1 Aurora Line/I-225 Rail Project Update Public Meeting June 4, 2014

2 FasTracks and I-225 Rail Line Update Danielle Smith I-225 Rail Line Design/Build Coordination Manager 2

3 The RTD FasTracks Plan 122 miles of rail 18 miles of bus rapid transit 31 Park-n-Rides 21,000+ new spaces Enhanced bus network and transit hubs Redevelopment of Denver Union Station 3

4 FasTracks Status West Rail Line (W Line) First FasTracks line to open April 2013, 8 months ahead of schedule Denver Union Station Bus Concourse opened May 9; began service May 11 East/Gold/Northwest Rail Lines (EAGLE) 54% complete U.S. 36 BRT Phase 1 of managed lanes 64% complete, Phase 2 27% North Metro Line Design underway Southeast Rail Extension 65% advanced basic engineering complete 4 4

5 I-225 Rail Line 10.5 mile light rail line Starts at Nine Mile Station Eight stations Serves Aurora City Center Serves University of Colorado Anschutz Medical Campus and Fitzsimons Life Science District Serves new VA Hospital Connects to East Rail Line Opens in

6 I-225 Rail Line Station Iliff Station Parking Spaces: 600 Nearest to: Iliff/Blackhawk Florida Station Walk-up/drop-off station Nearest to: Florida/Abilene Pedestrian bridge access to Medical Center of Aurora Aurora Metro Center Station 6 Walk-up/drop-off station Nearest to: Sable/Centrepoint 2nd /Abilene Station Parking Spaces: 200 Nearest to: 2nd/Abilene 13th Avenue Station Parking Spaces: 250 Nearest to: 13th/Sable Colfax Station Walk-up station/drop-off station Elevated over Colfax Fitzsimons Station Walk-up/drop-off station Nearest to: Fitzsimons/Peoria Peoria Station (Shared with East Rail Line) Parking Spaces: 550 Nearest to: Peoria/Smith Connection to DIA and Denver Union Station

7 Standard Station Amenities All light rail stations have standard amenities such as: 2 high blocks (ADA access) 3 canopy structures 2 windscreens 2 benches Way-finding signage Trash cans Lights 7

8 Project Flyover Video 8

9 Fitzsimons Parkway Realignment 9

10 Fitzsimons Parkway Realignment (cont.) CU & Fitzsimons Redevelopment Authority (FRA) raised concerns about EMI & vibration impacts RTD Board approved request & staff began reviewing options RTD evaluated alternatives to Montview corridor & selected Fitzsimons Parkway Screening process resulted in alignment along north side of Fitzsimons Parkway 10

11 Sable Boulevard Realignment 11

12 Sable Boulevard Realignment (cont.) Safer auto traffic crossings through Sable and Alameda intersection Safer train operations through Sable and Alameda Center running train made it difficult for auto left hand turning movements through intersection Early design found the need to acquire some parking at apartment buildings and other business driveways Refined design of the alignment determined the need to acquire apartment buildings, some parking and business driveways 12

13 Signals and Gates Signalized traffic intersection Train moves through intersections with automobile traffic Gated crossing Separates train movements from automobile traffic 13

14 Property Acquisition Process The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 The Uniform Act Established to provide uniform and equitable treatment of property owners for any properties needed for a public project Based on due process and fair market value compensation 14

15 Property Acquisition Process (cont.) RTD strictly adheres to regulations established by Congress in the Uniform Act of 1970 RTD follows the same process used by other public entities for federally-assisted projects Same process RTD has used on its previous rail projects, including the West Rail Line and T-REX RTD only purchases properties that are necessary for transit projects If a property or a portion of a property needs to be acquired, the property owner will be notified as soon as possible Every effort is made to acquire property through negotiations with property owners 15

16 Design Build Process A project delivery method that: Expedites schedule Is efficient and cost effective Minimizes impacts to businesses, neighboring communities and the traveling public Alignment divided into design packages by area and reviewed at 60% and 90% design Once released for construction, contractor can mobilize and begin construction in that area 16

17 Stakeholder Participation 17

18 RTD SBE Program The Kiewit I-225 team has developed a comprehensive plan for engaging RTD certified small business enterprises (SBE) and workforce initiative now (WIN) participants on the project RTD SBE Participation Goal for Kiewit is 25% SBE Categorical Goals were placed on the project to ensure all small businesses can compete Kiewit s SBE Commitment To-Date is 21% Kiewit is committed to awarding $87.5M in opportunities to SBE firms (per current contract amount) 104 SBE firms on the I-225 project to date, totaling approximately $73M Design, Construction, Professional and Consulting Services include the types of disciplines of SBE firms currently on the project 18

