III: TRANSMISSION SYSTEM PROFILE... 6 IV: PLANNING CRITERIA V: NEED FOR O&M CAPITAL EXPENDITURES... 16

Size: px
Start display at page:

Download "III: TRANSMISSION SYSTEM PROFILE... 6 IV: PLANNING CRITERIA V: NEED FOR O&M CAPITAL EXPENDITURES... 16"

Transcription

1

2

3 TABLE OF CONTENTS I: INTRODUCTION... 1 II: EXISTING TRANSMISSION SYSTEM North Luzon Region South Luzon Region Visayas Region Mindanao Region... 5 III: TRANSMISSION SYSTEM PROFILE North Luzon Region South Luzon Region Visayas Region Mindanao Region IV: PLANNING CRITERIA V: NEED FOR O&M CAPITAL EXPENDITURES Substation Secondary Devices Upgrading Replacement of Defective Line Materials and Hardware Implementation of Projects to Control and Mitigate the Effects of Fire and Flood Slope Protection of Transmission Line Structures Acquisition of Spares of High Voltage Equipment, Line Materials and Hardware Construction of Overall and Regional Disaster Command Centers Implementation of Various Environment Preservation and Protection Projects Acquisition of Heavy Equipment, Vehicles,Test Instruments and Linemen Tools.. 21 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 3

4 VI: CAPEX PROGRAM NORTH LUZON CAPEX PROGRAM North Luzon Work Orders North Luzon General Plant Equipment North Luzon Spares SOUTH LUZON CAPEX PROGRAM South Luzon Work Orders South Luzon General Plant Equipment South Luzon Spares VISAYAS CAPEX PROGRAM Visayas Work Orders Visayas General Plant Equipment Visayas Spares MINDANAO CAPEX PROGRAM Mindanao Work Orders Mindanao General Plant Equipment Mindanao Spares VII: CAPEX SUMMARY APPENDIX... 37

5 I. Introduction In line with the mandate of the National Grid Corporation of the Philippines (NGCP) to maintain, operate, expand and improve the high voltage backbone transmission system and facilities throughout the country pursuant to Republic Act 9136 or otherwise known as the Electric Power Industry Reform Act of 2001 or EPIRA, the Operations & Maintenance (O&M) group prepared the 2012 Transmission Development Plan (TDP) Volume II. In particular TDP Volume II is aimed at making the grid more reliable and to address the problems associated with an aging transmission facilities based given the realities of the current regulatory framework. The TDP, as required by the R.A. 9136, shall be submitted to the Department of Energy (DOE), which in turn would be integrated to the Philippine Development Plan (PDP) and the Philippine Energy Plan (PEP). The TDP Volume II shall contain the O&M capital expenditure program, covering the period 2012 to 202. The expenditures is in line with the goals and objectives of the O&M group to achieve the corporate vision of NGCP to build the strongest power grid and maintain the best utility practice in Southeast Asia. The TDP Volume II is one of the three (3) volumes that comprise the 2012 TDP. Volume I covers major network upgrades while Volume III covers the Capital Expenditure (CAPEX) program of System Operations. Volume II is made up of two parts. Part 1 focuses on Capital Expenditures (CAPEX) for the operation and maintenance of the power transmission grid covering the three (3) main islands namely Luzon, Visayas and Mindanao while Part 2 covers the Capital Expenditures (CAPEX) for revenue metering. The major categories of expenditures of TDP Volume II Part 1 are as follows: 1. Substation Secondary Devices Upgrading 2. Replacement of Defective Line Materials and Hardware 3. Implementation of Projects to Control and Mitigate the Effects of Fire and Flood 4. Acquisition of Heavy Equipment, Vehicles,Test Instruments, and Linemen Tools 5. Acquisition of Spares of High Voltage Equipment, Line Materials And Hardware 6. Slope Protection of Transmission Line Structure 7. Construction of Overall and Regional Command Centers 8. Implementation of Various Environment Preservation and Protection Projects The TDP Volume II Part 1 consists of seven (7) chapters. Chapter 1 provides a macro view of Volume II of the Transmission Development Plan. Chapter 2 contains the description of the transmission system in circuit kilometers, the capacities of substations in MVAs and the reactive/capacitive compensation in MVARs presently installed in North Luzon, South Luzon, Visayas and Mindanao Regions. Chapter 3 shows the transmission line profile of the four (4) NGCP regions. It provides information on the existing transmission lines and substations of each region and the major customers it serves. The geographical maps showing the set-up and route of the power system are also included in this chapter Chapter 4 explains the criteria and factors that were considered in preparing the CAPEX program Chapter 5 justifies the necessity of implementing the CAPEX program to sustain TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 1

6 and/or improve the reliability of the system, Chapter 6 provides detailed information on the CAPEX program of each region. Chapter 7 summarizes in tables and graphs the CAPEX Program of the O&M Group. 2 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

7 II. Existing Transmission System 1.0 North Luzon Region Of all the four (4) regions the North Luzon Operations and Maintenance (NLOM) is responsible for operating and maintaining the longest transmission and subtransmission lines with a total length of 5, circuit kilometers. NLOM has also the largest substation installed capacity of 12,597.5 MVA. The region is in charge of transmitting the electric power generation from the different power generating plants in North Luzon Region to the load centers. In order to maintain node voltages within the level prescribed by the Grid Code, a total of 1,210 MVARs capacitors and reactors are installed strategically in the North Luzon grid particularly in Bolo (Kadampat), San Jose and Mexico substations. The table below summarizes the transmission facilities of the North Luzon Region. Voltage Level Table 2.1: NLOM Summary of Existing Transmission Facilities Transmission Lines (ckt-km) Sub- Transmission Lines (ckt-km) Substation Capacity (MVA) Reactive/ Capacitive Compensation (MVAR) 500-kV , kV , kV kV & below , Total 3, , , , South Luzon Region The South Luzon Operations and Maintenance (SLOM) is responsible for transmitting the electric power generation of the different power generating plants in South Luzon Region. While SLOM is responsible for operating and maintaining the shortest length of transmission and sub-transmission lines compared to other regions, it is in-charge of transmitting the biggest generation capacity. Out of the 10,499 MW generation capacity installed in Luzon, SLOM is accountable for transmitting about sixty percent (60%) of this total capacity. The South Luzon O&M has a total transmission and subtransmission line length of 3, circuit kilometers (ckt-km), and total substation capacity of 8, MVA. To maintain node voltages within the level prescribed by the Grid Code, a total of 375 MVAR capacitors and reactors are installed strategically in the South Luzon Grid. SLOM, together with VOM, operates and maintains the one-of-a-kind HVDC system in the country, i.e. the Leyte-Luzon HVDC interconnection. The interconnection between the Luzon and Visayas grids is through HVDC overhead lines and submarine cables. Of the total 863 ckt-km HVDC overhead lines, 345 ckt-km is under the area of responsibility of SLOM. But the whole stretch of submarine cables, ckt-km, is under the area of responsibility of SLOM. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 3

