GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016

Size: px
Start display at page:

Download "GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016"

Transcription

1 GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016 GENERAL What is Regional Express Rail (RER)? / How is electrification linked to RER? Metrolinx is helping to transform the way the region moves by building a seamless, convenient and integrated transit network across the Greater Toronto Hamilton Area. Over the next 10 years, the GO rail network will be expanded to enable up to 15-minute, electrified train service in core areas and an increase of four times the number of train trips on off-peak hours and twice the current number of trips during peak hours throughout the network. The electrification of the GO network is one component of RER. Electrification is being undertaken in parallel with other projects in order to build all the infrastructure needed to increase service and electrify the corridor. Where are track expansions planned for RER and when will they be built? What is Hydro One s role in the project/ process? Why can t other service providers like Toronto Hydro provide the power? Who will maintain the electrification infrastructure? Which corridors are being electrified first/what is the phasing plan for electrification? It should be noted that the GO Rail Network Electrification TPAP is not examining the impacts of track expansion. The specific impacts of track expansions along the corridors are currently being assessed as part of separate EA/ TPAP projects (e.g., Lakeshore East Rail Corridor Expansion (Guildwood to Pickering) EA, Lakeshore East Rail Corridor Expansion (Don River to Scarborough) EA, Barrie Rail Corridor Expansion Project, etc.) or will be assessed as part of future EA/TPAP studies. However, the conceptual electrification design will protect for future/planned tracks in order to allow enough space for the required OCS infrastructure that will be constructed. Electrification of the GO Transit Network requires electrical power to be supplied from Ontario s electrical system through Hydro One s existing high voltage grid via new connections to several new Traction Power Substations (TPS) required specifically for Electrification. The locations of these new facilities and associated high voltage connections is being coordinated with Hydro One. The electrified GO rail system needs to be supplied from a 230 kv transmission system to provide the greatest level of both reliability and efficiency. Other utilities (such as Toronto Hydro) do not provide the necessary transmission lines at these power voltages. Metrolinx will be hiring a contractor who will be responsible for Designing, Building and Maintaining the electrification infrastructure. Electrification is planned to take place over a 10 year timeframe; the phasing plan is a work in progress and will initially involve testing of rolling stock on a commissioning track.

2 EA PROCESS Why is Metrolinx completing another Environmental Assessment (EA)? What is involved in the EA/TPAP? How were the locations of the first public meetings determined? Environmental Assessments carried out under the Transit Project Assessment Project (TPAP) examine the potential effects to the environment where infrastructure is being proposed (e.g., increases or decreases to noise/vibration, effects on natural environmental features, etc.). The TPAP for the electrification of UP Express looked at the effects of electrification along the UP Express/Kitchener corridor. Whereas the GO Rail Network Electrification TPAP is examining the effects on all other corridors to be electrified. Starting in July 2015, Metrolinx commenced the pre-consultation phase of the Transit Project Assessment Process (TPAP) for Network Electrification. The TPAP is an expedited Environmental Assessment (EA) process involving a preconsultation phase (no regulated timeline) followed by a regulated (up to 120-day) TPAP Phase. As part of this process, the technical and engineering work needs to be completed to support the TPAP, in addition to several environmental studies, and consultation with Review Agencies, Aboriginal communities, the public, and other stakeholders. The fifteen public meeting locations for the first round of public consultation were generally based on the proposed siting of the recommended traction power facilities along each corridor. The overall objective in locating the public meetings was to ensure sufficient geographic coverage and to provide convenient locations for attendees. All fifteen public meeting locations were accessible. In addition, for those who are unable to attend the meetings in person, the display materials have been posted online for comment at and metrolinxengage.com/en. Based on stakeholder feedback received during the first round of consultation, the public meeting venues will be reviewed and alternative locations may be recommended for the subsequent second round of consultation. PROJECT COSTS What will the new electric rolling stock be? How much will the new electric trains cost? MetrolinxW is currently in the process of determining which electric train will be used. There are two styles of electric trains under consideration. Electric Locomotive and dual level Electric Multiple Units (EMUs). The cost of the electric trains has yet to be determined.

