Emerald Reactive Support Alternative Solution Expressions of interest

Size: px
Start display at page:

Download "Emerald Reactive Support Alternative Solution Expressions of interest"

Transcription

1 Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017

2 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions of interest (EOI) to partner with suitably qualified and experienced organisations provide reactive compensation to Emerald Zone Substation. There are two high level options for this replacement. Reactive compensation such as a capacitor/statcom mix could be installed within the substation environment, or with an alternative solution, external to the substation site, such as, reactive output from a solar farm. This EOI is focussed on the Alternative solution. EECL believe an alternative solution may also provide additional benefit such as reduced system losses and also possibly a better economic/financial outcome. As reactive compensation is so important to the operation of the Emerald Network, any failure or late delivery of an alternative solution may put network performance at risk. Given this risk, a similar parallel process is being run for the internal solution, and an assessment will be made by EECL to determine the most appropriate solution. EECL recognises that the reactive requirements can be met with collaboration with external parties which are able to provide an alternative solution, and is interested in initiatives that will provide the same functionality/capability to the Network as an STATCOM/capacitor. Any solution must provide a demonstrable cost benefit for EECL, and meet various requirements which include, among others: The ability to absorb/supply reactive power as required by EECL The ability to interface to EECL operational systems for the dynamic control of the VAR support. High reliability and availability so as to provide firm VAR support On time delivery of the final solution. System availability of 24 hours per day, 7 days per week, with negotiated maintenance periods A likely alternate solution, which EECL considers may be feasible, is the development of a solar farm, where the inverters can be used to also provide dynamic VAR compensation. Other options may include a combination of solar/batteries, or other forms of generation. EECL is also willing to consider a hybrid approach where an alternative solution is combined with a scaled down substation based solution. As an example, a solar farm as an alternative solution could possibly be combined with a scaled down STATCOM within the substation environment. EECL is focussed on exploring all viable options to provide the best technical and economic outcome. The closing date for submissions is the 3 rd of March, page 2

3 Contents 1. Executive Summary Multi stage EOI/offer process Background Existing Emerald Network Existing 66kV Network Capability Insufficient Future 66kV Network Capability System Normal Conditions Safety Net Compliance Technical requirements of solution Stability Requirements Negative Phase Sequence Capability Harmonics Audio Frequency Load Control Reactive System Sizing Possible Solutions Renewable Generation Farm Summary Further information Information a provider is to include in an alternative solution proposal Criteria that will be applied in evaluating proposals page 3

4 2. Multi stage EOI/offer process The alternative supply of VARs for network support is a new concept for EECL and as part of this EOI process EECL is seeking vendor partners who are willing to work collaboratively to develop processes, standards and business models to ensure a sustainable solution. As this is a new concept, EECL are proposing to perform a multi staged EOI process to ensure that a suitable economic and technical solution is arrived at in a collaborative manner. Therefore our EOI process will be as follows: Stage 1, this stage involves an open expression of interest detailing the network needs and key restrictions. The purpose of this stage is to develop an understanding of the market capabilities and desire to provide a specialist solution for the supply of VAR support. Stage 2, involves a closed expression of interest, following a review of the outcomes of the open expression of interest. EECL may or may not enter into a closed expression of interest with selected parties to further explore the detailed technical options for VAR support. At the completion of the EOI process, EECL reserve the right to enter into closed tender negotiations with one or more of the tenderers. 3. Background Emerald is located in the Central Highlands area of the Central Region of EECL s Network. The Emerald town and adjoining rural area, with approximately 8,700 customers, is currently supplied from Ergon Energy s Emerald 66/22kV 3 x 20MVA Zone Substation, which receives supply from a 66kV line from H015 Lilyvale bulk supply substation, and a 66kV line from T032 Blackwater bulk supply substation. The Emerald maximum demand is presently 39.7MVA and is forecast to grow by approximately 1.7% per annum for the next 10 years. The existing 66kV network does not have sufficient capability to supply the forecast increased load at Emerald under system normal conditions, and voltage constraints may start to occur towards the end of this decade. The following Diagrams (Figure 1 and Figure 2) provide an overview of the sub transmission network in the region and the location of Emerald Substation. page 4

