Composite Load Model Sensitivity Study

Size: px
Start display at page:

Download "Composite Load Model Sensitivity Study"

Transcription

1 Composite Load Model Sensitivity Study An Analysis of the Sensitivity of WECC Grid Planning Models to Assumptions Regarding the Composition of Loads NERC LMTF Meeting Salt Lake City, UT January 12, 2016 Scott Ghiocel, Nick Tenza Mitsubishi Electric Power Products, Inc. (MEPPI) Power System Engineering Services Department Warrendale, Pennsylvania

2 Background Objectives Explore the sensitivity of planning models to uncertainty in the composition and behavior of loads Provide guidance for future planning studies and data collection Transmission Providers: PacifiCorp, PG&E, SCE, and SRP Tasks Develop list of parametric simulations to be conducted Investigate sensitivities of the parameter list Run all contingencies for each transmission provider (TP) Monitor all transmission bus voltages in each TP area Monitor generation for loss of synchronism or excessive oscillation Detailed analysis for specific parameters and cases High-sensitivity parameters Stressed base case 2

3 Composite Load Model in WECC Load Bus System Bus (230, 115, 69kV) Low-side Bus M Motor A M Motor B M Motor C M Motor D UVLS UFLS Electronic Static

4 Study Work Sensitivity analysis procedure: Phase 1 Base Case: Motor D stalling disabled Phase 2 Base Case: Enable Motor D stalling (Tstall = sec) Vary one parameter in the Phase 2 Base Case Two new cases: parameter set to minimum and maximum values Total load is unchanged (same power flow case) Results: Identify study thresholds and flag observations Compute sensitivities with respect to Phase 2 Base Case Grouped by observation type Percent change in number of observations Heat maps to quickly identify key parameters and contingencies Results summarized by parameter Detailed results for each contingency 4

5 Study Criteria (Thresholds) Transient voltage dips will be monitored and recorded for dips that exceed: 25% at load buses and 30% at non-load buses 20% for more than 20 cycles at load buses Frequency oscillations will be monitored and recorded for dips below 59.6 Hz for 6 cycles or more at load buses Post-transient voltage deviations exceeding 5% at any bus Voltage recovery to 70% in 1 second, 80% in 3 seconds, 90% in 5 seconds Power, angle, or voltage magnitude oscillations will be monitored and recorded for 5% damping from the first swing peak to the 3 rd swing peak Voltage overshoot will be monitored Voltage greater than 1.1 p.u, or greater than 1.05 p.u. for 5 seconds or longer. Any non-consequential load loss (total load loss to be calculated) Any generator that loses synchronism Damping ratio sensitivities (stressed cases) 5

6 Parameter Values for Motor D Part 1 Ref. No. Description of Parameter Phase 1 Base Value as given in dyd/dyr Phase 2 Minimum Value Maximum Value 1 Vstall, Stall voltage, p.u Tstall, Stall time delay, sec Vc1off, Contactor voltage at which tripping starts, p.u Vc2off, Contactor voltage at which tripping is complete, p.u Vc1on, Contactor voltage at which reconnection is complete, p.u Vc2on, Contactor voltage at which reconnection starts, p.u Tth, Motor D thermal time constant, sec Th1t, Motor D thermal protection trip start level, p.u. temperature Th2t, Motor D thermal protection trip completion level, p.u. temperature FmA, Motor A fraction of load P % +20% 11 FmB, Motor B fraction of load P % +20% 12 FmC, Motor C fraction of load P % +20% 13 FmD, Motor D fraction of load P % +20% 14 Fel, Electronic load fraction of P % +20% 15 Vtr1, First under voltage trip level, p.u Ttr1, First under voltage trip delay time, sec Fuvr, Fraction of load with under voltage relay protection Frst, Fraction of load that can restart after stalling Vrst, Voltage at which restart can occur, p.u Trst, Restart time delay Notes: 1. Contactor settings (Vc1off, Vc2off, Vc1on, Vc2on) are changed simultaneously. 2. Motor fraction (FmA, FmB, FmC, FmD) base values are examples. Load fractions vary from load to load in the base case. 6

7 Parameter Values for Motor D Part 2 Ref. No. Description of Motor D Parameter Base Value as given in dyd/dyr Phase 2 Value 1 Value 2 Value 3 Value 4 1 Vstall, Stall voltage, p.u Tstall, Stall time delay, sec Vc1off, Contactor voltage at which tripping starts, p.u Vc2off, Contactor voltage at which tripping is complete, p.u Vc1on Contactor voltage at which reconnection is complete (pu) Vc2on Contactor voltage at which reconnection starts (pu) Tth, Motor D thermal time constant, sec Th1t, Motor D thermal protection trip start level, p.u. temperature Th2t, Motor D thermal protection trip completion level, p.u. temperature FmD, Motor D fraction of load P % -10% +10% +40% 11 Fuvr, Fraction of load with under voltage relay protection Vrst, Voltage at which restart can occur, p.u Note: Contactor settings changed as a group. 7

