Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension

Size: px
Start display at page:

Download "Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension"

Transcription

1 Appendix C 5% Design Plan and Profile Drawings/ Additional Design Information The 5% plan and profile drawings were provided in a separate volume with the Draft Local EA and have not changed. Hard copies are available for review at study area libraries and at DART Headquarters. An electronic PDF version is available for viewing on Final Local Environmental Assessment C 1

2 ADDITIONAL DESIGN INFORMATION The following information was developed after the issuance of the 5% Preliminary Engineering (PE) drawings provided with the Draft Environmental Assessment (EA). The 5% PE package is not being modified for this Final EA; however, some of the information discussed below has resulted in design refinements that are addressed in this Final EA and will be carried forward into final design. Exhibit 1 Geothermal Wells and Police Driveway Relocation Exhibit 2 Ledbetter Station Platform Extension and Level Boarding Modifications Concept Exhibit 3 Ledbetter Station Architectural Site Plan Changes Exhibit 4 Oncor Transmission Lines Crossing and Steel Pole Assessment C 2 Final Local Environmental Assessment

3 GEOTHERMAL WELLS AND POLICE DRIVEWAY RELOCATION After issuing the 5% PE drawings, DART was informed that multiple geothermal wells exist in the landscaped area on the east side of the Dallas South Central Police Station between the police station building and Patrol Way. This area is where the proposed bridge structure for the South Oak Cliff Corridor Blue Line Extension project is located. As built drawings showing the geothermal wells were subsequently received from the City of Dallas. The actual configuration of the geothermal wells was estimated based on coordination with engineers and contractors involved with the geothermal well installation and will need to be verified as part of additional subsurface utility investigation (SUE) during final design. The attached exhibit shows the estimated location of the geothermal wells, and also shows proposed modifications to the 5% design. The proposed design avoids the geothermal wells, and also includes relocation of the northern police station driveway in order to increase the vertical clearance over the driveway from between the foot clearance discussed in the Draft EA to a new clearance of 15.8 feet described in this Final EA. The second exhibit includes a cross section showing that the total structural depth of the bridge structure above the driveway can be decreased in order to provide the 15.8 foot vertical clearance at that location. Also, moving the driveway south would allow for installation of bridge piers in locations outside the anticipated geothermal well areas near the driveway. Final Local Environmental Assessment C 3

