ACKNOWLEDGMENTS PROJECT STAFFING

Size: px
Start display at page:

Download "ACKNOWLEDGMENTS PROJECT STAFFING"

Transcription

1

2 ACKNOWLEDGMENTS This report was authorized by the Coachella Valley Association of Governments and prepared by Schiermeyer Consulting Services with assistance from Transportation Planning Services. Members of the Inter-City Rail Services Feasibility Study Project Development Team include: City of Indio, City of La Quinta, City of Palm Desert, City of Palm Springs, and SunLine Transit Agency. Further assistance was provided by the National Passenger Railroad Corporation (Amtrak). PROJECT STAFFING Allyn Waggle, Coachella Valley Association of Governments Carl Schiermeyer, Schiermeyer Consulting Services Elaine Kuhnke, Transportation Planning Services Laura Ayala, Graphics Ashley Hayward, Graphics

3 Table of Contents Chapter Page Executive Summary... i 1. Background and Study Approach A. Introduction...1 B. Goal and Approach of Current Study Evaluation of Service Options C. Service Description...5 D. Service Options...9 E. Evaluation of Service Characteristics...11 F. Recommended Service Option Evaluation of Projected Operating Costs and Revenues G. Train Operating Costs by Option...15 H. Discussion of Amtrak Operating Costs and Revenues Projected Capital Costs I. Capital Improvements and Rolling Stock Costs...20 J. Discussion of Rolling Stock Purchase Options Projected Service Operating Costs K. Summary of Service Operating Costs Proposed Funding Plan L. Capital and Operating Costs...30 M. Potential Local Funding Sources Study Findings and Recommendations N. Summary of Study Findings...33 O. Key Study Recommendations...35

4 List of Figures Figure Page 1 - Rail Route to Coachella Valley Coachella Valley Station Map...8 List of Tables Table Page 1 - Miles Between Stations Preliminary Train Schedules: Options A, B, & C Train Operating Costs and Revenues by Option Railroad Facility and Station Capital Costs Summary of Rolling Stock Costs Summary of Capital Costs Service Operating Costs and Revenue Projections ($11 One-way Fare) Service Operating Costs and Revenue Projections ($18 One-Way Fare) Proposed Net Operating Funding Scenario (CA Car Purchase) Proposed Net Operating Funding Scenario (Amtrak Horizon Lease)...31 List of Appendices Appendix Number Amtrak Correspondence and Detailed Operating Costs...1 Detailed Indio Layover or Turnaround Facility Requirements...2

5 EXECUTIVE SUMMARY Background of the Corridor The Los Angeles Coachella Valley Intercity Rail Corridor has been the subject of intense interest during the past decade. In 1991, the Riverside County Transportation Commission (RCTC) undertook its first of two studies when it evaluated the feasibility of operating three daily roundtrip State-sponsored trains in the Corridor. The results of this effort led to a Caltrans Division of Rail license plate survey of travel patterns and behavior in the Corridor, which in turn led to a series of debates over projected ridership and revenues. In 1993, while awaiting the results of Caltrans ridership projections, the RCTC completed its second study. This study analyzed the option of implementing service as an extension of regular Metrolink commuter rail service on weekends only for a two-year demonstration period. Unfortunately, this concept also foundered due to an inability to reach agreement with the host railroad. Now, five years later, local Coachella Valley governmental agencies are still desirous of implementing service. And, as part of their effort to refocus attention towards the Corridor, the Coachella Valley Association of Governments (CVAG) commissioned this follow-up study. While many of its service attributes are similar to the original study, the single greatest difference distinguishing this study from its predecessors is the proposed Local/State funding plan recommended for the start-up years of service. Proposed Service Description As proposed, two daily roundtrip trains would operate from Los Angeles to the Coachella Valley using the Burlington Northern Santa Fe alignment between Los Angeles and Colton; trains would then turn eastward and continue to the Coachella Valley following the Union Pacific Railroad. Station stops would include Los Angeles Union Station, Fullerton Transportation Center, Riverside Downtown, Palm Springs, and the former Amtrak Indio station. It is also proposed that a third station be located between Palm Springs and Indio in the vicinity of Palm Desert. Service would be operated by Amtrak as a three-year demonstration. Schiermeyer Consulting Services P. i

6 Projected Railroad and Station Costs A total of $9.3 million is required to construct the proposed track and facility improvements. This includes $1.3 million for the construction of layover facilities near the Indio terminus station, $5 million for unspecified host railroad track and signal improvements, and $3 million for the proposed third Coachella Valley station in the vicinity of Palm Desert. Projected Rolling Stock Costs In addition to the track and facility improvements described above, rolling stock will either need to be purchased or leased. Based on the findings of this analysis, it is recommended that two additional California Car trainsets be purchased as part of Amtrak s existing purchase option which expires on December 31, The total price for purchasing two additional 5-car trainsets and two F-59 locomotives is $28.6 million. Should a determination be made that equipment should be leased rather than purchased, the annual amount to lease two sets of Amtrak Horizon equipment is $1.46 million. Projected Net Operating Costs The estimated net annual cost for operating service ranges from $5.9 to $4.4 million depending on whether the rolling stock is purchased or leased. If the preferred option of purchasing new California Car equipment is ultimately selected, the annual net operating cost is significantly lower - $4.4 million. While selecting the lease option defers the large up-front capital expenditure, it also raises operating costs on an indefinite basis. Under both scenarios, however, it is firmly believed that these amounts represent worst case projections. As discussed in the full report, the estimated revenues and projections are based on the original Caltrans license plate survey which were the subject of intense debate and considered to be extremely conservative. Therefore, it is highly probable that actual net annual operating costs would be significantly less. Proposed Funding Plan Capital Improvements and Rolling Stock A total of $37.9 million in capital funding is required to implement the proposed service. Under the proposed funding plan, $34.9 million would be fully financed by the State of California. The additional $3 million would be funded by local resources for the construction of the proposed third Coachella Valley station in the Palm Desert vicinity. Schiermeyer Consulting Services P. ii

7 Should it be determined that the host railroad infrastructure improvements are not required, total State funding would be reduced to $29.9 million. Proposed Funding Plan Net Operating Costs In recognition of the strong interest in this service, it is proposed that local agencies contribute 25% of the anticipated net operating loss throughout the three-year demonstration period. At the conclusion of this time, should the service approximate the same performance standards of similar services during their start-up years, the State would assume complete funding responsibility. Assuming the selection of the preferred California Car purchase option, this amounts to $1.1 million annually and $3.3 million over the three-year period. Likewise, the State would be responsible for funding the remaining $3.3 million annually or $9.9 million over the three-year period. Should the lease option be pursued, local participation levels would increase to $4.4 million and State levels to $13.3 million. Key Study Findings The initiation of intercity passenger rail service in the Los Angeles Coachella Valley corridor is technically feasible and highly desired by local Coachella Valley entities. Additional key findings are listed below. Local Agency Interest 1. Local Coachella Valley governmental agencies have given the proposed service a high priority and have expressed interest in becoming a funding partner with the State of California to initiate service in the Corridor. Host Railroads in the Corridor 2. The Union Pacific Railroad has indicated strong opposition towards the operation of passenger rail service along its alignment in previous years and continues to be opposed at the time of this study. No opposition is anticipated from Burlington Northern Sante Fe. Schiermeyer Consulting Services P. iii

