Main Transmission System Planning Guideline

Size: px
Start display at page:

Download "Main Transmission System Planning Guideline"

Transcription

1 Main Transmission System Planning Guideline February, 2005 Page i Rev /04/04

2 NOTICE COPYRIGHT 2000 TRANS POWER NEW ZEALAND LIMITED ALL RIGHTS RESERVED The information contained in the report is protected by copyright vested in Trans Power New Zealand Limited ( Trans Power ). The report is supplied in confidence to you solely for your information. No part of the report may be reproduced or transmitted in any form by any means including, without limitation, electronic, photocopying, recording, or otherwise, without the prior written permission of Trans Power. No information embodied in the report which is not already in the public domain shall be communicated in any manner whatsoever to any third party without the prior written consent of Trans Power. Any breach of the above obligations may be restrained by legal proceedings seeking remedies including injunctions, damages and costs. LIMITATION OF LIABILITY/DISCLAIMER OF WARRANTY Trans Power make no representation or warranties with respect to the accuracy or completeness of the information contained in the report. Unless it is not lawfully permitted to do so, Trans Power specifically disclaims any implied warranties of merchantability or fitness for any particular purpose and shall in no event be liable for, any loss of profit or any other commercial damage, including but not limited to special, incidental, consequential or other damages. TABLE OF CONTENTS Page ii Rev /04/04

3 1. INTRODUCTION RELIABILITY DEFINITION CRITERIA Single contingency criterion Maintenance outage... Error! Bookmark not defined. An underlying assumption of the N-1 criteria is that maintenance is carried out during times of light load.... Error! Bookmark not defined Multiple contingency Sub-station arrangement RELIABILITY ASSESSMENT Load Dispatch STEADY STATE PERFORMANCE CRITERIA EQUIPMENT RATINGS Grid owner equipment Generating Unit Rating VOLTAGE QUALITY Normal Steady State Voltage Step Change in Voltage - Dynamic SHORT CIRCUIT LEVELS STABILITY CRITERIA TRANSIENT STABILITY Disturbances selected for testing Auto-reclose of Circuit Breakers Fault Clearing Time Transient Voltage Performance Criterion Over-voltages due to Load Rejection DYNAMIC STABILITY VOLTAGE STABILITY FREQUENCY STABILITY... ERROR! BOOKMARK NOT DEFINED. APPENDIX A: SECURITY CRITERIA APPENDIX B: INFREQUENT SWITCHING CRITERIA APPENDIX C: TRANSIENT STABILITY DISTURBANCES APPENDIX D: DAMPING CRITERIA FOR DYNAMIC STABILITY Page iii Rev /04/04

4 1. Introduction The purpose of transmission system planning is to develop a reliable and efficient transmission system for transferring power from areas of generation to areas of demand (load) under varying system conditions, while operating equipment within accepted ratings. The system conditions include - changing demand patterns, generation changes and equipment outages (planned or unplanned). The planning process involves applying a number of criteria: technical, economic, environmental and safety to the current or future transmission system. This document sets out the technical criteria to be applied in planning the main transmission network. While this document is focused on technical criteria only, readers are reminded that any proposed transmission development must also consider all other planning aspects such as environmental, economic, etc. The technical criteria used in transmission system planning can be divided into three main categories, which are covered in this Guideline as per Table 1.1: Table 1.1: Technical Criteria Category Defined as Section System reliability Is the system adequate and secure? 2 Steady state Is the normal operating state of the system 3 performance within prescribed limits? Stability Does the system remain normal or return to normal following a disturbance? 4 Additionally, for comparison purposes, the Appendices provide an international context to the standards and criteria that Transpower applies in meeting each of these activities. 2. System Reliability 2.1 Definition The accepted definition of transmission system reliability incorporates assessment of two basic aspects of the system - adequacy and security. The National Electricity Reliability Council, USA (NERC) 1 has defined these terms to mean: Adequacy The ability of the electric systems to supply aggregate electrical demand and energy requirements of their customers at all times, taking into account scheduled and reasonably expected unscheduled outages of system elements; and Security The ability of the electric systems to withstand sudden disturbances such as electric short circuits or unanticipated loss of system elements. 1 The National Electricity Reliability Council oversees and co-ordinates reliability and security for the entire United States. Page 1 Rev /04/04