19 RTD SBE Outreach Efforts Kiewit SBE Subcontractor Bi-monthly Orientations 19 Information & requirements on certified payroll, insurance, prompt payment, safety RTD/Kiewit Subcontractor Appreciation Luncheon Luncheon highlights subcontractors & appreciation of high level of performance & commitment to the project RTD DBE/SBE Program Orientation Workshop Discusses each of the programs Informs DBE & SBE firms of primes requirements & DBE/SBE requirements of working on a project with a DBE/SBE Goal Individual Association and Organization Outreach Events Inclusive of Hispanic Contractors of Colorado, COMTO, Black Construction Group Topics include bonding insurance, capacity building, available contracting opportunities

20 Construction Update Gabrielle Johnson Kiewit Infrastructure Group Communications Coordinator 20

21 21 Construction Underway Harvard Avenue phase II utility work Iliff Avenue light rail bridge Iliff and Florida platform Welding in Area A Mississippi Avenue (at I-225 intersection) bridge 6 th Avenue (at northbound I-225 on/off-ramps) bridge 13 th Avenue truck access from Sable Boulevard to storage yard South crossing of Toll Gate Creek bridge Colfax Avenue and I-225 intersection light rail bridge Wall and guideway work throughout alignment

22 Upcoming Construction Florida Station platform construction Colfax Avenue and I-225 intersection light rail bridge Fitzsimons Parkway roadway realignment 33 rd and Peoria utility relocations Exposition Avenue removals/ roadway realignment 22

23 Rail Delivery (Feb. 2014) 23

24 Rail Installation - 1 (May 2014) 24

25 Rail Installation - 2 (May. 2014) 25

26 Rail Welding (April 2014) 26

27 Iliff Avenue Bridge Span (April 2014) 27

28 Abilene Street Ductbank (April 2014) 28

29 Abilene Street Paving (May 2014) 29

30 Florida Avenue Ped. Bridge (April 2014) 30

31 Mississippi Avenue Bridge (April 2014) 31

32 Toll Gate Creek Bridge (April 2014) 32

33 Toll Gate Bridge Girder Set (May 2014) 33

34 6 th Avenue Bridge (May 2014) 34

35 Rebar Cage for Colfax Bridge (May 2014) 35

36 Colfax Avenue Bridge (May 2014) 36

37 Construction Activities Utility locates Removals Curb & gutter Fencing and guardrail Trees Roadway and sidewalk Utility relocations/replacements Roadway and sidewalk realignment Building walls Installing track 37

38 Stay Safe Around Construction Never play on or around construction equipment. Stay out of fenced areas. Always pay attention to warning and safety signage. Never go near construction areas after dark. Holes and sharp objects can be obscured. Drive slowly and be patient in construction areas. Stay away from utilities and exposed wires. Do not play on or under bridges or near streams or rivers. Never play on or around railroad tracks, and never place anything on the tracks. Always read construction updates and door hangers as they contain important safety and traffic information. 38

39 39 Questions?

40 How to Get Information (click on I-225 Rail Line)

I-225 Rail Line 2 nd /Abilene Station Design Public Meeting

I-225 Rail Line 2 nd /Abilene Station Design Public Meeting I-225 Rail Line 2 nd /Abilene Station Design Public Meeting Jan. 29, 2014 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18

More information

8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager

8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager Peoria Station Meeting August 14, 2014 1 Project Update Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager 2 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles

More information

I-225 Rail Line Iliff and Florida Stations Information Meeting

I-225 Rail Line Iliff and Florida Stations Information Meeting I-225 Rail Line Iliff and Florida Stations Information Meeting May 15, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager Chris Hinton I-225 Rail Line Deputy Project

More information

I-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013

I-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013 I-225 Rail Line 13 th Avenue Station Information Meeting July 25, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18 miles

More information

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016 July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit

More information

Iliff and Florida Stations Meeting Q&A What is the elevation of the Iliff Station? How was it decided which direction of lanes Abilene loses?