3 PROJECT SCOPE What is the scope of the GO Rail Network Electrification TPAP? The scope of the GO Rail Network Electrification TPAP involves electrification of the following GO rail corridors: USRC From UP Express Union Station to Don Yard Layover (UP Express Union Station to Strachan Avenue was previously assessed/approved as part of the UP Express Electrification EA and is therefore not included in the EA Study Area). Lakeshore West Corridor From Strachan Ave to Burlington Kitchener Corridor From UP Express Spur (at Highway 427) to Bramalea (Strachan Avenue to UP Express spur (at Highway 427) was previously assessed/approved as part of the UP Express Electrification EA and is therefore not included in the EA Study Area) Lakeshore East Corridor From Don Yard Layover to Oshawa GO Station Barrie Corridor From Parkdale Junction (off Kitchener Corridor) to Allandale GO Station Stouffville Corridor From Scarborough Junction (off Lakeshore East Corridor) to Lincolnville GO Station Portions of the Richmond Hill Corridor are not currently owned by Metrolinx. In addition, this corridor presents engineering complexities for electrification infrastructure because part of the corridor being located within a floodplain. This needs to be resolved prior to electrification. Similarly, the Milton corridor, part of the Kitchener corridor, and part of the Lakeshore West corridor are not currently owned by Metrolinx. While these corridors are not being assessed as part of this TPAP, the electrical power supply for the GO network is being designed with future electrification of all corridors in mind. How does the project compare to global examples? There are a number of places in North America, Europe, Asia, Australia and Africa where electrified commuter railways of a much higher capacity have been in service for a number of years. In Canada, a similar railway system exists and was built to serve the Montreal area Deux Montagnes. In the United States, a comparable example of an electrified rail system is the North East Corridor (New Jersey), Metra Electric Commuter Rail (Chicago), Metro North (Connecticut), Southeastern Pennsylvania Transportation Authority (Philadelphia), Maryland Area Regional Commuter (Baltimore), Northern Indiana Commuter Transportation District (Northern Indiana), Regional Transportation District (Denver), and CALTRAIN (coming soon to San Francisco).

4 IMPACTS TO GO TRANSIT RIDERS How will my commute be affected by construction? As with any construction, there will be some effects to our service and customers. For example, there may be temporary slow orders during construction. However, we will stage the work to minimize impacts to customers. The impacts will be temporary in nature but will result in a more frequent, reliable service. HEALTH AND SAFETY How will the public be kept safe from the electrified infrastructure? Is there an increased risk of fire with electric trains? Why is grounding/ bonding required? Electrification wires are similar to utility (e.g., hydro) wires. Their installation will follow strict electrical safety codes and will be installed high off the ground similar to power lines across Ontario. In addition, bridge screening will be provided on all overhead bridges to protect pedestrians from electrification equipment. Grounding and bonding will be put in place and tested regularly to ensure there are no safety risks. A properly installed and maintained electric service is no more of a risk for fire than a diesel service. Like your home, anything that requires electricity to operate requires bonding and grounding for safety. Electric trains are no different. Grounding is a safety measure used to help prevent people from accidentally coming in contact with electrical hazards. Think of a refrigerator. It is a metal box standing on rubber feet with electricity running in and out of it. The electricity running from the outlet and through the power cord to the electrical components inside the refrigerator are electrically isolated from the metal exterior of the refrigerator. Similarly, the OCS wires will need to be connected to something that is in turn connected to the earth or ground outside to help prevent people from accidentally coming in contact with electrical hazards. Typically this connection is a grounding electrode, such as a ground rod. Are electric trains as safe as the current trains? What are the effects of electromagnetic interference (EMI) on the environment/ my health? Electric trains and diesel trains are equally safe. Numerous studies over many decades have been done to examine the effects of EMI/Electromagnetic Frequency (EMF) on the environment/health. In addition, the Network Electrification TPAP includes an EMI/EMF study to assess the background EMF levels along the rail corridors to document existing EMF and EMI conditions and to determine the potential effects of an electrified system. In addition, during detailed design, further analysis and measurements will be done once the electric rolling stock specifications are known in order to confirm the results and any mitigation measures that may be required.

