April 27, 2015 ADDENDUM #1. To the Plans and Specifications for: CENTRAL CAMPUS ELECTRICAL MODIFICATIONS PHASE II. for MIAMI UNIVERSITY.

Size: px
Start display at page:

Download "April 27, 2015 ADDENDUM #1. To the Plans and Specifications for: CENTRAL CAMPUS ELECTRICAL MODIFICATIONS PHASE II. for MIAMI UNIVERSITY."

Transcription

1 April 27, 2015 ADDENDUM #1 To the Plans and Specifications for: CENTRAL CAMPUS ELECTRICAL MODIFICATIONS PHASE II for MIAMI UNIVERSITY Oxford, Ohio To: All Plan Holders Prepared by: M Engineering 750 Brooksedge Blvd. Westerville, Ohio Phone: Fax: rcarr@mengineering.us.com This addendum supplements and amends the original plans and specifications and shall be taken into account in preparing proposals and shall become a part of the contract documents. You must indicate receipt for ALL addenda on your bid form. This addendum includes the following: 1. Written addendum - 3 pages General 1. The agenda, minutes, and sign-in sheet of the April 22, 2015 Pre-Bid Meeting are attached. 1

2 Drawings ES-01 E Revise SERVICES as follows: A. Electrical contractor shall provide temporary service from owner's designated location and provide lighting, power and wiring as required to facilitate applicable temporary needs, and furnish extension cords. Any temporary wiring, fuses, etc., shall be removed upon completion of the project. Provide ground fault protection as required by NEC and local codes on all temporary services. B. Contractor shall specifically include the cost for temporary 120/240V, 1 phase, 3 wire power to Laws Hall (via generator through temporary connection to existing secondary lighting panel) while removing existing substation and installing new lighting transformer. The load of the entire lighting panel must be accommodated by this generator (approximately 50 kva) plus any additional equipment starting loads. C. Contractor shall specifically include the cost for temporary 277/480V, 3 phase, 4 wire power to Laws Hall (via generator through temporary ATS connection) while removing, installing and relocating existing primary service switches, fuses, surge arresters, and modifying transformer taps. The load of the entire building must be accommodated by this generator (approximately 180 kva) plus any additional equipment starting loads. D. Additional temporary generators may be required for work at Kreger Hall, Roudebush Hall, or Warfield Hall. Contractor shall coordinate work schedules with Owner to minimize building outages and project cost. E. Any temporary generators utilized for this project shall be provided with a base that includes heavy-duty Visqueen polyethylene plastic sheeting and a sand barrier around the perimeter of the base to prevent any damage to surrounding walkways, vegetation, and other surfaces from diesel fuel or oil spills. Provide temporary orange hurricane-type fencing around each generator. Remove all traces of temporary protection at the end of the project. 1. Coded note 2. Change to read as follows: Remove three (3) existing 14.4 kv type SM-5 fuse links (Cat. #15RBA480E) and turn over to Owner. Existing fuse holder is type RBA400. Provide and install three (3) 30E fuse links, (Cat. #15RBA430E). Provide three (3) spare fuse links to Owner. 2

3 E Coded note 3. Change to read as follows: Provide and install three (3) distribution class surge arresters, 9 kv rated, 7.65 MCOV, to the line side of the high voltage primary switch or in the primary cable entrance compartment. 1. Coded note 2. Change to read as follows: Existing fuses are 14.4 kv type SM-5 80E (Cat.#132125R4) and no change is required. Provide three (3) spare fuses to Owner. 2. Coded note 3. Change to read as follows: Existing surge arresters are 9 kv rated, 7.65 MCOV. No change is required. E Coded note 2. Change to read as follows: Remove three (3) existing 5.5 kv, DIN-type 100E (with 2 dia. Barrels) fuses and spares (Square D- Bussmann Cat. #55GDMSJD100E) and turn over to Owner. Remove 2 dia. Fuse clip holders and replace with 3 fuse clip holders to accommodate the new fuses. 2. Coder note 3. Change to read as follows: Provide and install three (3) DIN-type fuses, 15 kv, 40E, Square D-Bussmann Cat. #173GEMSJD40E. Provide three (3) spare fuses to Owner. 3. Coded note 4. Change to read as follows: Existing surge arresters are 9 kv rated, 7.65 MCOV. No change is required. E Coded note 2. Change to read as follows: Remove three (3) existing 5.5 kv fuses and spares and turn over to Owner. Prepare fuse clip holder bracket by relocating the lower bracket down to provide 15 center to center dimension of clip holders to accommodate the new fuses. 2. Coder note 3. Change to read as follows: Provide and install three (3) DIN-type fuses, 15 kv, 20E, GE (Mersen) Cat. #9f62HDD020. Provide three (3) spare fuses to Owner. 3. Coded note 4. Change to read as follows: Existing surge arresters are 15 kv rated, 12.7 MCOV. No change is required. End of Addendum #1 3

