Annual Report STATE LOAD DESPATCH CENTRE GUJARAT ENERGY TRANSMISSION CORPORATION LTD

Size: px
Start display at page:

Download "Annual Report STATE LOAD DESPATCH CENTRE GUJARAT ENERGY TRANSMISSION CORPORATION LTD"

Transcription

1 Annual Report STATE LOAD DESPATCH CENTRE GUJARAT ENERGY TRANSMISSION CORPORATION LTD

2

3

4

5 FROM THE CHIEF ENGINEER S DESK I am pleased to present the Annual Report of SLDC, Gujarat for the financial year SLDC s role in electricity sector is both vital and exceptional. SLDC is an essential link in the safe, cost-effective delivery of electric power across the State. Customer service, effective communication and operational excellence are the principles that guide us as we explore better ways to keep power moving safely, efficiently and reliably. Year was undeniably a period of major challenges for the grid operation. Despite all odds, SLDC has put up its best efforts to minimize deviation by prompting and sensitizing load and RE generation forecasting activity. The gross generation capacity addition was 8.56% (2133 MW) during the year The energy supplied had increased by 1.11% as compared to last year. The energy received from renewable sources (Wind and Solar only) is 9458 MUs (9.06% of total energy). In the month of April May 16, there were many bigger sized units under forced shutdown. Also, the variable cost of around 1000 MW gas based generators had increased drastically due to non-availability of gas under E-bid RLNG. At that time SLDC had performed an active role by deferring many unit outages and expediting revival of units which were under forced / planed outages to maintain adequacy of power supply looking to onset of summer. On 13th July 2016 at 02:37 A.M, there was 2820 MW generation loss at CGPL, Mundra. At that time, many proactive actions were taken by SLDC-Gujarat in order to maintain load - generation balance of the Gujarat power system. GWRDC availed Ukai left bank main canal (ULBMC) outage for 60 days from for major repairing work. During outage, it was not possible to keep all units of UHPS and UTPS except UTPS Unit No. 6 on bar due to acute water shortage. SLDC proactively coordinated all activities like ensuring water requirement of UTPS Unit No. 6, procurement of cheaper gas for NTPC s Kawas and Jhanor plants, augmentation of 315 MVA ICT at Ukai, unit outages at Ukai etc. Before facilitating ULBMC outage, The outage of 400/220 KV, 315 MVA ICT at Ukai was facilitated for augmentation work timely. The power system of South Gujarat was well managed securely and reliably by SLDC. Initiatives for Improvement: A lot of initiatives were taken to improve operational performance. During the year , two black start mock drills were carried out with objective of restoration of total system in the shortest possible time in case of large scale black out. All these exercises were distinct. In one exercise, two gas based Power Stations (Kawas and Jhanor) of NTPC participated jointly and in other exercise one hydro unit of RBPH and one gas based unit of CLPIPL participated jointly. SLDC had taken proactive steps to inform the field offices and other related agencies to avail the outages of important elements as and when there were opportunities in the system. Also, SLDC had made fabulous efforts to facilitate outages for construction of new EHV lines and for R & M work of EHV lines so

6 as to accommodate new elements in the grid at the right time. The outage of ± 500 KV Mundra - Mohindergadh HVDC Bipole outage was facilitated on for crossing work of 400 KV D/C Charanka - Sankhari line. At that time, generation at APL was restricted to 3000 MW to manage safe loading on AC network in Kutch and North - Gujarat area. 132 KV Nyara - Vajadi & 132 KV Nyara - Vikram line simultaneously for continuous five days was facilitated for line shifting and height raising work. The continuous outage of 400 KV D/C Vadavi - Dehgam line for 20 days and 18 days continuous outage of 400 KV CLPIPL Kasor line for rerouting of lines to facilitate DFCC crossing were facilitated. SLDC has taken keen interest to relieve congestion in the network by proposing worthwhile changes in network topology and getting them implemented through the concerned agencies so as to have a secure and reliable grid operation. As a result, the interconnection of 400 KV Ukai - Kosamba line No. 2 & 400 KV Jhanor - Dastan line No. 1 (so as to form 400 KV S/C UTPS Navsari line and 400 KV S/C Jhanor Kosamba line) has been established. Also, direct 220 KV links (one is 220 KV Kosamba - Ichhapore and another is 220 KV GSEG - Sachin line) have been established in South -Gujarat. It improves the reliability of power supply in South Gujarat area. SLDC has taken up the matter with WRPC regarding delay in scheduling of URS power of CGPL on account of late consent by the Utilities. SLDC informed that there is no need to take consent of respective SLDCs (whose beneficiaries has surrendered the share) / Discoms / Generators in exigency condition because their owned share has been allocated as per the scheduling procedure of IEGC without informing / taking consent of State SLDC / beneficiaries who has availed URS. It has been informed that URS of UMPP shall be allocated promptly to the beneficiary in need as per the scheduling procedure. In case of exigency condition, it shall be allocated as soon as possible without taking consent of the Generators / State SLDCs who has surrender the share so as to avoid delay in scheduling of URS power of CGPL on account of late consent by the Utilities. SLDC has done remarkable work accessing reliable data of renewable energy generation in real time which is very much helpful to recognize trend of RE generation and handle its variation. The service provider is finalized now. SLDC is getting more accurate forecasting of RE generation. At present, SLDC is getting day ahead, real time and weekly wind generation forecast for State as whole through online web based application from service provider. SLDC has developed in house wind energy generation forecasting module. SLDC is continuously analysing trend of wind energy generation forecast provided by FSP and provided by in house module. SLDC is continuously monitoring real time trend with forecasted generation. It is being regularly utilised for system analysis and better forecasting purpose. Also, a keen initiative has been taken for hiring load forecasting service, The service provider will be finalized soon. Our SCADA & IT team had done outstanding work for data visualization, maintaining RTU availability and communication link with control centre. Lot of efforts are made for accessing of various data by users from SLDC website which maintains a high degree of translucent environment. SLDC Gujarat is equipped with WAMS technology using Synchro phasor. Over hundred PMUs are commissioned at 25 locations. The Phasor Data Concentrator (PDC) is commissioned at SLDC which is capable of handling 1500 phasors. This facility is very much helpful for early detection of any forthcoming harmful event to the grid so as to respond quickly.

7 SLDC is equipped with NEW SCADA hardware. Also, the Back-up SLDC has been established at Gandhinagar with advanced IT and hardware infrastructures. It has been successfully tested. It will be helpful to manage the system in case of any disaster at main control centre. SLDC believes in knowledge sharing and skill enhancement of each of its working associates. Almost in all capacity building workshops and training programs, SLDC officials are delegated. Also, in-house discussion sessions are regularly arranged so that each individual s skill and area of interest is candidly recognized. As a result, many technical papers and presentations have been presented in various national and International summits by SLDC officials. A one day non-residential workshop on Power System Restoration was organized on (Saturday) at Gujarat Energy Training & Research Institute (GETRI), near 132 KV Gotri Substation, Gotri Road, Gotri, Vadodara. The workshop aimed to familiarize participants on Gujarat Power System, Role of defence Mechanisms, Role of each utilities during black out, Power system restoration approach, sharing of mock drill experience and to acquaint with Gujarat Power System restoration procedure etc. Officers and delegates from WRLDC, all generating Stations in Gujarat, NCA, GETCO, SLDC-Gujarat, Sub SLDC s, Railway, Discoms were invited. Almost 100 officials attended the workshop. I, on behalf of SLDC staff, take this opportunity to convey my sincere thanks to Shri S. K. Negi (Former MD, GETCO) for providing an excellent guidance and invaluable support and leading MD, GETCO Shri B. B. Chauhan for strengthening the State grid by executing various important transmission projects timely. All our efforts in preparation of this Annual Report would rather go in vain if I fail to thank GoG, GUVNL, GERC, WRPC, WRLDC (POSOCO) and beneficiaries and all others related to grid operation for rendering their continuous support, active involvement and kind cooperation. With Best Regards, (B.B. Mehta) Chief Engineer State Load Despatch Centre

8

9 TABLE OF CONTENTS 1. INTRODUCTION Formation Functions SALIENT FEATURES OF THE GUJARAT GRID Installed Capacity Sector wise Fuel wise Transmission Network as on State Distribution Companies in Gujarat & their contracted capacity(mw) inas on DEMAND FACTS... 6 Month wise Maximum Demand Catered in MW ENERGY GENERATION FACTS Sector wise Energy Generation (in MUs) Monthly Sector wise Energy Generation (MUs) State Generating Station wise Energy Generation for Year Thermal Units Gas Units Hydro Units Others RENEWABLE ENERGY GENERATION ABSORPTION Wind Energy Generation Facts Monthly Wind Energy Generation in Mus Month wise Maximum Wind Energy Generation in MW Month wise Maximum Wind Energy Generation in MUs Hourly Wind Energy Injection Trend during the year Maximum variation in wind energy generation in MUs on two consecutive days Solar Energy Generation Facts Month wise Solar Energy Generation in MUs Month wise Maximum Solar Energy Generation in a day in MWH Month wise Maximum Solar Energy Generation in a day in MUs Hourly Solar Energy Generation Pattern during the FY Typical Solar Generation Captured DISCOM-WISE DEMAND FACTS DISCOM wise Energy Catered Category wise Energy Supplied in MUs by State Discoms DISCOM wise Category wise energy supplied in MUs Month - wise Category - wise energy supplied in MUs:... 18

10 7. VOLTAGE PROFILE STATISTICS AT IMPORTANT NODES FREQUENCY PROFILE STATISTICS Monthly Average Frequency Trend for Last Three Financial Years Monthly Frequency Trend GENERATION CAPACITY ADDITION /DECOMMISSIONED GRID EXPANSION EHV lines added in Gujarat Grid during year MAJOR INCIDENTS MONTHLY GETCO NETWORK LOSSES (%) ENERGY ACCOUNTING & SETTLEMENT AND STOA DETAILS ABT Meters Registered for Data Processing at SLDC Nos. of active UI Pool Members in UI Pool Account of SLDC Users Registered under REC Mechanism Short Term Open Access Applications Processed SCADA & IT UPDATES Data Acquisition Updates IT Updates FINANCIAL FACTS & FIGURES Aggregate Revenue Requirement for the FY Major Figures for the FY CAPEX Plan of SLDC FUTURE OUTLOOK & NETWORK IMPROVEMENT State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 2

11 1. INTRODUCTION 1.1 FORMATION As per Energy & Petrochemical Department, Government of Gujarat, Order No. GHU-04-32GEB K of 29 th May 2004, established the load despatch centre, Jambuva as State Load Despatch Centre, for purposes of exercising the power and discharging functions under section 31 of IEA FUNCTIONS In accordance with section 32 of Electricity Act, 2003, the State Load Despatch Centre (SLDC) has to carry out following functions: a. SLDC has to ensure integrated operation of the power system in a State. b. SLDC is responsible for optimum scheduling and despatch of electricity within a State. c. Monitor grid operations; d. keep accounts of the quantity of electricity transmitted through the State grid; e. Exercise supervision and control over the intra-state transmission system; f. SLDC is responsible for carrying out real time operations for grid control and despatch of electricity within the State through secure and economic operation of the State grid in accordance with the Grid Standards and the State Grid Code. g. SLDC in a State may give such directions and exercise such supervision and control as may be required for ensuring the integrated grid operations and for achieving the maximum economy and efficiency in the operation of power system in that State. h. Every licensee, generating company, generating station, sub-station and any other person connected with the operation of the power system shall comply with the directions issued by the SLDC. i. The SLDC shall comply with the directions of the Regional Load Despatch Centre. j. In case of inter-state bilateral and collective short-term open access transactions having a state utility or an intra-state entity as a buyer or a seller, SLDC shall accord concurrence or no objection or a prior standing clearance. k. The following are contemplated as exclusive functions of SLDC. a. System operation and control covering contingency analysis and operational planning on real time basis; b. Scheduling / re-scheduling of generation; c. System restoration following grid disturbances; d. Metering and data collection; e. Compiling and furnishing data pertaining to system operation; f. Operation of state UI pool account, state reactive energy account. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 3