5 ELECTRIFICATION INFRASTRUCTURE What is the purpose of a Traction Power Substation (TPS)? What is the purpose of a Paralleling Station (PS)? What is the purpose of a Switching Station? What is being done to enhance the visual/aesthetics of the new electrified system? The purpose of a traction power substation is to provide electricity from the existing Hydro One Network to the Overhead Contact System (OCS) along the rail corridor, which then power electric trains. A Traction Power Substation also transforms the supply voltage from 230 kv to 25 kv for distribution along the rail corridor. Paralleling Stations are required to prevent the power voltage from dropping below permissible levels along the rail corridor. Like breaker panels in your home, they feed smaller sections of the railroad. This way, if a breaker trips in one section, it doesn t turn off power to the whole system. Just like when a hairdryer trips a circuit in the bathroom, the whole house does not lose power. A Switching Station is a traction power facility equipped with the electrical equipment that allows for switching power between one power source and another. Switching stations are typically located between any two traction power substations to split the electrical sections. Visual impacts are being assessed as part of the EA. Recommended mitigation measures (where required) will be developed in the form of design guidelines for each type of visual impact that is identified during the EA. These guidelines may include: Placement recommendations such as setbacks from surrounding structures and land uses, avoidance of identified important vistas; Recommendations for screening techniques such as fencing and landscaping; and Recommendations related to materials and colours of infrastructure components. In addition, as part of detailed design, Metrolinx s Design Excellence Committee will be engaged to review the electrification facilities possible design/treatments to enhance aesthetics where possible. Mitigation measures such as screening options of the facilities (where required) may also be considered. Why can t electrification be achieved through third rail? Electrification via an Overhead Contact System (OCS) is a proven technology that is used around the world. One key reason that a third rail approach is not being used is due to safety considerations and the fact that the majority of the GO rail network is open track compared to a system like a subway that is contained and not easily accessed. Metrolinx operates through open areas and a third rail system requires a completely secure area. An electrified third rail would present a serious safety risk to people and animals who might inadvertently cross or touch the track.

6 CONSTRUCTION AND FACILITY SITING How were the electrification facility locations determined? Prior to initiating the Metrolinx GO Rail Network Electrification EA, the 2010 GO Transit Electrification Study was completed by Metrolinx to examine the power supply and power distribution requirements of the entire GO network. This comprehensive study examined the impact of different rail technologies and involved a review and comparison of the power supply and power distribution options to deliver electricity to a potential future electrified rail service. As part of this work, power simulation modelling was completed to determine the approximate geographic locations for siting the required traction power supply and distribution facilities for the electrified GO network. Building on this work, the traction power facilities for network electrification were identified as part of the EA process. There are several criteria that must be satisfied when identifying possible locations for traction power facilities: a) Proximity to high voltage: to ensure sufficient power load and to maintain high reliability of power supply, Traction Power Substations should be located as close as possible to existing Hydro One transformer stations/transmission lines, b) Proximity to rail right-of-way (ROW) - to maintain high reliability of the system, Traction Power Substations should be located as close as possible to the rail corridor, c) Traction Power Substations are spaced to maintain highest level of operational flexibility with the fewest number of facilities, d) Switching stations (SWS) are required between any two substations in order to split the electrical sections, e) Paralleling Stations are spaced to maintain sufficient power quality on the system (i.e., prevent power voltage from dropping), f) Locations must satisfy minimum size requirements for the specified facility type to accommodate the electrical equipment Once possible TPF sites are identified, a more detailed comparative evaluation will be carried out involving application of several environmental, land use/socio-economic, cultural heritage, property, and technical criteria. What are the primary construction impacts? Construction activities for electrification are anticipated to be as follows. a) OCS: installation of OCS foundations via excavation along the rail right-of-way (ROW), installation of OCS poles, installation of OCS wiring involving running the contact and messenger wires to occur concurrently with OCS structure foundation installation, install gantry foundations and gantries. b) Construction of traction power facilities which may include: Site clearing, Install building foundation, Install prepackaged equipment, construct building, install grounding and bonding. c) Duct bank installation involving: soil excavation; install duct banks, backfill soil/restore site. d) Bridge work including: OCS attachments to bridge structures, install flash plates where required, construct bridge barriers where required, modifications to achieve required vertical clearance.

