Local Transmission Plan

Size: px
Start display at page:

Download "Local Transmission Plan"

Transcription

1 Local Transmission Plan Idaho Power Delivery Planning Final Report December Idaho Power

2

3 Idaho Power Company TABLE OF CONTENTS Table of Contents... i List of Tables... ii List of Figures... ii List of Appendices... iii 1. Introduction Local Planning Regional and Interconnection-Wide Coordination Planning Process and Time Line Transmission System Plan Inputs and Components Idaho Power s Transmission System Load Forecast Western Load Area Treasure Valley Load Area Southern Load Area Eastern Load Area Forecasted Resources Transmission Use Forecast Area Planning Economic studies System Conditions Studied Scenarios Studied Transmission System Model Reliability Evaluation Transmission System Analysis Heavy Summer Study Results Light Summer Study Results Heavy Winter Study Results...18 Page i

4 Idaho Power Company Production Cost Case Results Heavy Summer Study Results Summary and Conclusions...19 LIST OF TABLES Table 1 Meeting dates and descriptions...2 Table 2. Load forecasts for areas of Idaho Power...4 Table IRP Preferred Portfolio...8 Table 4 Modeled loads in 2032 power flow case...16 Table 5 Summary of performance criteria issues...18 Table B-1 Projects planned for 1-5 year horizon...25 Table B-2 Projects planned for 5-10 year horizon...26 Table B-3 Projects planned for year horizon...28 LIST OF FIGURES Figure 1 Planning cycle schedule...2 Figure 2 Idaho Power transmission system...3 Figure 3 Idaho Power load areas...4 Figure 4 Western load area...5 Page ii

5 Idaho Power Company Figure 5 Treasure Valley load area...6 Figure 6 Southern load area...7 Figure 7 Eastern load area...7 Figure 8 Future IRP and generation interconnection resources...9 Figure 9 Treasure Valley electrical plan...10 Figure 10 Magic Valley electrical plan...11 Figure 11 Wood River Valley electrical plan...11 Figure 12 Eastern Idaho electrical plan...12 Figure 13 Western Treasure Valley electrical plan...13 Figure 14 Eastern Treasure Valley electrical plan Ada County...14 Figure 15 Eastern Treasure Valley electrical plan Elmore County...15 LIST OF APPENDICES Appendix A Community Advisory Committee Process...21 Appendix B Twenty-year project list...25 Page iii

6 Idaho Power Company This page left blank intentionally. Page iv

7 Idaho Power Company 1. INTRODUCTION The 2013 Local Transmission Plan is the culmination of the local transmission planning process as described in Idaho Power s Open Access Transmission Tariff (OATT) Attachment K. The plan includes all transmissions system facility improvements identified through this planning process. A power flow reliability assessment of the plan was performed which demonstrated that the planned facility additions will meet NERC and WECC reliability standards. Idaho Power s OATT is located on its Open Access Same-time Information System (OASIS) at Additional information regarding Transmission Planning is located in the Transmission Planning folder on Idaho Power s OASIS. Unless otherwise specified, capitalized terms used herein are defined in either Section 1 of Idaho Power s OATT or Section 1 of Idaho Power s OATT Attachment K Local Planning This Local Transmission Plan (LTP) has been prepared within the two-year process as defined in Idaho Power s OATT Attachment K. The LTP identifies the Transmission System facility additions required to reliably interconnect forecasted generation resources and serve the forecasted Network Customers load, Native Load Customers load, and Point-to-Point Transmission Customers requirements, including both grandfathered, non-oatt agreements and rollover rights, over a twenty (20) year planning horizon. Additionally, the LTP incorporates any stakeholders requested economic congestion studies results. Links to documents related to the LTP are located in the Local Transmission Plan folder on Idaho Power s OASIS site Regional and Interconnection-Wide Coordination Idaho Power coordinates its planning processes with other transmission providers through membership in Northern Tier Transmission Group (NTTG) and the Western Electric Coordinating Council (WECC). Idaho Power uses the NTTG process for regional planning, coordination with adjacent sub-regional groups and other planning entities, and development of proposals to WECC for interconnection-wide planning. Additional regional coordination information is located in Idaho Power s OATT Attachment K and on the NTTG s website at Page 1

8 Idaho Power Company 2. PLANNING PROCESS AND TIME LINE This plan is for the planning cycle. The planning cycle schedule is shown below in Figure 1. Figure 1 Planning cycle schedule Idaho Power holds webinar meetings throughout the planning cycle to keep stakeholders and interested parties informed. The following table lists the meeting dates. Table 1 Meeting dates and descriptions Date Meeting Meeting Description 3/21/ st Quarter Idaho Power Local Transmission Plan Request for Information 6/20/ nd Quarter Idaho Power Local Transmission Plan Presentation of assumptions 9/19/ rd Quarter Idaho Power Local Transmission Plan Initial analysis results 12/19/ th Quarter Idaho Power Local Transmission Plan Analysis results 3/20/ th Quarter Idaho Power Local Transmission Plan Draft study results 6/19/ th Quarter Idaho Power Local Transmission Plan Draft report 9/18/ th Quarter Idaho Power Local Transmission Plan Draft report with 2013 IRP resource updates 12/18/ th Quarter Idaho Power Local Transmission Plan Final report Page 2