4 SOC3-CC1-0010b-GEO /27/2012 5:01:29 PM SMH CLEARANCE CLEARANCE MIN DWG No. RELOCATE 12" WATER LINE 11/27/2012 I:\Projects\_SOUTH\GPC 5\TO 24 SOC-3 PE-EA\EXHIBITS\Geo Wells Exhibits\SOC3-CC1-0010b-GEO TS ROW 510 SMH FH SC TS " (TYP) DALLAS8" PVCSS EXISTING GEOTHERMAL WELL (TYP.) (SEE NOTE 5) DALLAS12" PVCW SC SOC-3 NB SOC-3 SB 8-6" (TYP) CONSTRUCT NEW CURB INLET DALLAS 24" RCP SD PIER OFFSET FROM CENTER OF BRIDGE (SEE NOTE 4) DALLAS36" RCPSD FH RELOCATE FIRE HYDRANT 80 ROW RELOCATE DRIVEWAY EXISTING GEOTHERMAL WELL (TYP.) (SEE NOTE 5) SOC3-CC SOC3-C AS REQUIRED IN AREA OF PROPOSED BRIDGE PIERS ADJACENT TO PATROL WAY. PROPOSED ROW DALLAS8" PVCSS 490 DALLAS12" PVCW SOC-3 NB SOC-3 SB PROPOSED ROW PIER OFFSET FROM CENTER OF BRIDGE (SEE NOTE 4) DALLAS SOUTH CENTRAL POLICE STATION RCP 15-6" (TYP) SD DALLAS 48" ONCORUGE12.5 KV 490 RCP DALLAS SD 24" 24" CS RCP CS NOTE: HORIZ VERT SOC3-C (SB) SOC3-CC (NB) Rc= Rc= Ls= Lc= Ea= Eu= V= " 1.53" 30 MPH SCALE (IN FEET) SCALE (IN FEET) Ls= Lc= Ea= Eu= V= " 1.49" 30 MPH 1. SEE DWG. No. CC FOR ADDITIONAL NOTES. 2. LOSS OF PARKING SPACES AT THE DALLAS POLICE SUBSTATION MUST BE MITIGATED PRIOR TO CONSTRUCTION. FINAL DESIGNER MUST COORDINATE FURTHER WITH THE CITY OF DALLAS AND DART TO DETERMINE THE LOCATION AND CONFIGURATION OF REPLACEMENT PARKING SPACES, DRIVE AISLES AND OTHER SITE IMPROVEMENTS AFFECTED BY THIS PROJECT. chad_allen_v8i $$MODEL$$ PROPOSED T/R ELEV EXISTING GROUND ELEV STA END CAMP WISDOM STATION VPC % ex = 0.78 K = 108 LVC= 260 EL PVI EL VPT EL % VPC EL INVERTED TEE TX28 PIER CAP PROPOSED TOP OF RAIL ex = K = 113 LVC= 440 BEAM EXISTING ENTRANCE EXISTING PROPOSED DRIVEWAY DRIVEWAY EXISTING GROUND PVI EL MINIMUM REQUIRED VERTICAL CLEARANCE OF 16.5 FEET ACCORDING TO DART DESIGN CRITERIA IS NOT BEING PROVIDED OVER THE NORTHERN DRIVEWAY CONNECTION TO THE DALLAS SOUTH CENTRAL POLICE STATION. A DART DESIGN EXCEPTION WILL BE REQUIRED DURING THE FINAL DESIGN EFFORT IF DART AND THE CITY OF DALLAS AGREE TO LEAVE THE DRIVEWAY OPEN, OR THE DRIVEWAY MAY BE CLOSED AND DEMOLISHED AS PART OF THE PROJECT. IF THE DRIVEWAY IS REMOVED, REPLACEMENT ACCESS MAY NEED TO BE PROVIDED FROM CAMP WISDOM ROAD AT THE WEST SIDE OF THE POLICE STATION PROPERTY. ADDITIONAL COORDINATION WITH THE CITY OF DALLAS AND DART ABOUT THIS ISSUE IS REQUIRED PRIOR TO COMPLETION OF THE FINAL DESIGN PROCESS. 4. CRASH PROTECTION MAY BE REQUIRED FOR ROAD ADJACENT TO PROPOSED BRIDGE PIERS. FINAL DESIGNER TO DETERMINE IF CRASH PROTECTION IS REQUIRED PER CITY OF DALLAS CRITERIA. THE EXISTING SIDEWALK AT EACH PIER LOCATION WILL NEED TO BE RECONSTRUCTED AND REROUTED AROUND THE PIER. 5. THE LOCATIONS OF THE GEOTHERMAL WELLS SHOWN ON THIS SHEET ARE APPROXIMATE AND ARE BASED ON RECORD DRAWINGS PROVIDED BY THE CITY OF DALLAS. THE FINAL DESIGN TEAM SHALL FIELD VERIFY THE THE LOCATIONS OF THE GEOTHERMAL WELLS IN THE VICINITY OF THE PROPOSED BRIDGE PIERS PRIOR TO ISSUING FINAL CONSTRUCTION PLANS FOR THE PROJECT. THE LOCATIONS OF SOME OF THE PROPOSED BRIDGE PIERS MAY NEED TO BE ADJUSTED, OR DART AND THE CITY OF DALLAS MAY DECIDE TO RELOCATE SOME OF THE GEOTHERMAL WELLS AFTER THEIR LOCATIONS HAVE BEEN MORE ACCURATELY DETERMINED. NOT AN APPROVED DRAWING PRELIMINARY ENGINEERING 5% DESIGN CONTRACT SHEET No. IN-PROGRESS THIS DOCUMENT IS RELEASED FOR THE PURPOSE OF REVIEW UNDER THE AUTHORITY OF: CHAD ANTHONY ALLEN, P.E. NO ON 11/27/2012 URS CORPORATION TBPE ID #F NORTH STEMMONS FREEWAY SUITE 6000 DALLAS, TEXAS URS CORPORATION TBPE ID #F-3162 DART PROJECT SCALE DRAWN DESIGNED CHECKED IN CHARGE DATE AS SHOWN C. KESTILA C. KESTILA/J. YEOW C. ALLEN P. ZHAO 27 NOV 12 LIGHT RAIL TRANSIT SYSTEM LINE SECTION SOC-3 GEOTHERMAL WELL EXHIBIT 1 OF 2: GUIDEWAY PLAN AND PROFILE STA TO STA REV AMEND CR DATE DESCRIPTION BY ENG CHK APP IT IS NOT TO BE USED FOR CONSTRUCTION, BIDDING, OR PERMIT PURPOSES. c DART, all rights reserved, CONTRACT DWG No. REV I:\Projects\_SOUTH\GPC 5\TO 24 SOC-3 PE-EA\EXHIBITS\Geo Wells Exhibits\SOC3-CC1-0010b-