7 OPERATION AND SERVICE Will the electrification of the GO system fail in snowstorms? Can the train system lose power during a brownout? An electrified system is designed to stay operational under most weather conditions. Rain and snow have little effect on the system. Heavy ice storms may affect the system if wires get coated with ice, preventing electrical connections from occurring. However, running trains will assist with clearing any ice that has formed on the wires and helps to reduce build-up. The Hydro One high-voltage network has a very high capacity as compared to the power and energy requirements of the GO Network Electrification. Coordination with Hydro One is being undertaken to ensure electrified GO service will not be interrupted or affected by any shortages in power. ELECTRIFICATION BENEFITS AND IMPACTS What are the main benefits of electrifying? What are the air quality benefits of electrifying the GO network? The main benefits of electrification are: Improved Service Reliability Reduced Travel Times Reduction in Greenhouse Gas (GHG) Emissions Improved Air Quality The only GHG emissions produced by electric trains are the emissions created through the generation of electricity that powers them. As noted in the 2010 Electrification Study, it is predicted that there would be a 94% reduction in emissions from the operation of GO Transit electric trains. Likewise, electric trains do not emit Critical Air Contaminants (CAC). It is also important to note that there are predicted air quality and GHG emission benefits resulting from reductions in indirect emissions from personal automobiles. As the improvement of the service will likely increase GO transit ridership, personal vehicle trips may be reduced, resulting in potentially fewer total emissions from automobiles. An air quality study is being carried out as part of the GO Rail Network Electrification TPAP that will consider the overall air quality benefits of electrifying the GO network. Are electric trains faster than diesel trains? Are electric trains quieter than diesel trains? Electric trains accelerate faster than diesel trains, allowing electric trains to run a rail corridor faster. Maximum speeds on the corridors are dictated by many things like track geometry, signal systems, overhead bridge clearances etc. Like highways, rail corridors have speed limits as well. Both diesel and electric trains can operate at speeds over 100 mph (160 km/h), however once trains start reaching high speed rail speeds (over 150 mph/241 km/h) electric trains are more common practice Yes, without an internal combustor engine onboard electric trains are noticeably quieter. Think of the difference between an electric car and gas powered car. There will still be noise from the wheel/train regardless of diesel/electric trains.

GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT

GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT ASSESSMENT PROCESS Public Meeting Round #3 June July 2017 What We ve Done - Electrification 15 public meetings held as part of Consultation Round #1 - February/March

More information

Metrolinx Electrification Project

Metrolinx Electrification Project GO Rail Network Electrification TPAP REVIEW OF PARSONS PROPOSAL TO UPGRADE TRACK CIRCUITS Final Noise/Vibration Modelling Report Lakeshore East Corridor For Prepared by: Reviewed by: Gannett Fleming Project

More information

CREATING CONNECTIONS IN WATERLOO REGION

CREATING CONNECTIONS IN WATERLOO REGION CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX

More information

Appendix 6. Electrification Systems Technology Assessment. December 2010

Appendix 6. Electrification Systems Technology Assessment. December 2010 Appendix 6 Electrification Systems Technology Assessment December 2010 APPENDIX 6 Electrification Systems Technology Assessment December 2010 Prepared for: Prepared by: 20 Bay Street, Suite 901 Toronto

More information

Appendix 10. Implementation of Electrification Options. December 2010

Appendix 10. Implementation of Electrification Options. December 2010 Appendix 10 Implementation of Electrification Options December 2010 APPENDIX 10 Implementation of Electrification Options December 2010 Prepared for: Prepared by: 20 Bay Street, Suite 901 Toronto ON M5J

More information

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK

More information

CONNECTING THE REGION

CONNECTING THE REGION CONNECTING THE REGION MARY PROC, VICE PRESIDENT, CUSTOMER SERVICE DELIVERY, METROLINX NATIONAL RAILWAY DAY NOVEMBER 7, 2017 OUR NEW CEO PHIL VERSTER I am very excited about joining the team of dedicated

More information

CREATING CONNECTIONS IN THE CITY OF WATERLOO

CREATING CONNECTIONS IN THE CITY OF WATERLOO CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO

More information

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee. Presentation on Behalf of the Major Mackenzie & 48 Land Owners Group 1 Stouffville Corridor Rail Service Expansion Class Environmental Assessment City of Markham Development Services Committee 10 September