Iliff and Florida Stations Meeting Q&A What is the elevation of the Iliff Station? How was it decided which direction of lanes Abilene loses? Iliff and Florida Stations Meeting Q&A RTD FasTracks I-225 Rail Line Iliff and Florida Stations Information Meeting Q & A May 15, 2013, 5:30 p.m. Aurora Association of Realtors Office 14201 E. Evans Avenue,

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015

East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 1 East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 Today s Agenda Safety Eagle P3 Project Commuter rail vehicle East Rail Line Economic impacts DBE/SBE/WIN status Progress

More information

Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people

Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people December 2014 Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people FasTracks News I hear the train a- comin RTD s first electric commuter rail cars arrive in Denver

More information

Denver Metro Association of Realtors

Denver Metro Association of Realtors Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

Regional Transportation District. Dave Genova Interim General Manager and CEO August 21, 2015

Regional Transportation District. Dave Genova Interim General Manager and CEO August 21, 2015 Regional Transportation District Dave Genova Interim General Manager and CEO August 21, 2015 About RTD Created in 1969 Eight-county service area Service area: 2,340 square miles 2.8 million population

More information

B Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015

B Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015 1 B Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015 Northwest Rail (B) Line 6.2 miles electric commuter rail Downtown to Westminster at the 71 st /Lowell Station 11-minute travel time

More information

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017 Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,

More information

Community Meeting Station Elements

Community Meeting Station Elements Community Meeting Station Elements North Metro Rail Line September 25, 2014 1 RRP Shawn Plichta Design Build Coordination Manager 2 RTD Jane Donovan Deputy Project Manager 3 The RTD FasTracks Plan 122

More information

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The

More information

Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013

Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Construction of Peña Bridge - March 2013 South Platte River Bridge Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Today s Agenda Project background Schedule Design Systems Rail cars

More information

RTD Commuter Rail System APTA Rail Conference June 23, 2015

RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Eagle & North Metro Commuter Rail System Today s Presentation Eagle Design, Construction, Systems Commuter Rail Vehicles and CRMF/OCC EC

More information

Train Cars Are On The Move! Trains are rolling on the Eagle P3 Project.

Train Cars Are On The Move! Trains are rolling on the Eagle P3 Project. In This Issue Page 2 Transit-Oriented Development Good for Communities Page 3 Eagle P3 Public Tours are Back! Denver Stands Up for Transportation Page 4 $1.19 Billion: Eagle P3 Project Builds Local Economy

More information

The Southeast Rail Line extension is officially moving forward

The Southeast Rail Line extension is officially moving forward November 2015 Welcome to Inside FasTracks -- your monthly update about FasTracks news, progress and people FasTracks News The Southeast Rail Line extension is officially moving forward Lone Tree Mayor

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

I-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018

I-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018 I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station

More information

Construction Review Council. Sept. 13, 2011

Construction Review Council. Sept. 13, 2011 Construction Review Council Sept. 13, 2011 Introduction Rick Clarke, Assistant General Manager, Capital Programs FasTracks Program Update and Schedule Del Walker, Deputy Assistant General Manager, Capital

More information

Chapter 4.0 Transportation Systems

Chapter 4.0 Transportation Systems Chapter 4.0 Transportation Systems This chapter compares the impacts of the No Action Alternative and the Nine Mile to Iliff Station Minimum Operable Segment (I-225 MOS) Preferred Alternative with regard

More information

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1 Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

Project Status Update January 2017

Project Status Update January 2017 Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

3.15 SAFETY AND SECURITY

3.15 SAFETY AND SECURITY 3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum

More information

Mid-Coast Corridor Transit Project

Mid-Coast Corridor Transit Project San Diego Transportation Development Association Mid Coast Construction Update June 11, 2018 Mid-Coast Corridor Transit Project Mid-Coast Project 11-mile extension of Trolley Blue Line New LRT Infrastructure:

More information

WARES. October, 2018

WARES. October, 2018 WARES October, 2018 1 Project Overview A new 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County Operates mostly on the surface with 21

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Capital Programs and Construction BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Director of Transportation to execute

More information

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...

More information

SAN FRANCISCO TO SAN JOSE PROJECT SECTION

SAN FRANCISCO TO SAN JOSE PROJECT SECTION SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED

More information

West LRT Lewis Estates to Downtown Concept Plan

West LRT Lewis Estates to Downtown Concept Plan West LRT Lewis Estates to Downtown Concept Plan March 2011 We re moving forward. Learn more. On January 19, 2011, City Council approved the West LRT Concept Plan, with a modification to use Meadowlark

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012

Station Evaluation. Durham-Orange Light Rail Transit Project Spring 2012 Station Evaluation Durham-Orange Light Rail Transit Project Spring 2012 Key Ingredients for Station Development Platform Designs UNC Hospitals Station The UNC Hospitals Station Option D would be the westerly