5 2.2 Criteria Transpower uses a deterministic approach to planning. This approach is consistently applied in most transmission networks throughout the world. 2 The deterministic planning criteria uses N, (N- k ) terminologies to describe the service level for which a system is planned, where k is the number of elements out of service at any one time. These terms are defined as follows: (N) criterion denotes that the system is planned such that with all transmission facilities in service the system is in a satisfactory state and loads may have to be shed to return to a satisfactory state for a credible contingency event. It could be said that an N security policy results in a system that is not secure against contingent events. (N- k ) criterion denotes that the system is planned such that with all transmission facilities in service the system is in a secure state and for any k credible contingency event(s) the system moves to a satisfactory state. If any further contingency events were to occur loads may have to be shed to return to a satisfactory state Single contingency criterion The main interconnected transmission system shall be designed to maintain N-1 security criterion, meaning that the system is in a secure state with all transmission facilities in service and in a satisfactory state under credible contingent events. N-1 is a common security standard in many countries including Australia, Ireland, Denmark and France 3. The single contingencies to be considered under an N-1 criterion are: loss of a single transmission circuit loss of a single generator loss of an HVDC pole loss of a single bus section loss of an interconnecting transformer loss of a single shunt connected reactive component, e.g. capacitor bank, SVC The loss of an element could be either planned (as part of scheduled maintenance) or unplanned (as an unforeseen event) either by inadvertent disconnection or as a consequence of a fault occurring in/on the affected element Maintenance outages An underlying assumption of the N-1 criteria is that maintenance is carried out during times of light load so that the risk and consequences of an interruption due to unforseen events is minimised. 2 A 1992 survey by CIGRE confirmed that of 24 countries participating, all used the deterministic criteria 3 Refer to Appendix A for further detail. Page 2 Rev /04/04

6 2.2.3 Multiple contingency The risk and consequences of less frequent but more extreme credible contingencies must also be investigated to determine what emergency measures may be required to minimise the consequences and provide for restoration of supply in the shortest possible time Sub-station arrangement The sub-station arrangements are chosen to satisfy all the reliability performance criteria set out in this guideline while allowing for future extensions and maintenance. 2.3 Reliability Assessment Reliability is assessed by simulating performance of the system with all transmission facilities in service and then applying credible contingencies to the simulation, while generation and load patterns are varied to determine whether a satisfactory state for the system may be maintained for the various generation and load patterns Load All simulation studies shall be performed for system peak load conditions for both summer and winter periods. Studies may also be performed for light load conditions where required. These latter studies may be necessary, for example, where experience has identified that certain system issues arise only under light or trough load conditions. If a part of the system is radial, the studies for the radial part of the system must be carried out for peak load conditions for that area Dispatch Simulation studies shall be carried out for the worst case credible generation dispatch scenarios. For hydro generation (New Zealand s main source of electricity), these include dry, average and wet hydrological scenarios. 4 Studies shall also be carried out for extreme dry scenarios to identify emergency measures that may have to be put in place. 4 These have been developed within Transpower using information from a number of sources including NIWA Page 3 Rev /04/04

7 3. Steady State performance The steady state criteria apply to normal operating conditions and to post-disturbance conditions once the system settles to new operating conditions. The steady state performance criteria for planning are: Primary transmission equipment must operate within normal ratings when all transmission facilities are in service. Primary transmission equipment must operate within acceptable short term ratings during contingencies. There is no load curtailment required to maintain N-1 security level for any operating condition. Voltage quality is maintained as set out in section 3.2 Cascading outages do not occur. 3.1 Equipment Ratings Grid owner equipment The grid owner equipment ratings used are drawn from Transpower s Asset Capability Information (ACI) database. The ratings for equipment in this database are in accordance with Transpower policy document TP.GG on equipment ratings, which take into account manufacturer s recommendations, the age of equipment and local environmental conditions. The database includes all transmission equipment: lines, transformers, switchgear, protection and reactive equipment - synchronous condensers, capacitors, reactors and SVCs Generating Unit Rating The rating of all generating units connected to the grid shall be the ratings provided by the Generators as part of their Asset Capability Statement provided to Transpower ( as the Grid Owner). 3.2 Voltage Quality The criteria for voltage in steady state operation are defined by limits set for different conditions: Normal steady state voltage Step change in voltage Sustained steady state voltage (after tap changing, Reactive Power Controller and other dynamic sources actions ) These are discussed in the following subsections. Page 4 Rev /04/04

