Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85

Size: px
Start display at page:

Download "Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85"

Transcription

1 Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85, Inc.

2 Introduction The following impact study results are from the Progress Energy Inc., Carolinas (PEC) internal power-flow models that reflect specific conditions of the PEC system at points in time consistent with the generator interconnection request being evaluated. The cases include the most recent information for load, generation additions, transmission additions, interchange, and other pertinent data necessary for analysis. Future years may include transmission, generation, and interchange modifications that are not budgeted for and for which no firm commitments have been made. Further, PEC retains the right to make modifications to power-flow cases as needed if additional information is available or if specific scenarios necessitate changes. For the systems surrounding PEC, data is based on the NERC MMWG model. The suitability of the model for use by others is the sole responsibility of the user. The Customer and PEC entered into this agreement on Jan. 5, Higher queued generator interconnection requests #80, #81, #82, and #84 as well as the associated Network Upgrades were included in this analysis. Facilities to address transmission issues associated with higher queued request #84 were needed as a starting point for this study. Therefore, this generator interconnection impact study was commenced following the completion of the generator interconnection facility study for request #84, also located at Richmond County. Study work started on or about April 1, Purpose The purpose of this study is to assess the impact of a generator interconnection request on the reliability of the PEC transmission system with respect to power-flow, stability, and short circuit issues. The PEC internal system analysis consists of an evaluation of the internal PEC transmission system utilizing documented transmission planning criteria. The request is described in Table 1 below. The Customer s application proposed interconnection at 230 kv to PEC s Richmond 500 kv substation. A conference call between PEC and the Customer took place on April 15, In this meeting PEC shared preliminary results of studies to date. In this meeting it was agreed to proceed with studies assuming interconnection at the 500 kv level at the Richmond 500 kv Substation. Subsequent investigation revealed insufficient room in the Richmond 500 kv switchyard to accommodate the new units. A revised Point-of- Interconnection was therefore chosen to be on the Richmond-Newport 500 kv line approximately one-half mile from the Richmond 500 kv Substation. PEC Generator Interconnection Queue No. MW In-Service Date Table 1: Request County Queue # /01/08 Richmond County, North Carolina Facility PEC Richmond 500kV Substation - 2 -

3 Results Power-flow Analysis Facilities that may require upgrade within the first three to five years following the in-service date are identified. Based on projected load growth on the PEC transmission system, facilities of concern are those with post-contingency loadings of 95% or greater of their thermal rating and low voltage of 0.92 pu and below for the requested in-service year. The identification of these facilities is crucial due to the construction lead times necessary for certain system upgrades. This process will ensure that appropriate focus is given to these problem areas to investigate whether construction of upgrade projects is achievable to accommodate the requested interconnection service. Based on 2008 study results, Table 2 shows thermal facility loadings that were found: Table 2: Power-flow Thermal Results Transmission Facility Loading Contingency Delco Whiteville 115 kv line 150% Brunswick Unit #2 Whiteville 230 kv line Weatherspoon Plant Raeford 115 kv line 129% Weatherspoon Plant 230/115 kv transformer Fayetteville 230/115 kv #1 (#2) 126% Fayetteville 230/115 kv #2 (#1) transformer transformer Fayetteville Fayetteville East 230 kv line 120% Fayetteville Ft. Bragg Woodruff St. 230 kv line Richmond 500/230 kv #1 transformer 119% Cumberland Richmond 500 kv line Weatherspoon Plant Marion 115 kv line 119% Weatherspoon Plant 230/115 kv transformer Weatherspoon Plant 230/115 kv 118% Weatherspoon Plant Raeford 115 kv line transformer Cape Fear Erwin 115 kv line 118% Harris Plant Erwin 230 kv line Clinton Vander 115 kv line 115% Clinton Erwin 230 kv line Rockingham Anson 230 kv Black line 115% Richmond New Gen Site 500 kv line Rockingham Anson 230 kv White line 115% Richmond New Gen Site 500 kv line Sutton Plant Castle Hayne 230 kv line 114% BNP1 Castle Hayne and BNP2- Wilmington Corning 230 kv lines (common tower) Richmond 500/230 kv #2 transformer 113% Cumberland Richmond 500 kv line Greenville DVP Everetts 230 kv line 113% Greenville Wilson 230 kv line Blewett Plant Tillery Plant 115 kv line 112% Biscoe Rockingham 230 kv line Lee Sub Milburnie 230 kv line 110% Lee Sub Selma 230 kv line Rockingham West End 230 kv line 110% Cumberland Richmond 500 kv line Asheboro East Biscoe 115 kv line 109% Asheboro Biscoe 230 kv line Raeford Richmond 230 kv line 109% Cumberland Richmond 500 kv line Fayetteville Ft. Bragg Woodruff St % Fayetteville Fayetteville East 230 kv line kv line Cumberland 500/230 kv #1(#2) transformer 107% Cumberland 500/230 kv #2(#1) transformer - 3 -

