Question Question 1.2-8

Size: px
Start display at page:

Download "Question Question 1.2-8"

Transcription

1 Question A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to minimize this risk? Is the answer to run each pole on a separate tower with sufficient distance between two poles? Are there any concerns about continuous earth return operation for a long time? This issue is of particular importance when considering the increasing number of long distance transmission schemes under consideration or under construction in China and India, respectively mentioned in Papers 110 and 117. Is there any data available on the failure rate of bipolar HVDC transmission lines? What data is available on the types of dc transmission line faults? Should AGB4-04 be collecting this data? Question The converter losses of HVDC VSC systems can be almost 3 times as that of HVDC Line Commutated Converters, as mentioned in Paper 109. How are the other HVDC VSC advantages capitalized against the higher converter losses? Is there more detailed comparative analysis between VSC and LCC technologies to be reported by authors of the above four papers, from Paper 104 or from other contributors? What are presently the main reasons for selecting/rejecting VSC transmission? In the application shown in Paper 116, were there any issues with ESCR requirements in Sicily and Sardinia and for power reversal to North Africa? To contribute with the questions and an introduction to the Madeira Transmission System is a must. The Madeira River Power Plants represent the beginning of the Amazon Basin exploitation and are located about 2500 km from the major load centers of the Brazilian Interconnected System. The transmission studies recently finished indicated the DC technology as the solution of minimum investment and less overall costs. The solution recommended by these studies was 2 bipoles of 3,150 MW each, kv, 4 x 2312 MCM, 2375 km, to supply the loads in the Brazilian Southeast region, as shown in Figure 1. To local reinforcements (Acre and Rondônia), 2 back-to-back converters of 400 MW each are provided, to connect with the existing system of 230 kv, in parallel with the planned HVDC trunk. The reason for using such devices is to avoid overload conditons in the 230 kv system in parallel with the two bipoles and prevent torsional effects on local thermal plants.

2 Rio Branco 160 km 305 km S.Antônio Jirau Coletora 30km Back-to-back 2x400MW 41km 150km 165km Samuel Ariquemes 118km 2 x 3150 MW km Pimenta Bueno 160km 354km Vilhena Jauru Cuiabá +600 kv 230 kv 335km Ribeirãozinho 364km 242km 200km Rio Verde Itumbiara SOUTHEAST REGION Atibaia 350 km N. Iguaçu 3 x kv 250 km 345 kv 440 kv 138 kv Figure 1: DC Alternative According to the Brazilian regulatory system, the process to implement new transmission facilities is done by auctions, and considering the significant investments associated to the Madeira Project, the Ministry of Energy deemed strategic to bid out, in addition to the alternative of lower cost (DC), also the technology of alternating current (AC), in order to increase competitiveness, once in the recent AC new installations expressive discounts were observed. For the distances involved, however, a purely transmission would demand 4 to 5 circuits and would lead to a very high amount of ohmic losses, around 17% of the transmitted power. So, the AC option to be auctioned would then be the 765 kv, and for that the more promising alternative to that level of voltage was rescued, which would be composed by 3 circuits of MCM conductor bundle per phase each. In the evolution of technical studies, however, sustained overvoltage problems and risk of industrial frequency resonance appeared. The lack of time for resizing this alternative, and its cost, already well above that of DC alternative, led to the prudent decision to discard it. Finally, in order to meet the strategy of having two technologies at the auction, to stimulate competition and to grant bigger discounts, a hybrid (HB) DC-AC alternative came into play. This alternative provides the flow of approximately 50% of the power to Southeast using DC technology (1 x 3150 MW bipole - equivalent to 1 of the 2 bipoles of the DC alternative) and 50% in alternating current (2 lines of, 6 x 1033 MCM, single circuit, 70% series compensated).

