BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR

Size: px
Start display at page:

Download "BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR"

Transcription

1 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR CASE NO. Filing of Petition for True Up of & Determination of Tariff for FY Under GERC MYT Regulations 2016 and Section 62 of the Electricity Act, Filed by:- Gujarat Energy Transmission Corporation Limited Regd. Office: Vidyut Bhavan, Race Course Circle, Vadodara

2 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR Filing No: Case No: IN THE MATTER OF AND Filing of Petition for True Up of and Determination of Tariff for FY for GETCO under GERC MYT Regulations 2016 and Section 62 of the Electricity Act, IN THE MATTER OF Gujarat Energy Transmission Corporation Limited, Sardar Patel Vidyut Bhavan, Race Course, Vadodara PETITIONER THE PETITIONER ABOVE NAMED RESPECTFULLY SUBMITS Gujarat Energy Transmission Corporation Limited Page 2

3 TABLE OF CONTENTS SECTION 1. INTRODUCTION PREAMBLE INTRODUCTION MULTI-YEAR TARIFF REGULATIONS:... 7 SECTION 2. EXECUTIVE SUMMARY PREAMBLE TRUE UP FOR NET RECOVERY TRANSMISSION TARIFF FOR FY SECTION 3. TRUE UP OF PREAMBLE PRINCIPLES FOR TRUE UP FOR EXISTING CAPACITY OF GETCO IN CAPITAL EXPENDITURE FOR FUNDING OF CAPEX ADDITION TO TRANSMISSION LINES AND SUBSTATIONS AVAILABILITY OF TRANSMISSION SYSTEM TRANSMISSION LOSSES NETWORK OUTAGES & FAULTS LOADING OF TRANSMISSION SYSTEM ANNUAL FIXED COST FOR CATEGORIZATION OF HEADS OF EXPENSES OPERATION & MAINTENANCE EXPENDITURE FOR DEPRECIATION FOR INTEREST & FINANCE CHARGES FOR RETURN ON EQUITY FOR INTEREST ON WORKING CAPITAL FOR INCOME TAX FOR CONTRIBUTION TO CONTINGENCY RESERVE FOR INCENTIVE ON TRANSMISSION AVAILABILITY REVENUE FROM OTHER INCOME AGGREGATE REVENUE REQUIREMENT FOR SHARING OF GAINS & LOSSES REVENUE GAP FOR DETERMINATION OF TRANSMISSION TARIFF FOR FY REACTIVE ENERGY CHARGES FOR SOLAR ENERGY PROJECTS SECTION 4. COMPLIANCE OF DIRECTIVES PREAMBLE COMPLIANCE OF DIRECTIVES SECTION 5. PRAYER ANNEXURE A: REPORT ON TRANSMISSION PLANNING TO AVOID TRANSMISSION CONSTRAINTS IN GETCO SYSTEM ANNEXURE B: 2ND QUARTER (FY ) REPORT ON LOADING OF SUBSTATION. 51 TARIFF FILING FORMATS Gujarat Energy Transmission Corporation Limited Page 3

4 LIST OF TABLES Table 1 : True up for... 8 Table 2 : Summary of Controllable & Uncontrollable factors... 9 Table 3 : Net Recovery for Table 4: ARR for FY Table 5 : Transmission tariff for FY Table 6 : Existing Capacity of GETCO in Table 7 : Capital expenditure during Table 8 : Funding of CAPEX Table 9 : Network addition of GETCO during Table 10 : Transmission losses of GETCO for Table 11 : Network outages & faults for GETCO for Table 12 : Summary of loading of transmission system for Table 13 : Transmission lines & No. of bays for Table 14 : O&M cost (Normative / Actuals) for Table 15 : Net O&M cost (As per audited accounts) for Table 16 : Gains/ (losses) from O&M expenses Table 17 : Depreciation for Table 18 : Gain/ (losses) from Depreciation Table 19 : Interest & Finance charges for Table 20 : Gains/ (losses) from Interest & finance charges Table 21 : Return on Equity for Table 22 : Gains/ (losses) from Return on Equity Table 23 : Interest on working capital for Table 24 : Gains/ (losses) on Interest on working capital Table 25 : Gains/ (losses) on Income Tax Table 26 : Gains/ (losses) from Contingency Reserves Table 27 : Incentive for higher availability Table 28 : Gains/ (losses) on Incentive Table 29 : Revenue from other income Table 30 : Other income for Table 31 : Aggregate revenue requirement for Table 32 : Net gains/ (losses) for Table 33 : Revenue gap for Table 34: ARR for FY Table 35: Projected loading in MW for FY Table 36 : Transmission tariff for FY Gujarat Energy Transmission Corporation Limited Page 4

5 ABBREVIATIONS 1. A&G Administrative & General 2. AC Alternate Current 3. ARR Aggregate Revenue Requirement 4. CAPEX Capital Expenditure 5. Ckt. km Circuit Kilometer 6. FY Financial Year 7. GEB Gujarat Electricity Board 8. GERC Gujarat Electricity Regulatory Commission 9. GETCO Gujarat Energy Transmission Corporation Limited 10. GoG Government of Gujarat 11. GSECL Gujarat State Electricity Corporation Limited 12. GUVNL Gujarat Urja Vikas Nigam Limited 13. HVDC High Voltage Direct Current 14. KV Kilo Volt 15. MVA Mega Volt Ampere 16. MW Mega Watt 17. MYT Multi Year Tariff 18. O&M Operation & Maintenance 19. R&M Renovation & Modernization 20. S/s Sub Station Gujarat Energy Transmission Corporation Limited Page 5

6 SECTION 1. INTRODUCTION 1.1. PREAMBLE This section presents the background and reasons for filing of this Petition INTRODUCTION The Government of Gujarat (hereinafter referred to as GoG ) notified the Gujarat Electricity Industry (Reorganization and Regulation) Act 2003 (hereinafter called as Act ) in May 2003 for the reorganization of the entire power sector in the State of Gujarat Pursuant to the above, erstwhile GEB was divided into seven different entities where in all its transmission related assets were transferred to the newly created entity Gujarat Energy Transmission Corporation Ltd (hereinafter referred as GETCO ) As per Government of Gujarat s notification no GHU GEB K, GETCO has been notified as the State Transmission Utility with effect from 1 st June The Gujarat Electricity Regulatory Commission (hereinafter referred to as GERC or the Commission ), is an independent statutory body constituted under the provisions of the Electricity Regulatory Commissions (ERC) Act, 1998 and is currently under purview of the Electricity Act, GERC is vested with the authority of regulating the power sector in the State inter alia including determination of Tariff for electricity consumers Hon ble Commission notified the Gujarat Electricity Regulatory Commission (Multi Year Tariff) Regulations, 2011 ( GERC MYT Regulations, 2011 ). Based on the petition filed by GETCO, the Hon ble Commission issued MYT order on 31 st March, 2011 for determining the ARR for the Second Control Period i.e. FY to FY in line with provisions outlined in the GERC (MYT) Regulations, Further, the Hon ble Commission issued order for mid-term review of Business plan dated 29 th April, 2014 for modification of the ARR for the remaining year of the control period for GETCO i.e. for FY to FY GERC order dated 02 nd December, 2015 on the Suo-Motu Petition No. 1534/2015 states the following: We decide that the approved ARR of FY of the licensees / generating companies concerned be considered as provisional ARR of the licensees / generating companies for. We also decide that the licensees / generating companies shall file the ARR for FY based on the MYT Regulations for to FY and the true up for the same shall also be governed as per the new MYT Regulations Hon ble Commission notified the Gujarat Electricity Regulatory Commission (Multi- Year Tariff) Regulations, 2016 ( GERC MYT Regulations, 2016 ) on 29 th March 2016 and shall be applicable for determination of tariff in all cases covered under the Gujarat Energy Transmission Corporation Limited Page 6

