1 Scarborough Subway Extension Stakeholder Advisory Meeting February 28, 2017
2 City Council Direction The Scarborough Subway Extension (SSE) project and budget were approved by City Council in 2013, prior to an alignment or station concept being developed. In May, 2015, City Council directed staff to report back on a recommendation of whether to proceed with a Design-Build- Finance or a Design-Bid-Build approach to procurement of the SSE. In 2016, Council approved an express subway option to Scarborough Centre as part of a Scarborough transit network plan that also includes SmartTrack and an LRT on Eglinton Avenue East. Council directed staff to continue to develop an express subway option. 2
3 Summary of Report Recommendations This report recommends City Council: Approve the extension of Line 2 to Scarborough Centre via the McCowan alignment Approve the Triton bus terminal concept Authorize commencement of the Transit Project Assessment Process (TPAP) for the project Authorize the procurement of the SSE through a Design-Build procurement model, subject to: A satisfactory project procurement support agreement with Infrastructure Ontario Direction to Infrastructure Ontario from the Minister of Infrastructure to proceed with an agreement Request written confirmation of the sources of funding for the federal and provincial commitments to the SSE project 3
4 Express Alignments Evaluated 4
5 Alignment Evaluation Table Option Screening Assessment Cost Estimate ($B, YOE) 1. Brimley Underground, north/south alignment 2. Midland Elevated, east/west alignment Carried forward for further analysis: Evaluation is included in this updated IBC $2.945 Removed from consideration: Requires closure of SRT; cost savings not considered sufficient to justify impact to existing SRT customers $ Midland Elevated, east/west alignment, station further west Removed from consideration: Requires closure of SRT; inferior station location- i.e., further from centroid of existing and future customers; cost savings not considered sufficient to justify inferior station location and impact to existing SRT customers $ Midland Underground, east/west alignment 5. Midland Underground, east/west alignment, station further west 6. McCowan Underground, north/south alignment (previously preferred) 7. SRT Corridor Express subway to Scarborough Centre via SRT corridor (2.2km portion at-grade), with elevated east-west alignment into Scarborough Centre Removed from consideration: Requires closure of SRT; cost savings not considered sufficient to justify impact to existing SRT customers Removed from consideration: This option is approximately the same cost as the preferred McCowan alignment but has an inferior station location, i.e., further from centroid of existing and future customers Carried forward for further analysis: Evaluation is included in update to IBC $3.129 $3.316 $3.159; $3.346 with Triton bus terminal concept Removed from consideration: Requires closure of SRT $2.966 Notes: SSE cost estimates prepared by the TTC. Estimates include cost to construct. Costs do not include costs for project delivery, management reserve or risk allowances. These costs are reflected in the staff report to the Executive Committee. Costs do not include lifecycle and operations/maintenance. Costs have been escalated based on the preliminary schedule. The schedule reflects in service by Q2 2026, with construction taking approximately 6 years ( ). Schedule based 5 on March 2017 approval to proceed. Cost estimates have been developed at approximately 5% design and are a Class 4 cost estimate (per AACE guidelines).