3 The supply to the existing regional 230 kv system is accomplished by 3 x 500/230 kv transformers in. The alternative also provides for step down transformations in Jauru, Cuiabá and Água Vermelha substations. The configuration proposed for this alternative is shown in Figure 2. R.Branco Jirau 3300MW 305 km S.Antônio 3150MW Coletora Porto Velho 160 km 3 X km 41km Samuel Ariquemes 300 km C.Oeste P.Bueno Vilhena 1 x 3150 MW km 335 km 3x954MCM Jauru Cuiabá Ribeirãozinho +600 kv 230 kv 200km 380 km Rio Verde 400 km Rio Araguaia A. Vermelha 5 km A. Vermelha existente Itumbiara SOUTHEAST REGION 250 km Atibaia 350 km N. Iguaçu 3 x kv 345 kv 440 kv 138 kv Figure 2: HB Alternative With the experience gained in the preparation of these studies, the Brazilian contributions on the issues raised in WG - B4 are listed: 1. Steps to minimize the risks of forest fires and concerns about earth return operation for a long time: a. To minimize the risk of problems due to fires and winds, a minimum distance of 10 km between bipoles was established; b. The possibility to put converters in parallel, in case of losing one line, together with the capacity of the remaining line of twice the rated current in emergency, increases the reliability as well as reduces the time of system operation with earth return;

4 c. The possibility to operate lines in parallel, in case of losing one converter, not only reduces losses but also keeps the lines always energized, minimizing the risk of theft. 2. Definition of converters overloading capacity The converters capability to sustain overload is not necessary in alternative HB, since, during the first 30 minutes after any failure in the DC side, the AC system accommodates this overload. After that, re-dispatching becomes necessary, due to the loading limitations of the series capacitor banks. In the DC alternative, a transient overload capability (about 5 seconds) of 50% is essential to prevent frequencies higher than 66 Hz. In a period of 30 minutes, an overload capacity of 10% in the remaining converters is sufficient to ensure the fulfillment of the N-1 criterion in any scenario studied. In the worst of them, losing a pole during the wet period (5 months per year) and with light load in Acre/Rondônia (about 9 hours a day) and with all the 88 generators fully dispatched, the need arises to redistribute a generation amount of no more than 1000 MW along the system. This is accomplished by the machine controllers (speed governors), at the Madeira complex as well as in the rest of interconnected system. According to the above results, and considering that currently the system coexists with losses of generation even larger than 1000 MW, the choice of an overload capacity of about 10% could be an option. However, to ensure some operating security margin to the system, the System Operator suggested as a strategy the requirement of 33 %overcapacity for the DC alternative converters. 3. Use of other technologies For reinforcements in the local Acre/Rondônia system, two back-to-back converters of 400 MW each were considered. It was not found necessary to provide overload capacity for these equipments. Due to the low short-circuit ratio verified at 230 kv busbar, it was necessary to recommend the installation of 3 synchronous compensators of 100 Mvar each. For each of the above, other control or technology related solutions to improve the performance of the CA system of 230 kv can be adopted, provided that they clearly have performance equal to or superior than those obtained in the analyses already prepared Definition of voltage transmission According to the characteristics of the Brazilian Interconnected System at the time of the Madeira River power plants implementation (year 2012), a sudden loss of a single ±800 kv bipole carrying close to 6000 MW would certainly imply stability problems, leading to the collapse of the same Interconnected System. Even though it was not part of the planning criteria, the possibility of loss of a bipole was considered as an additional security measure to select two bipoles, regardless of the system voltage.

5 The choice of the 600 kv level was based on the comparison of the total costs of the ±500, ±600 and ±800 kv transmissions. Figure 3 shows the percentage of investments associated with the construction of 2 bipoles at each voltage level. One can see, as expected, that the investments in lower voltages are lower. The losses, however, have opposite behavior, and an analysis of the overall transmission costs (investment and losses) shown in Figure 4 points out that the transmission at ±500 or ±800 kv has costs approximately 10% higher than those at 600 kv. Comparação de investimentos não comuns % 120,0 100,0 80,0 60,0 40,0 20,0 0,0 2CC5 00 2CC600 2CC800 % 100,0 107,4 114,1 Figure 3 Investm ent (%) 120,0 100,0 80,0 60,0 40,0 20,0 0,0 2CC500 2CC600 2CC800 % 110,5 100,0 108,7 Figure 4 Overal Cost (%) It is interesting to note that, if a single bipole were acceptable, the level of ±800 kv would have greater economic benefits and would become the alternative with the lower total costs. For the assumptions used, therefore, the conclusion is that the alternative of ±600 kv is the one with lower overall costs.

Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution

Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution Centro de Pesquisas de Energia Elétrica - CEPEL Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution SEMINARIO Planificación Energética y de Expansión de la Transmisión

More information

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium Cigre SC B4 Activities Towards HVDC Grids Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics HVDC Grid Workshop Belgium 2014 1 Contents Why build HVDC Grids? Types of HVDC

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System

Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System John Graham* Sergio E Santo Abhay Kumar ABB Ltda Eletrobras-Furnas ABB AB, HVDC Brazil Brazil Sweden *Corresponding

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Offshore Wind Connections HVDC for Offshore Grids

Offshore Wind Connections HVDC for Offshore Grids Michael Bahrman P.E., Grid Systems, UWIG Technical Workshop, Maui, October 2011 Offshore Wind Connections HVDC for Offshore Grids October 18, 2011 Slide 1 HVDC for Offshore Grids Topics Offshore wind market

More information

The Application of Power Electronics to the Alberta Grid

The Application of Power Electronics to the Alberta Grid The Application of Power Electronics to the Alberta Grid Peter Kuffel, Michael Paradis ATCO Electric APIC May 5, 2016 Power Electronics Semiconductor devices used in power transmission systems Types: Thyristor

More information

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

HVDC Back-to-Back Interconnections Enabling reliable integration of power system HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for

More information

Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong

Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong Tsinghua University, Beijing, China 30 th March, San Francissico, USA 1 2 3 4 5 Background Cascading Fault in AC/DC Hybrid Grid Model and Simulation

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Transmission Grid Reinforcement with Embedded VSC-HVDC Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Outline Introduction HVDC-Light Transmission Technologies Embedded VSC-HVDC for AC Grid

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven 26.11.09 Electric grid on and off-shore: current status, obstacles and new developments November 26, 2009 Slide 1 Transmission grid The challenges Optimal

More information

MAXIMIZATION OF ENERGY GENERATED AT THE POWER PLANTS

MAXIMIZATION OF ENERGY GENERATED AT THE POWER PLANTS MAXIMIZATION OF ENERGY GENERATED AT THE POWER PLANTS OF THE NORTHERN REGION OF THE BRAZILIAN INTERCONNECTED POWER SYSTEM THROUGH THE SPECIAL PROTECTION SYSTEM - SPS ASSOCIATED TO XINGU - ESTREITO HVDC

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS Available Online at www.ijcsmc.com International Journal of Computer Science and Mobile Computing A Monthly Journal of Computer Science and Information Technology IJCSMC, Vol. 3, Issue. 10, October 2014,

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative ABB HVDC Slide 1 ABB Five global divisions Power Products Power Systems

More information

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission HVDC Solutions for Integration of the Renewable Energy Resources Marcus Haeusler HVDC Lead Engineer siemens.com/energy/power-transmission Agenda Principles of HVDC operation HVDC converter types HVDC configurations

More information

Electrical Test of STATCOM Valves

Electrical Test of STATCOM Valves 21, rue d Artois, F-75008 PARIS 619 CIGRE 2016 http : //www.cigre.org Electrical Test of STATCOM Valves Baoliang SHENG 1, Christer DANIELSSON 1, Rolf NEUBERT 2, Juha TURUNEN 3, Yuanliang LAN 4, Fan XU

More information

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011 EPRI HVDC Research John Chan, Ram Adapa, Bernie Clairmont & Gary Sibilant, EPRI EPRI HVDC & FACTS Conference August 30, 2011 Presentation Contents 1. Team Members 2. Research Program Objective & Scope

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

HVDC. TMT&D provides the best and most economical HVDC system.