8 Sensitivity Analysis Part 1: Motor D key parameters All contingencies with min/max parameter values Contingency screening Based on total observations and load loss Included specific contingencies as requested Geographic diversity Part 2: Motors A, B, C, and additional values for Motor D Stressed base case with selected contingencies Parameter variations for Motors A, B, and C, additional values for Motor D 8

9 Study Work Simulations in PSS/E or PSLF, depending on each TP For both PSS/E and PSLF: Start with base case Change parameter value in the DYR or DYD file Monitor all bus voltages at 69 kv or above Post-processing and analysis using Python Generally, most composite load model parameters are the same for all loads Some exceptions: motor fractions (FmA, FmB, FmC, FmD, etc.) Other parameter values that differ have few variations 9

10 Preliminary Results Motor D Observed similar results for all sets of data (SRP, SCE, PG&E, PacifiCorp) Important parameters for Motor D were identified for all four utilities studied: Tstall and Vstall (Motor D stall parameters) Vc1on/Vc2on and Vc1off/Vc2off (Motor D contactor) FmD (fraction of Motor D load) Tth, Th1t, and Th2t (thermal relay time constant and thresholds) Fuvr (fraction of Motor D load with undervoltage relays) Vrst (voltage at which of Motor D load restarts) 10

11 FmD (Voltages) 11

12 Tstall (Voltages) 12

13 Tth (Voltages) 13

14 Heat Maps Phase 2 Base Case Ref. No. Variable Setting > 25% Voltage Dip > 30% Voltage Dip Generator Swings Offline Observations Voltage overshoot over 1.1 Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage Deviation > 5% p.u. b/w 15 and 30 seconds Voltage overshoot over 1.1 p.u. b/w 8 and 15 seconds Type of observation Voltage overshoot over 1.1 p.u. within 8 seconds Parameters 1 Phase % % % 61-9% % % % 40-82% 20-89% 328-9% 88-16% 3-20% % % 68 1% % 340 6% % % 70-61% 385 7% 98-7% 4 FmD -10% % % 68 1% % 342 7% % % % 390 8% 96-9% 5 (varies) +10% % % 79 18% % % % % % 390 8% 111 6% 6 +20% % % 82 22% % % % % % % % 7 +40% % % 88 31% % % % % % 373 3% 114 9% % % 71 6% % % % 225 2% 196 8% 371 3% 96-9% % % 70 4% 190 7% 342 7% % 222 0% 193 7% 383 6% 101-4% 10 Fuvr % % 67 0% 177-1% 321 0% % 215-3% 188 4% 358-1% 108 3% 11 (0.1) % % 67 0% 192 8% 342 7% % 213-4% 169-7% 366 1% % % % 68 1% 177-1% 337 5% % 207-6% % 386 7% % % % 79 18% % % % 237 7% 36-80% % % % % 70 4% 178 0% 320 0% 683-4% 219-1% 177-2% 361 0% 105 0% % % 69 3% 178 0% 320 0% 709 0% 219-1% 191 6% 361 0% 105 0% 16 Th1t % % 67 0% 178 0% 320 0% 712 0% 219-1% 191 6% 361 0% 105 0% 17 (0.7) % % 68 1% 178 0% 320 0% 712 0% 222 0% 184 2% 361 0% 105 0% % % 69 3% 178 0% 320 0% 712 0% 219-1% 182 1% 361 0% 105 0% % % 69 3% 178 0% 320 0% 712 0% 204-8% 183 1% 361 0% 105 0% % change from Base Case for all contingencies (Motor D fraction) % % 75 12% 178 0% 320 0% 708-1% 237 7% % % 105 0% % % 74 10% 178 0% 320 0% 709 0% 233 5% % % 105 0% 22 Th2t % % 70 4% 178 0% 320 0% 712 0% 217-2% % 361 0% 105 0% 23 (1.2) % % 70 4% 178 0% 320 0% 712 0% 220 0% % 361 0% 105 0% % % 68 1% 178 0% 320 0% 712 0% 222 0% 164-9% 361 0% 105 0% % % 71 6% 178 0% 320 0% 712 0% 202-9% 67-63% 358-1% 105 0% % % 85 27% % % % % % 384 6% 83-21% % % 61-9% 173-3% % % 38-83% 21-88% % % 28 Tstall % % 61-9% 164-8% % % 39-82% 21-88% % % 29 (0.033) % % 61-9% 183 3% % % 38-83% 21-88% % % % % 60-10% 191 7% % % 38-83% 21-88% % % % % 60-10% 191 7% % % 38-83% 21-88% % % % % 76 13% 178 0% 320 0% 687-4% 236 7% % % 107 2% % % 72 7% 178 0% 320 0% 698-2% 221 0% % 378 5% 105 0% 34 Tth % % 70 4% 178 0% 320 0% 709 0% 221 0% % 361 0% 105 0% 35 (15) % % 69 3% 178 0% 320 0% 712 0% 216-2% % 361 0% 105 0% % % 71 6% 178 0% 320 0% 712 0% 202-9% % 361 0% 105 0% % % 73 9% 178 0% 320 0% 712 0% 203-8% 96-47% 358-1% 105 0% 38 Min % % 84 25% % % % % % 362 0% 104-1% 39 R % % 66-1% % % % 223 1% % % 100-5% 40 R % % 66-1% % % % 223 1% % % 100-5% Vc1Vc2 41 R % % 64-4% % 338 6% % % % 393 9% 104-1% 42 R % % 65-3% % % % % 50-72% % % 43 Max % % 67 0% % 319 0% 664-7% % % % 72-31% % % 66-1% 178 0% % % % % 380 5% 114 9% % % 66-1% 178 0% 315-2% 751 5% % % 361 0% 112 7% 46 Vrst % % 66-1% 178 0% 320 0% 714 0% % % 361 0% 108 3% 47 (0.95) % % 66-1% 178 0% 320 0% 712 0% 207-6% % 361 0% 105 0% % % 67 0% 178 0% 320 0% 712 0% 215-3% 167-8% 361 0% 105 0% % % 66-1% 178 0% 320 0% 712 0% 219-1% 195 8% 361 0% 105 0% % % 66-1% 173-3% % % 40-82% 21-88% % % % % 66-1% 170-4% % % 39-82% 18-90% % % 52 Vstall % % 72 7% 167-6% 299-7% % % 40-78% % % 53 (0.5) % % 71 6% 189 6% 326 2% % 220 0% 194 7% 353-2% 101-4% % % 80 19% 194 9% % % % % 365 1% 86-18% % % 73 9% % % % % % 7-98% 56-47% 14