5 SOC3SX03-GEO /27/2012 3:54:17 PM " = 1-0" DWG No. 11/27/2012 I:\Projects\_SOUTH\GPC 5\TO 24 SOC-3 PE-EA\EXHIBITS\Geo Wells Exhibits\SOC3SX03-GEO " 3-6" 10" DRIP GROOVE (TYP) EDGE OF DECK CONCRETE (TYP) NB 8" LOW POINT MIN HIGH POINT BRIDGE TOP OF LOW RAIL LOW POINT 40:1 40:1 40:1 40:1 BEARING 33-2" LEVEL (TYP) CATENARY POLE, NIC SB PGL 4-3" 4-3" 8-8" 4-3" 4-3" EDGE OF DECK CABLE TROUGH HAND RAIL, TYP TEXAS DOT TX28 I-GIRDER (TYP) 4-10" APPROX. HANDRAIL 6-0" 3-0" 6-6" PEJ 6-0" min. 6-0" min. FINISHED GRADE FINISHED GRADE 1-0" MIN 6-6" min. DRILLED SHAFT 1-0" MIN 6-6" min. DRILLED SHAFT DIA DIA PIER PIER TYPICAL SECTION SCALE: "=1-0" 1 ELEVATION SCALE: "=1-0" 2 chad_allen_v8i $$MODEL$$ STA TO STA STA TO STA NOT AN APPROVED DRAWING PRELIMINARY ENGINEERING 5% DESIGN CONTRACT SHEET No. IN-PROGRESS THIS DOCUMENT IS RELEASED FOR THE PURPOSE OF REVIEW UNDER THE AUTHORITY OF: B.W. ISAAC HWANG, P.E. NO ON 11/27/2012 URS CORPORATION TBPE ID #F NORTH STEMMONS FREEWAY SUITE 6000 DALLAS, TEXAS URS CORPORATION TBPE ID #F-3162 DART PROJECT SCALE DRAWN DESIGNED CHECKED IN CHARGE DATE C. KESTILA C. KESTILA I. HWANG C. ALLEN LIGHT RAIL TRANSIT SYSTEM LINE SECTION SOC-3 GEOTHERMAL WELL EXHIBIT 2 OF 2: TEXAS DOT TX28 I-BEAM 27 NOV 12 TYPICAL SECTION 3 REV AMEND CR DATE DESCRIPTION BY ENG CHK APP IT IS NOT TO BE USED FOR CONSTRUCTION, BIDDING, OR PERMIT PURPOSES. c DART, all rights reserved, CONTRACT DWG No. REV I:\Projects\_SOUTH\GPC 5\TO 24 SOC-3 PE-EA\EXHIBITS\Geo Wells Exhibits\SOC3SX03-GEO.00

6 LEDBETTER STATION PLATFORM EXTENSION AND LEVEL BOARDING MODIFICATIONS CONCEPT The anticipated extension and level boarding improvements at Ledbetter Station have been modified since the issuance of the 5% PE drawings for the project. A study is being conducted of existing platforms on the DART Red and Blue Lines in order to provide consistency with future extension and level boarding modifications throughout the LRT system. As part of the study, the plans for Ledbetter Station have been revised to incorporate a proposed canopy in the extension area and a shortened ramp length on the north end of the existing platform. The attached concept drawing shows these improvements relative to the existing conditions at the platform. C 6 Final Local Environmental Assessment

