1 CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO WATERLOO COMMITTEE OF THE WHOLE SEPTEMBER
2 CONGESTION COSTS OUR ECONOMY Residents could spend 109 minutes per day in traffic
3 GO EXPANSION PROGRAM
4 METROLINX: REGION BUILDER PLAN BUILD OPERATE 4
5 KITCHENER LINE OVERVIEW 101 km, Union to Kitchener 79% Metrolinx owned GO Train service began in stations, potentially increasing to 16 Connections with Grand River Transit, Guelph Transit, Brampton Transit, MiWay, TTC & UP Express TODAY 5 million annual boardings 85 rush hour trips per week 65 midday trips per week; no evening or weekend trips Diesel service WITH RER* 18 million annual boardings ~4 times the rush hour trips Hundreds of new midday, evening & weekend trips Electric or mixed electric & diesel** service * - Figures subject to refinement as they do not reflect 2016 expansion of scope ** - Electrification of all GO services is target; conditional on completion of freight bypass 5
6 KITCHENER GO RAIL SERVICE Kitchener GO Train service has doubled 2011 TODAY
7 KITCHENER GO BUS SERVICE 2016: Three new bus routes including express service from Kitchener with timed connections to and from trains at Bramalea GO station providing all-day two-way service Monday to Friday. MORE GO IN WATERLOO REGION 7
8 RAIL INFRASTRUCTURE IN KITCHENER/WATERLOO 8
9 KITCHENER CORRIDOR PROGRAM OVERVIEW Infrastructure Build: Additional track from Union Station to Mt. Pleasant GO Station New stations: Liberty Village, St. Clair West, Mount Dennis, and Breslau Station modifications/parking expansion Hwy 401/409 Rail Tunnel Strachan Avenue Grade Separation Signal improvements Bridge structure modifications Layovers at Georgetown, Shirley Avenue, Heritage Road Improved rail crossings West Toronto Railpath Extension Customer experience improvements 9
10 NEW FREIGHT BYPASS 10
11 BUILDING A NEW CORRIDOR Building a new corridor is complex and as outlined in initial feasibility work will require: Up to 35 new bridges for road and water crossings including significant crossings of 401, 410 Modification and/or relocation of up to 17 hydro towers and as much as 3.4 km of major gas line relocations Construction of 60 km of new track, new train signal system Construction of a new rail/rail grade separation where Kitchener line will cross the bypass corridor Noise and vibration mitigation as required for adjacent properties Property impacts Next Steps: Continue negotiations with CN, to progress from the Agreement in Principle (AiP) to a full agreement Initiate an Environmental Assessment (EA), including public and stakeholder engagement Continue planning and design to identify route alignment and address potential concerns. 11
12 ELECTRIFICATION Metrolinx can only proceed with electrification on owned corridors Electrification requires traction power substations, switching stations, paralleling stations, overhead contact systems, and various safety modifications EA underway now to plan and design the required infrastructure for electric service on the Kitchener line between Bramalea and Highway 427 in Toronto. This EA is on track to be complete by the end of 2017 The Kitchener line west of Bramalea can be electrified only once the new freight bypass is built 12
13 NEW TRACK & NEW STATIONS 13
14 NEW TRACK AND NEW STATIONS New Track Kitchener Corridor An additional track from Union Station to Mt. Pleasant GO Station to support 15-minute service between Union and Bramalea GO Station 30 km freight bypass between Bramalea and Milton (30 km x 2 tracks) 2 nd 52 km track between Georgetown and Kitchener New Stations Liberty Village St. Clair West Mount Dennis Breslau 14
15 BRESLAU GO STATION Plans for a new station at Breslau near Greenhouse Rd. Identified in a previous EA. Good opportunity to attract new riders from a wide catchment Will support adjacent transitoriented development Will provide limited impact to existing passengers Township of Woolwich plans an EA for a grade separation. Working with Waterloo Region staff and Township staff as we advance the station design 15
16 KING-VICTORIA TRANSIT HUB Working with Waterloo Region on its King-Victoria Transit Hub project Kitchener GO station will shift west to co-locate with the ION LRT, Grand River Transit, and VIA services Details of GO Bus and Rail facilities, including walking and cycling access, are in development with the Region MORE GO IN WATERLOO REGION 16