4 PRE-BID MEETING MEETING MINUTES Miami U CCEM II DATE: April 22, 2015 MEETING NO.: 01 TIME: 2:00 PM PLACE: Cole Service Bldg Room 137 PROJECT: CCEM II ATTENDEES: COMPANY PHONE NO. FAX NO. ADDR. Ron Carr M Engineering rcarr@mengineering.us.com Terrence Ponder Miami U/Contracting pondertl@miamioh.edu Dan Patterson Miami U/PAE patterd@miamioh.edu Scott Lessing Miami U/Facilities lessinsw@miamioh.edu Jody VanZant Miami U/UEA vanzanj@miamioh.edu Omer Jacobs Rapier Electric rapierelectri@fuse.net Greg Bulach Lake Erie Electric gbulach@lakeerieelectric.com X Indicates Not Present PREPARED BY: Ron Carr Contract Start Date: May 15, 2015 Contract Completion Date: August 15, 2015 Service, Support, Solutions for Ohio Government

5 (Continued) 1. Terry Ponder provided a review of the bidding documents and general requirements for the project, including required information to be provided with the contractors bids, EDGE requirements, Bid Form, and bid submission location and time. 2. Dan Patterson gave an overview of the project requirements and reviewed the Project Checklist, including start and completion dates, restrictions on work hours and campus operational issues, coordination with Owner, changes to the parking permits and locations, laydown areas and work area protection and other safety concerns, and construction meeting requirements. 3. Ron Carr (M-Engineering) provided an overview of the scope of work for the CCEM II project, including a review of the drawings and specifications, equipment and materials being provided, submittals, and timing and coordination of work. 4. The issue of temporary generator power was discussed. In particular, Laws Hall will require temporary power on two separate occasions: 1) The replacement of the 120/240V lighting transformer, and 2) the removal of the primary high-voltage switch and changeover of the primary substation transformer. Each of these outages will require different temporary generators. The Addendum #1 will elaborate on the actual requirements for each of these outages. 5. When generators are used, they will need to provide for diesel fuel spillage and containment. 6. Alumni Week will be June 11-14, Special requirements on contractors will be in effect during thqat time period. Details will be included in the next addendum. 7. A tour of construction areas was deferred by the bidders until a later date (if necessary). Service, Support, Solutions for Ohio Government

6

7

8

CONTRA COSTA COMMUNITY COLLEGE DISTRICT

CONTRA COSTA COMMUNITY COLLEGE DISTRICT ADDENDUM #1 CONTRA COSTA COMMUNITY COLLEGE DISTRICT Date: 11/15/2018 D 4014 Warehouse Demolition Project Diablo Valley College 321 Golf Club Road, Pleasant Hill, CA 94523 NOTICE TO ALL CONTRACTORS: You

More information

ADDENDUM #2 TO BID # BID NUMBER: ISSUE DATE: Friday, January 18, 2019

ADDENDUM #2 TO BID # BID NUMBER: ISSUE DATE: Friday, January 18, 2019 Georgetown County, South Carolina 129 Screven Street, Suite 239 Post Office Drawer 421270 Georgetown, SC 29442-4200 (843) 545-3083 Fax (843) 545-3500 E-Mail purch@gtcounty.org Website http://www.gtcounty.org

More information

New Panelboard for Lot H, EV Charger Energization, Las Positas College. Scope of Work and Technical Specifications

New Panelboard for Lot H, EV Charger Energization, Las Positas College. Scope of Work and Technical Specifications CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT New Panelboard for Lot H, EV Charger Energization, Las Positas College Scope of Work and Technical Specifications Chabot-Las Positas Community College District

More information

District-Wide Prop 39, Interior LED Lighting Upgrades Pre-Conference Meeting Re-Bid No January 9 at 10:00 AM Las Positas College

District-Wide Prop 39, Interior LED Lighting Upgrades Pre-Conference Meeting Re-Bid No January 9 at 10:00 AM Las Positas College January 9 at 10:00 AM Las Positas College AGENDA I. Welcome & Introduction II. Project Overview III. Site, Constraints & Challenges IV. Bid Document Summary V. Bid Schedule II. Project Overview A. Project

More information

Customer Substation Manual

Customer Substation Manual Customer Substation Manual Table of Contents Section Page 2 of 81 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

ADDENDUM NO. THREE (3) INSTALL BACKUP GENERATOR TERMINAL BUILDING SALISBURY-OCEAN CITY: WICOMICO REGIONAL AIRPORT SALISBURY, MARYLAND