8 Alternative Service Options 3. While three different single roundtrip options were reviewed as part of this study, it was the opinion of Amtrak that these options failed to offer the level of flexibility required by the general public. A minimum of two roundtrip trains must be available before service should be initiated. Station Assessment 4. The Palm Springs station is a modern intercity rail station with an enclosed building, restrooms, and parking. The City of Indio has received a $1.5 million grant from the State to construct its new station and will match this amount with local resources. A third Coachella Valley station to be constructed in the vicinity of Palm Desert would provide optimal service to the Valley s many resorts and facilities. 5. Due to the fluctuating climate conditions of the Coachella Valley, as well as its appeal as a vacation and tourist resort, all stations should be constructed with climatecontrolled, enclosed passenger facilities and strive to provide the same ground transportation services and facilities typically found at any airport. Key Study Recommendations Based on the above study findings, it is recommended that the Coachella Valley Association of Governments (CVAG), and its elected officials, take the necessary steps to seek agreement with the State of California to implement a jointly funded, three-year demonstration of intercity passenger rail service in the Los Angeles Coachella Valley Corridor. 1. The recommended service scenario includes the operation of two daily roundtrip trains between Los Angeles and the Coachella Valley along the BNSF/UP alignments. 2. The State of California should ensure the availability of rolling stock by purchasing two additional California Car trainsets as part of the existing Amtrak California Car purchase contract or assist in the lease of Amtrak Horizon cars. Schiermeyer Consulting Services P. iv

9 3. Coachella Valley governmental entities should enter into a partnership agreement with the State of California to share in the annual net operating costs during the threeyear demonstration period. 4. Caltrans Division of Rail, along with Amtrak officials, should pursue further discussions with Union Pacific for the use of its right-of-way. 5. Funding to construct a third Coachella Valley station in the vicinity of Palm Desert should be actively pursued, although service could technically begin operating in advance of its opening. 6. Plans to provide adequate passenger waiting facilities and appropriate connecting shuttle services at all Coachella Valley stations should be developed. Schiermeyer Consulting Services P. v

10 A. Introduction The operation of intercity rail service between the Coachella Valley and Los Angeles and Orange Counties has been a long-term goal of both the Coachella Valley Association of Governments (CVAG) and the Riverside County Transportation Commission (RCTC). During the early 1990 s, when the RCTC was planning and beginning the operation of its commuter rail program as a member agency of the Southern California Regional Rail Authority (SCRRA), two distinctly different, but comprehensive studies of the corridor were prepared by Schiermeyer Consulting Services (SCS). A brief summary of these studies and their respective outcomes is provided below. Los Angeles-Coachella Valley-Imperial County Intercity Rail Feasibility Study (Dec. 1991) The purpose of this study was to complete a comprehensive assessment of the technical, operational, financial, and institutional issues associated with operating Caltrans Statesponsored/Amtrak intercity rail services in the corridor. Preliminary station sites were identified, and capital and operating budgets were prepared based on a full-service operating scenario of three daily roundtrip trains between Los Angeles and the Coachella Valley. The proposed routing assumed that trains would operate over the Burlington Northern Santa Fe (BNSF) San Bernardino Subdivision via Fullerton from Los Angeles through Riverside to Colton, turn east onto the former Southern Pacific Yuma line (now owned and operated by Union Pacific), and continue to the Coachella Valley. An extension to the international United States/Mexico border was also considered as part of this service concept. The study was approved by CVAG and the RCTC Board and forwarded to Caltrans Division of Rail for review and action. While the feasibility study included a patronage forecast for the service based on standardized trip generation rates for intercity rail services, it was determined that additional travel data should be developed in order to better assess the corridor s intercity rail ridership potential. In an effort to obtain this data, Caltrans commissioned a comprehensive license plate survey of the corridor. A license plate survey consists of videotaping all vehicles which pass through a given checkpoint in a corridor, identifying the owner of each vehicle through vehicle registration records, and then mailing surveys to each owner. In this instance, the survey questions focused on trip purpose, origin and destination points (zip codes), and the number of passengers traveling together during that specific trip. The license plate data was then coded into the newly developed (at that time) Caltrans origin-destination travel demand model. While the survey itself was highly successful, the ridership results produced from it were Schiermeyer Consulting Services P. 1

11 significantly lower than previous estimates, creating a less than satisfactory operating deficit and a significant barrier to further programming of the service. Discussions regarding the differences between the two forecasts were inconclusive, but in summary, it suffices to say that the most significant variable separating the two forecasts focused on the projected number of regional through-trips versus subregional or local trips. Los Angeles-Coachella Valley Weekend Demonstration Passenger Rail Service (Nov. 1993) In an effort to jumpstart operations in the corridor and piggyback on existing Metrolink commuter rail services within Riverside County while the previous study was under review by Caltrans Division of Rail, the RCTC developed an alternative service concept. This concept differed from the previous study in that the proposed service would operate as a demonstration for a two year period on weekends only as an extension of regular Metrolink commuter rail services. Under this scenario, service would be operated by contracted Metrolink crews, using Metrolink equipment during the peak visitor season of November through May. According to the Nov study, the primary purpose of the demonstration would be to test the market and demonstrate that ridership levels would be sufficient to maintain State minimum farebox requirements. A total of ten one-way trips were proposed with one outbound Friday afternoon trip, two Saturday roundtrips, two Sunday roundtrips, and one Monday morning return trip. A fare structure which dovetailed with Metrolink s zone system and corresponded with Amtrak fares for similar distances was developed, as well as a thorough examination of several ticketing and cash collection options. An analysis of projected ridership was also completed by applying a series of factors to the estimates prepared for the Dec report. Alternate railroad alignments between Los Angeles and Riverside were also considered as part of this analysis, including the Burlington Northern Santa Fe (BNSF) San Bernardino Subdivision described earlier and the Union Pacific Railroad upon which Metrolink currently operates its Riverside Los Angeles via Ontario service. The primary advantage that the UP alignment had over the BNSF (at that time) was that it offered a quick start-up. Since Metrolink was already operating service in the corridor, it seemed that it would be a relatively easy step to simply extend the trains to the Coachella Valley. It was acknowledged and in fact reflected in the report that should it be determined that timing issues were not the most important issue that preliminary revenue and ridership estimates suggested that the BNSF alignment would be more productive due to its link to Orange County. Schiermeyer Consulting Services P. 2