4 Transmission Facility Loading Contingency Greenville Wilson 230 kv line 105% Greenville DVP Everetts 230 kv line Lee Plant Selma 115 kv line 105% Lee Sub Selma 230 kv line Wake 500/230 kv #1(#2) transformer 105% Wake 500/230 kv #2(#1) transformer Selma Wake 230 kv line 105% Erwin Milburnie and Lee Sub Milburnie 230 kv lines (common tower) Cary Regency Park Durham 230 kv line 105% Method Duke E. Durham and Durham Method 230 kv lines (common tower) Fayetteville Rockingham 230 kv line 104% Cumberland Richmond 500 kv line Blewett Plant Rockingham 115 kv line 104% Biscoe Rockingham 230 kv line Milburnie Selma 115 kv line 103% Selma 230/115 kv transformer Weatherspoon Plant Fayetteville 115 kv 103% Weatherspoon Plant 230/115 kv transformer line Sutton Plant Delco 115 kv line 103% BNP1 Castle Hayne and BNP2- Wilmington Corning 230 kv lines (common tower) Method Duke E. Durham 230 kv line 102% Durham Duke E. Durham 230 kv line Fayetteville Vander South 115 kv line 102% Fayetteville Vander North 115 kv line Laurinburg LOF Black (White) 115 kv 102% Laurinburg LOF White (Black) 115 kv line line Black Creek Wilson West 115 kv line 102% Black Creek Wilson East 115 kv line Cumberland Delco 230 kv line 102% Cumberland Fayetteville N. and S. 230kV lines (common tower) Rockingham West End 230 kv line 100% Cumberland Richmond 500 kv line Falls 230/115 kv transformer 100% Falls Franklinton and Falls Henderson 115 kv lines (common tower) Method Milburnie S. 115 kv line 100% Method Milburnie 230 kv and N. 115 kv line (common tower) Lee Sub Selma 230 kv line 99% Lee Sub Milburnie 230 kv line Laurinburg Richmond 230 kv line 99% Cumberland Richmond 500 kv line Laurinburg 230/115 kv #1 (#2) 99% Laurinburg 230/115 kv #2 (#1) transformer transformer Tillery Plant Biscoe 115 kv line 98% Biscoe Rockingham 230 kv line Weatherspoon Plant Laurinburg 230 kv 98% Cumberland Richmond 500 kv line line Selma 230/115 kv transformer 98% Lee Sub Selma 230 kv line Robinson Plant Florence 115 kv line 97% Cumberland Richmond 500 kv line Durham Falls 230 kv line 96% Roxboro Plant Falls and Roxboro Person 230 kv lines (common tower) Sutton Plant Delco 230 kv line 95% BNP1 Castle Hayne and BNP2- Wilmington Corning 230 kv lines (common tower) Florence Kingstree 230 kv line 95% Richmond Duke Newport 500 kv line - 4 -

