Design of the High Speed Rail System in California. Orange County to Los Angeles Segment

Size: px
Start display at page:

Download "Design of the High Speed Rail System in California. Orange County to Los Angeles Segment"

Transcription

1 Andrew W. Sokol 1 Design of the High Speed Rail System in California Orange County to Los Angeles Segment Andrew W. Sokol, P.E. STV Incorporated 2009 AREMA Conference and Exposition Chicago, Illinois (total 4,189 words)

2 Andrew W. Sokol 2 Design of the High Speed Rail System in California Orange County to Los Angeles Segment ABSTRACT The California High Speed Rail Authority was formed twelve years ago to develop a high speed rail network designed to meet California s future transportation challenges. Speeds up to 220 MPH using a steel-wheel-on-steel-rail system were envisioned to allow travel times between select destinations competitive with air travel. All of the major metropolitan areas within California are included in the planned routes. These include Sacramento, the San Francisco Bay Area, the Central Valley, Los Angeles, Orange County, the Inland Empire, and San Diego. Project Level EIR/EIS and Preliminary Engineering are now proceeding concurrently and are due to be completed in late The 30-mile segment between Anaheim and Los Angeles presents many significant engineering and construction challenges. Designing solutions to these will help establish precedents that may be applied to design of the rest of the system, and other future high speed rail systems in the U.S. Key issues of design significance include: Statewide and segment-specific design criteria for curve criteria, superelevation and clearances; Major new terminal stations are being planned in Los Angeles and Anaheim; Running in or adjacent to an existing rail corridor, Burlington Northern Santa Fe s active San Bernardino Subdivision and the challenges posed; Federal Railroad Administration Compliance Issues; and Running through a densely populated urban area, either at-grade or on aerial structure.

3 Andrew W. Sokol 3 INTRODUCTION The introduction of a high speed rail system in California, officially called the California High Speed Train (HST) Project, will provide safe, reliable intercity train service, Figure 1 Statewide Map of the California High Speed Train Project

4 Andrew W. Sokol 4 with travel times comparable to air transportation. At full build out, over 700 miles of tracks will connect all the major population centers of in California. A new, dedicated, fully grade separated, steel-wheel-on-steel-rail guideway will allow trains to operate at speeds of up to 220 miles per hour (MPH). An express service trip between Los Angeles and San Francisco is estimated to take just over 2 hours 30 minutes. High Speed trains will be electrically powered via a 2x25kV Autotransformer Power Supply System and an Overhead Contact System (OCS), which is a proven technology to provide safe, reliable traction power for electric rail systems. The California High Speed Rail Authority (CHSRA), formed in 1996, is a state agency that is tasked with the planning, design and construction of the HST system. In January 2007, a significant milestone was achieved, as one of the small but key segments, the Orange County to Los Angeles (OC-LA) segment, advanced into the more detailed, preliminary engineering and project-level Environmental Impact Study / Report (EIS/EIR) phase. Other segments followed or will follow shortly thereafter. The selected routes and a brief summary of key design issues will be presented for the OC-LA segment, which is one of the furthest advanced segments. For the OC-LA segment, moving into Preliminary Engineering and EIS/EIR meant the design team could begin tackling the many significant design challenges along the route. This paper will present a brief summary of the status of design, decisions made and some of the key engineering-related issues addressed or still to be addressed. The OC-LA segment is the furthest advanced and the work performed on that segment will set precedent that may be applied to design of the rest of the system, and likely other future high speed rail systems in the U.S.

5 Andrew W. Sokol 5 BACKGROUND A broad-based program level environmental review process was completed in 2005, culminating in a certified Statewide Final Program EIR/EIS. This process analyzed a host of issues related to the basic feasibility of building a HST system and the process established some key features about the system to move forward with. These included train vehicle technology and selection of the basic routes. For vehicle technology, the Very High Speed steel-wheel-on-steel-rail mode (speeds up to 220 MPH) was recommended over Maglev and Non-electrified alternatives. For the OC-LA segment, the LOSSAN (Los Angeles to San Diego) corridor was recommended over the Union Pacific Santa Ana Branch Line. The Route The recommended route follows the same basic path between Los Angeles and Anaheim Figure 2 Map of the Orange County to Los Angeles HST Segment Source: AE LLC, STV Incorporated

