DART Blue Line Extension. Garland to Rowlett. June 7, 2012
|
|
- Amos Moody
- 5 years ago
- Views:
Transcription
1
2 DART Blue Line Extension Design Build Project Garland to Rowlett Garland Construction Update June 7, 2012
3 Dawn Dorman DART
4
5 Ruben Landa Austin Bridge & Road, L.P.
6
7 Project Schedule Design & Construction Integrated Testing DART Milestone
8 Project Milestones KCS LRT Flyover Span No. 2 painting is 99% complete ROW Fencing is 99% complete LRT signal cabling is 99% complete Overhead Catenary System (OCS) Phase 1 is 99% complete (Downtown Rowlett Station to Centerville Road) Overhead CatenarySystem (OCS) Phase 2 is95% installed (Centerville Road to Downtown Garland Station) The Downtown Rowlett Station, Bus Loop and Parking Lot is 99% complete
9 Test schedule: System Testing Static Testing Underway Dynamic Testing / Live Wire Testing Centerville Road to Downtown Rowlett Station April 2012 Centerville Road to Downtown Garland Station July 2012 Communication Testing April 2012 Integrated Testing August 2012
10 System Testing Important facts about testing Obey all warning signs during testing Never stop on the tracks at any time During testing, DART trains will travel at various speeds. Testing will occur at all times of day and night Pedestrians are strictly forbidden from accessing the DART right-of-way
11 System Testing
12 System Testing
13 Safety #1 - Message If You re Walking Always pause and look both ways before crossing the tracks. Never cross tracks when the gates are down if you hear the bell or see the lights. Only cross the tracks at road crossings. If You re Driving Heed all warning/instruction signs. Respect crossing gates. Always look both ways before attempting to cross tracks.
14 Safety #1 - Signage
15 Safety #1 Notifications
16 DART Blue Line Extension City of Rowlett Construction Progress Photographs h
17 Rowlett Creek LRT Bridge N Rowlett Creek LRT Bridge DGNO Freight Rail
18 Rowlett Creek LRT Bridge N
19 Dexham Road At-Grade Crossing N Dexham Road
20 Dexham Road Traction Power Sub-Station Station (TPSS) N Dexham Road
21 Main Street LRT Bridge N Main Street Main Street Main Street
22 East of Rowlett Road At Grade Crossing N Rowlett Road [NB] DGNO Freight Line Rowlett Road [SB] Rowlett Road Rowlett Road
23 West of Rowlett Road At Grade Crossing N DGNO Freight Line Rowlett Road [NB] DGNO Freight Line Rowlett Road [SB] Rowlett Road
24 Martin Drive / Melcer Drive
25 Martin at Drive ve/ Melcer ece Drive N Industrial Street
26 Martin at Drive ve/ Melcer ece Drive N Industrial Street
27 Downtown Rowlett Station
28 Downtown Rowlett Station N
29 Downtown Rowlett Station
30 Downtown Rowlett Station N
31 Downtown Rowlett Station
32 Downtown Rowlett Station N Rowlett Station Rowlett Park & Ride
33 Downtown Rowlett Station N Rowlett Station Rowlett ttstationti Park & Ride
34 DART Blue Line Extension City of Garland Construction Progress Photographs
35 Focus Areas KCS LRT Bridge SH 78 LRT Bridge Rainbow Estates Sound Wall SH 66 LRT Bridge Centerville Road At Grade Crossing
36 KCS LRT Bridge Overview KCS LRT Bridge Zone A
37 KCS LRT Bridge N Walnut Drive
38 KCS LRT Bridge N Walnut Drive
39 KCS LRT Bridge N Walnut Drive
40 SH 78 LRT Bridge Overview SH 78 LRT Bridge SH 78 LRT Bridge Zone A
41 SH 78 Freight Bridge N SH 78
42 Rainbow Estates Sound Wall Overview Rainbow Estates Sound Wall Zone B
43 LRT Guideway / Rainbow Estates t Sound Wall N Rainbow Estates DGNO Freight Line
44 SH 66 LRT Bridge Overview SH 66 SH 66 LRT Bridge Zone C
45 SH 66 LRT Bridge N SH 66 SH 66
46 SH 66 LRT Bridge N SH 66 LRT Guideway SH 66 SH 66
47 Centerville Road At-Grade Crossing Overview Centerville Road At Grade Crossing Zone D
48 At-Grade Crossing: Centerville Road N Centerville Road Centerville Road [SB] DGNO Freight Rail
49 DART Blue Line Extension Public Outreach