8 With the operation of Wholesale Electricity Spot Market (WESM) in the Visayas, the HVDC link plays a very important role in this competitive electricity trading. Table 2.2 summarizes the transmission facilities of SLOM. Voltage Level Table 2.2: SLOM Summary of Existing Transmission Facilities Transmission Lines (ckt-km) Sub- Transmissi on Lines (ckt-km) Submarine Cable (ckt-km) Substation Capacity (MVA) Reactive/ Capacitive Compensa tion (MVAR) 500-kV , kV DC mh 230-kV 2, , kV kV & below Total 3, , Visayas Region The Visayas Operations and Maintenance (VOM) is responsible for transmitting the electric power generation of the different power generating plants in Visayas Region. VOM is also in charge of the most number of submarine cable interconnection in the country with submarine cable links to six (5) major islands of Leyte, Cebu, Bohol, Negros and Panay. The Samar Island is connected to Leyte through a special transmission line crossing at San Juanico Strait. The overhead transmission and subtransmission infrastructure cover a total of 4, circuit kilometers (ckt-km) length of lines and 3, MVAs substation capacities spread across the region. The transmission infrastructure includes the submarine cables interconnecting the main islands of the region, namely Leyte, Cebu, Bohol, Negros and Panay. To maintain the node voltages within the level prescribed by the Grid Code at any given time, a total of 300 MVARs capacitive compensations connected at 69-kV system are strategically situated throughout the grid to maintain the voltage level within tolerable limits. Likewise, there are reactive compensations with a total aggregate rating of 420 MVAR connected to the 230-kV system and 220 MVAR connected to 138-kV system as components of the island to island submarine cable interconnection intended for voltage correction. The table 2.3 summarizes the transmission facilities of the Visayas Region. 4 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

9 Voltage Level Table 2.3: VOM Summary of Existing Transmission Facilities Transmission Lines (ckt-km) Sub- Transmissio n Lines (ckt-km) Submarine Cable (ckt-km) Substatio n Capacity (MVA) Reactive/ Capacitive Compensa tion (MVAR) 350-kV DC mH 230-kV kV 1, kV & Below , Total 3, , , Mindanao Region The Mindanao Operations and Maintenance (MOM) is responsible for transmitting the electric power generated from the different power generating plants in Mindanao Region. The transmission and sub-transmission assets cover a total length of 5, circuit kilometers (ckt-km) and total substation capacity of 2,792.5 MVA. Of all the regions, MOM operates the second longest transmission and sub-transmission lines, next only to NLOM. To maintain node voltages within the level prescribed by the grid code, a total of MVARs capacitive compensation are installed strategically in the Mindanao grid. Table 2.4 summarizes the transmission facilities of MOM. Voltage Level Table 2.4: MOM Summary of Existing Transmission Facilities Transmission Lines (ckt-km) Sub- Transmission Lines (cktkm) Substation Capacity (MVA) Capacitive Compensation (MVAR) 138-kV 3, , kV & Below , Total 3, , , TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 5

10 III. Transmission System Profile 1.0 North Luzon Region The transmission system under North Luzon Region area of responsibility stretches from Cagayan province to Rizal province and northern portion of Metro Manila. It covers a total of 22 provinces including major cities and urban centers. The backbone of the system is a network of 500-kV Extra High Voltage (EHV) transmission lines that run through the provinces of Pangasinan, Nueva Ecija and Bulacan and a network of 230-kV lines that covers majority of the entire area of North Luzon except areas up to Ilocos Norte which are still served by 115-kV radial lines. Power generated by the Hydroelectric Power Plants in Ambuklao, Binga, Bakun, Magat, San Roque, Casecnan, Pantabangan and Angat and by the Coal Fired Power Plants in Masinloc and Sual are transmitted to the load centers in North and Central Luzon and Metro Manila through these networks of 500-kV and 230-kV transmission lines. The San Jose and (Dona Imelda) Araneta substations operate as the power interchange between North Luzon and South Luzon and together with Taytay(Dolores) Substation also serving as the gateway of power generated from North Luzon to Metro Manila. The North Luzon Region has a total of 29 major substations, 11 load-end substations and 6 power plant switchyards. There are a total of 107 load customers comprising of 41 Electric Cooperatives and Distribution Utilities which include MERALCO; 18 Government Agencies which include 4 Economic Zones; 10 NIA Pumping Stations; 48 Non-Utilities consisting of 13 Cement Plants, 2 Steel Factories, 5 Mining Companies and various industrial plants. These customers are being served at various voltage levels of 230-kV, 115-kV, 69-kV, 34.5-kV and 23-kV. The geographical map of North Luzon Grid as shown on the next page, illustrates the set-up of power systems in the North Luzon Region that include power plants, transmission system, sub-transmission networks and load-end substations. 6 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