9 Idaho Power Company 3. TRANSMISSION SYSTEM PLAN INPUTS AND COMPONENTS 3.1. Idaho Power s Transmission System Idaho Power s transmission system exists mostly in southern Idaho and eastern Oregon. The system extends north into Montana to Northwestern Energy s Mill Creek substation, east into Wyoming to the Jim Bridger power plant, south to Wells, Nevada, and west to LaGrande, Oregon as shown in Figure 2. Figure 2 Idaho Power transmission system 3.2. Load Forecast Idaho Power produces a forecast of native and network loads for its balancing area. This forecast includes Idaho Power s twenty-year load forecast and a 20 year network customer load forecast based on Bonneville Power Administration s ten-year forecast and PacifiCorp s ten-year forecast. The load forecasts include expected energy efficiency and demand response reductions. Page 3

10 Idaho Power Company Table 2, below, lists the load forecasts for the Western and Treasure Valley, Southern and Eastern load areas based on load forecasts established during quarter 1 of the process. Idaho Power generally divides its service territory into four load areas; however the load forecast reporting for the Western and Treasure Valley load areas are combined as their geographic areas overlap. Table 2. Load forecasts for areas of Idaho Power Area Description Load Level Western and Treasure Valley Idaho Power s system west of Mountain Home 3,006 MW Southern Idaho Power s system bounded by Mountain Home on the west and American falls on the east. 1,359 MW Eastern Idaho Power s system east of American Falls 665 MW A transmission map with the load areas presented in Table 2 is shown below in Figure 3. Eastern ONTARIO Western CALDWELL BOISE Treasure Valley MOUNTAIN HOME BLACKFOOT POCATELLO Legend Operating Voltage 138kV 161kV 230kV 345kV 500kV TWIN FALLS Southern Figure 3 Idaho Power load areas Page 4

11 Idaho Power Company The following sub-sections will present further information on Idaho Power load areas Western Load Area The Western Load Area includes Malheur County in Oregon and Payette, Valley, and Washington counties in Idaho. The area also includes the Brownlee East (Path 55) and Idaho to Northwest (Path 14) WECC transmission paths. The Western load area, including the area substations, generation facilities and transmission paths is shown in Figure 4. Figure 4 Western load area Treasure Valley Load Area The Treasure Valley Load Area includes the Idaho counties of Ada, Boise, Canyon, Elmore, and Gem. The Treasure Valley load area, including the area substations, generation facilities and transmission paths is shown in Figure 5. Page 5

12 Idaho Power Company Figure 5 Treasure Valley load area Southern Load Area The Southern Load Area includes the Idaho counties of Blaine, Cassia, Gooding, Jerome, Lincoln, Minidoka, and Twin Falls. The area also includes the Idaho to Sierra (Path 16) WECC rated transmission path and the Midpoint West internally monitored transmission path. The Southern load area, including the area substations, generation facilities and transmission paths is shown in Figure 6. Page 6

13 Idaho Power Company Figure 6 Southern load area Eastern Load Area The Eastern Load Area includes the Idaho counties of Bannock, Bingham, and Power. The area also includes the Borah West (Path 17) WECC rated transmission path. The Eastern load area, including the area substations and transmission paths is shown in Figure 7. Figure 7 Eastern load area Page 7

14 Idaho Power Company 3.3. Forecasted Resources The generation resource forecast is comprised of the resources identified in the Idaho Power 2013 Integrated Resource Plan (IRP), a total of 1,601 MW, and the projects in the Idaho Power generator interconnection queue with executed power sales agreements as of the end of the 1 st quarter of the LTP process. Table 3 contains the preferred 10 year resource portfolios for the next 20 years as presented in Idaho Power s 2013 IRP. Table IRP Preferred Portfolio Date Resource Capacity Demand Response Up to 150 MW 2018 Boardman to Hemingway 500 MW Transfer Capacity Summer 2024 Demand Response Up to 370 MW in 50 MW Increments Figure 8 depicts the 2013 IRP resources and interconnection queue generation resources by location and resource type. Page 8

15 Idaho Power Company Figure 8 Future IRP and generation interconnection resources 3.4. Transmission Use Forecast Forecasted use of the transmission system by others was modeled by scheduling the transfer of 2,000 MW of generation in Eastern Idaho and Wyoming across the Idaho Power system to the Pacific Northwest Area Planning Idaho Power develops long-term local area transmission plans with regional community advisory committees. These committees consist of jurisdictional planners; mayors; council members; commissioners; and large industry, commercial, residential, and environmental representatives. The plans identify the transmission and substation infrastructure required through the full development or build-out of the local area. The Treasure Valley, western Treasure Valley, eastern Treasure Valley, Magic Valley, Wood River Valley, and eastern Idaho electrical have been completed. Figures 9 through 15 present the future transmission infrastructure plans for Page 9

