Appendix I: Noise and Vibration Assessment Report

Size: px
Start display at page:

Download "Appendix I: Noise and Vibration Assessment Report"

Transcription

1 Appendix I: Noise and Vibration Assessment Report London Bus Rapid Transit Transit Project Assessment Process Environmental Project Report DRAFT April 2018 P R E PA R E D BY

2 RAPID TRANSIT CORRIDORS ENVIRONMENTAL ASSESSMENT - NOISE AND VIBRATION STUDY LONDON BUS RAPID TRANSIT CITY OF LONDON PROJECT NO.: DATE: APRIL 2018 WSP 100 COMMERCE VALLEY DRIVE WEST THORNHILL, ON, CANADA L3T 0A1 WSP.COM WSP Canada Inc.

3 S I G N A T U R E S PREPARED BY Johnson Trinh, EIT Designer Jeffery Park, EIT Designer REVIEWED BY Bill Hoogeveen, P.Eng. Senior Project Manager Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page ii

4 EXECUTIVE SUMMARY The City of London, Ontario has retained the IBI Group (IBI) in collaboration with WSP Canada Inc. (WSP) to provide engineering consulting and environmental assessment services for the development of a 24km-long Bus Rapid Transit (BRT) system for London, Ontario. As a part of the environmental assessment services, this noise and vibration study assesses the potential noise and vibration impacts of the BRT system on the surrounding area. The scope of this study addresses the potential noise and vibration impact of construction, road widening, and operation of the BRT system. The road traffic volumes were projected based on Turning Movement Counts (TMC) and future growth rates provided by the project team. Road noise levels were calculated using both the method outlined in the Ontario Ministry of the Enviroment document ORNAMENT (October, 1989) and the MOECC STAMSON 5.04 Computer Program for Road and Rail Traffic Noise Assessment. The projected increase in noise levels as a result of the implementation of the London BRT system is estimated to be greater than 5 db at four receptor locations. New 1.8 m to 2.4 m high sound barriers are recommended to attenuate the increase in sound levels. This study concluded that the existing noise sensitive land uses will not be impacted by the construction, road widening, and operation of the BRT system provided that all recommendations in this report are implemented. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page iii

5 Executive Summary... iii 1 INTRODUCTION STUDY AREA AND SURROUNDING LAND USES 2 3 NOISE GUIDELINES NOISE ANALYSIS... 4 Noise Sources... 4 Estimation Procedures... 4 Setbacks, Elevations, and Receptor Heights... 4 Results and Findings... 6 Noise Control Measures CONSTRUCTION NOISE VIBRATION ASSESSMENT CONCLUSIONS AND RECOMMENDATIONS Conclusions Recommendations REFERENCES Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page iv

6 TABLES TABLE 4-1: SUMMARY OF RECEPTORS... 4 TABLE 4-2: SUMMARY OF RESULTS... 6 TABLE 4-3: RECOMMENDED NOISE CONTROL MEASURES... 8 FIGURES FIGURE 1-1: APPROVED BRT NETWORK (JULY 2017)... 1 APPENDICES A TRAFFIC DATA B C SOUND LEVEL ANALYSES BARRIER LOCATIONS Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page v

7 1 INTRODUCTION The City of London, Ontario has retained the IBI Group (IBI) in collaboration with WSP Canada Inc. (WSP) to provide engineering consulting and environmental assessment services for the development of a 24km-long Bus Rapid Transit (BRT) system for London, Ontario. The BRT system is comprised of four segments, combined into two operational routes: the north and east corridor, and the south and west corridor, as presented in Figure A below. The BRT network was approved by the City of London Council with the Rapid Transit Master Plan in July 2017, and is comprised predominantly of dedicated bus lanes on existing streets, either in the curb or median lanes. The BRT corridors will also incorporate enhanced pedestrian amenities and active transportation infrastructure where feasible. A total of 35 new, fully-accessible BRT stops are provided at key signalized intersections throughout the network, with enhanced passenger amenities and safety features. The project will require the purchase of an additional 28 vehicles to operate the BRT services, which will be phased-in gradually as the BRT corridors come online. As a part of the environmental assessment services, this noise and vibration study assesses the potential noise and vibration impacts of the BRT system on the surrounding area. The scope of this study addresses the potential noise and vibration impact of construction, road widening, and operation of the BRT system. Figure 1-1: Approved BRT Network (July 2017) Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 1

8 2 STUDY AREA AND SURROUNDING LAND USES For the purposes of this evaluation, the study area extends 600 metres on both sides of the proposed 24 kilometre BRT system and adjacent residential areas. In practical terms, the study area extends only as far as the first row of housing since there will not be impacts beyond the first row. Existing land uses vary along the study corridors with a mix of recreational, residential, commercial, and institutional uses. Downtown London is primarily commercial and institutional uses while a couple of kilometres away from the downtown core is primarily residential. Notable land uses along the BRT corridors include Western University, Masonville Place, Cherry Hill Mall, North American Trade Schools, Gateway Casinos, and Fanshawe College. For more information about the surrounding land use, the City of London s website contains an interactive map at The noise and vibration assessments were undertaken based on a selection of private residential homes adjacent to the BRT corridors to represent the locations where the potential worst-case impacts to noise and vibration sensitive areas are expected. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 2

