Geomagnetic Disturbance Power System Study in Maine
|
|
- Ross Farmer
- 5 years ago
- Views:
Transcription
1 Geomagnetic Disturbance Power System Study in Maine Maine IEEE Joint Chapter PES/IAS Technical Meeting 7/22/2015 Presenter: Justin Michlig, PE
2 2
3 3
4 Overview NERC/FERC updates State of Maine Legislative updates Geomagnetic Disturbance (GMD) Theory GMD Power Flow data requirements Results of CMP GMD analysis Future Steps
5 NERC Standard TPL Applicability: Planning Coordinator Transmission Planner Transmission Owner Generator Owner Scope of facilities: Facilities operated or connected at 200+ kv Specifically transformers with a 200+ kv grounded winding are included
6 NERC Standard TPL High Level Summary: R1: Maintain Models for analysis R2: Run GMD Assessments every 5 years on peak and Off-Peak models Including reactive power device and other transmission facility contingences R3: If performance not acceptable, create Corrective Action Plan(s) R4: Must have criteria for acceptable steady state voltage R5: Coordinate responsibilities between PC and TP R6: Distribute assessment to neighbors R7: TO&GO to assess thermal impact to transformers R8: TO&GO to provide thermal assessment to PC and TP
7 NERC/FERC Updates FERC/NERC GMD Rulemaking activity: FERC Order 779: May 16, 2013 Directs NERC to develop GMD standards for Operations and Planning FERC Process started with Oct. 18, 2012 Notice of Proposed Rulemaking (NOPR) NERC GMD Taskforce scope started in 2010 FERC Order 797: June 19, 2014 Approves EOP Enforceable Date April 1, 2015 May 14, 2015 NOPR to approve TPL In addition send it back to NERC for edits Increase field strength to be tested Shorten implementation time if possible Enforceable date: TBD
8 Maine GMD Progress MPUC Docket: Started with LD 131 via resolve Report delivered to PUC & passed onto Legislature Jan 20, 2014 This report gathered pertinent documentation on past GMD and EMP events highlighting potential mitigation technologies. No tools available to quantify system impacts Continued in 2014 after PUC request to acquire software and perform analysis Results delivered to PUC end of 2014 and passed to Legislature 2014 Maine GMD/EMP Impacts Assessment LD 1363 Efforts to require installation of mitigation technologies and liability transferred to utilities Did not pass
9 GMD Planning Study Model the Transmission system Calculate the Geomagnetic Storm s Geoelectric intensity to be modeled Run a Geomagnetic Induced Current (GIC) DC power flow calculation Incorporate the DC results into an AC power flow simulation Apply contingencies and review for system deficiencies
10 DC GIC Theory - Voltages induced on the power system are calculated by geographic location and field intensity. - DC Resistance form lines, transformers, shunts, and other devices are utilized to construct the impedance network Figure 1 from K. Patil, Modeling and Evaluation of Geomagnetic Storms in the Electric Power System, DIGRE Used with Permission.
11 DC GIC Theory - GMD event casts a Geoelectric Field over the power system creating a DC current flow in the AC transmission system - Greatest impact while the Geoelectric Field is parallel to transmission line N Sub 1 Sub 2 DC Induced Voltage DC Induced Voltage
12 GIC Specific Data Data required in addition to traditional Steady State model: Geolocation (ex , ) Ground Grid Impedance Transformer * DC Resistance K Factor [4] Winding Connections Transformer core type NERC Benchmark Geoelectric Field intensity calculation* Other devices with low DC resistance Path *Additional detail on following slide
13 Transformer DC Data Auto Transformer Data Sheet Examples High Side Winding tested to ground in mω. Chose a phase or average value in Ω. Model value =.276 Ω Old Test reports are not easy to read and may be reported in total resistance. Divide total impedance by 3. Model value =.344 Ω
14 Transformer K Factor The K Factor Relates Effective GIC through the transformer to var consumption/additional losses 500 kv 345 kv Three Phase Shell form Single Phase (Separate Cores) Three Phase Three Legs Three Phase Five Legs Example 345 kv Grounded Auto Mvar Loss Calculation K factor Effective GIC Mvar A 20 Three Phase Seven Legs
15 NERC Reference GMD peak = 8 (V/km) peak = FERC NOPR directs NERC to update value Benchmark geoelectric field magnitude at System location Factor adjustment for geomagnetic latitude Factor adjustment for regional earth conductivity model
16 Lookup β Condensed Geoelectric Field Scaling Factors USGS Earth Model (β) AK1A 0.56 AK1B 0.56 AP FL NE PT SL BOU 0.28 FBK 0.56 PRU 0.21 Physiographic Regions of the Continental United States Figure 6 from NERC GIC Application Guide 2013
17 Calculation of α.001 e L L Geomagnetic North Latitude N N.6979 Geophysical Geomagnetic α N N.4169
18 Example Benchmark Field Calculation peak = 8 (V/km) FERC NOPR directs NERC to update value.001 e L L Geomagnetic North Latitude Geomagnetic conversion Latitude α Benchmark Field in Maine Northern ME 56.95N V/km Southern ME 52.46N V/km What does this calculation give me again? Electric Field to use in GIC power flow calculation Conservative value used in Maine 2014 study