11 NORTH LUZON TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 7

12 2.0 South Luzon Region The transmission system under the South Luzon Region area of responsibility is rated at 500-kV and 230-kV. The 230-kV transmission system extends from the provinces of Laguna, Cavite, Batangas and some south portions of Metro Manila down to provinces of Quezon, Camarines Norte, Camarines Sur, Albay and Sorsogon covering a total of eight (8) provinces. The 500-kV EHV transmission system stretches from Dasmariñas Substation in Cavite with one of the lines branching to Ilijan Power Plant to Tayabas Substation in Southern Tagalog Area down to Naga Substation in Bicol Area. Physically, the Tayabas-Naga EHV transmission lines were designed or rated at 500-kV but energized at 230-kV system. Up to this date, the Naga Substation is not yet uprated to 500-kV. The 500-kV transmission lines consist of double-circuit, bundle-of-four, 795 MCM ACSR. Also from Tayabas Substation are similar EHV transmission lines linking San Jose 500-kV Substation of NLOM. The 230-kV transmission system covers a total of 2, ckt-km, consisting of a total of 1,315 structures (steel towers and steel poles). It traverses different types of terrain that is about 60 % plain (open/rice field) and 40 % rugged (mountainous areas). The SLOM and VOM interconnection is through the high voltage DC overhead transmission lines and submarine cables linking Naga Converter Station and Ormoc Converter Station rated at 350-kV DC. The total length of the HVDC overhead lines is lkm., of which lkm is under the area responsibility of SLOM. The total length of submarine cables is lkm., all of which is under the area of responsibility of SLOM. SLOM has a total of 57 power customers, broken down as follows: 36 directly connected industries; 14 electric cooperatives and 7 government utilities / agencies. Almost all the power customers under SLOM are being served at 69-kV level, except for Meralco, which is served at 230-kV, 115-kV and 34.5-kV levels. Furthermore, the Cavite Economic Zone and directly connected government customers are being served at 34.5-kV and 13.8-kV levels, respectively. The South Luzon s power contribution to the load center, through its transmission backbone, accounts for about 60 to 70% of the total power generation in Luzon. The geographical map of South Luzon Grid as shown on the next page, illustrates the set-up of power systems in the South Luzon Region. The map includes power plants, transmission system, sub-transmission networks and load-end substations. 8 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

13 SOUTH LUZON TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 9

14 3.0 Visayas Region The transmission network under the Visayas Region area of responsibility serves as back-bone of the Visayas Grid. The transmission system covers the major islands of Samar, Leyte, Bohol, Cebu, Negros and Panay, consisting of 11 provinces. It is a combination of 230-kV and 138-kV transmission system that are installed strategically across these islands. A 350-kV high voltage DC located at the Northeast part of Visayas serves as interconnection between Visayas and Luzon Grids. The interconnections of transmission systems between the Visayas islands were made possible with the laying out of underwater high voltage submarine cables rated at 230-kV and 138-kV. The bulk of the generation comes from the geothermal fields of Leyte in the Northeastern part. Therefore, the normal power flow in the Visayas region is from the Northeastern to the western part of the region In order for the end consumers to avail of the electric power via the distribution network of their utilities, NGCP continues to operate and maintain the 69-kV subtransmission line assets that are yet to be sold to the qualified distribution utilities. Furthermore, by virtue of ERC decision on ERC Case No dated October 12, 2009 which reclassified a number of 69kV lines in Visayas Grid to transmission assets and ERC Resolution No. 18 dated August 10, 2009 which similarly mandates that Residual Sub-transmission Assets (RSTAs) which has not been disposed by the end of 2010 will be reclassified as transmission/network assets highlighted the need for NGCP to rehabilitate these RSTAs. The Visayas Region has a total of 80 customers, broken down as follows: 12 generation customers owned by private and government entities, 38 non-distribution utilities mostly directly connected industries and government establishments that included Economic Zones, and 30 distribution utilities comprising of private utilities and electric cooperatives. The load customers are being served at different receiving voltage levels, depending on their requirement, through their connection facilities that include dedicated lines and load-end substations. The geographical map for Visayas Grid as shown on the next page, shows the set-up of power generation and transmission systems in the Visayas Region that include power plants, transmission system comprising of high voltage lines and power substations and sub-transmission network. 10 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

15 VISAYAS TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 11

16 4.0 Mindanao Region In Mindanao, with the bulk of power coming from the northern part of the Region, power is transmitted to the Southern, Eastern and Western part through the 138-kV transmission lines. The Region covers 21 provinces, with fifty seven (57) customers, thirty (30) of which are Distribution Utilities with twenty-seven (27) Electric Cooperatives which are connected mainly by either 138-kV or 69-kV lines. Major industries such as cement and steel factories and big distribution utilities in Central and Southern Mindanao are directly connected to the grid at 138-kV level while other customers are served at 69- kv level. MOM operates and maintains 3,058 ckt-km of transmission lines and 2, cktkm of sub-transmission lines that are interconnected via 27 substations and 7 switchyards. To provide for the needed 1,230 MW peak demand in the Mindanao grid, there is a total of 1773 MW installed generating capacity. On the northern and central parts of Mindanao, there are Hydroelectric Plants operated by NPC, the Agus and Pulangi Hydroelectric Plants with a total installed capacity of 982 MW, Iligan Diesel Power Plants (NPC-IPPs) 98 MW, and Mindanao Coal Fired Power Plant (MCFPP), 200 MW. There are two (2) Power Barges at the eastern and southern parts, rated at 100MW each and Diesel Plants, SPCC at General Santos, 50 MW and WMPC at Zamboanga City, 100 MW. There is also geothermal power plant, MGPP, operated by PNOC rated at 95 MW. In the Region, there is still significant number of sub-transmission lines that are not yet divested to the distribution utilities. Hence, NGCP continues to operate and maintain these facilities in order to maintain service reliability of these subtransmission assets. The Geographical Map on the next page illustrates the set-up of transmission system network in the Mindanao Region, including the network of sub-transmission system that links the various customers. 12 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

17 MINDANAO TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 13

18 IV. Planning Criteria The objective of 2012 Transmission Development Plan (TDP), Volume II, Part 1 is to achive reliability by means of minimizing, if not totally preventing, power supply outages. With this objective in mind, a review of the current condition of the existing transmission and sub-transmission lines and substations and associated infrastructures was given utmost importance. One major consideration is the remaining useful life of the assets. With the assets nearing their economic life, it is prudent to anticipate that more maintenance and tests would be performed and more spares and spare parts would be needed and in due time the aging assets have to be replaced The table and graph below shows a summary of the age profile of major NGCP assets: Equipment Table 4: Age Profile of NGCP s Transmission Assets Assets ERC Recommend ed Economic Life Percentag e of Installed Equipment that have reached 50% of Economic Life Percentage of Installed Equipment that have reached 80% of Economic Life Percentage of Installed Equipment that have reached 100% of Economic Life Power Transformer Power Circuit Breaker Potential Transformer Current Transformer Protective Relays Battery and Chargers TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