7 regulations from 1 st April, 2016 onwards. Based on these Regulations, the Commission issued the Multi-Year Tariff Order dated 31 st March, 2017 in Petition No of 2016 wherein Truing up of ARR for FY and determination of final ARR of and approval of Multi-Year ARR for the Third Control Period to FY was carried out MULTI-YEAR TARIFF REGULATIONS: The key provisions of the Multi-Year Tariff Regulations, 2016 is reproduced below: Section 3.1 of the GERC MYT Regulations, 2016: 3.1: The Commission shall determine tariff within the Multi-Year Tariff framework, for all matters for which the Commission has jurisdiction under the Act, including in the following cases: i. Supply of electricity by a Generating Company to a Distribution Licensee.. ii. Intra-State transmission of electricity; iii. SLDC Fees and Charges; iv. Intra-State Wheeling of electricity; v. Retail supply of electricity Section 17 of the GERC MYT Regulations, 2016: 17.2 The filing for the Control Period under these Regulations shall be as under: b) From the second year of the Control Period and onwards, the Petition shall comprise of: i. Truing Up for and onwards to be carried out under Gujarat Electricity Regulatory Commission (Multi-Year Tariff) Regulations, 2016; ii. Revenue from the sale of power at existing tariffs and charges for the ensuing year (viz. FY ); iii. Revenue gap or revenue surplus for the ensuing year (viz. FY ) calculated based on Aggregate Revenue Requirement approved in the MYT Order and truing up for the previous year; iv. Application for determination of tariff for the ensuing year (viz. FY ) Under section 62 of the Electricity Act, 2003 and GERC MYT Regulations, 2016, GETCO is filing its Petition for True Up for and Determination of Tariff for FY to the Hon ble Commission for approval. Gujarat Energy Transmission Corporation Limited Page 7

8 SECTION 2. EXECUTIVE SUMMARY 2.1. PREAMBLE This section highlights the summary of Petition for True Up for and Determination of Tariff for FY TRUE UP FOR GETCO has worked out its Aggregate Revenue Requirement (ARR) for as a part of the True Up for. GETCO has presented the actual cost components based on audited annual accounts for The detailed comparison of various cost components with the values approved by Sr. No. the Hon ble Commission has been presented in Chapter of True up of. A summary of the proposed ARR for Truing-up of compared with the approved Final ARR for in Multi-Year Tariff Order dated 31 st March, 2017 is presented in the table given below. Table 1 : True up for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 Operation & Maintenance Expenses 1, , (14.04) 2 Depreciation (20.88) 3 Interest & Finance Charges Interest on Working Capital (0.07) 5 Return on Equity (3.64) 6 Contingency Reserve Total Fixed Costs 3, , Less: Expenses Capitalised (15.62) 8 Add: Income Tax Total Transmission Charges 3, , Less: Other Income Aggregate Revenue Requirement 3, , Add: Incentive for target availability (27.43) 13 Total Aggregate Revenue Requirement 3, , In line with the provisions of the GERC MYT Regulations, 2016, GETCO has computed the gains and losses on account of controllable and uncontrollable parameters and its proposed sharing mechanism. Summary of the deviation allocation to Controllable & Uncontrollable factors is outlined as per the table below: Gujarat Energy Transmission Corporation Limited Page 8

9 Sr. No. Petition for True Up for and Determination of Tariff for FY Table 2 : Summary of Controllable & Uncontrollable factors Particulars (Approved) (Normative/ Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Operation & Maintenance Expenses 1, , (4.76) (9.28) 2 Depreciation (20.88) 3 Interest & Finance Charges Interest on Working Capital (0.07) 5 Return on Equity (3.64) 6 Contingency Reserve ARR (1 to 6) 3, , (4.76) Less : Expense Capitalised (15.62) 9 Less : Other Income Add: incentive for target availibility (27.43) 11 Add: Income Tax Total ARR ( ) 3, , (4.76) Net Gains / Losses on account of Controllable/ Uncontrollable factor (4.76) Gain/ (Loss) on account of Controllable factor to be passed on to Consumer (1/3 x Sr. No. 13) (1.59) 15 Gain/(Loss) on account of Uncontrollable factor to be passed on to Consumer The net revenue gap recoverable from the Open Access Beneficiaries has been computed and the same would be recovered through the annual transmission charges in the FY NET RECOVERY It is submitted that GETCO has recovered the provisional ARR for approved vide Order dated 31 st March, 2016 in Petition No of 2016 (which was same as the ARR of FY approved by the Commission). Subsequently, the Commission approved the final ARR for GETCO for vide Order dated 31 st March, 2017 in Petition No of Due to this, there is shortfall in the recovery of approved ARR for which is computed in this Petition and sought to be recovered through revised ARR for FY Net recovery of GETCO for the is as per the table given below. The net recovery will be adjusted in the tariff determination for FY ; Gujarat Energy Transmission Corporation Limited Page 9

10 Table 3 : Net Recovery for Rs. Crores Sr. No. Particulars Amount 1 Provisional approved ARR for vide Order dated 31st March, 2016 in 2, Petition No of A 2 Final approved ARR of in MYT Order dated 31st March, 2017 in Petition No. 3, of B 3 Under-recovery of ARR for (A-B) (285.59) 4 Add: Impact of consequential order passed by Commission on and pursuant to APTEL Judgment in Appeal No. 201 of Gain / (Loss) on account of Uncontrollable factor to be passed on to Beneficiaries for FY Gain / (Loss) on account of Controllable factor to be passed on to Beneficiaries (1/3rd of Total Gain / (Loss) for 7 Total Gain/ (Loss) of the true up to be addresesd in the determination of tariff for FY ( ) (10.99) (1.59) (264.90) GETCO requests the Hon ble Commission to approve the True-up for and allow it to pass on the (gap)/surplus on the approved tariff for FY TRANSMISSION TARIFF FOR FY In accordance with provisions of the GERC MYT Regulations, 2016, ARR for FY as determined in Tariff Order dated 31 st March, 2017 is as follows: Table 4: Approved ARR for FY Rs. Crores Sr. No. Particulars FY (Approved) 1 Operation & Maintenance Expenses 1, Depreciation 1, Interest & Finance Charges Interest on Working Capital Return on Equity Contingency Reserve - 7 Total Fixed Costs Add: Provision for Tax Less: Expenses Capitalised Total Transmission Charges 4, Less: Other Income Add: Incentive for target availability - 13 Aggregate Revenue Requirement 3, GETCO has calculated the Transmission tariff for FY by adding net recovery for in the approved ARR for FY as mentioned above. Further, the MW allocation has been taken based on the projected loading of the transmission system for the FY The Transmission tariff of GETCO for FY after applying the gap of is as follows; Gujarat Energy Transmission Corporation Limited Page 10

11 Table 5 : Transmission tariff for FY Rs. Crores Sr. No. Particulars FY Aggregate Revenue Requirement approved in Tariff Order for FY , Add revenue Gap / (Surplus) for for FY computed in this petition ARR after considering Gaps of true-up for FY (1+2) 4, Total MW allocation 25,728 5 Transmission tariff Rs/ MW/ day 4, Recovery of Short-term Transmission Charges: As per sharing of inter-state transmission charges and losses Regulations 2010 and its amendments notified by the Hon ble CERC, for all types of short-term transaction, transmission charges are payable on per kwh basis i.e. transmission charges are applied on transaction through power exchange/ collective or bilateral. However, Hon ble Commission in the Order dated 31 st March, 2017 has allowed recovery of transmission charges on per kwh basis for power exchange/ collective short-term transaction and per MW/day basis for bilateral short-term transaction. This is leading to different treatment for two transactions done under short-term open access. To make the recovery of short-term transaction charges in line with CERC Regulations, it is proposed to allow recovery of transmission charges on per kwh basis for all types of short-term transactions irrespective of whether short-term transaction is done through power exchange or under bilateral arrangement GETCO has calculated the revised ARR for FY as Rs. 4, Crore. In MYT Order dated 31 st March, 2017, The Hon ble Commission has decided the methodology for working of short-term transmission charges on per kwh basis and worked out short-term charges for FY Considering the same methodology as adopted by the Hon ble Commission in the MYT Order dated 31 st March, 2017, GETCO has considered the Energy input of 89,632 MUs of Transmission System as per energy accounting of SLDC corresponding to Transmission Capacity of 21,547 MW during. Based on the actuals of the total estimated wheeled units during FY works out as 107,023 MUs on proportionate basis considering the Transmission Loading Capacity of 25,728 MW during FY As per the above methodology, transmission charges payable in the case of all types of short-term transactions works out to; TC (Rs/kWh) = Rs. 4, Crore/ 107,023 Mus = Ps./ kwh Gujarat Energy Transmission Corporation Limited Page 11