8 3.2.1 Normal Steady State Voltage The normal steady state voltage at buses shall be as specified in Table 3.1 or as stipulated in the contract agreement with the customer. Table 3.1 is consistent with the steady state voltage limits as prescribed in Rule 3.1, Section III, Part C of the Electricity Governance Rules and Regulations (EGRS). Table: 3.1 Voltage Limits During Normal Conditions Nominal Voltage (kv) Maximum Voltage (kv) Minimum Voltage (kv) Step Change in Voltage - Dynamic The voltage step change is the dynamic voltage change between the pre-switching voltage and the prevailing voltage in the period immediately after transient decay and AVR action but before any manual or slow control action e.g. manual tap changing, automatic tap changing, manual switching of capacitor banks under normal operating conditions. The allowable voltage deviation depends on the frequency of switching infrequent or routine Routine Switching The Australasian standard 5 for acceptable voltage deviation during routine switching is set out in Table 3.2: Table 3.2 Allowable Dynamic Voltage Deviation r no of events per hour Vdyn/Vn (%) MV HV r < r < r < r Note: MV refers to 1 kv < V N 35 kv MV refers to 35 kv < V N 230 kv Vdyn/Vn Maximum voltage change for normal operating conditions The voltage change at buses for routine switching of equipment to control voltage (e.g. switching of capacitor banks or circuits) must not exceed the value given in Table 3.2. Currently Transpower plans on the basis of a 2% voltage dip for routine switching - this is slightly more conservative than set out in the AS/NZS standard. 5 Australian/New Zealand Standard - AS/NZS :2001, Page 5 Rev /04/04

9 Infrequent switching There are no standards specifying the allowable voltage deviation for infrequent switching, but it would naturally be greater than for routine switching operations. Transpower has designed the system based on a 5% variation. Worldwide, the allowable voltage deviation is 5% to 6% depending on the utility Short circuit levels The default planned maximum short circuit levels are shown in Table 3.3. There are a limited number of locations, such as Otahuhu 110 kv and Islington 66 kv buses, where the maximum fault levels will exceed the default maximum short circuit levels shown, and these are documented in other Grid Owner documents. Table Maximum Short Circuit Power and Current Limits Nominal Voltage Maximum short-circuit Power and Current Limits kv MVA ka , , , , , Stability Criteria The stability of a power system is determined by its ability to remain stable when the system is subjected to any disturbance. It can be further divided into four categories of stability: Transient Stability Dynamic Stability Voltage Stability Frequency Stability. These are discussed in the following subsections. 4.1 Transient Stability Transient stability refers to the ability of the system to maintain synchronism when it experiences large disturbances like a line fault or loss of a generator. 6 Refer to Appendix B for further information Page 6 Rev /04/04

10 4.1.1 Disturbances selected for testing A key input into assessing transient stability is identification of the most severe disturbance on the system. Transpower has identified 7 types of significant disturbance, from which the most severe disturbance must be identified. The seven disturbance types are: (1) a 3-phase fault on a circuit close to a substation cleared in main protection clearance time by opening the circuit breakers at each end of the circuit to disconnect the circuit (2) a 3-phase fault on a circuit close to a substation cleared in main protection clearance time by opening the circuit breakers at each end of the circuit and reclosing on fault with subsequent reopening of the circuit breakers at each end to disconnect the circuit (3) a 3-phase fault on a transformer followed by disconnection of the transformer (4) a 3-phase fault on a bus section cleared by the bus zone protection operation of all circuit breakers connected to the faulted bus section. (5) a single-phase-to earth fault on a circuit cleared by the back-up protection operation of the circuit breakers at each end of the circuit. (6) a single-phase-to earth fault on any circuit cleared by circuit breaker failure protection of the relevant back-up circuit breakers. (7) a sudden disconnection of any plant including a generating unit This list of disturbances is similar to those used by overseas utilities. Refer to Appendix C for more detail Auto-reclose of Circuit Breakers Automatic reclosing may be employed on all transmission lines to enhance security. However, the system must be planned such that the system is stable without reclosure. The system must also be tested for stability with unsuccessful operation of the auto re-closing facility. If the studies show that fast re-closure onto a fault makes the system unstable, the dead time may be increased sufficiently to make the system stable. Alternatively, auto-reclose may be enabled for a single-phase fault and disabled for a 3-phase fault. Autoreclosing at line terminals that are in electrical proximity to turbine-generators may subject them to excessive shaft torque and winding stresses with resultant loss of life. These effects should be evaluated before autoreclosing is applied. Autoreclosing a region (with only one substation or group of substations) connected to the main transmission grid through a single circuit with no generators or limited generation in the region can cause voltage and/or frequency disturbances. There is a possibility of sustained low voltage or even voltage collapse depending on the type of load and the amount of load. These effects should be evaluated fully before applying auto reclosures. Page 7 Rev /04/04