19 Maine GMD Study Specifics Scope: Includes a GIC model within the Maine transmission system (a few buses into NB and NH) Focuses on 200+ kv Analyze Geoelectric fields from 4.53 V/km to 29 V/km in Maine Discuss system improvements and cost: Possible replacement of electromechanical relays Possible upgrades to capacitor banks to improve 5 min recovery time
20 2014 CMP GMD Analysis Review the transmission system per NERC GMD Planning Guide Establish the worst orientation of the Geoelectric Field Report the Effective GIC flows in transformers Report system impact to voltages
21 GMD Field Orientation PU Voltage vs. Geoelectric Field Orientation Shunt Switching_Chester Offline w/ Step-up out PU Voltage Entire Study Area State of Maine Degrees
22 GMD Field Orientation PU Voltage vs. Geoelectric Field Orientation Shunt Switching_Chester Offline w/ Step-up out Entire Study Area State of maine
23 Results from GMD field orientation effects match the orientation of the transmission in Maine. 23
24 CMP Results Mvar Transformer Mvar Consumption vs. Geoelectric Field 88 Chester SVC 18/345 kv Yarmouth GSU 22/345 kv #4 Keene Road GSU 115/345 kv Orrington 345/115 kv #1 Orrington 345/115 kv #2 South Gorham 345/115 kv #1 South Gorham 345/115 kv #2 Mason 345/115 kv #1 Macguire Road 345/115 #1 Keene Road 345/115 kv #1 Coopers Mill 345/115 kv #3 Surowiec 345/115 kv # V/km Geoelectric Field Albion Road 345/115 #1 Larrabe Rd 345/115 #1
25 CMP Results 1.04 Maine 345 kv Transmission Voltage vs Geoelectic Field V PU CHESTER SVC ORRINGTON COOPERS MILL RAVEN FARM MAINE YANKEE SUROWIEC YARMOUTH SOUTH GORHAM BUXTON MASON ALBION ROAD LARRABEE RD MAGUIRE ROAD KEENE ROAD V/km Geoelectric Field
26 CMP Results Reactive Reserves vs. Geoelectric Field Mvar 800 Online Capacitive Reactive Devices Total Installed Capacitive Reactive Devices V/km *Excludes Generator Reactive Capability, which is a significant source of reactive power
27 GMD Field Orientation Effective GIC A/phase for Maine transformers Degree Amp Max 4.53 V/km 14 V/km 20 V/km 23.5 V/km 29 V/km NERC 1 in 100 year Benchmark Study team assumed 1 in 50 year event Study team assumed 1 in 100 year event Study team assumed 1 in 200 year event Study team assumed 1 in 500 year event 2 winding delta - wye Chester SVC 18/345 kv Yarmouth GSU 22/345 kv # winding Auto Xfmrs Keene Road GSU 115/345 kv Orrington 345/115 kv # Orrington 345/115 kv # South Gorham 345/115 kv #1[1] South Gorham 345/115 kv # Mason 345/115 kv # Macguire Road 345/115 # Keene Road 345/115 kv # Coopers Mill 345/115 kv # winding Auto xfmrs Surowiec 345/115 kv # Albion Road 345/115 # Larrabee Rd 345/115 #
28 CMP Results Transformer Effective GIC using Each transformers most Impactful Geoelectric Field Angle Chester SVC 18/345 kv Yarmouth GSU 22/345 kv #4 Keene Road GSU 115/345 kv Orrington 345/115 kv #1 Effective GIC A/Phase Orrington 345/115 kv #2 South Gorham 345/115 kv #1 South Gorham 345/115 kv #2 Mason 345/115 kv #1 Macguire Road 345/115 #1 Keene Road 345/115 kv #1 Coopers Mill 345/115 kv #3 100 Surowiec 345/115 kv # Geoelectric Field Magnitude V/km Albion Road 345/115 #1 Larrabe Rd 345/115 #1
29 CMP Assumptions Change Results PU Voltage vs. Geoelectric Field 15V/km Entire Study Area State of maine
30 CMP Assumptions Change Results PU Voltage vs. Geoelectric Field 15V/km_No Shunt Switching_Chester Offline w/ Step-up in-service Entire Study Area State of maine
31 Maine Analysis Results Voltage performance of the Maine transmission system was very good Worst GMD storm angle ~88 degrees Each transformer had different angles which excited them the most Only Chester above 75 A/phase GIC recommended for thermal screening a 8 V/km benchmark event At 29 V/km field tested 8 transformers above thermal screening threshold
32 Not Covered But Important Harmonic Analysis May cause unintended tripping, but newer relays can filter No great method found to analyze GMD Harmonic effects
33 Maine Analysis Prospective Monitoring Chester Neutral current since 1991 GIC has been present and the power system has had voltage changes due to it Peak GIC neutral flow of 98 A (~33A/phase) Simulations of 75 A/phase during benchmark 8 V/km Capacitors, SVC Filters, and potential UPS functionality issue during events No customer outages No associated customer equipment damage reported
34 Maine Analysis Next Steps Reassemble previous study team Perform recommended thermal assessments of transformers Scope GMD monitoring for installation
35 Questions? 35
36 References [1] NERC GMD Project Page TPL GMD Task Force Planning Guide Benchmark Geomagnetic Disturbance Event Description Thermal Screening Criterion White Paper Transformer Thermal Impact Assessment White Paper Application Guide [2] Geomagnetic Location Calculator - [3] R. Horton, D. Boteler, T.J. Overbye, R. Pirjola, and R.C. Dugan, A Test Case for the Calculation of Geomagnetically Induced Currents, IEEE Transactions on Power Delivery, Vol. 27, No. 4, October 2012, pages [4] X. Dong, Y. Liu, J. G. Kappenman, Comparative Analysis of Exciting Current Harmonics and Reactive Power Consumption from GIC Saturated Transformers, Proceedings IEEE, 2001, pages [5] K. Patil, Modeling and Evaluation of Geomagnetic Storms in the Electric Power System, C4-306, CIGRE, 2014