12 Annual Report SALIENT FEATURES OF THE GUJARAT GRID 2.1 INSTALLED CAPACITY SECTOR WISE Installed Capacity (MW) State Sector Private Sector Central Sector Wind Farm Solar Biomass Mini Hydro Total As on As on As on As on As on As on State Sector Private Sector Central Sector Wind Farm Solar As on As on As on As on As on As on FUEL WISE Period Thermal Gas Hydro Nuclear Solar Wind Farm Biomass Total As on As on As on As on As on As on Thermal Gas Hydro Nuclear Solar Wind Farm Biomass As on As on As on As on As on As on State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 4

13 2.2 TRANSMISSION NETWORK AS ON Sr. No. Voltage Class No. of Substations As on As on Transmission Lines in circuit Km No. of Substations Transmission Lines in circuit Km KV KV KV /33 KV Total STATE DISTRIBUTION COMPANIES IN GUJARAT & THEIR CONTRACTED CAPACITY(MW) INAS ON Sr. No. Name of the Company Contracted Capacity from conventional sources in MW as on PGVCL UGVCL DGVCL MGVCL 2164 State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 5

14 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Annual Report DEMAND FACTS MONTH WISE MAXIMUM DEMAND CATERED IN MW Maximum Demand catered of last Ten years Max demand catered in MW Max demand catered in MW No of days when demand difference between Maximum and Minimum demand in a day remains more than 2000 MW Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 6

15 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Annual Report ENERGY GENERATION FACTS 4.1 SECTOR WISE ENERGY GENERATION (IN MUS) Year GSECL Private Sector Central Sector Wind Energy Solar Biomass Mini Hydro Total MUs MONTHLY SECTOR WISE ENERGY GENERATION (MUS) Month GSECL Private Central sector WEG Solar Biomass Mini Hydro Total MUs Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Total % Contribution Month wise energy supplied (in MUs) YEAR YEAR YEAR State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 7

16 4.3 STATE GENERATING STATION WISE ENERGY GENERATION FOR YEAR THERMAL UNITS Unit Unit Capacity (MW) Generation (MUs) GANDHINAGAR GTPS GTPS GTPS WANAKBORI WTPS WTPS WTPS WTPS WTPS WTPS WTPS UKAI(TH) UTPS UTPS UTPS UTPS UTPS UTPS SIKKA STPS STPS STPS STPS PANANDHRO KLTPS KLTPS KLTPS KLTPS TORRENT POWER AECO C AECO D AECO E AECO F SURAT LIGNITE SLPP SLPP SLPP SLPP AKRIMOTA ALPP ALPP APL APL APL State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 8

17 APL APL APL APL APL APL APL Essar Vadinar EPGL EPGL OPGS OPGS OPGS BECL BECL BECL Total Thermal generation GAS UNITS Unit Unit Capacity (MW) Generation (MUs) DHUVARAN GAS DTPS - GT DTPS -STG DTPS-GT DTPS-STG DGB GT UTRAN Stage-2 UGPP GT UGPP ST GIPCL-I GIPCL GT GIPCL GT GIPCL GT GIPCL ST GIPCL-II GIPCL GT GIPCL ST CLPIPL GPEC GT GPEC GT GPEC GT GPEC STG GSEG Stage-1 GSEG GSEG GSEG ST GSEG Stage-2 GT STG State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 9

18 SUGEN SUGEN GT SUGEN GT SUGEN GT UNO SUGEN UNO SUGEN GPPCL GPPCL GPPCL Total Gas Generation HYDRO UNITS Unit Unit Capacity (MW) Generation (MUs) UKAI(HY) UHPS UHPS UHPS UHPS UKAI LBCH ULBC ULBC KADANA KHPS KHPS KHPS KHPS PANAM PANAM PVT HY. MADHUBAN DAM MADHUBAN DAM MADHUBAN DAM Karjan Dam Total Hydro Generation OTHERS Others Generation (MUs) CPP Wind Farm Solar Biomass Central Sector Total Energy Generation State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 10

19 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Annual Report RENEWABLE ENERGY GENERATION ABSORPTION 5.1 WIND ENERGY GENERATION FACTS MONTHLY WIND ENERGY GENERATION IN MUS Wind energy integrated in Gujarat Power System (Last 5 years) Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar MONTH WISE MAXIMUM WIND ENERGY GENERATION IN MW Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 11

20 0 to 1 1 to 2 2 to 3 3 to 4 4 to 5 5 to 6 6 to 7 7 to 8 8 to 9 9 to to to to to to to to to to to to to to to 24 Annual Report MONTH WISE MAXIMUM WIND ENERGY GENERATION IN MUS Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar HOURLY WIND ENERGY INJECTION TREND DURING THE YEAR Less than 500 MWH More than 500 MWH and less than 1000 MWH More than 1000 MWH and less than 1500 MWH From the above, it is observed that the wind energy injection during 09:00 Hrs. to 12:00 Hrs. was quite less, whereas during 16:00 Hrs. to 18:00 Hrs, it was on higher side. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 12

21 Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Annual Report MAXIMUM VARIATION IN WIND ENERGY GENERATION IN MUS ON TWO CONSECUTIVE DAYS ( MUs) ( MUs) ( MUs) ( MUs) 5.2 SOLAR ENERGY GENERATION FACTS MONTH WISE SOLAR ENERGY GENERATION IN MUS Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Solar energy in MUs State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 13

22 8 T O 9 9 T O T O T O T O T O T O T O T O Annual Report MONTH WISE MAXIMUM SOLAR ENERGY GENERATION IN A DAY IN MWH Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar MONTH WISE MAXIMUM SOLAR ENERGY GENERATION IN A DAY IN MUS Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar HOURLY SOLAR ENERGY GENERATION PATTERN DURING THE FY Less than 250 MWH More than 250 MWH & less than 500 MWH Greater than 500 MWH HOURS State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 14

23 5.2.5 TYPICAL SOLAR GENERATION CAPTURED Maximum Solar energy received in a day, Maximum variation in solar energy in a two consecutive days, Minimum Solar energy in a day (Max Solar energy received MUs), (4.64 MUs) (3.87 MUs) (2.75 MUs) (1.63 MUs) (Min Solar energy received MUs) Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs Hrs. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 15

24 Annual Report DISCOM-WISE DEMAND FACTS 6.1 DISCOM WISE ENERGY CATERED DISCOM WISE ENERGY SUPPLIED IN MUS DURING LAST 7 YEARS PGVCL UGVCL MGVCL DGVCL SE CO AE CO Energy supplied by Discoms during PGVCL UGVCL MGVCL DGVCL TPSEC TPAEC 6.2 CATEGORY WISE ENERGY SUPPLIED IN MUS BY STATE DISCOMS JGY URB/TWN AGR IND Category wise energy supplied IND, 35098, 42% JGY, 12643, 15% URB / TWN, 13607, 17% AGR, 21789, 26% State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 16

25 Annual Report DISCOM WISE CATEGORY WISE ENERGY SUPPLIED IN MUS PGVCL JGY PGVCL URB PGVCL AG PGVCL IND UGVCL JGY UGVCL URB UGVCL AG UGVCL IND PGVCL UGVCL DGVCL JGY DGVCL URB DGVCL AG DGVCL IND MGVCL JGY MGVCL URB MGVCL AG MGVCL IND DGVCL MGVCL State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 17

26 6.4 MONTH - WISE CATEGORY - WISE ENERGY SUPPLIED IN MUS: JAN FEB MAR APR MAY JUN JUL JAN FEB MAR APR MAY JUN JUL DEC AUG DEC AUG NOV SEP NOV SEP OCT OCT JGY JGY JGY JGY JGY Urban Urban Urban Urban Urban MAR APR MAY MAR APR MAY FEB JUN FEB JUN JAN 0 JUL JAN 0 JUL DEC AUG DEC AUG NOV SEP OCT Agriculture Agriculture Agriculture Agriculture Agriculture NOV SEP OCT Industrial Industrial Industrial Industrial Industrial State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 18

27 7. VOLTAGE PROFILE STATISTICS AT IMPORTANT NODES 400 KV Kasor Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Asoj Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Jetpur Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Amreli Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 19

28 400 KV Hadala Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Chorania Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Vadavi Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Soja Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV KV Kansari Month Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar No. of days when bus voltage remained > 420 KV < 380 KV Max KV Min KV State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 20

29 Annual Report N O. D A Y S W H E N VOLTAGE R E M A I N E D M O R E T H A N K V K A S O R A S O J J E T P U R A M R E L I H A D A L A C H O R A N I A S O J A V A D A V I K A N S A R I Remark: SLDC had put up its best efforts to curb over voltage at 400 KV nodes. As a result, no. of days when voltage crossed its value (420 KV) had been reduced considerably at Kasor, Amreli & Chorania S/S. Even though in north Gujarat and at Asoj S/S, voltage remained high during the year. It might be due to less MVAR absorption support from WTPS, less schedule to WTPS units, light loading on newly commissioned 400 KV APL Kansari & 400 KV Varsana Kansari line and due to presence of 765 KV Vadodara. Also, there was unexpected rain in Oct 16. During high agriculture demand, low voltage had noticed in following 220 KV substations might be due to non-working / partial working of existing capacitor banks; South Gujarat area North Gujarat area Saurashtra area Bhilad Dhansura Vartej, Sagapara Navsari Chikhli Savarkundla Dhokadava, Timdi Keshod, Shapur Kangasiyali, Naghedi The additional capacitor bank or any other suitable measures shall be planned even though existing capacitor banks are in working condition to improve voltage profile. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 21

30 Hz Annual Report FREQUENCY PROFILE STATISTICS 8.1 MONTHLY AVERAGE FREQUENCY TREND FOR LAST THREE FINANCIAL YEARS Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Remark: The average frequency profile improved significantly. It remained in the range of Hz Hz during Year Whereas, it was in the range of Hz Hz during Year MONTHLY FREQUENCY TREND % of time block when frequency remained between Hz to 49.90Hz April May June July Aug Sept Oct Nov Dec Jan Feb Mar % of time block when frequency remained between Hz to 50.05Hz April May June July Aug Sept Oct Nov Dec Jan Feb Mar State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 22

31 <49.90, 59, 88 <49.90, 89, 108 > 50.05, 53, 158 > 50.05, 69, 129 > 50.05, 73, 121 > 50.05, 88, 129 Annual Report Frequency stastics in each time block of the Year % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% <49.90 >=49.90 AND <=50.05 > Remark: 1. In bock No. 53, 69, 73 & 88, the frequency remained more than Hz most of the times. 2. In block No. 37,75, 82, 88 & 89, the system frequency remained below Hz for 15-30% of time throughout the year. 3. From block No. 88 to 89 daily, there were sudden change in frequency. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 23

32 9. GENERATION CAPACITY ADDITION /DECOMMISSIONED Capacity Addition during FY Sl. Unit Capacity (MW) GUVNL Share (MW) Date of COD 1 GSEG Expansion* DGBPS Unit No. 3* BECL Unit No Mauda Stage II Unit No BECL Unit No Wind Solar 214 Total 2974 Total GUVNL Share of Conventional 1374 *Dhuvaran Stage 3 (376.1 MW) & GSEG Expansion project (351 MW) have been considered for bare minimum fixed cost w.e.f & respectively vide GUVNL Letter No. GUVNL / COM / CFM(IPP)/SLDC/319 dated Decommissioning of Capacity during FY Sl. Unit Capacity (MW) GUVNL Share (MW) De-commissioning From 1 EPOL, Hazira GIPCL Stage - II GTPS Unit No GTPS Unit No UGPP Stage Total Capacity Decommissioned 840 State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 24