12 SECTION 3. TRUE UP OF 3.1. PREAMBLE This section outlines performance of GETCO for. In line with the provisions of the GERC MYT Regulations, 2016, GETCO hereby submits the True up Petition comparing the actual performance of GETCO during with the forecast approved by the Hon ble Commission vide Multi-Year Tariff Order dated 31 st March, PRINCIPLES FOR TRUE UP FOR As per GERC MYT Regulations, 2016, the Hon ble Commission shall undertake the True Up of the licensee for the past financial year i.e. based on the actual performance of the licensee in that year with the approved forecast for such year In line with the provisions under GERC MYT Regulations, 2016, GETCO is furnishing the information in the form of present petition to the Hon ble Commission, together with the audited accounts for and other details as the Hon ble Commission may require to assess the reasons for variation in financial performance from the approved forecast of Aggregate Revenue Requirement for FY Accordingly, actual data for revenue and gap for are given in the following sections of this chapter For the purpose of True Up, all the expense heads have been categorized into Controllable and Uncontrollable factors as shown in the subsequent sections. Head wise comparison of the expenses has been made between the values approved by the Hon ble Commission vide MYT Order dated 31 st March, 2017 under Aggregate Revenue Requirement for and the actual figures for various expenditures for EXISTING CAPACITY OF GETCO IN The capacity of GETCO network as on 31 st March 2017 was 101,259 MVA which is 10.61% higher than the capacity (91,544 MVA) as on 31 st March GETCO has shown capacity addition of ( 9,715 MVA) during the in comparison to the FY (11,431 MVA). In addition, GETCO is undertaking rapid augmentation of transmission network to cater to the power requirement across the State The table below summarizes the voltage level wise capacity of GETCO system i.e. as on 31 st March, Gujarat Energy Transmission Corporation Limited Page 12

13 Table 6 : Existing Capacity of GETCO in Voltage class (Capacity in MVA) Sr.No. Name of Circle 400 KV (MVA) (MVA) 132 KV (MVA) 66 KV (MVA) TOTAL (MVA) 1 Amreli 945 2, ,090 7,628 2 Anjar 945 1, ,851 5,736 3 Bharuch 1,445 2, ,488 6,853 4 Gondal 2,390 2,960 1,025 4,578 10,953 5 Himatnagar 1,500 1, ,229 6,929 6 Jambuva 1,815 2,750 1,940 4,247 10,752 7 Jamnagar - 1, ,525 4,373 8 Junagadh - 2, ,680 6,330 9 Mehsana 1,260 2, ,758 6, Nadiad 945 2,820 1,495 4,225 9, Navsari - 3, ,208 9, Surendranagar 1,575 3, ,670 8, Palanpur 2,130 2, ,913 7,835 Total 14,950 31,010 8,838 46, , CAPITAL EXPENDITURE FOR In order to ensure unrestricted power flow across the State of Gujarat and maintain an efficient transmission system, GETCO had spent significant amount of capital expenditure for construction of transmission lines and substations during FY GETCO had projected a total capital expenditure of Rs. 2,530 Crores in the MYT Order dated 31 st March, 2017 and incurred an actual expenditure of Rs. 2, Crores during. GETCO has incurred this expenditure in construction of new substation and transmission lines required for strengthening of the transmission network of GETCO. The comparison of CAPEX approved by the Commission and actually incurred during are shown below: Table 7 : Capital expenditure during Rs. Crores Particulars Approved Actual 765 KV Lines KV Substations KV Lines Substation Lines KV Substation KV Lines KV Substation KV Lines Bus Reactor & SVC 40 - Capacitor Banks Total of New Projects 1,707 1, R&M Renovation and Modernization Augmentation of Sub-station/ Lines City Development Plan and ASSIDE Scheme Total R&M RTU Total 2, , Gujarat Energy Transmission Corporation Limited Page 13

14 3.5. FUNDING OF CAPEX Petition for True Up for and Determination of Tariff for FY The capital expenditure has been funded through grants, equity and the remaining expenditure incurred during has been funded through debt. The breakup of funding of capital expenditure during is mentioned below. Table 8 : Funding of CAPEX Rs in Crores Sr. No. Particulars (Actual) A CAPEX for the Year 2, B Capitalization 2, C Grants D Net Capitalization (B-C) 1, E Debt (70% of D) 1, F Equity (30% of D) ADDITION TO TRANSMISSION LINES AND SUBSTATIONS The details of Ckt. Km addition of transmission lines and substations during FY are as follows: Table 9 : Network addition of GETCO during Voltage Class 3.7. AVAILABILITY OF TRANSMISSION SYSTEM Substations (No.) Transmission Lines (Ckt. Km.) 400 KV KV KV 98 1,264 Total 100 3, In, GETCO has maintained its entire transmission system at exceptionally high level and achieved system availability of the tune of 99.40% (More than the benchmark specified in the Regulations for recovery of full transmission charges i.e. 98%) TRANSMISSION LOSSES The actual transmission losses for are as shown in the following table: Table 10 : Transmission losses of GETCO for Particulars (Actual - as per SLDC) (Actual - as per GETCO) Transmission Losses 3.88% 3.85% 3.9. NETWORK OUTAGES & FAULTS For any transmission system, network outages & faults are the true performance indicators of the power system condition. In order to have an efficient transmission system, GETCO is taking up planned shut downs for periodic maintenance of its transmission lines and substations. Gujarat Energy Transmission Corporation Limited Page 14

15 The following table indicates the network outages and faults in the GETCO system for the. It may be worth noting that GETCO has been able to perform well in maintaining the system to its best level. Table 11 : Network outages & faults for GETCO for Network Component Type of Fault Unit Monthly average for the PSD Hrs/100km KV TT Nos/100km SF Nos/100km ESD Nos/100km PSD Hrs/100km KV TT Nos/100km SF Nos/100km ESD Nos/100km PSD Hrs/100km KV TT Nos/100km SF Nos/100km ESD Nos/100km PSD Hrs/100km KV TT Nos/100km SF Nos/100km ESD Nos/100km Wherein PSD: Planned shutdown TT: Transient tripping SF: Sustained fault ESD: Emergency shut down LOADING OF TRANSMISSION SYSTEM The actual loading of transmission system of GETCO for is given in the table below. Gujarat Energy Transmission Corporation Limited Page 15

16 Table 12 : Loading of transmission system for Sr. No. Station Rated Capacity Aux Cons (%) Gujarat Share Transmission Losses (%) Total MW on GETCO System A GSECL Plants 1 Ukai TPS Unit 1 to Ukai TPS Unit Ukai Hydro PS Gandhinagar TPS Unit 3 to Gandhinagar TPS Unit Wanakbori TPS Unit 1 to 6 1, ,260 1,147 7 Wanakbori TPS Unit Sikka TPS Unit No.1 & Sikka TPS Unit No.3 & Kutch Lignite TPS Kadana Hydro Utran CCPP Extension Dhuvaran Gas Based - Stage-I Dhuvaran Gas Based - Stage-II Dhuvaran Extension CCPP Total GSECL Plants 5,996 5,559 B IPPs 1 GIPCL Stage-I GPEC (CLP) GIPCL-SLPP GIPCL-SLPP Extension GSEG GPPC Pipavav GMDC - Akrimota Adani, Mundra - Bid-01 (Unit-1 to 4) 1,320 1,000 1,000 9 Adani, Mundra - Bid-02 (Unit - 5 & 6) 1,320 1,000 1, Essar, Vadinar (Salaya) 1,200 1,000 1, ACB Limited Siddhivinayak Glass Industries, Hazira OPGS Power, Bhadreshwar GSEG Extension Hazira BECL, Padva, Bhavnagar (Unit - 1 & 2) Total IPPs Plant 6,777 6,555 C Share from Central Sector 1 NPC - Tarapur 1& NPC - Kakrapar 1& NPC - Tarapur 3&4 1, NTPC - Korba 2, NTPC - Korba Unit NTPC - Vindhyachal-I 1, NTPC - Vindhyachal-II 1, NTPC - Vindhyachal-III 1, NTPC - Vindhyachal-IV 1, NTPC - Vindhyachal-V NTPC - Kawas NTPC - Jhanor NTPC - Kahalgaon 1, NTPC - SIPAT-I 1, NTPC - SIPAT-II 1, CGPL, Mundra (TATA UMPP) 4,150 1, , SSNNL - Hydro 1, NTPC Mauda STPP Stage - 1 1, NTPC Mauda STPP Stage - 2 (Unit 1) Total Central Sector Share 5,885 5,347 TOTAL 18,659 17,460 CPP Wheeling Wind Power capacity 5,318 5,318 Solar Power capacity 1,230 1,230 Bio-Mass Power capacity Mini Hydro 9 9 Total (MW) 25,484 24, ANNUAL FIXED COST FOR As per the GERC MYT Regulations, 2016, the fixed cost has been computed under following heads: Operation and Maintenance Expenses Depreciation Gujarat Energy Transmission Corporation Limited Page 16