11 4.1.3 Fault Clearing Time Where the exact fault-clearing times are not known, the following fault clearing times shall be used in simulation studies: Main protection for 220 kv circuits: 120 msec. Main protection for 110 kv circuits: 200 msec Main protection for 66 kv circuits: 200 msec CB failure time: 350 msec Transient Voltage Performance Criterion The performance criteria for transient voltage performance for large disturbances are: For single contingencies, the transient voltage dip after the fault is cleared should not exceed 25% at load buses or 30% at non load buses. Furthermore, at load buses, voltage dip should not exceed 20% for more than 20 cycles. For multiple contingencies, the transient voltage dip after the fault is cleared should not exceed 30% at load or non-load buses. Furthermore, at load buses, voltage dip should not exceed 20% for more than 20 cycles. This criteria has been adopted from the Western Electricity Co-ordinating Council 7 (WECC) planning standard, which is also applied in Western Australia Over-voltages due to Load Rejection Power frequency over-voltages due to load rejection must be limited to values within the over voltage envelope shown in Figure 4.1 Figure 4.1 Acceptable Overvoltage Envelope Post-Disturbance Voltage Ratio = Pre-Disturbance Voltage pu pu 3 Cycles Time(Cycles) 7 Formerly the Western System Coordinating Council. Represents at least 40 electricity providers on the Western seaboard of North America from Canada through to northern Mexico. Page 8 Rev /04/04

12 4.2 Dynamic Stability Dynamic stability refers to the ability of a power system to withstand small changes in loads, switching of lines and also to return to a satisfactory state following large disturbances like a line fault. The main problem in dynamic stability is with electromechanical oscillations of increasing amplitude between generators, causing generators to lose synchronism unless there is positive damping of these oscillations. The damping criterion set by Transpower is that the oscillations must decay within 12 seconds (settling time). If oscillations do not settle within the time specified, appropriate measures must be taken to damp the oscillations. The 12 second decay time is similar to that used by most other utilities. Refer to Appendix D for more information. 4.3 Voltage Stability Voltage stability refers to the ability of the system to maintain voltage at all buses under steady state conditions, for any disturbance, such as a variation in load or an outage of circuit(s). During periods of voltage instability, voltage drops progressively, leading to low voltage throughout the system/region. When voltage throughout the system/region reaches and stays at low values, the system is considered to have reached voltage collapse. How near the system is to voltage instability can be assessed on the basis of real and reactive power margins for the system or particular region concerned. Note that the voltage stability margin may not always be a reliable indicator. For example in a heavily reactive power compensated system, instability can occur even at high voltages. There are no international standards on acceptable real or reactive power margins, as this depends very much on the system. The criteria adopted by Transpower are drawn from the Western Electric Co-ordinating Council (US) 8 report and are based on Q-V and P-V analyses. They are: i) For the outage of a single element, (a generator, circuit, transformer or any reactive source), the real power (MW) margin must be 5% as measured from the nose point of the P-V curve. ii) The reactive power (Mvar) margin at the most reactive-deficient bus must have an adequate reactive power margin for the worst single contingency, to satisfy either a 5% increase beyond maximum forecast loads or a loss of reactive support close to the bus that is considered most susceptible to voltage collapse and for which the Q-V plots are derived. The worst single contingency is the one causing the largest decrease in the reactive power margin. iii) For outage of a bus section or for a double contingency, the MW margin must be 2.5% as measured from the nose point of the P-V curve. iv) The reactive power (Mvar) margin at the most reactive-deficient bus must have an adequate reactive power margin for the loss of a bus section or a double contingency at 50% of that required for the worst single contingency. 8 Formerly the Western System Co-ordinating Council Page 9 Rev /04/04