16 Idaho Power Company each of the fore mentioned electrical plans. A description of the community advisory committee process can be found in Appendix A. More information about electrical plans can be found on the Idaho Power website at: Figure 9 Treasure Valley electrical plan Page 10

17 Idaho Power Company Figure 10 Magic Valley electrical plan Figure 11 Wood River Valley electrical plan Page 11

18 Idaho Power Company Figure 12 Eastern Idaho electrical plan Page 12

19 Idaho Power Company Figure 13 Western Treasure Valley electrical plan Page 13

20 Idaho Power Company Figure 14 Eastern Treasure Valley electrical plan Ada County Page 14

21 Idaho Power Company Figure 15 Eastern Treasure Valley electrical plan Elmore County 3.6. Economic studies Eligible customers or stakeholders may submit an economic congestion study request during either quarter 1 or quarter 5 of the planning cycle. Idaho Power did not receive any study requests during quarter 1 or quarter 5 of the planning cycle Scenarios Studied 4. SYSTEM CONDITIONS STUDIED Idaho Power uses scenario planning to evaluate the performance of the transmission system for different load and generation dispatch patterns in the future. A 20 year heavy summer load study case was evaluated as the primary study scenario. A five year heavy load scenario, a 10 year light load scenario and a 10 year heavy load scenario were studied. The five and 10 year cases were selected to assess future system adequacy and performance under different load and generation patterns (seasonal conditions). Further, a 10 year production cost case was also evaluated to determine if any unusual flow pattern exists that is not represented in the selected seasonal cases. Ultimately, an autumn Page 15

22 Idaho Power Company condition with heavy east to west transfers across Idaho Power s system was selected and evaluated in the same manner as the five, 10 and 20 year scenarios Transmission System Model The 20 year power flow case was based on the WECC 2019 HS1 base case, approved by WECC on June 10, Load levels in the 20 year case were increased to approximate Idaho Power s forecasted control area load in the year The total Idaho Power control area load was modeled at 5,030 MW. This is roughly a 1,600 MW increase in load from Idaho Power s historical peak load of 3,407 MW, which occurred on July 2, The loads in the case were increased to achieve the following distribution across the Idaho Power s system: Table 4 Modeled loads in 2032 power flow case Area Description Load Level Western and Treasure Valley Idaho Power s system west of Mountain Home(approximately 50 miles east of Boise) Southern Idaho Power s system bounded by Mountain Home on the west and American falls on the east. 3,006 MW 1,359 MW Eastern Idaho Power s system east of American Falls 665 MW The 20 year power flow case was also modified to reflect the expected 500 kv transmission improvements for the Gateway West and Boardman to Hemingway (B2H) transmission projects. Lower voltage transmission modeling detail was added to the Idaho Power service territory that was not originally modeled in the WECC base case. Transmission growth and reliability driven projects that have been planned for the next 20 years have also been added to the case. A list of projects scheduled for the next 20 years can be found in Appendix B. The five year and ten year scenarios utilized WECC approved power flow cases. Idaho Power also evaluated the same cases as part of its 2012 NERC TPL compliance reliability evaluation. The following three WECC cases were utilized: 2017 Heavy Summer case (17hs1a1), approved 10/7/ Heavy Winter case (22hw1a1), approved 03/14/ Light Summer case (22ls1sa), approved 12/6/12 The load, resource dispatch and path flow data modeled in the WECC base cases for the five and ten year cases were not modified from the WECC published cases. The 2022 production cost case utilized the WECC TEPPC production cost model (PC1). The TEPPC 2022 PC1 model is a security constrained economic-commitment-and-dispatch model based on forecasted loads and resources for the year 2022 that were submitted from all WECC balancing authorities. The balancing authorities supply monthly peak and energy forecasts. The forecasts are then dispersed into hourly load demands. Page 16