ADDENDUM NO. THREE (3) INSTALL BACKUP GENERATOR TERMINAL BUILDING SALISBURY-OCEAN CITY: WICOMICO REGIONAL AIRPORT SALISBURY, MARYLAND ADDENDUM NO. THREE (3) INSTALL BACKUP GENERATOR TERMINAL BUILDING SALISBURY, MARYLAND Delta Project No. 15065 MARCH 15, 2017 From: To: Delta Airport Consultants, Inc. 9711 Farrar Court, Suite 100 Richmond,

More information

BGE STRATEGIC CUSTOMER ENGINEERING

BGE STRATEGIC CUSTOMER ENGINEERING TABLE OF CONTENTS 1. GENERAL.. 2 2. BGE SUPPLY FEEDER.. 4 3. SWITCHGEAR ENCLOSURE AND ASSEMBLY... 5 4. SWITCHGEAR MANUFACTURERS.. 8 5. CIRCUIT BREAKER.. 8 6. SWITCHGEAR EQUIPMENT.... 10 7. MAIN AND GROUND

More information

ADDENDUM NO. 1 PAGE 1 Norfolk International Airport Replace Existing 300kW Diesel Generator Delta Project No September 22, 2017

ADDENDUM NO. 1 PAGE 1 Norfolk International Airport Replace Existing 300kW Diesel Generator Delta Project No September 22, 2017 ADDENDUM NO. 1 PAGE 1 Norfolk International Airport Replace Existing 300kW Diesel Generator Delta Project No. 14051 September 22, 2017 The Norfolk Airport Authority (the Owner ) hereby issues this Addendum

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 29 21 ENCLOSED SWITCHES AND CIRCUIT BREAKERS SPEC WRITE NOTE: Delete between // // if not applicable to project. Also delete any other item or paragraph not

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 1 DATE: 3/8/2011 RE: BID/RFP #: RFP-DOT-10/11-9031-LG BID/RFP TITLE: FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT CARYVILLE OPENING DATE: March

More information

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment. General Unit substations shall be 500 kva minimum, 1500 kva maximum unless approved otherwise by the University. For the required configuration of University substations see Standard Electrical Detail

More information

COMMERCIAL QUICK REFERENCE

COMMERCIAL QUICK REFERENCE COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

City of Mobile. Recycling Equipment Rental & Hauling BID NUMBER: 5024

City of Mobile. Recycling Equipment Rental & Hauling BID NUMBER: 5024 Recycling Equipment Rental & Hauling BID NUMBER: 5024 BID DUE DATE MARCH 31, 2017 NEW BID DUE DATE APRIL 4, 2017 ADDENDUM #1 TO BID 5024 ISSUE DATE 03/28/2017 Notice to Contractors: Sealed bids for the

More information

University of Houston Master Construction Specifications Insert Project Name

University of Houston Master Construction Specifications Insert Project Name SECTION 26 13 13 MEDIUM VOLTAGE SWITCHGEAR PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical General

More information

CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT

CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT ADDENDUM NO. 2 DATE: March 30, 2017 REVISIONS TO: Request for Bids Specification No. ES17-0020F METAL SOLID WASTE AND RECYCLING CONTAINERS NOTICE TO ALL

More information

C. System Design and Performance Requirements

C. System Design and Performance Requirements Change History Date Description of Change Pages / Sections Modified 6/15/16 Updated division section from 16361-E-E to 26 10 03, removed references to other section numbers A. Summary - mgl44 Change Approver

More information

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: Joseph Ramon Date Issued: July 29, 2014 BID NO.: 14-5053 FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR PUMP REPAIRS SUBMERSIBLE TRAINS AND CENTRIFUGAL

More information

SWITCHGEAR DIVISION PRODUCT PROFILES

SWITCHGEAR DIVISION PRODUCT PROFILES SWITCHGEAR DIVISION PRODUCT PROFILES Metal-Enclosed Load-Interrupter Switchgear Product Profiles Three-Phase, Group-Operated Load-Interrupter Switches with Fuses in Single and Multi-Bay Assemblies Manual,

More information

CITY OF MARYVILLE ELECRIC DEPARTMENT Maryville, Tennessee SPECIFICATIONS FOR 15KV POWER CIRCUIT BREAKERS. September 2018

CITY OF MARYVILLE ELECRIC DEPARTMENT Maryville, Tennessee SPECIFICATIONS FOR 15KV POWER CIRCUIT BREAKERS. September 2018 CITY OF MARYVILLE ELECRIC DEPARTMENT Maryville, Tennessee SPECIFICATIONS FOR 15KV POWER CIRCUIT BREAKERS September 2018 Myrick Clinton Cannon TN P.E. #112337 Patterson & Dewar Engineers, Inc. P. O. Box

More information

RFQ Fleet Vehicles. The City of Dawson Creek is requesting quotations for the supply and delivery of:

RFQ Fleet Vehicles. The City of Dawson Creek is requesting quotations for the supply and delivery of: RFQ 2016-23 Fleet Vehicles The City of Dawson Creek is requesting quotations for the supply and delivery of: One (1) 2016 Minimum GVW 4300kg, 4 Wheel Drive, Regular Cab, Long Box Truck. One (1) 2016 Minimum

More information

A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system.