12 While the concept was given serious consideration by both Metrolink and RCTC staff, implementation of the proposed service was opposed by Union Pacific because of its reluctance to add increased passenger rail service on the Yuma mainline during weekends (a busy time for movement of freight trains). In addition to the railroad opposition, there were some secondary issues associated with keeping the Metrolink equipment overnight in the Coachella Valley, as well as the possible degradation of regular Monday morning commuter schedules should the train be delayed upon its return to Riverside. It is believed, however, that these secondary issues could have been eventually overcome. B. Goal and Approach of Current Study While the goal of this study is similar to the previous two feasibility studies to develop a plan for operating passenger rail services in the Los Angeles Coachella Valley Corridor it is distinguished from its predecessors in at least three ways. First, this study recognizes the need for increased local participation at both the policy and financial levels. To this end, CVAG commissioned this study and created an Inter-City Rail Services Feasibility Study Project Development Team to support its efforts. Elected officials and executive management from the following jurisdictions are members of this initial advisory group: City of Indio, City of La Quinta, City of Palm Desert, City of Palm Springs, and SunLine Transit Through a series of discussions with this group, a total of three service options were reviewed, as well as alternative funding plans which include a local participation element. Secondly, this study recognizes the fact that Amtrak (the National Passenger Railroad Corporation) already has rights to operate in the corridor. As part of its original charter, Amtrak enjoys an absolute right to operate passenger trains virtually anywhere within the United States it wants, subject to schedule and infrastructure negotiations with the host railroad. While Metrolink also has the right to operate over either the BNSF or UP track between Los Angeles and Riverside/Colton, they have no operating rights between Colton and the Coachella Valley. Therefore, since Amtrak already has these rights, it is assumed that the proposed service would be operated by Amtrak and that negotiations with UP could be reached more quickly and with less of a financial penalty. Thirdly, at the time of the previous two studies, the only passenger rail stop located in the Coachella Valley was in Indio for the transcontinental Amtrak route known as the Sunset Limited. Now, a second modern station has been constructed as part of the State Transit Capital Improvement (TCI) funding cycle in the City of Palm Springs. While this station also serves the Sunset Limited during the early morning hours, more importantly it serves as a constant reminder of what could be, but isn t. In addition, however, its presence Schiermeyer Consulting Services P. 3

13 somewhat changes the playing field from earlier years and puts the Coachella Valley one step closer to realizing its long term goal. Finally, it should be pointed out what this study is not. This study is not a market research document; its objective is not to convince the reader how much passenger rail service is needed in the study corridor. In fact, after reading this report, one will not know how many tourists or seasonal residents visit the Coachella Valley on a daily basis, how many live within the catchment area of the corridor route, or what the various trip purposes might be. It assumes that there is a market for the service and uses as its base the most conservative of the three ridership forecasts completed to date, the Caltrans Division of Rail estimate prepared as part of the license plate survey described above. What this document will do, however, is provide the framework for further operational and funding discussions relative to implementing service in the corridor. Its objective is to lay out a recommended service plan which has been developed through coordination with local Coachella Valley agencies, as well as Amtrak, and provide a realistic hands-on assessment of the technical and funding issues associated with implementing service. Schiermeyer Consulting Services P. 4

14 C. Service Description The proposed alignment is similar to that of the Dec Intercity Rail Feasibility Study. Service would begin at Los Angeles Union Station in downtown Los Angeles and follow the BNSF San Bernardino Subdivision through Fullerton and Riverside. In Colton, at the junction of the BNSF and UP railroads, the alignment would turn eastward towards the Coachella Valley following the Union Pacific Railroad (Figure 1). Proposed Station Locations Between Los Angeles and Riverside, the proposed trains would be served by the following existing Amtrak and/or Metrolink stations: Los Angeles Union Station, Fullerton Transportation Center, and Riverside Downtown. Within the Coachella Valley, a total of three stations are envisioned: the existing Palm Springs Amtrak station, a substantially improved Indio terminus located at the former Amtrak station stop, and a totally new mid- Coachella Valley station to be built between Palm Springs and the Indio terminus, in the vicinity of Palm Desert near Monterey Avenue. A third site was also previously recommended in the Dec study in order to better serve its elongated geography. Table 1 provides a mileage chart based on these proposed stations. Table 1 MILES BETWEEN STATIONS Station Area Served Miles Los Angeles Los Angeles County - Fullerton Orange County 26 Riverside- Downtown Inland Empire 36 Subtotal 62 Palm Springs West Coachella Valley 56 Cumulative Subtotal 118 Palm Desert Vicinity Mid-Coachella Valley 11 Indio East Coachella Valley 12 Subtotal 23 TOTAL CORRIDOR DISTANCE 141 Schiermeyer Consulting Services P. 5

15 [INSERT FIGURE 1: RAIL ALIGNMENT] Schiermeyer Consulting Services P. 6

16 Description of Coachella Valley Stations Situated at the head of the Coachella Valley and just south of the intersection of Indian Avenue and Interstate 10, the Palm Springs station is well-positioned to serve passengers with final destinations in West Coachella Valley. From this location, the many resorts and recreational attractions located both within the cities of Palm Springs and Desert Hot Springs (north of I-10) can be easily accessed (Figure 2). The Palm Springs Amtrak station is a modern, intercity rail facility situated on a 13 acre parcel. The facility includes a passenger loading platform, an enclosed 2,161 square foot building with restrooms and a vending area, lighting, landscaping, and parking for 40 automobiles, plus bus/rv parking and loading. Likewise, the former Indio Amtrak stop (located northeast of Jackson Street and Avenue 45) is also well-situated to serve passengers with final destinations in East Coachella Valley. It should be pointed out, however, that while the Indio site is well-positioned to serve east Coachella Valley, it will require significant improvements in order to bring it to modern intercity standards. To this end, the City of Indio has requested and received a State grant of $1.5 million to be matched with $1.5 million in City funds. Currently, the City is moving into the design phase of its station development plans. As previously discussed, a third site has always been recommended in order to adequately serve the resorts and residents of mid-coachella Valley. As shown in Table 1, the distance between the Palm Springs station and Indio terminus is approximately 23 miles. If Palm Springs were the only station stop, passengers with a final destination in mid or east Coachella Valley would be forced to travel quite an additional distance before reaching their final destination. Vice versa, if only the Indio station were used, passengers would have to backtrack significantly. Between these two points, however, are a host of additional resorts located in the cities of Cathedral City, Rancho Mirage, Palm Desert, Thousand Palms, and Indian Wells. Furthermore, because the rail alignment is located as much as five miles north of the urbanized area, actual driving distances to these points are greater than those shown in Table 1. Therefore, in an effort to provide the most attractive intercity rail services possible to as many major resorts and desert communities as feasible, three stations continue to be recommended in this report. Alternative Service Scenario Nonetheless, should it not be possible to initiate service with three fully-operational stations, the location of the Palm Springs station would make it technically feasible to start service with only a single station. While such a service scenario is not optimum, nor is it Schiermeyer Consulting Services P. 7

17 [INSERT FIGURE 2: MAP OF COACHELLA VALLEY STATIONS] Schiermeyer Consulting Services P. 8

18 recommended, the location of the Palm Springs station at the far west end of the Valley would make such a scenario feasible. On the other hand, were, the only operational station located at the east end of the Valley in Indio, a single station scenario would not be practical as the majority of passengers would have to backtrack to reach their final destination. In addition, the Palm Springs station enjoys the added benefit of immediate access to I-10, which would make the prospect of operating continuing, connecting service more efficient and practical although still not as desirable as the recommended three-station scenario. D. Service Options In developing the alternative service scenarios to be further reviewed as part of this study, the key objective of the Project Development Team (PDT) was to develop a service option which would provide potential passengers with an attractive alternative for traveling to the Coachella Valley. Therefore, while it is acknowledged that operation of the service would ultimately have the added value of increased passenger rail service to various other destinations located along the corridor, its primary orientation would be to bring visitors and seasonal/part-time residents to the Coachella Valley. To this end, the PDT explored several preliminary service concepts and schedules. Based on discussions among the team members, however, a total of three service options were recommended for further review. These three options are described below. Option A Daily Service with Equipment Layover Facility As the name implies, this option assumes the operation of a single, daily roundtrip train within the corridor. As envisioned, the train would depart Los Angeles Union Station each afternoon around 3:45 pm, remain overnight in the Coachella Valley, and depart the Indio/East Coachella Valley station each morning around 7:30 am. This option of course requires the construction of a secured, layover facility near the Indio terminus. A preliminary schedule showing intermediate stops is shown in Table 2. Option B Weekend Service with Equipment Layover Facility Option B assumes that trains would operate on weekends throughout the entire year. Under this scenario, a train would depart Los Angeles Union Station around 3:45 pm each Friday, Saturday, and Sunday. As in Option A, these trains would layover in the Coachella Valley overnight and depart the Indio terminus at approximately 7:30 am each Saturday, Sunday, Schiermeyer Consulting Services P. 9