23 Idaho Power Company After reviewing the hourly 2022 PC1 data, the model data from November 6, hour 10:00 was extracted into a PowerWorld power flow model. The case was selected for Idaho Power s LTP analysis because it contained high east-to-west transfers across the Idaho Power system. This same case was utilized by Northern Tier Transmission Group (NTTG) for its Planning process. The extracted case was selected by the NTTG Planning group because it represented the maximum NTTG footprint export condition. 5. RELIABILITY EVALUATION 5.1. Transmission System Analysis PowerWorld power flow software was utilized to perform contingency analysis on the 10 year production cost case and the 20 year planning power flow case. POM software was used to perform contingency analysis on the five and ten year cases. A total of 410 single element outage (N-1) contingencies were evaluated based on single transmission line or single transformer outages on the 138 kv, 161 kv, 230 kv, 345 kv and 500 kv systems. Thirty-six credible N-2 contingencies were evaluated. Idaho Power s Common Corridor analysis was the basis for a list of credible two element outage (N-2) contingencies. The power-flow simulation results are measured against North American Electric Reliability Council (NERC) and WECC reliability criteria. Specifically, the NERC Reliability Standards TPL-001 and TPL-002 b require that transmission facilities maintain operation within normal and emergency limits. The WECC business practice TPL-001-WECC-RBP-2 establishes the voltage-violation threshold for N-1 contingencies. Additionally, Idaho Power files its reliability criteria via FERC Form No. 715, part IV Reliability Criteria for System Planning. Combined, the NERC, WECC and Idaho Power criteria formed the criterion for which every N-1 and N-2 contingency was screened. Every N-1 contingency was screened for thermal overloads and voltage issues. Thermal overloads over 100% of equipment emergency ratings were reported. Voltage deviations greater than 5% were reported. Per Idaho Power s Reliability Criteria for System Planning, post-outage deviations greater than 5% are acceptable if minimum voltage remains above nominal of 0.90 per unit and distribution bus voltage is within ANSI Emergency Range. Regardless, 5% deviations were flagged as part of the screening process. A low voltage screening threshold was set for 0.93 PU and a high voltage threshold was set for 1.10 PU. Thus, any contingency that resulted in a voltage below 0.93 or greater than 1.10 was reported, regardless of the amount of voltage deviation. Flagged contingencies were then reviewed further to determine if the reported issue was a reliability criteria violation. A summary of results can be found below in Table 5 and the results are discussed further in the following sections. The system improvements identified for the next 20 years are presented in Appendix B. Page 17

24 Idaho Power Company Table 5 Summary of performance criteria issues Case Number of Flagged Contingencies Thermal Issues Voltage Issues 2017 Heavy Summer Light Summer Heavy Winter PC1-Nov, 6 Hour Heavy Summer Heavy Summer Study Results The N-1 contingency analysis resulted in six thermal issues and two different line outages scenarios that resulted in voltage deviation issues. Each of the thermal issues were a result of a 230/138 kv transformer outage causing an overload of the parallel 230/138 kv transformer. Two of the locations, Locust and Adelaide, are a result of modeling the study case. The 138 kv system is not modeled in detail in this study case so the 138 kv aggregations are causing overloads that would not occur if the system were modeled in detail. The transformer thermal overload at Ontario is a legitimate issue. A project has been proposed to address the overload issue and is included in the project list in Appendix B. The Wood River Midpoint 138-kV line outage resulted in a voltage deviation greater than 5% and post-contingency voltage less than 0.95 per unit. The study results are more drastic than they appear because the modeling in the 17 HS case has all of the load buses on the 138 kv lines between Midpoint-Wood River-138 kv aggregated and modeled as one large load at the Wood River bus. In real life, if either of the lines opens, load tapped off the line would be disconnected. If the contingency is modeled with the expected load dropping, the voltage performance improves to an acceptable level. No thermal or voltage issues resulted from the N-2 contingency analysis Light Summer Study Results No thermal or voltage issues resulted from the N-1 and N-2 contingency analysis Heavy Winter Study Results Four N-1 contingencies were flagged in the long-term 2022 heavy winter case. The outage of Ontario-Weiser 138-kV line resulted in voltage deviation greater than 5%, but the performance is acceptable in this case because the post contingency voltage remained above 0.95 per unit. Three outages; King-Wood River-138 kv line, Midpoint-Wood River-138 kv line and Midpoint 230/138 kv transformer, resulted in voltage deviations greater than 5% at Wood River 138-kV Page 18

25 Idaho Power Company bus. The Midpoint-Wood River-138 kv line outage also resulted in thermal overload of the King-Wood River 138 kv line. As noted above for other study cases, the results are not as drastic as they appear because the modeling in the case has all of the load buses on the 138 kv lines between King-Wood River-138 kv and Midpoint-Wood River-138 kv aggregated and modeled as one large load at Wood River. In real life, if either of the lines opens, load tapped off the lines would be disconnected. If either line outage is modeled with the expected load dropping the voltage performance improves to acceptable levels. No thermal or voltage issues resulted from the N-2 contingency analysis Production Cost Case Results No thermal or voltage issues of concern resulted from the N-1 and N-2 contingency analysis Heavy Summer Study Results The N-1 contingency analysis resulted in no thermal overloads and three different line outages that resulted in voltage issues. Each of the three outages resulted in voltage deviations greater than 5%. However, in each instance, the post-contingency voltage was between 0.95 per unit and 1.05 per unit so the contingency results were acceptable. No thermal or voltage issues of concern resulted from the N-1 and N-2 contingency analysis. 6. SUMMARY AND CONCLUSIONS Idaho Power s Local Transmission Plan has been prepared as part of the two-year process defined in Idaho Power s OATT Attachment K. The Plan has identified the transmission system facility additions required to reliably interconnect forecasted generation resources, serve Native Customer and Network Customer forecasted load and Point-to-Point Transmission Customers requirements over a twenty (20) year planning horizon. A list of such facility additions and upgrades can be found in Appendix B. A power flow reliability assessment was performed on cases modeling system conditions 5, 10 and 20 years into the future. The results of the power flow analysis indicate that the planned system performs reliably for the forecasted loads, generation resources and transmission services over the planning horizon. Page 19