5 Figure 1 - Emerald Subtransmission Network page 5

6 Figure 2 - Location of Emerald Substation 3.1. Existing Emerald Network The Emerald area, with approximately 8,700 electricity customers, is currently supplied from Ergon Energy s Emerald 66/22kV 3 x 20MVA Zone Substation. Emerald Zone Substation is supplied by two 66kV subtransmission lines, one from each from the Lilyvale and Blackwater bulk supply substations. The Blackwater line also supplies the Comet 5+2MVA Zone Substation via a tee-off. There are currently two 5MVAr capacitor banks installed at Emerald Zone Substation to compensate for the reactive power demand in the downstream distribution network, and to provide voltage support on the 66kV network. The substation transformers have a tap range of +/-10%. Voltage set point on the distribution bus is currently 101%. The demand on Emerald Zone Substation is a mixture of commercial, industrial and residential loads, and peak loads generally occur in late summer afternoons. In the summer of 2014/15 the load at Emerald peaked at 39.7MVA. Peak load at Comet Zone Substation is around 2.7MVA. The Comet load is largely driven by irrigation and has a relatively low coincidence with the load at Emerald. Typical coincident load at Comet, when the load on Emerald Zone Substation peaks, is 50 70% Existing 66kV Network Capability The capability of the existing 66kV network that supplies Emerald is presented in Table 1 below. Table 1 Emerald 66kV Network Capability Thresholds Elements in Service Thermal Capacity Design Temperature Voltage Constraint Threshold page 6

7 Blackwater Emerald 66kV Feeder SD: 31.7MVA (277A) SE: 33.7MVA (295A) 65 C 23.2MVA at Emerald MVA at Comet (full coincident load) Lilyvale Emerald 66kV Feeder SD: 69.5MVA (608A) SE: 71.5MVA (629A) 75 C 36.0MVA at Emerald 2 Both 66kV Feeders in Service As above As above 44.3MVA at Emerald + 2.5MVA at Comet (full coincident load) Both 66kV Feeders in Service + One New Major Customer As above As above 40.8MVA at Emerald + 2.5MVA at Comet (full coincident load) SD = Summer Day (9am 5pm), SE = Summer Evening (5pm 10pm) 1 With Backwater Emerald line in service only. 2 With Lilyvale Emerald line in service only. Comet cannot be supplied with the entire Blackwater Emerald feeder out of service Insufficient Future 66kV Network Capability System Normal Conditions The maximum demand at Emerald is presently 39.7MVA and is forecast to grow by approximately 1.7% per annum for the next 10 years. The existing 66kV network does not have sufficient capability to supply the forecast increased load at Emerald under system normal conditions (i.e. with all plant in service). Network modelling indicates that with the current level of reactive compensation, voltage constraints will begin to occur at Emerald Zone Substation when the Emerald load exceeds 44.3MVA (see Table 1, above). Ergon Energy has also received recent connection enquiries for two major customers in the Emerald area, which would take supply from the 66kV network. Connection of either one will reduce the maximum load that can be supplied to Emerald to 40.8MVA. This will bring forward the date that voltage constraints may start to occur such that additional network capability will be required before connection can be offered. To connect both of these major customers, more significant network augmentation, or an alternate connection point, will be required. Ergon Energy does however consider the most probable future scenario to be that either none or one of these major connections will occur. Therefore, the voltage constraint threshold at Emerald that will need to be used when planning for non-network solutions has been set to 40.8MVA. page 7

8 Figure 3 Emerald Forecast Maximum Demand vs 66kV Network N Capability PoE = Probability of Exceedance. 50% PoE represents the forecast peak load during an average year. Used for contingency management planning. 10% PoE represents a peak load that only has a 10% risk of being exceeded, and that is expected to occur once in 10 years, e.g. during an unusually hot summer. Used when planning for N capability. Figure 3 above illustrates: The 10% PoE maximum demand at Emerald is expected to exceed the voltage constraint threshold of the 66kV network under system normal conditions in summer 2022/23 and onwards. With the connection of either one of the new major customer loads, the 10% PoE maximum demand at Emerald is expected to exceed the voltage constraint threshold of the 66kV network from summer 2018/19 and onwards. In other words, in the absence of any mitigation/solution to address the above issues: Ergon Energy will not be able to offer connection to any of the major customer loads from the Emerald 66kV network. Emerald Zone Substation, and the entire underlying distribution network, may experience undervoltage issues in the event of a 10% PoE load (system normal) from summer 2022/23 and onwards. page 8