13 v) Adequate dynamic reserve should be provided to ensure that voltage during the transient period does not result in a sustained voltage collapse. The static analysis must be supplemented by a limited number of dynamic studies to establish that the static approach is satisfactory. In the dynamic analysis, the effect of generator over-excitation limiters, transformer taps, induction motors, etc should be represented in detail. Page 10 Rev /04/04

14 Appendices Page 11 Rev /04/04

15 Appendix A: Security Criteria Introduction The security criteria adopted by international utilities have been identified by reviewing published papers and by direct correspondence. Generally utilities adopt N-1 or N-2 security criteria for the main transmission grid. Many of the utilities use N-1 security criterion for the main grid and N-2 security criterion for critical loads. The degree to which the transmission networks are meshed and the availability of generation within regions of the transmission network are important factors in determining the appropriate security criteria for a region. Table A.1 gives a comparison of security criteria used by some of the major utilities in the world. More detail can be found in the following country sections. Table A.1 Comparison of Security Standard Utility Security Criterion Remarks Transpower N-1 Maintenance to be carried out at appropriate time without violating N-1 security criteria NECA, Australia N-1 Western Australia N-2 When circuit is out on maintenance, the system is planned to meet only 80% of the demand WECC, USA N-2 No loss of demand. Allows for simultaneous outage of two elements with planned outage of an element but with some load shedding NGC, UK N-2 N-1, N-2 N-2 For the main transmission system A mix of N-1 and N-2 for specific regions, depending on demand Ireland, Belgium, Denmark, N-1 CIGRE 1992 Survey (meshed system with interconnection to neighbouring countries) Finland, France Brazil N-1 Italy N-2 CIGRE 1992 Survey ESB, Ireland N-2 Loss of load is allowed for maintenance events Australia All the Australian utilities, except Western Australia follow the National Electricity Code (NEC) which specifies that the network must be planned, operated and maintained so that it is capable of withstanding any single credible contingency event. The code allows for higher standards to be adopted where appropriate due, for example, to the size and importance of the customer groups. Western Power, Western Australia, specifies N-1 security criterion to meet peak load and (N-2) security criteria to meet 80% of load. Supply to CBD Sydney CBD is supplied by TransGrid over the 330 kv and by Energy Australia over a large 132 kv cable network. The security standard adopted for supply to the CBD allows for the simultaneous outage of a TransGrid 330 kv cable into Sydney and any 132 kv cable or 330/132 kv transformer within the Energy Australia Network. It Page 12 Rev /04/04

16 also allows for outage of any section of a 132 kv busbar. It does not allow for the outage of two 330 kv cables, as this is considered too costly. Supply to the Melbourne and Adelaide CBD s are designed to meet N-2 criteria. The 110 kv supply to the Brisbane CBD is being planned so that full supply is maintained with two 110 kv cables out of service. United States - Western Electric Co-ordinating Council (WECC), WECC also uses (N-2) criterion for planning the transmission grid. However, there are some differences in defining contingencies: WECC considers bus section outage as a double contingency not a single contingency. WECC allows for unplanned outage of two elements with planned load curtailment or shedding but does not specify the percentage of load that is met under such conditions. United Kingdom - National Grid Company (NGC) The security standard adopted by NGC for the main interconnected transmission system is (N-2). However, there are significant differences between the NGC system and the New Zealand system; the NGC system is heavily meshed with generation in diverse areas, whereas the New Zealand system is comprised of a weak, longitudinal transmission with significant generation located in a few areas, remote from the demand. In addition, the NGC demand is around 10 times that of NZ and due to its density, there are generally alternative supply options to any grid off-take, via the distribution networks, which means the restoration times can be reduced. Table A.2 Security Level for Group Demand Group Initial System Condition Demand Intact System With Single Arranged Outage Over 1500 MW In accordance with main interconnected transmission system planning criteria Over 300 MW To 1500 MW Over 60 MW To 300 MW Immediately No loss of supply Note 1 Immediately Group Demand minus 20 MW Note 2 Within 3 hrs No loss of supply Immediately Maintenance Period Demand Within time to restore arranged outage Group Demand Within 3 hrs Smaller of (Group Demand minus 100 MW) and 1/3 Group Demand. Within time to restore arranged outage Group Demand Page 13 Rev /04/04