6 Andrew W. Sokol 6 used by existing Metrolink commuter rail and Amtrak intercity service. The 30-mile long route parallels a busy rail corridor and contains three segments of different ownership. Starting from the Los Angeles (north) end, the west bank line of the Los Angeles River is owned by Metro; the San Bernardino Subdivision is owned by the Burlington Northern Santa Fe Railway (BNSF); and the Orange Subdivision is owned by the Orange County Transportation Authority (OCTA). The corridor is generally a two or three track high density line mainline carrying up to 160 trains per day. The HST system is planned to be constructed mainly on the southwest side of the existing R/W (though a short portion of the HST flies over and runs on the north east side of the existing R/W). Running parallel to (and partially within) an existing rail corridor has the benefits of reducing property or roadway impacts compared to non-rail corridor alternatives, but it does require mitigating numerous freight spurs and connections branching off the main line. Approximately 50% of the land abutting the route is industrial, 8% residential, 4% commercial and 2% parks and 2% institutional. Approximately 30% is occupied by transportation uses (both roadway and railroad). Operations Operations analysis for the OC-LA HST segment considered the entirety of train operations along the LOSSAN Corridor (i.e. conventional passenger and freight in addition to HST). The majority of the segment (BNSF s San Bernardino Subdivision, from Redondo Junction to Fullerton Junction 20 miles) is two- or three-track mainline carrying both freight and conventional passenger service, with the current and forecast volumes shown in table 1.

7 Andrew W. Sokol 7 Table 1 Current and Forecast Train Volumes Operator Type of Service Current Volume (trains per day) Year 2030 Forecast Volume (trains per day) BNSF Freight 90 (approx.) 133 Metrolink Commuter Amtrak Regional / Intercity Source: CHSRA- Concept Level Operational Feasibility Study The basic findings were that for the forecasted volumes of the year 2030: 1) Two tracks dedicated to freight only would be insufficient for freight operations. 2) Two new dedicated HST tracks could support a limited amount of conventional passenger train service. 3) Three tracks dedicated to freight and conventional passenger service, while sufficient for the short term, may become insufficient when considering forecasted volumes. Therefore, either a portion of conventional service could run on the HST tracks, or a fourth conventional track would need to be added along parts of the corridor. Therefore, the design approach is to provide a new two-track HST guideway that does not preclude the potential of accommodating conventional passenger train equipment. This HST guideway would be situated such that the third conventional main track can be readily constructed (where it doesn t already exist) without impact, and a fourth track could be added in the future within the R/W (refer to Figure 1).

8 Andrew W. Sokol 8 Figure 3 Basic Track Configuration between Redondo Jct. and Fullerton Jct. Initial service is planned for 6 high speed trains per hour in each direction. The two HST main tracks could support up to 20 high speed trains, or some combination of HST and Metrolink trains, per hour in each direction, assuming a compatible signal system and comparable operating speeds. The optimal maximum speed for HST for the OC-LA segment was found to be 125 MPH. Whereas speeds up to 150 MPH could be achieved on some straight portions of the alignment, the overall trip time saved would only be six seconds. Trip time between Anaheim and Los Angeles is approximately 20 minutes. High Speed trains will be electrically powered via a 2x25kV Autotransformer Power Supply System and an Overhead Contact System (OCS), which is a proven technology to provide safe, reliable traction power for electric rail systems.

9 Andrew W. Sokol 9 PRELIMINARY ENGINEERING Preliminary engineering for the OC-LA segment began in January 2007 concurrently with project level EIR/EIS. A 10% Design plan set was submitted in March 2009, and a 15% will be completed in December Preliminary engineering (30% design level) will be completed in December The CHSRA is currently contemplating tailoring the 30% design into procurement documents for a Design Build contract. Track Configuration Figure 4 Summary of HST Vertical Configuration Source: AE LLC, STV Incorporated The HST system is planned to be a dedicated double track with dedicated north- and southbound tracks and no reverse running permitted under normal circumstances (except at station

10 Andrew W. Sokol 10 approaches and off-hour non-revenue moves). The HST guideway will be fully isolated and grade separated from all other railroads and roadways. Currently, approximately 50% of the HST guideway is planned to be at-grade, 26% on and aerial viaduct, 2% in a trench, and 23% yet to be determined. In the areas still to be determined, preliminary engineering is proceeding equally on both, with the final selection to be determined prior to the end of the preliminary engineering phase. Limited sharing of the HST tracks with conventional train service (Amtrak and Metrolink) is being considered as it could bring nearer term benefits and long term enhancements to conventional passenger train operations, but adds significant complexity, particularly in the connections of existing conventional lines to the HST tracks. Also, operational logistics, motive power and signaling systems will have to be made compatible, with approval from the Federal Railroad Administration. Grade Crossings No at-grade crossings are permitted, so all existing road and rail grade crossing will have to be grade separated or closed. A total of 87 crossings exist along the corridor (many already grade separated). All of the roadway crossings are being evaluated for closure, lowering (generally, the road will be lowered under the HST guideway), or modification of the existing grade separated crossings. A handful of existing grade crossings are in various stages of design and construction by others, and the HST design team is coordinating with those projects to help ensure compatibility with HST construction.