9 3 NOISE GUIDELINES When examining the noise impacts of transportation improvements on existing residential areas, the Ministry of the Environment and Climate Control s approach for the assessment of noise impacts is documented in "A Protocol for Dealing with Noise Concerns during Preparation, Review and Evaluation of Provincial Highway Environmental Assessments", February 1986, prepared by the Ontario Ministry of Transportation and the Ministry of the Environment (hereafter referred to as the Protocol). The Protocol states "The objective for outdoor sound levels is the higher of the L eq 55 dba or the ambient. The significance of a noise impact will be quantified by using this objective in addition to the change in noise level above the ambient. Where noise increases above the ambient do not exceed 5 dba, no mitigation is required". A summary of the guidelines to determine noise impact is as follows: If the L eq 16 hour daytime traffic sound levels in the outdoor living areas of the adjacent dwelling units are less than or equal to 55 dba and the impact is less than or equal to 5 dba (over ambient noise levels), noise mitigation measures will not be required. If the L eq 16 hour daytime traffic sound levels in the outdoor living areas of the adjacent dwelling units are greater than 55 dba and the impact is less than or equal to 5 dba (over ambient), attenuation measures will not normally be required. For both cases noted above, if the noise impact exceeds 5 dba (over ambient), noise control measures should be investigated within the right-of-way and if mitigation is warranted, attempts should be made to reduce the noise to objective sound levels or as much as possible, within the constraints of administrative, aesthetic, economic and technical feasibility. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 3

10 4 NOISE ANALYSIS NOISE SOURCES The primary noise sources are vehicular traffic along the major roads (Dundas Street, King Street, Oxford Street East, Oxford Street West, Highbury Avenue North, Wharncliffe Road North, Wellington Road, Richmond Street and Western Road). The road traffic volumes were projected based on Turning Movement Counts (TMC) and future growth rates provided by the project team. A medium to heavy truck ratio was not provided and a ratio of 5:8 was assumed. The traffic data used is provided in Appendix A. The conservative case of diesel BRT fleet was assumed. ESTIMATION PROCEDURES Sound levels were calculated using the method outlined in the Ontario Ministry of the Environment document ORNAMENT, October 1989 and the Ontario Ministry of the Environment and Climate Change (MOECC) STAMSON, Computer Program for Road and Rail Traffic Noise Assessment (Version 5.04 issued in 2000). SETBACKS, ELEVATIONS, AND RECEPTOR HEIGHTS An Outdoor Living Area (OLA) is an outdoor area easily accessible from a building and is designed for the quiet enjoyment of the outdoor environment. A review of the study area identified OLAs that would have the greatest exposure to the BRT corridor and therefore be most impacted by the project. The location of these OLA receptors are 3 metres from the rear façade of the building at a height of 1.5 metres above the existing grade at the critical noise sensitive areas. Table 4-1 summarizes all the assessed receptors. Table 4-1: Summary of Receptors NOISE RECEPTOR ADDRESS TYPE OF RESIDENTIAL UNIT N1 106 St Bees Crt. Detached House N2 38 St Bees Pl. Detached House N3 1 Ambleside Dr. Detached House N4 326 Windermere Rd. Detached House N The Parkway Detached House N6 15 Tower Lane Detached House N Richmond St. Detached House N8 208 Huron St. Detached House N9 3 Richmond St. Detached House N Cromwell St. Detached House N Sydeham St. Detached House E Dundas St. Detached House E2 248 Paardeberg Cres. Detached House Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 4

11 NOISE RECEPTOR ADDRESS TYPE OF RESIDENTIAL UNIT E Oxford St. E. Detached House E Oxford St. E. Detached House S1 2 Kennon Pl. Detached House S2 4 Watson St. Detached House S3 3 Watson St. Detached House S4 119 McClary Ave Detached House S5 32 Frank Pl. Detached House S6 8 Bond St. Detached House S7 13 Bond St. Detached House S8 21 Raywood Ave. Detached House S9 484 Moore St. Detached House S Emery St. E. Detached House S11 60 Thomas Janes Dr. Detached House S Wellington Rd. Detached House S13 57 Thomas Janes Dr. Detached House S Base Line Rd. E. Detached House S Nadine Ave. Detached House S St Stephens Dr. Detached House S Glenbanner Rd. Detached House S Glenbanner Rd. Detached House S Glenbanner Rd. Detached House S Dunelm Lane Detached House W1 217 Platt's Lane Detached House W2 189 Woodward Ave. Detached House W3 226 Cooper St. Detached House W4 82 Empress Ave. Detached House W5 101 Wharncliffe Rd. N. Detached House W6 34 Kensington Ave. Detached House W7 12 Wilson Ave. Detached House Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 5

12 RESULTS AND FINDINGS The sixteen hour sound levels (L eq 16 hr) for all receptors were determined using STAMSON Both the existing and future with the BRT system scenario were calculated to determine the noise impact of the proposed BRT system. A summary of the results are shown in Table 4-2. Table 4-2: Summary of Results NOISE RECEPTOR EXISTING SOUND LEVELS WITHOUT BRT (1) (dba) FUTURE SOUND LEVELS WITH BRT (2) (dba) CHANGE IN SOUND LEVELS (dba) MITIGATION TO BE INVESTIGATED? N No N No N No N No N No N No N No N No N No N No N No E No E No E No E No S Yes S No S No S No S No S No S Yes S No S Yes S No S No Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 6

13 NOISE RECEPTOR EXISTING SOUND LEVELS WITHOUT BRT (1) (dba) FUTURE SOUND LEVELS WITH BRT (2) (dba) CHANGE IN SOUND LEVELS (dba) MITIGATION TO BE INVESTIGATED? S No S No S No S No S No S No S No S No S No W No W No W Yes W No W No W No W No (1) Based on projected 2018 traffic volumes (2) Based on 2034 traffic volumes and 2034 BRT volumes As tabulated above, existing sound levels range from 48 dba to 69 dba and future sound levels with BRT from 53 dba to 70 dba. The largest change in sound levels is 9 dba. NOISE CONTROL MEASURES Based on the results summarized in Table 4-2, most receptors experience a small increase in sound levels but will not require noise control measures. However, receptors S1, S7, S9, and W3 increases by more than the 5 db. Noise control measures were investigated at these locations. It should be noted that increases greater than 5 db are predicted to only occurred as a result of intervening buildings needing to be removed to accommodate the design. Accordingly, it is recommended that sound barriers be constructed to provide sufficient attenuation to reduce sound levels to objective sound levels for the affected receptors. Table 4-3 summarizes the recommended noise control measures. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 7