9 Demand (MVA) Safety Net Compliance Under the revised reliability standards, Ergon Energy is no longer required to provide full N-1 security of supply on the 66kV network that supplies Emerald, i.e. either 66kV feeder alone does not have to have sufficient capability to supply the full peak load at Emerald. Instead, a set of supply restoration targets, known as the Service Safety Net Targets apply. The Safety Net restoration targets specify maximum permissible unsupplied load versus time that has lapsed after a credible contingency has occurred, and as such, define the worst permissible consequence of a system contingency. Under Safety Net, Emerald is classified as a Regional Centre and the following restoration time targets apply for credible contingencies, defined as maximum unserved load: 1. Less than 20 MVA after 1 hour 2. Less than 15 MVA after 6 hours 3. Less than 5 MVA after 12 hours 4. Fully restored within 24 hours Since none of the 66kV feeders alone has sufficient capability to supply the peak load at Emerald, an outage on either 66kV line may result in loss of supply to a portion of the load at Emerald. This potential load shedding is significant for a loss of the Lilyvale Emerald line, due to the comparatively low capability of the Blackwater Emerald line. Actual vs required supply restoration following a contingency on the Lilyvale Emerald line on a peak day is shown in Figure 4 below. A significant section of the Lilyvale line runs through black soil country, remote from any roads. This could present accessibility issues after periods of heavy rainfall, and it is expected it may take as long as 24 hours to return the line to service after a permanent fault. Due to the low capability of the Blackwater line, and limited load transfer/backup supply options available for the 66kV network that supplies Emerald, Ergon Energy would be unable to meet the Service Safety Net Targets. N-1 (max load supplied by Blackwater line) Sheddable Load Transfer to adjacent substations Line Repaired Load (MVA) 23.2 MVA 0.0 MVA Time hr 24 hr Ergon Safety Net Analysis for: Emerald Load Restoration Timeline for Worst Case Outage - Typical Effort Restoration Timeline (Hours) Load Not Supplied Supplied Minimum Restoration Actual Restoration N-1 Total Demand Safety Net Compliance: NOT COMPLIANT Figure 4 Emerald Safety Net Compliance Lilyvale Feeder Peak Day Contingency To be compliant with the Safety Net, the green dashed line (actual restoration) needs to be at or above the red continuous line (minimum restoration). page 9

10 4. Technical requirements of solution A suitable replacement to meet EECL s ongoing operational requirements in this system needs to be capable of providing the VAR support characteristics of a minimum of ±10MVAR. EECL seeks this solution to feed in to the Ergon Energy network at 66kV. It is highly desirable that these units have the capability to be expanded up to a total of ±20MVAR, to cater for possible growth and changing voltage constraints beyond EECL however is also willing to consider other connection arrangements as may be proposed, such as connection at 22kV. Please note however that this is not an exhaustive list and EECL is willing to consider other possible solutions which may be identified as part of this EOI process Stability Requirements EECL has the following stability requirements for any Alternative technology installations: 1. Will not go out of service as a result of inrush currents on Emerald Zone Substation transformers or other substation transformers or devices 2. Will not go out of service if the steady state capacitive or inductive limits are reached. i.e. there is protection put in place such that it will remain operable, without causing damage to itself or adjacent plant and equipment 3. Will not simply trip as a result of reaching Negative Phase Sequence (NPS) limits, but will continue to correct voltage as much as possible at limit levels 4. Will not trip as a result of dips or transients in the network. It will instead look to minimise the impacts of these dips or transients as much as possible 5. Will remain operable if High or Low voltages are seen and look to correct and stabilise these voltages as much as possible Negative Phase Sequence Capability The proposed network solution has negative phase sequence capability in order to maintain voltage balance. The alternative solution must also have NPS capability. This capability must maintain and correct voltage balance across the Emerald network such that EECL meets the voltage unbalance requirements detailed in S5.1a.7 of the National Electricity Rules Harmonics The alternative solution must not cause harmonic problems on EECL s network. It is expected that the alternative solution will meet the automatic access standard detail in S5.3.8 of the National Electricity Rules. Harmonic Voltages at the connection point(s) must not exceed the levels determined in accordance with AS/NZS Audio Frequency Load Control The alternative solution replacement and associated equipment must not cause attenuation or excessive magnification of the Audio Frequency Load Control signal. It is recommended that when impedance details of any proposed solution are known studies are completed to ensure no problems are introduced. page 10

