm system capacity of the transmission system east of Bay d Espoir would not occur until the end of the five year planning horizon. A summary of this analysis is provided in Table 6. The next available load forecast from Newfoundland Power for use in the planning and capital budget cycle revealed actual system peaks for As indicated in Table 6, these figures are higher than previously forecasted. Given the near term violation Newfoundland and Labrador Hydro Page 16

19 Page 19 of 47 of the firm transmission capacity criterion, a detailed investigation was performed to identify acceptable transmission system alternatives that will meet all technical requirements. Table 6 Forecasted Load for the Bay d Espoir East Transmission System Forecast Year Load (MW) Percent Loading* (%) 96% 98% 99% 100% 102% 2010 Load (MW) Percent Loading* (%) 102% 103% 106% 108% 114% *Percent Loading is based on an existing system capacity of 854 MW east of Bay d'espoir. As indicated in the following sections, the required transmission upgrades have been identified for both proposed generation expansion scenarios including a continued Isolated Island and a Labrador Infeed. These upgrades have been reviewed from a technical standpoint to ensure that the proposed solution would ensure sufficient system capacity for both scenarios. Continued Isolated Island Under a continued Isolated Island generation expansion scenario, the least cost hydroelectric generation sources include: Island Pond 36 MW Round Pond 18 MW Portland Creek 23 MW These sources are all located west of Bay d Espoir and a continued Isolated Island scenario would therefore result in increased loading on the Bay d Espoir to Western Avalon transmission corridor. In such a scenario, the system s existing transfer limits would not be acceptable. No additional generation would be installed east of Bay d Espoir in a continued Isolated Newfoundland and Labrador Hydro Page 17

20 Page 20 of 47 Island scenario until the 2022 timeframe when a 170 MW combined cycle combustion turbine (CCCT) would be installed on the Avalon Peninsula. Transmission upgrades are therefore required. Alternatives for the transmission system East of Bay d Espoir include: (1) Performing thermal upgrades on TL202, TL206 and TL203; (2) Installing series compensation on TL202 and TL206; (3) Constructing a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station; (4) Installing shunt capacitor banks; (5) Performing thermal upgrades on TL202, TL206 and TL203, installing series compensation on TL202 and TL206, and installing shunt capacitor banks; (6) Constructing a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station and installing shunt capacitor banks; (7) Adding a 315 kv transmission line; or (8) Adding a 315 kv transmission line and installing shunt capacitor banks. A proposal involving only thermal upgrades on TL202, TL206 and TL203 would not improve system capacity. As demonstrated in Figure 4, system limitations for the contingency involving the loss of Holyrood Unit 1 relate primarily to reactive support on the Avalon Peninsula. Solutions involving thermal upgrades alone are only applicable after sufficient reactive power compensation has been added to the system and transmission lines become overloaded at higher system loads. The installation of series compensation on TL202 and TL206 would help to improve transmission capacity east of Bay d Espoir by reducing the amount of reactive power absorbed by the lines. Using the Hydro Québec TransÉnergie system as a benchmark (as discussed in Section 3.6), an upper limit of 50% series compensation was added to each line. This level of compensation maximizes the transfer capability of the transmission system. Newfoundland and Labrador Hydro Page 18

21 Page 21 of 47 Figure 5 illustrates the result with 50% series compensation on TL202 and TL206. In this scenario 940 MW is transferred to loads east of Bay d Espoir before the limits of the reactive power support on the Avalon Peninsula are reached. Loads in this case are representative of a scenario where total system generation is approximately 1410 MW. At this increased loading level, analysis indicates that no transmission line overloading would occur under any contingency. Series compensation therefore provides an increase of 130 MW in the capacity of the Island transmission system. Figure 5 Series Compensation Loss of Unit 1 at Holyrood Another alternative to improve the transfer capability of the existing system would involve the construction of a new 230 kv transmission line from Bay d Espoir to Western Avalon. As illustrated in Figure 6, the Bay d Espoir East Transmission System would be able to transfer approximately 950 MW to loads in the contingency case involving the loss of a unit at Newfoundland and Labrador Hydro Page 19