17 Up to 60 MW Within 15 min Smaller of (Group Demand minus 12 MW) and 2/3 Group Demand Within 3 hrs No loss of supply Nil Note 1 The maintenance period demand is 67% of the group demand. Note 2 The group demand are the forecast maximum demand. The NGC also defines separate planning criteria for areas of grouped demand. The security standards for these areas is such that, for an outage of any of the following: a) A single transmission circuit; or b) A single transmission circuit with a single arranged outage of another transmission circuit, generating unit or any reactive supporting equipment, any loss of supply shall be in accordance with Table A.2. Ireland - ESB National Grid ESB National grid plans their system for N-2 security criteria. However, they allow for some loss of load for an unplanned outage when another transmission element is on planned outage. International Surveys CIGRE published a report in 1992 on a survey carried out on standard used in transmission planning. Twenty four countries participated in this survey. The findings from the survey are: All countries use deterministic technique for planning. In addition about half use or have probabilistic techniques available. The number of countries that use (N-2) criterion just exceeds the number that use only an (N-1) criterion. However, the definition of (N-2) criteria and its application varies. Some countries consider the outage of double circuits only (not any two circuits); some do not apply the criteria at peak load conditions; and some apply it only for critical loads. Those countries that use N-2' criterion do not also consider the outage of a busbar. 10 of the 24 countries (Brazil, Canada, UK, USA, South Africa, etc) use additional transfer requirements for zones or groups of circuits. Page 14 Rev /04/04

18 Appendix B: Infrequent Switching Criteria Australia Western Australia uses +/-6% voltage change for infrequent switching whereas the regulator overseer - NEC does not make any specific distinction between routine and infrequent switching. Specifically, the NEC code specifies in Clause S5.3.7 that voltage should not exceed the following limit: Where only one Distribution Network Service Provider or Customer has a connection point associated with the point of supply, the limit is 80% of the threshold of perceptibility set out in Figure 1 of AS2279 Part 4; or Where two or more Distribution Network Service Providers or Customers causing voltage fluctuations have a connection point associated with the point of supply, the threshold of perceptibility limit is to be shared in a manner to be agreed between the Distribution Network Service Provider and the Code Participant in accordance with good electricity industry practice. Ireland ESB National Grid (Ireland) allows step voltage changes of 3% for capacitor bank switchings with all transmission facilities in service. It does not specify any step voltage change for infrequent switchings. Page 15 Rev /04/04

19 Appendix C: Transient Stability Disturbances Australia All Australian utilities except Western Power (WA), follow the National Electricity Code in planning their system. The NECA specifies the following disturbances for planning the system: Disconnection of any single generating unit with or without application of a fault Disconnection of any transmission line, with or without the application of a single circuit two-phase-to-ground solid fault on lines operating at or above 220 kv, and a single circuit three-phase solid fault on lines operating below 220 kv. Western Power specifies the following disturbances for planning the system: A three-phase-to-ground fault cleared by main protection A single phase fault cleared by backup protection Single phase auto-reclosing of lines Tripping of lines or transformer without a fault United States The Western Electricity Coordinating Council (WECC) 9, USA specifies the following disturbances for planning the system: a) Single line to ground fault (SLG) or three-phase fault on generator, transformer, or generator cleared by main protection b) Loss of a transmission component - transmission line, transformer, generator without a fault c) SLG fault on bus section or breaker with normal clearing d) SLG fault with delayed clearing on generator, transformer, transmission circuit or bus section. For a) and b) above, no loss of demand is allowed. For other events, depending on system design and expected system, the controlled load shedding and planned removal of some generators is allowed. Additionally, cascading outages are not allowed for any of the above events. United Kingdom The NGC specifies the following disturbances for planning the system: A three-phase-to-ground fault cleared by main protection A single phase fault cleared by backup protection Single phase auto-reclosing of lines Tripping of lines or transformer without a fault 9 Formerly the Western System Coordinating Council. Represents at least 40 electricity providers on the Western seaboard of North America from Canada to northern Mexico. Page 16 Rev /04/04