33 10. GRID EXPANSION EHV LINES ADDED IN GUJARAT GRID DURING YEAR Sr. No Name of line / Equipment 400 KV Kosamba - Jhanor line (Interconnection of 400 KV Ukai - Kosamba line No. 2 with 400 KV Jhanor - Kosamba line No. 1) 400 KV Ukai - Navsari (PG) line (Interconnection of 400 KV Ukai - Kosamba line No. 2 with 400 KV Jhanor - Kosamba line No. 1) 220 KV Kosamba - Ichhapore line & 220 KV GSEG - Essar line (Interconnection between one circuit of 220 KV GSEG - Kosamba and 220 KV Essar - Ichhapore line) Date of Commissioning KV GPPC - Sintex (Rajula) /220 KV, 315 MVA ICT No. 3 at Kasor KV Ichhapore - Sachin line (Interconnection of 220 KV Ichhapore -Essar line with 220 KV Essar - Sachin line No. 1) KV GSEG -Sachin line (Interconnection of 220 KV GSEG -Essar line with 220 KV Essar - Sachin line No. 2) KV D/C Visavadar - Timdi line KV Dhokadava - Sintex line KV D/C Dhokadava - GPPC line KV Vikram - Padavla line KV Padavla - Paliyad line /66 KV 50MVA Tr-1 Padavla /220 KV, 500 MVA ICT at UTPS (Augmentation from 315 MVA to 500 MVA) KV Bechraji - Maruti line No KV Bechraji - Maruti line No KV Mitha - Bechraji line No KV Mitha - Bechraji line no /132 KV, 150 MVA Trf - 2 Botad /132 KV, 150 MVA ICT - 2 Gondal (Augmentation from 100 MVA to 150 MVA) /220 KV, 500 MVA ICT 4 Kosamba /132 KV, 150 MVA ICT - 3 Gondal (Augmentation from 100 MVA to 150 MVA) KV Charanka - Veluda line No KV Charanka - Veluda Line No KV D/C Achhalia Tilakwada line /132 KV, 100 MVA ICT - 2 Bhatia /220 KV, 500 MVA ICT - 4 Amreli /132 KV, 150 MVA ICT - 2 Jamnagar (Augmentation from 100 MVA to 150 MVA) KV Sadla - Maruti WF line No KV Sartanpar - Vaghasiya line KV Botad - Parabdi WWIL line No /132 KV, 100 MVA ICT - 2 Sartanpar KV D/C Amreli - Visavadar line State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 25

34 11. MAJOR INCIDENTS Sr. No. Date PS / Substation affected Summary Load loss Gen loss (MW) (MW) :47 Hrs 220 KV Shapur S/S Prior to incident, the outage of 220/66 KV, 100 MVA Trf No. 1 was taken from 08:35 Hrs on for OLTC overhauling work. At 14:47, 220/66 KV, 100 MVA Trf No. 2 and 220/132 KV, 100 MVA Trf tripped at Shapur S/S due to activation TRSM3 96 relay There was load loss of about 62 MW :00 Hrs OPGS PS Prior to occurrence, there was a generation of 241 MW at OPGS ( Unit No. 1 was running on 114 MW & No. 2 on 227 MW). At 14:01 Hrs, 220 KV Varsana - OPGS line No. 1 tripped (OPGS end: Z1 B-Y, 4.0 KM. Varsana end:z2 R-Y, 50.1 KM, 1.9 KA). At the same time, 220 KV Varsana - OPGS line No. 2 tripped (OPGS end: Z3 Y-B. Varsana end: Z1 B-E, 50.8 KM, 1.86 KA). It led to black out at OPGS power Station. A tree found in induction zone between location No There was generation loss of 241 MW :04 Hrs. 400 KV Asoj S/S The R- ph. CT of 400 KV Asoj - Kosamba line fired. It led to tripping of 400 KV bus - 1. All elements connected to 400 KV bus -1 (Chorania line No. 1, Vadodara line No. 1, SSP line, 400/220 KV, 500 MVA ICT - 1, 400/220 KV, 315 MVA ICT - 3) along with bus coupler tripped. After isolating Asoj - Kosamba line, 400 KV bus - 1 was charged through bus coupler 02:49 Hrs. Thereafter, all elements were taken in service one by one. 0 0 However, there was no generation / load loss :40 Hrs. 220 KV Halvad S/S At 05:40 Hrs., 220 KV Halvad - Dhrangadhra line No. 2 which was on 220 KV Bus -B tripped (Halvad end: Z-I, Y-B Ph. 9.9 Km, 1.92 KA Dhrangadhra end: B Ph. Trip, Km, 1 KA). At the same time, B - ph. flyover string of 220/66, KV, 160 MVA Trf No. 1 bay flashed over. It led to bus fault on 220 KV Bus - A. All elements connected to 220 KV Bus A (Mansar line No. 1, Sartanpar line No. 2, Dhrangadhra line No. 1 ) tripped. 0 0 However, there was no generation / load loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 26

35 :07 Hrs.& 22:57 Hrs. WTPS All WTPS units were on bar. 400 KV WTPS - Dehgam line tripped at 22:07:55 Hrs on R- ph. to earth fault. The auto reclose had been operated, but again line tripped at 22:07:56 Hrs. At the same time, fire took place in 400 KV R - ph. CT of CT-11 bay (Tie bay between Dehgam line & GT of Unit No. 6) towards GT bay of unit No. 6 and it busted. It led to tripping of all breakers connected to 400 KV Bus 2 and unit No. 6 (running at 208 MW). Also, there was damage found in 400 KV B-ph CT of CT-15 bay i.e. tie bay (middle bay) between GT-7 & Soja line bay. There was heavy oil leakage found in CT and oil completely drained out Just after within few seconds, 400 KV WTPS Soja line tripped. It led to tripping of WTPS Unit No. 7 (running at 206 MW) due to evacuation constraint. Before exercising restoration of 400 KV Bus 2, 400 KV B-ph CT of CT 1 bay (ICT bay) got fired at 22:57 Hrs. It led to tripping of ICT and Unit No. 4 (running at 211 MW) due to evacuation constraint. There was a generation loss of 627 MW :58 Hrs. ALTPS & KLTPS Prior to incident, all Units of KLTPS TPS with total generation of 216 MW and all Units of ALTPS with total generation of 168 MW were on bar. 220 KV KLTPS - Kukma line No. 2 was made off at 09:00 Hrs. under R&M Work. At 16:45 Hrs., 220 KV KLTPS - Kukma line No. 1 tripped due to accident occurred while removing vibration damper at location No. 364 (S) on 220 KV KLTPS - Kukma line No. 2. At the same time 220 KV ALTPS - Nakhatrana line No. 1 tripped from ALTPS end on SOTF. thereafter at 16:56 Hrs., 220 KV KLTPS - Nakhatrana line No. 1 tripped from both ends (At Location No. 58 (T), conductor found broken) and 220 KV KLTPS - Nakhatrana line No. 2 tripped from KLTPS end only (Only breaker tripped. No relay indication was there). Only one line i.e. 220 KV ALTPS - Nakhatrana line No. 2 remained available for evacuation of ALTPS & KLTPS generation At 16:58 Hrs., 220 KV ALTPS - Nakhatrana line No. 2 tripped at ALTPS end only (R - Ph. Breaker Pole problem at ALTPS). Simultaneously, 220 KV KLTPS-ALTPS line No.1 & 2 tripped on Under-Voltage from ALTPS end. It led to black out at ALTPS & KLTPS. There was generation loss of 384 MW. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 27

36 :57 Hrs. 220 KV Tebhada WF Pooling station At 20:57 Hrs., the 33 KV feeder No. 13 tripped due to one insulator string flashover. It led to severe voltage dip at Tebhada S/S. It led to temporary disconnection of all WTG connected to pooling station There was wind generation loss of 219 MW for short duration for about three to four minutes :45 Hrs. 220 KV Vagra S/S The weather was very heavy humid and heavy wind there at the time of incident. At 21:45 Hrs., one insulator string of double tension string insulator of Y- ph. fly over bus of 220 KV Vagra - Dahej line bay flashed over. It led to activation of bus bar protection Zone 1 scheme. As a result, all elements connected to 220 KV Bus - 1 (220 KV Bus Coupler, 220 KV Dahej, 220 KV RVNL-01 and 220/66, KV 50 MVA Trf -01) tripped. 0 0 However, there was no load loss :45 Hrs. 220 KV Vagra S/S The weather was very heavy humid and heavy wind there at the time of incident. At 04:45 hrs. one insulator string of double tension string insulator of B- ph. fly over bus of 220 KV Vagra - Haldarva line bay flashed over. It led to activation of bus bar protection Zone -2. As a result, all elements connected to 220 KV Bus - 2 (220 KV Bus Coupler, 220 KV Haldarva line 220 KV RVNL line No. 2 and 220/66, KV 50 MVA Trf -1) tripped There was 20 MW load loss :20 Hrs. ALTPS Prior to tripping, ALTPS Unit No. 2 was on bar with 95 MW generation. 220 KV ALTPS - Nakhatrana line No. 1 tripped on Z1 B ph. to E, 1.5 Km from ALTPS end only. At the same time, 220 KV ALTPS - Nakhatrana line No. 2 tripped from ALTPS end. Also, 220 KV KLTPS - ALTPS line No. 1 & 2 tripped. It led to black out at ALTPS There was generation loss of 95 MW :32 Hrs. ALTPS There was heavy chattering in switch yard at ALTPS. All elements connected to 220 KV Bus A & Bus B tripped. It led to tripping of all elements connected to ALTPS There was generation loss of 92 MW (ALTPS Unit No. 2 was running at 92 MW). State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 28

37 :50 Hrs. 220 KV Vagra S/S The weather was very heavy humid. There was heavy chattering in switch yard especially on bus PT bay. It led tripping of 220 KV Bus - 2. As a result all elements connected to 220 KV Bus - 2 (220 KV Bus Coupler, 220 KV Haldarva line 220 KV RVNL line No. 1 and 220/66, KV 50 MVA Trf -1) There was 22 MW load loss :14 Hrs KLTPS At 18:14 Hrs, R- ph. conductor of 220 KV Panandhro - Kukma line No. 1 snapped and dropped down on 220 KV Bus - 1. As a result, bus fault occurred on 220 KV bus-1 and busbar protection activated at KLTPS. It led to tripping of all elements (GT - 1, GT - 2, 220 KV Nakhatrana line No. 1, 220 KV ALTPS line No. 1) connected to 220 KV Bus There was a generation loss of 136 MW :10 Hrs 132 KV Gotri S/S At 14:10 Hrs, 132/66 KV, 100 MVA Trf No. 1 & 4 and 132/66 KV, 40 MVA Trf No. 2 tripped from LV side only on B - ph. O/C due to thin piece of metal wire fallen down from beak of flying bird on B ph. of LV side isolator of Trf No There was load loss of around 130 MW for just few minutes :45 Hrs Pirana (PG) & Pirana (T) and df/dt operation at various S/S. At 19:45 Hrs at Pirana (PG) S/S, there were simultaneous tripping of multiple elements occurred at 19:45 Hrs due to inclement weather conditions. It was observed that external flashover had occurred across Y phase CVT of 400 KV Vadodara - Pirana line No. 2 and it extended to Wave trap of R phase. The fault persisted for about 500 ms At the same time, 400 KV Pirana(PG) - Pirana(TPL) line No. 2 from Torrent end and 132 KV D/C Pirana (TPL) - Vinzol line tripped. It led to 200 MW load loss at Pirana (TPL) S/S. Also, the df/dt relay operated at 220 KV Tharad, Jangral, Radhanpur, Kansari, Sankhari & Kim S/S. There was load relief of about 270 MW due to df/dt operation. There was load loss of about 470 MW :50 Hrs. 132 KV Bhatia S/S 132 KV Sikka -Bhatia line tripped at 7:45 Hrs. Thereafter within few minutes at 7:50 Hrs, 132 KV Bhatia - Khambhalia line No 1 & 2 tripped There was 70 MW wind generation and 21 MW load loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 29