A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system. 1. APPLICATION A. Three-phase, oil filled self-cooled, padmounted transformers are installed outdoors on pads in the EWEB distribution system. 2. REFERENCE STANDARDS A. The transformers supplied shall

More information

Electrical Switchgear Replacement Montgomery County Community College

Electrical Switchgear Replacement Montgomery County Community College Electrical Switchgear Replacement Montgomery County Community College ADDENDUM NO.1 #08-112014-SB01 November 12, 2014 The following clarifications, changes, additions or deletions for this project shall

More information

UNLV Animal Care Facility. University of Nevada Las Vegas CAM 1513/PC ADDENDUM A August 5, 2016

UNLV Animal Care Facility. University of Nevada Las Vegas CAM 1513/PC ADDENDUM A August 5, 2016 UNLV Animal Care Facility University of Nevada Las Vegas ADDENDUM A August 5, 2016 Owner: Architect: To: University of Nevada Las Vegas 4505 S. Maryland Parkway Las Vegas, Nevada 89154 Tate Snyder Kimsey

More information

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work Section 16435 - SWITCHBOARDS Introduction Part 1 - General Related Work Section 16070 Seismic Anchorage and Restraint Section 16075 Electrical Identification Section 16080 Power Distribution Acceptance

More information

III. Substation Bus Configurations & Substation Design Recommendations

III. Substation Bus Configurations & Substation Design Recommendations III. Substation Bus Configurations & Substation Design Recommendations 1.0 Introduction Pre-existing conditions, electrical arrangements or the criticality of the existing facility may limit this flexibility,

More information

Advanced Guide To Understanding Assembly Short-Circuit Current Rating WITH ENGINEERING SOLUTIONS AND OVERCURRENT PROTECTION DEVICES TO ENHANCE SCCR

Advanced Guide To Understanding Assembly Short-Circuit Current Rating WITH ENGINEERING SOLUTIONS AND OVERCURRENT PROTECTION DEVICES TO ENHANCE SCCR Advanced Guide To Understanding Assembly Short-Circuit Current Rating WITH ENGINEERING SOLUTIONS AND OVERCURRENT PROTECTION DEVICES TO ENHANCE SCCR Assembly Short-Circuit Current Ratings What Is A Short-Circuit

More information

Three (3) New Ford Fusion Sedans Bid No Notice to Bidders

Three (3) New Ford Fusion Sedans Bid No Notice to Bidders CITY OF SAN LEANDRO INVITATION FOR BIDS SUBMIT BID TO: City of San Leandro Purchasing Department 835 East 14th Street San Leandro, CA 94577 FOR FURTHER INFORMATION CONTACT: Julie Jenkins Purchasing Agent

More information

Cleaning Flooded Gear

Cleaning Flooded Gear S&C Manual Metal-Enclosed Switchgear Indoor and Outdoor Distribution (4.16 kv through 34.5 kv) Cleaning Flooded Gear Table of Contents Section Page Section Page Introduction.... 2 Safety Information Understanding

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

MATERIAL STANDARD ELECTRIC OPERATIONS ORGANIZATION. ****Supercedes BECo Standard E and ComElectric Spec ****

MATERIAL STANDARD ELECTRIC OPERATIONS ORGANIZATION. ****Supercedes BECo Standard E and ComElectric Spec **** Page 1 of 8 ****Supercedes BECo Standard E2.12-2.14 and ComElectric Spec 7-0895**** THREE-PHASE DEADFRONT PAD-MOUNTED DISTRIBUTION TRANSFORMERS, LOOP & RADIAL FEED DESIGNS 1.0 General Requirements 1.1

More information

COUNTY OF ROCKLAND Department of General Services Purchasing Division

COUNTY OF ROCKLAND Department of General Services Purchasing Division COUNTY OF ROCKLAND Department of General Services Purchasing Division Title: Contract Period: Sludge Hauling and Disposal November 8, 2016 through November 7, 2017 with 2 one-year options, Extended through

More information

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION 100 KVA AND LARGER (CONCRETE PADS ONLY) 27.05-01 CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION

More information

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications:

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications: DEVELOPMENT SERVICES PHONE: (209) 668-5520 ENGINEERING DIVISION FAX: (209) 668-5563 156 S. BROADWAY, SUITE 150 TDD: (800) 735-2929 TURLOCK, CA 95380 engineering@turlock.ca.us Date: 04/20/2018 City Project