17 Interest and Finance Charges Return on Equity Interest on Working Capital Contribution to Contingency Reserve Net Aggregate Revenue Requirement has been computed with addition of actual tax paid and incentive for achieving target availability and after deduction of Other Income & Expenses capitalized of GETCO For the purpose of True Up, all the heads mentioned above has been categorized into Controllable or Uncontrollable factors in line with provisions of GERC MYT Regulations, 2016, as discussed in subsequent sections of the petition. A head wise comparison has been made between the values approved by the Hon ble Commission and actuals to arrive at the revenue gap/surplus for the CATEGORIZATION OF HEADS OF EXPENSES As per provision of section 22 of GERC MYT Regulations, 2016, expenses have been categorized into 2 factors viz. (1) Controllable (Under the control of the petitioner) & (2) Uncontrollable (Not under control of petitioner). The Hon ble Commission vide section 23 and 24 of its GERC MYT Regulations, 2016 has defined the mechanism for sharing of gain/ losses arising on account of uncontrollable & controllable factors respectively The details of the expenses categorized into the above factors have been covered in the subsequent sections Based on the existing practice for allocation & as approved by the Commission in previous years true-ups, all the items of expenditure for have been classified as either controllable or uncontrollable. Accordingly, the gains/ losses attributed to such controllable & uncontrollable factors have been determined in the subsequent sections GETCO has worked out its Aggregate Revenue Requirement (ARR) for as a part of the True Up for. GETCO has presented the actual cost components based on audited annual accounts for OPERATION & MAINTENANCE EXPENDITURE FOR As per GERC MYT Regulations, 2016, O&M Expenses shall be computed based on the norms provided in clause of the Regulations. As per the norms, the O&M expenses shall be computed based on the no. of bays and transmission line length (in Ckt.km). Accordingly, the normative O&M expense for the is given as below: Gujarat Energy Transmission Corporation Limited Page 17

18 Table 13 : Transmission lines & No. of bays for Sr. No. Particulars Reference Approved in MYT Order Normative Actual 1 Based on no. of Bays - Opening no. of Bays No. 11,811 11,811 - Addition during the year No Average no. of bays during the year No. 12,095 12,203 2 Based on no. of Transmission lines - Opening Balance ckt km 54,605 54,605 - Addition during the year ckt km 2,080 2,424 - Average lines' length during the year ckt km 55,645 55,817 Sr. No. Table 14 : O&M cost (Normative / Actuals) for Particulars Reference (Approved) Rs. Crores (Normative/ Actual) 1 Based on no. of Bays - Average no. of bays during the year No. 12, , O&M exp norm per Bay Rs.lacs Total O&M Expenses based on no. of bays Rs. crores Based on no. of Transmission lines - Average lines' length during the year No. 55, , O&M exp norm per ckt km Rs.lacs Total O&M Expenses based on no. of ckt km Rs. crores Total O&M Expenses (as per norms) Rs. crores 1, , GETCO has computed O&M expenses by considering the actual employee costs, R&M expenses & A&G expenses for the for working of gain/ (loss). The O&M expenses as per audited annual accounts are as shown in the table below: Table 15 : O&M cost (As per audited accounts) for Rs. Crores Sr. No. Particulars Actual 1 Employee Costs R&M Expenses A&G Expenses Operation & Maintenance Expenses 1, O&M expenses are controllable in nature, under Regulation 22 of GERC MYT Regulations, However, as per the methodology adopted by the Hon ble Commission, the variance in the O&M expenses as approved in MYT Order and the normative O&M expense as per actual performance during the year is considered as uncontrollable and variation in the normative O&M expenses and actual as per audited accounts is considered as controllable. The O&M expenses and gains / (losses) considered in the Truing up for are summarized in Table below: Gujarat Energy Transmission Corporation Limited Page 18

19 Sr. No. Petition for True Up for and Determination of Tariff for FY Particulars Table 16 : Gains/ (losses) from O&M expenses (Approved) (Normative Actual) (As per audited accounts) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor (2-3) (1-2) 1 O&M Cost 1, , , (4.76) (9.28) DEPRECIATION FOR The actual depreciation for works out to be Rs Crores. The Weighted Average Rate of Depreciation works out to be 4.96% which is higher as compared to 4.87%, the rate approved by the Commission for The depreciation to be allowed for the year should be based on the value of the gross fixed assets as stated in clause 39 of MYT Regulation, The depreciation for the has been taken from the Profit & Loss statement The variation in the amount of depreciation as per the actual cost incurred by Sr. No. GETCO in against the amount approved by the Hon ble Commission is Rs Crores. This can be considered as gain/ (loss) on account of uncontrollable factor and has been appropriately treated as indicated in below tables. Table 17 : Depreciation for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 Gross Block in Beginning of the year 18, , Additions during the Year (Net) 2, , Depreciation for the Year (20.88) 4 Average Rate of Depreciation 4.87% 4.96% 5 Total Depreciation claimed for (20.88) Sr. No. Table 18 : Gain/ (losses) from Depreciation Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Depreciation (20.88) INTEREST & FINANCE CHARGES FOR The opening loan balance for has been considered as the revised closing loan balance for FY approved by the Hon ble Commission vide consequential order dated 6 th October, 2017 issued pursuant to the APTEL Judgment in Appeal No. 201 of The actual interest & finance charges incurred during are Rs Crores as against Rs Crores approved by the Hon ble Commission The weighted average interest rate on the loan portfolio during the year FY , computed in accordance with Regulation 38.5 (first proviso) is 8.79%. Gujarat Energy Transmission Corporation Limited Page 19

20 The value of interest and finance charges approved by the Hon ble Commission and Sr. No. those actually incurred by GETCO for is shown as per the table below. The variation on account of Interest & Finance charges is considered as Uncontrollable factor and accordingly, GETCO has compared actual expenses vis-àvis the approved expenses and worked out deviation on account of uncontrollable factor. The same has been outlined in the tables given below: Table 19 : Interest & Finance charges for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 Opening Loans 5, , Loan Additions during the Year 1, , Repayment during the Year Closing Loans 5, , Average Loans 5, , Interest on Loan Guarantee Charges Total Interest & Financial Charges Weighted Average Rate of Interest on Loan 10.11% 8.79% Sr. No. Table 20 : Gains/ (losses) from Interest & finance charges Particulars (Approved) (Normative/ Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Interest & Finance Charges RETURN ON EQUITY FOR The return on equity for GETCO has been computed based on a rate of return of Sr. No. Sr. No. 14% as provided in the GERC MYT Regulations, The comparison between the values of return on equity for with the value approved by the Hon ble Commission in MYT Order dated 31 st March, 2017 is shown as per the table below. The deviation from return on equity is considered as Uncontrollable factor. Table 21 : Return on Equity for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 Opening Equity Capital 4, , Equity Additions during the Year Closing Equity 5, , Average Equity 4, , Rate of Return on the Equity 14% 14% 6 Return on Equity (3.64) Table 22 : Gains/ (losses) from Return on Equity Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Return on Equity (3.64) Gujarat Energy Transmission Corporation Limited Page 20

21 3.17. INTEREST ON WORKING CAPITAL FOR Working Capital is computed based on the norms provided in GERC MYT Regulations, 2016 by considering O&M expenses and receivables for 1 month and maintenance spares as 1% of historical cost (i.e. GFA) As per GERC MYT Regulations, 2016, GETCO has considered weighted average of Sr. No. SBI Base Rate for plus 250 basis points i.e %. The comparison of actual value of interest on working capital based on above methodology and the value approved by the Hon ble Commission is shown as per the table below. This deviation has been considered as gain/ (loss) to GETCO on account of uncontrollable factor. Table 23 : Interest on working capital for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 O & M expenses (1 Month) Maintenance Spares (1% of Cost) Receivables (1 Month) Total Working Capital Rate of Interest on Working Capital 11.70% 11.79% 6 Interest on Working Capital (0.07) Sr. No. Table 24 : Gains/ (losses) on Interest on working capital Particulars (Approved) (Normative/ Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Interest on Working Capital (0.07) INCOME TAX FOR GETCO s actual tax worked out to be Rs Crores in as against Sr. No. approved tax of Rs Crores resulting into uncontrollable Gain of Rs Crores. The comparison of actual tax against the tax approved by the Commission is shown below: Table 25 : Gains/ (losses) on Income Tax Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Income Tax CONTRIBUTION TO CONTINGENCY RESERVE FOR Contribution to Contingency Reserve for is nil as per the audited annual accounts of GETCO which is the same as approved by the Commission in the MYT Order dated 31 st March, The table indicating the Gain/ (Loss) on account of Contingency Reserves is shown below; Gujarat Energy Transmission Corporation Limited Page 21