HVDC. TMT&D provides the best and most economical HVDC system. HVDC TMT&D HVDC TMT&D provides the best and most economical HVDC system. In 1955, TMT&D started the development of HVDC and is the leading HVDC supplier in Japan. TMT&D has continued to develop HVDC technology

More information

Electricity sector overview

Electricity sector overview Electricity sector overview Electricity market structure Snapshot of electricity sector Growth in capacity and production Growth in consumption Growth in transmission line and transformer capacity Institutional

More information

ABB Wind Power Solution

ABB Wind Power Solution Feng Li, Wind ISI, CNABB, November, 2016 ABB Wind Power Solution November 13, 2016 Slide 1 ABB deliveries from A to Z into the wind industry Wind power generation, transmission and integration, control

More information

Evaluation of offshore HVDC grid configuration options

Evaluation of offshore HVDC grid configuration options Evaluation of offshore HVDC grid configuration options Keith Bell and Callum MacIver Dept. of Electronic and Electrical Engineering University of Strathclyde, UK This work has benefited from support by:

More information

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1 Characteristics of the Project Parameter Detail

More information

HVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University

HVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University HVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University Why has HVDC taken off? HV is needed to transmit DC

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2.

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2. CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO Rexhep Shaqiri 1, Bogdanov Dimitar 2 1 Technical University - Sofia, E-mail: rexhep_shaqiri@hotmail.com). 2 Technical University -

More information

Extra-High-Voltage SF 6 Gas-Insulated Switchgear

Extra-High-Voltage SF 6 Gas-Insulated Switchgear Extra-High-Voltage SF 6 Gas-Insulated Switchgear Shuichi Sugiyama Masahiko Fujita Takahiro Shinohara 1. Introduction Due to location criteria and toughened restrictions on transportation, it has become

More information

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008 IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008 Improving Power System Dynamic Performance in Laredo, TX Prepared by Paul Hassink (AEP) Paul Marken (GE) Rob O Keefe (AEP) Gerardo

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Chapter 3.1: Electrical System

Chapter 3.1: Electrical System Part-I: Objective type Questions and Answers Chapter 3.1: Electrical System 1. The heat input required for generating one kilo watt-hour of electrical output is called as. a) Efficiency b) Heat Rate c)

More information

ELG4125: Flexible AC Transmission Systems (FACTS)

ELG4125: Flexible AC Transmission Systems (FACTS) ELG4125: Flexible AC Transmission Systems (FACTS) The philosophy of FACTS is to use power electronics for controlling power flow in a transmission network, thus allowing the transmission line to be loaded

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Experience on Technical Solutions for Grid Integration of Offshore Windfarms Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow

More information

Cigre and Trends in Power Electronics for the Grid. Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics

Cigre and Trends in Power Electronics for the Grid. Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics Cigre and Trends in Power Electronics for the Grid Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics Contents SC B4 Activites Present Status of HVDC System Technology Active

More information

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. N. Lettas*, A. Dagoumas*, G. Papagiannis*, P. Dokopoulos*, A. Zafirakis**, S. Fachouridis**,

More information

ABB Group August 27, 2010 Slide 1

ABB Group August 27, 2010 Slide 1 Michael Bahrman P.E., ABB Grid Systems, August 31, 2010, Asia Pacific Clean Energy Summit 2010, Honolulu Integration of Variable Renewable Energy for Hawaii Transmission of Isolated Resources August 27,

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Chapter 1. Overview of HVDC applications

Chapter 1. Overview of HVDC applications ELEC0445 - High Voltage Direct Current grids Part 1. Line Commutated Converters Chapter 1. Overview of HVDC applications Patricia Rousseaux t.vancutsem@ulg.ac.be Thierry Van Cutsem www.montefiore.ulg.ac.be/~vct

More information

Electrical grid stability with high wind energy penetration

Electrical grid stability with high wind energy penetration ECOWAS Regional Workshop on WIND ENERGY Praia, Cape Verde. November 4 5, 2013 Electrical grid stability with high wind energy penetration Fernando CASTELLANO HERNÁNDEZ Head of Wind Energy Section Renewable

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

High Voltage Direct Current Systems

High Voltage Direct Current Systems GE Grid Solutions High Voltage Direct Current Systems imagination at work Today s Environment Globally the utility environment is becoming more complex and utilities are having to manage new challenges

More information

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg Experience on Realizing Smart Grids Bazmi Husain 2010-10-12 IEEE PES conference, Gothenburg IEEE PES Conference, Gothenburg, 2010-10-12. Slide 1 On the way to the smarter grid A quietly astounding evolution

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector

More information

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK 91 CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK CHAPTER CONTENTS: 5.1 INTRODUCTION 5.2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL 5.3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW

More information

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar OFFSHORE WIND FARM CONNECTIONS TO THE GRID Energy to Quality S.L. Santiago Arnaltes Gómez Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the

More information

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011 1 HVDC Transmission 2 HVDC Transmission High Voltage Direct Current Transmission 3 AC to DC Comparison Originally the power systems were DC An historical struggle between Edison and Westinghouse was called:

More information

The Role of Offshore Wind

The Role of Offshore Wind The Role of Offshore Wind Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Richard Proctor ENI

More information

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science Raphael Görner, Head of Marketing & Sales, Grid Systems Germany 20.05.2011 Building bridges with HVDC Solar Energy for Science May 20, 2011 Slide 1 Europe 20XX Scenario ABB s DC grid vision already in

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System

DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System Public Project Report Project RENE-005 University of Toronto 10 King s College Rd. Toronto, ON 2016 Shunt Current Mes. IGBTs MOV Short

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

Physical Design of a Volt/Var Implementation

Physical Design of a Volt/Var Implementation 1 Physical Design of a Volt/Var Implementation Hydro-Québec Distribution s approach Prepared by Bruno Fazio 2 Subjects Context Volt control Planning Control strategies and exploitation Var control Planning

More information

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian Shunt Capacitor Bank Protection in UHV Pilot Project Qing Tian 2012-5 INTRODUCTION State Grid Corp. of China, the largest electric power provider in the country, has first build a 1000 kv transmission

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

SUMMARY OF THE IMPACT ASSESSMENT

SUMMARY OF THE IMPACT ASSESSMENT COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 13.11.2008 SEC(2008) 2861 COMMISSION STAFF WORKING DOCUMT Accompanying document to the Proposal for a DIRECTIVE OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL

More information

Status and Trends of HVDC

Status and Trends of HVDC Status and Trends of HVDC Dr. Mohamed Rashwan Chairman of CIGRE Study Committee B4 HVDC and Power Electronics ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE INTERNATIONAL COUNCIL ON LARGE ELECTRIC SYSTEMS The

More information

Alves, F.R.M. Henriques, R.M. Passos Fº, J.A. Gomes Jr., S. Borges, C.L.T. CEPEL UFJF UFJF CEPEL UFRJ

Alves, F.R.M. Henriques, R.M. Passos Fº, J.A. Gomes Jr., S. Borges, C.L.T. CEPEL UFJF UFJF CEPEL UFRJ 1 Integrating Solution Engines Under a Distributed Processing Environment: An Alternative Approach for Static and Dynamic Security Assessment of Large Scale Power Systems Alves, F.R.M. Henriques, R.M.

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

GE Energy. Variable Frequency Transformers Grid Inter-tie

GE Energy. Variable Frequency Transformers Grid Inter-tie GE Energy Variable Frequency Transformers Grid Inter-tie Variable Frequency Transformers GE Energy revolutionizes the world of transmission solutions with its new Variable Frequency Transformer (VFT).

More information

Wind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment

Wind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment 2012 2nd International Conference on Power and Energy Systems (ICPES 2012) IPCSIT vol. 56 (2012) (2012) IACSIT Press, Singapore DOI: 10.7763/IPCSIT.2012.V56.2 Wind Power Plants with VSC Based STATCOM in

More information

Electricity System Operator EAD. Difficulties in Grid Planning & Development

Electricity System Operator EAD. Difficulties in Grid Planning & Development Electricity System Operator EAD Difficulties in Grid Planning & Development The Electricity System Operator EAD is responsible for managing the Bulgarian power system, its parallel operation with other

More information

Getting Smart Evolution to the Smart Grid April 2008

Getting Smart Evolution to the Smart Grid April 2008 Getting Smart Evolution to the Smart Grid April 2008 Thomas F Garrity Vice President, Sales and Business Development Siemens Power T&D, Inc. Electrical energy is the backbone of our society Page 2 Mar-07

More information

Long distance bulk transmission

Long distance bulk transmission Long distance bulk transmission Dr. Yanny Fu, KEMA Consulting 6 October 2010 Experience you can trust. 2 Contents Transmission technologies AC and DC Overhead lines and underground/submarine cables Transmission

More information

Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON

Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON 21, rue d Artois, F-75008 PARIS B4-70 CIGRE 2016 http : //www.cigre.org Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON VILES Consulting

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Review paper on Fault analysis and its Limiting Techniques.