5 Based on 2008 study results, Table 3 shows facility low voltages that were found: Number of Low Voltage Buses Lowest Voltage (pu) Table 3: Power-flow Voltage Results Bus Number and Name of Lowest Voltage Contingency Description #10453, PA-WASH 230 Cumberland Delco 230 kv line #10047, WSP 1-3F 115 Cumberland Richmond 500 kv line #10259, E15-Hall 115 Harris Plant Erwin 230 kv line #10451, PA-Grnvl 230 Greenville DVP Everetts 230 kv line #10525, M-LEJN#1 230 Castle Hayne Jacksonville 230 kv line #10525, M-LEJN#1 230 Jacksonville Havelock 230 kv line #10453, PA-Wash 230 BNP1 Jacksonville 230 kv line #10457, Chocwnty 230 BNP2 Whiteville 230 kv line #10451, PA-Grnvl 230 Lee Milburnie 230 kv line #10451, PA-Grnvl 230 Wake Wilson 230 kv line #10451, PA-Grnvl 230 Lee Selma 230 kv line #10259, E15-Hall 115 Clinton Erwin 230 kv line #10229, Farmvill 230 Greenville Wilson 230 kv line #10176, PA-SMFLD 115 Selma Wake 230 kv line #10451, PA-Grnvl 230 Wake DVP Carson 500 kv line #10453, PA-WASH 230 Jacksonville Wallace 230 kv line #10451, PA-Grnvl 230 Mayo Plant Durham 500 kv line #10451, PA-Grnvl 230 BNP1 Weatherspoon 230 kv line #10451, PA-Grnvl 230 Harris Plant Cary Regency Park 230 kv line #10256, CL Ferel 115 Sutton Plant Wallace 230 kv line #10260, Roseboro 115 Harris Plant Ft. Bragg Woodruff St. 230 kv line #10455, I-PCS 230 Aurora Greenville 230 kv line #10451, PA-Grnvl 230 Lee Wommack N. 230 kv line #10451, PA-Grnvl 230 Greenville Greenville West 230 kv line #10441, E10-PEMB 115 Laurinburg Richmond 230 kv line #10451, PA-Grnvl 230 Lee Wommack S. 230 kv line #10451, PA-Grnvl 230 Person Rocky Mt. 230 kv line #10505, ROSE HIL 230 Clinton Wallace 230 kv line #10418, E10-ROCK 115 Raeford Richmond 230 kv line - 5 -

6 Number of Low Voltage Buses Lowest Voltage (pu) Bus Number and Name of Lowest Voltage Contingency Description #10593, WHTV IND 115 Marion Whiteville 115 kv line #10440,E10-WLUM 115 Weatherspoon Plant 230/115 kv transformer #10451, PA-Grnvl 230 Rocky Mt. DVP Nashville 230 kv line #10481,PA-AYDEN 115 Goldsboro Kinston DuPont 115 kv line #10455, I-PCS 230 New Bern Wommack N. 230 kv line #10451, PA-Grnvl 230 Cumberland Whiteville 230 kv line #10265, E15-STED 115 Clinton Vander 115 kv line #10403, HM Churc 115 Weatherspoon Plant Fayetteville 230 kv line #10488, E2-CH PT 115 Havelock Morehead Mildwood N. 115 kv line #10451, PA-Grnvl 230 Richmond Duke Newport 500 kv line #10430, RED SPRG 115 Weatherspoon Plant Raeford 115 kv line #10476, ICG-WYHS 115 Kinston DuPont New Bern 115 kv line #10482, E13-HUGO 115 Kinston DuPont 230/115 kv transformer #10440, E10-WLUM 115 Weatherspoon Plant Laurinburg 230 kv line #10451, PA-Grnvl 230 Jacksonville New Bern 230 kv line #10256, CL Ferel 115 Clinton 230/115 kv transformer #10176, PA-SMFLD 115 Milburnie Selma 230 kv line #10544, HOLLY RG 115 Castle Hayne Jacksonville 115 kv line #10107, E18-WEMC69.0 Falls Franklinton 115 kv line #10242, PA-W Rocky Mt. Wilson E. 115 kv line #10460, E3-MANCH 115 Rockingham West End 230 kv line #10418, E10-ROCK 115 Cumberland Wake 500 kv line #10451, PA-Grnvl 230 Durham Wake 500 kv line #10404, E3-MANCH 115 Weatherspoon Plant Fayetteville 115 kv line #10176, PA-SMFLD 115 Selma 230/115 kv transformer #10495, N RIVER 115 Havelock Morehead Mildwood S. 115 kv line #10658, I-GE FL 115 Florence Marion 115 kv line #10084, I-NOVO 115 Franklinton Spring Hope 115 kv line #10572, ELIZABTN 115 Weatherspoon Plant Delco 115 kv line #10440, E10-WLUM 115 Weatherspoon Plant Laurinburg 115 kv line #10451, PA-Grnvl 230 Rocky Mt. Wilson 230 kv line #10484, Havelock 230 Havelock Jacksonville 230 kv line #10460, E3-MANCH 115 Fayetteville Ft. Bragg Woodruff St. 230 kv line - 6 -