More information

Power/Vac Switchgear Concepts And Basic Configurations

Power/Vac Switchgear Concepts And Basic Configurations Contents Section 1 Section 1 Power/Vac Switchgear Concepts And Basic Configurations Page USE OF APPLICATION GUIDE... 1-2 Power/Vac METALCLAD SWITCHGEAR... 1-2 SWITCHGEAR STANDARDS... 1-4 TWO-TIER BREAKER

More information

Q: I saw a WCB on the schedule but cannot find it in any of the drawings? A: Refer to Addendum to the Project Drawings

Q: I saw a WCB on the schedule but cannot find it in any of the drawings? A: Refer to Addendum to the Project Drawings Studio Southwest Architects, Inc. 2101 Mountain Road Albuquerque, New Mexico 87104 505.843.9639 Fax 505.843.9683 Jan. 09, 2015 ADDENDUM 2 Project: Onate Elementary School SSWA Project Number: 0822 Albuquerque,

More information

City of Hammond Purchasing Department RFP # General Maintenance and Repair Service Contract City Generators

City of Hammond Purchasing Department RFP # General Maintenance and Repair Service Contract City Generators 1 City of Hammond Purchasing Department RFP # 15-33 General Maintenance and Repair Service Contract City Generators Proposals Shall Be Received by the Purchasing Department, City of Hammond 310 East Charles

More information

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014. NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service Effective: For bills rendered on and after January 1, 2014. SECTION 1. AVAILABILITY AND APPLICABILITY 1.1 This Rate Schedule

More information

Cleaning Flooded Gear

Cleaning Flooded Gear S&C Manual PMX Modular Metal-Enclosed Switchgear Outdoor Distribution (13.8 kv and 25 kv) Cleaning Flooded Gear Table of Contents Section Page Section Page Introduction.... 2 Safety Information Understanding

More information

Requirements for Secondary Voltage Revenue Metering (750 V and less)

Requirements for Secondary Voltage Revenue Metering (750 V and less) Requirements for Secondary Voltage Revenue Metering (750 V and less) To view the latest revision of this document go to: http://www.bchydro.com/ext/metering/ January 28, 2010 Copyright 2008 by BC Hydro.

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE PAGE 261116-1 SECTION 261116 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Generator Fire Safety: Generator assemblies should be located outside the building.

Generator Fire Safety: Generator assemblies should be located outside the building. SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building

More information

10 Commercial, Industrial, Agricultural Services

10 Commercial, Industrial, Agricultural Services 10 Commercial, Industrial, Agricultural Services This section describes the Power Company requirements for commercial, industrial, and agricultural services. This section covers single phase and three

More information

GENERAL INFORMATION 1.01 PURPOSE

GENERAL INFORMATION 1.01 PURPOSE GENERAL INFORMATION 1.01 PURPOSE The purpose of this manual is to supply essential information to customers, employees, architects, engineers, contractors, and others concerned with electrical installations

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

Switchgear Skid, C1192

Switchgear Skid, C1192 CUSTOM SOLUTIONS 15kV Modular Stairs stored on floor in front of battery bay Ground grid stored on front tongue of trailer Stairs deployed for unit access Storage box for fencing materials and other parts

More information

SECTION MOTOR CONTROLLERS

SECTION MOTOR CONTROLLERS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 29 11 MOTOR CONTROLLERS SPEC WRITER NOTE: Delete between // ---- // if not applicable to project. Also, delete any other item or paragraph not applicable to

More information

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT SECTION 16400 LOW VOLTAGE DISTRIBUTION EQUIPMENT A. General 1. The University does not accept Series-Rated equipment for power distribution switchboards, distribution panels and branch circuit panelboards.

More information

Single phase pole mounted. 11kV. Electrical Engineer KEU ID#:

Single phase pole mounted. 11kV. Electrical Engineer KEU ID#: Single phase pole mounted Distribution Transformers 11kV Prepared by: ARY SAIDAHMED SHEKSAEED Electrical Engineer KEU ID#: 4252 Email: ary.sayd@hotmail.com 1 S # Contents Page # 1 Introduction 3 2 Type

More information

Revision to Mailing Standards for the Transport of Lithium Batteries. ACTION: Notice of prospective revision of standards; invitation to comment.

Revision to Mailing Standards for the Transport of Lithium Batteries. ACTION: Notice of prospective revision of standards; invitation to comment. This document is scheduled to be published in the Federal Register on 02/22/2017 and available online at https://federalregister.gov/d/2017-03397, and on FDsys.gov 7710-12 POSTAL SERVICE Revision to Mailing

More information

ADDENDUM NO. 1. This Addendum shall form part of the Contract Documents.