22 Sr. No. Petition for True Up for and Determination of Tariff for FY Table 26 : Gains/ (losses) from Contingency Reserves Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Contingency Reserve INCENTIVE ON TRANSMISSION AVAILABILITY GETCO has achieved an availability of 99.40% for its transmission network during FY certified by SLDC Regulation 67 of the GERC MYT Regulations, 2016 provides that the transmission licensee shall be entitled to an incentive for increase in annual availability beyond 98.5% GETCO has computed the incentive on higher availability based on the target availability for incentive purpose of 98.5% and the same is presented in the table given below. The incentive is calculated on Aggregate Revenue Requirement. Table 27 : Incentive for higher availability Rs. Crore Sr. No. Particulars 1 Target Availability as per MYT Regulations (%) 98.50% 2 Actual Availability (%) 99.40% 3 Aggregate Revenue Requirement 3, Incentive for Transmission System Availability Sr. No. Table 28 : Gains/ (losses) on Incentive Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Incentive for target availability (27.43) REVENUE FROM OTHER INCOME GETCO has earned Rs Crores as non-tariff revenue for the in comparison to the approved values of Rs Crores. The heads under which non-tariff income is computed as below; Sr. No. Table 29 : Revenue from other income Particulars Rs in Crores GETCO 1 Interest on Staff Loans and Advances. - 2 Income from Investments deposits Interest on Advances to Others. - 4 Interest from Banks (other than on Fixed Deposits). - 5 Income from Trading -Stores,Scrap etc Penalties received from suppliers and consumers Revenue subsidy & grant Miscellaneous Receipts Contribution and Grants towards cost of capital assets Gain on Foreign exchange fluctuation Misc. Charges from Consumers Parallel Operation Charges Net Other Income * Income from Scheduling charges of SLDC is substracted under the head Miscellaneous Receipts to determine net value for GETCO. Gujarat Energy Transmission Corporation Limited Page 22

23 Miscellaneous receipts includes other income like pro-rata charges, reactive energy charges, O&M charges for dedicated lines and supervision charges of deposit work as approved by Commission GETCO is also receiving grants/consumer contribution as deferred income during the year. The amount of deferred income received for the is Rs Crores as per the Annual Accounts The Net other income has been deducted from Transmission Charges to arrive at Sr. No. Aggregate Revenue Requirement for. Table 30 : Other income for Particulars (Approved) (Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Other Income AGGREGATE REVENUE REQUIREMENT FOR Based on above expenses, table below summarizes actual Aggregate Revenue Sr. No. Requirement for for GETCO in comparison with values approved by the Hon ble Commission. Table 31 : Aggregate revenue requirement for Particulars (Approved) (Normative/A ctual) Rs. Crores Deviation 1 Operation & Maintenance Expenses 1, , (14.04) 2 Depreciation (20.88) 3 Interest & Finance Charges Interest on Working Capital (0.07) 5 Return on Equity (3.64) 6 Contingency Reserve Total Fixed Costs 3, , Less: Expenses Capitalised (15.62) 8 Add: Income Tax Total Transmission Charges 3, , Less: Other Income Aggregate Revenue Requirement 3, , Add: Incentive for target availability (27.43) 13 Total Aggregate Revenue Requirement 3, , SHARING OF GAINS & LOSSES GERC MYT Regulations, 2016, specifies the mechanism for treatment of Gains and Losses on account of Uncontrollable and Controllable expenses. The methodology approved by the Hon ble Commission for sharing of such gains/ losses is as follows. 23. Mechanism for pass through of gains or losses on account of uncontrollable factors 23.1 The approved aggregate gain or loss to the Generating Company or Transmission Licensee or SLDC or Distribution Licensee on account of uncontrollable factors shall be passed through as an adjustment in the tariff of the Generating Company or Transmission Licensee or SLDC or Distribution Licensee over such period Gujarat Energy Transmission Corporation Limited Page 23

24 as may be specified in the Order of the Commission passed under these Regulations The Generating Company or Transmission Licensee or SLDC or Distribution Licensee shall submit such details of the variation between expenses incurred and revenue earned and the figures approved by the Commission, in the prescribed format to the Commission, along with the detailed computations and supporting documents as may be required for verification by the Commission Nothing contained in this Regulation 23shall apply in respect of any gain or loss arising out of variations in the price of fuel and power purchase, which shall be dealt with as specified by the Commission from time to time. 24 Mechanism for sharing of gains or losses on account of controllable factors: 24.1 The approved aggregate gain to the Generating Company or Transmission Licensee or SLDC or Distribution Licensee on account of controllable factors shall be dealt with in the following manner: (a) One-third of the amount of such gain shall be passed on as a rebate in tariffs over such period as may be stipulated in the Order of the Commission under Regulation 21.6; (b) The balance amount, which will amount to two-thirds of such gain, may be utilised at the discretion of the Generating Company or Transmission Licensee or SLDC or Distribution Licensee The approved aggregate loss to the Generating Company or Transmission Licensee or SLDC or Distribution Licensee on account of controllable factors shall be dealt with in the following manner: (a) One-third of the amount of such loss may be passed on as an additional charge in tariffs over such period as may be stipulated in the Order of the Commission under Regulation 21.6; and (b) The balance amount of loss, which will amount to two-thirds of such loss, shall be absorbed by the Generating Company or Transmission Licensee or SLDC or Distribution Licensee As indicated above, GETCO has identified various expenditure heads under controllable and uncontrollable categories. The gain/ losses arising as a result of True Up for for GETCO shall be suitably passed through the Tariff as per mechanism specified by the Hon ble Commission Table below summarizes total gain/ (loss) to GETCO during on account of controllable & uncontrollable factors. Gujarat Energy Transmission Corporation Limited Page 24

25 Sr. No. Petition for True Up for and Determination of Tariff for FY Table 32 : Net gains/ (losses) for Particulars (Approved) (Normative/ Actual) Gain/(Loss) due to Controllable Factor Rs. Crores Gain/(Loss) due to Uncontrollable Factor 1 Operation & Maintenance Expenses 1, , (4.76) (9.28) 2 Depreciation (20.88) 3 Interest & Finance Charges Interest on Working Capital (0.07) 5 Return on Equity (3.64) 6 Contingency Reserve ARR (1 to 6) 3, , (4.76) Less : Expense Capitalised (15.62) 9 Less : Other Income Add: incentive for target availibility (27.43) 11 Add: Income Tax Total ARR ( ) 3, , (4.76) Net Gains / Losses on account of Controllable/ Uncontrollable factor (4.76) Gain/ (Loss) on account of Controllable factor to be passed on to Consumer (1/3 x Sr. No. 13) (1.59) 15 Gain/(Loss) on account of Uncontrollable factor to be passed on to Consumer The above table summarizes the net gains/losses on account controllable/ uncontrollable factors. GETCO incurred a gain/ (loss) of Rs. (4.76) Crores on account of controllable factors and Rs Crores on account of Uncontrollable factors for As per mechanism specified in the GERC MYT Regulations 2016, GETCO proposes to pass on 1/3 rd of total gain/ (loss) on account of controllable factors i.e. Rs. (1.59) Crores and total gain/ (loss) on account of uncontrollable factor i.e. Rs Crores to the consumers REVENUE GAP FOR As stated in earlier section, GETCO has computed the head wise controllable/uncontrollable gains/ (losses) for. The revenue gap has been computed based on the above factors against the approved costs by the Commission for the Further, it is submitted that GETCO has recovered the provisional ARR for FY approved vide Order dated 31 st March, 2016 in Petition No of 2016 (which was same as the ARR of FY approved by the Commission). Subsequently, the Commission approved the final ARR for GETCO for vide Order dated 31 st March, 2017 in Petition No of Due to this, there is shortfall in the recovery of approved ARR for to the tune of Rs Crores. GETCO has included this gap while determining the total gap on true up of The Hon ble APTEL has passed Judgment on 7 th September, 2017 in GETCO s Appeal No. 201 of 2016 challenging the Commission s Order dated 31 st March, 2016 in Petition No of Pursuant to this Judgment, the Hon ble Commission has passed consequential orders dated 6 th October, 2017 and 25 th October, The net impact of both these orders works out to a net gap of Rs Crore. Gujarat Energy Transmission Corporation Limited Page 25