19 and Monday. Again, the equipment would be stored at a secured facility near the Indio terminus. Options A & B:* (with layover facility) Table 2 PRELIMINARY TRAIN SCHEDULES: OPTIONS A, B, & C Station To Coachella Valley (read down): Option C:** (no layover facility) 3:45 pm Los Angeles 2:00 pm 4:25 pm Fullerton 2:40 pm 5:15 pm Riverside 3:30 pm 6:35 pm Palm Springs 4:50 pm 6:47 pm Palm Desert (Mid-Coachella Valley) 5:02 pm 7:00 pm Indio (East Coachella Valley) 5:15 pm To Los Angeles (read down): 7:30 am Indio (East Coachella Valley) 6:30 pm 7:42 am Palm Desert (Mid-Coachella Valley) 6: 42 pm 7:55 am Palm Springs 6:55 pm 9:10 am Riverside 8:15 pm 10:05 am Fullerton 9:05 pm 10:45 am Los Angeles 9:45 pm * Option A: Daily Service Schedules Option B: Departures from Los Angeles on Friday, Saturday, and Sunday afternoons Departures from Indio on Saturday, Sunday, and Monday mornings ** Option C: Departures from Los Angeles on Friday, Saturday, and Sunday early afternoons Departures from Indio on Friday, Saturday, and Sunday evenings Option C Weekend Service with No Equipment Layover Facility Option C would also operate each weekend throughout the year. However, instead of laying over in the Coachella Valley each evening, the trains would return to Los Angeles that same day. Under this scenario, a train would depart Los Angeles around 2:00 pm each Friday, Saturday, and Sunday and return from Indio/East Coachella Valley at 6:30 pm of each corresponding day. No equipment layover facility is required for this option. Schiermeyer Consulting Services P. 10

20 E. Evaluation of Service Characteristics Because each option provides distinctively different benefits, it is helpful to list their respective service characteristics before further analysis is undertaken. Option A: 1. Provides service every day of the week, with a mid-afternoon departure from Los Angeles and an early morning return any given day 2. Requires potential passengers traveling to the Coachella Valley to spend the night 3. Same-day roundtrips to/from the Coachella Valley are not possible 4. Same-day roundtrips to destinations in the westbound direction are possible 5. Provides for weekday or weekend travel within the Corridor 6. Requires the construction of a layover facility Option B: 1. Provides weekend service only with a mid-afternoon Friday departure from Los Angeles, and early morning returns on Saturday, Sunday, and Monday morning 2. Designed specifically for weekend/weekly visits to the Coachella Valley, but requires passengers to depart early Sunday or Monday mornings 3. Same-day roundtrips to/from the Coachella Valley are not possible 4. Same-day roundtrips to destinations in the westbound direction are possible 5. Requires the construction of a layover facility Option C: 1. Provides weekend service only an early-afternoon Friday departure from Los Angeles, with evening returns on Friday, Saturday, and Sunday 2. Designed specifically for weekends/weekly visits to the Coachella Valley, but allows passengers to depart on Saturday or Sunday evenings 3. Same-day roundtrips to/from the Coachella Valley are not possible 4. Same-day roundtrips to destinations in the westbound direction are not possible 5. Does not require the construction of a layover facility Schiermeyer Consulting Services P. 11

21 Discussion of Alternatives As the PDT considered these service characteristics, it became apparent that each option had its own specific benefits and constraints. Option A: Although this Option would provide daily service to and from the Coachella Valley at reasonable times, further analysis finds that it misses two important intercity corridor market segments. First, it does not allow for same-day roundtrip travel to and from the Coachella Valley potential passengers must stay overnight. Second, it offers only early morning departures out of the Coachella Valley. While an evaluation of this situation from a tourism perspective might initially find such conditions to be economically favorable, in reality, such a schedule is very confining and will likely limit the overall market potential of the service. Additionally, given the typical trip purpose of most visitors to the Coachella Valley (leisure, recreational), it is questionable if such early departure times will prove attractive. Certainly, it would seem reasonable to assume that weekend visitors will be less than enthusiastic as they would be forced to either cut their trip short and depart early Sunday morning or extend their weekend to Monday morning and be late to work. On the other hand, the proposed schedule does offer some attractive options for travel in the westbound direction. As shown with the proposed schedule, almost a full day could be spent in Riverside or Fullerton any day of the week, as well as a much shorter day in Los Angeles. While it is unknown how big the market is for same-day roundtrip service in either direction, this additional pool of potential passengers is an important factor in considering the route s overall revenue potential. Apart from these considerations and probably of greatest significance, however, is the fact that Amtrak considers the operation of one roundtrip in any given corridor to be insufficient. On several occasions throughout the course of this study, Amtrak staff emphasized their position that one roundtrip fails to offer the flexibility or attractiveness required to successfully stimulate the market potential of an intercity rail corridor. While it might be thought that a single roundtrip provides a starting point from which service could grow and expand, experience has found that it will fail before it is given this opportunity. Passengers expect a specific level of scheduling flexibility, even during the introduction of a new service, before considering it a viable transportation option. One roundtrip fails to meet this requirement and therefore provides little justification for further development of this Option. Schiermeyer Consulting Services P. 12

22 Option B: This Option has many of the same problems associated with Option A the need to construct a layover facility for what is essentially a single, daily one-way trip, with the added constraint of operating on weekends only. Based on the above discussion, therefore, it would initially appear that this Option would be even less attractive. However, in some ways, because of the weekend service schedule, the total impact of these constraints is less severe. Option B is designed to serve a specific market segment: the weekend Coachella Valley visitor or part-time/seasonal resident, as well as visitors who can stay a week at a time. Because of this specific market definition, the need or expectation for same-day roundtrip service or additional scheduling flexibility is greatly reduced. Since the schedules are designed to serve a specific market, it would seem reasonable to assume that as long as the service meets the travel needs of this market, the overall impact of operating only a single roundtrip train would be less severe than that described for Option A. In consideration of these points, Option B offers a fairly acceptable weekend schedule pattern. Option B also provides for same-day, roundtrip travel in the westbound direction on Saturdays and Sundays, as well as a Saturday overnight. As with Option A, however, it requires passengers to either depart the Coachella Valley early Sunday morning or extend their weekend visit to early Monday morning. Again, for reasons cited earlier, these schedules and service characteristics may prove problematic. Option C: The strength of Option C is that it can be fully operated without the need to construct any layover facilities in the Coachella Valley. It also appears to come closest to meeting the travel needs of Coachella Valley weekend visitors. Based on the proposed schedule in Table 2, it would be possible to spend Friday or Saturday evenings in the Coachella Valley, as well as both, and still return the following evening. The proposed schedule also eliminates the problems associated with the early Sunday or Monday morning departures, by providing a convenient 6:30 pm Sunday evening departure. While weekend travel in the westbound direction is also possible, the train does not arrive in Fullerton till 9:05 pm or in Los Angeles till 9:45 pm somewhat late for an optimal weekend visit in Los Angeles, although not so late as to be considered totally unattractive. Unfortunately, because the train does not remain overnight in the Coachella Valley, sameday, roundtrip travel in either direction is eliminated in this Option. Schiermeyer Consulting Services P. 13