26 Idaho Power Company This page left blank intentionally. Page 20

27 Idaho Power Company Appendix A Appendix A Community Advisory Committee Process 1. Background The process develops a plan to meet needs through buildout, regardless of when that occurs. The process is possible due to an effective collaboration driven by significant commitment from both Idaho Power and the specific area community. Idaho Power dedicates significant skilled staff resources through the integral participation of planners and engineers to support the technical needs of the process. The unique community needs, interests and goals are represented through the Community Advisory Committee; a broad-based participation of elected officials, businesses, landowners, planners, agencies and other key stakeholders. The result is an effective blend of technical and non-technical input, combined to develop an electrical plan that is both technically sound and sensitive to each area s needs. 2. Purpose of the Electrical Plan Process To create a clear and documented electrical energy supply plan to serve the load needs of the area from now through buildout. The public process is the starting point of all electrical supply plans and any resulting transmission rights-of-way and substation siting requirements 3. The Planning Process The planning process follows a specific outline of steps, divided into three basic components; education, infrastructure siting and plan implementation. The overall process typically involves 9 to 12 months beginning with education, followed by development of community criteria and alternatives, to a committee consensus decision for the final plan. Committee input is focused on two primary areas; where to, and where not to locate new infrastructure such as transmission lines, substations, etc. to be acceptable to the community, and recommendations for related delivery, conservation and demand-side management programs to support desired implementation of electrical service in the area. In general, the planning process does not address recommendations for electrical generation or future high voltage (500kV) transmission lines to move electricity into and through the region. 4. Typical Planning Steps Meeting 1: Bus Tour Committee orientation and ground rules Idaho Power introduction and overview Electric Power 101 Meeting 2: Education Generation Idaho Power voltage levels Transmission including Gateway West, etc. Substation Page 21

28 Appendix A Idaho Power Company Meeting 3: Education (continued) Meeting 4: Education (continued) Meeting 5: Infrastructure Mapping Meeting 6: Mapping and Evaluation Meeting 7: Preferred Alternatives Rates and regulatory Demand side management (energy efficiency) Planning area existing electrical system conditions Begin developing community criteria Confirm community criteria Future electrical buildout needs Transmission & related components to meet buildout needs Initial alternative discussion Review of community criteria Mapping/alternatives development orientation Small group mapping exercises Mapping/alternatives development review and feedback Resume mapping exercises if needed Evaluation/scoring matrix orientation Alternatives evaluation and scoring process Identify preferred alternatives for each of the planning areas Meeting 8: Plan Consensus Verify/confirm preferred alternative(s) and ranking Meeting 9: Plan Document and Next Steps Develop implementation plan Discuss local plans coordination Review draft plan Comments Plan rollout discussion 5. The Community Advisory Committee The Community Advisory Committee for each of the Electrical Plans includes individuals, representing a broad cross section of elected officials, local governments, businesses, community development organizations, planning entities, landowners, affected agencies, environmental organizations, and other key stakeholders. Together, they provide both individual and regional perspective regarding the key issues and concerns that are important to the specific area residents when meeting the long-term electrical needs for that area Advisory Committee Purpose Develop consensus support and lend credibility for identified electrical energy supply improvements necessary to serve the area. Page 22

29 Idaho Power Company Appendix A Advisory Committee Role Propose ideas and solutions to Idaho Power s load serving needs that meet the area through buildout. 6. Benefits and Uses of the Plan The development of the Electrical Plans provide two primary benefits; First, the completed document outlines a specific plan based on community goals, with a range of acceptable alternatives for Idaho Power to follow as it implements specific infrastructure projects to meet the area s electrical needs through buildout. Second, the planning process develops significant community awareness and support that is critical to successful project development that is acceptable to community residents. In addition to its use by Idaho Power, the plan is also intended for use by local jurisdictions, governments and affected agencies through incorporation into local planning documents. The plan is also a key tool for use by economic development organizations in support of existing and potential new businesses to the region. Finally, it is important to note that the plan is intended to be a living document, that can be adjusted with additional advisory committee and community input to respond to significant changes in electrical needs of the area. 7. Summary of Community Plans Electrical Plans Year Completed Updates Year Updated Treasure Valley Electric Plan 2006 Revised for Birds of Prey Area 2007 Wood River Electric Plan 2007 Ongoing Magic Valley Electric Plan 2008 Planned for 2118 Eastern Idaho Electric Plan 2009 Planned for 2019 Western Treasure Valley Electrical Plan 2011 Planned for 2021 Eastern Treasure Valley Electrical Plan 2012 Planned for 2022 Page 23