14 Table 4-3: Recommended Noise Control Measures NOISE RECEPTOR BARRIER HEIGHT (m) OBJECTIVE SOUND LEVELS (dba) ATTENUATED SOUND LEVELS (dba) MITIGATION PROVIDED BY BARRIER (dba) S S S W The locations and heights of the sound barriers are schematically shown in Appendix C, Figures C-1 to C-4. Sound barriers must be continuous and without gaps. All fence material must have a minimum surface density of 20 kg/m 2. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 8

15 5 CONSTRUCTION NOISE With respect to the noise impacts during construction of the London BRT, the following should be specified during the preparation of detailed design drawings and adhered to during construction: The Contractor will be required to comply with the City of London s noise by-law (Noise By-Law, PW-12) regarding noise emission standards for construction equipment that may be in place at the time of construction. General noise control measures (not sound level criteria) will be referred to, or placed into the City of London contract documents. Any initial complaint from the public will require verification by the City of London to determine if the general noise control measures agreed to, are in effect. The City of London will investigate any noise concerns, warn the Contractor of any problems and enforce its contract. Nighttime construction activities should be avoided to reduce the potential impact of construction noise. Construction should be planned to minimize the number of nights where noisy nighttime construction activities may be required. All construction equipment used should be in good repair and properly maintained to limit noise emissions. All construction equipment should be operated with effective muffling devices that are in good working order and idling of construction equipment kept to a minimum to reduce noise from construction activities. Unnecessary noise caused by faulty or non-operating components shall be addressed by regularly maintaining all equipment. Noise emissions from construction equipment are to be in compliance with the limits set out in NPC-115 and NPC-118. The concurrent use of high impact construction equipment such as pile driving should be avoided. The feasibility of augur pile driving should be investigated if pile driving is required. Construction noise mitigation options should be considered based on administrative, operational, economic, and technical feasibility. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 9

16 6 VIBRATION ASSESSMENT Vibration impacts on nearby vibration sensitive areas due to the operation of the proposed BRT system is not expected to be a concern. The rubber tires and suspension systems of the buses and trucks will provide sufficient vibration dampening and isolation under satisfactory pavement conditions. There are no federal, provincial, or municipal construction vibration limits. The construction vibration is temporary and vibration-intensive activities such as pile driving are not expected to occur. However, construction best practices should be followed. Construction activities should be kept as far as possible from nearby structures and the duration of construction activities near structures should be kept to a minimum. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 10

17 7 CONCLUSIONS AND RECOMMENDATIONS CONCLUSIONS The conclusions of the noise and vibration assessments are as follows: The projected increase in noise levels as a result of the implementation of the London BRT system is estimated to be greater than 5 dba at receptors S1, S7, S9, and W3 and warrants an investigation of mitigation measures. Vibration impacts on nearby vibration sensitive areas due to the operation of the proposed BRT system is not expected to be a concern. RECOMMENDATIONS Based on the review of proposed noise mitigation at the affected receptor locations, new 1.8 m to 2.4 m high sound barriers are recommended. The locations and heights of the sound barriers are schematically shown Appendix C, Figures C-1 to C-4. Construction noise control program noted in Section 5 of this report be adhered to during the construction of the London BRT system. Construction best practices should be followed to minimize the possibility of a potential noise/vibration impact. Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 11

18 REFERENCES [1] Ontario Ministry of Transporation and the Ministry of the Environment, "A Protocol for Dealing with Noise Concerns during Preparation, Review and Evaluation of Provincial Highway Enironmental Assessments," February [2] Ontario Ministry of the Environment, "Ontario Road Noise Analysis Method for Environment and Transportation (ORNAMENT)," Queen's Printer for Ontario, Rapid Transit Corridors EA Noise and Vibration Study Project No City of London WSP April 2018 Page 12

19 APPENDIX A TRAFFIC DATA

20 Receptor Number Relevant Intersection Approach N1 Western & Richmond North N2 N3 N4 Western & Richmond Western & Richmond Western & Richmond West (Western) West (Western) West (Western) N5 Richmond & University West N6 Richmond & University West N7 Richmond & University South N8 Richmond & University South N9 Richmond & Huron South N10 Richmond & Grosvenor North N11 Richmond & Oxford North E1 Dundas & Highbury West E2 Oxford & Highbury (All outs) E3 Oxford & Highbury East E4 Oxford & Highbury East Direction (In or Out) Direction # Med. Trucks # Heavy Trucks 2034 Growth (Do Nothing) 2034 Growth (with BRT) No. of BRT Buses (Future) No. of Local Buses (Future) Medium Truck % Heavy Truck % Day/Night Ratio NB (Out) NB % 1.4% % SB (In) SB % 1.4% EB (In) EB % 1.4% % WB (Out) WB % 1.0% EB (In) EB % 1.4% % WB (Out) WB % 1.0% EB (In) EB % 1.4% % WB (Out) WB % 1.0% EB (In) EB % 2.9% % WB (Out) WB % 3.6% EB (In) EB % 2.9% % WB (Out) WB % 3.6% NB (In) NB % 2.0% % SB (Out) SB % 1.7% NB (In) NB % 2.0% % SB (Out) SB % 1.7% NB (In) NB % 2.1% % SB (Out) SB % 1.9% NB (Out) NB % 2.3% % SB (In) SB % 2.5% NB (Out) NB % 1.9% % SB (In) SB % 2.3% EB (In) EB % 2.6% % WB (Out) WB % 3.1% NB (Out) NB % 2.7% % SB (Out) SB 1, % 3.4% EB (Out) EB % 2.7% % WB (Out) WB % 3.5% EB (Out) EB % 2.7% % WB (In) WB 1, % 4.7% EB (Out) EB % 2.7% % WB (In) WB 1, % 4.7% Road Gradient Speed Limit