15 Sensitivity Results Utility A (1) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. 1 Base % 22-72% 946-6% % % Fel 3 20% % % % % 4-20% 19-76% % % % Fma 5 20% % % % % 6-20% 20-74% % % % Fmb 7 20% % % % % 8-20% 22-72% % % % Fmc 9 20% % % % % 10-20% 19-76% % % % Fmd 11 20% % % % % 12 Frst % % % % 13 (0.2) % % % % 14 Fuvr % % % % 15 (0.1) % 27-97% 66-99% % 16 Th1t % % % % 17 (0.7) % % % % 18 Th2t % % % % 19 (1.2) % % % % 15

16 Sensitivity Results Utility A (2) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. 20 Trst % % % % 21 (0.3) % % % % 22 Tstall % 27-97% 62-99% % 23 (0.033) % % % % 24 Tth % % % % 25 (15) % % % % 26 Ttr % % % % 27 (0.02) % % % % 28 Vc1Vc % % % % 29 (0.5) % % % % 30 Vrst % % % % 31 (0.95) % % % % 32 Vstall % 27-97% % % 33 (0.5) % % % % 34 Vtr % % % % 35 (0.6) % 999-1% % % Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. 2. Contactor settings (Vc1off, Vc2off, Vc1on, Vc2on) are changed simultaneously. (Ref. No. 28 and 29) 16

17 Sensitivity Results Utility B (1) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. 1 Base % % % % % Fel 3 20% % % % % 4-20% % % % % FmA 5 20% % % % % 6-20% % % % % FmB 7 20% % % % % 8-20% % % % % FmC 9 20% % % % % 10-20% % % % % FmD 11 20% % % % % % % % % Frst % % % % % % % % Fuvr % % % % % % % % Th1t % % % % % % % % Th2t % % % % Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. 17

18 Sensitivity Results Utility B (2) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u % % % % Trst % % % % % % % % Tstall % % % % % % % % Tth % % % % % % % % Ttr % % % % 28 Max % % % % Vc1Vc2 29 Min % % % % % % % % Vrst % % % % % % % % Vstall % % % % % % % % Vtr % % % % Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. 2. Contactor settings (Vc1off, Vc2off, Vc1on, Vc2on) are changed simultaneously. (Ref. No. 28 and 29) 18