More information

PROJECT BACKGROUND 3

PROJECT BACKGROUND 3 AGENDA 1. Welcome & Introductions 2. Project Background 3. Project Approach & Schedule 4. Draft Long List of Options 5. Evaluation Process 6. Next Steps 2 PROJECT BACKGROUND 3 OUR RAPID TRANSIT NETWORK

More information

Metrolinx Electrification Project

Metrolinx Electrification Project Final Electromagnetic REVIEW OF PARSONS Interference/Electromagnetic PROPOSAL TO UPGRADE TRACK CIRCUITS Fields Baseline Conditions Report For Prepared by: Insert TUV Logo Reviewed by: Gannett Fleming Project

More information

CONNECTING THE REGION

CONNECTING THE REGION CONNECTING THE REGION GERRY CHAPUT VICE PRESIDENT, RAPID TRANSIT, METROLINX VALUE ANALYSIS CANADA SUMMIT KEYNOTE OCTOBER 16, 2017 Metrolinx was created in 2006 by the Province of Ontario to improve the

More information

Developing Toronto s Transit Network Plan to 2031

Developing Toronto s Transit Network Plan to 2031 RE:EX16.1 Developing Toronto s Transit Network Plan to 2031 Executive Committee Meeting June 28, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration

More information

CREATING CONNECTIONS IN THE CITY OF KITCHENER

CREATING CONNECTIONS IN THE CITY OF KITCHENER CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016 Developing Toronto s Transit Network Plan to 2031 Public Information Meeting June 21, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration options

More information

CREATING CONNECTIONS IN EAST GWILLIMBURY

CREATING CONNECTIONS IN EAST GWILLIMBURY CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK

More information

Scarborough Transit Planning

Scarborough Transit Planning Scarborough Transit Planning April 23, 2016 Transportation Planning Section City Planning Division Overview 1. Developing Toronto s Transit Network Plan 2. Scarborough Transit Planning 1. Minutes of last

More information

PROJECTS $500K AND OVER FOR 2012

PROJECTS $500K AND OVER FOR 2012 EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)

More information

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding 2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding By George Ardavanis, PhD Keywords: overhead catenary system (OCS), electric multiple unit (EMU), grounding and bonding (G&B), overhead contact line (OCL),

More information

CREATING CONNECTIONS IN RICHMOND HILL

CREATING CONNECTIONS IN RICHMOND HILL CREATING CONNECTIONS IN RICHMOND HILL Mohamed Alkoka, Director, Corridor Infrastructure Metrolinx Anthony Irving, Manager, Community Relations Metrolinx May 15, 2017 1 GRIDLOCK COSTS OUR ECONONY Residents

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015 Development Services Committee June 23, 2015 Building Markham s Future Together Transit Update Presentation: 1. Overview of Metrolinx 2. The Big Move 3. Projects Update 4. Investment Strategy 5. Next Steps

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information

Developing Toronto's Transit Network Plan: Phase 1

Developing Toronto's Transit Network Plan: Phase 1 EX13.3 STAFF REPORT ACTION REQUIRED Developing Toronto's Transit Network Plan: Phase 1 Date: March 3, 2016 To: From: Wards: Executive Committee City Manager, Deputy City Manager, Cluster B and Chief Planner

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

The Preferred Alternative: a Vision for Growth on the Northeast Corridor

The Preferred Alternative: a Vision for Growth on the Northeast Corridor A Long-Term Vision is Needed The Preferred Alternative: a Vision for Growth on the Northeast Corridor The Federal Railroad Administration (FRA) has released the Tier 1 Final Environmental Impact Statement

More information

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016 Metrolinx: Transforming the Way We Move - A Network Wide Approach Greg Percy, Chief Operating Officer November 1, 2016 2 Greater Toronto & Hamilton Area Total Population in the GTHA Total Population 2001-2041

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

CREATING CONNECTIONS IN AURORA

CREATING CONNECTIONS IN AURORA CREATING CONNECTIONS IN AURORA NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX MARCH 28, 2017 GRIDLOCK COSTS OUR ECONONY

More information

GO Transit s deliverable: the 2020 Service Plan

GO Transit s deliverable: the 2020 Service Plan GO Transit s deliverable: the 2020 Service Plan GO Transit s 2020 Service Plan describes GO s commitment to customers, existing and new, to provide a dramatically expanded interregional transit option