17 WATERLOO ION LRT/GO BUS CONNECTION Creating connections with Waterloo ION LRT. Project led by Waterloo Region, Metrolinx has been asked to contribute funding for 3 bus bays and 2 bus layover spaces at the University of Waterloo LRT stop. Working with Waterloo Region on funding arrangement and updated work schedule. MORE GO IN WATERLOO REGION 17
18 SHIRLEY AVENUE TRAIN LAYOVER Shirley Avenue Train Layover complete and fully operational Used to store trains overnight for efficient deployment during morning commute MORE GO IN WATERLOO REGION 18
19 KITCHENER GO BUS FACILITY Scope Indoor storage for 20 buses Can accommodate both singleand double-decker buses Indoor fuelling lane and equipment, underground tank system Indoor bus wash bay Admin and staff support areas Milestone Schedule Design Completion October 2015 Procurement Construction November 2015-March 2016 April 2016-February 2018 In-Service February 2018 MORE GO IN WATERLOO REGION 19
20 NOISE Noise is a key concern among residents in communities throughout the network Metrolinx will work with the City of Waterloo on modelling proposed areas of noise mitigation That work will commence during the EA for the freight bypass 20
21 COMMUNITY ENGAGEMENT 21
22 COMMUNITY ENGAGEMENT April : MPP Daiene Vernile s transit townhall update on RER projects in KW April : Mx Board Member Carl Zehr presentation to Rotary Club of Kitchener Moving forward: Planning on-the-ground engagement in post-secondary institutions in Waterloo Region and the University of Guelph. Community Relations Specialist for Kitchener corridor: Laura Durie Laura.Durie@metrolinx.com
23 HOW WE ARE GOING TO WORK WITH YOU Metrolinx recognizes that with new infrastructure and construction comes impacts to the community that must be worked through with residents and their elected officials. A regional Municipal and Community regional tour is currently underway that creates an annual schedule for getting to every municipal council and for providing a comprehensive narrative for residents of each municipality that details what this program will look like locally. We are working with municipal partners to schedule local consultations on new stations We are developing a community charter which will commit the organization to building the regional transportation system in a way that is respectful of the communities it touches. This is in addition to the standard community relations support that we have traditionally provided on the ground on projects like Georgetown South and the Eglinton Crosstown. 23
24 COMMUNITY ENGAGEMENT: PROJECT CYCLE Introduce the project to municipal partners & community and ask for initial feedback Formal consultation period included in the TPAP Work with residents to establish why the project is needed and proposed approach Planning & Feasibility Environmental Assessment (only applies to new infrastructure ) Construction Design & Procurement Focus on minimizing impact to residents, keeping the community informed and managing/being responsive to issues as they arise. Work with municipal partners/community to inform the details of the project, address design concerns and build momentum. 24
25
26 REQUIREMENTS FOR THE BYPASS CORRIDOR Preliminary planning and design work is underway at the same time negotiations with CN move forward. Remaining work cannot begin until an agreement is secured. Phases Technical and feasibility studies Planning studies Design studies Project Planning Community engagement Community impact and mitigation Environmental assessment Permit and approvals Durations (*some can be done in parallel) 2-3 years (approx.) 3 years (approx.) Procurement Construction Commissioning 4 years (approx.) Community impact and engagement Ongoing MORE GO IN WATERLOO REGION 26