38 :25 Hrs. OPGS The connectivity of OPGS Plant is extended to 400 KV network via 400/220 KV, 315 MVA ICT No. 3 at Varsana S/S. At 06:25 Hrs, 400/220 KV, 315 MVA ICT No. 3 at Varsana tripped on REF relay There was generation loss of 203 MW at OPGS :29 Hrs. 400 KV Varsana S/S 400 KV Bus - 1 at Varsana S/S tripped due to bus bar protection operated. At the same time, 400/220 KV, 315 MVA ICT No. 3 at Varsana tripped on REF relay. As connectivity of OPGS Plant is extended to 400 KV network via 400/220 KV, 315 MVA ICT No. 3 at Varsana, the blackout occurred at OPGS There was 88 MW generation loss :50 Hrs. 400 KV Varsana S/S Prior to disturbance, 400 KV Bus 1 was under forced shutdown. At 21:50 Hrs, 400 KV Bus - 2 at Varsana S/S tripped due to bus bar protection operated and it leads to tripping of all elements connected with bus There was 80 MW load loss :56 Hrs. 220 KV Jamanwada WF Pooling Station At 13:56 Hrs., 220KV Jamanwada - Varsana line tripped. At that time, 220kV Jamanwada - Ukheda line was in PF. There was 40 MW wind generation loss :37 Hrs. CGPL Prior to occurrence, four units of CGPL were on bar and both 400 KV buses at Varsana S/S were out due to tripping. The test charge of 400 KV Bhachau - Varsana line No. 1 from Bhachau end was taken at 2:37 Hrs. At that time, all EHV lines connected to CGPL tripped. It led to tripping of CGPL Unit No. 10, 30, 40 and 50 on over speed There was 2820 MW generation loss at CGPL :02 Hrs. 220 KV Limbdi S/S At 17:02 Hrs, 66KV Limbdi - Surendranagar line No. 2 tripped. At 17:07 Hrs., the test charge was taken, but due to reflected fault on line, 132/66 KV, Trf. No. 1, 2 & 3 tripped from LV side There was 66 MW load loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 30

39 :47 Hrs 400 KV Varsana S/S Prior to occurrence, 400 KV Varsana - Kansari line was on 400 KV Bus - 2. The shutdown was planned for attending 89 - A bus isolator of 400 KV Varsana - Kansari line by transferring said element on transfer bus. While taking 400 KV Varsana - Kansari line on transfer bus, elements connected to 400 KV Bus - A (400/220 KV 315 MVA ICT No. 1 & 3, 400 KV Varsana - Hadala line, 400 KV Bus coupler, 400 KV 50 MVAR reactor) tripped on activation of LBB protection. The 400/220 KV, 315 MVA ICT No. 3 is radially connected with OPGS generation plant (2 x 150 MW) through 220 KV D/C Varsana - OPGS line. Hence, there was generation loss of around 210 MW The 400/220 KV, 315 MVA ICT No. 3 was charged on 400 KV Bus - B at 13:02 Hrs and power supply was extended to OPGS. 400 KV Bus - A was charged through 400 KV Bus coupler at 14:03 Hrs :25 Hrs 220 KV Halvad S/S At 08:25 Hrs, Zone - 2 bus bar protection operated at Halvad S/S due to failure of 220 KV R ph. PT of 220 KV Bus-2. It led to tripping of all elements connected to 220 KV Bus - B (220 KV Mansar - Halvad line No. 2, 220 KV Halvad - Dhrangadhra line No. 2, 220 KV Halvad - Sartanpar line No. 2 and 220/66 KV, 160 MVA Trf No. 1). 0 0 There was no generation / load loss in system :30 Hrs 220 KV Halvad S/S There was saline atmosphere with drizzling rain in surrounding area. The 220 KV B ph. post insulator of 220/66 KV, 160 MVA Trf No 1 bay near circuit breaker flashed over at 04:30 Hrs. It led to tripping of all elements on activation of bus bar protection for both buses There was load loss of 19 MW :05 Hrs 132 KV Vikram S/S At 06:05 Hrs, both 66 KV Vikram - Tramba line 1 and 2 tripped. At the same time, all 132/66 KV transformers at Vikram S/S tripped from LV side There was load loss of 54 MW :30 Hrs. 220 KV Sadodar WF pooling station At 14:30 Hrs, all 33 KV CTs of 33 KV Fulnath - 2 feeder blasted. It led to tripping of 220 KV D/C Motipaneli - Sadodar line from Motipaneli end only There was 70 MW wind generation loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 31

40 :20 Hrs. Akrimota PS 220 KV ALTPS - KLTPS line No. 1 was made off at 08:55 hours for attend hot point at KLTPS end. At 09:20 Hrs, 220 KV ALTPS - KLTPS line No. 2 tripped (Relay at KLTPS end: Z1 R - ph Km, 4.9 KA Relay at ALTPS end: Z1 R - ph. SOTF, 13.5 Km). The R ph. jumper found open at location No. 3. It led to tripping of all elements connected to 220 KV Bus B along with Buscoupler at ALTPS There was 86 MW generation (ALTPS Unit No. 2 was running at 86 MW and connected with Bus - B) loss :42 Hrs 220 KV Jamanwada WF pooling station At 13:42 Hrs, 220 KV Jamanwada - Varsana & 220 KV Jamanwada - Ukheda line tripped on over voltage from Jamanwada end only. There was 72 MW wind generation loss :45 Hrs 220 KV Sadodar WF pooling station At 00:45 Hrs, 220 KV D/C Sadodar Motipaneli line tripped from both end. There was 82 MW wind generation loss :22 Hrs 400 KV Amreli S/S At 09:22 Hrs, 400 KV B Ph. breaker pole of 400 KV 125 MVAR reactor flashed over. It led to activation of Bus bar Zone - 1 protection. As a result, all elements connected to 400 KV Bus - 1 (400 KV Amreli - Chorania line, 400 KV Amreli - Jetpur line No. 2, 400/220 KV, 315 MVA ICT-3) tripped. 0 0 However, there was no generation / load loss :10 Hrs 220 KV Halvad S/S There was planned shutdown of 220/66 KV, 160 MVA Trf No. 1. At 12:10 hrs, heavy sparking observed on LV side of 220/66 KV, 160 MVA Trf No. 2 bus-a isolator T-clamp R & B phase jumpers. So, it was hand tripped from LV side due to security reason There was 78 MW load loss :45 Hrs. 220 KV Gondal S/S At 14:45 Hrs, all 132/66 KV transformers tripped on over current from LV side There was 136 MW load loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 32

41 :37 Hrs 400 KV Jetpur S/S The special load shedding scheme (SPS) is armed to restrict over loading at Jetpur ICT. When loading on any 400/220 KV, 315 MVA ICT at Jetpur reaches to 431 Amp and remains for 5 sec, SPS will activate and It will trip all 66 KV feeders connected to Jetpur S/S At 05:17 Hrs, the outage of 400/220 KV, 315 MVA ICT No. 3 was taken for carry out off line tap change operation. At 05:37 Hrs, SPS initiated and tripped all 66 KV feeders connected to 66 KV bus of 400 KV Jetpur S/S. There was load loss of around 120 MW :05 Hrs 400 KV Jetpur S/S There was heavy rain in surrounding area. 400 KV side Zone -1 bus bar protection operated at 03:05 Hrs. It led to tripping of all elements connected to 400 KV Bus - 1 (400/220 KV, 315 MVA ICT - 1, 400/220 KV, 500 MVA ICT - 4, 400 KV Amreli - Jetpur line No. 1, 400 KV CGPL - Jetpur line No. 1, 400 KV Bus coupler). During detail observation, Y ph. centre break isolator of 400 KV 50 MVAR bus reactor bay found open. 0 0 However, there was no generation / load loss in system :31 Hrs Sikka PS There is an one and half breaker scheme arrangement at 220 KV switch yard Sikka TPS. Prior to occurrence, both STPS Unit No. 3 and 4 were on bar. The generation was about 385 MW As per the planning, the testing of distance protection scheme of newly erected bay for 220 KV Jamnagar line and 220 KV Jetpur line was being carried out. Also, the tie breaker of GT 3 & 4 bay were kept open. At 14:31 Hrs, protection system mal operated while testing. All elements connected to 220 KV Bus - 2 tripped on activation of busbar protection scheme. As a result, there was 385 MW generation loss at STPS :07 Hrs 220 KV Gavasad S/S At 04:55 Hrs, 220 KV Bus Zone - 1 protection operated. It led to tripping of all elements connected to 220 KV Bus - 1 (SLPP line No. 1, Kasor line No. 1, Kosamba line, Karjan line, 220/66 KV, 50 MVA Trf No. 1 & 3). At the same time, 220/66 KV, 50 MVA Trf No. 2 tripped on over current. The suspected B - ph. pilot string of Trf No. 3 bay 220 KV side replaced There was 74 MW load loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 33

42 :50 Hrs Sikka TPS At 12:50 Hrs, B - ph top flyover jumper of suspension insulator of 132 KV Sikka - RPL line bay broken and fallen down on 132 KV Bus - B. It led to bus fault at Sikka S/S. All elements connected to both 132 KV buses tripped. Also, there was heavy deep in voltage. It led to tripping of all auxiliaries of Unit No. 3. As a result, Unit No. 3 tripped of low forward power protection There was generation loss of 190 MW :45 Hrs 220 KV Halvad S/S At 05:15 Hrs, 220 KV R- ph. CT of 220 KV Halvad - Dhrangadhra line No. 2 flashed over. As a result, 220 KV Bus Zone -2 protection operated. It led to tripping of all elements connected to 220 KV Bus Later on at 05:45 Hrs, 220 KV R - ph CT of 220 KV Halvad - Dhrangadhra line No. 1 flashed over. As a result, 220 KV Bus zone -1 protection operated. It led to tripping of all elements connected to 220 KV Bus 1. It led to complete blackout at Halvad S/S. There was 50 MW load loss :20 Hrs 220 KV Charadava S/S At 10:20 Hrs, 220/66 KV, 100 MVA Trf No. 1 and 2 tripped simultaneously due to mal-operation of protection scheme while testing There was 48 MW load loss :47 Hrs 220 KV Halvad S/S At 05:47 Hrs, 220 KV Y ph. breaker pole of 220 KV Halvad - Dhrangadhra line No. 1 flashed over. As a result, 220 KV Bus zone - A protection operated. It led to tripping of all elements connected to 220 KV Bus However, there was no generation / load loss :45 Hrs 220 KV Sagapara S/S At 10:45 Hrs, 66 KV Sagapara - Devaliya (Tap to Thadach) line tripped from Devaliya end only. The line breaker did not trip at Sagapara end. It led to tripping of 220/66 KV, 100 MVA Trf 1 & 2 from LV side and Trf No. 3 from both side There was 110 MW load loss in system :40 Hrs 220 KV Charanka S/S At 09:40 Hrs, 220 KV Charanka - Jangral line No. 1 & 2 tripped from Jangral end only on Z3, RYB There was 60 MW Solar generation loss :14 Hrs 220 KV Charanka S/S At 12:14 Hrs, 220 KV Charanka - Jangral line no. 1 & 2 tripped from Jangral end only on Z3, RYB There was 155 MW Solar generation loss. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 34