11 Andrew W. Sokol 11 At-Grade Guideway The default design is to have the HST system run at grade. At the current level of design, it is critical to establish the total width of the guideway and offset from existing tracks. This will be used to determine property and Figure 5 Basic At-grade Typical Section environmental impacts (a process that is advancing concurrently). Figure 5 shows the basic dimensions that have been established to design the track alignments and determine the footprint that will be required to build the system. Aerial Guideway Where it is exceedingly difficult or Figure 6 Basic Aerial Viaduct Typical Section cost-prohibitive to keep the HST guideway at grade, it will rise up and fly over the conflicting facility on and aerial viaduct (typical section shown in Figure 6). Similar to the at grade portions, at this early stage of design, it is crucial to select a basic typical section that provides enough room for

12 Andrew W. Sokol 12 the track running clearances, OCS system, system duct banks, and emergency and maintenance walkways. Offset of the structure from existing tracks is also an important factor that can greatly affect cost and impact to adjacent properties, as well as constructability of the system. As such, sizing of the structure based on design loading cases and geotechnical conditions must be considered. Because these include factors that are not fully established at this time, the sizing and location of the aerial viaduct portions must be carefully considered and selected conservatively enough to accommodate anticipated future design refinement. Trench and Tunnel The majority of the HST system will run either at-grade or aerial, but there are short sections of shallow trench to lower the HST under two potential conflicts: The Fullerton Municipal Airport flight path, and an existing crossing of Alondra Blvd., where the HST guideway would follow the profile of the BNSF tracks and run in a retained cut. A two and a half mile long tunnel is being considered as an alternative for a particularly constrained portion of the LOSSAN in the Anaheim area. More specifics will be provided later in this paper. Track Alignment Alignment design for HST operation is generally based upon European and Japanese standards, though also incorporates applicable common American practices and AREMA recommendations. The basic CHSRA mandate is to design all unrestricted portions of the route to a 220 MPH design speed, and where not cost-prohibitive, without precluding the future possible increase up

13 Andrew W. Sokol 13 to 250 MPH operation. Where the HST runs adjacent to existing railroad tracks, and where other constraints exist, design speeds will be lower as a practical necessity. The OC-LA segment runs between Anaheim and downtown Los Angeles, and generally parallels the existing LOSSAN railroad corridor, which includes a number of track curves that will constrain design speed. Because of the dense urbanized nature of this segment, the maximum design speed has been established at 125 MPH. This is the same case for the San Jose to San Francisco segment, which parallels the Caltrain Corridor. To summarize the segment, there is one sharp curve at Fullerton Junction that limits speed to 60 MPH. The remainder of the curves along the corridor is designed for 100 to 125 MPH operation, with the exception of the station approaches. Curve radius, superelevation, spiral transition, and vertical curve parameters are very similar to those for conventional passenger lines. All criteria are based upon maintaining high passenger ride comfort levels, generally meeting or exceeding current HST systems around the world. Superelevation is calculated using the formula: Total Superelevation (Ea + Eu) = 4.0V 2 / R Where: Ea = Actual Superelevation Eu = Unbalanced Superelevation V = Design Velocity R = Curve Radius in Feet

14 Andrew W. Sokol 14 Minimum spiral transition length is determined by the greatest length determined based upon the factors indicated in table x. Generally, desirable parameters are used, except where geometric constraints require use Minimum or Exceptional values to maintain desired speeds. Table 2 Minimum Spiral Transition Length Spiral Minimum Length Based Upon Desirable Minimum Exceptional Actual Superelevation 1.63EaV 1.30EaV 1.09EaV Unbalanced Superelevation 2.10EuV 1.57EuV 1.26EuV Twist Rate 140Ea 118Ea 98Ea Minimum Segment 2.64V 2.20V 1.47V Source: CHSRA Alignment Standards for HST Operations Passenger Stations Major HST Stations are planned at Los Angeles and Anaheim. An intermediate station may also be included, and would be located adjacent to the Metrolink / Amtrak stations at Fullerton or Norwalk / Santa Fe Springs. Cities will be active partners in developing plans for the station in their respective City. Los Angeles Station The Los Angeles station is projected to be the busiest station in the system. A number of different configurations were analyzed for this station, including underground below the existing red line subway station under Los Angeles Union Station (LAUS). Another alternative considered was a partially underground station along the west bank of the Los Angeles River approximately 1,500 feet east of LAUS. The configuration being carried forward in Preliminary Engineering is an aerial HST station located directly above the existing at-grade Metrolink,