11 4.5. Reactive System Sizing The alternative solution shall have a minimum VAR capability of ±10MVAR or equivalent and should ideally be able to be expanded a total of ±20MVAR or equivalent pending possible load or generation growth. It also needs to be noted that this VAR requirement may vary depending on the proposal. For example, a larger Solar Farm may require additional inductive support to maximise real power export, whilst maintaining suitable voltage levels. Any alternative solution must provide EECL with the capability and flexibility to manage 66kV voltage at Emerald. This may mean EECL will require direct control or some agreed level of control over the alternative solution, such that it integrates with EECL s network requirements. 5. Possible Solutions EECL has identified a number of Alternative Solutions which may be possible for the reactive compensation installation. As mentioned, this not an exhaustive list and EECL is willing to consider other possible solutions which may be identified as part of this EOI process. Other combinations including other generation technologies, solar coupled with batteries and or storage may also be possible. It is thought solar would be particularly appropriate as a Renewable Generation option. It is also important to note that the size of any renewable energy farm may also impact the amount of VAR compensation that may be required. It is a requirement of any proposed solution that the capacitive support would be available 24 hours per day, 7 days per week (with negotiated maintenance outages) Renewable Generation Farm It may be possible to construct a Renewable Generation Farm and use the inverters for the farm (if suitably specified) to provide reactive support. Please see Figure 5. It would be an essential EECL requirement that EECL effectively has control over the reactive compensation component. page 11

12 Renewable Energy Farm Inverters Used for Compensation ~ = ~ = ~ = ~ = ~ = ~ = Blackwater Feeder Lilyvale Feeder 66kV 22kV Existing capacitor Existing capacitor Existing Emerald Substation Figure 5: Renewable Generation Farm with inverters used for VAR compensation Please note: the 66kV connection is indicative only, and will be determined depending on the particulars of the proposed solution. It is essential that the reactive support could be maintained in case of an outage of the Lilyvale-Emerald 66kV feeder Summary The alternative supply of MVARs for network support is a new concept for EECL. EECL will continue to develop an appropriate standard and ensure any supplier can meet the performance metrics required for network stability. Network performance will be at risk if the alternative solution is not delivered in time or not able to provide the necessary support hence the network replacement solution investigation will occur in parallel. It is possible that the load may grow more quickly than predicted bringing forward the replacement requirement. page 12

13 6. Further information 6.1. Information a provider is to include in an alternative solution proposal EECL has provided below a nominal list of the data that should be considered for inclusion in the proposal. The intent of this list is to provide guidance to facilitate information exchange, and to provide a more efficient process for all parties involved in developing such a proposal. The list is not intended to replace or supersede any requirement published in the expression of interest (EOI). Rather, the intent is to provide advance indications of the types of information that EECL would need in the assessment of options. 1. Proponent name and contact details. 2. A detailed description of the proposal, and a brief explanation of the relevance of the proposal in relation to the need for investment in the distribution network. 3. Operational parameters including; - capacity in MW s, MVA or MVAR s of network support to be provided and number of units, if generation. - availability of the alternative resource and any restriction on network support capacity or output at any times of the year, - availability and reliability performance benchmarks, 4. Proposed operational and contractual arrangements that the proponent would be prepared to enter into with EECL. 5. Any special conditions to be included in a contract with EECL. 6. Network interface requirements. 7. The economic life of the proposal. 8. Network interface requirements Criteria that will be applied in evaluating proposals The preferred option is the credible option that maximises the net economic benefit to all those who produce, consume and transport electricity in the NEM, compared to all other credible options. The net economic benefit takes into account the market benefits versus the economic costs of each option. A credible option is a project, or set of projects, established to meet the identified need. EECL is willing to consider a variety of possible financial, ownership and operational models. EECL reserves the right to select the final model at its own discretion. In assessing each credible option that has been identified to satisfy the need, the following broad criteria are taken into account during the option assessment stage, page 13