19 Sensitivity Results Utility C (1) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. 1 Phase % % % % % Fel 3 20% % % % % 4-20% % % % % FmA 5 20% % % % % 6-20% % % % % FmB 7 20% % % % % 8-20% % % % % FmC 9 20% % % % % 10-20% % % % % FmD 11 20% % % % % 12 Frst % % % % 13 (0.2) % % % % 14 Fuvr % % % % 15 (0.1) % % % % 16 Th1t % % % % 17 (0.7) % % % % 18 Th2t % % % % 19 (1.2) % % % % 19

20 Sensitivity Results Utility C (2) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. 20 Trst % % % % 21 (0.3) % % % % 22 Tstall % % 59-98% % 23 (0.033) % % % % 24 Tth % % % % 25 (15) % % % % 26 Ttr % % % % 27 (0.02) % % % % 28 Vc1off Max % % % % 29 (0.5) Min % % % % 30 Vrst % % % % 31 (0.95) % % % % 32 Vstall % % % % 33 (0.5) % % % % 34 Vtr % % % % 35 (0.6) % % % % Notes: 1. Phase 2 base case values are shown in parentheses under each parameter. 2. Contactor settings (Vc1off, Vc2off, Vc1on, Vc2on) are changed simultaneously. (Ref. No. 28 and 29) 20

21 Sensitivity Results Utility D (1) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage Deviation > 5% Voltage overshoot over 1.1 p.u. 1 Phase % 368 0% % % % Fel 3 20% 364-1% % % % 4-20% 368 0% % % % FmA 5 20% 360-2% % % % 6-20% 373 1% % % % FmB 7 20% 355-4% % % % 8-20% 371 1% % % % FmC 9 20% 389 6% % % % 10-20% 342-7% % % % FmD 11 20% % % % % 12 Frst % % % % 13 (0.2) % % % % 14 Fuvr % % % % 15 (0.1) % % % % 16 Th1t % % % % 17 (0.7) % % % % 18 Th2t % % % % 19 (1.2) % % % % 21

22 Sensitivity Results Utility D (2) Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage Deviation > 5% Voltage overshoot over 1.1 p.u. 20 Trst % % % % 21 (0.3) % % % % 22 Tstall % % % % 23 (0.033) % % % % 24 Tth % % % % 25 (15) % % % % 26 Ttr % % % % 27 (0.02) % % % % 28 Vc1off % % % % 29 (0.5) % % % % 30 Vrst % % % % 31 (0.95) % % % % 32 Vstall % % % % 33 (0.5) % % % % 34 Vtr % % % % 35 (0.6) % % % % 22

23 Detailed Sensitivity Results Motor D Ref. No. Variable Setting Generator Swings Offline Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage Deviation > 5% 1 Phase % 61-9% % % % 40-82% 3-20% 68 1% % 340 6% % % 4 FmD -10% 68 1% % 342 7% % % 5 (varies) +10% 79 18% % % % % 6 +20% 82 22% % % % % 7 +40% 88 31% % % % % % % % % 225 2% % 190 7% 342 7% % 222 0% 10 Fuvr % 177-1% 321 0% % 215-3% 11 (0.1) % 192 8% 342 7% % 213-4% % 177-1% 337 5% % 207-6% % % % % 237 7% % 178 0% 320 0% 683-4% 219-1% % 178 0% 320 0% 709 0% 219-1% 16 Th1t % 178 0% 320 0% 712 0% 219-1% 17 (0.7) % 178 0% 320 0% 712 0% 222 0% % 178 0% 320 0% 712 0% 219-1% % 178 0% 320 0% 712 0% 204-8% % 178 0% 320 0% 708-1% 237 7% % 178 0% 320 0% 709 0% 233 5% 22 Th2t % 178 0% 320 0% 712 0% 217-2% 23 (1.2) % 178 0% 320 0% 712 0% 220 0% % 178 0% 320 0% 712 0% 222 0% % 178 0% 320 0% 712 0% 202-9% % % % % % % 173-3% % % 38-83% 28 Tstall % 164-8% % % 39-82% 29 (0.033) % 183 3% % % 38-83% % 191 7% % % 38-83% % 191 7% % % 38-83% 23