27 GO BUS SERVICES TO/FROM KITCHENER/WATERLOO GO Transit currently operates a number of express GO bus services connecting Kitchener/ Waterloo Region with the Greater Toronto Area. These include: Route 30: Kitchener Bramalea GO: an express service that operates all day Monday Friday, running between Downtown Kitchener and Bramalea GO station via Hwys 401/407. The service provides timed connections to/from Kitchener line GO train & bus services at Bramalea GO, which operate between Bramalea and Toronto s Union station during off-peak & counter-peak periods. (During peak periods, direct GO train service is available between Kitchener and Toronto s Union Station). Connections can also be made at Bramalea to other GO routes serving Brampton, York Region, York University and North York Route 25: U of Waterloo Mississauga - Express Services: Are provided daily, with additional express trips operated on Thursday s, Fridays, Saturday s and Sundays, connecting the University of Waterloo and Wilfred Laurier University with Mississauga s Square One Connections can be made at Square One to other GO bus routes serving various Toronto-area destinations such as Downtown Toronto, North York, Pearson Airport & the Airport Corporate Centre Area, Brampton, York Region and Hamilton. Daily local service is also provided between U of Waterloo and Mississauga Square One with stops at Wilfred Laurier University, Downtown Kitchener, Cambridge, Guelph, Milton and Western Mississauga. Route 25F: University of Waterloo York University Express: An express service that operates on Fridays & Sundays, between the University of Waterloo and York University via Hwy.407, with stops at Wilfred Laurier University, Hwy.407 & Hurontario Street in Mississauga, and Bramalea GO in Brampton. Connections to other GO routes can be made at Bramalea GO or York University, serving multiple destinations in York Region, Durham Region, North York, Scarborough as well as Downtown Toronto. MORE GO IN WATERLOO REGION 27
28 WATERLOO CUSTOMER BASE For Q1 2017/18, approximately 58,000 total weekday boardings originating in Waterloo, 14,000 on weekends Also in Q1, there were 6700 unique PRESTO customers with home stations (or bus stops) in Waterloo Majority of the PRESTO customers (96%) are infrequent riders making less than 10 trips per month PRESTO use is higher during the weekdays than the weekend primarily due to commuters The top origin stop in terms of boardings is the University of Waterloo stop on both weekdays (422 average daily boardings) and weekends (365 average daily boardings) The most common destinations are Square One, Union Station and Milton ~80% of trips are direct without transfers MORE GO IN WATERLOO REGION 28
CREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationCREATING CONNECTIONS IN THE CITY OF KITCHENER
CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION
More informationTRANSFORMING THE WAY OUR REGION MOVES
TRANSFORMING THE WAY OUR REGION MOVES Judy Pfeifer, Chief Communications and Public Affairs Officer Gord Troughton, Director, Corridor Infrastructure Chris Burke, Director, Service Planning GRIDLOCK COSTS
More informationCREATING CONNECTIONS IN THE TOWN OF NEWMARKET
CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK
More informationCREATING CONNECTIONS IN EAST GWILLIMBURY
CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK
More informationCREATING CONNECTIONS IN AURORA
CREATING CONNECTIONS IN AURORA NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX MARCH 28, 2017 GRIDLOCK COSTS OUR ECONONY
More informationCREATING CONNECTIONS IN RICHMOND HILL
CREATING CONNECTIONS IN RICHMOND HILL Mohamed Alkoka, Director, Corridor Infrastructure Metrolinx Anthony Irving, Manager, Community Relations Metrolinx May 15, 2017 1 GRIDLOCK COSTS OUR ECONONY Residents
More informationCONNECTING THE REGION
CONNECTING THE REGION GERRY CHAPUT VICE PRESIDENT, RAPID TRANSIT, METROLINX VALUE ANALYSIS CANADA SUMMIT KEYNOTE OCTOBER 16, 2017 Metrolinx was created in 2006 by the Province of Ontario to improve the
More informationScarborough Transit Planning
Scarborough Transit Planning April 23, 2016 Transportation Planning Section City Planning Division Overview 1. Developing Toronto s Transit Network Plan 2. Scarborough Transit Planning 1. Minutes of last
More informationGO Transit s deliverable: the 2020 Service Plan
GO Transit s deliverable: the 2020 Service Plan GO Transit s 2020 Service Plan describes GO s commitment to customers, existing and new, to provide a dramatically expanded interregional transit option
More informationDeveloping Toronto s Transit Network Plan to 2031
RE:EX16.1 Developing Toronto s Transit Network Plan to 2031 Executive Committee Meeting June 28, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration
More informationDeveloping Toronto s Transit Network Plan to Public Information Meeting June 21, 2016
Developing Toronto s Transit Network Plan to 2031 Public Information Meeting June 21, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration options