23 F. Recommended Service Option Upon further discussion of each of the proposed options and their projected operating costs (presented in the following chapter), the PDT determined that each of the alternatives had significant constraints or deficiencies. Nonetheless, the most significant constraint associated with each of the options a single roundtrip train - proved to be unacceptable. Therefore, after careful consideration and at the recommendation of Amtrak, the PDT decided to recommend a new alternative, Option D. As envisioned, Option D assumes the operation of two daily roundtrip trains with an overnight layover at both ends. By operating two roundtrip trains, many of the deficiencies described above would be reduced and passengers would be given more of the flexibility required to make the service attractive. While this recommendation will require greater resources from a capital and operating perspective, it was agreed that the single roundtrip service scenario underlying each of the preliminary options would ultimately fail to meet not only the needs of the Coachella Valley, but the Corridor as a whole. Schiermeyer Consulting Services P. 14

24 G. Train Operating Costs by Option As part of the review process associated with evaluating each of the proposed service options, CVAG contacted Amtrak and requested their assistance in preparing a cost estimate for each option. In addition to the requested cost estimates, Amtrak graciously agreed to provide projected revenues based on their judgement of patronage and net operating costs. A copy of their correspondence, as well as their preliminary detailed estimates, is included in Appendix 1. These estimates are summarized below for discussion purposes. Table 3 TRAIN OPERATING COSTS AND REVENUES BY OPTION Option A (one daily roundtrip with layover) Option B (one roundtrip on weekends with layover) Option C (one roundtrip on weekends with no layover) Option D* (two daily roundtrips with layover) Annual Revenue** $ 471,859 $ 259,523 $ 235,930 $ 943,718 Annual Train $ 2,599,387 $ 1,461,609 $1,064,322 $ 5,198,774 Operating Cost Annual Train $ (2,127,527) $ (1,202,087) $ (828,392) $ (4,255,056) Operating Loss Annual Passengers 38,677 21,272 19,339 77,354 Annual Passenger 2,890,265 1,589,646 1,445,132 5,780,530 Miles Farebox Recovery Ratio (revenue/costs) 18.15% 17.76% 22.16% 18.15% * Revenue, costs, and passengers assumed to be twice that of Option A ** Includes food and beverages revenues Schiermeyer Consulting Services P. 15

25 In reviewing Table 3, it should be noted that the projected train operating costs and revenues for Options A and D assume one daily roundtrip and two daily roundtrips respectively. Options B and C assume the operation of service on weekends only. The projected annual revenues are based on average revenues of $11.00 per passenger. Train operating costs include all Amtrak costs associated with crews, fuel, servicing and maintaining train, railroad payments, support and reservation functions, insurance, and general administration. They do not include additional costs associated with maintaining the Indio layover facility or leasing rolling stock. For a discussion of these expenses, please see Chapter 5. In reviewing the detailed Amtrak costs included in Appendix 1, it should be pointed out that food and beverage service is a potential line item cost which could be eliminated in order to reduce overall operating losses. According to Option A, food and beverage services are anticipated to generate an annual amount of $46,412. The cost of providing this on-board service is $181,856 ($149,831 for on-board service labor and $32,025 for on-board supplies), yielding a net loss of $135,444. Eliminating this service would reduce overall costs and produce the above estimated cost savings. However, food and beverage service is an amenity which intercity rail passengers have come to expect and appreciate. Therefore, given the relatively small cost of providing this service in comparison to the total operating budget, it is not recommended that it be eliminated. H. Discussion of Amtrak Operating Costs and Revenues As would be expected, the train operating costs associated with providing daily service are much greater than weekend service options due to the greater number of operating days. Between the two weekend options, however, Option C has a slightly lower operating cost. When a review of these cost estimates was completed, it was found that single largest cost difference related to train and engine crew expenses. Train and engine crew costs for Option B (with layover) are $312,481, while the costs for Option C are $152,897. Equipment maintenance costs are also significantly lower for Option C, $228,805 versus $305,073 for Option B. Since Option D was not one of the service scenarios discussed with Amtrak, a detailed cost estimate was not prepared for this option. However, based on follow-on conversations with Amtrak staff, it was agreed that a preliminary cost estimate could be developed by simply doubling the projected costs and revenues of Option A. While it is likely that the operation of two roundtrips would provide the opportunity for some economies and cost savings, it was agreed that the difference would not be significant and that doubling the figures would provide a conservative approach for preliminary cost comparisons. Schiermeyer Consulting Services P. 16

26 While this methodology is acceptable for this preliminary analysis and was agreed upon, there are some additional considerations relative to projected revenues which must not be forgotten as part of the financial review of Option D. First of all, the operation of Option D will provide significantly more travel options to potential passengers, specifically same-day, roundtrip travel in either direction of the corridor each day of the week throughout the year. Because of these additional travel options, a strong case can be made that the projected number of passengers, passenger miles, and revenues shown in Table 3 will more than double. Should this occur, resulting annual operating losses will be reduced and farebox recovery ratios will increase accordingly. Further discussion on these points is provided below. Projected Passengers The estimates developed by Amtrak and presented in Table 3 were based on adjustments to the earlier Caltrans Division of Rail license plate survey projections. As discussed in Chapter 1, the Caltrans Division of Rail estimates were much lower than original projections developed for the Dec study and were the subject of much controversy. However, since a detailed patronage assessment was outside the scope and purpose of this study, Amtrak had little choice upon which to base its projections. Nonetheless, this approach is a two-edged sword. While on the one hand, the use of conservative estimates allows for a worst case review of projected operating losses and farebox recovery rates, it can also jeopardize otherwise worthy projects by allowing them to be incorrectly characterized as financially unsound. This is especially true in this case where there are ample indicators supporting the use of higher revenue projections. Therefore, caution is strongly advised while considering all of the assumptions used in the Amtrak detailed cost estimates as further discussed below. Projected Passenger Miles The projected average trip length as calculated by Amtrak is miles per passenger. Since the total corridor distance between Los Angeles and the Indio terminus is approximately 141 miles, this assumption implies that the average trip length will be only slightly greater than half the corridor distance. While the calculations which allowed Amtrak to reach this trip length may be methodologically correct, it seems too short when compared to the actual distances between stations. According to Table 1, the distance from Riverside to Palm Springs is 56 rail miles. However, because these two points are geographically relatively close to one another and are Schiermeyer Consulting Services P. 17