24 Detailed Sensitivity Results Motor A Ref. No. Variable Setting Voltage < 70% in 1 second Voltage < 80% in 3 seconds Voltage < 90% in 5 seconds Voltage overshoot over 1.1 p.u. b/w 15 and 30 seconds Voltage overshoot over 1.1 p.u. b/w 8 and 15 seconds Voltage overshoot over 1.1 p.u. within 8 seconds 1 Phase % 336 5% % % 334-7% % 11 H % 330 3% 779 9% 197 9% 359-1% 109 4% 12 (0.1) % 313-2% 649-9% % % 91-13% % 315-2% 735 3% 78-57% % % % 308-4% % % 384 6% 110 5% 15 Ls % % % % 343-5% % 16 (1.8) % 332 4% % 166-8% 387 7% 98-7% % % % % 388 7% 88-16% % 331 3% 758 6% % 363 1% 86-18% 19 Tpo % 328 2% 713 0% % 361 0% 90-14% 20 (0.095) % 323 1% % 171-6% 360 0% 106 1% % 320 0% 661-7% 169-7% 358-1% 107 2% % 326 2% 728 2% 40-78% % 73-30% 23 Trc % 329 3% 770 8% 41-77% % 75-29% 24 (9999) % 326 2% 766 8% 44-76% % 77-27% % 322 1% 703-1% 39-78% % 86-18% % 337 5% 717 1% % 377 4% 100-5% 31 Ttr1 (0) % 329 3% 757 6% % 357-1% 103-2% % % % 165-9% 383 6% 78-26% % 334 4% % 43-76% 364 1% 84-20% 45 Vtr % 330 3% % 55-70% 373 3% 91-13% 46 (0.7) % 319 0% 746 5% % 369 2% 101-4% % 304-5% 738 4% % % % 24

25 Load Loss Summary Per Contingency Ref. No. Variable Setting Contingency 1 Contingency 2 Contingency 3 Load Loss (MW) 1PH Stuck Breaker 5+ branches lost Load Loss (MW) Load Loss (MW) Contingency 4 Contingency 5 Load Loss (MW) Load Loss (MW) 1 Phase % % 490-8% 261-3% % % 3-20% % 512-4% 266-2% % % 4 FmD -10% % 523-2% 268-1% % % 5 (varies) +10% % 542 2% 272 1% % % 6 +20% % 552 4% 273 1% % % 7 +40% % 569 7% 276 2% % % % 533 0% 270 0% % % % 533 0% 270 0% % % 10 Fuvr % 533 0% 270 0% % % 11 (0.1) % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % 28 Tstall % 533 0% 270 0% % % 29 (0.033) % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % 34 Tth % 533 0% 270 0% % % 35 (15) % 533 0% 270 0% % % % 533 0% 270 0% % % % 533 0% 270 0% % % No-fault gen loss No-fault gen loss Line and gen loss Double line loss 25

26 Fast Tripping of Stalled Motor D Load Main idea for Motor D load Detect the stall condition and trip early (< 1 sec) instead of waiting for the thermal relay to trip (10+ sec)? Functionality is not included in the composite load model Change thermal time constant (Tth) from 15 seconds to 0.5 seconds Sensitivity analysis for the Tth parameter Tth values: 0.5, 5, 10, and 15 sec 2 contingencies in the SCE area (500 kv line outage and double line outage) 8 bus voltages plotted at the 230 kv and 500 kv voltage level Result Setting Tth = 0.5 sec results in large amounts of motor load tripping, leading to significant overvoltages Steady-state overvoltage is nearly the same for all parameter values 26

27 Fast Motor D Tripping (1)

28 Fast Motor D Tripping (2)

29 Fast Motor D Tripping (3)

30 Fast Motor D Tripping (4)

31 Fast Motor D Tripping (5)

32 Fast Motor D Tripping (6)

33 Other Observations Switching behavior can cause hunting Example: Motor D contactors with a high setpoint Switching occurs every time step (no time constant or limit) 33

34 Expected Outcomes of the Study Better understanding of how the composite load model parameters affect planning studies System response to different types of contingencies How each parameter affects different portions of the voltage response Guidance for model users on setting or changing parameter values Can be helpful for model validation and benchmarking to measurement data More information for future model updates and software development Identification of important and unimportant parameters Public report to be issued at completion of the project 34

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 NERC Load Modeling Activities Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 Introduction Kickoff January 2016 LMTF webpage Chair: Dmitry Kosterev,

More information

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager Transient Stability Analysis Tool (TSAT) Update April 11, 2016 Hongming Zhang EMS Network Applications Manager Agenda Peak Online TSAT Introduction: Where we are on Wide-wide System Model (WSM) -TSAT online

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

ECEN 667 Power System Stability Lecture 19: Load Models

ECEN 667 Power System Stability Lecture 19: Load Models ECEN 667 Power System Stability Lecture 19: Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 7 Homework 6 is