19 Figure 4: Age Profile of NGCP s Transmission Assets As seen in the table and graph above, an alarming number of the secondary devices of major substations in NGCP have already reached or are nearing their economic life. If these substations are not given utmost attention, a major disturbance may soon be experienced. With the data at hand, the replacement and upgrade of secondary devices of major substations remains a priority thereby enhancing and strengthening the existing protection and control system which would then lead to a more stable and reliable grid. As in the past, typhoons continue hitting the country with a significant number of transmission line structures and substations being severely affected. These continuing occurrences necessitated the need to address concerns on flooding and erosion of foundation. Procurement of spares to replace those damaged by typhoons and the construction of anti-flooding measures to mitigate the effect of flooding brought by these natural calamities have to be implemented.. The Philippines, being archipelagic in nature, poses logistical problems in responding to outages. To provide better service to our customers in case of outages, more spare materials, equipment and logistics have to be stored in strategic locations throughout the country. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 15

20 V. Need for O&M Capital Expenditures In line with the planning criteria set, the following activities have to be implemented in order to meet the PIS targets set forth by the ERC at the beginning of the Third Regulatory Period covering the years 2011 to 2015: a. Substation Secondary Devices Upgrading b. Replacement of Defective Line Materials And Hardware c. Implementation of Projects to Control and Mitigate the Effects of Fire and Flood d. Slope Protection of Transmission Line Structure e. Acquisition of Spares of High Voltage Equipment, Line Materials And Hardware f. Construction of Overall And Regional Command Centers g. Implementation of Various Environment Preservation and Protection Projects h. Acquisition of Heavy Equipment, Vehicles,Test Instruments, and Linemen Tools 1.0 Substation Secondary Devices Upgrading With substantial improvement in the reliable operation of substations by means of the reduction of the undesired operation of the secondary devices, O&M continues its drive to upgrade the secondary devices of critical substations. North Luzon, with the aim of enhancing the reliability of the grid and load sectors in Metro Manila, started the upgrade of Quezon (Balintawak) Substation in 2011 with the plan of upgrading Doña Imelda (Araneta) in These substations are considered as the critical link in transmitting the power from the North to the South. With the age of secondary devices in these substations now over 20 years, instability has started to manifest. Furthermore, a separate Control Room/ Relay Room for the Quezon (Balintawak) Substation is also needed since NGCP and Meralco share the same control building and space would be inadequate for relay panel expansions. Mexico, San Jose and Hermosa Substation on the other hand, play a vital role in the transmission of power from the Northern Region to Metro Manila. With the secondary devices in these substations being in service for 15 years, O&M has already started the upgrading of San Jose and Mexico substation with Hermosa Substation scheduled to start in In 2011, South Luzon O&M upgraded the secondary devices of Biñan substation and the plan to upgrade the secondary devices of Muntinlupa (Sucat) substation has already been started. The Muntinlupa (Sucat) and Biñan substations in South Luzon can be compared with Mexico, San Jose and Hermosa Substations in terms of criticality and functions. These substations are responsible for the transmission of power from the Southern Region to the Metro Manila Area, which is the Load center in Luzon. The secondary devices in these substations also need replacement since most of these devices have been in service for at least 15 years. Calaca Substation also needs a separate control house facility since NGCP shares the same the control building with DMCI power and space would be inadequate for secondary panel expansions. The Calaca secondary upgrading is part of the Calaca Uprating Project of P&E. The Visayas region will also upgrade the critical substations. These are Daan- Bantayan (Talisay), Sta. Barbara and Compostela Substations. The secondary devices of Talisay, Sta. Barbara and Compostela substations are already well beyond the service life. The secondary facilities in these substations are already 13, 16 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

21 17 and 16 years old respectively. The obsolete MBSC of the Bacolod substation will also be replaced. In Mindanao, The Balo-I (Abaga) Substation is the largest Substation in terms of the number of connected lines. Figuratively speaking, it is the heart of the power transmission in Mindanao. It is responsible in transmitting power to various parts of the Mindanao Region. Some of the devices in this substation have been in service for 37 years, thus the secondary devices in this substation are in need replacement. This prompted O&M to upgrade the secondary devices of Abaga substation this NLOM, SLOM, VOM and MOM have also identified other critical substations in need of upgrading and those whose secondary devices have reached the ERC economic life a. 2.0 Replacement of Defective Line Materials and Hardware Of the 19, circuit kilometers (ckt-km) of transmission lines under NGCP, around 2, ckt-km or 14% are 30 years and older while around ckt-km or 4% are 50 years and older. Considering the advanced age of these transmission lines, a considerable number of line materials and hardware are expected to become defective, hence, replacement will be needed. The Graphs below illustrate that from 2011 to October 2012, tripping due to TL conductor and hardware defects constitute 26% of major causes of Forced Outages. This statistics support the need for the replacement of defective line materials and hardware. Major Causes of Forced Outage 48% 5% 21% 26% TL Conductor and Hardware Defects Protection Relay/Control System SS Equipment Trouble Insulator Failure TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 17

22 No. of Foced Outages TL Conductor and Hardware Defects Forced Outages Protection Relay/Cont rol System SS Equipment Trouble Insulator Failure Vegetation Within ROW Violation of safe electrical clearance Outage Implementation of Projects to Control and Mitigate the Effects of Fire and Flood The recent flooding of Hermosa Substation reiterated the need to further review the vulnerability of substations in low-lying areas. The implementation of anti-flooding measures will minimize if not prevent the flooding in these substations. The effectiveness of the anti-flooding measures has already been observed in Mexico, Muntinlupa and Araneta Substations. 18 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

23 The recent Fire Incident at Agus 6 switchyard wherein NGCP s fire- proofing system effectively blocked the fire from spreading to the cable trenches highlights the effectiveness and the subsequent need to further implement Anti-fire Protection measures to correct this deficiency in critical substations. 4.0 Slope Protection of Transmission Line Structures The Philippines is frequently visited by an average of 20 typhoons per year. These typhoons often carry not only high-speed wind but also devastating floodwater. This flooding had caused soil erosion at the transmission line structure foundations and, sometimes, has even caused the toppling of these structures. Hence, it is necessary that remedial measures be implemented immediately whenever these problems occur to strengthen the foundations in preparation for the occurrence of another typhoon. On the average, O&M has been implementing an average of 100 slope protection projects annually. Shown below is a completed slope protection project. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 19