50 Upcoming Community Activities June 9, 2012 City of Garland Juneteenth Celebration June 10, 2012 Dump the Hawaiian Falls Garland June 12, 2012 Dec Fare Restructure Community Meeting June J 26, 2012 Dec Fare Restructure t Public Hearing August 2012 Garland NAACP Back to School Health Fair Event August 2012 Garland Urban League Back to School Celebration August 2012 Mt. Hebron Baptist Church Unity Fest
51 Contacts Please direct future comments to: Ruben Landa Dawn Dorman Austin Bridge & Road DART Project thotline Community Affairs (c) ddorman@dart.org rlanda@austin-ind.com
52 DART Blue Line Extension Questions / Comments
Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015
Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update
More informationCONFEDERATION LINE EAST SEGMENT
The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit
More informationStittsville OC Transpo Services
Stittsville OC Transpo Services Transportation Services Department March 22, 2018 0 Ottawa s Transit Challenge 1 1 What s Coming in 2018 O-Train Network 2 2 Confederation Line - Alignment 3 3 VEHICLE AND
More informationExpo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011
Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More information1.0 Introduction 1.0 Introduction
1.0 Introduction 1.0 Introduction DART RAIL TO ROWLETT Connecting Communities 1.0 INTRODUCTION DART s Northeast Corridor Major Investment Study (MIS) 1995 identified cost-effective solutions to meet the
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles
More information8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager
Peoria Station Meeting August 14, 2014 1 Project Update Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager 2 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles
More informationAurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014
Aurora Line/I-225 Rail Project Update Public Meeting June 4, 2014 FasTracks and I-225 Rail Line Update Danielle Smith I-225 Rail Line Design/Build Coordination Manager 2 The RTD FasTracks Plan 122 miles
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationB Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015
1 B Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015 Northwest Rail (B) Line 6.2 miles electric commuter rail Downtown to Westminster at the 71 st /Lowell Station 11-minute travel time
More informationDFW HSR Station Plans People Movers Hyperloop
DFW HSR Station Plans People Movers Hyperloop Transit-Oriented Development Task Force Meeting May 1, 2018 Automated Transportation Systems (People Movers) Traditional People Movers Fixed, Closed Guideways
More informationRTD Commuter Rail System APTA Rail Conference June 23, 2015
RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Eagle & North Metro Commuter Rail System Today s Presentation Eagle Design, Construction, Systems Commuter Rail Vehicles and CRMF/OCC EC
More informationElected Officials Briefing. North Metro Rail Line Update. February 9, 2017
Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,
More informationMaking. Connections: Access, Connectivity and Parking at the Downtown SMART Station. Petaluma SMART Station Area TOD Master Plan.
Petaluma SMART Station Area TOD Master Plan Photo by Scott Hess, see http://cityofpetaluma.net/ Making June 23, 2011 Connections: Access, Connectivity and Parking at the Downtown SMART Station Petaluma
More informationElected Officials Briefing North Metro Rail Line Update. November 10, 2016
Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April
More informationCommunity Advisory Committee. October 5, 2015
Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical
More informationMidtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions
Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...