7

8 LEDBETTER STATION ARCHITECTURAL SITE PLAN CHANGES Additional coordination has been performed with TxDOT about the Ledbetter Station site improvements currently shown in the 5% PE drawings for the project. It was determined that the previously proposed northbound left turn lane into the proposed kiss & ride area from Lancaster Road was too short and did not meet TxDOT design criteria. As a result, a new location for the kiss & ride area has been developed in coordination with TxDOT. The kiss & ride area is now envisioned to be located between Shellhorse Street and 56 th Street. Kiss & ride vehicles would enter at Shellhorse Street, drop off on a lane parallel to the bus lane, and exit south of 56 th Street. A revised architectural site plan is attached to show the new improvements. C 8 Final Local Environmental Assessment

9 GUARDRAIL, TYP NEW PLANTERS "ABOVE RAMP RAMP "ABOVE "ABOVE 22 WIDE 4.8%SLOPED SIDEWALK NEW PLANTERS STEPS TO RAISED PLATFORM 22 WIDE 4.8% SLOPED SIDEWALK 8"ABOVE GUARD RAIL KISS AND RIDE BUSES ONLY 22 WIDE 4.8% SLOPED SIDEWALK STEPS TO RAISED PLATFORM "ABOVE ONLY ONLY ONLY GUARDRAIL, TYP NEW LANDSCAPE TRAFFIC SIGNAL LANCASTER ROAD TRAFFIC SIGNAL LANCASTER ROAD TRAFFIC SIGNAL LEDBETTER SITE STUDY LEVEL BOARDING PLATFORM 1201 Elm Street Suite 5240 Dallas, TX T F TBPE REGISTRATION No. F NORTH STEMMONS FREEWAY SUITE 6000 DALLAS, TEXAS URS CORPORATION ID #3162 DART PROJECT R SCALE DRAWN DESIGNED CHECKED IN CHARGE DATE AS SHOWN G. BRINGAS V. SADR J. LIBURY D. JAMES 26 NOV 12 SOUTH OAK CLIFF 3 BLUE LINE EXTENSION PE/EA LEDBETTER STATION SITE LAYOUT STUDY REVISED c DART, all rights reserved,

10 ONCOR TRANSMISSION LINES CROSSING AND STEEL POLE ASSESSMENT Additional coordination was conducted with Oncor about the proposed crossing under the transmission lines south of Camp Wisdom Road near Runyon Springs Branch Creek. Oncor has analyzed the crossing and has provided the attached drawing showing the steel pole modifications anticipated to be required as part of this project. Oncor currently believes it will be necessary to raise three nearby steel poles in order to provide the vertical clearance required over the proposed South Oak Cliff Corridor Blue Line Extension tracks. This includes the poles immediately adjacent to and on either side of the rail crossing and one additional pole to the east. All wires between the three poles and between these poles and the two adjacent outside poles will be required to be adjusted and raised. This assessment is based on the track profile currently shown in the 5% PE drawings that were issued with the Draft EA. The possible lowering of the track profile to reduce the extent of pole modification has not yet been assessed and was not considered at the time. Final design efforts may examine lowering the profile to minimize pole and wire modifications. C 10 Final Local Environmental Assessment

11 90 STEEL POLE 95 STEEL POLE 85 STEEL POLE CONDUCTOR SHOT

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

DRAFT REPORT TXDOT SH 183 MASTER DRAINAGE STUDY HYDRAULIC ANALYSIS OF ELM FORK OF TRINITY RIVER CROSSING AT SH 183 WITHIN THE ELM FORK WATERSHED

DRAFT REPORT TXDOT SH 183 MASTER DRAINAGE STUDY HYDRAULIC ANALYSIS OF ELM FORK OF TRINITY RIVER CROSSING AT SH 183 WITHIN THE ELM FORK WATERSHED DRAFT REPORT TXDOT SH 183 MASTER DRAINAGE STUDY HYDRAULIC ANALYSIS OF ELM FORK OF TRINITY RIVER CROSSING AT SH 183 WITHIN THE ELM FORK WATERSHED FOR TEXAS DEPARTMENT OF TRANSPORTATION DALLAS DISTRICT CONTRACT

More information

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site. Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS

More information

1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON

1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON 1. INTRODUCTION This report summarizes traffic impacts of the proposed CUBES Self-Storage Mill Creek project in comparison to the traffic currently

More information

The Design-Builder shall meet local road criteria provided by the local governing agencies.