14 addresses the identified need commercially feasible technically feasible and possible provision of other technical performance advantages. life cycle cost including ongoing maintenance and operational requirements suitability. This includes the suppliers ability to deliver, ability to maintain the system, and financial suitability. It also includes the technical capability and economic value when compared to other options. An option is commercially and technically feasible where its estimated costs are comparable to (or less than) other credible options that address the identified need. page 14

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8 Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Eyre Peninsula electricity supply options investigation

Eyre Peninsula electricity supply options investigation 20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

NYCA LOLE Violations (Methods D and E )

NYCA LOLE Violations (Methods D and E ) Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Standard Battery Energy Storage System (BESS) Connection Arrangements

Standard Battery Energy Storage System (BESS) Connection Arrangements Standard Battery Energy Storage System (BESS) Connection Arrangements Introduction A battery energy storage system (BESS) can be operated in a number of different ways to provide benefit to a customer.

More information

C PER. Center for Advanced Power Engineering Research C PER

C PER. Center for Advanced Power Engineering Research C PER Center for Advanced Power Engineering Research C PER 2017 Summer Research Planning Workshop Energy Storage Technologies and Application Roadmap Presented By: Johan Enslin Zucker Family Graduate Education

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid India need regulations for energy storage to implement grid ancillary services

More information

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 106 CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 5.1 INTRODUCTION Inherent characteristics of renewable energy resources cause technical issues not encountered with conventional thermal,

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

DIgSILENT Pacific PowerFactory Technical Seminar

DIgSILENT Pacific PowerFactory Technical Seminar DIgSILENT Pacific PowerFactory Technical Seminar Topic: The Wonders of Optimal Power Flow Presenter: Wayne Ong Venue: Sydney Novotel Central / Brisbane Marriott Hotel Date: 16 th and 30 th November 2017

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Presented By: Bob Uluski Electric Power Research Institute. July, 2011 SMART DISTRIBUTION APPLICATIONS &THEIR INTEGRATION IN A SMART GRID ENVIRONMENT Presented By: Bob Uluski Electric Power Research Institute July, 2011 Key Smart Distribution Applications What are the major

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic 1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision is for solar energy to be

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources Operational Impacts Jenny Riesz Principal, Operational Analysis & Engineering About AEMO We operate Australia's National Electricity Market and power grid in Australia s eastern

More information

Key Learnings from The Establishment of a Battery Energy Storage Testing Facility. by Peter Langley, Eskom Research

Key Learnings from The Establishment of a Battery Energy Storage Testing Facility. by Peter Langley, Eskom Research Key Learnings from The Establishment of a Battery Energy Storage Testing Facility by Peter Langley, Eskom Research Demand Demand Traditional vs Evolving Grid Peak Load Intermediate Load Base Load Time

More information

Net +Plus Connection Code

Net +Plus Connection Code Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Integration of Large Wind Farms into Electric Grids

Integration of Large Wind Farms into Electric Grids Integration of Large Wind Farms into Electric Grids Dr Mohammad AlZoubi Introduction Development WHAT IS NEXT!! Over the next 12 years, Europe must build new power capacity equal to half the current total.

More information

Connecting your business diesel generation

Connecting your business diesel generation Connecting your business diesel generation March 2018 For connections more than 10kW 2 Contents Introduction to large distributed generation systems 3 Congestion management and safety 6 Application form

More information

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund Project Title: Sodium Sulfur Battery Energy Storage Contract Number: RD3-1 Milestone Number: 1 Report Date: May 0, 009 Reporting Period: September 007 April 008 Milestone Description: Milestone 1 - Specifications

More information

Standards, Procedures and Policies for Grid Connection

Standards, Procedures and Policies for Grid Connection Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Micro Embedded Generating Units (0-30 kva)

Micro Embedded Generating Units (0-30 kva) Connection Standard Micro Embedded Generating Units (0-30 kva) These standards ensure that Ergon Energy s and Energex s requirements are met. If this standard is a printed version then the Ergon Energy