27 within easy driving distance, it would seem reasonable to assume that the majority of intercity rail trips would be to and from locations west of Riverside, namely Fullerton or Los Angeles. The rail distance from Fullerton to the mid-coachella Valley station at Palm Desert is 103 miles; the rail distance from Los Angeles to the mid-coachella Valley station is 129 miles. Based on these actual distances, it would therefore appear reasonable to assume that the average trip length would be closer to 100 miles rather than the 75 miles assumed by Amtrak. By using the shorter trip length, Amtrak appears to be placing greater weight on the Riverside Coachella Valley trip segment which is not anticipated to be the primary station pair of this corridor. And again, while use of the shorter trip length provides a worst case scenario, the question as to whether the analysis is too conservative cannot be overlooked. Using a longer trip length would result in increased revenues and reduced operating losses. For example, Amtrak s typical revenue per mile on the San Diegan Line is $.18 per mile (based on a $23 one-way fare and a total corridor length of 128 miles). The proposed fare shown for the L.A. Coachella Valley Corridor is $11.00 one-way or $.15 per mile. If the 100 mile average trip length were assumed as described above, as well as the Amtrak San Diegan per mile rate of $.18, the average revenue per passenger would increase to $ Projected Farebox Recovery Rates According to Table 3, the projected farebox recovery ratios range from 18%-22% (projected revenues divided by train operating costs) assuming the $11.00 one-way fare and distance projected by Amtrak. This range is well within the limits of acceptability for the start-up years of a new service. In fact, these rates are comparable to those achieved in the early days of the Oakland-Bakersfield- San Joaquin rail service when it was operated with a single trip. Nonetheless, if the above referenced distance was increased to 100 miles with an $18 average one-way fare, the estimated amounts would increase as indicated below. Revenue* Farebox Option D (with average revenue/passenger of $11): $ 943, % Option D (with average revenue/passenger of $18): $ 1,545, % * Includes food & beverage revenue calculated at 11% of transportation revenue Clearly, these calculations demonstrate the significant impact that these seemingly insignificant underlying assumptions can have on projected revenues and farebox recovery rates. And, since it is believed that the greatest number of riders will originate or terminate Schiermeyer Consulting Services P. 18

28 in either Los Angeles or Fullerton, use of the longer trip length is well justified, as is the increased fare based on existing Amtrak San Diegan Line practices. Schiermeyer Consulting Services P. 19

29 I. Capital Improvements and Rolling Stock Costs The capital elements required to implement the proposed service include three different cost categories as listed and described below: a) Layover facilities and host railroad track improvements, b) Station improvements, c) Rolling stock purchase or lease costs. a) Layover Facilities and Host Railroad Track Improvements As shown in Table 4, the estimated cost to construct the Indio Layover Facility is $968,000. While no specific location for this facility has been identified at this time, it would be situated as close to the Indio terminus as possible. In summary, a typical layover facility includes installation of the following items: service track, fencing, tanks for storage of nonpotable water, lighting, and drip pans. For a more detailed line item budget, see Appendix 2. It is assumed that the layover facility will require an approximate 40 ft. by 1,000 ft strip of land. Since this can be totally accommodated in the railroad right-of-way, no land acquisition costs are included in the capital budget. However, an additional $300,000 is Table 4 RAILROAD FACILITY AND STATION CAPITAL COSTS Amount Indio Layover Facilities $ 968,000 Powered Switch for Maintenance Tracks $ 300,000 Host RR Track & Signal Improvements* $ 5,000,000 Subtotal $ 6,268,000 Station Construction $ 3,000,000 Subtotal $ 3,000,000 TOTAL CAPITAL COSTS $ 9,268,000 * May not be required by Union Pacific for only four daily train movements Schiermeyer Consulting Services P. 20

30 shown for the installation of a powered switch which will allow the trains to automatically enter and exit the maintenance tracks. In addition, the facility will require some ongoing maintenance services. Typical services usually include water, electric, and trash collection. In sum these costs are estimated to total $191,900 annually. A total of $5 million has also been budgeted for unspecified track and signal improvements required by the host railroad to improve the overall railroad plant between Colton and Indio. While Union Pacific has not in any sense indicated approval for the proposed service, in fact they have frequently stated their opposition, a placeholder amount has been included in the budget in the event that UP requires a contribution to improve overall capacity. Although it would seem reasonable to assume that the proposed four train movements would not place an excessive burden on UP s capacity requirements, in order to be prudent, $5 million as been set aside for possible signal and track improvements On the positive side, previous studies always identified another capital expense known as an interconnect track at Colton Crossing. This track was needed in order for the train to transition from the BNSF railroad to the UP railroad at Colton Crossing. This was a costly expenditure, requiring construction of new track, power switches, and signalization. Fortunately, as part of their own track plant improvements, Union Pacific has already made this improvement and therefore it is no longer included as part of the capital budget for this service. Station Improvements and Services Table 4 includes a total of $3 million for station improvements at the proposed Palm Desert station in mid-coachella Valley. While a detailed station cost estimate was not prepared for this preliminary report, this amount has been budgeted based upon recent experience in constructing other stations. In terms of required parcel size, it is assumed that the proposed station would require a 4-5 acre parcel in order to accommodate approximately 300 parking spaces and the required bus turnaround/staging facilities. A summary of typical station costs is provided below for reference purposes only. Item Unit Cost Amount Platforms $ 500,000 each $ 500,000 Parking $ 1,500 per 300 spaces $ 450,000 Climate-Controlled Building $ 125/sq 4,500 sq ft $ 562,500 Subtotal $ 1,512,500 Schiermeyer Consulting Services P. 21

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING ENVIRONMENTAL SETTING The following analysis summarizes the findings and conclusions of the Traffic Analysis (Traffic Study), prepared by The Mobility Group,

More information

Bedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015

Bedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015 Bedford/Franklin Regional Rail Initiative (BFRRI) Rationale for a Bedford Amtrak Station June 30, 2015 SUBJECT: Bedford Amtrak Station Why an Amtrak station in Bedford makes sense. I. BACKGROUND: In January

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: COMMUNITY BUS SERVICES ACTION ITEM RECOMMENDATION It is recommended that the Board not approve any routing

More information

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project

More information

U.S. System Summary: ARIZONA/SOUTHWEST

U.S. System Summary: ARIZONA/SOUTHWEST U.S. System Summary: ARIZONA/SOUTHWEST Arizona/Southwest High-Speed Rail System (Source: Texas A&M Transportation Institute) The Arizona/Southwest high-speed rail system described in this summary groups

More information

Roma McKenzie-Campbell Amtrak, Project Manager. Caroline Ducas VHB, Senior Transit Planner. Boston, Massachusetts

Roma McKenzie-Campbell Amtrak, Project Manager. Caroline Ducas VHB, Senior Transit Planner. Boston, Massachusetts DMU Implementation on Existing Commuter Rail Corridors: Opportunities, Challenges and Lessons Learned Roma McKenzie-Campbell Amtrak, Project Manager Caroline Ducas VHB, Senior Transit Planner Boston, Massachusetts

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Ohio Passenger Rail Development. Northwest Ohio Passenger Rail Association

Ohio Passenger Rail Development. Northwest Ohio Passenger Rail Association Ohio Passenger Rail Development Northwest Ohio Passenger Rail Association Ohio Rail Development Commission June 11, 2010 Ohio Strategy Establish the Market Grow the Market Capture the Value of the Market

More information

Abstract. Executive Summary. Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County