The Design-Builder shall meet local road criteria provided by the local governing agencies. 11 ROADWAYS 11.1 General The -Builder shall conduct all Work necessary to meet the requirements of roadways. Roadway classifications include mainline, acceleration lanes, deceleration lanes, auxiliary

More information

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016

I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 I-290 Phase I Study Summary of NFPA-130 Analysis of Proposed CTA Station Platform Widths May 2016 INTRODUCTION As part of the I-290 reconstruction phase I study, IDOT has coordinated with the CTA regarding

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

City of Houston Fondren Road Paving and Drainage

City of Houston Fondren Road Paving and Drainage City of Houston Fondren Road Paving and Drainage From Braeswood Boulevard to Creekbend Drive TRC Meeting March 2016 Location and Vicinity Maps City Council District K Key Map 530 Z, 530 Y Land Use Commercial

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

ALEXANDRIA, VIRGINIA PRINCE ST. SUITE 114. ADG, INC. COPYRIGHT c. PH

ALEXANDRIA, VIRGINIA PRINCE ST. SUITE 114. ADG, INC. COPYRIGHT c.   PH 1600 PRINCE ST. SUITE 114 ALEXANDRIA, VIRGINIA 22314 PH. 703.549.9556 www.archdesigngroup.com ADG, INC. COPYRIGHT c C-1 1 2 3 4 5 6 E D Tie Prop. Sidewalk, Curb & Gutter Into Existing Prop. Storm Drain

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

Appendix H: Construction Impacts H-2 Transportation

Appendix H: Construction Impacts H-2 Transportation Appendix H: Construction Impacts H-2 Transportation \ AECOM 71 W. 23 rd Street New York, NY 10010 www.aecom.com 212 366 6200 tel 212 366 6214 fax Memorandum To CC Subject Robert Conway Donald Tone Construction

More information

UBC Watermain as shown on Sheet 202 : Sub total 97,050

UBC Watermain as shown on Sheet 202 : Sub total 97,050 Preliminary Cost Estimate Brock Commons Phase 1 Watermain replacement UBC Portion of Works only Replace existing 150mm dia CI and 200mm dia AC watermain with 200mm & 250mm dia DI (ductile iron) watermain

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS. Paul Mak, PE, SE - DMJM HARRIS

PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS. Paul Mak, PE, SE - DMJM HARRIS 1 PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS Paul Mak, PE, SE - DMJM HARRIS 515 S. Flower Street 9th Floor, Los Angeles, CA 90071. Tel 213-593-8337 Fax 213-593-8622

More information

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS Paul Mak, PE, SE HDR Inc 801 S. Grand Ave. Suite 500, Los Angeles, CA 90017. Tel

More information

Confederation Line West Alignment Improvement. September 21, 2016

Confederation Line West Alignment Improvement. September 21, 2016 Confederation Line West Alignment Improvement September 21, 2016 Agenda Background Lincoln Fields Station and alignment improvement LRT alignment, west of Lincoln Fields to Queensview, including: Pedestrian

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) CFS:TEH 1 of 10 APPR:KPK:JFS:07-07-16 FHWA:APPR:07-15-16 a. Description. This

More information

Appendix F-1 Description of the Long-Term Alternatives

Appendix F-1 Description of the Long-Term Alternatives Appendix F-1 Description of the Long-Term Alternatives Memorandum Page 1 of 21 Project No. 9309 Phase 280 Date June 2, 2015 From Chris Sidlar (LEA) To Edward Presta / City of Toronto C.C. Terry Wallace

More information

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016 635 S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program Transportation and Trinity River Project Committee May 23, 2016 Project Scope Increase safety by removing the existing

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

3.15 SAFETY AND SECURITY

3.15 SAFETY AND SECURITY 3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum

More information

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee 05.28.09 09 Bridge Type - Cost Vertical Clearance Bicycle Pedestrian Path Width Bridge Type - Cost WRBAC