24 5.0 Acquisition of Spares of High Voltage Equipment, Line Materials and Hardware Spares include items such as high voltage primary equipment, and line materials/hardware that should be maintained at all times to answer for immediate or urgent need that may arise from time to time in the course of operating the grid. An optimum level/quantity of spares 1 has to be maintained in order to ensure availability of replacement in case of an unexpected failure of equipment and to avoid further delay in the restoration and prolonged outage. The graph on the next page illustrates the percentages of outage caused by different substation equipment. Substation Equipment Trouble 2% 2% 7% Power Transformer Power Circuit Breaker 38% Disconnect Switch 23% Lightning Arrester Instrument Transformer Capacitor Bank Shunt / Line Reactor 2% 9% 17% Switchgear 1 Please see appendix for optimum level of spares per equipment/material 20 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

25 6.0 Construction of Overall and Regional Disaster Command Centers The construction of disaster command centers will mitigate the effect brought about by the fury of nature. O&M can be forewarned of an impending disaster or calamity that might cause damage to NGCP facilities like typhoon. This would result to a faster response time during power restoration and safety of personnel. 7.0 Implementation of Various Environment Preservation and rotection Projects Some of the projects that will be implemented by NGCP for the years 2012 to 2021 are for environmental compliance like the procurement of SF6 handling units, construction of oil catchment and oil spill containment and other Environmental Protection Projects. The following are the government environmental regulations that NGCP have to be complied with: a. RA 9003/DAO : Ecological Solid Waste Management Act b. RA 6969/DAO 92-29/DAO 04-36/MC 03-11: Hazardous Waste Management and Chemical Management c. DAO 04-08: Revised CCO for Ozone Depleting Substances (ODS) d. DAO 04-01: Chemical Control Order for PCBs e. DAO : Philippine Clean Water Act and its IRR f. DAO : Clean Air Act of the Philippines and its IRR A corresponding penalty for every violation found against these regulations shall be imposed by the government if not acted upon in a given time. 8.0 Acquisition of Heavy Equipment, Vehicles,Test Instruments, and Linemen Tools General Plant Equipment which include items such as substation and line testing and maintenance tools & equipment, line vehicles, heavy equipment, and office & support equipment will from time to time be replaced or upgraded to address the requirements of maintaining the grid. Based on the result of the evaluation made in line with the standardization policy of NGCP, a significant number of vehicles, tools and test equipment are already old, obsolete, unreliable, and costly to maintain not to mention that in some aspect, appropriate equipment are not available to substation and transmission line maintenance personnel (lines and substations). Statistics show that 61% of the existing vehicles are over 10 years old. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 21

26 VI. CAPEX Program With the monitoring of the ERC of the performance of NGCP according to the set parameters and criteria in the Third Regulatory Period, the enhancement of system reliability and integrity were retained as the two main considerations in the development of the O&M CAPEX for As with the 2011 TDP, full compliance to the Grid Code and other energy regulations with due concerns to safety, quality and environmental aspects were also considered. Internally, the TDP supports the programs being espoused by the corporation such as the Quality Management System, Environmental Management System and the Occupational Health and Safety Assessment System. This approach aims to enhance the system performance by the consolidation and integration of procedures, strategies and techniques in addressing technical and administrative issues. 1.0 North Luzon CAPEX Program The Summary of the CAPEX Program of North Luzon is shown below. 22 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

27 Million (Php) 1.1 North Luzon Work Orders The proposed Work Orders of North Luzon are intended to improve network reliability. These include upgrading of substation control and monitoring system for reliable on-line monitoring of critical substation equipment; replacement of old and unreliable electromechanical relays such as transformer differential relays, bus differential relays, feeder protections with state-of-the-art electronic relays; upgrading of transformer monitoring and control system for reliable control and real time monitoring on critical power transformers; Installation of additional line arresters for reliability and protection from lightning strike; Installation of fire and flood control projects; Upgrading of switchgears in substations; and the construction of hazardous waste storage facilities at various substations. For transmission and sub-transmission lines, the proposed projects include the upgrading and rehabilitation of ageing line hardware; replacement of wood poles with steel structures; construction of tower foundation; and replacement of wood poles with steel poles along various 69-kV lines. The rest of the work orders cover the repair, rehabilitation and/or refurbishment of building/support facilities, and the needed compliance with environment and IMS requirements. The projects will require an amount of Billion Pesos for the period 2012 to The project cost summary is shown in Figure North Luzon Work Orders RSTA RAB Figure 1.1: North Luzon Work Orders 1.2 North Luzon General Plant Equipment The proposed GPE consists mainly of acquisition of Maintenance Tools and Equipment for the replacement of old and defective units. Various equipment used for maintenance and repair of power equipment as well as diagnostic tools are also covered in the proposal. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 23

28 Million (Php) Million (Php) The rest of the proposed GPE mostly covers the purchase of personal protective equipment (PPE), ICT, building/office equipment and other vital support devices. The projects will require an amount of Billion Pesos for the period 2012 to The summary is shown in Figure 1.2. North Luzon GPE RSTA RAB Figure 1.2: North Luzon GPE 1.3 North Luzon Spares In planning for the spares requirement, utmost consideration were given to the minimum stock level and economic life of power equipment and accessories / devices, transmission line hardware, The materials for use in reconditioning of oil & SF6 insulated equipment; substation primary and secondary equipment such as transformer bushings & cooling fans, current transformers, potential transformers, battery banks, capacitor cells, and lightning arresters; steel poles and steel cross arms; and other line hardware such as connectors, insulators, clamps, vibration dampers, conductors, bolts and others. The projects will require an amount of Billion Pesos for the period 2012 to The spares cost summary is shown in Figure1.3. North Luzon Spares RSTA RAB Figure 1.3: North Luzon Spares 24 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

29 2.0 South Luzon CAPEX Program The CAPEX Program of the South Luzon is shown below. 2.1 South Luzon Work Orders The Work Orders for the replacement, rehabilitation, repair, and refurbishment of the existing power transmission facilities (Substations, Transmission Lines, Sub- Transmission Lines including Support Facilities) aim to enhance the reliability of the power system in South Luzon, with the end objective of providing reliable safe and quality power service to all customers. The work orders primarily cover the replacement of major substation components due to obsolescence, defects and/or operating problems. Bulk of the work orders also include the replacement/rehabilitation of transmission/sub-transmission line materials and hardware, due to corroded insulators and overhead ground wires. The rest of the TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 25