7 Number of Low Voltage Buses Lowest Voltage (pu) Bus Number and Name of Lowest Voltage Contingency Description #10262, E17-MT O 115 Mt. Olive 230/115 kv transformer #10451, PA-Grnvl 230 New Bern Wommack S. 230 kv line #10451, PA-Grnvl 230 Havelock Morehead Mildwood 230 kv line #10453, PA-WASH 230 Cumberland Whiteville 230 kv line #10449, DILLON 115 Weatherspoon Plant Marion 115 kv line #10145, NEUSE 115 Chestnut Hills Falls 115 kv line #10418, E10-ROCK 115 Laurinburg Raeford 230 kv line #10418, E10-ROCK 115 Raeford 230/115 kv #1 transformer #10266,E17-Geno 115 Lee Plant Clinton 230 kv line #10281, Belfast 115 Lee Plant Goldsboro N. 115 kv line #10418, E10-ROCK 115 Fayetteville Rockingham 230 kv line #10451, PA-Grnvl 230 Harris Plant Wake 230 kv line #10451, PA-Grnvl 230 Erwin Selma 230 kv line #10451, PA-Grnvl 230 BNP2 Wallace 230 kv line #10451, PA-Grnvl 230 Milburnie Person 230 kv line #10451, PA-Grnvl 230 Delco Whiteville 115 kv line #10451, PA-Grnvl 230 Sutton Plant Castle Hayne 230 kv line #10451, PA-Grnvl 230 Roxboro Plant Falls 230 kv line #10451, PA-Grnvl 230 Durham Duke E. Durham 230 kv line #10451, PA-Grnvl 230 Kinston DuPont Wommack 230 kv line Based on 2008 study results, Table 4 shows overloads of 230 kv bus equipment at the Richmond 500 kv Substation: Table 4: Power-flow Bus Thermal Results Richmond 230 kv Bus Section Loading Contingency Rockingham#1-Raeford 230 kv Bay 131% Rockingham #1 230 kv Bus CB Richmond Co. White-#1 500/230 kv Bank Bay 122% Richmond Co.230 kv Bus CB OR #1 500/230 kv Bank Bus CB Stability Analysis A detailed stability analysis to determine the impacts that Queue #85 generation has on system stability would normally be performed as part of this Generator Interconnection Impact Study. Significant influences to the results of a stability analysis are the location of the proposed generating units, interconnect ion to the transmission system, and the configuration of the - 7 -

8 surrounding transmission. As evidenced by the Power-flow Analysis section of this report, a large number of facility thermal loading and low voltage issues were identified due to the addition of the Customer s generation. Performing a detailed stability analysis prior to resolution of these power-flow issues would be of little or no value due to the uncertainty of the system configuration necessary to remedy the power-flow issues. Nevertheless, based on prior analysis, stability issues are probable. Stability issues will likely be aggravated without inclusion of the upgrades needed to address the identified thermal and voltage issues. Based on the above, a detailed stability analysis will be included in Generator Interconnection Facilities Study. Based on PEC s current generator interconnection queue status, the stability analysis would include higher queued generator interconnection requests #80, #81, #82 and #84. Any changes to the queue with respect to these other requests will be incorporated as necessary. Additionally, it can be noted that prolonged oscillations following system disturbances in the PEC transmission system can occur under certain system conditions due to the minimal natural damping available. It is likely that the installation of power system stabilizers on the proposed generating units will be needed to mitigate the adverse impact that adding the proposed generation will have in contributing to these prolonged oscillations. Short Circuit Analysis A short circuit analysis was performed to examine the fault current levels at the 115 kv, 230 kv and 500 kv levels one and two substations away from the proposed Richmond County Queue #85 generation. The proposed generation was assumed to be interconnected to the Richmond-Newport 500 kv line near PEC s Richmond 500 kv Substation via an individual generator step-up transformer for each of the six generating units. The transmission system configuration modeled also included proposed generation additions, with related system changes, for higher queued requests 80, 81, 82 and 84. Results of this analysis indicate that the interrupting capability of three 230 kv, 54 ka circuit breakers at Richmond 500/230 kv Substation will be exceeded with the addition of Queue #85 Richmond County generation. Additionally, eleven 230 kv, 50 ka circuit breakers at the existing PEC Richmond County Plant would be near their interrupting capability limit and may also need to be replaced. The results of this short circuit analysis are based on Customer provided generation equipment data, location, and the use of typical data for the generator step-up transformers. If the generation equipment data or location changes, the results of this analysis may need to be reevaluated. Additionally, it is anticipated that these short circuit results will need to be reevaluated to address system configuration changes needed to resolve the large number of power-flow issues identified in the Power-flow Analysis section of this report