More informationWest Broadway Transit Study. Community Advisory Committee September 17, 2015
West Broadway Transit Study Community Advisory Committee September 17, 2015 Introductions Community Engagement Summer Outreach Fall Outreach Technical Analysis Process Update Alternatives Review Economic
More informationStreetcar and Light Rail Design Differences. March 2015
Streetcar and Light Rail Design Differences March 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets served
More informationChicago St. Louis High-Speed Rail. Braidwood Construction Public Meeting. August 7, 2014
Chicago St. Louis High-Speed Rail Braidwood Construction Public Meeting August 7, 2014 1 Chicago-St. Louis Corridor Goals and Benefits» Reduction in travel time by about an hour» Enhanced reliability»
More informationHarlem Avenue between 63 rd and 65 th
Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)
More informationMETRO Blue Line LRT Extension (BLRT) 5514 West Broadway Avenue, Suite 200, Crystal, MN
Brooklyn Park Open House August 11, 2015 *All comments are recorded verbatim from comment cards and discussion worksheets. No grammatical, word choice changes or spelling has been corrected. If handwriting
More informationW&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)
W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE
More informationAPTA RAIL CONFERENCE June 20, 2016
APTA RAIL CONFERENCE June 20, 2016 Hawaiian Islands Mainland Honolulu, Hawaii: Some of the Worst Traffic Congestion in the Nation Island of Oahu: 600-square miles Oahu s congestion ranked second in the
More informationClick to edit Master title style
Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment
More informationExpo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014
Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily
More informationConfederation Line Stage 1 and 2. Our Lady of Fatima Church May 10 th, 2018
Confederation Line Stage 1 and 2 Our Lady of Fatima Church May 10 th, 2018 Agenda Confederation Line Stage 1 Overview project, consortium, vehicles Confederation Line Stage 2 Overview project, benefits
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationCotton Belt Corridor. Area Focus Group (AFG) Richardson/Plano April 27, John Hoppie, Capital Planning
Cotton Belt Corridor Area Focus Group (AFG) Richardson/Plano April 27, 2017 John Hoppie, Capital Planning 0 Agenda Introductions Area Focus Group (AFG) Purpose Project Background Project Scope Richardson/Plano
More informationExpo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014
Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationPurple Line Extension, Section 2 Southern California Edison, Phase I
Purple Line Extension, Section 2 Southern California Edison, Phase I 1 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work: 10am-6pm Left
More informationSWLRT Business Advisory Committee. October 10, 2012
SWLRT Business Advisory Committee October 10, 2012 2 Today s Topics Approval of Meeting Minutes SWLRT 101 LRT 101 Guides to Commenting on the DEIS Future Topics of Interest Member/Committee Reports Public
More informationPurple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017
Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work:
More informationTransit on the New NY Bridge
Transit on the New NY Bridge TZB Cross Section North bridge incorporating 12ft shared use path and space for future bus lane South bridge with space for a future bus lane Gap between the two decks for
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationDallas Area Rapid Transit (DART) Cotton Belt Regional Rail Project
Dallas Area Rapid Transit (DART) Cotton Belt Regional Rail Project Kick-Off Meeting - Richardson and Plano Community Stakeholders Richardson Civic Center March 28, 2019 0 How to Stay Informed Visit www.dart.org/cottonbelt
More informationOverview of Transit Projects in the Transportation Investment Act in MARTA Jurisdictions. June 11, 2012
Overview of Transit Projects in the Transportation Investment Act in MARTA Jurisdictions June 11, 2012 TIA-023: I-20 East $ 225 million Project will construct bus P&R intended to be future rail stations
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationTrain Cars Are On The Move! Trains are rolling on the Eagle P3 Project.
In This Issue Page 2 Transit-Oriented Development Good for Communities Page 3 Eagle P3 Public Tours are Back! Denver Stands Up for Transportation Page 4 $1.19 Billion: Eagle P3 Project Builds Local Economy
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationI-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013
I-225 Rail Line 13 th Avenue Station Information Meeting July 25, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18 miles
More informationEast Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary
East Link Extension September 16, 2014 Bel-Red Conclusion to Final Design Open House Public Involvement Summary Table of contents 1 Background 2 Overview 2 Notification 3 Open House Overview 4 Comment
More informationGreen Line opens June 14
Winter 2014 Green Line opens June 14 To-do list for METRO Green Line s grand opening Yours: Study safety tips at www.centralcorridor.org/safety Learn about planned Metro Transit bus service changes on
More informationI-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011