26 Further, the revenue (gap)/surplus for from True up of has been worked out to be Rs Crores on account of Uncontrollable factors and Rs. (1.59) Crores on account of Controllable factors (1/3rd of total gains/ (losses) Table below summarizes Revenue Gap obtained after treating gains and losses from controllable and uncontrollable factor for : Table 33 : Revenue gap for Rs. Crores Sr. No. Particulars Amount 1 Provisional approved ARR for vide Order dated 31st March, 2016 in 2, Petition No of A 2 Final approved ARR of in MYT Order dated 31st March, 2017 in Petition No. 3, of B 3 Under-recovery of ARR for (A-B) (285.59) 4 Add: Impact of consequential order passed by Commission on and pursuant to APTEL Judgment in Appeal No. 201 of Gain / (Loss) on account of Uncontrollable factor to be passed on to Beneficiaries for FY Gain / (Loss) on account of Controllable factor to be passed on to Beneficiaries (1/3rd of Total Gain / (Loss) for 7 Total Gain/ (Loss) of the true up to be addresesd in the determination of tariff for FY ( ) (10.99) (1.59) (264.90) It is requested to the Hon ble Commission to approve the above revised ARR and allow GETCO to pass on the Revenue Gap of Rs. (264.90) Crores obtained after treating gains/ (losses) for in Transmission tariff for FY DETERMINATION OF TRANSMISSION TARIFF FOR FY In accordance with provisions of the GERC MYT Regulations, 2016, tariff for FY is determined as follows: Table 34: Approved ARR for FY Rs. Crores Sr. No. Particulars FY (Approved) 1 Operation & Maintenance Expenses 1, Depreciation 1, Interest & Finance Charges Interest on Working Capital Return on Equity Contingency Reserve - 7 Total Fixed Costs Add: Provision for Tax Less: Expenses Capitalised Total Transmission Charges 4, Less: Other Income Add: Incentive for target availability - 13 Aggregate Revenue Requirement 3, Gujarat Energy Transmission Corporation Limited Page 26

Gujarat Energy Transmission Corporation Limited (GETCO)

Gujarat Energy Transmission Corporation Limited (GETCO) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2010-11 and For Gujarat Energy Transmission Corporation Limited (GETCO) Case No. 1152 of 2011 7 th April, 2012 1 st Floor, Neptune

More information

DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED SURAT MYT Petition, True-up Petition Formats - Distribution & Retail Supply Sr. No. Title Reference 1 Aggr

DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED SURAT MYT Petition, True-up Petition Formats - Distribution & Retail Supply Sr. No. Title Reference 1 Aggr DAKSHIN GUJARAT VIJ COMPANY LIMITED LIMITED Title Reference 1 Aggregate Revenue Requirement - Summary Sheet ARR-Summary 2 Customer Sales Forecast Form 1 3 Power Purchase Expenses Form 2 4 Summary of Operations

More information

Gujarat Power Sector A Statistical Profile

Gujarat Power Sector A Statistical Profile Power Sector A Statistical Profile 6th Floor, GIFT ONE, Road 5C, Zone 5, GIFT CITY, Gandhinagar, 8 55. Ph.: +91796 Fax : +91796 5/55 Email : gerc@gercin.org Website : www.gercin.org 6th Floor, GIFT ONE,

More information

Intra-State Availability Based Tariff (ABT)

Intra-State Availability Based Tariff (ABT) Intra-State Availability Based Tariff (ABT) What is ABT? 1. In Year 2000, the CERC revised the tariff structures of inter- state generators from drawal-based tariffs to ABT to discipline grid operations.

More information

Analysis of Operating Results and Financial Status

Analysis of Operating Results and Financial Status 29 Analysis of Operating Results and Financial Status 1. Analysis of Operating Results of EGAT and Its Subsidiaries Operating results of EGAT and its subsidiaries including associated company and joint

More information

Consolidated Edison Company of New York, Inc.

Consolidated Edison Company of New York, Inc. PSC NO: 11 Electricity Leaf: 1 Initial Superseding Economic Development Delivery Service No. 2 Consolidated Edison Company of New York, Inc. Schedule For Economic Development Delivery Service Subsequent

More information

Renewable Regulatory Fund (RRF) Mechanism : -

Renewable Regulatory Fund (RRF) Mechanism : - Renewable Regulatory Fund () Mechanism : - : Chronology of events Outline : Objectives at a glance : Approach : Applicability Role of different stakeholders Brief on CERC Orders on State Load Dispatch

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007 KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.1/1/KSERC-2006/ Dated, Thiruvananthapuram 6 th August,2007 KSERC (Supply of Power from Captive Generating Plants to Distribution Licensees)

More information

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order :

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order : Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order : 07.01.2016 PRESENT: 1. Hon ble Sri Desh Deepak Verma, Chairman 2. Hon ble Sri Indu

More information

Tariff Circular & Tariff Schedules

Tariff Circular & Tariff Schedules Tariff Circular & Tariff Schedules (Effective from 01 st April 2015) Madhya Gujarat Vij Company Limited Corporate Office, S.P. Vidyut Bhavan, Race Course, Vadodara-390 007 1465/2014 ANNEXURE: TARIFF SCHEDULE

More information

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 457 JOINT ELECTRICITY REGULATORY COMMISSION Joint Electricity Regulatory Commission for State of Goa & Union Territories Grid Connected Solar Power Regulations 2015 Dated 8 th May 2015 Sl. No Description

More information

Before the. Case No. 106 of 2009

Before the. Case No. 106 of 2009 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Case No. 163 of In the matter of

Case No. 163 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE 10 MAY 2018 Page 1 of 19 TABLE OF CONTENTS Introduction... 6 Applicable Law... 6 The Methodology... 6 Decision-Making

More information

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

State Bank of India PRESS RELEASE

State Bank of India PRESS RELEASE State Bank of India PRESS RELEASE Q2FY18 / H1FY18 RESULTS Note: Historical Data has been arrived at by aggregating the audited numbers of the erstwhile Associate Banks, Bharatiya Mahila Bank and SBI for

More information

Determination of Average Pooled Purchase Cost for FY

Determination of Average Pooled Purchase Cost for FY BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA Determination of Average Pooled Purchase Cost for FY 2014-15 Submitted to Himachal Pradesh State Electricity Regulatory Commission

More information

POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU TEL: FAX: PUBLIC NOTICE

POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU TEL: FAX: PUBLIC NOTICE POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU - 180007 TEL: 0191-2532809 FAX: 0191-2530265 PUBLIC NOTICE Comments / Suggestions on Annual Revenue Requirement (ARR) and Electricity Proposal

More information

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY ANNEXURE: TARIFF SCHEDULE Tariff Schedule for Adani Ports and SEZ Ltd License area of MPSEZ Utilities Pvt. Ltd. Effective from 1 st April, 2018 General Conditions 1. This tariff schedule is applicable

More information

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in

More information

In-House Paper on the implementation of Single Part Tariff in Power Distribution

In-House Paper on the implementation of Single Part Tariff in Power Distribution December 9, 2016 In-House Paper on the implementation of Single Part Tariff in Power Distribution Background: Tariff Introduction: Tariff is the price Structure at which electricity is sold to the consumers.

More information

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1 TRANSMISSION CAPACITY ADDITION PROGRAMME DURING 2006-07 Sl. No. Contents Page No. 1 Introduction 1 2 Chapter 1 Transmission Capacity Additions During 2005-06 of 10 th plan period 3 Chapter 2 Construction

More information

Portland General Electric Company Second Revision of Sheet No. 122-1 P.U.C. Oregon No. E-18 Canceling First Revision of Sheet No. 122-1 PURPOSE SCHEDULE 122 RENEWABLE RESOURCES AUTOMATIC ADJUSTMENT CLAUSE

More information

Guidelines for Solar Grid Power Projects

Guidelines for Solar Grid Power Projects Guidelines for Solar Grid Power Projects NTPC Ltd. NTPC Vidyut Vyapar Nigam Ltd. AGENDA 1 2 3 NTPC / NVVN at a glance Broad Guidelines for Selection of Solar Power Developers Elements of PPA NTPC Limited

More information

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE Objections/ comments invited from various stakeholders on ARR filing and Tariff Petition of Hydro Electric Stations, Gas Turbine

More information

CASE No. 35 of In the matter of

CASE No. 35 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Analysis of Operating Results and Financial Status

Analysis of Operating Results and Financial Status Analysis of Operating Results and Financial Status 1. Analysis of Operating Results of EGAT and its Subsidiaries Operating results of EGAT and its subsidiaries including associated company and jointly

More information

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015 26 June, 2015 PRESS NOTE Distribution for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015 MSEDCL s Multi-Year Petition for the Control Period

More information

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter:

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter: BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Fuel and purchased power cost recovery clause with generating performance incentive factor. ORDER NO. PSC-17-0219-PCO-EI ISSUED: June 13, 2017 The following

More information

PRESS RELEASE ON 19March, 2018

PRESS RELEASE ON 19March, 2018 TARIFF APPROVED FOR ASSAM POWER GENERATION COMPANY LIMITED (APGCL), ASSAM ELECTRICITY GRID CORPORATION LIMITED (AEGCL) &ASSAM POWER DISTRIBUTION COMPANY LIMITED (APDCL) FOR FY 2018-19, APPLICABLE WITH

More information

Financial Data Supplement Q4 2017

Financial Data Supplement Q4 2017 Bank Financial Data Supplement Q4 2017 2 February 2018 Due to rounding, numbers presented throughout this document may not sum precisely to the totals we provide and percentages may not precisely reflect

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd.