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS April 2009 Prepared by VACAR Stability Working Group: Kirit Doshi Anthony Williams John O Connor Joe Hood Art Brown Dominion Virginia

More information

VACAR 2015 SUMMER PEAK RELIABILITY STUDY

VACAR 2015 SUMMER PEAK RELIABILITY STUDY VACAR 2015 SUMMER PEAK RELIABILITY STUDY August 2010 STUDY PARTICIPANTS Prepared by: VACAR Power Flow Working Group (PFWG) Representative Joey West Brian D. Moss Kale L. Ford, Chair Vanessa M. Abercrombie

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Southeast Pond Stocking, LLC Spring Fish Day Schedule

Southeast Pond Stocking, LLC Spring Fish Day Schedule Southeast Pond Stocking, LLC. 2019 Spring Fish Day Schedule Thursday February 28 th 9:00 am 10:30 am Big Blue Store Kinston 701 McLewean St. 11:00 am 12:30 pm Yoder s Farm & Garden Grifton 4100 Hwy. 118

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Southeast Pond Stocking, LLC Spring Fish Day Schedule Round 2

Southeast Pond Stocking, LLC Spring Fish Day Schedule Round 2 Southeast Pond Stocking, LLC. 2016 Spring Fish Day Schedule Round 2 Friday May 13 th 8:00 am 9:00 am Tractor Supply Wadesboro 1051 E. Caswell St. 10:00 am 11:30 am Tractor Supply Co. Midland 11855 US Hwy

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Exemptions currently in force

Exemptions currently in force exemptions by Western Power s currently in force Neerabup Units G11 & G12 3.3.3.1 (a) 16 Jan 2008 Ongoing Modified performance criteria: 0.8 Lagging 101.3 MVAr 0.9 Leading 68.5 MVAr Financial contribution

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2 Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia

More information

SERTP Southeastern Regional Transmission Planning

SERTP Southeastern Regional Transmission Planning REGIONAL TRANSMISSION PLAN & INPUT ASSUMPTIONS OVERVIEW SERTP Southeastern Regional Transmission Planning November 29, 2018 Regional Transmission Plan & Input Assumptions Overview REGIONAL TRANSMISSION

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Quick Facts About NCEMPA Debt & Wholesale Electric Rates in Eastern North Carolina

Quick Facts About NCEMPA Debt & Wholesale Electric Rates in Eastern North Carolina Quick Facts About NCEMPA Debt & Wholesale Electric Rates in Eastern North Carolina The History Behind NCEMPA s Debt: Construction of Shearon Harris Nuclear Plant Cost Was Significantly Higher Than Original

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017

Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017 Market Congestion Planning Study (South)- Robustness Analysis Economic Planning Users Group Meeting August 11 th, 2017 Key Takeaways The benefit calculations were updated due to a flowgate rating correction

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

GODURHAM PROGRESS REPORT

GODURHAM PROGRESS REPORT GODURHAM PROGRESS REPORT OVERVIEW OPERATIONS & PERFORMANCE With the service enhancements, total revenue hours increased In 2016, GoDurham connected 5.9 million passengers to jobs, education and health

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009) COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI-2007-12, RESTUDY 1 (August 6, 2009) On June 15, 2009 Xcel Energy released a restudy of a System Impact

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan 10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

3 Reliability Issues and Solutions

3 Reliability Issues and Solutions 3 Reliability Issues and Solutions 3.1 Reliability issues identified Figure 3 1 summarizes the transmission reliability issues identified as part of the 2009 planning process. These areas represent locations

More information

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909 Amy C. Monopoli Counsel Regulatory & Legislative Phone: 774-452-4227 amonopoli@itctransco.com May 11, 2017 Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway

More information