22 Page 22 of 47 Holyrood. This scenario is representative of a loading condition where total system generation is in the order of 1440 MW. The new transmission line would therefore increase the capacity of the existing system by approximately 140 MW. Figure 6 New 230 kv BDE WAV Transmission Line Loss of Unit 1 at Holyrood In each of the cases defined above, it is noted that the capacity of the Bay d Espoir East Transmission System is limited primarily due to a lack of reactive power support on the Avalon Peninsula. A logical proposed would be to investigate the addition of capacitor banks as a means of avoiding voltage collapse. The application of capacitors is illustrated in Figure 7 where a 153 Mvar bank is installed at Come by Chance Terminal Station. This site was selected at it represents one of the lowest points in the system s voltage profile and also due to the stringent undervoltage limitations Newfoundland and Labrador Hydro Page 20

23 Page 23 of 47 required for the operation of the North Atlantic Refinery. As illustrated, this system would able to transfer 950 MW to loads east of Bay d Espoir. It should also be noted that at this increased loading level, no transmission lines would be overloaded under contingency. From a voltage stability and thermal overload perspective, the firm capacity of the transmission system in this case would reach 1420 MW. Figure 7 Capacitor Bank Installation Loss of Unit 1 at Holyrood While the addition of the capacitor banks on the Avalon Peninsula would increase the voltage stability of the system by providing significant reactive power support, the system must also be designed to have an adequate angular stability. This type of stability refers to the ability of the generators within the transmission system to maintain synchronism following a disturbance. In an ac transmission system, the only way to increase the angular stability is to add transmission lines or to provide series compensation for existing lines. Newfoundland and Labrador Hydro Page 21

24 Page 24 of 47 A solution involving the addition of shunt capacitor banks alone would therefore not improve the angular stability of the power system. Figure 8 demonstrates the angular stability of a generator at Holyrood following a contingency involving an unsuccessful reclose for a single line to ground fault event on transmission line TL202. Figure 8 Angular Stability following SLG Fault on TL202 The blue line in Figure 8 illustrates the post fault behaviour of the Holyrood unit for the scenario where the transmission system is reinforced with the new 230 kv circuit from Bay d Espoir to Western Avalon. As indicated, the system demonstrates angular stability as the unit quickly settles to a constant relative rotor angle. A similar result is illustrated by the red line, which demonstrates the angular stability of the system when reinforced with series compensation on TL202 and TL206. Newfoundland and Labrador Hydro Page 22

25 Page 25 of 47 The green line in Figure 8 indicates that the system is highly unstable in a scenario where only shunt capacitor banks are added to the transmission system. Following the fault, the unit at Holyrood would begin to oscillate uncontrollably and would have to be tripped to avoid damage. This situation would then require underfrequency load shedding in an attempt to prevent the collapse of the Island Transmission System. Due to the poor angular stability of this system, a solution involving the addition of a shunt capacitor bank alone would not be an acceptable solution. Based on the analysis, it is evident that in order to increase the capacity of the Bay d Espoir East Transmission System, both voltage stability and the angular stability must be improved. As noted, a combination of transmission line reinforcement and reactive support in the form of capacitor banks would provide an optimal solution. Figure 9 illustrates a scenario involving series compensation on TL202 and TL206 and a new capacitor bank at Come by Chance. As indicated, this system allows for the transfer of 1017 MW to loads east of Bay d Espoir. It should be noted that at this increased load level, contingencies on TL202, TL206, or TL207 would result in thermal overloading on TL206, TL202, and TL203, respectively. Thermal uprating of these lines are therefore required in this case. For TL202 and TL206, thermal uprating would require the installation of mid span structures and the modification of terrain in the transmission line right of way. For TL203, uprating would require that the full line (44 km) be re conductored with 795 kcmil, 26/7 ACSR DRAKE with additional mid span structures or 804 kcmil 54/19 AACSR/TW with additional mid span structures and modifications to dead end structures. With the 795 conductor, TL202, TL206, and TL203 will each be rated for a conductor temperature of 75 C. The 804 conductor option will allow for TL203 to be rated for a conductor temperature of 80 C. Total system generation in this case would be in the order of 1485 MW. While this would represent an increase of 235 MW in firm transmission system capacity over the existing Newfoundland and Labrador Hydro Page 23