More information

TABLE 4-4 DAILY LRT ALTERNATIVE STATION PASSENGER VOLUMES IN 2030

TABLE 4-4 DAILY LRT ALTERNATIVE STATION PASSENGER VOLUMES IN 2030 Station Volumes and Boardings/Alightings The stations proposed for the LRT Alternative were selected due to their proximity to population and employment centers, major existing transportation facilities,

More information

DART Capital Program Update

DART Capital Program Update DART Capital Program Update CMAA North Texas April 30, 2015 David Ehrlicher Assistant Vice President, Program Delivery Overview of DART System Multimodal System: 120 + bus routes 90 miles of Light Rail

More information

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013 NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013 Control 6237-93-001 Project RMC - 623793001 Highway US0075 County DALLAS Ladies/Gentlemen: Attached please find an addendum on the above captioned

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...

More information

Table Station Elements

Table Station Elements The overall layout of the station in the Preferred Alternative (Modified Alternative 2) is described in Table 7.5-1. Table 7.5-1 Station Elements Ground Level Mezzanine Level Platform Level Existing/Upgraded

More information

Appendix C Preferred Solution

Appendix C Preferred Solution Appendix C Preferred Solution C.1 Conceptual Design Drawings C.2 Preferred Option Ideas and Inspiration C.3 Concept Renderings C.4 Cost Estimate Appendix C.1 Conceptual Design Drawings Plan View Brock

More information

APPENDIX E. Traffic Analysis Report

APPENDIX E. Traffic Analysis Report APPENDIX E Traffic Analysis Report THIS PAGE INTENTIONALLY BLANK EAGLE RIVER TRAFFIC MITIGATION PHASE I OLD GLENN HIGHWAY/EAGLE RIVER ROAD INTERSECTION IMPROVEMENTS TRAFFIC ANALYSIS Eagle River, Alaska

More information

City of Bellevue East Link Light Rail B7/C9T to NE 2nd Portal (B7 Revised) Alternative RP03 Interim Analysis Report

City of Bellevue East Link Light Rail B7/C9T to NE 2nd Portal (B7 Revised) Alternative RP03 Interim Analysis Report East Link Light Rail B7/C9T to NE nd Portal (B7 Revised) Alternative RP3 Interim Analysis Report 538/RP3 Review Draft 3 May Arup North America Ltd 43 Columbia Street Suite Seattle WA 984 United States

More information

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015 Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z145-235 2720 Hillside Drive, Dallas, TX October 27, 2015 Introduction: The Lakehill Preparatory School is located on the northeast

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

NORTHWEST HIGHWAY S-CURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY. Northwest Highway (US 14) From Seegers Road to Western Avenue

NORTHWEST HIGHWAY S-CURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY. Northwest Highway (US 14) From Seegers Road to Western Avenue NORTHWEST HIGHWAY SCURVE PEDESTRIAN/BICYCLE ACCESS FEASIBILITY STUDY Northwest Highway (US 14) From Seegers Road to Western Avenue Northwest Highway SCurve Pedestrian/Bicycle Access Feasibility Study City

More information

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS TRAFFIC IMPACT STUDY FEBRUARY 214 OA Project No. 213-542 TABLE OF CONTENTS 1. INTRODUCTION...

More information

Confederation Line West Queensway Terrace North. May 27, 2017

Confederation Line West Queensway Terrace North. May 27, 2017 Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Cost to extending KC Streetcar north approximately ½ mile

Cost to extending KC Streetcar north approximately ½ mile Technical Memorandum September 22, 2015 Attention: Jason Waldron, PE From: Lucas L. Olson, PE; Cory Imhoff, PE RE: Cost to extending KC Streetcar north approximately ½ mile HDR was asked for their opinion

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

PUBLIC INFRASTRUCTURE PROJECTS

PUBLIC INFRASTRUCTURE PROJECTS PUBLIC INFRASTRUCTURE PROJECTS FM 664 / OVILLA ROAD WIDENING & IMPROVEMENTS FM 664 / OVILLA ROAD CONNECTS US 287 WITH I-45 (SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION. 2016 FM 664 / OVILLA ROAD WIDENING

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior

More information

Proposed Program of Interrelated Projects

Proposed Program of Interrelated Projects DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