15 Andrew W. Sokol 15 Amtrak and Metro Orange Line LRT tracks, on a second level. The HST station will include three 1,380-foot long platforms served by six tracks. Anaheim Station (key station) The City of Anaheim and OCTA are jointly developing a large, multi-modal transportation center in the City of Anaheim. Located near State Route 57, at the site of the existing train station, and adjacent to two major sports facilities (Angel Stadium and the Honda Center), the planned ARTIC will serve as a major transportation hub in the area with a number of potential future modes being accommodated. The HST system will terminate at this station with what is currently planned as a two platform, four track HST station. Grade separated connections to Metrolink, Amtrak and bus service will be provided. Norwalk / Santa Fe Springs Station (optional station) This station is near the geographic midpoint between Los Angeles and Anaheim. The planned HST station is a grade, located approximately a half mile north of the existing Metrolink / Amtrak station, which would remain in place. Bypass tracks will be provided to permit express train service to run through the station without stopping. Fullerton Station (optional station) Fullerton Station is a substantial passenger station and is therefore being considered for a HST station. It is at Fullerton Junction, where Metrolink train service splits off toward either San Bernardino or Anaheim. This station is located approximately five miles north of the planned Anaheim station. Due to significant geometric constraints including nearby new and existing

16 Andrew W. Sokol 16 residential housing, the HST station at Fullerton would be an aerial station, located above the existing Metrolink / Amtrak station. As with the Norwalk / Santa Fe Springs Station, bypass tracks will be provided. Significant Constraints and Design Issues The OC-LA segment has approximately ten project areas where significant physical obstacles will require complex and carefully considered design solutions. The following is a sample of a few of these issues. Los Angeles Station South Approach / Los Angeles River Bank The area just south of Los Angeles Union Station involves a number of important design considerations. There is no existing railroad right-of-way (R/W) in the area immediately south of the station, so an all new R/W will need to be acquired. The area is mixed industrial and commercial, but as the HST alignment approaches the Los Angeles River, there is also some existing and planned residential development. To minimize impacts, the HST guideway is on an aerial structure coming south out of the station, and remains aerial, flying over the historic 1 st Street bridge, before descending under the historic 4 th Street bridge once entering existing railroad R/W. A fairly sharp S-curve is used to direct the HST alignment from the station to the Los Angeles River, where the existing Metro-owned West Bank Line exists, while avoiding a large property development project and other key properties. Speed on the south approach the station is limited to 35 MPH as a result.

17 Andrew W. Sokol 17 Amtrak has plans for a set of run-through tracks coming out of the south end of Los Angeles Union Station that would allow through movement into and out of the station for Amtrak and select Metrolink trains. Currently, the station is stub ended. These run through tracks are being accommodated in the design of the HST tracks. BNSF Hobart Yard / I-710 Freeway BNSF s Hobart Yard, a very large intermodal rail yard located only a few miles from the north end of the Alameda Corridor, principally receives and handles shipping containers coming from the Ports of Los Angeles and Long Beach. This is built-out, fixed facility which the HST alignments must avoid without impact. Due to this fact, and the busy nature of the roadway (26 th Street) which is heavily utilized by truck traffic related to the intermodal yard and other uses, and the industrial land uses to the south, the HST line will traverse this area on an aerial viaduct. The total length of this viaduct, which begins at the Los Angeles River, crosses over the north end of Hobart Yard and ends at the I-5, is approximately 5.3 miles. DT Junction / Slauson Avenue Bridge The DT Junction / Slauson Avenue Bridge area poses a design challenge, with a couple of potential design solutions still being considered. The Union Pacific (UP) Patata Line, which runs along the east bank of the San Gabriel River, crosses the BNSF main tracks in this area right under the Slauson Avenue bridge. The presence of a high tension power line in the vicinity also adds to the complexity of the area.

18 Andrew W. Sokol 18 The first alternative being considered is to have the HST guideway run at-grade on the south side of the existing tracks, under the bridge (shown in Figure x). This would necessitate the lowering of the UP Patata Line into a trench, relocation of the high tension power line, and heavy modification, or possibly complete reconstruction of the Slauson Avenue bridge. The second alternative is to have the HST guideway fly over the Slauson Avenue bridge on an aerial structure that would also then fly over the I-610 and the UP La Habra Subdivision track; a total length of just over two miles. A decision on which alternative to use will be made prior to completion of preliminary engineering. La Mirada Corridor A three mile long portion of the LOSSAN is highlighted by extensive industrial freight tracks on the south side, and an important roadway (Stage Road) on the north. The track alignment has been refined in this area with a series of gentle reversing curves to minimize the impacts to existing rail and roadway facilities, generally running at-grade. Typical geometry used in the reversing curves is shown below. Note the large radius selected to maintain minimum curve length with very slight deflection angles: Design Velocity: Curve Radius: Actual Superelevation: Unbalanced Superelevation: Spiral Length: 125 MPH 30,000-feet 1.0 inches 1.08 inches 330-feet (based on 2.64V)