30 Million (Php) Million (Php) work orders cover the repair, rehabilitation and/or refurbishment of building/support facilities, and the needed compliance with environment and IMS requirements. The projects will require an amount of Billion Pesos for the period 2012 to The Work Order summary is shown in Figure South Luzon Work Orders RSTA RAB Figure 2.1: South Luzon Work Orders 2.2 South Luzon General Plant Equipment The bulk of the proposed GPE is primarily intended for the acquisition of test equipment, tools, instruments and devices as replacement to the obsolete and defective units. Acquisition of additional GPE is also included to ensure that tools and equipment are adequate for the effective and efficient implementation of various substation and line maintenance activities. The rest of the proposed GPE mostly cover the purchase of personal protective equipment (PPE), ICT, building / office equipment and other vital support devices. The projects will require an amount of Billion Pesos for the period 2012 to The GPE summary is shown in Figure 2.2. South Luzon GPE RAB Figure 2.2: South Luzon GPE 26 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

31 Million (Php) 2.3 South Luzon Spares The spares requirement, as proposed, considers the minimum stock level of installed power equipment, instruments, devices and accessories as well as line materials and hardware. It is aimed primarily to provide readily available spares for all critical and slow moving equipment. Bulk of the proposed Spares requirements cover the acquisition of substation primary equipment, such as but not limited to: power transformers, instrument transformers, lightning arresters, transformer bushings, and a number of substation secondary devices. The projects will require an amount of Billion Pesos for the period 2012 to The spares cost summary is shown in Figure South Luzon Spares RAB Figure 2.3: South Luzon Spares TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 27

32 3.0 Visayas CAPEX Program The summary of the CAPEX Program of Visayas is shown below. 3.1 Visayas Work Orders The work order proposals for the region primarily consists projects that are intended for the operation and maintenance of major facilities which are directly used in the transmission of electric power. These are the following: a. Rehabilitation of existing transmission lines to restore them to their top operational condition by replacing defective and old component such as insulators, vibration dampers, poles, cross-arms and other hardware. This includes also the rehabilitation of HVDC facilities in Leyte and construction of tower foundation slope and river bank protection. 28 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

33 b. Major rehabilitation of substation primary equipment or its major component that had experienced excessive wear and tear and needs to be re-conditioned in order to restore to its top operation condition that includes replacement of transformer bushing that are 30 years old or above, overhauling of transformer OLTC, replacement of major parts of PCB s, etc. c. Upgrading substation secondary devices which are either old, obsolete (spare parts not already available in the market) and with recurring operational problem such as protective relays giving undesired tripping signal, etc. d. Installation of additional substation secondary devices which will improve the reliability of the system, such as provision of N-1 compliant 125VDC system, separate DC power supply for M1 and M2 protection. e. Modification of the existing station service installation (metal-clad containing the LV switchgear is directly attached to the main transformer body) will be transferred to a separate house several meters away from the main transformer. f. Construction of anti-fire projects describes as follows: i. Erection of fire wall that will protect the main transformer from flying debris coming from an adjacent HV equipment that exploded due to insulation failure, or the other way around. ii. Installation of fire stop/barrier in all critical wire/bus ways of the substation to protect control wires from the spread of fire in case of fire accident in the nearby areas. g. Construction of Anti-Flooding projects that will prevent occurrence of flooding inside the substation that may endanger the operation of the facilities. h. Re-routing portion of transmission/sub-transmission lines that is frequently affected by soil movement or with ejectment complaint from the landowner. In order to comply with the environmental, safety and security requirements, proposals for the construction of oil secondary containment were made; the rest of the work orders include the construction of new support facilities and repair of the existing structures. The summary of Work Orders which amounts to Billion Pesos is shown in Figure 3.1. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 29

34 Million (Php) Million (Php) Visayas Work Orders RSTA RAB Figure 3.1: Visayas Work Orders 3.2 Visayas General Plant Equipment Bulk of GPE proposals for Visayas include the acquisition of test and diagnostic equipment, tools, instruments and devices. Likewise, there are also proposals for the replacement of obsolete and defective units, to ensure that tools and equipment are reliable, adequate for the safe and efficient implementation of various substation and line maintenance activities. It also considers the replacement of obsolete testing equipment with state of the art technology. The rest of the proposed GPE covers the purchase of new personal protective equipment (PPE), ICT, building / office equipment and other vital O&M support devices. The summary of GPE which amounts to Billion Pesos is shown in Figure Visayas GPE RSTA RAB Figure 3.2: Visayas GPE 30 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

35 Million (Php) 3.3 Visayas Spares In planning for the Spares requirement of the Region, the minimum stock level and economic life of installed facilities and testing/measuring devices were given utmost consideration. Maintaining the minimum stock level is part of the contingency measures in order to assure readiness and attain high level of response efficiency. This is particularly important in Visayas Region where sharing of spares is very difficult due to its geographical configuration. Likewise, there is a focus on the rehabilitation of the existing sub-transmission lines that are unlikely to be acquired by the distribution utilities due to technical and financial reasons. Hence, significant amount of investment is proposed for the procurement of line materials and hardware for sub-transmission lines. The summary of Spares which amounts to Billion Pesos is shown in Figure Visayas Spares RSTA RAB Figure 3.3: Visayas Spares TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 31

36 4.0 Mindanao CAPEX Program The Summary CAPEX Program of Mindanao is shown below. 4.1 Mindanao Work Orders The Mindanao Region work order proposals primarily consist of replacement, rehabilitation, repair, and refurbishment of the existing substations, transmission and sub-transmission lines, switchyards and other support facilities. In particular, this includes coupling capacitor potential device and other High Voltage Equipment, the upgrading of the DC system of the substations, upgrading of the protection system of the grid by replacing old and unreliable fault clearance equipment with state-of-the-art and efficient relays,. Also included, are the reconstruction of transmission line towers which were toppled or have suffered structural instability due to sabotage/pilferage and the implementation of slope protection of structures. 32 TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1