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationAMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationSession 10 NERC Interconnection Requirements
GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationReactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018
1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationInterconnection Feasibility Study Report GIP-369-FEAS-R1
Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power
More informationEL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV
EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department
More informationOperational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks
Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationEvaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection
Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba
More informationEPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011
EPRI HVDC Research John Chan, Ram Adapa, Bernie Clairmont & Gary Sibilant, EPRI EPRI HVDC & FACTS Conference August 30, 2011 Presentation Contents 1. Team Members 2. Research Program Objective & Scope
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationDUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION
More informationInterconnection System Impact Study Final Report February 19, 2018
Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen
More informationTerry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis
Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience
More informationInterconnection Feasibility Study Report GIP-157-FEAS-R2
Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia
More informationSYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company
SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationECEN 667 Power System Stability Lecture 19: Load Models
ECEN 667 Power System Stability Lecture 19: Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 7 Homework 6 is
More informationPSNH INTERCONNECTION REQUEST
PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.
More informationExperience on Technical Solutions for Grid Integration of Offshore Windfarms
Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow
More informationElectric Power Research Institute, USA 2 ABB, USA
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity
More informationGrid Operations & Planning R&D Area Overview
Grid Operations & Planning R&D Area Overview Daniel Brooks Speaker s Job Title Sept 2016 Advisory Committee 2016 Sept 19: Hollywood, FL Grid Operations & Planning R&D Area at a Glance Grid Operations Advanced
More informationTransient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager
Transient Stability Analysis Tool (TSAT) Update April 11, 2016 Hongming Zhang EMS Network Applications Manager Agenda Peak Online TSAT Introduction: Where we are on Wide-wide System Model (WSM) -TSAT online
More informationCHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM
61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More informationProject #94. Generation Interconnection System Impact Study Report Revision
Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection
More informationQ217 Generator Interconnection Project
Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,
More informationRocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationDynamic Scheduling NI A F S NI S. Where:
Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated
More informationDETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT
DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationVoltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC
IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 01 July 2015 ISSN (online): 2349-784X Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC Ravindra Mohana
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationTechnical & Regulatory Standards Development
GE Energy Management Technical & Regulatory Standards Development RENEW / ISONE Interconnection of Renewable Generation Jason MacDowell GE Energy Consulting September 30, 2014 Global Renewable Codes &
More informationLarge Scale Solar Integration
Large Scale Solar Integration Experiences and Coming Changes in Distributed Energy Resource Interconnections October 26 th, 2017 Overview Background on Xcel Energy Expansion of Solar in Minnesota Changes
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationPower System Economics and Market Modeling
Power System Economics and Market Modeling M5: Security Constrained Optimal Power Flow 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationSimulated Switching Transients in the External Grid of Walney Offshore Wind Farm
Downloaded from orbit.dtu.dk on: Apr 07, 2019 Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm Arana Aristi, Iván; Johnsen, D. T.; Soerensen, T.; Holbøll, Joachim Published
More informationAnalysis of Grid Connected Solar Farm in ETAP Software
ABSTRACT 2017 IJSRSET Volume 3 Issue 3 Print ISSN: 2395-1990 Online ISSN : 2394-4099 Themed Section: Engineering and Technology Analysis of Grid Connected Solar Farm in ETAP Software Komal B. Patil, Prof.