43 :05 Hrs 220 KV Halvad S/S Prior to incident, 220/66 KV, 160 MVA Trf No. 2 was under planned shutdown. There was planning of 66 KV Bus - B shutdown. At 10:05 Hrs, while changing 66KV Bus Isolator of 220/66KV 160 MVA TR-1 from 66 KV Bus - B to 66 KV Bus - A, a heavy spark occurred. It led to tripping of 66 KV Bus coupler as well as 220/66KV, 160 MVA Trf No. 1 from LV side. As a result, there was blackout at Halvad S/S There was 73 MW load loss :12 Hrs 132 KV Wanakaner S/S Prior to incident, 132 KV Jamnagar - Wankaner line was made off from Wankaner end for load control on 220/132 KV ICTs at Sikka. There was planned shutdown of 132/66 KV, 50 MVA Trf No. 2. While opening of 132 KV Bus isolator of Transformer at 12:12 hrs, R- ph. post insulator of bus isolator broken down from bottom and it came down in induction zone of 132 KV bus. As a result, 132 KV Wankaner - Limbdi line tripped on Z-2 R ph. OC at Wankaner end & on Zone-2 at Limbdi end. Simultaneously, 132kV Wankaner - Sitagadh line tripped from Sitagadh end on Zone There was of 81 MW load loss :30 Hrs 220 KV Savarkundla S/S At 17:30 hrs, 220 KV Savarkundla-Amreli line No. 2 tripped from Amreli end on PT fuse fail. It led to activation of SPS provided at Savarkundla S/S. As a result, 7 (Seven Nos.) 66 KV feeders tripped There was load loss of around 48 MW :58 Hrs 220 KV Jambuva S/S Prior to occurrence, 220 KV Jambuva Haldarva line was in shock charge condition from 220 KV Haldarva S/S end under load control. On at 15:58 hours, R phase CT of 220 KV Jambuva - Haldarva line flashed over at Jambuva S/S. It led to tripping of all EHV elements connected to 220 KV Bus I and Bus II on activation of bus bar protection scheme at 220 KV Jambuva S/S. However, 132 KV bus supply at Jambuva S/S survived on Asoj system There was load loss of 22 MW :15 Hrs 220 KV Vav S/S At 17:15 Hrs, all 220/66 KV Transformers tripped due to hazardous blast occurred in 66 KV Capacitor Bank. However, all 220 KV lines remained live There was load loss of 306 MW. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 35

44 12. MONTHLY GETCO NETWORK LOSSES (%) Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 36

45 13. ENERGY ACCOUNTING & SETTLEMENT AND STOA DETAILS 13.1 ABT METERS REGISTERED FOR DATA PROCESSING AT SLDC No. of ABT Meters Registered As on As on NOS. OF ACTIVE UI POOL MEMBERS IN UI POOL ACCOUNT OF SLDC No. of active UI Pool Members in UI Pool account of SLDC As on As on USERS REGISTERED UNDER REC MECHANISM No. of Users registered under REC Mechanism As on As on SHORT TERM OPEN ACCESS APPLICATIONS PROCESSED Short Term Open Access Applications Statistics Year No. of Application Received No. of Application Approved No. of Application Rejected State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 37

46 14. SCADA & IT UPDATES 14.1 DATA ACQUISITION UPDATES No of RTUs RTU Category As on As on IT UPDATES Generating station and Substation Level Solar OA consumer Wind Farm Pooling Stn a. New SCADA system (Alstom make) has been commissioned at SLDC Gotri, Sub - SLDC Jambuva, Sub - SLDC Jetpur, Sub SLDC Gandhinagar. Also, the backup control centre has been established and functioning with NEW SCADA system at Sub SLDC Gandhinagar. In new SCADA system additional 8 nos of VPS Screen provided for accommodating more display for efficient and better power system operation b. To ensure 100 % availability of real time data availability between various control centres following leased lines are provided. 1) Main Control centre Gotri Backup Control Centre Gandhinagar (10 Mbps-BSNL) 2) Main Control centre Gotri Sub SLDC Control Centre Gandhinagar (4 Mbps-BSNL, Airtel) 3) Main Control centre Gotri Sub SLDC Control Centre Jetpur (4 Mbps-BSNL, Airtel) 4) Main Control centre Gotri Sub SLDC Control Centre Jambuva (2 Mbps-BSNL) 5) Backup Control centre Gandhinagar Backup WRLDC Control Centre Delhi upto Dehgam PGCIL (6 Mbps-BSNL) 6) Backup Control centre Gandhinagar Sub SLDC Control Centre Jetpur (4 Mbps-BSNL, Airtel) 7) Backup Control centre Gandhinagar Sub SLDC Control Centre Jambuva (4 Mbps- BSNL, Airtel) c. SLDC has planned for replacement of old RTUs of GE due to obsolete technology. a. Cyber security monitoring has been ensured with the help of admin based Quick heal antivirus through Cyberoam Firewall for internet. b. SLDC Control room is equipped with WIFI facility for official communication and android based Samsung mobile instrument. c. Automatic Demand Management Scheme (ADMS) is implemented in all four State Distribution companies. ADMS Phase-II is under planning stage for implementation in 100 more Substations. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 38

47 d. The E-payment facility for online payment is made operational. e. SLDC is equipped with CCTV (PTZ & static) camera, additional 4 Nos of camera installed and made operationalized for more security purpose. Total 16 nos of CCTV cameras are working. f. SLDC is equipped with high speed scanners (5 Nos.) for providing faster and better services to the stake holders. g. The Gujarat network is modelled in PSS/E software. It is very much helpful for critical outage security assessment and to carry out studies for proposed network topology changes etc h. Video conferencing facility has been successfully working between WRLDC Mumbai and Gotri SLDC, Gandhinagar Backup-SLDC and Jetpur Sub-SLDC. i. Implementation of wind forecasting mechanism. j. Analytics Software 1) On Line Oscillation Mode Identification, 2) Hybrid State Estimator and 3) Dynamic Security Assessment from PMU data developed by IIT Bombay is implemented. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 39

48 SYSTEM ARCHITECTURE FOR INTEGRATION ON RENEWABLE ENERGY GENERATION DATA State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 40

49 15. FINANCIAL FACTS & FIGURES 15.1 AGGREGATE REVENUE REQUIREMENT FOR THE FY SLDC is filing its Aggregate Revenue Requirement (ARR) independently from the FY First ARR was filed in Jan 2010 and since then SLDC has not looked back and achieved new feats towards becoming financially self-reliant. A glimpse of the ARR for the FY is given below: Particulars Rs. In Lacs Approved by GERC Employee Cost Repairs & Maintenance Admin & General Expenses Interest on Working Capital RLDC Fees and Charges Charges for ULDC & Other related projects WAM Charges -- SCADA Upgradation Less : Other Income Operating Cost Budget (a) Depreciation Interest & Finance Charges Return on Equity Less : Expenses Capitalized -- Add : Provision for Tax Capital Cost Budget (b) Total Revenue Budget On the basis of the above, tariff rates decided by Hon ble GERC for SLDC are : SLDC Charges budget for the FY Approved by GERC 1 ARR Approved in the MYT Order for FY Rs./Lakh Less : Revenue Surplus approved in Truing-up for FY Rs./Lakh Total SLDC Charges Rs./Lakh Grid Connection Charges Rupees 10, State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 41

50 15.2 MAJOR FIGURES FOR THE FY As per GERC directive, SLDC got its Final Accounts audited from a Chartered Accountant from the FY SLDC is near to closing its financial books for the FY after which it will be presented before a Charted Accountant for Statutory Audit; however, some major unaudited figures for the FY are as below: Rs. in Lacs Particulars (Income) Amount Particulars (Expenses) Amount SLDC Charges Repairs & Maintenance* STOA Scheduling Employee Cost STOA Application Admin & General Expenses Miscellaneous Income Depreciation Finance Charges 7.53 Loss on Sale 1.34 Total Total * Including ULDC Charges The above figures are subject to provision entry of Terminal benefits such as Gratuity, Leave Encashment, Finance Charges and any rectification entry arising out of audit of the FY % 4% 10% 0% 23% Major Income 19% Major Expenses 23% SLDC Charges STOA Scheduling STOA Application Misc. Income 65% R & M Employee Cost A& G Depreciation Finance Charges Loss on Sale 48% State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 42

51 15.3 CAPEX PLAN OF SLDC A significant portion of SLDC cost arises because of the grid operations activities, which are to be carried out round-the-clock requiring adequate redundancy in resources to tide over contingencies. There is a heavy reliance on information technology with components having high obsolescence rate. A few of the applications (such as SCADA/EMS) are offered by a limited number of vendors with high cost. In view of revised role of State Load Despatch Centre after enactment of Electricity Act 2003, it is necessary to strengthen SLDC to meet forthcoming challenges for the coming years. Accordingly, Capital Expenditure (CAPEX) is planned for modernization of SLDC to strengthen and develop to meet all forthcoming challenges. CAPEX plan includes, projects mainly focused on system expansion, real time data requirements, installation & development of telemeter infrastructure, technological innovations and obsolescence & replacement of existing infrastructure, strengthening of existing data communication channels, billing & commercial centre development, system study and IT related infrastructure. SLDC CAPEX plan approved by Hon ble GERC for the FY is as follows : Sr. No. Particulars Approved in MYT (Rs. In Lacs) 1 Augmentation/ Upgradation of existing systems Strengthening of communication channels IT Infrastructure Office Equipment Additional Expenditure Total Capital Expenditure Upgradation Strengthening IT Infra Office Eqp. Additional State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 43

52 16. FUTURE OUTLOOK & NETWORK IMPROVEMENT A. Enhancing Transformation Capacity The need of augmentation to cater future load growth reliability is summarized as under: Particular Additional 400/220 KV, 500/315 MVA ICT requirement Augmentation to be planned at Substations Replacement of existing 220/132 KV, 100 MVA ICT with 150 MVA capacity Power Stations / Substations Ukai, WTPS, Kansari and Varsana (* for reliable evacuation of OPGS generation). Karamsad, Limdi, Jambuva and STPS B. Skewed despatch scenario in Central & South Gujarat Pocket Due to availability of substantial cheaper generation on 400 KV network, power flow through 400/220 KV ICTs has increased significantly. Major part of 220 KV EHV lines in South Gujarat always remained loaded throughout the year. Generation capacity of the order of 2500 MW, which otherwise was served to consumers at 220 KV / 132 KV level remains unutilized most of the time due to costly fuel (Gas). Hence, there are always severe constraints in Central & South Gujarat system. Particularly, 220 KV S/C Asoj - Jambuva, 220 KV D/C Kasor Karamsad line, 220 KV D/C Ukai - Mota, 220 KV D/C Jhanor Haldarva and 220 KV D/C Navsari (PG) Navsari (GETCO) lines remains critically loaded. After commissioning 400/220 KV, 500 MVA ICT No. 4 at Kosamba, augmentation of transformation capacity at Ukai and establishing few lines (400 KV Ukai - Dastan line, 400 KV Kosamba - Jhanor line, 220 KV GSEG Sachin line, 220 Ichhapore Sachin line), the system reliability has significantly improved. Also, it helps to evacuate power of UTPS Unit No. 6 smoothly. Also, following transmission schemes which are under execution in the area shall be expedited: Additional 400/220 KV, 500 MVA ICT at Ukai and WTPS LILO of 220 KV Haldarva Zaghadia line at NTPC Jhanor PS 220 KV D/C Navsari Bhestan line LILO of one circuit of 220 KV Vyankatpura - Achhalia line (under construction) at Waghodia S/S from crossing point of 220 KV Asoj - Waghodia and 220 KV Waghodia Jambuva line to have 2 nd circuit of 220 KV Asoj Jambuva line. 220 KV D/C Vyankatpura Vadodara (PG) line. Interconnection of 220 KV D/C GSEG - Mota line (under construction) with existing 220 KV Kosamba Utran line: State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 44