26 Page 26 of 47 system, this solution would not be adequate to meet capacity requirements beyond As additional generating capacity would not be added east of Bay d Espoir until 2022, this solution would not provide an acceptable technical alternative. Figure 9 Series Compensation, Thermal Upgrades, and Capacitor Bank Loss of Unit 1 at Holyrood The scenario involving the addition of a new 230 kv transmission line from Bay d Espoir to Western Avalon and a capacitor bank at Come by Chance is illustrated in Figure 10. In this case, the transmission system is capable of providing firm supply of approximately 1045 MW to loads east of Bay d Espoir. System generation in the case would be in the order of 1555 MW, which would indicate that these upgrades would increase the firm capacity of the transmission system by 275 MW. The addition of the third line would also allow for the thermal uprating of transmission lines TL202, TL206, and TL203 to be avoided. The alternative also ensures sufficient transmission capacity until 2022, at which point and 170 Newfoundland and Labrador Hydro Page 24

27 Page 27 of 47 MW of generation would be available on the Avalon Peninsula following the construction of a new 170 MW CCCT. Figure 10 New 230 kv TL and Capacitor Bank Loss of Unit 1 at Holyrood As part of the investigation, solutions involving the increase of the system voltage in the Bay d Espoir to Western Avalon transmission corridor were also considered. Specifically, analysis was performed involving a new 315 kv line from Bay d Espoir to Western Avalon. Results of this analysis indicate that the addition of a transmission line at this voltage would increase in the transfer capacity of the system only slightly beyond the thresholds reached in the previous example. As illustrated in Figure 11, the addition of the 315 kv transmission line would not allow for an appreciable increase in transfer capacity over the case involving a new 230 kv transmission line. Due to reactive power limitations of the system, the Newfoundland and Labrador Hydro Page 25

28 Page 28 of 47 transfer limit of the Bay d Espoir East Transmission System is limited to 950 MW. Firm total system capacity is therefore limited to approximately 1440 in this case. Figure 12 New 315 kv Transmission Line Loss of Unit 1 at Holyrood If a new 315 kv circuit were to be supplemented with a capacitor bank at Come By Chance, approximately 1065 MW to be transferred to loads east of Bay d Espoir, as illustrated in Figure 12. This would be representation of a loading condition where system generation has reached approximately 1583 MW. Newfoundland and Labrador Hydro Page 26

29 Page 29 of 47 Figure 12 New 315 kv TL and Capacitor Bank Loss of Unit 1 at Holyrood It should also be noted that the establishment of the 315 kv transmission voltage would require fully redundant 230/315 kv transformation at both Bay d Espoir Terminal Station #2 and Western Avalon Terminal Station, complete with 315 kv circuit breakers and disconnect switches. Such an addition would also require the complete set of terminal station additions described above in Section 2 to permit the interconnection of 315 kv infrastructure to the existing stations. In combining this extensive listing of terminal station upgrades to the increased construction cost of a 315 kv transmission line, this solution would involve an increased capital expenditure without providing a substantial improvement in system capacity beyond those provided by the 230 kv alternatives discussed above. Based on the results presented, it is concluded that an optimal solution for improving transmission system capacity would involve a combination of transmission line Newfoundland and Labrador Hydro Page 27

30 Page 30 of 47 reinforcement and reactive support. A solution involving only reactive support would not be acceptable due to poor angular stability, while a solution involving only thermal upgrades would not improve system capacity. Reinforcements in the form of series compensation or a new transmission line would therefore be required. Solutions involving the series compensation do not provide sufficient system capacity beyond 2017 and are not acceptable given that no generation will be added east of Bay d Espoir until Therefore, a new transmission line should be constructed from Bay d Espoir to Western Avalon to meet the 2022 transfer requirement. Both the 230 kv and 315 kv transmission line alternatives were considered. It has been determined that solutions involving 315 kv transmission lines require a significant number of additional system upgrades while only provided marginal improvements in system capacity. Given this result, the construction of a new 230 kv transmission line is found to be the optimal solution for a generation expansion scenario involving the continued Isolated Operation of the Island System. Labrador Infeed Under the Labrador Infeed generation expansion scenario the concept includes a 900 MW HVdc transmission system between Muskrat Falls in Labrador and Soldiers Pond on the Avalon Peninsula and a second 500 MW HVdc transmission system between western Newfoundland (Bottom Brook Terminal Station) and Cape Breton, Nova Scotia. The power and energy delivered to the Island from Labrador will displace that generated at the Holyrood Thermal Generating Station. Up to 816 MW will be delivered to the Island over peak. The HVdc system to the Maritimes will operate as an export line under normal operation with power and energy in excess of the Province s needs being sold to the Maritime and New England markets. For loss of the HVdc system between Labrador and the Island, the HVdc link to the Maritimes will be capable of delivering up to 475 MW to the Island in the post contingency period. Newfoundland and Labrador Hydro Page 28