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

2008 Annual Report to DRCOG on FasTracks. April 2009

2008 Annual Report to DRCOG on FasTracks. April 2009 April 2009 Table of Contents EXECUTIVE SUMMARY... 1 INTRODUCTION... 8 1.0 Project Definition: Scope and Costs... 8 1.1 Project Definition and Scope... 8 1.2 Current Plan and Corridor Costs... 10 1.3 2009

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Janice Fortunato Senior Director Business Partnerships

Janice Fortunato Senior Director Business Partnerships Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these

More information

Sidewalk Working Group Update October 22, 2018

Sidewalk Working Group Update October 22, 2018 Sidewalk Working Group Update October 22, 2018 The Neighborhood Sidewalk Repair Program & The Sidewalk Gap Program Improving Mobility Freedom in Denver Neighborhood Sidewalk Repair Program: Repairing hazardous

More information

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No TECHNICAL MEMORANDUM TO: FROM: Transit Advisory Group Jeff Rhoda DATE: RE: I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P. 2785-330B SEH No. 123252 04.00 I-494/I-35W Interchange

More information

State Avenue Corridor Bus Rapid Transit (BRT)

State Avenue Corridor Bus Rapid Transit (BRT) State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!

More information

Extending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process

Extending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process Extending TRACKS Issue 5 Spring 2014 Preliminary design plan review underway Public comment and approval process in May & June Residents and businesses along the Southwest LRT (METRO Green Line Extension)

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019

Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 VENDOR OPEN HOUSE AGENDA Welcome and Introductions Safety Briefing NICTD Website and Plan Room Upcoming Projects Disadvantaged

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Elected Officials Briefing North Metro Rail Line Update. August 11, 2016

Elected Officials Briefing North Metro Rail Line Update. August 11, 2016 Elected Officials Briefing North Metro Rail Line Update August 11, 2016 1 Christina Henderson, Suncor Director of Energy Pipelines U.S. 2 August 11, 2016 RTD Update Christina Henderson Director, Suncor

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014 Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

Paid Parking at Park & Ride Lots: Framing the Issues. Capital Programs Committee May 2014

Paid Parking at Park & Ride Lots: Framing the Issues. Capital Programs Committee May 2014 Paid Parking at Park & Ride Lots: Framing the Issues Capital Programs Committee May 2014 Outline Current Status Industry Review DART Case Study Issues Alternatives Mechanics 2 Current Status: All Lots

More information

Reston Transportation Strategy July 9, 2018

Reston Transportation Strategy July 9, 2018 Reston Transportation Strategy July 9, 2018 Background: On February 11, 2014, the Board of Supervisors adopted the Reston Phase I Comprehensive Plan Amendment for the core areas of Reston between Sunset

More information

Taxi Task Force. Work Plan Progress Report, September 9, Updates since the last meeting are highlighted.

Taxi Task Force. Work Plan Progress Report, September 9, Updates since the last meeting are highlighted. Taxi Task Force Work Plan Progress Report, September 9, 2015 Updates since the last meeting are highlighted. Taxi Driver Recruitment/Retention: Recruitment/retention initiative: o Driver outreach events:

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

CRRMA BOARD PRESENTATION

CRRMA BOARD PRESENTATION CRRMA BOARD PRESENTATION El Paso Streetcar Construction Status Report Gilbert Gardner August 9, 2017 El Paso Streetcar Infrastructure Construction Status Report AGENDA Progress Summary SBE Progress Construction

More information

4 Circulation & Transportation

4 Circulation & Transportation 4.1 Mobility Network The mobility network at the new St. Paul s hospital and health campus is comprised of an interconnected system of sidewalks, cycle paths, transit routes and roadways. Figure 4-1: Indicative

More information

Central Loop Bus Rapid Transit

Central Loop Bus Rapid Transit Central Loop Bus Rapid Transit Transportation Goals of the Chicago Central Area ACTION Plan, page 2-6 Central Area Plan Improve Transit in Central Area Improve Pedestrian Environment Manage Traffic Circulation

More information

Swift Green Line April 11, 2019

Swift Green Line April 11, 2019 Swift Green Line April 11, 2019 Overview Swift BRT Overview Swift Green Line Project Snohomish County Partnership Early Results Swift Washington s first BRT Overlay BRT Stations approx. 3/4-1 mile apart

More information

Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY

Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY RAB Citizen Working Group Meeting, August 1 st 2016 CITIZEN WORKING GROUP (CWG)

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015 Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017

Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017 Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017 Background PSRC s 2017 funding: Rural Town Centers and Corridor program Regional FTA competition May - Board released projects

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information