53 C. Reliability improvement suggestions for Saurashtra - Kutch and North Gujarat Power System operation: The following EHV lines / elements remains critically loaded in West Gujarat Power System: KV D/C Amreli Savarkundla line KV Jetpur - Visavadar line KV Jetpur - Shapur line KV Jetpur Gondal line KV Hadala Kangasiyali line KV Jasdan Paliad line (In high wind scenario) KV Nyara Vikram & 132 KV Nyara Vajadi line /132 KV ICTs at STPS After commissioning 400/220 KV, 500 MVA ICT No. 4 at Amreli, 220 kv D/C Amreli - Visavadar & 220 KV D/C Visavadar - Timdi line and augmentation of transformation capacity at Gondal and Jamnagar, the system reliability and voltage profile has significantly improved. However, the integration of following transmission schemes / projects would strengthen the Power System in Suarashtra area: Augmentation of ICT at STPS LILO of 220 KV Jetpur - Sardargadh line at 220 KV Shapur S/S LILO of 220 KV Jetpur - Jamnagar line No. 2 at STPS Interconnection of 220 KV S/C Nyara - Jetpur line with 220 KV D/C Kangasiyali - Kalavad (under construction) so as to have LILO of 220 KV Nyara - Jetpur line at Kangasiyali S/S. Interconnection at interception point of 132 KV Sikka - Bhomiavadar line with one circuit of 132 KV D/C Bhatia - Khambhalia line to have one additional circuit of 132 KV Sikka - Bhatia line and one circuit of 132 KV Khambhalia - Bhomiavadar line. The following EHV lines / elements remains critically loaded in North Gujarat Power System: KV Vadavi Chhatral line /220 KV, 315 MVA ICTs at Kansari KV Karamsad Nadiad line The commissioning of 4 th ICT at Kansari, LILO of 132 KV Dhuvaran - Vatva at Mahemdavad S/S will improve reliability of North Gujarat Power System. To restrict loading on 220 KV Vadavi - Chhatral line, one circuit of 220 KV Gandhinagar - Chhatral line shall be made LILO at Vadavi S/S. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 45

54 D. Emerging need to establish connectivity at 132 KV S/S Randeja of TPL: Presently, load of the Capital city of Gujarat is catered from 132 KV D/C Randeja - Sabarmati TPS (TP AE Co) line. The Generating capacity of 422 MW of TPL AE Co Sabarmati is connected to GETCO Sabarmati substation subsequently to Ranasan substation of GETCO through 132 KV D/C Sabarmati Ranasan line. Around 500 MW demand is cater with the generation of TPL AE Co and import of around 150 MW power from GETCO grid through KV D/C Sabarmati Ranasan line. The 132 KV D/C Ranasan Sabarmati line is passing through dense city area of Ahmedabad which is prone to tripping of the line. The tripping of any one circuit of 132 KV Ranasan - Sabarmati line or 132 KV Sabarmati - AE Co line or ICT at Ranasan S/S may lead generation loss of around 300 MW & load loss of around 450 to 500 MW in case of failure of islanding scheme installed at AE Co OR around 150 MW load loss on account of activation of islanding scheme. Therefore, it is utmost necessary to plan connectivity at Randeja S/S of TPL from 132 KV Chiloda S/S of GETCO to form ring system. It will definitely enhance reliability of power supply to capital city of Gujarat and VIP areas of Ahmedabad. E. Emerging need for enhancement of transformation capacity at Sugen: At TPL Sugen, there are three Nos. 400/220 KV, 315 MVA ICT in service to cater the load of Surat City (around 550 to 650 MW). To comply CEA reliability criteria (N-1-1) and to enhance reliability of power supply to Surat city, there is a need of 4th ICT at Sugen S/S. F. Establishment of pump mode operation at SSP: It is well known fact that the pump mode operation of hydro plant plays a vital role in Power System Operation. During high wind injection, it is utmost necessary to store energy in the form of hydro and for maintaining under drawl within the specified limit and to curb over voltage during off-peak system condition. Also, the storage of energy in off peak hours and utilizing it in peak hours will help to optimize the cost of electricity. As Gujarat is one of the Renewable Energy rich States having installation of 6500 MW with no balancing facility and flexibility, the establishment of pump mode operation at SSP is emerged as principal and long term requirement of secure, reliable, flexible and economical Power System operation of the State. There are mainly two parts involved in project: 1. Construction of Garudeshwar weir 2. Upgradation of RBPH Units. The issue of establishment of pump mode operation at SSP is being repeatedly taken up in WRPC (Western Regional Power Committee), CEA, Mumbai by this office. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 46

55 G. Re-establishing of pump mode operation at Kadana HPS: The reestablishment of pump mode operation at KHPS is emerging need of Gujarat power system as Gujarat is having sizable portfolio of renewables. It will extend flexibility of picking generation as well as providing load within few minutes to the system. GSECL should come out with strong action plan for the reestablishing pump mode operation in time bound period. GSECL may apply for funding from PSDF for the said work. SLDC will extend all cooperation for taken up proposal in PSDF. H. SCADA up-gradation with Back-up SLDC SLDC is equipped with SCADA system in which Remote Terminal Units (RTU) are placed at substations / generating stations. RTU sends analog data like Active power, Reactive power, Frequency, Voltage and Digital data like breakers and isolators status. The system also provides EMS package. The New Alstom (now GE system) has been installed and working satisfactorily. It has more advance features and enhanced EMS package. The Alstom E-terra network model is having following modules; Power System Model Update State Estimation (SE) Bus Load Forecast (BLF) Transmission Loss Sensitivity Factors (TLSF) Contingency Analysis (CA) Optimal Power Flow (OPF) Transmission Line / Corridor Capability Monitor (TCM) Short Circuit Analysis (SCA) Transient / Dynamic Stability Analysis. At present, hierarchy of the system operation is set as, three Sub SLDCs looking after individual area functions and SLDC for the State as a whole. Maintaining same hierarchy, a back-up SLDC at Sub SLDC Gandhinagar has been established and operationalized. The mock drill for power system operation from back up SLDC is being arranged at regular interval to take over real time system operation in case of any contingency arising at main SLDC. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 47

56 I. Analytics Software from PMU data for System operation: SLDC has implemented WAMS project for system operation. Under this project, 118 Nos. of PMUs have been installed at 25 locations and 1500 phasors data of 500 feeder bays are received at SLDC. PDC is commissioned at SLDC for visualization of PMU data in operation activity. It is very useful tool for angle relationship between electrical area and important substations to access the system strength and various other features like df/dt, voltage magnitude etc. It is becoming very useful tool for post event analysis and system calibration. The PMU data are being used to design the intelligent software for system operation work. SLDC has executed MOU with IIT-Bombay for developing following three Analytics software from PMU data for system operation work under Research and Development project. 1. Online oscillation stability mode identification 2. Hybrid State Estimator 3. Dynamic Security Assessment (DSA) At Present, first analytics i.e. online oscillation stability mode identification has been installed and put in service. It had been observed that the Gujarat Power System is having oscillation with higher damping i.e. more than 5. The 2nd analytics i.e. HSE is also commissioned. The third analytics i.e. DSA is developed and will be commissioned as HSE is stabilized as output of the HSE will be used as input to the DSA with voltage stability. Optimum utilization of these analytics for exercising supervision of Gujarat power system will be through very advance tool available in the world which will be very much useful for secure grid operation and increase the confidence of the system operator. J. Establishment of Renewable Energy Management Centre (REMC): Gujarat is established one of RE reach State of India. As on , the installed capacity of the State in Wind farms is 5318 MW and 1230 MW in Solar. Also, it has emerged as highest potential for development renewable energy generation because of 1600 Km long costal line. SLDC has identified the necessity of RE generation forecasting for safe and reliable grid operation. SLDC Gujarat & PGCIL had worked together for the pilot project on RE generation forecasting. After gaining the experience from pilot project, SLDC had initiated process for hiring services from RE generation forecasting service provider. The service provider is finalized now. SLDC is getting more accurate forecasting of RE generation. At present, SLDC is getting day ahead, real time and weekly wind generation forecast for State as whole through online web based application from service provider. For the said service, SLDC is providing various static and variable data through FTP access. In turn, FSP is providing forecast in State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 48

57 96 blocks on online web based application, & FTP access. SLDC is also fetching real time data from each RE pooling stations. SLDC is continuously monitoring real time trend with forecasted generation. It is being regularly utilised for system operation and better forecasting & analysis purpose. Further under guideline of Ministry of Power, Government of India, PGCIL has initiated development of establishment of full fledge REMC on behalf of seven Nos. RE rich State. Gujarat is one of the State participating in the development. K. LVRT protection for Wind & Solar generators in Western Region - Compliance to order of the Hon ble CERC in petition No. 420/MP/2014 The LVRT-term is capturing the ability of a wind turbine to stay connected to the grid throughout a short mains voltage drop. It is essential that a wind park stay online in order to prevent major blackouts whenever there is a sudden dip in voltage. Hon ble CERC in its order in petition No. 420/MP/2014 dated directed that: 1. LVRT should be implemented for all wind turbines commissioned before and connected to voltage level of 66 KV and above except for stall type WEGs and having installed capacity equal to or more than 500 KW. 2. The Solar generators whose bidding process has not yet commenced i.e. NIT has not yet been issued on date of CERC order shall take necessary steps to implement LVRT in their generating stations. With regard to monitoring of the installation and performance of LVRT installed in existing WTGs, Hon ble CERC directed SLDCs to prepare quarterly reports and submit to RPCs. RPCs are directed to validate the report and deficiency and non-compliance to the Commission in accordance with the Law. SLDC - Gujarat has taken up the matter with all RE developers. L. Phasing out thermal capacity which are noncompliant to New Environmental Norms (issued by MoEF&CC) to be implemented w.e.f. 7th December 2017 A committee was constituted by Ministry of Power; Govt. of India on for preparing a phasing plan for implementation of new environmental norms issued by MoEF&CC in December The first meeting of committee was held on It was decided that the concern RPC shall prepare phasing of implementation plan in consultation with concerned power utilities at State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 49

58 regional level and POSOCO considering the power supply position. It was opinion that units in which ESP retrofitting/upgrade is implemented should be allowed to run at least 5 years from the date of completion of work. The 2 nd meeting of committee was held on It was informed that ESP upgradation is require to meet new environmental norms regarding SPM. It is necessary that FGD (Flue Gas Desulphurization) to be installed to comply with new SOx emission norms. The thermal units which have space for FGD installation does not require ESP upgradation as effective SPM reduction would be possible by FGD apart from control of SOx emissions. The total installed capacity of Gujarat State is 27,057 MW as on Amongst total capacity, the share of thermal capacity is 13,938 MW. The older units does not have space for FGD installation. For provision of FGD, generators shall have to invest capital expenditure as well as their auxiliary consumption would also increase. Therefore, it needs principal approval of regulator as well as procurer as there may be hike in fixed as well as variable cost. The plant load factor will be adversely affected due to high variable cost. Even if 25 years lifespan of thermal unit would consider for phasing out due to non-compliant of new environment norms, than around 3500 MW capacity would likely to be phased out for only in Gujarat State. In such condition, majority of State thermal units will be phased out from System. The Gujarat State is usually dependent on thermal capacity to meet the demand and to integrate renewable energy generation and its variation. Also, the developments of Intra State as well as Inter State transmission system have been planned considering full dispatch from the thermal units for catering the system demand. There is a 1000 MW on an average demand rise every year. The rate of increase in thermal / gas capacity is very slow compared to demand rise. The power procurement by the Discoms and development and strengthening of transmission network against capacity to be phased out shall take considerable time horizon. M. 5th amendment of IEGC Regarding implementation thereof Hon ble CERC vide its order dated 12th April, 2017 has notified 5th amendment in IEGC principal regulation of IEGC (Indian Electricity Grid Code) It is become effective from 1st May, As per the 5th amendment of IEGC, all Coal/lignite based thermal generating unit s of 200 MW State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 50