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. 2016Fuji Electric Co., Ltd. All rights reserved. 1 Summary of Consolidated Financial Results for 1Q FY2016 (YoY Comparison)

More information

P. SUMMARY: The Southeastern Power Administration (SEPA) establishes Rate Schedules JW-

P. SUMMARY: The Southeastern Power Administration (SEPA) establishes Rate Schedules JW- This document is scheduled to be published in the Federal Register on 08/29/2016 and available online at http://federalregister.gov/a/2016-20620, and on FDsys.gov 6450-01-P DEPARTMENT OF ENERGY Southeastern

More information

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008 TABLE OF CONTENTS Page 1 Introduction... 2 2 Charging Methodology Objectives... 4 3 Connection Charging Methodology... 5 4 Connection

More information

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th floor, Cuffe Parade, Mumbai - 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services

More information

MEGHALAYA POWER GENERATION CORPORATION LTD. PETITION BEFORE MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION, SHILLONG

MEGHALAYA POWER GENERATION CORPORATION LTD. PETITION BEFORE MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION, SHILLONG BEFORE MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION, SHILLONG PETITION FOR APPROVAL OF BUSINESS PLAN AND ANNUAL REVENUE REQUIREMENT FOR FY 2015-16 TO FY 2017-18 FILED BY MEGHALAYA POWER GENERATION

More information

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of determination of Parallel Operation Charges. Suo-Motu Petition No. 73/2012 ORDER (Date of order 31 st December, 2012) MPERC,

More information

MYT Petition citing various reasons and uncertainties in the electricity market.

MYT Petition citing various reasons and uncertainties in the electricity market. EXECUTIVE SUMMARY A. Background Considering the concerns expressed by MSEDCL about certain provisions of MYT Regulations 2011, Hon ble Commission vide Order dated 23 rd August, 2011 (Case No. 24 of 2011)

More information

INVESTOR CALL 26 th April, Mahindra Towers

INVESTOR CALL 26 th April, Mahindra Towers INVESTOR CALL 26 th April, 2012 Mahindra Towers The opportunity Indian Hotel Industry Rs. 191 Bn Leisure usage Rs. 101 Bn Source : IBEF - India Brand Equity Foundation Business Model Revenue recognition

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. Present : Sri. T. M. Manoharan, Chairman Sri. K. Vikraman Nair, Member OP 11/2016

KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. Present : Sri. T. M. Manoharan, Chairman Sri. K. Vikraman Nair, Member OP 11/2016 1 KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram Present : Sri. T. M. Manoharan, Chairman Sri. K. Vikraman Nair, Member OP 11/2016 In the matter of Implementation of Unnat Jyothi by

More information

Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION

Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION IN THE MATTER of Section 20 of the Electric Power Act (R.S.P.E.I. 1988, Cap. E- 4) and

More information

OVERVIEW OF UNIFORM TRANSMISSION RATES

OVERVIEW OF UNIFORM TRANSMISSION RATES Exhibit H1 Tab 1 Schedule 1 Page 1 of 2 1 OVERVIEW OF UNIFORM TRANSMISSION RATES 2 3 4 5 6 7 8 9 Transmission rates in Ontario have been established on a uniform basis for all transmitters in Ontario since

More information

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing.

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing. Mary L. Cottrell, Secretary March 27, 2009 Page 1 Stacey M. Donnelly Counsel September 23, 2009 Mark D. Marini, Secretary Department of Public Utilities One South Station Boston, MA 02110 Re: D.P.U. 09-03

More information

Overview of S.L Competitive Energy Solutions for North Carolina

Overview of S.L Competitive Energy Solutions for North Carolina Overview of S.L. 2017-192 Competitive Energy Solutions for North Carolina JENNIFER MCGINNIS CHRIS SAUNDERS STAFF AT TORNEYS, LEGISLATIVE ANALYSIS DIVISION 1 Overview Product of extensive stakeholder process

More information

ASSAM ELECTRICITY REGULATORY COMMISSION

ASSAM ELECTRICITY REGULATORY COMMISSION ASSAM ELECTRICITY REGULATORY COMMISSION FILE NO. AERC. 503/2015 PETITION NO. 15/2015 IA No. 2/2016 ORDER SHEET 17.11.2016 Before the Assam Electricity Regulatory Commission ASEB Campus, Dwarandhar, G.

More information

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow No.UPERC/ Secy/JD(G)/2018/ dated : 20 th August, 2018 Public Notice The Commission is in process of reviewing

More information

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G.Road, Bangalore-560 001 Present: Shri M.R. Sreenivasa Murthy Chairman Shri H. D. Arun Kumar Shri D.B. Manival

More information

Federated States of Micronesia

Federated States of Micronesia IMF Country Report No. 13/17 Federated States of Micronesia 2012 ARTICLE IV CONSULTATION 2012 Statistical Appendix January 29, 2001 January 29, 2001 This Statistical Appendix paper for the Federated States

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 41. Procurement Of RMR Generation... 2 41.1 Procurement Of Reliability Must-Run Generation By The CAISO... 2 41.2 Designation Of Generating Unit As Reliability Must-Run Unit... 2 41.3

More information

Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar , Orissa ** ** ** PUBLIC NOTICE

Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar , Orissa ** ** ** PUBLIC NOTICE Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar-751022, Orissa ** ** ** PUBLIC NOTICE Publication of Applications u/s Sec. 64(2) of the Electricity Act, 2003, read with Reg. 53(7) of the

More information

24. SOLAR INCENTIVE PROGRAM II

24. SOLAR INCENTIVE PROGRAM II 24. SOLAR INCENTIVE PROGRAM II A. General California Senate Bill 1 requires publicly owned utilities that sell electricity at the retail level, to adopt, implement, and fund a solar incentive program for

More information

BlueScope Steel Limited Consolidated Financial Headlines

BlueScope Steel Limited Consolidated Financial Headlines BlueScope Steel Limited Consolidated Financial Headlines 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2013 2013 2014 2014 2014 2015 2015 2015 2016 2016 2016 2017 2017 2017 2018 2018 2018 Total

More information

ANNEXURE: TARIFF SCHEDULE

ANNEXURE: TARIFF SCHEDULE ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2017 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION Sheet 1 of 28 Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests Net Metering services from the Distribution Company, with the exception

More information

This Distribution Charter explains how PLS distributes collective licensing

This Distribution Charter explains how PLS distributes collective licensing Distribution Charter 1 This Distribution Charter explains how PLS distributes collective licensing revenues. 1. Introduction 1.1 Collective licensing for published materials was introduced in the UK in

More information

STATE LOAD DISPATCH CENTRES (SLDC)

STATE LOAD DISPATCH CENTRES (SLDC) ACTIVITIES OF SLDC STATE LOAD DISPATCH CENTRES (SLDC) **The State Load Despatch Centre:- As per section 33 of Electricity Act - 2003 (Central Act 36 of 2003), SLDC performs powers as defined below:- SLDC

More information

Case No. 141 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. V/s Maharashtra State Electricity Distribution Co. Ltd.