Abstract. Executive Summary. Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County Abstract The purpose of this investigation is to model the demand for an ataxi system in Middlesex County. Given transportation statistics for

More information

EXECUTIVE SUMMARY. Introduction

EXECUTIVE SUMMARY. Introduction EXECUTIVE SUMMARY Introduction The purpose of this study is to ensure that the Village, in cooperation and coordination with the Downtown Management Corporation (DMC), is using best practices as they plan

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period 8. Operating Plans The following Section presents the operating plans for the Short-List Alternatives. The modern streetcar operating plans are presented for Alternatives 2 and 3, followed by bus rapid

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

2.0 INTRODUCTION. Around the Bay Rail Study LS Transit Systems, Inc. in association with DKS & Nelson\Nygaard

2.0 INTRODUCTION. Around the Bay Rail Study LS Transit Systems, Inc. in association with DKS & Nelson\Nygaard 2.0 INTRODUCTION Passenger rail service has continually expanded in California for the past twentyyears. The State s growing network of commuter, intercity and inter-state trains now forms the second largest

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS. A Case Study of the Alameda Corridor

REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS. A Case Study of the Alameda Corridor REALIZING THE AIR QUALITY BENEFITS OF PORT INFRASTRUCTURE PROJECTS A Case Study of the Alameda Corridor April 29, 25 Dr. Margaret Lobnitz, Weston Solutions, Inc. 1 BACKGROUND In mid-198 s, growing concern

More information

I-15 Commuter Rail Feasibility Study

I-15 Commuter Rail Feasibility Study Final Report I-15 Commuter Rail Feasibility Study Prepared for Riverside County Transportation Commission in association with Cambridge Systematics, Inc. Schiermeyer Consulting Services June 29, 2007 Interstate

More information

The Preferred Alternative: a Vision for Growth on the Northeast Corridor

The Preferred Alternative: a Vision for Growth on the Northeast Corridor A Long-Term Vision is Needed The Preferred Alternative: a Vision for Growth on the Northeast Corridor The Federal Railroad Administration (FRA) has released the Tier 1 Final Environmental Impact Statement

More information

Clean Harbors Canada, Inc.

Clean Harbors Canada, Inc. Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260

More information

UTA Transportation Equity Study and Staff Analysis. Board Workshop January 6, 2018

UTA Transportation Equity Study and Staff Analysis. Board Workshop January 6, 2018 UTA Transportation Equity Study and Staff Analysis Board Workshop January 6, 2018 1 Executive Summary UTA ranks DART 6 th out of top 20 Transit Agencies in the country for ridership. UTA Study confirms

More information

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1

More information

DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY

DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY APPENDIX 1 DEVELOPMENT OF RIDERSHIP FORECASTS FOR THE SAN BERNARDINO INFRASTRUCTURE IMPROVEMENT STUDY INTRODUCTION: This Appendix presents a general description of the analysis method used in forecasting

More information

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project.

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project. EXECUTIVE SUMMARY This study addresses the traffic impacts associated with the proposed Shopko redevelopment located in Sugarhouse, Utah. The Shopko redevelopment project is located between 1300 East and

More information

CLAREMONT METROLINK STATION STUDY Claremont Town Hall Meeting December 11, 2017

CLAREMONT METROLINK STATION STUDY Claremont Town Hall Meeting December 11, 2017 CLAREMONT METROLINK STATION STUDY Claremont Town Hall Meeting December 11, 2017 1 Welcome Larry Schroeder Claremont Mayor 2 Agenda 1. Introduction of Panelists 2. Background 3. Metro Board Motion - Metrolink

More information

9. Downtown Transit Plan

9. Downtown Transit Plan CORRADINO 9. Downtown Transit Plan KAT Transit Development Plan As part of the planning process for the TDP, an examination of downtown transit operations was conducted. The Downtown Transit Plan 1 is

More information

Traffic and Toll Revenue Estimates

Traffic and Toll Revenue Estimates The results of WSA s assessment of traffic and toll revenue characteristics of the proposed LBJ (MLs) are presented in this chapter. As discussed in Chapter 1, Alternatives 2 and 6 were selected as the

More information

Service Quality: Higher Ridership: Very Affordable: Image:

Service Quality: Higher Ridership: Very Affordable: Image: Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to

More information

Submission to Greater Cambridge City Deal

Submission to Greater Cambridge City Deal What Transport for Cambridge? 2 1 Submission to Greater Cambridge City Deal By Professor Marcial Echenique OBE ScD RIBA RTPI and Jonathan Barker Introduction Cambridge Futures was founded in 1997 as a

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

Figure 2-14: Existing Bus Routing at Irwindale Station

Figure 2-14: Existing Bus Routing at Irwindale Station 494 W oothill Blvd 69 N Irwindale Ave 185 Irwindale E 1st St 3 6 feet igure 2-14: Existing Bus Routing at Irwindale 39 Proposed Bus Route 494 W oothill Blvd Proposed Discontinued Bus Route Proposed New

More information

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

Background Information about the Metrobus 29 Lines Study

Background Information about the Metrobus 29 Lines Study Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR Independence Institute 14142 Denver West Parkway, Suite 185 Golden, Colorado 80401 303-279-6536 i2i.org/cad.aspx BRT = BTR Bus-Rapid Transit Is Better Than Rail: The Smart Alternative to Light Rail Joseph

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

TITLE. Planning and Design for Commuter Rail on a Busy Branchline. By Train to Perris, Not Paris

TITLE. Planning and Design for Commuter Rail on a Busy Branchline. By Train to Perris, Not Paris TITLE Planning and Design for Commuter Rail on a Busy Branchline By Train to Perris, Not Paris The Riverside County Transportation Commission's Perris Valley Line AUTHOR Tyler Bonstead STV Incorporated

More information

Portland Area Mainline Needs Assessment DRAFT. Alternative 4 Public Transportation: New or Improved Interstate Bus Service

Portland Area Mainline Needs Assessment DRAFT. Alternative 4 Public Transportation: New or Improved Interstate Bus Service Portland Area Mainline Needs Assessment DRAFT Alternative 4 Public Transportation: New or Improved Interstate Bus Service HNTB Corporation April 2018 Table of Contents 4.1 Overview... 4-1 4.2 Key Assumptions...

More information

Chicago Milwaukee Intercity Passenger Rail Corridor

Chicago Milwaukee Intercity Passenger Rail Corridor Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department

More information

Caltrain Business Plan

Caltrain Business Plan Caltrain Business Plan FEBRUARY 2019 LPMG February 28, 2019 Caltrain Business Plan Project Update 2 3 What is the Caltrain Business Plan? What Why Addresses the future potential of the railroad over the

More information

San Rafael Civic Center Station Area Plan May 2012 DRAFT FOR PUBLIC REVIEW

San Rafael Civic Center Station Area Plan May 2012 DRAFT FOR PUBLIC REVIEW CHAPTER 4. PARKING Parking has been identified as a key concern among neighbors and employers in the area, both in terms of increased demand from potential new development and from SMART passengers that

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION REFRIGERATION UNITS AND MAINTENANCE SHOPS. CHAPTER FIVE railyards

More information

Coachella Valley Plug-in Electric Vehicle Coordinating Council

Coachella Valley Plug-in Electric Vehicle Coordinating Council Coachella Valley Plug-in Electric Vehicle Coordinating Council Thursday, May 10, 2012 12:00 Noon CVAG Offices 73-710 Fred Waring Drive, Suite 119 Palm Desert, CA 92260 (760) 346-1127 THIS MEETING IS HANDICAPPED

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR

More information

RE: A Traffic Impact Statement for a proposed development on Quinpool Road

RE: A Traffic Impact Statement for a proposed development on Quinpool Road James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 31, 2018 Ellen O Hara, P.Eng. Project Engineer DesignPoint Engineering & Surveying Ltd. 200 Waterfront

More information

Denver Car Share Program 2017 Program Summary

Denver Car Share Program 2017 Program Summary Denver Car Share Program 2017 Program Summary Prepared for: Prepared by: Project Manager: Malinda Reese, PE Apex Design Reference No. P170271, Task Order #3 January 2018 Table of Contents 1. Introduction...