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationRegional Express Rail: Kipling Station Project Update. Ryah Kazman, Community Relations Specialist Metrolinx
Regional Express Rail: Kipling Station Project Update Ryah Kazman, Community Relations Specialist Metrolinx GRIDLOCK COSTS OUR ECONONY Residents could spend 109 minutes per day in traffic METROLINX PLAN
More informationThe Regional Transportation Plan PLAN BUILD OPERATE
WHO IS METROLINX? Metrolinx was created in 2006 by the Province of Ontario as the first Regional Transportation Agency for the Greater Toronto and Hamilton Area (GTHA). The Regional Transportation Plan
More informationCONNECTING THE REGION
CONNECTING THE REGION MARY PROC, VICE PRESIDENT, CUSTOMER SERVICE DELIVERY, METROLINX NATIONAL RAILWAY DAY NOVEMBER 7, 2017 OUR NEW CEO PHIL VERSTER I am very excited about joining the team of dedicated
More informationMetrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016
Metrolinx: Transforming the Way We Move - A Network Wide Approach Greg Percy, Chief Operating Officer November 1, 2016 2 Greater Toronto & Hamilton Area Total Population in the GTHA Total Population 2001-2041
More informationMr. Vince Mauceri General Manager Transportation Operations and Technology
Mr. Vince Mauceri General Manager Transportation Operations and Technology METROLINX OVERVIEW AND MANDATE Established in 2006 to address the significant transportation challenges in the Greater Toronto
More informationCONNECTING THE REGION
CONNECTING THE REGION JUDY PFEIFER CHIEF COMMUNICATIONS & PUBLIC AFFAIRS OFFICER LESLIE WOO CHIEF PLANNING OFFICER, PLANNING & POLICY PRESENTED AT AMO INSIGHT BREAKFAST SESSION AUGUST 14, 2017 7:15AM 8:15AM
More informationAttachment 5 Eglinton West LRT Planning and Technical Update
Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the
More informationDeveloping Toronto's Transit Network Plan: Phase 1
EX13.3 STAFF REPORT ACTION REQUIRED Developing Toronto's Transit Network Plan: Phase 1 Date: March 3, 2016 To: From: Wards: Executive Committee City Manager, Deputy City Manager, Cluster B and Chief Planner
More informationJourney to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015
Development Services Committee June 23, 2015 Building Markham s Future Together Transit Update Presentation: 1. Overview of Metrolinx 2. The Big Move 3. Projects Update 4. Investment Strategy 5. Next Steps
More information5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE
5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationGTA West Corridor Planning and EA Study Stage 1
GTA West Corridor Planning and EA Study Stage 1 Draft Development Strategy Presentation to Peel Goods Movement Task Force April 8 2011 Study Areas 2 Unique Approach Unprecedented two-stage EA process:
More informationThe City of Toronto s Transportation Strategy July 2007
The City of Toronto s Transportation Strategy July 2007 Presentation Outline Transportation Statistics Transportation Building Blocks Toronto s Official Plan Transportation and City Building Vision Projects
More informationYonge-Eglinton. Mobility Hub Profile. September 19, 2012 YONGE- EGLINTON
September 19, 2012 PEEL YORK HALTON DURHAM HAMILTON TORONTO YONGE- EGLINTON MOBILITY HUBS: places of connectivity between regional and rapid transit services, where different modes of transportation come
More informationMississauga Transit 2009 Budget
Mississauga Transit 2009 Budget Budget Committee Presentation December 2, 2008 Revenue Ridership Forecasted 2008 Total Rides Including transfers 11% growth in the last 24 months Transit Service Area Business
More informationPROJECT BACKGROUND 3
AGENDA 1. Welcome & Introductions 2. Project Background 3. Project Approach & Schedule 4. Draft Long List of Options 5. Evaluation Process 6. Next Steps 2 PROJECT BACKGROUND 3 OUR RAPID TRANSIT NETWORK
More informationYonge Relief Network Study (YRNS)
Yonge Relief Network Study (YRNS) Report for June 25 th Metrolinx Board Meeting Leslie Woo, Chief Planning Officer Anna Pace, Director, Project Planning and Development Summary of Yonge Relief Network
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationElected Officials Briefing North Metro Rail Line Update. November 10, 2016
Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April
More informationCITY of GUELPH Transit Growth Strategy and Plan, Mobility Services Review. ECO Committee