Review paper on Fault analysis and its Limiting Techniques. Review paper on Fault analysis and its Limiting Techniques. Milap Akbari 1, Hemal Chavda 2, Jay Chitroda 3, Neha Kothadiya 4 Guided by: - Mr.Gaurang Patel 5 ( 1234 Parul Institute of Engineering &Technology,

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Reactive power support of smart distribution grids using optimal management of charging parking of PHEV

Reactive power support of smart distribution grids using optimal management of charging parking of PHEV Journal of Scientific Research and Development 2 (3): 210-215, 2015 Available online at www.jsrad.org ISSN 1115-7569 2015 JSRAD Reactive power support of smart distribution grids using optimal management

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS Investigate Feasibility of Converting or Upgrading Existing LCC to VSC Two Scenarios Considered

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 100 CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 6.1 INTRODUCTION Conventional energy resources are not sufficient to meet the increasing electrical power demand. The usages of

More information

HVDC Multi-Terminal Interconnections a viable and optimal solution for India

HVDC Multi-Terminal Interconnections a viable and optimal solution for India Presented at Cigré 2000 Conference, Paris, France, Aug/Sept 2000 HVDC Multi-Terminal Interconnections a viable and optimal solution for India K.M.Saxena Dr. Channakeshava Mata Prasad* Dr.R.P.Bhatele Dr.

More information

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 01 July 2015 ISSN (online): 2349-784X Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC Ravindra Mohana

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal Gunnar Asplund HVDC R&D Manager Sweden Latest HVDC Light developments IEEE Montreal 2006-06-21 HVDC Light, continuous reactive power control HVDC static Q (p.u.) HVDC dynamic HVDC Light P (pu) BA PTPS

More information

Renewable and Distributed Energy Resource Technologies

Renewable and Distributed Energy Resource Technologies OCIECE EACJ5300/ELG7114i - 2013 Winter Term Renewable and Distributed Energy Resource Technologies Chapter 1 Power System Basics Instructor: Xiaoyu Wang, Assistant Professor Department of Electronics,

More information

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016 The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply Offshore Wind: Grid Connection & Technology Options Dietmar Retzmann 1 10-2011 E T PS S/Re Focus on CO 2 Reduction Green Energy Megacities Security of Supply 2 10-2011 E T PS S/Re 1 EWEA s 2030 Offshore

More information

Rural electrification using overhead HVDC transmission lines

Rural electrification using overhead HVDC transmission lines Rural electrification using overhead HVDC transmission lines Leon Chetty Nelson Ijumba HVDC Centre, University of KwaZulu-Natal, South Africa Abstract One of mankind s greatest modern challenges is poverty

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy. The Smart Way HVDC PLUS One Step Ahead Answers for energy. 2 HVDC PLUS Maximum power in the smallest space The customized solution for evolving energy markets Keeping the power flowing is part of our life

More information

HVDC-Flexible in China. Sep

HVDC-Flexible in China. Sep HVDC-Flexible in China Sep 2015 1 Content SGCC and CET Overview HVDC Flexible Technology Comparison of Conventional HVDC and Flexible HVDC Applications of Flexible HVDC Flexible HVDC in China Sep 2015

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani High Voltage Direct Current and Alternating Current Transmission Systems Conference at EPRI Palo Alto CA August 30 31 2011 Scope of VSC Based Technology in HVDC and FACTS Nari Hingorani HVDC and FACTS:

More information

Climate change drivers for a single and smart EU grid

Climate change drivers for a single and smart EU grid Climate change drivers for a single and smart EU grid Smart and Secure Transmission Grids to Realise US and EU Renewable Energy Potentials Keith Bell University of Strathclyde, Scotland Expected growth

More information

AIR CORE REACTORS. Phoenix Electric Corporation

AIR CORE REACTORS. Phoenix Electric Corporation AIR CORE REACTORS Phoenix Electric Corporation PHOENIX ELECTRIC CORPORATION designs and manufactures Dry Type Air Core Reactors for operation on systems rated through 800 kv. All reactors are custom designed

More information