More information

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 Project Facts 4-mile route, 23 stops 8 made in USA modern streetcars All electric and green Voter-approved project Connects

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 11, 2018 To: The Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at Overview Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at www.garail.com Commuter rail service between Lovejoy and Atlanta is ready for implementation:

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,

More information

Knoxville Area Transit (KAT) Transit Development Plan Downtown Transit Plan

Knoxville Area Transit (KAT) Transit Development Plan Downtown Transit Plan Knoxville Area Transit (KAT) Transit Development Plan Submitted to: Knoxville Area Transit and Knoxville Knox County Metropolitan Planning Commission Submitted by: Connetics Transportation Group Under

More information

Passenger Rail Solar Electrification: A Primer. Oregon Department of Transportation Rail Division. June 2009

Passenger Rail Solar Electrification: A Primer. Oregon Department of Transportation Rail Division. June 2009 Passenger Rail Solar Electrification: A Primer Oregon Department of Transportation Rail Division June 2009 Betsy Imholt ODOT Rail Division 503.986.4077 phone betsy.imholt@odot.state.or.us Executive Summary

More information

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Memorandum Date: February 7, 07 To: From: Subject: John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Introduction Hexagon Transportation Consultants, Inc.

More information

SEPULVEDA PASS CORRIDOR

SEPULVEDA PASS CORRIDOR SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000

More information

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Overview Commuter rail service between Lovejoy and Atlanta is ready for implementation: $87.08 Million is in

More information

Click to edit Master title style

Click to edit Master title style Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE September 7, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE PURPOSE To update Council on Kamloops

More information

is being pushed by the locomotive, which reduces the number of seats in that car.

is being pushed by the locomotive, which reduces the number of seats in that car. Commuter rail is passenger rail service that is designed to transport large volumes of passengers over long distances in a fast and comfortable manner. The primary market for commuter rail service is usually

More information

More than $9 Million coming to Central Valley for transportation

More than $9 Million coming to Central Valley for transportation More than $9 Million coming to Central Valley for transportation From free bus service to electric buses Part of overall $97 Million awarded to public transportation projects A total of 152 local public

More information

Appendix C. Parking Strategies

Appendix C. Parking Strategies Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed

More information

REQUEST FOR PROPOSALS Downtown Hartford Transit Circulation and Through-Routing Study Transit Operations Planning Services

REQUEST FOR PROPOSALS Downtown Hartford Transit Circulation and Through-Routing Study Transit Operations Planning Services REQUEST FOR PROPOSALS Downtown Hartford Transit Circulation and Through-Routing Study Transit Operations Planning Services The Capitol Region Council of Governments (CRCOG) seeks consulting services in

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

REMOVE II VANPOOL VOUCHER INCENTIVE PROGRAM

REMOVE II VANPOOL VOUCHER INCENTIVE PROGRAM REMOVE II VANPOOL VOUCHER INCENTIVE PROGRAM GUIDELINES, POLICIES, AND PROCEDURES Complete Version The San Joaquin Valley Air Pollution Control District (District) is seeking applications from vanpool riders

More information

Southern California - CHSRA

Southern California - CHSRA CALIFORNIA HIGH-SPEED RAIL Michael Gillam, Deputy Program Director Southern California - CHSRA CMAA - Construction Management Association of America July 19, 2012 CALIFORNIA S HIGH-SPEED TRAIN SYSTEM Largest

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site TRAFFIC IMPACT STUDY for USD #497 Warehouse and Bus Site Prepared by: Jason Hoskinson, PE, PTOE BG Project No. 16-12L July 8, 216 145 Wakarusa Drive Lawrence, Kansas 6649 T: 785.749.4474 F: 785.749.734

More information

Parks and Transportation System Development Charge Methodology

Parks and Transportation System Development Charge Methodology City of Sandy Parks and Transportation System Development Charge Methodology March, 2016 Background In order to implement a City Council goal the City of Sandy engaged FCS Group in January of 2015 to update

More information

DRAFT Evaluation Scores. Transit

DRAFT Evaluation Scores. Transit DRAFT Evaluation s The criteria for evaluating applications for new funding commitments are used to measure how well they advance the six goals identified for the MTP. Through transportation: Reduce per

More information

Successful Passenger Rail in the State of California

Successful Passenger Rail in the State of California Successful Passenger Rail in the State of California Texas Transportation Forum Austin, Texas Eugene K. Skoropowski, Managing Director Capitol Corridor Joint Powers Authority (CCJPA) Oakland, California

More information

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ).

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ). 20 September 2017 Low-emissions economy inquiry New Zealand Productivity Commission PO Box 8036 The Terrace Wellington 6143 info@productivity.govt.nz Dear Commission members, Re: Orion submission on Low

More information

NICTI Alternatives Analysis

NICTI Alternatives Analysis EXECUTIVE SUMMARY Development of Detailed Alternatives Report Prepared for: Northern Illinois Commuter Transportation Initiative City of Rockford, Illinois Prepared by: 222 South Riverside Plaza, Suite

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

Executive Summary October 2013

Executive Summary October 2013 Executive Summary October 2013 Table of Contents Introduction... 1 Rider Transit and Regional Connectivity... 1 Plan Overview... 2 Network Overview... 2 Outreach... 3 Rider Performance... 4 Findings...

More information

Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS

Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS Annie Nam Southern California Association of Governments September 24, 2012 The Goods Movement

More information

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost.

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost. Policy Note Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost Recommendations 1. Saturate vanpool market before expanding other intercity

More information

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016

CTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis

More information

Treasure Island Mobility Management Program

Treasure Island Mobility Management Program Treasure Island Mobility Management Program Preliminary Toll Policy Recommendations For Buildout Year (2030) Draft TIDA CAB June 2, 2015 About the Treasure Island Mobility Management Program 2003 2008

More information

Michigan/Grand River Avenue Transportation Study TECHNICAL MEMORANDUM #18 PROJECTED CARBON DIOXIDE (CO 2 ) EMISSIONS

Michigan/Grand River Avenue Transportation Study TECHNICAL MEMORANDUM #18 PROJECTED CARBON DIOXIDE (CO 2 ) EMISSIONS TECHNICAL MEMORANDUM #18 PROJECTED CARBON DIOXIDE (CO 2 ) EMISSIONS Michigan / Grand River Avenue TECHNICAL MEMORANDUM #18 From: URS Consultant Team To: CATA Project Staff and Technical Committee Topic:

More information