More informationAn Introduction to Completing a NERC PRC Study
An Introduction to Completing a NERC PRC-019-2 Study For Synchronous and Distributed Generation Sources PRESENTED BY: MATTHEW MANLEY TEXAS A&M PROTECTIVE RELAYING CONFERENCE MARCH 26-29, 2018 Presentation
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationTargeted Application of STATCOM Technology in the Distribution Zone
Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric
More informationSYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company
SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report
More informationModeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA
, rue d Artois, F-8 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation X. XU,
More informationQ95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.
A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final
More informationTHE TRES AMIGAS PROJECT
UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More informationTECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008
NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0
More informationOCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC
OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC
More informationPower System Economics and Market Modeling
Power System Economics and Market Modeling M5: Security Constrained Optimal Power Flow 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More information2015 Minnesota Power Systems Conference Managing Bakken Oil Field Load Growth From a Transmission Perspective
2015 Minnesota Power Systems Conference Managing Bakken Oil Field Load rowth From a Transmission Perspective Matthew Stoltz Basin Electric Manager of Transmission Services November 10 2015 eneration =
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationManaging California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station
Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center
More informationXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS
XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page
More informationPES Cook Islands KEMA Grid Study Final Report
Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2
More informationEl PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS
El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the
More informationInterconnection Feasibility Study Report GIP-IR373-FEAS-R1
Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationQP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:
FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationInterconnection. Maine Public Utilities Commission
Renewable Generator Interconnection Jason N. Rauch, Ph.D. Maine Public Utilities Commission March 24, 2014 Agenda Overview of generator interconnection process State vs. Federal jurisdiction State interconnection
More informationAPPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation
APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationTransmission Planning using Production Cost Simulation & Power Flow Analysis
ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL
More informationEl Paso Electric Company
Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationWestern Area Power Administration Sierra Nevada Region
Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationMidway/Monument Area TTC Study
Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny
More informationCHAPTER I INTRODUCTION
CHAPTER I INTRODUCTION 1.1 GENERAL Power capacitors for use on electrical systems provide a static source of leading reactive current. Power capacitors normally consist of aluminum foil, paper, or film-insulated
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationSPS Planning Criteria and Study Methodology
SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability
More informationTRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)
TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) Nazneen Choudhari Department of Electrical Engineering, Solapur University, Solapur Nida N Shaikh Department of Electrical
More informationABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study
ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an
More informationComposite Load Model Sensitivity Study
Composite Load Model Sensitivity Study An Analysis of the Sensitivity of WECC Grid Planning Models to Assumptions Regarding the Composition of Loads NERC LMTF Meeting Salt Lake City, UT January 12, 2016
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationSTATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.
STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER
More informationSheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017
Sheffield-Highgate Export Interface SHEI VSPC Quarterly Meeting October 18, 2017 Northern Vermont Export Study Update VELCO is providing information to enable evaluation of potential solutions Incremental
More informationRenewable Energy Systems 14
Renewable Energy Systems 14 Buchla, Kissell, Floyd Chapter Outline The Electric Power Grid 14 Buchla, Kissell, Floyd 14-1 THREE-PHASE AC 14-2 THREE-PHASE TRANSFORMERS 14-3 GRID OVERVIEW 14-4 SMART GRID
More informationCHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR
100 CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 6.1 INTRODUCTION Conventional energy resources are not sufficient to meet the increasing electrical power demand. The usages of
More informationAdvanced Protective Relay Training
Advanced Protective Relay Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq A properly designed protection
More information