21 Receptor Number Relevant Intersection Approach S1 Wellington & Grand North S2 Wellington & Grand South S3 Wellington & Grand South S4 Wellington & Grand South S5 Wellington & Grand South S6 Wellington & Grand South S7 Wellington & Base Line North S8 Wellington & Base Line North S9 Wellington & Base Line North S10 Wellington & Base Line North S11 Wellington & Base Line North S12 Wellington & Base Line North S13 Wellington & Base Line North S14 Wellington & Base Line (All outs) S15 Wellington & Southdale North S16 Wellington & Southdale South S17 Wellington & Montgomery North S18 Wellington & Montgomery South S19 Wellington & Bradley North S20 Wellington & Bradley North W1 Oxford & Woodward/Platts East W2 Oxford & Woodward/Platts East W3 Oxford & Woodward/Platts East W4 Oxford & Wharncliffe South W5 Wharncliffe & Mt Pleasant North W6 Wharncliffe & Riverside (All outs) W7 Wharncliffe & Riverside East Direction (In or Out) Direction # Med. Trucks # Heavy Trucks 2034 Growth (w/o BRT) 2034 Growth (with BRT) No. of BRT Buses (Future) No. of Local Buses (Future) Medium Truck % Heavy Truck % Day/Night Ratio Road Gradient Speed Limit NB (Out) NB % 2.1% % 50 SB (In) SB % 2.0% NB (In) NB % 2.2% % 50 SB (Out) SB % 1.9% NB (In) NB % 2.2% % 50 SB (Out) SB % 1.9% NB (In) NB % 2.2% % 50 SB (Out) SB % 1.9% NB (In) NB % 2.2% % 50 SB (Out) SB % 1.9% NB (In) NB % 2.2% % 50 SB (Out) SB % 1.9% NB (Out) NB % 1.9% % 50 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 50 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 50 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 50 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 60 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 60 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 60 SB (In) SB % 2.1% NB (Out) NB % 1.9% % 60 SB (Out) SB % 1.7% 126 EB (Out) EB % 1.2% % 50 WB (Out) WB % 1.7% NB (Out) NB % 2.0% % 60 SB (In) SB % 1.8% NB (In) NB % 2.0% % 60 SB (Out) SB % 1.8% NB (Out) NB % 2.1% % 60 SB (In) SB % 2.0% NB (In) NB % 2.0% % 60 SB (Out) SB % 2.0% NB (Out) NB % 2.1% % 60 SB (In) SB % 1.9% NB (Out) NB % 2.1% % 60 SB (In) SB % 1.9% EB (Out) EB % 1.4% % 50 WB (In) WB % 1.5% EB (Out) EB % 1.4% % 50 WB (In) WB % 1.5% EB (Out) EB % 1.4% % 50 WB (In) WB % 1.5% NB (In) NB % 1.8% % 50 SB (Out) SB % 1.8% NB (Out) NB % 1.3% % 50 SB (In) SB % 1.4% NB (Out) NB % 1.4% % 50 SB (Out) SB % 1.2% 277 EB (Out) EB % 2.4% % 50 WB (Out) WB % 1.5% EB (Out) EB % 2.4% % 50 WB (In) WB % 2.0%

22 APPENDIX B SOUND LEVEL ANALYSES

23 STAMSON 5.0 NORMAL REPORT Date: :16:36 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s1.te Description: S1 Time Period: 16 hours Road data, segment # 1: Wellington - Car traffic volume : veh/timeperiod Medium truck volume : 377 veh/timeperiod Heavy truck volume : 603 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 3 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Wellington -- Angle1 Angle2 : deg 0.00 deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: Wellington - Source height = 1.20 m ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 58.42

24 STAMSON 5.0 NORMAL REPORT Date: :38:32 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s1brt.te Description: S1BRT Time Period: 16 hours Road data, segment # 1: WellingtonNB Car traffic volume : veh/timeperiod Medium truck volume : 258 veh/timeperiod Heavy truck volume : 331 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 3 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: WellingtonNB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 2 (Reflective ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier) Barrier angle1 : deg Angle2 : deg Barrier height : 2.40 m Barrier receiver distance : 6.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Road data, segment # 2: WeelingtonSB Car traffic volume : veh/timeperiod Medium truck volume : 220 veh/timeperiod Heavy truck volume : 272 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 3 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 2: WeelingtonSB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 2 (Reflective ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier)

25 Barrier angle1 : deg Angle2 : deg Barrier height : 2.40 m Barrier receiver distance : 6.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Results segment # 1: WellingtonNB Source height = 1.20 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.38! 1.38 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Results segment # 2: WeelingtonSB Source height = 1.18 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.43! 1.43 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq

26 - Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 58.49

27 STAMSON 5.0 NORMAL REPORT Date: :22:29 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s7.te Description: S7 Time Period: 16 hours Road data, segment # 1: Wellington - Car traffic volume : veh/timeperiod Medium truck volume : 371 veh/timeperiod Heavy truck volume : 594 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 2 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Wellington -- Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier) Barrier angle1 : deg Angle2 : deg Barrier height : 3.00 m Barrier receiver distance : m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Results segment # 1: Wellington - Source height = 1.19 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.39! 1.39 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq

28 Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 53.91

29 STAMSON 5.0 NORMAL REPORT Date: :39:21 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s7brt.te Description: S7BRT Time Period: 16 hours Road data, segment # 1: Wellinton NB Car traffic volume : veh/timeperiod Medium truck volume : 236 veh/timeperiod Heavy truck volume : 297 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 2 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Wellinton NB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier) Barrier angle1 : deg Angle2 : deg Barrier height : 2.30 m Barrier receiver distance : 5.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Road data, segment # 2: WellingtonSB Car traffic volume : veh/timeperiod Medium truck volume : 236 veh/timeperiod Heavy truck volume : 297 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 2 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 2: WellingtonSB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier)

30 Barrier angle1 : deg Angle2 : deg Barrier height : 2.30 m Barrier receiver distance : 5.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Results segment # 1: Wellinton NB Source height = 1.18 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.46! 1.46 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Results segment # 2: WellingtonSB Source height = 1.20 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.44! 1.44 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq

31 - Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 55.28

32 STAMSON 5.0 NORMAL REPORT Date: :23:48 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s9.te Description: S9 Time Period: 16 hours Road data, segment # 1: Wellington - Car traffic volume : veh/timeperiod Medium truck volume : 371 veh/timeperiod Heavy truck volume : 594 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Wellington -- Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 1 House density : 80 % Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: Wellington - Source height = 1.19 m ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 50.18

33 STAMSON 5.0 NORMAL REPORT Date: :46:07 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: s9brt.te Description: S9BRT Time Period: 16 hours Road data, segment # 1: WellingtonNB Car traffic volume : veh/timeperiod Medium truck volume : 236 veh/timeperiod Heavy truck volume : 297 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: WellingtonNB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier) Barrier angle1 : deg Angle2 : deg Barrier height : 1.80 m Barrier receiver distance : 9.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Road data, segment # 2: WellingtonSB Car traffic volume : veh/timeperiod Medium truck volume : 236 veh/timeperiod Heavy truck volume : 297 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 2: WellingtonSB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier)

34 Barrier angle1 : deg Angle2 : deg Barrier height : 1.80 m Barrier receiver distance : 9.00 m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Results segment # 1: WellingtonNB Source height = 1.18 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.45! 1.45 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Results segment # 2: WellingtonSB Source height = 1.20 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.44! 1.44 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq

35 Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 52.25

36 STAMSON 5.0 NORMAL REPORT Date: :17:59 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: w3.te Description: W3 Time Period: 16 hours Road data, segment # 1: Oxford Car traffic volume : veh/timeperiod Medium truck volume : 285 veh/timeperiod Heavy truck volume : 456 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Oxford - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 1 House density : 80 % Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: Oxford Source height = 1.09 m ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 50.15

37 STAMSON 5.0 NORMAL REPORT Date: :50:00 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: w3brt.te Description: W3BRT Time Period: 16 hours Road data, segment # 1: Oxford EB Car traffic volume : veh/timeperiod Medium truck volume : 195 veh/timeperiod Heavy truck volume : 234 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: Oxford EB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier) Barrier angle1 : deg Angle2 : deg Barrier height : 1.80 m Barrier receiver distance : m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Road data, segment # 2: Oxford WB Car traffic volume : veh/timeperiod Medium truck volume : 230 veh/timeperiod Heavy truck volume : 290 veh/timeperiod Posted speed limit : 50 km/h Road gradient : 1 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 2: Oxford WB - Angle1 Angle2 : deg deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : m Receiver height : 1.50 m Topography : 2 (Flat/gentle slope; with barrier)

38 Barrier angle1 : deg Angle2 : deg Barrier height : 1.80 m Barrier receiver distance : m Source elevation : 0.00 m Receiver elevation : 0.00 m Barrier elevation : 0.00 m Reference angle : 0.00 Results segment # 1: Oxford EB Source height = 1.09 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.39! 1.39 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq Segment Leq : dba Results segment # 2: Oxford WB Source height = 1.10 m Barrier height for grazing incidence Source! Receiver! Barrier! Elevation of Height (m)! Height (m)! Height (m)! Barrier Top (m) ! 1.50! 1.41! 1.41 ROAD ( ) = dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq

39 - Segment Leq : dba Total Leq All Segments: dba TOTAL Leq FROM ALL SOURCES: 52.27

40 APPENDIX C BARRIER LOCATIONS

41 S1 2.4m high Noise Barrier Noise Barrier Noise Receptor FIGURE C-1 Barrier Recommendation for S1 Scale 1:500

42 S7 2.3m high Noise Barrier Noise Barrier Noise Receptor FIGURE C-2 Barrier Recommendation for S7 Scale 1:500

43 1.8m high Noise Barrier S9 Noise Barrier Noise Receptor FIGURE C-3 Barrier Recommendation for S9 Scale 1:500

44 m high Noise Barrier W3 Noise Barrier Noise Receptor FIGURE C-4 Barrier Recommendation for W3 Scale 1:1000

Appendix J. Noise Impact Assessment Report

Appendix J. Noise Impact Assessment Report Appendix J Noise Impact Assessment Report Appendix J Sheridan Park Drive Extension Municipal Class Environmental Assessment Noise Impact Assessment Report City of Mississauga R.J. Burnside & Associates

More information

Appendix B: Travel Demand Forecasts July 2017

Appendix B: Travel Demand Forecasts July 2017 Appendix B: Travel Demand Forecasts July 2017 Table of Contents 1 Introduction... 2 2 Model Review and Updates... 2 2.1 Overview of Smart Moves Model ( City of London Model )... 2 2.1.1 Network and Zone

More information

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

Welcome. The purpose of today s session is to:

Welcome. The purpose of today s session is to: Welcome The purpose of today s session is to: Update you on what we ve heard from the community Share the preferred Rapid Transit network solution Present the draft Rapid Transit Master Plan Representatives

More information

Appendix A-M Public Information Centre 4 Materials

Appendix A-M Public Information Centre 4 Materials Appendix A-M Public Information Centre 4 Materials NOTICE OF PUBLIC INFORMATION CENTRE #4 RAPID TRANSIT CORRIDORS MASTER PLAN ENVIRONMENTAL ASSESSMENT STUDY The City of London is entering a new chapter

More information

FLAMBOROUGH QUARRY HAUL ROUTE STUDY HAUL ROUTE VIBRATION REPORT. itrans Consulting Inc 100 York Boulevard Richmond Hill, Ontario L4B 1J8

FLAMBOROUGH QUARRY HAUL ROUTE STUDY HAUL ROUTE VIBRATION REPORT. itrans Consulting Inc 100 York Boulevard Richmond Hill, Ontario L4B 1J8 FINAL REPORT FLAMBOROUGH QUARRY HAUL ROUTE STUDY HAUL ROUTE VIBRATION REPORT Project Number: #W08-5107A August 28, 2008 SUBMITTED TO: Tara Erwin itrans Consulting Inc 100 York Boulevard Richmond Hill,

More information

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for:

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for: TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY 2014 Prepared for: Hartford Companies 1218 W. Ash Street Suite A Windsor, Co 80550 Prepared by: DELICH ASSOCIATES 2272 Glen Haven Drive

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

East Turnaround. Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan.