ADDENDUM NO. 1. This Addendum shall form part of the Contract Documents. Date: January 4, 2018 To: Bidders for Rodney Pumping Station Upgrades Tender 173747 From: Muhannad Bagajati, R.V. Anderson Associates Ltd. mbagajati@rvanderson.com Subject: Addendum No. 1 ADDENDUM NO.

More information

Florida Public Service Commission 2011 Hurricane Season Preparation Briefing

Florida Public Service Commission 2011 Hurricane Season Preparation Briefing Florida Public Service Commission 2011 Hurricane Season Preparation Briefing OUC The Reliable One May 4, 2011 Byron Knibbs Vice President, Sustainable Services (407) 434-2194 bknibbs@ouc.com 1 Florida

More information

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

9. Non-Residential Services (Commercial, Industrial, and Agricultural) Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect

More information

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019. NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service Effective: For bills rendered on and after February 1, 2019. SEDC:60/7/8/9 SECTION 1. AVAILABILITY AND APPLICABILITY 1.1

More information

ECE/TRANS/180/Add.1/Amend.1

ECE/TRANS/180/Add.1/Amend.1 29 August 2012 Global Registry Created on 18 November 2004, pursuant to Article 6 of the Agreement concerning the establishing of global technical regulations for wheeled vehicles, equipment and parts

More information

3.1 Overview of ATCO Electric s URD System Design

3.1 Overview of ATCO Electric s URD System Design Page: 3-1 3.0 URD DESIGN GUIDELINES 3.1 Overview of ATCO Electric s URD System Design The power supply to all single lot underground residential services is through front lot service. Single phase transformers

More information

CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-115

CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-115 CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-115 PADMOUNTED TRANSFORMERS 12kV AND DUAL VOLTAGE, RADIAL FEED STAINLESS STEEL NOVEMBER 2011 Specification:ELE_115_R1 Page

More information

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS THREE-PHASE PADMOUNTED TRANSFORMERS Originated 1/85 Revised 6/95 Revised 6/02 Revised 11/05 Revised 4/08 Revised 11/09 Revised 1/12 Revised 11/12 Revised

More information

UNLV Animal Care Facility. University of Nevada Las Vegas CAM 1513/PC ADDENDUM B August 19, 2016

UNLV Animal Care Facility. University of Nevada Las Vegas CAM 1513/PC ADDENDUM B August 19, 2016 UNLV Animal Care Facility University of Nevada Las Vegas ADDENDUM B August 19, 2016 Owner: Architect: To: University of Nevada Las Vegas 4505 S. Maryland Parkway Las Vegas, Nevada 89154 Tate Snyder Kimsey

More information

CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-112 SUBSTATION CLASS VACUUM CIRCUIT BREAKERS OCTOBER 2008

CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-112 SUBSTATION CLASS VACUUM CIRCUIT BREAKERS OCTOBER 2008 CITY OF LOMPOC UTILITIES DEPARTMENT ELECTRICAL DIVISION SPECIFICATION NO. ELE-112 SUBSTATION CLASS VACUUM CIRCUIT BREAKERS OCTOBER 2008 SPECIFICATION NO: ELE_112_R1.doc Page 1 of 3 Rev. 10/28/2008 SPECIFICATION

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

Shippensburg University

Shippensburg University Shippensburg University 1871 Old Main Drive Shippensburg, PA 17257 SUPPLEMENT 1 Electrical Coordination Study Professional: Entech Engineering, Inc. 4 South Fourth Street P.O. Box 32 Reading, PA 19603

More information

Chapter 6 Generator-Voltage System

Chapter 6 Generator-Voltage System Chapter 6 Generator-Voltage System 6-1. General The generator-voltage system described in this chapter includes the leads and associated equipment between the generator terminals and the low-voltage terminals

More information

Customer Requirements Downtown Secondary Network Service

Customer Requirements Downtown Secondary Network Service Application This standard describes the limitations and requirements for receiving service from the Tacoma Power secondary network system within the City of Tacoma downtown core area. In This Standard

More information

Outdoor Power Transmission & Distribution

Outdoor Power Transmission & Distribution Description: The purpose of the section is to highlight the current applicable UMCP Design Standards and requirements for Outdoor Power Transmission and Distribution, including but not limited to the following:

More information

Appendix Item Addendum

Appendix Item Addendum Addendum to ESAH Version 3 Supply Application Appendix Item Addendum 1 Electrical System Item 1.4.5 Short Circuit Ratings Addendum for type of short circuit rating for system voltage of 275kV. 2 Types

More information

This tender addendum and clarification forms part of the Request for Proposal and Contract documents, and modifies them as follows:

This tender addendum and clarification forms part of the Request for Proposal and Contract documents, and modifies them as follows: This tender addendum and clarification forms part of the Request for Proposal and Contract documents, and modifies them as follows: I. ADDENDUM Isinya Mandatory Spares list Description Quantity A AIS 400kV

More information

REQUEST FOR PROPOSALS EAGLE COUNTY RECYCLE DROP-OFF COLLECTION CONTAINER HAULING

REQUEST FOR PROPOSALS EAGLE COUNTY RECYCLE DROP-OFF COLLECTION CONTAINER HAULING REQUEST FOR PROPOSALS EAGLE COUNTY RECYCLE DROP-OFF COLLECTION CONTAINER HAULING INTRODUCTION August 27, 2010 Eagle County is soliciting proposals from qualified service providers to haul collected recyclable

More information

2018 Golf Cart Lease Sunset Valley Golf Club

2018 Golf Cart Lease Sunset Valley Golf Club Invitation for Bid Sunset Valley Golf Club February 5, 2018 Sunset Valley Golf Club Bid Opening: Friday, February 16, 2018 at 1:00 PM at West Ridge Center, 636 Ridge Road, Highland Park, IL 60035 Ryan

More information

Street Address. City-Village-Township

Street Address. City-Village-Township Schedule Designation D11 Primary Supply Agreement D11 963-1816 77/15 THIS AGREEMENT, dated, 20, by and between (Name) a, (Legal Entity and State of Organization) herein called the "Customer", and DTE Electric

More information

DELETE first sentence of first paragraph that reads: REPLACE with the following:

DELETE first sentence of first paragraph that reads: REPLACE with the following: To Bidder of Record: SAN ANTONIO WATER SYSTEM Addendum 2 To Construction Documents For 2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB NO. 12-5001 SAWS SEWER JOB NO. 12-5501 Solicitation

More information

Metering and Service Installation:

Metering and Service Installation: Table of Contents 1. Metering Installation Requirements, General... 1 2. Type of Service... 2 3. Definitions... 2 4. Who Provides Metering Equipment?... 2 5. Establishment of Service... 2 6. Meter Access...

More information

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet DRAWING NUMBER INTRODUCTORY INFORMATION Important Notices Underground Plant Protection Information Code Clearances Commercial/Industrial Information Sheet Work Management Customer Projects Engineering

More information

February 8, Potential Vendors:

February 8, Potential Vendors: February 8, 2018 Potential Vendors: Please find following Addendum A: 2018 GOLF CART LEASE SUNSET VALLEY GOLF CLUB. Questions regarding this addendum should be directed to Ryan Ochs at 847-579-4158 or

More information

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION! PREFACE This publication has been prepared as a guide for Architectural and Engineering (A&E) firms in the preparation of documents for the design and construction of new structures and the remodeling

More information

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5 PAGE 1 OF 5 USE: Requirements for entrance equipment. PREVIOUS REVISION 07-01-98 ORIGINATED 03-94 PREVIOUS NUMBER ER 100 (12-01-81) LATEST REVISION: Updated meter socket labeling specification and instrument

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS San Antonio Water System Standard Specifications for Construction ITEM NO. 834 FIRE HYDRANTS 834.1 DESCRIPTION: This item shall consist of fire hydrant installations using joint restraints in accordance

More information

Addendum No. 1 BID NO. S Bidders responding to Bid #S Traffic Signal Installation.

Addendum No. 1 BID NO. S Bidders responding to Bid #S Traffic Signal Installation. Purchasing Division 2101 O Neil Ave., Room 309 Cheyenne, WY 82001 307/637-6345 Addendum No. 1 BID NO. S-7-18 To: From: Bidders responding to Bid #S-7-18 2018 Traffic Signal Installation. Sara Vasquez,

More information

TRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 03/05/09 TSEWG TP-11: UFC N BEST PRACTICES

TRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 03/05/09 TSEWG TP-11: UFC N BEST PRACTICES TSEWG TP-11: UFC 3-500-10N BEST PRACTICES UFC 3-500-10N was developed by NAVFAC and was used as the starting point for the tri-services development of UFC 3-500-10, Design: Electrical Engineering. UFC

More information

South Dock Replacement Prescott Park. This addendum forms part of the original document marked: Bid#44-14 South Dock Replacement Prescott Park.