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership Grid Management Voltage Control Distribution Grid Voltage Regulation with DER Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership Overview of Grid Management Distribution Voltage Control Grid

More information

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Jim Calore Public Service Electric & Gas Co. Overview This

More information

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian Shunt Capacitor Bank Protection in UHV Pilot Project Qing Tian 2012-5 INTRODUCTION State Grid Corp. of China, the largest electric power provider in the country, has first build a 1000 kv transmission

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Ancillary Services & Essential Reliability Services

Ancillary Services & Essential Reliability Services Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO.1 275 KV BUSBAR ON 30 OCTOBER 2011 PREPARED BY: Electricity System Operations Planning and Performance

More information

Exemptions currently in force

Exemptions currently in force exemptions by Western Power s currently in force Neerabup Units G11 & G12 3.3.3.1 (a) 16 Jan 2008 Ongoing Modified performance criteria: 0.8 Lagging 101.3 MVAr 0.9 Leading 68.5 MVAr Financial contribution

More information

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in

More information

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/10/2018 Mr Peter Adams General Manager, Wholesale Markets Australian Energy

More information

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014 City Power Johannesburg: Response to Potential Load Shedding Presented by : Stuart Webb General Manager : PCM October 2014 Topics to be discussed Background Challenges Options Available Summary 2 Background

More information

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT Prof. Chandrashekhar Sakode 1, Vicky R. Khode 2, Harshal R. Malokar 3, Sanket S. Hate 4, Vinay H. Nasre 5, Ashish

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

Physical Design of a Volt/Var Implementation

Physical Design of a Volt/Var Implementation 1 Physical Design of a Volt/Var Implementation Hydro-Québec Distribution s approach Prepared by Bruno Fazio 2 Subjects Context Volt control Planning Control strategies and exploitation Var control Planning

More information

Large Embedded Generation User Guide A

Large Embedded Generation User Guide A Large Embedded Generation User Guide A For Generating Systems AS4777 compliant and up to 200kW January 2013 SA Power Networks www.sapowernetworks.com.au Table of Contents 1. Introduction... 3 1.1 Embedded

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

2018 Load & Capacity Data Report

2018 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system 1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration 2 High

More information

Generation Connections Industry Workshop 2017

Generation Connections Industry Workshop 2017 Generation Connections Industry Workshop 2017 1 Introduction- Topics to be covered Background: SONI & NIE Networks Generation Connections Guide Renewable Generation Update Phase 1 Review UR Connections

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality Surabaya Seminar 2014 Ferdinand Sibarani, Surabaya, 30 th October 2014 Power Quality Content 1. Power quality problems 2. ABB s low voltage (LV) solution PCS100 AVC (Active Voltage Conditioner) PCS100

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Economics and Barriers to Solar Photovoltaic Applications in Barbados

Economics and Barriers to Solar Photovoltaic Applications in Barbados Economics and Barriers to Solar Photovoltaic Applications in Barbados Roland R Clarke PhD Clarke Energy Associates www.clarkeenergy@aol.com clarkeenergy@aol.com Presented to Alternative Energy: Pathways

More information

Siemens Hybrid Power Solutions. Technical and Financial Simulation Tools for High Penetration Hybrid Power Systems, Bangkok June 2015

Siemens Hybrid Power Solutions. Technical and Financial Simulation Tools for High Penetration Hybrid Power Systems, Bangkok June 2015 Siemens Hybrid Power Solutions Technical and Financial Simulation Tools for High Penetration Hybrid Power Systems, Bangkok June 2015 Instrumentation, Controls & Electrical Overview 1. Applications 2. High

More information

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor

More information

Dynamic Reactive Power Control for Wind Power Plants

Dynamic Reactive Power Control for Wind Power Plants Dynamic Reactive Power Control for Wind Power Plants Ernst Camm, Charles Edwards, Ken Mattern, Stephen Williams S&C Electric Company, 6601 N. Ridge Blvd, Chicago IL 60626 USA ecamm@sandc.com, cedwards@sandc.om,

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa Content Introduction Overview of Categories for Grid Connection of

More information

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY DRAFT Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY 2018 1. INTRODUCTION Solar energy has become the most popular renewable energy source

More information