19 Andrew W. Sokol 19 There are also a number of existing and proposed roadway grade separations in place that the design team is accommodating and proposing modifications to where necessary. Fairly extensive modifications to Stage Road and the freight tracks on the south will be required. Narrow Right-of-Way in Anaheim An approximate 2-mile long portion of the corridor located in the City of Anaheim (between Vermont and La Palma Avenue) is only 50 wide and contains two existing tracks. There are also densely spaced at-grade crossings (total of six) in this area. The R/W in this area is owned by OCTA and primarily supports Metrolink and Amtrak operation, though also some local freight traffic (5 to 10 freight trains per day). Due to the narrow width of the R/W; the number of grade separations that would be required; and impacts to the nearby residential neighborhoods, a bored tunnel alternative is being studied in this area. The bored tunnel would have to be deep enough to pass under the existing roadway Lincoln Avenue, Carbon Creek and would require temporary shooflies that would require significant property acquisitions. A cut and cover tunnel option was considered but was found to be infeasible from a constructability perspective. The other alternative is to acquire an entire new strip of R/W west of the existing R/W to accommodate the full width of the HST guideway at grade. The at-grade alternative would necessitate the grade separation of all the existing grade crossings. In either alternative, extensive impacts and land acquisition will be required.

20 Andrew W. Sokol 20 Trains and Vehicle Maintenance Vehicles have not yet been selected, therefore the tracks, stations and infrastructure are being designed to allow large latitude in the selection of vehicles, so to not preclude any potential vehicle designs, either existing or new. The primary vehicle maintenance facility, to be used for major repair and overhaul, is planned to be located in the Central Valley, near the geographic center of the system. A large layover and light-maintenance facility will also be required at Los Angeles, and/or Anaheim. Sites in both cities within 3-miles of the stations are being studied. The facility needs to be sized to provide daily cleaning and storage of 60 trains a day, as well as perform periodic inspection and running repairs. Sites of 80 acres to 140 acres are being studied. Federal Railroad Administration (FRA) Compliance Issues If the HST tracks share operation with limited Metrolink service, which is under consideration, a waiver allowing FRA-compliant vehicles to run on the same tracks as non-compliant HST trains would need to be granted by the FRA. The CHSRA will also seek formal input and guidance from the FRA on requirements for physical separation distance, intrusion detection systems, and barrier walls that will be needed between conventional tracks and the HST guideway. To this point in design, the FRA has provided general input and review comments on design submittals, including conceptual plans and environmental documents completed to date.

21 Andrew W. Sokol 21 CONCLUSION The California High Speed Train Project, with the OC-LA segment at the forefront of the process, is establishing new design standards and criteria that can be used in other U.S. high speed rail systems developed in the future. The design process is still at an early stage, as preliminary engineering is scheduled to be completed at the end of 2010, however, many important design standards and criteria are presently being established. Final track alignments and full environmental clearance will be completed at the end of the preliminary engineering phase. The OC-LA segment may also provide valuable guidance in designing such systems in densely urbanized environments, and along busy existing railroad corridors.

22 Andrew W. Sokol 22 List of Figures and Tables Page Number Figure 1 Statewide Map of the California High Speed Train Project Figure 2 Map of the Orange County to Los Angeles HST Segment Figure 3 Basic Track Configuration between Redondo Jct. and Fullerton Jct. Figure 4 Summary of HST Vertical Configuration Figure 5 Basic At-grade Typical Section Figure 6 Basic Aerial Viaduct Typical Section Table 1 Current and Forecast Train Volumes Table 2 Minimum Spiral Transition Length

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Southern California - CHSRA

Southern California - CHSRA CALIFORNIA HIGH-SPEED RAIL Michael Gillam, Deputy Program Director Southern California - CHSRA CMAA - Construction Management Association of America July 19, 2012 CALIFORNIA S HIGH-SPEED TRAIN SYSTEM Largest

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM California High-Speed Train Project TECHNICAL MEMORANDUM TM 1.1.0 Prepared by: Mike Hawkins, PE Checked by: Christian Schang Approved by: Signed document on file 16 Mar 07_ Ken Jong, PE, Engineering Manager

More information

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS Paul Mak, PE, SE HDR Inc 801 S. Grand Ave. Suite 500, Los Angeles, CA 90017. Tel

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS. Paul Mak, PE, SE - DMJM HARRIS

PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS. Paul Mak, PE, SE - DMJM HARRIS 1 PAPER FOR AREMA 2004 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS Paul Mak, PE, SE - DMJM HARRIS 515 S. Flower Street 9th Floor, Los Angeles, CA 90071. Tel 213-593-8337 Fax 213-593-8622

More information

June WASHINGTON STATE DEPARTMENT OF TRANSPORTATION Alaskan Way Viaduct and Seawall Replacement Program Seattle, Washington

June WASHINGTON STATE DEPARTMENT OF TRANSPORTATION Alaskan Way Viaduct and Seawall Replacement Program Seattle, Washington DESIGN DEVIATION NOs. 1 & 2 Horizontal Stopping Sight Distance and Shoulder Width Reduction SR 99 S. Holgate St to S. King St. Viaduct Replacement Stage 2 MP 29.89 TO MP 30.78 XL-3237 PIN-809936D June