30 Appendix A Idaho Power Company This page left blank intentionally. Page 24

31 Idaho Power Company Appendix B Appendix B Twenty-year project list Table B-1 Projects planned for 1-5 year horizon Region Time Frame Project Title Project Scope Treasure Valley 5 year Install 138 kv series reactor on the Mountain Home Junction 1 - Lower Malad line Treasure Valley 5 year Add 138 kv series reactor on the Dram-Lucky Peak line Treasure Valley 5 year Add 138kV series reactor on the Mountain Home Junction -Upper Salmon 1&2 line Install a 138 kv series reactor on the Mountain Home Junction 1-Lower Malad 138 kv transmission line. Install a 138 kv series reactor at Dram on the Dram- Lucky Peak transmission line. Install a 138 kv series reactor at Mountain Home Junction on the Mountain Home Junction -Upper Salmon 1&2 transmission line. Treasure Valley 5 year Build new 138 kv line from Bowmont to Happy Valley Build new 138 kv Bowmont to Happy Valley line to improve reliability and integrate B2H project into the Treasure Valley. Southern 5 year Build new 138 kv transmission line and new 138 kv distribution station to serve Buhl Build new 138 kv distribution station east of Buhl and construct a new 138 kv transmission line to meet future load growth. Southern 5 year Rebuild 138 kv line from King to Moonstone Rebuild existing 138 kv line between King substation and Moonstone substation to improve reliability and performance to the Wood River loop. Southern 5 year Build 138 kv line from Wood River to Ketchum Build a 2 nd 138 kv line into Ketchum substation to improve reliability in the Ketchum area Treasure Valley 5 year Add circuit breakers at Chestnut substation Install circuit breakers at Chestnut substation to increase reliability in the Nampa area Eastern 5 year Rebuild Goshen-Big Grassy 161 kv line Rebuild existing 70+ year old 161 kv line Treasure Valley 5 year Build new Lakeshore distribution substation Construct new kv distribution substation south of Nampa near Lake Lowell. Treasure Valley 5 year Build new 138 kv line from Lowell Junction to new Lakeshore substation Build a 138 kv transmission line to serve the new Lakeshore substation south of Nampa near Lake Lowell. Page 25

32 Appendix B Idaho Power Company Table B-2 Projects planned for 5-10 year horizon Region Time Frame Project Title Project Scope NTTG 10 year Boardman to Hemingway 500 kv Line Build a new 500 kv transmission line from Boardman, Oregon area to Idaho Power s Hemingway substation. Treasure Valley 10 year Hemingway-Bowmont Build 230 kv line Add the second 230 kv line circuit on existing structures from Hemingway to Bowmont to integrate B2H project into Treasure Valley. Treasure Valley 10 year Hubbard-Bowmont Build 230 kv line This project uprates the existing 138 kv line from Bowmont-Hubbard to 230 kv to integrate B2H project into Treasure Valley. Treasure Valley 10 year Add T MVA 230/138 kv tie transformer at BOMT Add a second 300 MVA 230/138 kv transformer t at Bowmont to integrate B2H project into the Treasure Valley Treasure Valley 10 year Hubbard-Hemingway 230kV Line Terminal Install a 230 kv line terminal at Hubbard to integrate B2H project into Treasure Valley. Treasure Valley 10 year Kuna-Bowmont Build 138 kv line Build new 7 mile 138 kv line from Kuna Tap to Bowmont to serve Kuna after the existing 138 kv line between Bowmont and Mora/Hubbard is converted to 230 kv. Treasure Valley 10 year Willis-Star Build 11 mile 138 kv line Build a new approximately 11 mile 138 kv transmission line between Willis and Star to improve reliability in the area. Southern 10 year Add 200 MVA 230:138 kv transformer at Midpoint Add a 200 MVA 230:138 kv transformer at Midpoint to relieve overload concerns. Treasure Valley 10 year Gem-Houston Rebuild 6.5 miles to 138 kv Rebuild Gem-Houston 69 kv line to 138 kv. Treasure Valley 10 year Add 230/138 kv capability at Cloverdale Add a 230 kv line terminal and T /138 kv 300 MVA transformer in the north side of the station. Treasure Valley 10 year Add Cloverdale 230 kv terminal Add a 230 kv terminal for the new line to Cloverdale substation. Western 10 year Parma-Nyssa Rebuild 9 miles Rebuild 9 miles of existing Parma-Nyssa 69 kv transmission with 138 kv insulation. NTTG 10 year Gateway West 500 kv Line Bridger to Populus Build a new 500 kv transmission line from Jim Page 26