I-405 Sepulveda Pass Improvements Project Community Advisory Committee July 28, 2011 1 Wilshire Segment 2 Wilshire Segment (National to Waterford) Ramp and Wall Construction at Sepulveda/Wilshire Intersection
More informationNEWSLETTER CONSTRUCTION PROGRESS IN THIS ISSUE:
Issue 4 Fall 2016 IN THIS ISSUE: Construction Progress Western Stations Downtown Stations Queen and Rideau Streetscaping Eastern Stations Where We ve Been Where We re Going Stage 2 Update CONSTRUCTION
More informationRegional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013
Regional Transit Extension Studies Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013 Topics Virginia Beach Transit Extension Study (VBTES) Naval Station
More informationProject Description: Georgia Department of Transportation Public Information Open House Handout PI#(s): , County: Muscogee
Why We Are Here: GDOT s Transportation Improvement Act (TIA) Office, the City of Columbus, and the project delivery team are here this evening to display and answer questions concerning the proposed roadway
More informationI-225 Rail Line Iliff and Florida Stations Information Meeting
I-225 Rail Line Iliff and Florida Stations Information Meeting May 15, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager Chris Hinton I-225 Rail Line Deputy Project
More informationMid-Coast Corridor Transit Project
San Diego Transportation Development Association Mid Coast Construction Update June 11, 2018 Mid-Coast Corridor Transit Project Mid-Coast Project 11-mile extension of Trolley Blue Line New LRT Infrastructure:
More informationEagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013
Construction of Peña Bridge - March 2013 South Platte River Bridge Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Today s Agenda Project background Schedule Design Systems Rail cars
More informationGold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014
Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationSUMMARY OF COMMENTS AT PUBLIC OPEN HOUSES SCOPING OF ALTERNATIVES GATEWAY CORRIDOR ALTERNATIVES ANALYSIS
SUMMARY OF COMMENTS AT PUBLIC OPEN HOUSES SCOPING OF ALTERNATIVES GATEWAY CORRIDOR ALTERNATIVES ANALYSIS A second series of four public open houses was held for the Gateway Corridor Alternatives Analysis
More informationB.C. MINISTRY OF TRANSPORTATION. Vancouver Island Electrical Services Area - LOCAL AREA SPECIFICATION #1 MOVABLE BRIDGE MAINTENANCE
1. OBJECTIVE B.C. MINISTRY OF TRANSPORTATION Vancouver Island Electrical Services Area - LOCAL AREA SPECIFICATION #1 MOVABLE BRIDGE MAINTENANCE 17 th Street Bridge (lift span, at Courtenay) To ensure safe
More informationStreetcar and Light Rail Design Differences. February 2015
Streetcar and Light Rail Design Differences February 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationAGENDA. Thursday, August 2, 2018 at 10:00 a.m. South Georgian Bay Community Health Centre Board Room 45 th Street & Ramblewood, Wasaga Beach
AGENDA Thursday, August 2, 2018 at 10:00 a.m. South Georgian Bay Community Health Centre Board Room 45 th Street & Ramblewood, Wasaga Beach 1. CALL TO ORDER 2. DISCLOSURE OF PECUNIARY INTEREST 3. MINUTES
More informationWhat We Heard. Edmontonians in communities Northwest of City Centre share their vision of the Metro Line NW LRT Expansion
What We Heard Edmontonians in communities Northwest of City Centre share their vision of the Metro Line NW LRT Expansion Overview The Metro Line NW LRT is part of the City s Transportation Master Plan
More informationV03. APTA Multimodal Operations Planning Workshop August Green Line LRT
V03 APTA Multimodal Operations Planning Workshop August 2016 Green Line LRT 2 Presentation Outline Past Present Future 3 16/03/2016 RouteAhead Update 4 4 16/03/2016 RouteAhead Update 5 5 16/03/2016 6 6
More informationGODURHAM PROGRESS REPORT
GODURHAM PROGRESS REPORT OVERVIEW OPERATIONS & PERFORMANCE With the service enhancements, total revenue hours increased In 2016, GoDurham connected 5.9 million passengers to jobs, education and health
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationWhat s going on? no train service safety control system
Weekend overview 1. What s going on? 2. Why the entire line, and why now? 3. Bus shuttles available 4. How much do I pay? 5. You can also try 6. Getting the word out 7. Contact us What s going on? From
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationConfederation Line West Alignment Improvement. September 21, 2016
Confederation Line West Alignment Improvement September 21, 2016 Agenda Background Lincoln Fields Station and alignment improvement LRT alignment, west of Lincoln Fields to Queensview, including: Pedestrian
More informationUpdate on Transportation Activities in Fairfax County
Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationPublic Meeting. June 15, :30 7:30 p.m.
Public Meeting June 15, 2017 5:30 7:30 p.m. Welcome 2015 Naval Station Norfolk Transit Extension Study 2015 Naval Station Norfolk Transit Extension Study 2017 Norfolk Westside Transit Study HRT and the
More informationDetailed Definition of Alternatives
West Broadway Transit Study Detailed Definition of Alternatives 9/4/2015 DRAFT Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 2040 No-Build Alternative... 1 Build Alternatives...
More informationFasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016
July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit
More informationI-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY
EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented
More informationWest Broadway Transit Study. Minnesota APA Conference Charles Carlson, Metro Transit Adele Hall, SRF Consulting September 24, 2015
West Broadway Transit Study Minnesota APA Conference Charles Carlson, Metro Transit Adele Hall, SRF Consulting September 24, 2015 Study Context: Blue Line Planning 2 Study Context: Arterial BRT Study completed
More informationEast Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015
1 East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 Today s Agenda Safety Eagle P3 Project Commuter rail vehicle East Rail Line Economic impacts DBE/SBE/WIN status Progress
More informationJOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm
ART and APS Bus Parking Informational Session July 27, 2017 7 8:30 pm 2 Agenda Introductions & overview APS Bus Parking APS Bus Facts APS Bus Operations ART Bus Parking Story of ART and its role in County
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationPlatform, Parking and Access Planning Introduction April 5, 2007
Gold Line Environmental Impact Statement (EIS) Platform, Parking and Access Planning Introduction April 5, 2007 Meeting Objectives Provide an understanding of the platform, parking, and access needs; planning
More informationJihong Cao, PE, Parsons Brinckerhoff Arnab Gupta, PE, Parsons Brinckerhoff Jay Yenerich, PE, Valley Metro
Jihong Cao, PE, Parsons Brinckerhoff Arnab Gupta, PE, Parsons Brinckerhoff Jay Yenerich, PE, Valley Metro Outline Background Predictive Priority Algorithm Simulation Analysis Measure of Effectives (MOE)
More informationDART Capital Program Update
DART Capital Program Update CMAA North Texas April 30, 2015 David Ehrlicher Assistant Vice President, Program Delivery Overview of DART System Multimodal System: 120 + bus routes 90 miles of Light Rail
More informationFixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018
Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority
More informationJanice Fortunato Senior Director Business Partnerships
Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these
More informationMetra Milwaukee District West Line Transit-Friendly Development Plan
Metra Milwaukee District West Line Transit-Friendly Development Plan Community Input Workshop April 6, 2011 Overview of Presentation Workshop Goals Study Context Existing Conditions Market Overview Employment
More informationPARKING. Passenger vehicles and vans must park in the regular daily parking lot and pay the daily rate.
NEW! Exhibitors will have complimentary parking during move-in (Nov. 9-13) and move-out (after 4pm, Nov. 17 through 12pm, Nov. 19) if they show a valid IAAPA Attractions Expo 2017 exhibitor badge. During
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationPedestrians Road Safety
Pedestrians Road Safety Overview According to the World Health Organization, the World Bank, the FIA Foundation for the Automobile and Society and the Global Road Safety Partnership collaborative report
More informationClick to edit Master text styles
I-405 Sepulveda Pass Improvements Project Quarterly Community Meeting November 17, 2011 1 Wilshire Segment 2 Quarterly Community Meetings 2012 Month Meeting(s) February 16 May 17 Quarterly Quarterly August
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half
More informationTABLE 4-4 DAILY LRT ALTERNATIVE STATION PASSENGER VOLUMES IN 2030
Station Volumes and Boardings/Alightings The stations proposed for the LRT Alternative were selected due to their proximity to population and employment centers, major existing transportation facilities,
More informationI-35W Past, Present, and Future: METRO Orange Line
I-35W Past, Present, and Future: METRO Orange Line 2018 State Public Transportation Partnerships Conference Charles Carlson Director, BRT Projects Metro Transit Charles.Carlson@metrotransit.org Metro Transit:
More information4.0 TRANSPORTATION IMPACTS
4.0 TRANSPORTATION IMPACTS This chapter describes the anticipated transportation impacts of the No-Build and LRT Alternative. The evaluation is based upon the anticipated travel demand, transportation
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010
ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010 Presentation Outline Context t of Mississauga i City Centre Implementing Paid Parking and TDM
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationUtility work, road construction substantially done on Fourth Street
November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road
More informationCommunity Meeting Station Elements
Community Meeting Station Elements North Metro Rail Line September 25, 2014 1 RRP Shawn Plichta Design Build Coordination Manager 2 RTD Jane Donovan Deputy Project Manager 3 The RTD FasTracks Plan 122
More informationCapital Metro Plans & Projects Update NASWC July 27, capmetro.org
Capital Metro Plans & Projects Update NASWC July 27, 2017 1 Capital Metro at a Glance Established in 1985 535 square mile service area 1,079,995 population 7 Member Cities Austin Leander Manor Lago Vista
More informationMetro Gold Line Eastside Extension Review Advisory Committee March 12, 2009
Review Advisory Committee March 12, 2009 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within
More information