East Turnaround. Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan. East Turnaround Options at Fanshawe College Ayreswood Access Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan. To mitigate the impacts

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited.

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited. RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Guycoki (Eastern) Limited June 16, 2016 116-638 Brief_1.doc D. J. Halpenny & Associates Ltd. Consulting

More information

Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph)

Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph) Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph) Prepared By: 332 Lorne Avenue East Stratford ON N5A 6S4 Prepared for: Paul Kemper, President

More information

Rapid Transit Implementation Working Group #4 February 9, 2017

Rapid Transit Implementation Working Group #4 February 9, 2017 Rapid Transit Implementation Working Group #4 February 9, 2017 Agenda 1. Business Case Update 2. Rapid Transit Master Plan Overview 3. Corridor Concepts 4. Public Consultation Event 5. Schedule Outlook

More information

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MARCH 20, 2019 RECOMMENDATION

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MARCH 20, 2019 RECOMMENDATION TO: FROM: SUBJECT: CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MARCH 20, 2019 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Tunney s Pasture to Dominion Station Traffic and Transit Detours. April 4, 2017 C. Wheeler/ C. Swail

Tunney s Pasture to Dominion Station Traffic and Transit Detours. April 4, 2017 C. Wheeler/ C. Swail Tunney s Pasture to Dominion Station Traffic and Transit Detours April 4, 2017 C. Wheeler/ C. Swail Purpose of Presentation Outline key principles for traffic and transit management Implementation strategies

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Environmental Noise Assessment Stonebridge Golf & Country Club Maintenance Facility. Nepean, Ontario

Environmental Noise Assessment Stonebridge Golf & Country Club Maintenance Facility. Nepean, Ontario Environmental Noise Assessment Stonebridge Golf & Country Club Maintenance Facility Nepean, Ontario REPORT: GmE 09-042-Noise Prepared For: Rob Pierce 3584 Jockvale Road Nepean, Ontario K2C 3H2 Prepared

More information

Lacey Gateway Residential Phase 1

Lacey Gateway Residential Phase 1 Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West

More information

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND Prepared for: Department of Public Works Anne Arundel County Prepared by: URS Corporation 4 North Park Drive, Suite 3 Hunt Valley,

More information

Report Addendum. Terry Keller, SDDOT. Noise Study Technical Report I-29 from Tea Interchange to Skunk Creek Sioux Falls, South Dakota

Report Addendum. Terry Keller, SDDOT. Noise Study Technical Report I-29 from Tea Interchange to Skunk Creek Sioux Falls, South Dakota Report Addendum To: Terry Keller, SDDOT From: HDR Project: Noise Study Technical Report I-29 from Tea Interchange to Skunk Creek Sioux Falls, South Dakota cc: file Date: May 28, 2010; rev July 16, July

More information

Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University

Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University Shift: The City of London s Rapid Transit Proposal Shift: The City of London s Rapid Transit Proposal

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

105 Toronto Street South, Markdale Transportation Impact Study. Paradigm Transportation Solutions Limited

105 Toronto Street South, Markdale Transportation Impact Study. Paradigm Transportation Solutions Limited 105 Toronto Street South, Markdale Transportation Impact Study Paradigm Transportation Solutions Limited December 2016 Project Summary Project Number 162060 December 2016 Client Zelinka Priamo Ltd 318

More information

DUFFERIN AGGREGATES ACTON QUARRY EXTENSION PROJECT

DUFFERIN AGGREGATES ACTON QUARRY EXTENSION PROJECT DUFFERIN AGGREGATES ACTON QUARRY EXTENSION PROJECT Noise Impact Study Project#: 06183 Prepared By: Steven Titus, B.A.Sc. P.Eng. Bob Rimrott, M.A.Sc, P.Eng AERCOUSTICS ENGINEERING LIMITED 50 Ronson Drive

More information

On-Street Electric Vehicle Charging Stations - Parking Amendments

On-Street Electric Vehicle Charging Stations - Parking Amendments / STAFF REPORT ACTION REQUIRED On-Street Electric Vehicle Charging Stations - Amendments Date: August 20, 2012 To: From: Toronto and East York Community Council Acting Director, Transportation Infrastructure

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny

More information

Downtown One Way Street Conversion Technical Feasibility Report

Downtown One Way Street Conversion Technical Feasibility Report Downtown One Way Street Conversion Technical Feasibility Report As part of the City s Transportation Master Plan, this report reviews the technical feasibility of the proposed conversion of the current

More information

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project.

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project. EXECUTIVE SUMMARY This study addresses the traffic impacts associated with the proposed Shopko redevelopment located in Sugarhouse, Utah. The Shopko redevelopment project is located between 1300 East and

More information

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.

More information

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1.

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1. DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Subhas Bhargava July 9, 2015 115-620 Overview_1.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

West Hills Shopping Centre Lowe s Expansion Traffic Impact Study

West Hills Shopping Centre Lowe s Expansion Traffic Impact Study West Hills Shopping Centre Lowe s Expansion Traffic Impact Study Prepared for: Armel Corporation January 2015 Paradigm Transportation Solutions Ltd. 22 King Street South, Suite 300 Waterloo ON N2J 1N8

More information

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015 Memo To: From: Adrian Soo, P. Eng. Markham, ON : 165620021 Date: Reference: E.C. Row Expressway, Dominion Boulevard Interchange, Dougall Avenue Interchange, and Howard 1. Review of Interchange Geometry

More information

APPENDIX C: TECHNICAL SUPPORTING DOCUMENTS APPENDIX C-9: NOISE AND VIBRATION REPORT

APPENDIX C: TECHNICAL SUPPORTING DOCUMENTS APPENDIX C-9: NOISE AND VIBRATION REPORT City of Hamilton and Metrolinx Hamilton Light Rail Transit (LRT) Environmental Project Report (EPR) Addendum APPENDIX C: TECHNICAL SUPPORTING DOCUMENTS APPENDIX C-9: NOISE AND VIBRATION REPORT PART 1/1

More information

Clean Harbors Canada, Inc.