33 Idaho Power Company Appendix B Region Time Frame Project Title Project Scope Bridger station in Wyoming to Populus station in Southeastern Idaho. NTTG 10 year Gateway West 500 kv Line Populus to Hemingway Build a new 500 kv transmission line from Populus Station in Southeastern Idaho to Hemingway Station in Southwestern Idaho. Treasure Valley 10 year Build 138 kv line from Zilog substation to new Cherry substation Obtain ROW and build about 2.2 miles 138 kv transmission line from Zilog tap to the new Cherry substation. Treasure Valley 10 year Build new Cherry distribution substation Construct new kv distribution substation at the SE corner of Cherry Lane and Can-Ada in Nampa. Western 10 year Parma-Wilder Build 8 miles Build 8 miles from Parma to Wilder to operate at 69 kv. Western 10 year Relieve N-1 overload on Ontario tie bank Add 3 rd tie bank or upgrade existing tie banks at Ontario. Treasure Valley 10 year Relieve N-1 overload on Locust tie bank (per 2012 TPL-002 Study Results) Construct a new 138 kv line between Blackcat and Zilog substations. Eastern 10 year Build 138 kv line between Kramer and Pingree Build a new 138 kv transmission line between Kramer substation and Pingree substation to provide a second source to the 46 kv system served out of Pingree Treasure Valley 10 year Build new Wagner distribution substation Construct new kv distribution substation in the area of Farmway and Purple Sage Road Treasure Valley 10 year Build new 138 kv line between existing Willis substation and new Wagner substation Construct a new 138 kv circuit from existing Willis substation to the new Wagner substation. Page 27

34 Appendix B Idaho Power Company Table B-3 Projects planned for year horizon Region Time Frame Project Title Project Scope Treasure Valley 20 year Build new Beacon Light Substation Build new Beacon Light distribution substation in the area northwest of Eagle. Treasure Valley 20 year Star-Beacon Light Build new 138 kv line Extend 138 kv line approximately 2 miles to new Beacon Light substation. Treasure Valley 20 year Build Eagle loop 138 kv line Build new approx 5 mile 138 kv transmission line from the Locust 230 kv station to the corner of Linder Rd and State St. This line will improve reliability to customers in the area. Western 20 year Parma-Caldwell Rebuild 16 miles to 138kV Rebuild 16 miles of 69 kv transmission between Parma-Caldwell with 138 kv insulation. Western 20 year Parma-Nyssa Rebuild 9 miles to 138kV Rebuild 9 miles of 69 kv transmission between Parma-Nyssa with 138 kv insulation. Southern 20 year New 138 kv switching station south of Jerome Build a 138 kv switching station south of Jerome to break up Dale-Hunt, Upper Salmon 1&2-Cliff and Midpoint-Twin Falls lines. Southern 20 year Poleline-Filer Build 6 new 6 mile 138 kv line Build 6 miles of new 138 kv transmission line from Poleline substation to Filer substation. Convert Filer from 46 kv to 138 kv. Western 20 year Rebuild 10 miles from Emmett to Montour Rebuild 69 kv line from Emmett to Montour station. Construct at 138 kv. Treasure Valley 20 year Build new Amity distribution substation Construct new kv distribution substation at Amity and Ten Mile Roads. Treasure Valley 20 year Build 138 kv 4.5 mile line from Happy Valley to new Amity substation Southern 20 year Add 230 kv and 138 kv capability at Cedar Hill Build a new 138 kv transmission line from the Happy Valley station to the new Amity distribution substation at Amity and Ten Mile Roads. Add tie bank(s) at the proposed Cedar Hill substation to serve the Magic Valley area loads. Southern 20 year Build 138 kv line from Cedar Hill to Artesian Build a new 138 kv line from the Cedar Hill station to Artesian substation. Page 28