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

GO RER INITIAL BUSINESS CASE SUMMARY

GO RER INITIAL BUSINESS CASE SUMMARY GO RER INITIAL BUSINESS CASE SUMMARY 2015 GO RER INITIAL BUSINESS CASE SUMMARY 2015 2 TABLE OF CONTENTS 1. Ready, Set, GO 1.1 Building on success 1 1.2 Fixing the GTHA s transportation problem 2 1.3 RER

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

CPG is pleased to report the following accomplishments this quarter:

CPG is pleased to report the following accomplishments this quarter: MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Electric Multiple Unit Procurement Update

Electric Multiple Unit Procurement Update Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

TRANSFORMING THE WAY OUR REGION MOVES

TRANSFORMING THE WAY OUR REGION MOVES TRANSFORMING THE WAY OUR REGION MOVES Judy Pfeifer, Chief Communications and Public Affairs Officer Gord Troughton, Director, Corridor Infrastructure Chris Burke, Director, Service Planning GRIDLOCK COSTS

More information

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street

More information

Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013

Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013 Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013 2013, All Rights Reserved. 1 The Maricopa Association of Governments (MAG) is the designated metropolitan planning organization

More information

Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University

Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University Shift: The City of London s Rapid Transit Proposal Shift: The City of London s Rapid Transit Proposal

More information

The City of Toronto s Transportation Strategy July 2007

The City of Toronto s Transportation Strategy July 2007 The City of Toronto s Transportation Strategy July 2007 Presentation Outline Transportation Statistics Transportation Building Blocks Toronto s Official Plan Transportation and City Building Vision Projects

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions SYSTEM INTEGRATION Railway and urban transport electrification Energy-efficient and reliable solutions 2 R A I LWAY & U R B A N T R A N S P O R T E L E C T R I F I C AT I O N S O L U T I O N S ABB s substation

More information

Mr. Vince Mauceri General Manager Transportation Operations and Technology

Mr. Vince Mauceri General Manager Transportation Operations and Technology Mr. Vince Mauceri General Manager Transportation Operations and Technology METROLINX OVERVIEW AND MANDATE Established in 2006 to address the significant transportation challenges in the Greater Toronto

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

Peninsula Corridor Electrification Update Meeting

Peninsula Corridor Electrification Update Meeting Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

Staff Contact: Carlos de Melo, Community Development Director, (650)

Staff Contact: Carlos de Melo, Community Development Director, (650) Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

Public Information Session June 2, Transportation Planning Section City Planning Division Toronto Transit Commission

Public Information Session June 2, Transportation Planning Section City Planning Division Toronto Transit Commission Coordinated Transit Planning in Toronto SmartTrack/GO RER Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session June 2, 2016 Transportation

More information

Caltrain Modernization EMU Procurement

Caltrain Modernization EMU Procurement Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

Welcome to Open House #5 Scarborough Rapid Transit

Welcome to Open House #5 Scarborough Rapid Transit Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details

More information

What is the Peninsula Corridor Electrification Project (PCEP)?

What is the Peninsula Corridor Electrification Project (PCEP)? What is the Peninsula Corridor Electrification Project (PCEP)? Project Purpose and Need Improve Train Performance Increase Service and Ridership Increase Revenue and Reduce Cost Reduce Environmental Impacts

More information

RELEASED UNDER THE OFFICIAL INFORMATION ACT 1982

RELEASED UNDER THE OFFICIAL INFORMATION ACT 1982 Subject MINISTERIAL BRIEFING NOTE Rapid Transit in Auckland Date 1 November 2017 Briefing number BRI-1133 Contact(s) for telephone discussion (if required) Name Position Direct line Cell phone 1 st contact

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the EMU, DMU and DMU double deck (DMU dd) analysis Including: Description

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

INTEGRATED GO RER- SMARTTRACK OPTIONS

INTEGRATED GO RER- SMARTTRACK OPTIONS APPENDIX 3 INTEGRATED GO RER- SMARTTRACK OPTIONS INITIAL BUSINESS CASE JUNE 2016 Table of Contents Page 1 TABLE OF CONTENTS 1.0 Executive Summary... 4 2.0 Introduction... 10 3.0 Methodology... 12 4.0 Options