20 CIGRE CIGRE published a report in 1992 on a survey carried out on standards used in transmission planning. Of the 24 countries participating, 20 (83%) confirmed use of 3-phase faults to test stability. Other findings included: Australia, Brazil and CIS (formerly part of USSR) countries do not plan for 3- phase faults. Australia and CIS use two-phase-to-ground faults and Brazil uses single phase faults. Some countries consider two-phase faults and single phase faults to assess the effect of torsional interaction and voltage transients to generators and industrial users. Page 17 Rev /04/04

21 Appendix D: Damping Criteria for Dynamic Stability The following table compares the criteria across a number of electricity utilities: Utility Damping Criteria Transgrid, VENCorp, Electranet, Western Power Halving time of the least damped oscillations must not be more than 5 seconds. (Australia) Powerlink Damping ratio of at least 0.05 Elsam (Denmark) Oscillations to be damped within seconds Statnet (Norway) Oscillations to be damped within seconds ESB (Ireland) Damping coefficient of not less than 0.05 UK Power frequency oscillations time constant should be less than 12 seconds WECC, (USA) Do not include specific requirement. It is updated from time to time. Page 18 Rev /04/04

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 3 August 2017 INCIDENT CLASSIFICATIONS

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 PREPARED BY: Electricity System Operations Planning and Performance DATE: 22 March 2012 FINAL

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO.1 275 KV BUSBAR ON 30 OCTOBER 2011 PREPARED BY: Electricity System Operations Planning and Performance

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Journal of American Science 2015;11(11)   Integration of wind Power Plant on Electrical grid based on PSS/E Integration of wind Power Plant on Electrical grid based on PSS/E S. Othman ; H. M. Mahmud 2 S. A. Kotb 3 and S. Sallam 2 Faculty of Engineering, Al-Azhar University, Cairo, Egypt. 2 Egyptian Electricity

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014 Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang PREPARED BY: AEMO Systems Capability DATE: 19 May 2014 STATUS: FINAL CONTENTS 1 Introduction... 3 2 The Incident...

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

Experiences with Wind Power Plants with Low SCR

Experiences with Wind Power Plants with Low SCR 1 Experiences with Wind Power Plants with Low SCR Lessons learned from the analysis, design and connection of wind power plants to weak electrical grids IEEE PES General Meeting Denver CO, 26 March 2015

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2. Stakeholder Comment and Rationale Form AESO AUTHORITATIVE DOCUMENT PROCESS Stakeholder Consultation Draft 2012-11-29 Proposed New ISO Rules Section 502.5 Version 2.0 Generating Unit Technical Requirements

More information

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Presenter: Bernard Magoro, System Operator, Transmission Division, Eskom SOC Holdings Date: 05 October 2018 Contents 1. Background

More information

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

HVDC Back-to-Back Interconnections Enabling reliable integration of power system HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013 POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS MARCH 03 PREPARED Y: Systems Capability DATE: 7 June 03 FINAL Disclaimer Purpose This

More information

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha 1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015 TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 AN AEMO POWER SYSTEM OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: August 2016 IMPORTANT

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013 Power System Operating Incident Report Trip of Murray Lower Tumut No.66 0 kv Transmission PREPARED BY: AEMO Systems Capability DATE: 1 December 201 FINAL Version Release History VERSION DATE BY CHANGES

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Emerald Reactive Support Alternative Solution Expressions of interest

Emerald Reactive Support Alternative Solution Expressions of interest Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 PREPARED BY: System Performance and Commercial DATE: 7 March 2013 FINAL Disclaimer Purpose This