6 Recommended Alignment McCowan alignment is strongly preferred due to placement of station: Focal point of Scarborough Centre is on McCowan Road Development potential largely on the east side of McCowan Brimley alignment is not recommended It would fail to achieve project s main objective to transform Scarborough Centre into a vibrant urban node because the station would be far from current and future destinations Limited development potential on the western edge of Scarborough Centre due to proximity to heavy industrial uses Brimley alignment would be approximately $214M less than the base McCowan At-grade alignment Brimley cost savings largely due to lack of constraints on station site and a shorter alignment; station would be located in green field. 6
7 Alignment Map 7
8 Scarborough Centre Station Location 8
9 Bus Terminals At-Grade Concept Triton 9 Concept
10 Recommended Bus Terminal Concept Staff recommend the Triton Terminal concept as it best achieves project objectives of developing Scarborough Centre into a vibrant urban node Preserves development potential and would not preclude a future urban street network consistent with the vision for Scarborough Centre This concept would see bus bays stacked on two levels, within the vicinity of Triton Road The Triton concept adds approx. $187M (YOE$) to the McCowan At-grade construction cost estimate TTC is proceeding with further design refinement on this option 10
11 Vision for Scarborough Centre Development shown is conceptual and for illustration only. 11
12 Vision for Scarborough Centre Development shown is conceptual and for illustration only. 12
13 Recommended Procurement Approach The TTC and the City are recommending a Design-Build or Design-Build-Finance (DBF) approach, subject to reaching a satisfactory agreement with Infrastructure Ontario The design-build model would minimize conflicts between designer and contractor, thereby reducing risk, and if added, the financing element would motivate the contractor to finish on schedule The TTC and the City do not have expertise to support a DBF delivery without the support of IO If a satisfactory agreement with IO cannot be reached, TTC and the City recommend pursuing a Design-Bid-Build procurement, based on a single construction contract 13
14 Updated Capital Cost Estimate This report recommends approval of the Triton bus terminal concept, which adds $187M to the Class 4 cost estimate for the McCowan At-grade alignment Table 1 - Breakdown of Update to Construction Cost Estimate ($Billions YOE) Category/Source Description Incremental Cost Impact Sub- Total/Total June, 2016 Business Case Estimate for McCowan alignment with At-Grade Bus Terminal at SC Triton Bus Terminal at SC Updated Class 4 cost estimate
15 Next Steps
16 Next Steps Initiate TPAP process Undertake an OPA Continue design work on the McCowan alignment and Triton bus terminal concept Finalize an agreement with Infrastructure Ontario Finalize intergovernmental agreements 16
17 Questions?
Developing Toronto s Transit Network Plan to 2031
RE:EX16.1 Developing Toronto s Transit Network Plan to 2031 Executive Committee Meeting June 28, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration
More informationDeveloping Toronto s Transit Network Plan to Public Information Meeting June 21, 2016
Developing Toronto s Transit Network Plan to 2031 Public Information Meeting June 21, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration options
More informationScarborough Transit Planning
Scarborough Transit Planning April 23, 2016 Transportation Planning Section City Planning Division Overview 1. Developing Toronto s Transit Network Plan 2. Scarborough Transit Planning 1. Minutes of last
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the
More informationForm Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse
More informationRapid Transit Implementation Working Group #4 February 9, 2017
Rapid Transit Implementation Working Group #4 February 9, 2017 Agenda 1. Business Case Update 2. Rapid Transit Master Plan Overview 3. Corridor Concepts 4. Public Consultation Event 5. Schedule Outlook
More informationPublic Information Session June 2, Transportation Planning Section City Planning Division Toronto Transit Commission
Coordinated Transit Planning in Toronto SmartTrack/GO RER Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session June 2, 2016 Transportation
More informationDeveloping Toronto's Transit Network Plan: Phase 1
EX13.3 STAFF REPORT ACTION REQUIRED Developing Toronto's Transit Network Plan: Phase 1 Date: March 3, 2016 To: From: Wards: Executive Committee City Manager, Deputy City Manager, Cluster B and Chief Planner
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationAttachment 5 Eglinton West LRT Planning and Technical Update
Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to
More informationJourney to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015
Development Services Committee June 23, 2015 Building Markham s Future Together Transit Update Presentation: 1. Overview of Metrolinx 2. The Big Move 3. Projects Update 4. Investment Strategy 5. Next Steps
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: MAY 6, 2010 SUBJECT: SCARBOROUGH RAPID TRANSIT TRANSIT PROJECT ASSESSMENT STUDY RECOMMENDATIONS ACTION ITEM RECOMMENDATION
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationEglinton East LRT Project Update and Next Steps