37 Million (Php) And to comply with the environmental and safety requirement, there are proposals for the construction of oil containment basins and hazardous waste storage facilities, the implementation of the anti-fire and anti-flood programs for the substations, to mitigate the risk involve in fire and flooding. The rest of the Work Orders include the improvement and renovation of existing support facilities, as well as the construction of new ones. These projects are considered to ensure the reliability of the power system in Mindanao, with the end objective of providing reliable, safe and quality power service to all customers. The Work Order projects will require the amount of PhP Billion Pesos for the period 2012 to The cost summary is shown in Figure 4.1. Mindanao Work Orders RSTA RAB Figure 4.1: Mindanao Work Orders 4.2 Mindanao General Plant Equipment The GPE for the transmission lines and substation maintenance, testing and calibration is driven by the criteria imposed by System Reliability Enhancement, End-of-Life Assets Replenishment, Grid Code & Environmental/Safety Compliance, Timely Response and Data Management & Analysis Improvements. It also considers the replacement of obsolete testing equipment with state of the art ones. The acquisition of new technology equipment as part of quality advancement is also considered. Replacement of obsolete and defective tools and equipment and acquisition of modern test and monitoring equipment, such as Earth Resistance Tester, Insulation Resistance Tester, Frequency Response Analyzer, Insulation Power Factor Tester, Infrared Scanners, Transformer Diagnostic Devices, UV Scanner, Circuit Breaker Analyzer, Battery Impedance Tester, Hotline Tools, various type of stringing blocks and other power line related tools are components in the implementation of maintenance strategy. Included in the proposal is the refleeting of line maintenance vehicles and equipment consisting of line and boom trucks. TRANSMISSION DEVELOPMENT PLAN 2012 VOLUME II PART 1 33

TRANSMISSION DEVELOPMENT PLAN

TRANSMISSION DEVELOPMENT PLAN FINAL REPORT TRANSMISSION DEVELOPMENT PLAN NOVEMBER 2009 DISCLAIMER The Transmission Development Plan (TDP) is prepared and published solely for information purposes. While NGCP, to the best of its knowledge,

More information

Update on the Philippine Wholesale Electricity Spot Market

Update on the Philippine Wholesale Electricity Spot Market Update on the Philippine Wholesale Electricity Spot Market A Presentation to the APEx Asia Pacific Conference New Delhi, India 1 Presentation WESM Overview 2010 Market Results Market Outlook 2 WESM Overview

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Java-Sumatra Interconnection Transmission Line Project (I) Loan Agreement: April 30, 2010 Loan Amount:

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

PHILIPPINE DISTRIBUTION CODE 2017 EDITION PHILIPPINE DISTRIBUTION CODE 2017 EDITION PDC 2017- Background Revised the PDC 2001 Starts of revision in 2010 April 18 and 24, 2012 conducted a series of expository presentation for Visayas and Mindanao

More information

Service and Rehabilitation Electrical Power Systems

Service and Rehabilitation Electrical Power Systems Service and Rehabilitation Electrical Power Systems From water to wire 3 ANDRITZ HYDRO Electrical Power System Modernization and rehabilitation International technology group ANDRITZ is a globally leading

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Efficient Implementation of Power Sector Reforms in the Philippines

Efficient Implementation of Power Sector Reforms in the Philippines Local Energy Presentation Template Efficient Implementation of Power Sector Reforms in the Philippines DIRECTOR PATRICK T. AQUINO, CESE Energy Policy and Planning Bureau Public Consultation on National

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

III. Substation Bus Configurations & Substation Design Recommendations

III. Substation Bus Configurations & Substation Design Recommendations III. Substation Bus Configurations & Substation Design Recommendations 1.0 Introduction Pre-existing conditions, electrical arrangements or the criticality of the existing facility may limit this flexibility,

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks by Georges Barbarin Executive summary Aging electrical switchgear infrastructure is a threat to the reliability of power

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Progress and Challenges in Philippine Energy Sector Reform

Progress and Challenges in Philippine Energy Sector Reform Progress and Challenges in Philippine Energy Sector Reform A Presentation by: Lily Gutierrez Energy Policy Advisor Office of Energy and Environment Infrastructure for Rebuilding and Developing Countries

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Electricity industry structure and capacity growth trends

Electricity industry structure and capacity growth trends Electricity industry structure and capacity growth trends Restructuring since 1997 has resulted in the separation of electricity generation from transmission and distribution. However, the sector continues

More information

ABB Wind Care Service Offering

ABB Wind Care Service Offering ABB Wind Care Service Offering ABB Wind Care Service Offering ABB is the largest supplier of electrical components, systems, and services to the wind power industry. With continued investment and expansion

More information

Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA

Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA George Horvath george.horvath@aecom.com Month Day, Year Part A Introduction

More information

Substation Expansion Project

Substation Expansion Project Philippines Substation Expansion Project Report Date: August 2002 Field Survey: June 2001 1. Project Profile and Japan s ODA Loan Location Map of the Project The Concepcion substation 1.1 Background The

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Microgrid solutions Delivering resilient power anywhere at any time

Microgrid solutions Delivering resilient power anywhere at any time Microgrid solutions Delivering resilient power anywhere at any time 2 3 Innovative and flexible solutions for today s energy challenges The global energy and grid transformation is creating multiple challenges

More information

Regulating the Philippine Electric Power Industry

Regulating the Philippine Electric Power Industry Regulating the Philippine Electric Power Industry Atty. Josefina Patricia Magpale-Asirit ERC Commissioner 2018 Asia Pacific Energy Regulatory (APER) Forum 28 November 2018 PHILIPPINE POWER SYSTEM Power

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Shunt reactors Proven history for future success

Shunt reactors Proven history for future success P OW E R T R A N S FO R M E R S Shunt reactors Proven history for future success 2 SHUNT REACTORS PROVEN HISTORY FOR FUTURE SUCCESS 3 Shunt reactors an investment for today and for the future Improving

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

2016 INTEGRATED TRANSMISSION PLAN SCHEDULES SEPTEMBER 2016

2016 INTEGRATED TRANSMISSION PLAN SCHEDULES SEPTEMBER 2016 2016 INTEGRATED TRANSMISSION PLAN SCHEDULES SEPTEMBER 2016 Contents 1 Expenditure overview Summary of all capital and operating expenditure 2 Base capital expenditure Capital expenditure by asset class

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Delhi Mass Rapid Transport System Project Phase 2 (V) Loan Agreement: March 31, 2010 Loan Amount:

More information

ABB Next Level Big shift in power attractive opportunities

ABB Next Level Big shift in power attractive opportunities Bernhard Jucker and Claudio Facchin, Capital Markets Day, London, ABB Next Level Big shift in power attractive opportunities Slide 1 Agenda Profitably growing ABB s power business Shifting the center of