35 Idaho Power Company Appendix B Region Time Frame Project Title Project Scope Southern 20 year Build new 4 mile 138 kv line to serve South Park substation at 138 kv. Build new 4 mile 138 kv transmission line between Twin Falls substation and South Park substation. Southern 20 year Build 138 kv line from Hydra to Flat Top Build a new 138 kv line from Hydra substation to Flat Top substation. Southern 20 year Build 138 kv line from Flat Top to Midpoint Build a new 138 kv line from Flat Top to substation Midpoint substation. Treasure Valley 20 year Build Garden City Substation Construct new Garden City substation. The station will be sourced off a tap on the existing Ustick Boise 138 kv line. Southern 20 year Upgrade Shoshone station to 138 kv Convert Shoshone station from 46 kv to 138 kv Western 20 year Emmett-Lake Fork Build 90 miles 138 kv line Build new 138 kv transmission line and remove the existing 69 kv line between Emmet and Lake Fork. Treasure Valley 20 year Build Dry Creek 230 kv hub station Construct new Dry Creek 230/138 kv station to provide a source to the north side of the Treasure Valley Treasure Valley 20 year Build 230 kv double circuit to Dry Creek 230 kv station Southern 20 year Connect Hagerman to the Lower Malad-King 138 kv line Connect new 230 kv Dry Creek substation to existing Brownlee-Boise Bench 230 kv line Connect Hagerman to the Lower Malad-King 138 kv line Treasure Valley 20 year Boise Bench-Blacks Creek Rebuild 8 miles to 138kV Rebuild the existing 69 kv Boise Bench - Blacks Creek line to 138 kv. Treasure Valley 20 year Blacks Creek-Orchard Rebuild 10 miles to 138kV Rebuild the existing 69 kv Blacks Creek-Orchard line to 138 kv. Treasure Valley 20 year Orchard-Elmore Rebuild 8 miles to138kv Rebuild the existing 69 kv Orchard-Elmore line to 138 kv. Treasure Valley 20 year Add second 230 kv line terminal at Nampa and convert 230 kv tap into in/out Add 230 kv line terminal and convert Nampa to an in/out station on the existing HBRD-NMPA-CDWL 230 kv line. Page 29

36 Idaho Power Company Thank you for your interest. Page 30

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

WestConnect Regional Planning Update

WestConnect Regional Planning Update WestConnect Regional Planning Update WRP Energy Committee May 4, 2015 Webinar Outline WestConnect Overview Membership, Structure & Footprint Planning process and regulatory status Order 890 Update (2014)

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

ERCOT Independent Review of Houston Import RPG Project

ERCOT Independent Review of Houston Import RPG Project ERCOT Independent Review of Houston Import RPG Project ERCOT System Planning 2014 Electric Reliability Council of Texas, Inc. ERCOT Regional Planning ERCOT Independent Review of Houston Import Project

More information

REDACTED. Eastside Needs Assessment Report Transmission System King County. Redacted Draft. October 2013 Puget Sound Energy

REDACTED. Eastside Needs Assessment Report Transmission System King County. Redacted Draft. October 2013 Puget Sound Energy Eastside Needs Assessment Report Transmission System King County Redacted Draft October 2013 Puget Sound Energy Report prepared by: Thomas J. Gentile, P.E. Quanta Technology Donald J. Morrow, P.E. Quanta

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

Idaho Power sincerely thanks the members of the Eastern Treasure Valley Electrical Plan, Community Advisory Committee.

Idaho Power sincerely thanks the members of the Eastern Treasure Valley Electrical Plan, Community Advisory Committee. Idaho Power sincerely thanks the members of the, Community Advisory Committee. Rebecca Arnold Lisa Bachman Adam Bartelmay Richard Beck John Bialke Chris Bryant Alan Christy Mark Eriksen Sharon Fisher Sally

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Southeastern Regional Transmission Planning (SERTP)

Southeastern Regional Transmission Planning (SERTP) Southeastern Regional Transmission Planning (SERTP) December 2014 Regional Transmission Planning Analyses I. Overview of Regional Analyses SERTP sponsors plan and expand the transmission system to reliably

More information

2013 CARIS Phase 1 Report

2013 CARIS Phase 1 Report 2013 CARIS Phase 1 Report Timothy Duffy Manager, Economic Planning New York Independent System Operator Business Issues Committee September 18, 2013 KCC 2013 New York Independent System Operator, Inc.

More information

Chapter 7: Transmission

Chapter 7: Transmission Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key Findings... 1 Background... 1 Northwest Transmission Planning... 6 SUMMARY OF KEY FINDINGS For a number of years

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Preliminary Plan of Development

Preliminary Plan of Development June 2010 Boardman to Hemingway Transmission Line Project Prepared By: Idaho Power Company 1221 West Idaho Street Boise, ID 83702 Prepared By Idaho Power Company 1221 West Idaho Street Boise, ID 83702

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE In this Section: Overview Evaluation of Initial Requests Rollover Request Competing Request Competing Examples 1.0 OVERVIEW Pursuant to Section 2.2

More information

Transportation Electrification Public Input Workshop. August 3, 2016

Transportation Electrification Public Input Workshop. August 3, 2016 Transportation Electrification Public Input Workshop August 3, 2016 1 Agenda Welcome and Introductions Company Overview Existing Transportation Electrification Initiatives Accelerating Transportation Electrification

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Western NY Public Policy Transmission Report

Western NY Public Policy Transmission Report Western NY Public Policy Transmission Report Dawei Fan Supervisor, Public Policy and Interregional Planning ESPWG/TPAS July 20, 2017, KCC Agenda Public Policy Transmission Planning Process Western NY Public

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail Application No. -0- Exhibit PAC/00 Witness: Richard A. Vail BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Investment in Distribution and Transmission Systems April 0 PAC/00

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information