Clean Harbors Canada, Inc. Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260

More information

Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality Project

Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality Project Memo To: Paul DiDonato, ATI Architects and Engineers From: David Parisi, PE and Ashley Tam, EIT Date: February 23, 216 Subject: Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality

More information

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5.1 INTRODUCTION This chapter of the TMP presents an opinion of probable cost estimates for the proposed Horizon Year roadway network improvements

More information

Environmental Assessment Derry Road and Argentia Road Intersection

Environmental Assessment Derry Road and Argentia Road Intersection Air and Noise Study Environmental Assessment Derry Road and Argentia Road Intersection Project 11-4295 City of Mississauga, Region of Peel October 17, 2014 1 Region of Peel Environmental Assessment for

More information

5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS

5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS 5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS The Transportation Services Committee recommends the adoption of the recommendations contained in the following report

More information

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS... Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

More information

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) WELCOME TO OUR PUBLIC OPEN HOUSE EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) Preliminary Planning for a Transit Project Assessment Open House Martin Grove Road to Pearson International Airport September

More information

RE: A Traffic Impact Statement for a proposed development on Quinpool Road

RE: A Traffic Impact Statement for a proposed development on Quinpool Road James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 31, 2018 Ellen O Hara, P.Eng. Project Engineer DesignPoint Engineering & Surveying Ltd. 200 Waterfront

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES

OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES October 12, 2017 PREPARED FOR: Ms. Chantly Banayan 4822 Van Nuys Blvd. Sherman Oaks, CA 91403 PREPARED

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES...

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES... Transportation Impact Fee Study September 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS......4 POTENTIAL FUNDING SOURCES...7 PROPOSED

More information

Appendix F-1 Description of the Long-Term Alternatives

Appendix F-1 Description of the Long-Term Alternatives Appendix F-1 Description of the Long-Term Alternatives Memorandum Page 1 of 21 Project No. 9309 Phase 280 Date June 2, 2015 From Chris Sidlar (LEA) To Edward Presta / City of Toronto C.C. Terry Wallace

More information

V. DEVELOPMENT OF CONCEPTS

V. DEVELOPMENT OF CONCEPTS Martin Luther King, Jr. Drive Extension FINAL Feasibility Study Page 9 V. DEVELOPMENT OF CONCEPTS Throughout the study process several alternative alignments were developed and eliminated. Initial discussion

More information

3.15 SAFETY AND SECURITY

3.15 SAFETY AND SECURITY 3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum

More information

Construction Noise Memorandum

Construction Noise Memorandum Construction Noise Memorandum To: Ms. Paula Daneluk Date: June 13, 2013 Development Impact 9370 Studio Court, Suite 160 Elk Grove, CA 95758 From: Paul Bollard Bollard Acoustical Consultants, Inc. 3551

More information

4 SPEED LIMIT REVISIONS ON REGIONAL ROADS

4 SPEED LIMIT REVISIONS ON REGIONAL ROADS Report No. 4 of the Transportation Services Committee Regional Council Meeting of April 19, 2012 4 SPEED LIMIT REVISIONS ON REGIONAL ROADS The Transportation Services Committee recommends the adoption

More information

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017 Bennett Pit Traffic Impact Study J&T Consulting, Inc. Weld County, Colorado March 3, 217 Prepared By: Sustainable Traffic Solutions, Inc. http://www.sustainabletrafficsolutions.com/ Joseph L. Henderson,

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

Vanier Parkway and Presland Road Residential Development Transportation Impact Study

Vanier Parkway and Presland Road Residential Development Transportation Impact Study Vanier Parkway and Presland Road Residential Development Transportation Impact Study Final Report (Revised) March 2011 Submitted to: Groupe Lépine Ottawa Project No. 09-1613 Submitted by: Groupe Lépine

More information

TRANSPORTATION REVIEW

TRANSPORTATION REVIEW TRANSPORTATION REVIEW - PROPOSED MIX OF LAND USES IS CONSISTENT WITH THE CITY S UNDER THE GRANVILLE BRIDGE POLICIES THAT AIM TO MEET NEIGHBOURING RESIDENTS SHOPPING NEEDS AND REDUCE RELIANCE ON AUTOMOBILE

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

MEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:

MEMO VIA  . Ms. Amy Roth DPS Director, City of Three Rivers. To: MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed

More information

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution:

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Technical Memorandum To: Tom Hanrahan Jeff Sharp From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Barrie Lockhart Road LP Conformity Review Scott Young Sorbara Group

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA Assessment of Helicopter Noise A report Prepared on behalf of: JamCo Constructions Pty Ltd PO Box 631 Yarraville Victoria 3013 Ref: 11573-3jg March 2015

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:

More information

GTA West Corridor Planning and EA Study Stage 1

GTA West Corridor Planning and EA Study Stage 1 GTA West Corridor Planning and EA Study Stage 1 Draft Development Strategy Presentation to Peel Goods Movement Task Force April 8 2011 Study Areas 2 Unique Approach Unprecedented two-stage EA process:

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING ENVIRONMENTAL SETTING The following analysis summarizes the findings and conclusions of the Traffic Analysis (Traffic Study), prepared by The Mobility Group,

More information

Alpine Highway to North County Boulevard Connector Study

Alpine Highway to North County Boulevard Connector Study Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1