59 and above, Open Cycle Gas Turbine/Combined Cycle generating stations having gas turbines of capacity more than 50 MW each and all hydro units of 25 MW and above, which are synchronized with the grid, irrespective of their ownership, shall have their governors in operation at all times. Open Cycle Gas Turbine/Combined Cycle generating stations having gas turbines of capacity more than 50 MW each shall have their governors in operation with effect from There should not be any reduction in generation in case of improvement in grid frequency to a level below Hz. (For example, if grid frequency changes from 49.9 to Hz, or from to Hz there shall not be any reduction in generation). For any fall in grid frequency, generation from the unit should increase as per generator droop up to a maximum of 5% of the generation subject to ceiling limit of 105% of the MCR of the unit having regard to machine capability. All coal/lignite based thermal generating unit s of 200 MW and above, Open Cycle Gas Turbine / Combined Cycle generating stations having gas turbines of more than 50 MW each and all hydro unit s of 25 MW and above operating at or up to 100% of their MCR shall have the capability of (and shall not in any way be prevented from) instantaneously picking up to 105%, 105% and 110% of their MCR, respectively, when the frequency falls suddenly. After an increase in generation as above, a generating unit may ramp back to the original level at a rate of about one percent (1%) per minute, in case continued operation at the increased level is not sustainable. Any generating unit not complying with the above requirements shall be kept in operation (synchronized with the Regional grid) only after obtaining the permission of RLDC. For the purpose of ensuring primary response, RLDCs/SLDCs shall not schedule the generating station or unit (s) thereof beyond exbus generation corresponding to 100% of the Installed capacity of the generating station or unit (s) thereof. The generating station shall not resort to Valve Wide Open (VWO) operation of units whether running on full load or part load, and shall ensure that there is margin available for providing Governor act ion as primary response. In case of gas/liquid fuel based unit s, suitable adjustment in Installed Capacity should be made by RLDCs/SLDCs for scheduling in due consideration of prevailing ambient conditions of temperature and pressure vis-à-vis site ambient conditions on which installed capacity of the generating station or unit (s) thereof have been specified: Provided that scheduling of hydro stations shall not be reduced during high inflow period in order to avoid spillage: Provided further that the VWO margin shall not be used by RLDC to schedule Ancillary Services. To arrest sharp rise or drop of frequency, quick response from the generators through RGMO is indeed the inevitable requirement for safeguarding the grid. There are still several instances of sharp frequency excursions on daily basis. It has to be contained with the help of automatic primary response from the generating units. SLDC-Gujarat has been consistently pursuing with all the RGMO eligible generators in the State to implement RGMO as per the provisions of IEGC State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 51

60 SLDC has also taken up the matter with all State Generators having lignite based thermal generating units of 200 MW and above, Open Cycle Gas Turbine / Combined Cycle generating stations having gas turbines of capacity more than 50 MW each and all hydro unit s of 25 MW and above to take necessary actions regarding provision and operation of RGMO in their units. State Load Despatch Centre, Gujarat Energy Transmission Corporation Limited 52

61

62 Together, we can do great things. STATE LOAD DESPATCH CENTRE GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED 132 KV Gotri Sub Station Compound, Vadodara , Gujarat, INDIA Phone: , II Fax: II

ANNUAL REPORT

ANNUAL REPORT ANNUAL REPORT 2012-13 STATE LOAD DESPATCH CENTRE GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED From The Chief Engineer s Desk I am pleased to present the Annual Report of SLDC, Gujarat for the financial

More information

Gujarat Power Sector A Statistical Profile

Gujarat Power Sector A Statistical Profile Power Sector A Statistical Profile 6th Floor, GIFT ONE, Road 5C, Zone 5, GIFT CITY, Gandhinagar, 8 55. Ph.: +91796 Fax : +91796 5/55 Email : gerc@gercin.org Website : www.gercin.org 6th Floor, GIFT ONE,

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION Gandhinagar

GUJARAT ELECTRICITY REGULATORY COMMISSION Gandhinagar GUJARAT ELECTRICITY REGULATORY COMMISSION Gandhinagar Minutes of the 15 th Meeting of the Co-Ordination Forum held on 6 th August, 2014. The 15 th meeting of the Co-ordination Forum was held in the Conference

More information

Intra-State Availability Based Tariff (ABT)

Intra-State Availability Based Tariff (ABT) Intra-State Availability Based Tariff (ABT) What is ABT? 1. In Year 2000, the CERC revised the tariff structures of inter- state generators from drawal-based tariffs to ABT to discipline grid operations.

More information

The Electric Power System

The Electric Power System The Electric Power System INDIA Indian Power System 1 2 Basic facts Area:3.288 million km² Population:1.25 Billion Electricity consumers: 216 Million- (31.3.2013) Number of TSOs: 14- (31.3.2013) Numbe

More information

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR CASE NO. Filing of Petition for True Up of & Determination of Tariff for FY 2018-19 Under GERC MYT Regulations 2016 and Section 62 of the

More information

State Energy Account (SEA) based on Availability Based Tariff (ABT) for the Month of April 2010

State Energy Account (SEA) based on Availability Based Tariff (ABT) for the Month of April 2010 // / Gaujrat AenjIR ansmisn koporrexn ilim3ed GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED - rajy war p/e8` kend/ STATE LOAD DESPATCH CENTRE 132KV Substation Campus, Gotri, Vadodara-390021 Email: sldcabt@gebmail.com,tel:-

More information

DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED SURAT MYT Petition, True-up Petition Formats - Distribution & Retail Supply Sr. No. Title Reference 1 Aggr

DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED SURAT MYT Petition, True-up Petition Formats - Distribution & Retail Supply Sr. No. Title Reference 1 Aggr DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED Title Reference 1 Aggregate Revenue Requirement - Summary Sheet ARR-Summary 2 Customer Sales Forecast Form 1 3 Power Purchase Expenses Form 2 4 Summary of Operations

More information

Renewable Regulatory Fund (RRF) Mechanism : -

Renewable Regulatory Fund (RRF) Mechanism : - Renewable Regulatory Fund () Mechanism : - : Chronology of events Outline : Objectives at a glance : Approach : Applicability Role of different stakeholders Brief on CERC Orders on State Load Dispatch

More information

MINUTES OF THE 47 th SLCF MEETING HELD ON

MINUTES OF THE 47 th SLCF MEETING HELD ON MINUTES OF THE 47 th SLCF MEETING HELD ON 23.11.2016 Shri. Rafikul Islam, Chief Engineer (SLDC), WBSETCL & Chairperson, SLCF welcomed all the participant members to the 47 th SLCF meeting.. ITEM-1: CONFIRMATION

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY JULY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for e FY FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues

More information

Minutes of 18 th Meeting of the Coordination Forum held on at Conference Room, Circuit House, Rajkot. List of Participants

Minutes of 18 th Meeting of the Coordination Forum held on at Conference Room, Circuit House, Rajkot. List of Participants Minutes of 18 th Meeting of the Coordination Forum held on 25.01.2017 at Conference Room, Circuit House, Rajkot List of Participants Hon ble Chairman & Members: 1. Shri Anand Kumar, Chairman, GERC 2. Shri

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 219 FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

System Improvement Scheme(R&M) : FY

System Improvement Scheme(R&M) : FY GUJARAT ENERGY TRANSMISSION CORPORATION LTD System Improvement Scheme(R&M) : FY 2012-13 In GETCO network, large number of substations and lines are quite old, some of its equipments viz. CT s, PT s, Breakers,

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY MARCH 21 MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for uary FY 21 FINANCIAL HEALTH Standard and Poor s Bond Rating Current AA AA Budget Based Revenues

More information

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007 to: details Version: 2007 Technical Rules 1 16-Jan-08 2 16-Jan-08 3 29-Jan-08 Neerabup (two generating units - Units G11 and G12) Neerabup (two generating units - Units G11 and G12) Bluewaters Power Station

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for ember FY 219 FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues

More information

Operational Opportunities to Minimize Renewables Curtailments

Operational Opportunities to Minimize Renewables Curtailments Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY MAY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics for ch FY FINANCIAL HEALTH Standard and Poor s Bond Rating Current AA Target AA Budget Based Revenues and

More information

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1 TRANSMISSION CAPACITY ADDITION PROGRAMME DURING 2006-07 Sl. No. Contents Page No. 1 Introduction 1 2 Chapter 1 Transmission Capacity Additions During 2005-06 of 10 th plan period 3 Chapter 2 Construction

More information

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD AUSTIN ENERGY MONTHLY PERFORMANCE DASHBOARD A report highlighting key Austin Energy metrics FINANCIAL HEALTH Standard and Poor s Bond Rating Austin Energy Rating AA AA Budget Based Revenues and Expenses

More information

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676) P.O BOX 429, NUKU ALOFA, Tel: (676) 27-390 Fax: (676) 23-047 Email: jvanbrink@tongapower.to 22 October 2012 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Compliance Reporting

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

Appendix-C TARIFF FILING FORMS (TRANSMISSION) Page 34

Appendix-C TARIFF FILING FORMS (TRANSMISSION) Page 34 Appendix-C TARIFF FILING FORMS (TRANSMISSION) Page 34 INDEX Checklist of Forms and other information/ documents for tariff filing for Transmission System Form No. Tariff Filing Formats (Transmission) Tick

More information

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid India need regulations for energy storage to implement grid ancillary services

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007 KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.1/1/KSERC-2006/ Dated, Thiruvananthapuram 6 th August,2007 KSERC (Supply of Power from Captive Generating Plants to Distribution Licensees)

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

STATE LOAD DISPATCH CENTRES (SLDC)

STATE LOAD DISPATCH CENTRES (SLDC) ACTIVITIES OF SLDC STATE LOAD DISPATCH CENTRES (SLDC) **The State Load Despatch Centre:- As per section 33 of Electricity Act - 2003 (Central Act 36 of 2003), SLDC performs powers as defined below:- SLDC

More information

STATISTICS BOTSWANA ELECTRICITY GENERATION & DISTRIBUTION 2016/2 STATS BRIEF, FIRST QUARTER Copyrights Statistics Botswana 2016

STATISTICS BOTSWANA ELECTRICITY GENERATION & DISTRIBUTION 2016/2 STATS BRIEF, FIRST QUARTER Copyrights Statistics Botswana 2016 2016/2 ELECTRICITY GENERATION & DISTRIBUTION STATS BRIEF, FIRST QUARTER 2016 Copyrights Statistics Botswana 2016 Statistics Botswana. Private Bag 0024 Botswana Tel: (267) 367 1300. Fax: (267) 395 2201.