CITY of GUELPH Transit Growth Strategy and Plan, Mobility Services Review ECO Committee July 19, 2010 1 Study Purpose Vision and growth strategy for Guelph Transit, ensuring broad consultation Operational
More informationCPG is pleased to report the following accomplishments this quarter:
MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That
More informationGreen Line LRT: Beltline Segment Update April 19, 2017
Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street
More informationPROJECTS $500K AND OVER FOR 2012
EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)
More informationNew McNicoll Bus Garage Public Open House
New McNicoll Bus Garage Public Open House Kennedy Public School 1 The Need for a New Bus Garage Riders Increased ridership means Buses Need for new buses Garage And a new buses facility Problems Garages
More informationGO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT
GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT ASSESSMENT PROCESS Public Meeting Round #3 June July 2017 What We ve Done - Electrification 15 public meetings held as part of Consultation Round #1 - February/March
More information5 New GO Stations in York Region to Support Regional Express Rail
Clause 5 in Report No. 14 of Committee of the Whole was adopted by the Council of The Regional Municipality of York at its meeting held on October 20, 2016 with the following additional recommendation:
More informationWe Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:
We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationMETRO Light Rail Update
American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations
More informationPresentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.
Presentation on Behalf of the Major Mackenzie & 48 Land Owners Group 1 Stouffville Corridor Rail Service Expansion Class Environmental Assessment City of Markham Development Services Committee 10 September
More informationScarborough Subway Extension. Stakeholder Advisory Meeting February 28, 2017
Scarborough Subway Extension Stakeholder Advisory Meeting February 28, 2017 City Council Direction The Scarborough Subway Extension (SSE) project and budget were approved by City Council in 2013, prior
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationGO RER INITIAL BUSINESS CASE SUMMARY
GO RER INITIAL BUSINESS CASE SUMMARY 2015 GO RER INITIAL BUSINESS CASE SUMMARY 2015 2 TABLE OF CONTENTS 1. Ready, Set, GO 1.1 Building on success 1 1.2 Fixing the GTHA s transportation problem 2 1.3 RER
More informationACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010
ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010 Presentation Outline Context t of Mississauga i City Centre Implementing Paid Parking and TDM
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationEGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)
WELCOME TO OUR PUBLIC OPEN HOUSE EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) Preliminary Planning for a Transit Project Assessment Open House Martin Grove Road to Pearson International Airport September
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationMcNICOLL BUS GARAGE. Public Open House June 12, 2017 Mary Ward Catholic School
McNICOLL BUS GARAGE Public Open House June 12, 2017 Mary Ward Catholic School THE NEED FOR A NEW BUS GARAGE riders Increased ridership means buses Need for new buses garage And a new bus facility Garages
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationPublic Information Session June 2, Transportation Planning Section City Planning Division Toronto Transit Commission
Coordinated Transit Planning in Toronto SmartTrack/GO RER Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session June 2, 2016 Transportation
More informationEX29.1 REPORT FOR ACTION. SmartTrack Project Update and Next Steps SUMMARY
EX29.1 REPORT FOR ACTION SmartTrack Project Update and Next Steps Date: November 17, 2017 To: Executive Committee From: City Manager and Deputy City Manager, Cluster B Wards: All SUMMARY In July 2016,
More informationEGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) PLEASE SIGN IN
WELCOME TO OUR PUBLIC OPEN HOUSE EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) Preliminary Planning for a Transit Project Assessment June 15, 17, 18, 23, 24 and 25, 2009 PLEASE SIGN IN Members of the Project
More informationThe Engineering Department recommends Council receive this report for information.
CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision
More informationLAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006
LAX Specific Plan Amendment Study CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 Agenda Background on public planning process Regional planning update LAWA progress on settlement commitments
More informationOttawa LRT Stage 2. McKellar Park Information Session
Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville
More informationBUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN
APPENDIX 1 CITY OF MISSISSAUGA BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN Executive Summary McCORMICK RANKIN May 2003 Introduction This executive summary highlights the findings and
More information2.4 TRANSIT VISION 2040 FROM VISION TO ACTION. Support the revitalization of urban cores STRATEGIC DIRECTION
TRANSIT VISION 2040 FROM VISION TO ACTION TRANSIT VISION 2040 defines a future in which public transit maximizes its contribution to quality of life with benefits that support a vibrant and equitable society,
More informationBenchmarking, Planning, and Promoting Transit- Oriented Intensification in Rapid Transit Station Areas: Project Key Indicators March 2016
Benchmarking, Planning, and Promoting Transit- Oriented Intensification in Rapid Transit Station Areas: Project Key Indicators March 2016 This project was produced by MITL with support from the Government
More informationF.P.O. Yonge subway extension: concept plan and profile. Langstaff/Longbridge. Royal Orchard Station. Clark Station. Steeles Station.
Yonge subway extension: concept plan and profile Legend 407 Transitway preliminary routes under study Community connector Hydro corridor Existing GO parking Proposed Park & Ride R LONGB Thornhill Heritage
More informationRapid Transit Implementation Working Group #4 February 9, 2017
Rapid Transit Implementation Working Group #4 February 9, 2017 Agenda 1. Business Case Update 2. Rapid Transit Master Plan Overview 3. Corridor Concepts 4. Public Consultation Event 5. Schedule Outlook
More informationWhat We Heard Report - Metro Line NW LRT
What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: August 19, 2014 OPPORTUNITIES TO IMPROVE TRANSIT SERVICE IN TORONTO ACTION ITEM RECOMMENDATIONS It is recommended that the
More informationElected Officials Briefing. North Metro Rail Line Update. February 9, 2017
Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,
More informationAPPENDIX 6: Transportation Modelling Considerations City of Toronto, February 2014
APPENDIX 6: Transportation Modelling Considerations City of Toronto, February 2014 Transportation and Infrastructure The future of the elevated Gardiner Expressway east of Jarvis Street forms part of a
More informationWaterfront Transit Reset Phase 2 Study. Public Information & Consultation Meetings September 18 & 26, 2017
Waterfront Transit Reset Phase 2 Study Public Information & Consultation Meetings September 18 & 26, 2017 2 Agenda 6:00 Open House 6:30 Agenda Review, Opening Remarks and Introductions 6:40 Study Overview
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationGO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016
GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016 GENERAL What is Regional Express Rail (RER)? / How is electrification linked to RER? Metrolinx is helping to transform the way the region
More informationMadison BRT Transit Corridor Study Proposed BRT Operations Plans
Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is
More informationConverting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada
Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population
More informationUpdate on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:
Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017 Item 1, Report No. 41, of the Committee of the Whole (Working Session), which was adopted without amendment by the Council of the
More informationAppendix A-M Public Information Centre 4 Materials
Appendix A-M Public Information Centre 4 Materials NOTICE OF PUBLIC INFORMATION CENTRE #4 RAPID TRANSIT CORRIDORS MASTER PLAN ENVIRONMENTAL ASSESSMENT STUDY The City of London is entering a new chapter
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationFunctional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to
Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to March 14, 2013 1 Online Consultation Overview Online Consultation
More informationLate Starter. Tuesday, November 6, 2018
Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,
More informationINTEGRATED GO RER- SMARTTRACK OPTIONS