31 Page 31 of 47 As part of the preliminary technical feasibility analysis performed for the Lower Churchill Project, a series of integration studies have included investigations of the upgrades required within the Island Transmission System to ensure reliability and security of supply for the Project. In these studies, many contingencies were investigated. A benchmark case was chosen to assess transient system stability in the event of a three phase fault near the 230 kv bus at Sunnyside Terminal Station. This three phase fault was identified as being particularly severe as it would (1) suppress ac system voltages to a point where the HVdc link from Labrador would experience a commutation failure (effectively causing it to shut down during the fault), while (2) impacting the transmission of power from hydroelectric sources to the significant loads in the eastern portion of the province. Results of the transient stability studies indicate that the system would be able to withstand the three phase fault at Sunnyside Terminal Station with appropriate system upgrades. The upgrades include the installation of high inertia synchronous condensers and either: (1) series compensation on TL202 and TL206; or (2) a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station. Stability plots for the above cases are provide in Figures 13 and 14, respectively. Newfoundland and Labrador Hydro Page 29

32 Page 32 of 47 Figure 13 Stability Plot from DC1210 HVdc System Sensitivity Analysis Three Phase Fault on TL202 Series Compensation on TL202 and TL206 Newfoundland and Labrador Hydro Page 30

33 Page 33 of 47 Figure 14 Stability Plot from DC1210 HVdc System Sensitivity Analysis Three Phase Fault on TL202 New 230 kv Transmission Line from BDE WAV Newfoundland and Labrador Hydro Page 31

34 Page 34 of 47 While each of these alternatives ensures transient stability for specified 230 kv system contingencies, the transmission capacity of the Bay d Espoir to Western Avalon corridor also has a significant impact in a scenario involving the loss of the HVdc link between Labrador and the Island. For this contingency, power will be imported from the Maritimes to supplement the startup of standby generation on the Island. As in the continued Isolated Operation, Island System upgrades consisting of series compensation for transmission lines TL202 and TL206 will increase the angular stability of the power system, as illustrated in Figure 13. However, unlike the continued Isolated Operation scenario, the Holyrood Thermal Generating Station is not available to provide active power (MW) to the Bay d Espoir East Transmission System in the Labrador Infeed Scenario. As a result, contingencies involving the loss of the Labrador Infeed would result significant overloading on the transmission lines, and therefore require the thermal uprating of TL202, TL206, and TL203. Despite these thermal upgrades, analysis has indicated that thermal overloading will occur on TL202 and TL206 following the loss of the HVdc link from Labrador. Figure 15 illustrates the case where all generation on the island is brought online and a full import of 475 MW is received from the Maritimes following the loss of the HVdc link from Labrador. In this case, 1060 MW is being supplied to loads east of Bay d Espoir. As illustrated, the uprated TL202 and TL206 will be loaded to 107% of their rated limits. This will result in the sagging of the transmission lines beyond Newfoundland and Labrador Hydro s clearance requirements. Such violations are unacceptable as they could lead to potential safety concerns. Analysis indicates that thermal overloads will be experienced on TL202 and TL206 if the import from the Maritimes were to exceed 440 MW. Newfoundland and Labrador Hydro Page 32

35 Page 35 of 47 Figure 15 Thermal Upgrades and Series Compensation Loss of HVdc Infeed Figure 16 demonstrates how the addition of the new 230 kv transmission line between Bay d Espoir and Western Avalon results in the elimination of all transmission line overloads. This solution will allow for firm transmission system capacity in excess of 1600 MW in the event of the loss of the Labrador Infeed without any thermal upgrades to TL202, TL206, or TL203. Newfoundland and Labrador Hydro Page 33