Case No. 141 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. V/s Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 07-097 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for Adjustment of Stranded Cost Recovery Charge Order Following Hearing O R D E R N O. 24,872

More information

SCHEDULE 6 RESIDENTIAL SERVICE ON-SITE GENERATION

SCHEDULE 6 RESIDENTIAL SERVICE ON-SITE GENERATION I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. 6-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available at points on the Company's interconnected system within the State

More information

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Australian Capital Territory Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Disallowable instrument DI2016 189 made under the Utilities Technical Regulation

More information

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:

More information

Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar , Orissa ** ** ** PUBLIC NOTICE

Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar , Orissa ** ** ** PUBLIC NOTICE Orissa Power Transmission Corporation Ltd. Janpath, Bhubaneswar-751022, Orissa ** ** ** PUBLIC NOTICE Publication of Applications u/s Sec. 64(2) of the Electricity Act, 2003, read with Reg. 53(7) of the

More information

Docket No EI Date: May 22, 2014

Docket No EI Date: May 22, 2014 Docket No. 140032-EI Big Bend Units 1 through 4 are pulverized coal steam units that currently use distillate oil 2 for start-ups and for flame stabilization. The Company seeks to use natural gas in place

More information

Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS

Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS Antigua Tables 2006 1 Main Indicators 03/11/2006 08:05 AM Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 a/ Annual growth rates b/ Gross domestic

More information

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, 2015- DRAFT 1. PREAMBLE 1.1 To harness the potential of renewable energy resources in the state, Government of Madhya Pradesh

More information

Solar Energy Corporation of India Limited New Delhi Expression of Interest for Setting up of Solar PV Manufacturing Capacities in India

Solar Energy Corporation of India Limited New Delhi Expression of Interest for Setting up of Solar PV Manufacturing Capacities in India SECI/SD/EoI/20000 MW Mfg./I/2017 18.12.2017 Expression of Interest for Setting up of Solar PV Manufacturing Capacities in India 1. Objective of EOI: SECI intends to invite Expression of Interest from the

More information

UTTARAKHAND POWER CORPORATION LIMITED

UTTARAKHAND POWER CORPORATION LIMITED UTTARAKHAND POWER CORPORATION LIMITED PUBLIC-NOTICE In terms of the provisions of section 45 of the Electricity Act, 2003, the consumers and the general public are hereby informed of the tariff and charges

More information

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports

More information

:Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg

:Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg :Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg Technical Branch (Per) TANGEDCO Proceedings. (FB) No.

More information

Indian Energy Exchange December For Public Use

Indian Energy Exchange December For Public Use Indian Energy Exchange December 2017 For Public Use In this presentation Installed RE Capacity Total Installed Capacity Renewable Installed Capacity RES 60157 Solar, 14,771 Hydro 44963 W to P; 114 Biopower;

More information

UK Power Networks Use of System Charging Methodology

UK Power Networks Use of System Charging Methodology UK Power Networks Use of System Charging Methodology Effective From: 1 July 2018 Published: 15 June 2018 Contents General Introduction... 3 Who we are 3 Licence Obligations 3 Price Control 3 Connection

More information

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation RPO-REC Framework: Emerging Challenges and way forward Background Presentation Ashwin Gambhir, Vishal Toro, Vijaypal Singh Prayas (Energy Group), Pune 10 th June, 2013, IHC, New Delhi Prayas Energy Group,

More information

RIDER NM NET METERING

RIDER NM NET METERING d/b/a Ameren Illinois 5 th Revised Sheet No. 24 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 24) PURPOSE * The purpose of this tariff is to establish an offering of net

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public

More information

Money and banking. Flow of funds for the third quarter

Money and banking. Flow of funds for the third quarter Statistical tables Money and banking Page S South African Reserve Bank: Liabilities... 2 South African Reserve Bank: Assets... 3 Corporation for Public Deposits: Liabilities... 4 Corporation for Public

More information

Panel Discussion on Accelerating Large Scale Deployment of Rooftop SPV in India

Panel Discussion on Accelerating Large Scale Deployment of Rooftop SPV in India Panel Discussion on Accelerating Large Scale Deployment of Rooftop SPV in India February 20, 2014 Context Setting Rooftop SPV can be a good solution for reducing demandsupply gap and distribution losses.

More information

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services

More information

Unaudited Financial Statements for the Third Quarter ( 3Q ) and Nine Months ( 9M ) Ended 30 September 2017

Unaudited Financial Statements for the Third Quarter ( 3Q ) and Nine Months ( 9M ) Ended 30 September 2017 BUMITAMA AGRI LTD. Unaudited Financial Statements for the Third Quarter ( 3Q ) and Nine Months ( 9M ) Ended 30 September 2017 1(a)(i) Income statement (for the group) together with a comparative statement

More information

Statistical tables S 0. Money and banking. Capital market. National financial account. Public finance

Statistical tables S 0. Money and banking. Capital market. National financial account. Public finance Statistical tables Money and banking Page S South African Reserve Bank: Liabilities... 2 South African Reserve Bank: Assets... 3 Corporation for Public Deposits: Liabilities... 4 Corporation for Public

More information

Statistical tables S 0. Money and banking. Capital market. National financial account. Public finance

Statistical tables S 0. Money and banking. Capital market. National financial account. Public finance Statistical tables Money and banking Page S South African Reserve Bank: Liabilities... 2 South African Reserve Bank: Assets... 3 Corporation for Public Deposits: Liabilities... 4 Corporation for Public

More information

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers

More information

ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016

ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016 ANNEXURE: TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1 st April, 2016 GENERAL 1. The tariff figures indicated in this tariff schedule

More information

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Summer Reliability Assessment Report Electric Distribution Companies Perspective Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.

More information

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved. Factbook Tokyo Electric Power Company Holdings, Inc. August 2018 (Note) Please note that the following to be an accurate and complete translation of the original Japanese version prepared for the convenience

More information

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Trustees are being requested to approve a resolution adopting modifications to the Long Island Power Authority

More information

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE Sheet 1 AVAILABILITY Electric delivery service shall be taken under this rate for all purposes by any customer who is placed on the rate by the Company in accordance with this paragraph. The Company shall

More information

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents Annexure-1-B ANNEXURE TO TARIFF ORDER PASSED BY MPERC For Financial Year 2005-06 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS Table of Contents Sr No Particulars

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Louisville Gas and Electric Company Case No Table of Contents

Louisville Gas and Electric Company Case No Table of Contents Description of Contents Cover Letter Statutory Notice Application Filing Requirements Tab No. Filing Requirement Description Sponsoring Witness 1 807 KAR 5:001 Section 14 Application requirements Mr. Conroy

More information

FISCAL YEAR END MARCH 2013 FIRST HALF FINANCIAL RESULTS. New Mazda6 (Atenza)

FISCAL YEAR END MARCH 2013 FIRST HALF FINANCIAL RESULTS. New Mazda6 (Atenza) FISCAL YEAR END MARCH 2013 FIRST HALF FINANCIAL RESULTS New Mazda6 (Atenza) Mazda Motor Corporation October 31, 2012 1 PRESENTATION OUTLINE Highlights Fiscal Year March 2013 First Half Results Fiscal Year

More information

Contents. Solar Select TM Frequently Asked Questions

Contents. Solar Select TM Frequently Asked Questions Solar Select TM Frequently Asked Questions Contents Program Overview and How Solar Select Works... 1 Participation Requirements... 3 Cost and Payment... 4 Solar Production... 5 Development, Equipment,

More information

160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh

160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh Presentation on 160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh by Solar Energy Corporation of India Ltd. Feb 3, 2019 2 February 2019 Solar Energy Corporation of India Ltd 1 Indian

More information

Net Metering Policy Framework. July 2015

Net Metering Policy Framework. July 2015 Net Metering Policy Framework July 2015 Table of Contents 1.0 BACKGROUND... 2 2.0 POLICY OBJECTIVE... 2 3.1 Eligibility... 3 3.1.1 Renewable Generation... 3 3.1.2 Customer Class... 3 3.1.3 Size of Generation...

More information

Need Assessment Document (NAD) DDUGJY

Need Assessment Document (NAD) DDUGJY Need Assessment Document (NAD) DDUGJY Index SNo. Details Page No. 1.0 General Instruction 3 2.0 Objectives of DDUGJY 5 3.0 Scope of works 7 4.0 General information of project area 10 5.0 Details of existing

More information

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna 800 021 ------------------------------------------------------------------------------------------------------------- ROOFTOP

More information

78th OREGON LEGISLATIVE ASSEMBLY Regular Session. House Bill 4036

78th OREGON LEGISLATIVE ASSEMBLY Regular Session. House Bill 4036 th OREGON LEGISLATIVE ASSEMBLY--0 Regular Session House Bill 0 Introduced and printed pursuant to House Rule.00. Presession filed (at the request of House Interim Committee on Energy and Environment) SUMMARY

More information