More information

PROJECT BACKGROUND 3

PROJECT BACKGROUND 3 AGENDA 1. Welcome & Introductions 2. Project Background 3. Project Approach & Schedule 4. Draft Long List of Options 5. Evaluation Process 6. Next Steps 2 PROJECT BACKGROUND 3 OUR RAPID TRANSIT NETWORK

More information

Attachment E3 Vibration Technical Memorandum

Attachment E3 Vibration Technical Memorandum Attachment E3 Technical Memorandum 77 South Bedford Street Burlington, MA 01803 T 781.229.0707 F 781.229.7939 E jross@hmmh.com W www.hmmh.com TECHNICAL MEMORANDUM To: Alisa Swank, CH2M HILL Jodi Ketelsen,

More information

GASOLINE SERVICE STATION 1618, 1622 ROGER STEVENS DRIVE OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for:

GASOLINE SERVICE STATION 1618, 1622 ROGER STEVENS DRIVE OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for: GASOLINE SERVICE STATION 1618, 1622 ROGER STEVENS DRIVE OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT Prepared for: Invecta Development (Ottawa) Corporation 758 Shanks Height Milton, ON L9T 7P7 May

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA Proposed location of Camp Parkway Commerce Center Vicinity map of Camp Parkway Commerce Center Southampton County, VA Camp Parkway Commerce Center is a proposed distribution and industrial center to be

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

King Street & Wyman Road Transportation Impact Study & Transportation Demand Management. Paradigm Transportation Solutions Limited

King Street & Wyman Road Transportation Impact Study & Transportation Demand Management. Paradigm Transportation Solutions Limited King Street & Wyman Road Transportation Impact Study & Transportation Demand Management Paradigm Transportation Solutions Limited April 28 Project Summary Project Number 822 April 28 Client RISE Commercial

More information

NOISE ANALYSIS TECHNICAL REPORT. Route 58 Martin Luther King Freeway. Portsmouth Virginia

NOISE ANALYSIS TECHNICAL REPORT. Route 58 Martin Luther King Freeway. Portsmouth Virginia NOISE ANALYSIS TECHNICAL REPORT Route 58 Martin Luther King Freeway Portsmouth Virginia May 2008 Prepared for: Virginia Department of Transportation NOISE ANALYSIS TECHNICAL REPORT Route 58 Martin Luther

More information

2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN

2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN 2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN The Transportation Services Committee recommends the adoption of the recommendations contained in the following report dated

More information

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

Table of Contents. Traffic Impact Analysis Capital One Building at Schilling Place

Table of Contents. Traffic Impact Analysis Capital One Building at Schilling Place Traffic Impact Analysis Capital One Building at Schilling Place Table of Contents Executive Summary... 1 1. Introduction... 4 2. Project Description... 4 3. Background Information... 4 4. Study Scope...

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 24 UPDATED

More information

Appendix A-L Public Information Centre 3 Materials

Appendix A-L Public Information Centre 3 Materials Appendix A-L Public Information Centre 3 Materials RAPID TRANSIT CORRIDORS ENVIRONMENTAL ASSESSMENT STUDY NOTICE OF PUBLIC INFORMATION CENTRE #3 The City of London is entering a new chapter in its history

More information

Yonge-Eglinton. Mobility Hub Profile. September 19, 2012 YONGE- EGLINTON

Yonge-Eglinton. Mobility Hub Profile. September 19, 2012 YONGE- EGLINTON September 19, 2012 PEEL YORK HALTON DURHAM HAMILTON TORONTO YONGE- EGLINTON MOBILITY HUBS: places of connectivity between regional and rapid transit services, where different modes of transportation come

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

November 14, 2016 Reference No

November 14, 2016 Reference No November 14, 2016 Reference No. 11115752 Mr. Andrew Booth Engineering Services City Service Centre 9505-112 Grande Prairie, Alberta T8V 6H8 Dear Mr. Booth: Re: 2016 Arterial Traffic Noise Survey City of

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

Brad Pridham, P.Eng., Ph.D. R. L. Scott Penton, P.Eng.

Brad Pridham, P.Eng., Ph.D. R. L. Scott Penton, P.Eng. Eglinton Crosstown Light Rail Transit Project East of Black Creek Drive to Jane Street And the Maintenance and Storage Facility Environmental Noise and Vibration Assessment Novus Reference No. 12-0167

More information

Silverado Village Project

Silverado Village Project Environmental Noise Assessment Silverado Village Project Elk Grove, California BAC Job # 2011-053 Prepared For: Vintara Holdings, LLC Attn: Mr. Paul Eblen 140 Diamond Creek Place Roseville, CA 95747 Prepared

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for:

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for: L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY 2012 Prepared for: Hillside Construction, Inc. 216 Hemlock Street, Suite B Fort Collins, CO 80534 Prepared by: DELICH ASSOCIATES

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

Proposed Pit Development

Proposed Pit Development July 5, 2017 via email: sam@greenwoodconst.ca CCTA File 114239 Sam Greenwood Greenwood Aggregates 205467 County Road 109 Amaranth, ON L9W 0V1 Re: Proposed Violet Hill Gravel Pit, Town of Mono Traffic Review

More information

Mercer Island Center for the Arts Parking Management Plan

Mercer Island Center for the Arts Parking Management Plan Parking Stalls Mercer Island Center for the Arts Parking Management Plan June 15, 2016 This Parking Management Plan (P) covers all tenants at the Mercer Island Center for the Arts (MICA) campus, including

More information

2.1 TRANSIT VISION 2040 FROM VISION TO ACTION. Expand regional rapid transit networks STRATEGIC DIRECTION

2.1 TRANSIT VISION 2040 FROM VISION TO ACTION. Expand regional rapid transit networks STRATEGIC DIRECTION TRANSIT VISION 2040 FROM VISION TO ACTION TRANSIT VISION 2040 defines a future in which public transit maximizes its contribution to quality of life with benefits that support a vibrant and equitable society,

More information