More information

Community Advisory Committee. October 5, 2015

Community Advisory Committee. October 5, 2015 Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Recommended Vision for the Downtown Rapid Transit Network

Recommended Vision for the Downtown Rapid Transit Network Recommended Vision for the Downtown Rapid Transit Network April 2008 Presentation Overview Context Transit options Assessment of options Recommended network Building the network 2 1 Rapid Our Vision Reliable

More information

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

JCP&L Verbatim Response to Middletown Township s Questions

JCP&L Verbatim Response to Middletown Township s Questions JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses

More information

5 New GO Stations in York Region to Support Regional Express Rail

5 New GO Stations in York Region to Support Regional Express Rail Clause 5 in Report No. 14 of Committee of the Whole was adopted by the Council of The Regional Municipality of York at its meeting held on October 20, 2016 with the following additional recommendation:

More information

2013/2014 Strategic Priorities Fund Application Overview

2013/2014 Strategic Priorities Fund Application Overview 2013/2014 Strategic Priorities Fund Application Overview Bob Paddon, Executive Vice President Strategic Planning and Public Affairs TransLink 3 December 2013 Strategic Priorities Fund Application Context

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

THE WAY WE MOVE LRT FOR EVERYONE

THE WAY WE MOVE LRT FOR EVERYONE THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the, and double deck ( dd) analysis Including: Description of the Vehicles

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to

Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to March 14, 2013 1 Online Consultation Overview Online Consultation

More information

CONNECTING THE REGION

CONNECTING THE REGION CONNECTING THE REGION JUDY PFEIFER CHIEF COMMUNICATIONS & PUBLIC AFFAIRS OFFICER LESLIE WOO CHIEF PLANNING OFFICER, PLANNING & POLICY PRESENTED AT AMO INSIGHT BREAKFAST SESSION AUGUST 14, 2017 7:15AM 8:15AM

More information

Denver Metro Association of Realtors

Denver Metro Association of Realtors Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Panel Discussion: Planning for Today and Tomorrow

Panel Discussion: Planning for Today and Tomorrow Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO David Short, Power System Assessments, IESO Ahmed Maria, Senior Manager,

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California

More information

The Screening and Selection of Regionally Significant Projects

The Screening and Selection of Regionally Significant Projects The Screening and Selection of Regionally Significant Projects UTC 2018 Seminar Series March 15, 2018 Claire Bozic Martin Menninger ON TO 2050 CMAP is the Region s MPO, seven county region Land use and

More information

TECHNICAL WHITE PAPER

TECHNICAL WHITE PAPER TECHNICAL WHITE PAPER Chargers Integral to PHEV Success 1. ABSTRACT... 2 2. PLUG-IN HYBRIDS DEFINED... 2 3. PLUG-IN HYBRIDS GAIN MOMENTUM... 2 4. EARLY DELTA-Q SUPPORT FOR PHEV DEVELOPMENT... 2 5. PLUG-IN

More information

Mountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012

Mountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012 Mountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012 PLANNING FOR OUR FUTURE Planners with the Mountainland Association of Governments (MAG) have evaluated

More information

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION REFRIGERATION UNITS AND MAINTENANCE SHOPS. CHAPTER FIVE railyards

More information

Public Information Centre

Public Information Centre Junction Street Wastewater Pumping Station & Forcemain Schedule B Municipal Class Environmental Assessment Study Public Information Centre June 28, 2017. 6:00 to 8:00 pm. The Burlington Performing Arts

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED nsert TTC logo here STAFF REPORT ACTION REQUIRED Gap Between Subway Trains and Platforms Date: November 13, 2017 To: From: TTC Board Chief Executive Officer Summary This report is in response to an October

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015

East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 1 East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 Today s Agenda Safety Eagle P3 Project Commuter rail vehicle East Rail Line Economic impacts DBE/SBE/WIN status Progress

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

New McNicoll Bus Garage Public Open House

New McNicoll Bus Garage Public Open House New McNicoll Bus Garage Public Open House Kennedy Public School 1 The Need for a New Bus Garage Riders Increased ridership means Buses Need for new buses Garage And a new buses facility Problems Garages

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information