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Load Modeling for Power System Studies

Load Modeling for Power System Studies Load Modeling for Power System Studies WECC Load Modeling Task Force Dmitry Kosterev Bonneville Power Administration Transmission Planning Timescale of Interest Our primary interest is the fast dynamic

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Generating Unit Model Validation Policy

Generating Unit Model Validation Policy Generating Unit Model Validation Policy approved by WECC BOT WECC Generator Testing Task Force History August 10, 1996 WSCC Outage 4600 Observed COI Power (Dittmer Control Center) Real event 4400 4200

More information

STATCOM Application to Address Grid Stability and Reliability: Part II. D.J. SHOUP, N.W. TENZA Mitsubishi Electric Power Products, Inc.

STATCOM Application to Address Grid Stability and Reliability: Part II. D.J. SHOUP, N.W. TENZA Mitsubishi Electric Power Products, Inc. 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium STATCOM Application to Address Grid Stability and Reliability: Part II D.J. SHOUP, N.W.

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience SPIDER Modeling Sub-Group DER Modeling, CAISO Experience Irina Green, Modeling Sub-Group Chair Regional Transmission Senior Advisor, California ISO NERC SPIDER Work Group Meeting, January 2019 Presentation

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Load Composition Modeling Update

Load Composition Modeling Update Load Composition Modeling Update OCT 5 TH, 217 PRESENTER: YU ZHANG TEAM: YU ZHANG (PNNL) DAVE CHASSIN (SLAC) PAVEL ETINGOV, DAN JAMES, YUAN LIU, SOUMYA KUNDU, QIUHUA HUANG, YINGYING TANG, JIAN ZHANG, YULONG

More information

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0 S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s Revision 3.0 July 21, 2016 Revision History Version Number Author Change Description Comments 1.0

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Southwest Power Pool, Inc TPL Stability Study. MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group

Southwest Power Pool, Inc TPL Stability Study. MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group Southwest Power Pool, Inc. 2011 TPL Stability Study MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group PUBLISHED: 12/19/2011 Approved by TWG: 12/19/2011 2 2011 Stability Study Revisions

More information

Transient Stability Analysis with PowerWorld Simulator

Transient Stability Analysis with PowerWorld Simulator Transient Stability Analysis with PowerWorld Simulator 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com Transient Stability Basics Overview

More information

Unit Protection System for Pumped-Storage Power Stations

Unit Protection System for Pumped-Storage Power Stations Unit Protection System for Pumped-Storage Power Stations 1. Introduction In many power systems, pumped-storage power stations are used in addition to run-of-river power stations. These power stations serve

More information

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Journal of American Science 2015;11(11)   Integration of wind Power Plant on Electrical grid based on PSS/E Integration of wind Power Plant on Electrical grid based on PSS/E S. Othman ; H. M. Mahmud 2 S. A. Kotb 3 and S. Sallam 2 Faculty of Engineering, Al-Azhar University, Cairo, Egypt. 2 Egyptian Electricity

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

MEPPI Power Systems Engineering Division (PSED)

MEPPI Power Systems Engineering Division (PSED) Loss of Synchronous Generation Impacts and Mitigation MEPPI Power Systems Engineering Division (PSED) for EE500E Energy & Environment Seminar, University of WA, October 5, 2017 Agenda 1. An Active Industry

More information

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections Jeff Smith, Matt Rylander EPRI Robert Broderick Sandia National Laboratory Barry Mather NREL 6 th International

More information

2018 CG Transient Stability and MOD 33 Updates

2018 CG Transient Stability and MOD 33 Updates 2018 CG Transient Stability and MOD 33 Updates CG Planning Meeting Oct. 4, 2018 1 Transient Stability Study Updates 2 Studied Case Study performed for 2024HS case Two Colstrip units retired, with ATR model

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Essential Reliability Services Engineering the Changing Grid

Essential Reliability Services Engineering the Changing Grid Essential Reliability Services Engineering the Changing Grid Robert W. Cummings Senior Director Engineering and Reliability Initiatives i-pcgrid March 39, 2016 Change is Coming Characteristics and behavior

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Technical & Regulatory Standards Development

Technical & Regulatory Standards Development GE Energy Management Technical & Regulatory Standards Development RENEW / ISONE Interconnection of Renewable Generation Jason MacDowell GE Energy Consulting September 30, 2014 Global Renewable Codes &

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Electrical grid stability with high wind energy penetration