36 Page 36 of 47 Figure 16 New 230 kv Transmission Line Loss of HVdc Infeed It should be noted that reactive compensation in the form of a 153 Mvar capacitor bank at Come by Chance was included in both of the cases described above. Without this capacitor bank, the system would suffer from low voltage violations in the event of the loss of the Labrador Infeed. This capacitor bank can be considered part of the overall reactive power requirements of the HVdc converter station in this scenario. Based on the analysis, it is concluded that a new 230 kv circuit from Bay d Espoir to Western Avalon meets all of the technical requirements for the Labrador Infeed Scenario. Newfoundland and Labrador Hydro Page 34

37 Page 37 of 47 This new circuit ensures transient stability during severe ac contingencies and security of supply in the event of the failure of the HVdc link from Labrador. In order for this transmission line to be in service prior to the proposed HVdc interconnection in 2017, line construction must begin in 2012 as per the five year project schedule provided in Section 5.2. Analysis of the thermal upgrades plus 50% series compensation on TL202 and TL206 indicate that the option cannot provide the transfer capacity required to supply the loads east of Bay d Espoir in the event of the failure of the HVdc link from Labrador. 4.1 Net Present Value The construction of a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station is a technical requirement needed to meet the forecasted system loads east of Bay d Espoir. A complete net present value analysis was not performed as the project is required in both the Labrador Infeed and continued Isolated Operation generation expansion alternatives. As a result of being common to both alternatives, the cost of the project has no relevant impact on overall cumulative present worth. 4.2 Levelized Cost of Energy The levelized cost of energy is a high level means to compare costs of developing two or more alternative generating sources. Therefore, the levelized cost of energy is not applicable for the project. 4.3 Cost Benefit Analysis The new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station is a technical requirement needed to meet the forecasted system loads east of Bay d Espoir. A complete cost benefit analysis was not performed as the project is common to both the Newfoundland and Labrador Hydro Page 35

38 Page 38 of 47 Labrador Infeed and continued Isolated Operation generation expansion scenarios. 4.4 Legislative or Regulatory Requirements This project is not required to comply with legislation or regulations. The project is required to ensure reliable operation of the power system and to supply forecasted loads east of Bay d Espoir while adhering to all system planning criteria. 4.5 Historical Information The proposed project is not routine and is a technical requirement to meet load growth east of Bay d Espoir for the Labrador Infeed and continued Isolated Operation generation expansion scenarios. 4.6 Forecast Customer Growth The 2010 Peak Load Forecast for the Newfoundland and Labrador Hydro System is provided in Table 7. This forecast is equal to the 2010 Peak Load Forecast for the Interconnected Island System minus generation from Newfoundland Power and Deer Lake Power. Based upon the peak system load data presented in Table 1, it is estimated that loads east of Bay d Espoir will account for approximately 67% of the total system load. These values have been corrected to account for additional load associated with the Vale facility in Long Harbour and also for the reduced system losses in cases involving the construction of a new transmission line from Bay d Espoir to Western Avalon. This reduction in losses would effectively decrease the required transfer capacity east of Bay d Espoir. Newfoundland and Labrador Hydro Page 36

39 Page 39 of 47 Table Newfoundland and Labrador Hydro System Peak Load Forecast Year NLH System Generation (MW) Required BDE East Transmission System Capacity (MW) Required BDE East Transmission System Capacity (With New TL) (MW) Energy Efficiency Benefits The new 230 kv circuit significantly increases the transmission capacity east of Bay d Espoir to and allows for improved efficiency in the operation of generators at Holyrood. This results in reduced fuel consumption and, in turn, may reduce the potential for spill at hydroelectric facilities in a continued Isolated Operation generation expansion scenario. These values require extensive hydrological modeling to be quantified. 4.8 Losses During Construction There are no anticipated losses during construction. Newfoundland and Labrador Hydro Page 37