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India 26th March 2014 Infrastructure Revitalization in India 1 Outline Indian Power System Indian Grid - WAMS

More information

ELECTRICITY GENERATION AND DISTRIBUTION. Electricity Generation & Distribution Q2,

ELECTRICITY GENERATION AND DISTRIBUTION. Electricity Generation & Distribution Q2, Contact Statistician: Otsile Chelenyane Industry Statistics Unit Email: ochelenyane@statsbots.org.bw Tel: (+267) 367 1300; Ext. 333 ELECTRICITY GENERATION AND DISTRIBUTION Stats Brief, Quarter 2, 2018

More information

Exemptions currently in force

Exemptions currently in force exemptions by Western Power s currently in force Neerabup Units G11 & G12 3.3.3.1 (a) 16 Jan 2008 Ongoing Modified performance criteria: 0.8 Lagging 101.3 MVAr 0.9 Leading 68.5 MVAr Financial contribution

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

System Status Briefing

System Status Briefing System Status Briefing Phakamani Hadebe Interim Group Chief Executive 3 May 2018 Contents 1 Performance summary 2 Operational highlights 3 Generation performance 4 Distribution overview 5 Transmission

More information

ENERGY STORAGE. Integrating Renewables thanks to Consumers Flexibility. Energy Pool Développement SAS

ENERGY STORAGE. Integrating Renewables thanks to Consumers Flexibility. Energy Pool Développement SAS ENERGY STORAGE Integrating Renewables thanks to Consumers Flexibility 1 Introduction to Energy Pool The leading European Demand Response Operator YOUNG, FAST DEVELOPING COMPANY 2009 2010 2013 Company set

More information

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015 ADB Knowledge Partnership Week Hirokazu Yamaguchi May, 2015 TEPCO AT A GLANCE 1 THE 10 ELECTRIC POWER COMPANIES BY SERVICE AREA In Japan, 10 regional privately owned and managed General Electricity Utilities

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn Transmission Planning for Wind Energy Resources in the Eastern United States Dale Osborn Layered Design Typical utility planning Distribution delivery to loads Lower voltage transmission delivery from

More information

NJ Solar Market Update As of 6/30/15

NJ Solar Market Update As of 6/30/15 NJ Solar Market Update As of 6/30/ Prepared by Charlie Garrison July 17, 20 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 6/30/ is approximately 1,500.7 MW. Approximately

More information

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region 1.0 Applications for Connectivity and Long Term (Open) Access. Applications for grant of Connectivity

More information

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

NJ Solar Market Update

NJ Solar Market Update NJ Solar Market Update April 16, 20 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 3/31/ is approximately

More information

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107

More information

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng Smarter Network Storage UK first multi-purpose application of grid scale storage Dr. Panos Papadopoulos, PhD, CEng UK Power Networks GENERATION TRANSMISSION DISTRIBUTION SUPPLY INDUSTRIAL COMMERCIAL RESIDENTIAL

More information

INCREASING electrical network interconnection is

INCREASING electrical network interconnection is Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers

More information

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014 Policy & Regulatory Issues : Solar & Wind Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014 About Us Vision To develop a solution with low cost, high technology power generation & fulfill

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

Contact person: Pablo Taboada Mobile:

Contact person: Pablo Taboada   Mobile: Contact person: Pablo Taboada e-mail: ptaboada@aenor.es Mobile: 34 609015450 Génova 6 28004 Madrid. Spain Phone: 34 91 4326004 Fax: 34 91 3190581 CDM Executive Board RESPONSE TO REQUEST FOR REVIEW Request

More information

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options Electricity demand in France: a paradigm shift Electricity

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Strategy for Promoting Centers of Excellence (CoE) Activities

Strategy for Promoting Centers of Excellence (CoE) Activities Strategy for Promoting Centers of Excellence (CoE) Activities 1. The Background of the ITU Centers of Excellence (CoEs) Network: The Centres of Excellence project was established pursuant to resolutions

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

Guidelines for Solar Grid Power Projects

Guidelines for Solar Grid Power Projects Guidelines for Solar Grid Power Projects NTPC Ltd. NTPC Vidyut Vyapar Nigam Ltd. AGENDA 1 2 3 NTPC / NVVN at a glance Broad Guidelines for Selection of Solar Power Developers Elements of PPA NTPC Limited

More information

Indian Energy Exchange December For Public Use

Indian Energy Exchange December For Public Use Indian Energy Exchange December 2017 For Public Use In this presentation Installed RE Capacity Total Installed Capacity Renewable Installed Capacity RES 60157 Solar, 14,771 Hydro 44963 W to P; 114 Biopower;

More information

ANNEXURE: TARIFF SCHEDULE

ANNEXURE: TARIFF SCHEDULE ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2017 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

Smart initiatives in Transmission System. Dr Shekhar Kelapure PRDC, Bangalore

Smart initiatives in Transmission System. Dr Shekhar Kelapure PRDC, Bangalore Smart initiatives in Transmission System Dr Shekhar Kelapure PRDC, Bangalore Overview Introduction Objectives Challenges Technologies Conclusions Page #2 Why Smart Transmission Grids (STG)? Improve grid

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

National Electricity Market of Singapore: The Road to Liberalisation and Challenges Ahead

National Electricity Market of Singapore: The Road to Liberalisation and Challenges Ahead National Electricity Market of Singapore: The Road to Liberalisation and Challenges Ahead Yip Pak Ling Senior Vice President, Market Operations Energy Market Company 1 Agenda Singapore s reform programme

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Summer Reliability Assessment Report Electric Distribution Companies Perspective Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.

More information

Monthly Electrical Energy Overview May 2015

Monthly Electrical Energy Overview May 2015 215 Monthly Electrical Energy Overview 215 Launch of Central West Europe zone (CWE) Flow-Based market coupling on 2 -the threshold of 5, MW of exchange capacity was exceeded on 22. Fossil fuel thermal

More information

IEEE SESSION COMPUTER AIDED SMART POWER GRID

IEEE SESSION COMPUTER AIDED SMART POWER GRID IEEE SESSION COMPUTER AIDED SMART POWER GRID GEN_1 t.giras@ieee.org GEN_2 LOAD_1 LOAD_2 1 HIGH SMART GRID LEVEL LOW SMART POWER GRID TECHNOLOGY HISTORY MIT NETWORK ANALYZER 1940 ANALOG DISPATCH ACE SCADA

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

ELE-OS-E-2002 Start-up Shift Operation Engineer & Permit Coordinator PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS

ELE-OS-E-2002 Start-up Shift Operation Engineer & Permit Coordinator PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS 101934-ELE-OS-E-2002 Start-up Shift Operation Engineer & Permit Coordinator Holds a B. Sc. and a Diploma in Electrical Power & Machines Engineering. Has about 15 years hands-on experience working in operation,

More information

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008 Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008 2 Table of Contents Administrative Data...3 Network Performance...3 Reliability Measures

More information

Master Class on PVsyst Solar Project Designing Tool 7 th June 2013

Master Class on PVsyst Solar Project Designing Tool 7 th June 2013 10-06-2013 Master Class on PVsyst Solar Project Designing Tool 7 th June 2013 Objectives Fundamental aspects of PV system design Performance assessment of PV systems PVSyst simulation process PV array

More information

Net Consumption (GWh)

Net Consumption (GWh) GEORGIAN ENERGY MARKET Over the last 20 years Georgia s power market has evolved from a vertically integrated single buyer utility, to a competitive regional power market model. The Georgian wholesale

More information

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC)

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC) Ancillary Services Horace Horton Senior Market Trainer, Market Training, NYISO New York Market Orientation Course (NYMOC) June 5-8, 2018 Rensselaer, NY 12144 1 Ancillary Services SESSION OBJECTIVES: attendees

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates For Internal Use Only. FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority ,.,.;i')!i,:;;',;~~~. 'ffrff mm I Government of India ~ ~.I Ministry of Power 4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority III ~~~~~~I"1",~~1 ;J' :. r System Planning & Project Appraisal Division

More information

Economic & Steel Market Development in Japan

Economic & Steel Market Development in Japan 1 Economic & Steel Market Development in Japan 68 th OECD Steel Committee Paris May 6-7, 2010 The Japan Iron & Steel Federation 2 Macro-economic overview Steel Supply and Demand v v v Steel Production

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

December 2018 RenewableGenerations Monthly Report

December 2018 RenewableGenerations Monthly Report 2018 RenewableGenerations Monthly Report Ecosystem of Clean Energy Programs Contractor Training Webinar Table of Contents Solar Electric... 3 Solar Thermal Heating (Northern Nevada Gas Customers)... 5

More information

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

PHILIPPINE DISTRIBUTION CODE 2017 EDITION PHILIPPINE DISTRIBUTION CODE 2017 EDITION PDC 2017- Background Revised the PDC 2001 Starts of revision in 2010 April 18 and 24, 2012 conducted a series of expository presentation for Visayas and Mindanao

More information

MARKET RATES UPDATE Paula Gold-Williams Cory Kuchinsky

MARKET RATES UPDATE Paula Gold-Williams Cory Kuchinsky MARKET RATES UPDATE I N T R O D U C T I O N BY: Paula Gold-Williams President & Chief Executive Officer (CEO) P R E S E N T E D BY: Cory Kuchinsky Interim Vice President, Financial Services September 24,

More information

Sound Transit Operations July 2016 Service Performance Report. Ridership

Sound Transit Operations July 2016 Service Performance Report. Ridership Ridership Total Boardings by Mode Mode Jul-15 Jul-16 % YTD-15 YTD-16 % ST Express 1,618,779 1,545,852-4.5% 10,803,486 10,774,063-0.3% Sounder 333,000 323,233-2.9% 2,176,914 2,423,058 11.3% Tacoma Link

More information

IMM Quarterly Report: Summer 2017

IMM Quarterly Report: Summer 2017 IMM Quarterly Report: Summer 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics September 19, 2017 Highlights and Findings: Summer 2017 The MISO markets performed competitively

More information

Monthly Operating Report. February 2018

Monthly Operating Report. February 2018 Monthly Operating Report February 2018 February overview» For the month of February 2018 Contact recorded: Electricity and gas sales of 534 GWh (February 20: 551 GWh) Netback of $82.16/MWh (February 20:

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Department of Market Quality and Renewable Integration November 2016

Department of Market Quality and Renewable Integration November 2016 Energy Imbalance Market March 23 June 3, 216 Available Balancing Capacity Report November 1, 216 California ISO Department of Market Quality and Renewable Integration California ISO i TABLE OF CONTENTS

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Pilbara Undergrounding Program Smart Grid Opportunities November 2009 DMS#

Pilbara Undergrounding Program Smart Grid Opportunities November 2009 DMS# Pilbara Undergrounding Program Smart Grid Opportunities November 2009 1 Smart Grid? A Smart Grid is an electricity network that can intelligently integrate the actions of all users connected to it generators,

More information

Indian Power System Framework

Indian Power System Framework R P SASMAL 1 ST JUNE 2016 Indian Power System Framework Electricity - A Concurrent Subject Both Central & State Govt. are responsible for overall development of Power Sector Generators Central Level Central

More information

Details of concern person for future communication/clarification. Mobile No. Address

Details of concern person for future communication/clarification. Mobile No.  Address 114 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4] GENERATION OF ELECTRICITY FORMAT-1 PERIODICITY-ANNUAL DATA OF YEAR 20 20. Submission by 30th June NAME AND ADDRESS OF UTILITY: Sl. No. (A) Name

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

Transmission System Operators in the Interplay between Physics and Market

Transmission System Operators in the Interplay between Physics and Market Session 02: Large Scale Renewables Integration and the Changing Roles of TSO and DSO Companies Transmission System Operators in the Interplay between Physics and Market DI Mag.(FH) Gerhard Christiner Chief

More information