More information

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013 East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM California High-Speed Train Project TECHNICAL MEMORANDUM Alignment Standards for Shared Use Corridors (Specific to Los Angeles to Anaheim) TM 1.1.6 Prepared by: Signed document on file 17 Dec 07_ George

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) A: 2014 SFMTA TRANSIT SERVICE INFORMATION B: SFMTA TRAFFIC COUNT DATA C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) E: LAND USE AND VALUE

More information

U.S. System Summary: ARIZONA/SOUTHWEST

U.S. System Summary: ARIZONA/SOUTHWEST U.S. System Summary: ARIZONA/SOUTHWEST Arizona/Southwest High-Speed Rail System (Source: Texas A&M Transportation Institute) The Arizona/Southwest high-speed rail system described in this summary groups

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

High-speed Rail in California:

High-speed Rail in California: High-speed Rail in California: The Process to Success AREMA 2010 National Conference By: Bruce Armistead Assistant Vice President Parsons Brinckerhoff 444 S. Flower Street, Suite 3700 Los Angeles, CA 90071

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

U.S. System Summary: CALIFORNIA

U.S. System Summary: CALIFORNIA U.S. System Summary: CALIFORNIA California High-Speed Rail System (Source: CHSRA) The California high-speed rail system is a proposed system containing 798 miles of routes in nine segments wholly contained

More information

San Francisco to San Jose Preliminary Alternatives Analysis

San Francisco to San Jose Preliminary Alternatives Analysis San Francisco to San Jose High-Speed Train Project EIR/EIS San Francisco to San Jose Preliminary Alternatives Analysis April 15, 2010 Page 1 Largest Public Transportation Project in U.S. History 800 miles

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

Metro Green Line to LAX Alternatives Analysis. March 2012

Metro Green Line to LAX Alternatives Analysis. March 2012 Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX

More information

Sepulveda Pass Corridor Systems Planning Study Update

Sepulveda Pass Corridor Systems Planning Study Update Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Update June 20, 2012 Measure R Transit Corridors One of 12 Measure R Transit Corridors approved by

More information

Introducing the Solution to LA s Airport Congestion Problem

Introducing the Solution to LA s Airport Congestion Problem Presentation by Roger J. Rudick Introducing the solution to the County s airport congestion problem Introducing the Solution to LA s Airport Congestion Problem Existing infrastructure, off-the-shelf technology,

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE.

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. Comment to CHSRA Missing Utility Costs Page!1 May 7, 2018 COMMENT FOR CHSRA BUSINESS PLAN: ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. HIGH VOLTAGE TOWERS THAT CARRY ELECTRICITY

More information

Successful Passenger Rail in the State of California

Successful Passenger Rail in the State of California Successful Passenger Rail in the State of California Texas Transportation Forum Austin, Texas Eugene K. Skoropowski, Managing Director Capitol Corridor Joint Powers Authority (CCJPA) Oakland, California

More information

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012 Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried

More information

SAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017

SAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017 SAN FRANCISCO TO SAN JOSE PROJECT SECTION City of Brisbane Baylands Public Hearing June 7, 2017 CALIFORNIA HIGH-SPEED RAIL PROGRAM OVERVIEW 2 HIGH-SPEED RAIL: Connecting California 3 HIGH-SPEED RAIL: It

More information

The range of alternatives has been reviewed with the RTAC Subgroup and the preliminary analysis is proceeding on the following HCT alternatives:

The range of alternatives has been reviewed with the RTAC Subgroup and the preliminary analysis is proceeding on the following HCT alternatives: Attachment 2 Boise Treasure Valley Phase 1 Alternatives Analysis August 14, 2009 Introduction The Treasure Valley High Capacity Transit Priority Corridor Phase 1 Alternatives Analysis is being prepared

More information

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Pantograph Clearance Envelopes TM 3.2.3 Prepared by: Signed document on file 21 Mar 08 Xavier de Vimal Checked by: Signed document on file 15 July 09 Richard Schmedes Approved by:

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

Metro Harbor Subdivision Transit Corridor November 2009 Alternatives Analysis Report Final

Metro Harbor Subdivision Transit Corridor November 2009 Alternatives Analysis Report Final 3. ALTERNATIVES 3.1. INTRODUCTION 3.1.1. Chapter Purpose and Structure The purpose of the Alternatives Chapter is to introduce a preliminary set of alternatives, screen these alternatives using and identify

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California

More information

FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST)

FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST) FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST) The Fresno County subsection of the California High- Speed Train System (HST) is analyzed in two separate EIR/EISs the Merced-Fresno EIR/EIS

More information

Sepulveda Pass Corridor Systems Planning Study

Sepulveda Pass Corridor Systems Planning Study Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Streets and Freeways Subcommittee January 17, 2013 1 Sepulveda Pass Study Corridor Extends for 30

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

Caltrain Downtown Extension Project (DTX)