APPENDIX 3 INTEGRATED GO RER- SMARTTRACK OPTIONS INITIAL BUSINESS CASE JUNE 2016 Table of Contents Page 1 TABLE OF CONTENTS 1.0 Executive Summary... 4 2.0 Introduction... 10 3.0 Methodology... 12 4.0 Options
More informationExecutive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1
Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationV03. APTA Multimodal Operations Planning Workshop August Green Line LRT
V03 APTA Multimodal Operations Planning Workshop August 2016 Green Line LRT 2 Presentation Outline Past Present Future 3 16/03/2016 RouteAhead Update 4 4 16/03/2016 RouteAhead Update 5 5 16/03/2016 6 6
More informationThe ION Story. November 2015
The ION Story November 2015 Planning For The Future The Region of Waterloo has been planning for rapid transit for more than a decade ION will: Limit urban sprawl; ease traffic congestion Protect environmentally-sensitive
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationRELEASED UNDER THE OFFICIAL INFORMATION ACT 1982
Subject MINISTERIAL BRIEFING NOTE Rapid Transit in Auckland Date 1 November 2017 Briefing number BRI-1133 Contact(s) for telephone discussion (if required) Name Position Direct line Cell phone 1 st contact
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationLocation Concept Plan Amendment Recommendation Approved 2011 Concept Plan
Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West
More informationWELCOME TO OUR PUBLIC OPEN HOUSE Eglinton Crosstown Light Rail Transit (LRT)
WELCOME TO OUR PUBLIC OPEN HOUSE Eglinton Crosstown Light Rail Transit (LRT) Preliminary Planning for a Transit Project Assessment November 23 rd, 24 th, 25 th, 26 th & December 2 nd, 8 th, 10 th 2009
More informationCorporate Report. Report from Economic Development and Customer Service, Corporate Planning
Corporate Report Report from Economic Development and Customer Service, Corporate Planning Officer Date of Report: July 19, 2013 Date of Meeting: August 12, 2013 Report Number: EDCS-228-2013 File: 68.46.99
More informationKeeping Seattle Moving Seattle City Council February 2013
Keeping Seattle Moving Seattle City Council February 2013 Seattle City Council February 2013 1 Mobility Challenges Ahead Viaduct mitigation expires June 2014 Potential system-wide service cuts begin in
More information2.1 TRANSIT VISION 2040 FROM VISION TO ACTION. Expand regional rapid transit networks STRATEGIC DIRECTION
TRANSIT VISION 2040 FROM VISION TO ACTION TRANSIT VISION 2040 defines a future in which public transit maximizes its contribution to quality of life with benefits that support a vibrant and equitable society,
More informationEglinton East LRT Project Update and Next Steps
EX34.1 REPORT FOR ACTION Eglinton East LRT Project Update and Next Steps Date: May 7, 2018 To: Executive Committee From: Interim Deputy City Manager, Cluster B and Chief Planner and Executive Director,
More informationDS Discussion Paper. for the Next Regional Transportation Plan GREATER TORONTO AND HAMILTON AREA AUGUST 2016
DS-16-163 Discussion Paper for the Next Regional Transportation Plan GREATER TORONTO AND HAMILTON AREA AUGUST 2016 ABOUT METROLINX AND THE REGIONAL TRANSPORTATION PLAN As the regional transportation agency
More informationService and Operations Planning for Ottawa s New Light Rail Line Pat Scrimgeour
Service and Operations Planning for Ottawa s New Light Rail Line Pat Scrimgeour Manager, Transit Service Planning and Reporting OC Transpo Ottawa, Ontario Ottawa Light Rail Project 12.5 km, 13 stations
More informationMass Transit in Charlotte and San Antonio. Keith T. Parker, AICP
Mass Transit in Charlotte and San Antonio Keith T. Parker, AICP President/CEO Presentation Overview Charlotte Agency and Customer Profile San Antonio Agency and Customer Profile Attracting New Customers
More informationNewmarket GO Station Mobility Hub Study. Open House #1 MAY 18, 2017
Newmarket GO Station Mobility Hub Study Open House #1 Naren Garg Metrolinx Advisor, RER Project Planning Amy Shepherd IBI Group Associate, Manager, Planning INTRODUCTIONS - METROLINX Metrolinx is an agency
More informationTunney s Pasture Station Bus Loop and Lay-up Area Design
2017 Canadian Consulting Engineer Award Submission Tunney s Pasture Station Bus Loop and Lay-up Area Design Presented to: Canadian Consulting Engineer 80 Valleybrook Drive Toronto, Ontario M3B 2S9 April
More information10-Year Vision Update. Vancouver City Council May 2, 2017
1 10-Year Vision Update Vancouver City Council May 2, 2017 The 10-year Vision is our Regional Blueprint for Multimodal Transportation Investments Welcome 1 million more people and 500,000 more jobs in
More information