40 Page 40 of Status Quo A solution involving the status quo would not be acceptable for generation expansion scenarios involving a Labrador Infeed or continued Isolated Operation. In a generation expansion scenario involving the Labrador Infeed, the existing transmission system must be reinforced to maintain stability in the event of contingencies on the 230 kv system. Upgrades to the Bay d Espoir East Transmission System are also required to ensure security of supply in the event of contingencies involving the loss of the Labrador Infeed via import from the Maritimes. For a generation expansion scenario involving continued Isolated Operation, the limitations of the existing transmission system result in an inadequate transfer capacity for loads east of Bay d Espoir. This is of particular concern as all proposed hydroelectric developments in this scenario are west of Bay d Espoir Alternatives Alternatives considered for this project include: (1) Performing thermal upgrades on TL202, TL206 and TL203; (2) Installing series compensation on TL202 and TL206; (3) Constructing a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station; (4) Installing shunt capacitor banks; (5) Performing thermal upgrades on TL202, TL206 and TL203, installing series compensation on TL202 and TL206, and installing shunt capacitor banks; (6) Constructing a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station and installing shunt capacitor banks; (7) Adding a 315 kv transmission line ; or Newfoundland and Labrador Hydro Page 38

41 Page 41 of 47 (8) Adding a 315 kv transmission line and installing shunt capacitor banks. Based upon the analysis in Section 4, a new 230 kv transmission line from Bay d Espoir to Western Avalon Terminal Station (supplemented with reactive support in the form of shunt capacitor banks) is the preferred alternative for generation expansion scenarios involving both the Labrador Infeed and continued Isolated Operation. Newfoundland and Labrador Hydro Page 39

42 Page 42 of 47 5 CONCLUSION It is recommended that a new 230 kv transmission line be constructed from Bay d Espoir to Western Avalon Terminal Station. This upgrade is required to ensure the security of supply for loads east of Bay d Espoir in generation expansion scenarios involving both a Labrador Infeed and a continued Isolated Operation. Budget Estimate Table 8 Budget Estimate Project Cost: ($ x1,000) TOTAL Material Supply , , , , ,076.8 Labour 2, , , , , ,135.1 Consultant Contract Work , , , , ,399.1 Other Direct Costs ,164.4 Interest and Escalation , , , , ,984.0 Contingency , , , , , , , ,376.3 Newfoundland and Labrador Hydro Page 40

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical.1_ UFSS#p A:_. DAVID/ IC, L re Mechanical Civil Protection & Control an LAND& 4^ Transmission & Distribution Telecontrol System Planning

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical vo1e.5s 0j 44, AMY., CK NI r. SIGNATURE Mechanical Civil Protection & Control t^ /DATE 1 o Transmission & Distribution AND Telecontrol

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4a >estro Mechanical re *.i Civil f ::^:s '1 E 1 t i^.l. al1.i 2 Or Protection & Control Transmission & Distribution Telecontrol System

More information

Insulator Replacements

Insulator Replacements A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Insulator Replacements Electrical Mechanical. Civil Protection & Control Transmission & Distribution Telecontrol System Planning HYDRO THE POWER

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical Mechanical Civil Protection & Control S1GNATLJL 2oü 4 "DAT Transmission & Distribution Telecontrol - System Planning OVERHAUL DIESEL

More information

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4v ^c 0:01'1 S0^O c.. ^ '^ W E. G. PIERCY i^ x zoto/off/zq,.'ftrif4^#ft^^,' r Mechanical Civil Protection & Control Transmission &

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines.

A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines. A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES Electrical Mechanical ( Protection Civil & Control & Distribution System Planning Overhaul Diesel Engines Various Locations July 2012 newfoundland

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

NEWFOUNDLAND AND LABRADOR HYDRO. Glossary of Terms

NEWFOUNDLAND AND LABRADOR HYDRO. Glossary of Terms NEWFOUNDLAND AND LABRADOR HYDRO AC See Alternating Current Alternating Current (AC) A continuous electric current that regularly reverses direction, usually sinusoidally. Alternating current is used in

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

We trust the foregoing is satisfactory. If you have any questions or comments, please contact the undersigned.

We trust the foregoing is satisfactory. If you have any questions or comments, please contact the undersigned. \ newfoundland labrador hydro a nalcor energy company Hydro Place. 00 Columbus Drive. P.O. Box 00. St. John's. NL Canada AB K t. 0..00 f. 0..00 www.nh.nl.ca December, 0 The Board of Commissioners of Public

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Unit Protection System for Pumped-Storage Power Stations

Unit Protection System for Pumped-Storage Power Stations Unit Protection System for Pumped-Storage Power Stations 1. Introduction In many power systems, pumped-storage power stations are used in addition to run-of-river power stations. These power stations serve