Caltrain Downtown Extension Project (DTX) Presentation to TJPA Board Caltrain Downtown Extension Project Update June 21, 2007 Caltrain Downtown Extension Project (DTX) Topics: DTX Progress HSR QA Initiative Next Steps 1 DTX Progress DTX Progress

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM California High-Speed Train Project TECHNICAL MEMORANDUM Station Platform Geometric Design TM 2.2.4 Prepared by: Signed document on file 16 May 08_ Dominique Rulens Checked by: Signed document on file

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Agenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close

Agenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close Agenda Open House Presentation Question and Answer Break Out Groups Report Out & Close Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Sunnyvale Dominic Spaethling

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

IH 35 FEASIBILITY STUDY

IH 35 FEASIBILITY STUDY IH 35 FEASIBILITY STUDY COOKE COUNTY, TEXAS February 1, 2007 Prepared by: Carter & Burgess, Inc. For: The Wichita Falls District of the Texas Department of Transportation INDEX I. INTRODUCTION. 3 II. PURPOSE

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

ALAMEDA CORRIDOR. A A Project of National Significance. TRB Summer Conference MTS as a Component of the Nation s Transportation System June 25, 2002

ALAMEDA CORRIDOR. A A Project of National Significance. TRB Summer Conference MTS as a Component of the Nation s Transportation System June 25, 2002 ALAMEDA CORRIDOR A A Project of National Significance TRB Summer Conference MTS as a Component of the Nation s Transportation System June 25, 2002 Top U.S. Container Ports (2001) LOS ANGELES 5.18 LONG

More information

SAN FRANCISCO TO SAN JOSE PROJECT SECTION

SAN FRANCISCO TO SAN JOSE PROJECT SECTION SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

Rail~Volution 2012 R. Gregg Albright

Rail~Volution 2012 R. Gregg Albright CALIFORNIA HIGH-SPEED RAIL AUTHORITY October 16 th, 2012 Rail~Volution 2012 R. Gregg Albright WHAT IS CALIFORNIA HIGH-SPEED TRAIN PROJECT (CHSTP) and HOW WILL IT BE IMPLEMENTED? 2 CALIFORNIA HIGH SPEED

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

3. PRELIMINARY DEFINITION OF ALTERNATIVES

3. PRELIMINARY DEFINITION OF ALTERNATIVES 3. PRELIMINARY DEFINITION OF ALTERNATIVES The purpose of the Preliminary Definition of Alternatives is to introduce the alternatives, including modes and off- and on-airport routes that will be carried

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

SAN RAFAEL CITY COUNCIL AGENDA REPORT

SAN RAFAEL CITY COUNCIL AGENDA REPORT Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79

More information

SF-LA (125 mph) 2: : :32. SF-SJ (110 mph)

SF-LA (125 mph) 2: : :32. SF-SJ (110 mph) California High-Speed Rail Program Management Team To: Fr: Re: 3 January 203 Jeff Morales, CEO, California High-Speed Rail Authority Frank Vacca, Chief Program Manager, California High-Speed Rail Authority

More information

Conceptual renderings subject to change

Conceptual renderings subject to change Conceptual renderings subject to change OCTA Special Needs Committee Presentation Tuesday, Project Presenter Jamie Lai, P.E. Transit Manager, City of Anaheim The ARTIC Project Manager 2 The ARTIC Project

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

TITLE. Planning and Design for Commuter Rail on a Busy Branchline. By Train to Perris, Not Paris

TITLE. Planning and Design for Commuter Rail on a Busy Branchline. By Train to Perris, Not Paris TITLE Planning and Design for Commuter Rail on a Busy Branchline By Train to Perris, Not Paris The Riverside County Transportation Commission's Perris Valley Line AUTHOR Tyler Bonstead STV Incorporated

More information

Measure R Funded Transit Projects

Measure R Funded Transit Projects Measure R Funded ransit Projects Crenshaw/LAX ransit Corridor New Potential LAWA erminal & Ground Access Facilities ypes of Connections Direct Light Rail ransit (LR) Branch Metro goes to the airport Metro

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii TABLE OF CONTENTS SECTION PAGE Executive Summary... xii 1.0 Introduction... 1 1.1 Study Area... 2 1.2 Traffic Impact Analysis Scenarios... 4 1.3 Study Area - City of Orange... 4 2.0 Project Description

More information

David Chow, P.E., AICP Director, IBI Group

David Chow, P.E., AICP Director, IBI Group David Chow, P.E., AICP Director, IBI Group Existing Conditions get worst ROADWAY CONDITIONS IN 2030 Daily delay goes from 2.2 to up to 5.4 million hours lost in congestion Unreliability of the roadway

More information

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

The Eastern Connector Study November, 2007 planning for the future

The Eastern Connector Study November, 2007 planning for the future The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team