SEPULVEDA PASS CORRIDOR

SEPULVEDA PASS CORRIDOR SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000

More information

Schedule 18 (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES

Schedule 18 (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) Project Overview Briefing Packet March 2017 PROJECT OVERVIEW Environmental Impact Statement (EIS) Project divided into 3 Segments Segment 1: Beltway 8

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

Median Barriers in North Carolina

Median Barriers in North Carolina Median Barriers in North Carolina AASHTO Subcommittee on Design - 2006 June 13-16, 2006 Jay A. Bennett North Carolina DOT State Roadway Design Engineer Brian Murphy, PE Traffic Safety Engineer Safety Evaluation

More information

This letter summarizes our observations, anticipated traffic changes, and conclusions.

This letter summarizes our observations, anticipated traffic changes, and conclusions. Mr. David Jorschumb Project Manager Boulder Valley School District Re: Review of proposed school access improvements at the Foothills Elementary School in Boulder Dear Mr. Jorschumb, At your request, the

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

Sepulveda Pass Corridor Systems Planning Study Final Compendium Report. Connecting the San Fernando Valley and the Westside

Sepulveda Pass Corridor Systems Planning Study Final Compendium Report. Connecting the San Fernando Valley and the Westside Los Angeles County Metropolitan Transportation Authority November 2012 Connecting the San Fernando Valley and the Westside Interstate 405 Sepulveda Pass THIS PAGE INTENTIONALLY LEFT BLANK Sepulveda Pass

More information

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Date: August 10, 2016 Subject: Bid for Construction of NW 89 th Avenue, NW 93 rd Street and NW

More information

APPENDIX A Basis of Design and Design Criteria Memorandum

APPENDIX A Basis of Design and Design Criteria Memorandum APPENDIX A Basis of Design and Design Criteria Memorandum Job No: Y01-500 Files are stored in: Engineering / Client / Yolo/Y01500 Buckeye and Rumsey/Rumsey CR 41 over Cache Creek, CAD files stored in:

More information

Appendix G Aquilla Lake Pool Rise Recreational Resources

Appendix G Aquilla Lake Pool Rise Recreational Resources Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Central Corridor LRT Project Technical Information and Studies APPENDIX J2 ELECTROMAGNETIC FIELDS AND INTERFERENCE

Central Corridor LRT Project Technical Information and Studies APPENDIX J2 ELECTROMAGNETIC FIELDS AND INTERFERENCE Central Corridor LRT Project Appendix J Technical Information and Studies APPENDIX J2 ELECTROMAGNETIC FIELDS AND INTERFERENCE Final EIS May 2009 Electromagnetic Interference Measurement and Assessment

More information

Public Health Services San Joaquin Co.

Public Health Services San Joaquin Co. Proposed San Joaquin Co. Stockton, California REVISIONS No. Description Cover Sheet Data CS No. Description Site Plan A1 No. Description Enlarged Existing Lab Area Site / Demolition Plan A2 No. Description

More information

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented

More information

RECOMMENDED ALTERNATIVE REPORT

RECOMMENDED ALTERNATIVE REPORT DRAFT METROCENTER CORRIDOR STUDY RECOMMENDED ALTERNATIVE REPORT JULY 12, 2005 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 2.0 TIER 1 ALTERNATIVES EVALUATION... 1 3.0 TIER 2 ALTERNATIVES EVALUATION...

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) 2010 Rank: Rank: 12

IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) 2010 Rank: Rank: 12 Mobility Investment Priorities Project Houston IH 45 IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) Current Conditions From IH 10 to IH 610 south, IH 45 is a 6- to 9-lane facility with three

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Brent Spence Bridge Design Exceptions - Alternative I

Brent Spence Bridge Design Exceptions - Alternative I s - Alternative I ITERCHAGE umber Existing Reason(s) For Potential Impact(s) to Eliminate s Potential Mitigation Solutions CURVE O. 5 PI Sta. 24+98.87 Y 1 57 mph (60) 526' (570') 44 mph The line of sight

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION 03SP502(P) SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA) C&T:TEH 1 of 8 C&T:APPR:JFS:MJE:01-28-08 FHWA:APPR:02-01-08 a. Description. Provide

More information

The Re:Queen and Sparks Traffic Brief - Addendum #2

The Re:Queen and Sparks Traffic Brief - Addendum #2 June 11, 2015 Ashcroft Homes 18 Antares Drive Ottawa, ON K2E 1A9 EMAIL: mpham@ashcrofthomes.com Attention: May Pham Development Planner Dear May, Re: The Re:Queen and Sparks Traffic Brief - Addendum #2

More information

Please do not hesitate to contact me with any questions or concerns. I look forward to hearing from you.