South Dock Replacement Prescott Park. This addendum forms part of the original document marked: Bid#44-14 South Dock Replacement Prescott Park. City of Portsmouth Public Works Department June 27, 2014 Addendum #3 Bid #44-14 South Dock Replacement Prescott Park This addendum forms part of the original document marked: Bid#44-14 South Dock Replacement

More information

REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF SOLAR ENERGY

REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF SOLAR ENERGY SAUT/17-18/002 REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF SOLAR ENERGY ISSUED BY: Southern Arkansas University Tech Purchasing Office PO Box 3499 Camden, AR 71711 PROPOSAL OPENING DATE & TIME: February

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

Specification Number: Product Name: GROUP MOUNTED MAIN FUSIBLE SWITCH, GROUP MOUNTED BRANCH FUSIBLE SWITCH (LONG) SECTION

Specification Number: Product Name: GROUP MOUNTED MAIN FUSIBLE SWITCH, GROUP MOUNTED BRANCH FUSIBLE SWITCH (LONG) SECTION Specification Number: 26 24 13.20 Product Name: GROUP MOUNTED MAIN FUSIBLE SWITCH, GROUP MOUNTED BRANCH FUSIBLE SWITCH (LONG) SECTION 26 24 13.20 SWITCHBOARDS (Long) Main Disconnect Group Mounted Fusible

More information

Medium Voltage Metal-Enclosed Switches

Medium Voltage Metal-Enclosed Switches Medium Voltage Metal-Enclosed Switches Outdoor Medium Voltage Switch.1 Medium Voltage Switch MVS Product Description............................................. 2 Application Description..........................................

More information

BID PROPOSAL. Item Description Unit Quantity Unit Price Total Price No. (Unit Price to be written in Words) (Figures) (Figures)

BID PROPOSAL. Item Description Unit Quantity Unit Price Total Price No. (Unit Price to be written in Words) (Figures) (Figures) BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions and Invitations to Bidders, the undersigned proposes

More information

INVITATION TO BID SPECIFICATIONS & INSTRUCTIONS FOR:

INVITATION TO BID SPECIFICATIONS & INSTRUCTIONS FOR: INVITATION TO BID SPECIFICATIONS & INSTRUCTIONS FOR: HOMEWOOD-FLOSSMOOR PARK DISTRICT Golf Car Lease/Purchase Coyote Run Golf Course Flossmoor, IL 60422 BID OPENING ON: Thursday, October 25, 2018 TIME:

More information

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Robert P. Hansen, P.E., PhD GE Specification Engineer Introduction Switchboards are a widely used type of equipment

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

35-kV Safefront 200 Amp SuperWell Primary Metering Station Pad-Mounted Outdoor

35-kV Safefront 200 Amp SuperWell Primary Metering Station Pad-Mounted Outdoor 35-kV Safefront 2 Amp SuperWell 5-33 Page 1 216 EPM-PMS-35-311P-R2/ESW Three Phase Two Ways per Phase 2 Amp 35 kv Class Eaton's CPS LRTPs NEMA Standard Outdoor Instrument Transformer Provisions 21.1/36.6

More information

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia 30071 678.982.8928 brad.bozich@efacec.com SCOPE This document is intended to help define the main parameters

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Current Ratings. Standards & codes note 1. Introduction. interest. By Steve Hansen Sr. Field Engineer

Current Ratings. Standards & codes note 1. Introduction. interest. By Steve Hansen Sr. Field Engineer Achieving Higher Short Circuit Current Ratings for Industrial Control Panels Standards & codes note 1 By Steve Hansen Sr. Field Engineer Introduction Articles 9.1 and. in the National Electrical Code require

More information

Three-Phase Pole Mounted Recloser

Three-Phase Pole Mounted Recloser Three-Phase Pole Mounted Recloser Page 1 of 8 Table of Contents 1 GENERAL... 3 2 CONSTRUCTION... 3-5 3 BUSHINGS... 5 4 LINE CONNECTOR... 5 5 TOOLS....5 6 NAMEPLATES..6 7 PAINT... 6 8 EXTERNAL HARDWARE

More information

SYSTEM PROTECTION AND CONTROL WORKING GROUP

SYSTEM PROTECTION AND CONTROL WORKING GROUP Southwest Power Pool SYSTEM PROTECTION AND CONTROL WORKING GROUP and SPP UFLS Standard Drafting Team Meeting MINUTES November 12, 2010 9:00 a.m. 11:00 a.m. Net conference Item 1 Administrative: Shawn Jacobs,

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee May 27, 2014 City Council June 2, 2014 Agenda Item: Consideration of Bids for City Project Nos. 7152 Dist. No. 501; 7153 Dist. No. 317 and 7154

More information

Frequency of Maintenance Tests These specifications have been developed by the InterNational Electrical Testing Association for use by electrical power distribution system engineers. Copyright 2001 InterNational

More information

RESIDENT PARKING IN University Village

RESIDENT PARKING IN University Village RESIDENT PARKING IN University Village 2010-2011 PARKING PERMIT OPTIONS AND REGULATIONS OF UNIVERSITY VILLAGE at THE UNIVERSITY OF MIAMI Parking & Transportation Services Visit us on the web at: http://www.miami.edu/parking

More information