More information

Key Project Elements Status Report

Key Project Elements Status Report Los Angeles County Metropolitan Transportation Authority Key Project Elements Status Report presented to the Corridor Advisory Committee August 18, 2016 Background Motion 22.1 elements are grouped into

More information

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC

Rocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013

Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013 Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013 2013, All Rights Reserved. 1 The Maricopa Association of Governments (MAG) is the designated metropolitan planning organization

More information

Development of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation

Development of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation Development of 220 mph High Speed Rail Service for Illinois Mark C. Walbrun, PE TranSystems Corporation 1 Study Purpose Worldwide Use of High Speed Rail Technology Japan, France, Italy, Germany, Spain,

More information

REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS. A Case Study of the Alameda Corridor

REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS. A Case Study of the Alameda Corridor REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS A Case Study of the Alameda Corridor April 29, 25 Dr. Margaret Lobnitz, Weston Solutions, Inc. 1 BACKGROUND In mid-198 s, growing concern

More information

Sepulveda Pass Corridor Systems Planning Study Final Compendium Report. Connecting the San Fernando Valley and the Westside

Sepulveda Pass Corridor Systems Planning Study Final Compendium Report. Connecting the San Fernando Valley and the Westside Los Angeles County Metropolitan Transportation Authority November 2012 Connecting the San Fernando Valley and the Westside Interstate 405 Sepulveda Pass THIS PAGE INTENTIONALLY LEFT BLANK Sepulveda Pass

More information

CALIFORNIA HIGH SPEED TRAIN PROJECT, A CASE STUDY: THE TECHNICAL CHALLENGES IN LOCATING INTERMEDIATE HIGH SPEED RAIL STATIONS

CALIFORNIA HIGH SPEED TRAIN PROJECT, A CASE STUDY: THE TECHNICAL CHALLENGES IN LOCATING INTERMEDIATE HIGH SPEED RAIL STATIONS CALIFORNIA HIGH SPEED TRAIN PROJECT, A CASE STUDY: THE TECHNICAL CHALLENGES IN LOCATING INTERMEDIATE HIGH SPEED RAIL STATIONS James Langham Genaro Mejia, PE Arup 12777 Jefferson Blvd, Los Angeles, CA 90066;

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

CONNECTING AND TRANSFORMING CALIFORNIA

CONNECTING AND TRANSFORMING CALIFORNIA CONNECTING AND TRANSFORMING CALIFORNIA High-Speed Rail Local Policy Maker Group (LPMG) San Carlos, CA January 28, 2016 INTRODUCTIONS 1 STATEWIDE OVERVIEW CONNECTING CALIFORNIA Phase I:» 520 Miles» San

More information

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015 Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In

More information

Goods Movement Plans. Summary of Needs Assessments. January 21, 2015 GOODS MOVEMENT COLLABORATIVE AND GOODS MOVEMENT PLAN 6

Goods Movement Plans. Summary of Needs Assessments. January 21, 2015 GOODS MOVEMENT COLLABORATIVE AND GOODS MOVEMENT PLAN 6 Goods Movement Plans Summary of Needs Assessments January 21, 2015 GOODS MOVEMENT COLLABORATIVE AND GOODS MOVEMENT PLAN 6 Goods Movement Vision and Goals GOODS MOVEMENT COLLABORATIVE AND GOODS MOVEMENT

More information

Electric Multiple Unit Procurement Update

Electric Multiple Unit Procurement Update Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

REGIONAL RAIL RIGHT OF WAY ACTION PLAN TECHNICAL MEMORANDUM #1 RIGHT OF WAY INVENTORY

REGIONAL RAIL RIGHT OF WAY ACTION PLAN TECHNICAL MEMORANDUM #1 RIGHT OF WAY INVENTORY REGIONAL RAIL RIGHT OF WAY ACTION PLAN TECHNICAL MEMORANDUM #1 RIGHT OF WAY INVENTORY This memorandum provides an update to the description of corridor planning contained in the 2007 MTC Regional Rail

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

Chicago Milwaukee Intercity Passenger Rail Corridor

Chicago Milwaukee Intercity Passenger Rail Corridor Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

Public Advisory Committee Meeting #3. February 11, 2014

Public Advisory Committee Meeting #3. February 11, 2014 Public Advisory Committee Meeting #3 February 11, 2014 Agenda 1. Welcome & Meeting Purpose (5 minutes) a. Where we are in the process b. Purpose of today s meeting 2. Update from P&N Working Group (10

More information

Validation Study. Proposed Railroad Grade Separation Algonquin Road at the Union Pacific Milwaukee Railroad. May 15, 2008.

Validation Study. Proposed Railroad Grade Separation Algonquin Road at the Union Pacific Milwaukee Railroad. May 15, 2008. Validation Study Proposed Railroad Grade Separation Algonquin Road at the Union Pacific Milwaukee Railroad May 15, 2008 Prepared for: City of Des Plaines Des Plaines Civic Center 1420 Miner Street Des

More information