Please do not hesitate to contact me with any questions or concerns. I look forward to hearing from you. 367.001.001 March 2, 2018 Mr. Anthony Fontaine Maine Department of Transportation P.O. Box 358 Scarborough, ME 04070 RE: Application for Driveway/Entrance Permit 1400 US Route 1, York Dear Tony, On behalf

More information

West LRT. Alignment Update and Costing Report May Calgary Transit Transportation Planning Clifton ND Lea Consultants

West LRT. Alignment Update and Costing Report May Calgary Transit Transportation Planning Clifton ND Lea Consultants West LRT Alignment Update and Costing Report 2006 May Calgary Transit Transportation Planning Clifton ND Lea Consultants West LRT Update Background The service area for West LRT is generally described

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS Emerald Isle Commercial Development Prepared by SEPI Engineering & Construction Prepared for Ark Consulting Group, PLLC March 2016 I. Executive Summary A. Site Location The Emerald

More information

Request for Design Exception (#1) S.M. Wright Phase IIB

Request for Design Exception (#1) S.M. Wright Phase IIB Request for Design Exception (#1) S.M. Wright Phase IIB County: Dallas CSJ s: 0092-01-059, 0092-14-088 Project Limits: From Pennsylvania Avenue to North of Al Lipscomb Way Date: June 28, 2016 Proposed

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Chapter 5. General Site and Building Elements

Chapter 5. General Site and Building Elements 501 General Chapter 5. General Site and Building Elements 501.1 Scope. General site and building elements required to be accessible by the scoping provisions adopted by the administrative authority shall

More information

Appendix E Description of Alternatives DRAFT ENVIRONMENTAL IMPACT STATEMENT

Appendix E Description of Alternatives DRAFT ENVIRONMENTAL IMPACT STATEMENT Appendix E Description of Alternatives DRAFT ENVIRONMENTAL IMPACT STATEMENT Chicago Red Line Extension Project Description of Alternatives October 31, 2012 Updated July 29, 2015 Prepared for: Chicago Transit

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

Craigieburn Employment Precinct North and English Street

Craigieburn Employment Precinct North and English Street Craigieburn Employment Precinct North and English Street METROPOLITAN PLANNING AUTHORITY Intersection Analyses 7 February 2014 Intersection Analyses Craigieburn Employment Precinct North and English Street

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition Countdown to the Closure Extended 3-Hour Closure of I-40 Freeway Between U.S. 0 and I-0 Planned in Mid-July for Mulholland Bridge Demolition Work Los Angeles, Calif. Plan Ahead, Avoid The Area, Or Stay

More information

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.

More information

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis Durham-Orange Light Rail Transit Project July 25, 218 ROMF Transportation Impact Analysis Version

More information

Terminal Alternatives

Terminal Alternatives Chapter 5 Terminal Alternatives Missoula International Airport Master Plan Update Prepared for Missoula County Airport Authority OCTOBER 2008 Contents Section Page 5 Terminal Alternatives...5-1 5.1 Terminal

More information

Standards for Design and Construction

Standards for Design and Construction Standards for Design and Construction Of Water, Wastewater, Fiber optics and Reclaimed Water Facilities For Pasco County Utilities Department Revised: March 2018 Board of County Commissioners: Kathryn

More information

Ottawa LRT Stage 2. McKellar Park Information Session

Ottawa LRT Stage 2. McKellar Park Information Session Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville

More information

Transportation & Traffic Engineering

Transportation & Traffic Engineering Transportation & Traffic Engineering 1) Project Description This report presents a summary of findings for a Traffic Impact Analysis (TIA) performed by A+ Engineering, Inc. for the Hill Country Family

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information