More information

V. Design, Application, Maintenance & Operation Technical Requirements

V. Design, Application, Maintenance & Operation Technical Requirements V. Design, Application, Maintenance & Operation Technical Requirements V.L Line & Substation Operation and Maintenance 1.0 General Requirements 1.1 Each facility owner shall have an established and documented

More information

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6b ACTION ITEM Date of Meeting August 4, 2015 DATE: TO: FROM: Dave Soike, Director, Aviation Facilities and Capital Programs Wayne Grotheer, Director,

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. A GUIDE TO TRANSPOWER 2009 TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. Contents 01 Introduction 02 System Operator 24/7

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Modular Standardized Electrical and Control Solutions for Fast Track Projects Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive

More information

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E. (Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Power Infrastructure. PowerToGrowPHX.com

Power Infrastructure. PowerToGrowPHX.com Power Infrastructure PowerToGrowPHX.com Electricity 101 Key utility terms Power supply and generation mix Overview of the electric power system Federal and State Regulation Electric Ready Site What information

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Japanese ODA Loan. Ex-ante Evaluation

Japanese ODA Loan. Ex-ante Evaluation Japanese ODA Loan Ex-ante Evaluation 1.Name of the Project Country:Republic of the Philippines Project:Capacity Enhancement of Mass Transit Systems in Metro Manila Project Loan Agreement:27 March 2013

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Promoting Investment in the Energy Sector

Promoting Investment in the Energy Sector October 16, 2013 Marubeni as a Sogo Shosha The Japanese sogo shosha is a collection of various groups involved in different business fields. Each part of the organization has something unique to offer

More information

Small Electrical Systems (Microgrids)

Small Electrical Systems (Microgrids) ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding

More information

Dynamic Reactive Power Control for Wind Power Plants

Dynamic Reactive Power Control for Wind Power Plants Dynamic Reactive Power Control for Wind Power Plants Ernst Camm, Charles Edwards, Ken Mattern, Stephen Williams S&C Electric Company, 6601 N. Ridge Blvd, Chicago IL 60626 USA ecamm@sandc.com, cedwards@sandc.om,

More information

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and RESOLUTION NO. WHEREAS, the City of Los Angeles (City) Department of Water and Power (LADWP) will be further accelerating its efforts to replace its aging Power System infrastructure, much of which was

More information

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY CHAPTER 8 - AS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY Summary This chapter presents a cost analysis of building gas and electricity transmission infrastructure to support a 1,000 MW combined-cycle

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category General Title Reference Number PMP 01 (RIC Standard: EP 00 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

Ancillary Services & Essential Reliability Services

Ancillary Services & Essential Reliability Services Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To

More information

MVDC PLUS Managing the future grid

MVDC PLUS Managing the future grid MVDC PLUS Managing the future grid Bridge the distance How should we connect Islands, platforms, and remote areas? Connecting weak or unstable grids How will we integrate and stabilize grids? Reduce footprint

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Pike County Light & Power Company Summer Reliability Outlook

Pike County Light & Power Company Summer Reliability Outlook Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Schedules 1 to 4, Lot B: Extension of the Lessos Substation 1.0 LIGHTNING ARRESTORS 1.1 ZNO lightning arrester, 192 kv rated voltage, 10 ka nominal discharge current 2.0 CAPACITIVE VOLTAGE TRANSFORMER ea. 45 2.1 220 kv capacitive voltage transformer 220/ 3 / 0.11/

More information

Contact person: Pablo Taboada Mobile:

Contact person: Pablo Taboada   Mobile: Contact person: Pablo Taboada e-mail: ptaboada@aenor.es Mobile: 34 609015450 Génova 6 28004 Madrid. Spain Phone: 34 91 4326004 Fax: 34 91 3190581 CDM Executive Board RESPONSE TO REQUEST FOR REVIEW Request

More information

When Grids Get Smart - ABB s Vision for the Power System of the Future

When Grids Get Smart - ABB s Vision for the Power System of the Future When Grids Get Smart - ABB s Vision for the Power System of the Future When Grids Get Smart ABB s Vision for the Power System of the Future There is a convergence occurring between the business realities

More information

India Smart Grid Week, 2017

India Smart Grid Week, 2017 India Smart Grid Week, 2017 N. Venu President and Head, Power Grids Division, South Asia, Middle East and Africa ABB 1 Big Shift in Power: Shaping the System of the Future Several global challenges Population

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Question Question 1.2-8

Question Question 1.2-8 Question 1.2-7 A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to

More information

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 1 of 5. Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 2 Definitions 2 Not seen the definition for Inspector. But with, - Qualifications,

More information

Building Collaboration Between East African Nations via Transmission Interconnectors

Building Collaboration Between East African Nations via Transmission Interconnectors Building Collaboration Between East African Nations via Transmission Interconnectors Eng. Christian M.A. Msyani Ag. DEPUTY MANAGING DIRECTOR TRANSMISSION - TANESCO CONTENTS 1. TANESCO - Existing Power

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

Derrick Boltt Southern Region Hydro Generation Eskom South Africa Derrick Boltt Southern Region Hydro Generation Eskom South Africa Hydro Power in the S/Region. History of Hydro in the S/Region. In 198 the former Transkei government financed the development of Hydro

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian Shunt Capacitor Bank Protection in UHV Pilot Project Qing Tian 2012-5 INTRODUCTION State Grid Corp. of China, the largest electric power provider in the country, has first build a 1000 kv transmission

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

8. TRIP DISTRIBUTION. 8.1 Trip Distribution by Trip Purpose. Figures 8.1 show desire lines by trip purpose. < To Work >

8. TRIP DISTRIBUTION. 8.1 Trip Distribution by Trip Purpose. Figures 8.1 show desire lines by trip purpose. < To Work > 8. TRIP DISTRIBUTION 8.1 Trip Distribution by Trip Purpose Figures 8.1 show desire lines by trip purpose. < To Work > Quezon (II) and Makati form large centers for to Work trips. Manila also attracts a

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines. Post-Conflict Assistance to Afghanistan

ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines. Post-Conflict Assistance to Afghanistan ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines Post-Conflict Assistance to Afghanistan February 2012 ABBREVIATIONS ADB Asian Development Bank ADF Asian Development

More information