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

A REPORT TO. Electrical. Mechanical. Civil. Transmission & Distribution. System Planning REPLACE UNIT 2 STEAM SEAL REGULATOR

A REPORT TO. Electrical. Mechanical. Civil. Transmission & Distribution. System Planning REPLACE UNIT 2 STEAM SEAL REGULATOR A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical ^ ^^ t wiessio PBG n ^, wl I,,dn,w l.n Mechanical Civil T I.C LINS Protection & Control 41 41 4-01 "i"""11'"" ii. cl u Z`^ M 1K ' ^""

More information

Muskrat Falls Project - Exhibit 26 Page 1 of 14 FORCED OUTAGE RATES 2006 UPDATE

Muskrat Falls Project - Exhibit 26 Page 1 of 14 FORCED OUTAGE RATES 2006 UPDATE Page 1 of 14 FORCED OUTAGE RATES 2006 UPDATE System Planning December 2006 1 Page 2 of 14 1. INTRODUCTION The Forced Outage Rates (FOR) used as a basis for STRATEGIST modeling are derived from the Canadian

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS NORTH AUCKLAND AND NORTHLAND GRID UPGRADE PROJECT ATTACHMENT J OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS UPGRADE WITH HIGH TEMPERATURE LOW SAG CONDUCTOR September 2007 Contents 1 INTRODUCTION

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

CI Number: ACE CI Page 1 of 9. Title: Metro Voltage Support - Add Capacitor Bank

CI Number: ACE CI Page 1 of 9. Title: Metro Voltage Support - Add Capacitor Bank 216 ACE CI 46587 Page 1 of 9 CI Number: 46587 Title: Metro Voltage Support Add Capacitor Bank Start Date: 215/6 InService Date: 216/12 Final Cost Date: 217/6 Function: Transmission Forecast Amount: 3,373,511

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Line using HTLS Conductors to increase

Line using HTLS Conductors to increase Upgradation of 132kV Transmission Line using HTLS Conductors to increase the load transfer capacity. By Srikrushna S. Navlakhe Executive Engineer, EHV Construction cum Operation and Maintenance Zone, MSETCL,

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Mr. Geoffrey Young Newfoundland and Labrador Hydro P.O. Box St. John's, NL AIB 4K7.

Mr. Geoffrey Young Newfoundland and Labrador Hydro P.O. Box St. John's, NL AIB 4K7. NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES 120 Torbay Road, P.O, Boa 21040, St. John's, Newfoundland and Labrador. Canada, AlA 5B2 E-mail: gyoung@nlh,nl.ca 2014-08-22 Mr. Geoffrey

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2 Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Quarterly Regulatory Report December 31, 2014 Appendix E Annual Report on Key Performance Indicators A REPORT TO 2014 ANNUAL REPORT

Quarterly Regulatory Report December 31, 2014 Appendix E Annual Report on Key Performance Indicators A REPORT TO 2014 ANNUAL REPORT 1\1LH 2013 Amended General Rate Application Information - 'kt ) p iled:p ''Gelb- Board Secretary: Quarterly Regulatory Report December 31, 2014 Appendix E A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

June Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA

June Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA 2.1 2012 Substatiort Refu14bislrment and Modernization NP 2012 CBA 2012 Substation Refurbishment and Modernization June 2011 Prepared by: Peter Feehan, P.Eng. A FORTIS COMPANY 2.1 2012 Substation Refurbishment

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

2011 Substation Refurbishment and Modernization. June 2010

2011 Substation Refurbishment and Modernization. June 2010 Z,1 Substatiort Refurbish~nent and Modernization NP 2011 CBA 2011 Substation Refurbishment and Modernization June 2010 Prepared by: Peter Feehan, P.Eng. 2.1 2011 Substation Refurbishment and Modernization

More information

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants

More information

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8 Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,

More information

and Board Secretary Newfoundland and Labrador Hydro 2017 Capital Budget Application Revision

and Board Secretary Newfoundland and Labrador Hydro 2017 Capital Budget Application Revision ANir I newfoundland labrador a nalcor energy company September 7, 2016 Hydro Place. 500 Columbus Drive. P.O. Box 12400. St. John's. NI Canada AlB 4K7 t. 709.737.1400 f. 709.737.1800 www.n1h.nl.ca Board

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions

More information