Electrical grid stability with high wind energy penetration ECOWAS Regional Workshop on WIND ENERGY Praia, Cape Verde. November 4 5, 2013 Electrical grid stability with high wind energy penetration Fernando CASTELLANO HERNÁNDEZ Head of Wind Energy Section Renewable

More information

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE Yunqi WANG, B.T. PHUNG, Jayashri RAVISHANKAR School of Electrical Engineering and Telecommunications The

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Steady-State Power System Security Analysis with PowerWorld Simulator

Steady-State Power System Security Analysis with PowerWorld Simulator Steady-State Power System Security Analysis with PowerWorld Simulator S3: Techniques for Conditioning Hard-to-Solve Cases 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha 1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration

More information

REPORT. System Impact Assessment Report. Thierry Mine Development CONNECTION ASSESSMENT & APPROVAL PROCESS CAA ID

REPORT. System Impact Assessment Report. Thierry Mine Development CONNECTION ASSESSMENT & APPROVAL PROCESS CAA ID REPORT IESO_PRO_0499 System Impact Assessment Report Thierry Mine Development CONNECTION ASSESSMENT & APPROVAL PROCESS CAA ID 2008-309 Applicant: Richview Resources Inc Market Facilitation Department 2009

More information

Grid Operations & Planning R&D Area Overview

Grid Operations & Planning R&D Area Overview Grid Operations & Planning R&D Area Overview Daniel Brooks Speaker s Job Title Sept 2016 Advisory Committee 2016 Sept 19: Hollywood, FL Grid Operations & Planning R&D Area at a Glance Grid Operations Advanced

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA , rue d Artois, F-8 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation X. XU,

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Performance Analysis of Transient Stability on a Power System Network

Performance Analysis of Transient Stability on a Power System Network Performance Analysis of Transient Stability on a Power System Network Ramesh B Epili 1, Dr.K.Vadirajacharya 2 Department of Electrical Engineering Dr. Babasaheb Ambedkar Technological University, Lonere

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

Next Steps in Load Modeling. Dmitry Kosterev, BPA, NERC LMTF Meeting August 2017

Next Steps in Load Modeling. Dmitry Kosterev, BPA, NERC LMTF Meeting August 2017 Next Steps in Load Modeling Dmitry Kosterev, BPA, NERC LMTF Meeting August 2017 1 Need for Flexible Load Model Structure Current composite load model CMPLD is rigid with respect to model components and

More information

9.1.4 Troubleshooting of Faults in LCD Screen

9.1.4 Troubleshooting of Faults in LCD Screen User Manual 9 and Maintenance 9.1.2 Arc Detection Self-test An auto-test circuit is included in the module design of the inverter s AFDI function. If a DC arc fault is detected, the corresponding fault

More information

Regenerative Utility Simulator for Grid-Tied Inverters

Regenerative Utility Simulator for Grid-Tied Inverters Regenerative Utility Simulator for Grid-Tied Inverters AMETEK s RS & MX Series with the SNK Option provides the solution Testing of grid-tied inverters used in solar energy systems is emerging as a major

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

TRIPS AND FAULT FINDING

TRIPS AND FAULT FINDING WWW.SDS.LTD.UK 0117 9381800 Trips and Fault Finding Chapter 6 6-1 TRIPS AND FAULT FINDING Trips What Happens when a Trip Occurs When a trip occurs, the drive s power stage is immediately disabled causing

More information

Transportation Electrification

Transportation Electrification Transportation Electrification Bulk Power System Reliability Aspects of Electric Vehicle Charging Ryan Quint, Advanced Analytics and Modeling, NERC 2018 i-pcgrid Conference March 2018 Trends and Perspectives

More information

Computer Aided Transient Stability Analysis

Computer Aided Transient Stability Analysis Journal of Computer Science 3 (3): 149-153, 2007 ISSN 1549-3636 2007 Science Publications Corresponding Author: Computer Aided Transient Stability Analysis Nihad M. Al-Rawi, Afaneen Anwar and Ahmed Muhsin

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

Impact of Distributed Energy Resources on Transmission System Reliability

Impact of Distributed Energy Resources on Transmission System Reliability S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

KD LV Motor Protection Relay

KD LV Motor Protection Relay 1. Protection Features KD LV Motor Protection Relay Overload (for both cyclic and sustained overload conditions) Locked rotor by vectorial stall Running stall / jam Single phasing / Unbalance Earth leakage

More information

Western Electricity Coordinating Council Modeling and Validation Work Group

Western Electricity Coordinating Council Modeling and Validation Work Group Western Electricity Coordinating Council Modeling and Validation Work Group Renewable Energy Modeling Task Force Development of Planning Models dl for Solar PV Systems November 18, 2009 Phoenix, AZ Contact:

More information

Power Technology Issue 104

Power Technology Issue 104 SIEMENS Siemens Energy, Inc. Power Technology Issue 104 PSS E Test System for Voltage Collapse Analysis Leonardo T. G. Lima Principal Consultant leonardo.lima@siemens.com James W. Feltes Senior Manager

More information

Modelling and Control of Highly Distributed Loads

Modelling and Control of Highly Distributed Loads Modelling and Control of Highly Distributed Loads Ian A. Hiskens Vennema Professor of Engineering Professor, Electrical Engineering and Computer Science Acknowledge: Duncan Callaway, Univ of California,

More information

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Presenter: Bernard Magoro, System Operator, Transmission Division, Eskom SOC Holdings Date: 05 October 2018 Contents 1. Background

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

INSTALLATION INSTRUCTIONS FOR SYMCOM'S MODEL 777-HVR-SP ELECTRONIC OVERLOAD RELAY

INSTALLATION INSTRUCTIONS FOR SYMCOM'S MODEL 777-HVR-SP ELECTRONIC OVERLOAD RELAY CONNECTIONS INSTALLATION INSTRUCTIONS FOR SYMCOM'S MODEL 777-HVR-SP ELECTRONIC OVERLOAD RELAY BE SURE POWER IS DISCONNECTED PRIOR TO INSTALLATION!! FOLLOW NATIONAL, STATE AND LOCAL CODES! READ THESE INSTRUCTIONS

More information

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Transmission Planning using Production Cost Simulation & Power Flow Analysis ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL

More information

responsible for maintenance and upkeep) Web URL: Previous name/number (if any)

responsible for maintenance and upkeep) Web URL: Previous name/number (if any) Document name WECC MVWG Load Model Report ver.1.0 Category ( ) Regional reliability standard ( ) Regional criteria ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document date June 12, 2012 Adopted/approved

More information

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues Designing and Maintaining a Pollution-Resilient Electric Power System Tom McDermott IEEE/PES T&D Conference April 21-24, 2008 Chicago, IL Managing Pollution Issues Define the metrics, and measure them

More information

The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions

The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions Mining The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions Reprint Authors: Kurt Tischler Siemens AG, Mining Technologies, Erlangen, Germany Reprint: WORKSHOP SAG

More information

Intelligent Fault Analysis in Electrical Power Grids

Intelligent Fault Analysis in Electrical Power Grids Intelligent Fault Analysis in Electrical Power Grids Biswarup Bhattacharya (University of Southern California) & Abhishek Sinha (Adobe Systems Incorporated) 2017 11 08 Overview Introduction Dataset Forecasting

More information

Application Note: Protection of Medium-Power Motors With SIPROTEC Compact 7SK80

Application Note: Protection of Medium-Power Motors With SIPROTEC Compact 7SK80 Application Note: Protection of Medium-Power Motors With SIPROTEC Compact 7SK80 Motor settings using the SIPROTEC Compact motor protection relay 7SK80 is explained below. Information is given on how to

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT By Girija Shankar Sharma, M.Tech (Power System), DGM (O&M-Opn), NTPC-Rihand, E-mail: gssharma@ntpc.co.in Presentation Points System Description and Grid

More information

Power System Analysis for a Utility with Localized Wind Generation: Southern Negros Oriental Case

Power System Analysis for a Utility with Localized Wind Generation: Southern Negros Oriental Case Power System Analysis for a Utility with Localized Wind Generation: Southern Negros Oriental Case Maria Lorena Tuballa* a, b, Michael Lochinvar Abundo a, c a School of Engineering, University of San Carlos,

More information

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS April 2009 Prepared by VACAR Stability Working Group: Kirit Doshi Anthony Williams John O Connor Joe Hood Art Brown Dominion Virginia

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Case No. 5 Sequential Motor Dynamic Acceleration Simulation ETAP TS V&V Case Number TCS-TS-181

Case No. 5 Sequential Motor Dynamic Acceleration Simulation ETAP TS V&V Case Number TCS-TS-181 ETAP Transient Stability Validation Cases and Comparison Results Case No. 5 Sequential Motor Dynamic Acceleration Simulation ETAP TS V&V Case Number TCS-TS-181 Comparison with PTI PSS/E Simulation Results

More information

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy PSO project EaseWind Enhanced ancillary services from Wind Power Plants Anca D. Hansen DTU Wind Energy Background PSO project EaseWind (2011-2014) Enhanced Ancillary Services from Wind Power Plants Partners:

More information