More information

EFFECT OF SOLAR PV ON TRANSIENT STABILITY OF THE NEW ZEALAND POWER SYSTEM

EFFECT OF SOLAR PV ON TRANSIENT STABILITY OF THE NEW ZEALAND POWER SYSTEM EFFECT OF SOLAR PV ON TRANSIENT STABILITY OF THE NEW ZEALAND POWER SYSTEM DECEMBER 2017 TECHNICAL REPORT Table of Contents Table of Contents EXECUTIVE SUMMARY... VIII 1 INTRODUCTION...1 1.1 Programme

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS April 2009 Prepared by VACAR Stability Working Group: Kirit Doshi Anthony Williams John O Connor Joe Hood Art Brown Dominion Virginia

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Grid Impacts of Variable Generation at High Penetration Levels

Grid Impacts of Variable Generation at High Penetration Levels Grid Impacts of Variable Generation at High Penetration Levels Dr. Lawrence Jones Vice President Regulatory Affairs, Policy & Industry Relations Alstom Grid, North America ESMAP Training Program The World

More information

Computation of Sensitive Node for IEEE- 14 Bus system Subjected to Load Variation

Computation of Sensitive Node for IEEE- 14 Bus system Subjected to Load Variation Computation of Sensitive Node for IEEE- 4 Bus system Subjected to Load Variation P.R. Sharma, Rajesh Kr.Ahuja 2, Shakti Vashisth 3, Vaibhav Hudda 4, 2, 3 Department of Electrical Engineering, YMCAUST,

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE Yunqi WANG, B.T. PHUNG, Jayashri RAVISHANKAR School of Electrical Engineering and Telecommunications The

More information

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority ,.,.;i')!i,:;;',;~~~. 'ffrff mm I Government of India ~ ~.I Ministry of Power 4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority III ~~~~~~I"1",~~1 ;J' :. r System Planning & Project Appraisal Division

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm

Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm Downloaded from orbit.dtu.dk on: Apr 07, 2019 Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm Arana Aristi, Iván; Johnsen, D. T.; Soerensen, T.; Holbøll, Joachim Published

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

Eric John, ABB FACTS, Raleigh NC

Eric John, ABB FACTS, Raleigh NC CAPER 2017 SUMMER RESEARCH PLANNING WORKSHOP, AUGUST 7-8, 2017 ABB Ensuring Grid Stability as the Power Generation Mix Changes Eric John, ABB FACTS, Raleigh NC ABB Presentation Outline Generation Mix Drivers

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Standards, Procedures and Policies for Grid Connection

Standards, Procedures and Policies for Grid Connection Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED

More information

Performance Analysis of Transient Stability on a Power System Network

Performance Analysis of Transient Stability on a Power System Network Performance Analysis of Transient Stability on a Power System Network Ramesh B Epili 1, Dr.K.Vadirajacharya 2 Department of Electrical Engineering Dr. Babasaheb Ambedkar Technological University, Lonere

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) Nazneen Choudhari Department of Electrical Engineering, Solapur University, Solapur Nida N Shaikh Department of Electrical

More information

Service and Rehabilitation Electrical Power Systems

Service and Rehabilitation Electrical Power Systems Service and Rehabilitation Electrical Power Systems From water to wire 3 ANDRITZ HYDRO Electrical Power System Modernization and rehabilitation International technology group ANDRITZ is a globally leading

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Statcom Operation for Wind Power Generator with Improved Transient Stability

Statcom Operation for Wind Power Generator with Improved Transient Stability Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 4, Number 3 (2014), pp. 259-264 Research India Publications http://www.ripublication.com/aeee.htm Statcom Operation for Wind Power

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

INVESTIGATION OF THE IMPACT OF SWITCHING A HEAVILY LOADED TRANSMISSION LINE ON OPERATION OF A POWER PLANT WITH TURBINE-GENERATOR UNITS

INVESTIGATION OF THE IMPACT OF SWITCHING A HEAVILY LOADED TRANSMISSION LINE ON OPERATION OF A POWER PLANT WITH TURBINE-GENERATOR UNITS Investigation of the Impact of Switching a Heavily Loaded Transmission Line on Operation of a Power Plant with Turbine-generator Units INVESTIGATION OF THE IMPACT OF SWITCHING A HEAVILY LOADED TRANSMISSION

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information