EX34.1 REPORT FOR ACTION Eglinton East LRT Project Update and Next Steps Date: May 7, 2018 To: Executive Committee From: Interim Deputy City Manager, Cluster B and Chief Planner and Executive Director,
More informationEX29.1 REPORT FOR ACTION. SmartTrack Project Update and Next Steps SUMMARY
EX29.1 REPORT FOR ACTION SmartTrack Project Update and Next Steps Date: November 17, 2017 To: Executive Committee From: City Manager and Deputy City Manager, Cluster B Wards: All SUMMARY In July 2016,
More information5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE
5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the
More informationRecommended Vision for the Downtown Rapid Transit Network
Recommended Vision for the Downtown Rapid Transit Network April 2008 Presentation Overview Context Transit options Assessment of options Recommended network Building the network 2 1 Rapid Our Vision Reliable
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationO-Train Confederation Line Stage 1
O-Train Confederation Line Stage 1 Presented to: Regional Public Works Commissioners of Ontario June 23, 2017 by Steve Cripps, Director, O-Train Construction The Need Ottawa s population is projected to
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationLRT vs. Subway. Scarborough RT and Sheppard
LRT vs. Subway Scarborough RT and Sheppard SRT highest ridership of all Transit City Lines SRT ridership is closest to subway technology Subway Within Existing Right-of-Way The SRT cannot be replaced by
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationCREATING CONNECTIONS IN THE CITY OF WATERLOO
CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationCONNECTING THE REGION
CONNECTING THE REGION MARY PROC, VICE PRESIDENT, CUSTOMER SERVICE DELIVERY, METROLINX NATIONAL RAILWAY DAY NOVEMBER 7, 2017 OUR NEW CEO PHIL VERSTER I am very excited about joining the team of dedicated
More informationRe: EX16.1. Developing Toronto's Transit Network Plan to Attachment 5
Re: EX16.1 Developing Toronto's Transit Network Plan to 2031 1 Contents 1. Executive Summary... 3 2. Background and Context... 7 Problem Statement... 9 Decision History on Options Development... 10 Options
More informationMetrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016
Metrolinx: Transforming the Way We Move - A Network Wide Approach Greg Percy, Chief Operating Officer November 1, 2016 2 Greater Toronto & Hamilton Area Total Population in the GTHA Total Population 2001-2041
More informationIssues Facing the Panel
Issues Facing the Panel Choice of technology for Sheppard Avenue (not for every corridor every where for all time!): subway vs. LRT Budget implications I would argue that procurement, construction management
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This
More informationSTAFF REPORT ACTION REQUIRED
nsert TTC logo here STAFF REPORT ACTION REQUIRED Gap Between Subway Trains and Platforms Date: November 13, 2017 To: From: TTC Board Chief Executive Officer Summary This report is in response to an October
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationYonge Relief Network Study (YRNS)
Yonge Relief Network Study (YRNS) Report for June 25 th Metrolinx Board Meeting Leslie Woo, Chief Planning Officer Anna Pace, Director, Project Planning and Development Summary of Yonge Relief Network
More informationProposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1
Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation
More informationGreen Line LRT: Beltline Segment Update April 19, 2017
Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationYRRTC Business Plan
2014 2024 YRRTC Business Plan 2014 Annual Update updated 2014 edocs #4891132 mission Our mission is to design and deliver an exceptional rapid transit system attracting, moving and connecting people to
More informationSCARBOROUGH RAPID TRANSIT ENVIRONMENTAL PROJECT REPORT CHAPTER 2 PROJECT DESCRIPTION. Project Description
Project Description 2 PROJECT DESCRIPTION This chapter documents the extensive preliminary planning activities undertaken prior to the commencement of this Transit Project Assessment Process. Preliminary
More informationCHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 6, 2018
TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 6, 2018 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER HAMILTON
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationEGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)
WELCOME TO OUR PUBLIC OPEN HOUSE EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) Preliminary Planning for a Transit Project Assessment Open House Martin Grove Road to Pearson International Airport September
More informationWhat We Heard Report - Metro Line NW LRT
What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail
More informationCREATING CONNECTIONS IN THE TOWN OF NEWMARKET
CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Purchase Sixty (60) Low Floor Wheel-Trans Mini-Buses Date: September 5, 2017 To: From: TTC Board Chief Executive Officer Summary This report recommends
More informationCREATING CONNECTIONS IN EAST GWILLIMBURY
CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK
More information1 Downtown LRT Connector: Draft Concept
Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future
More informationNew McNicoll Bus Garage Public Open House
New McNicoll Bus Garage Public Open House Kennedy Public School 1 The Need for a New Bus Garage Riders Increased ridership means Buses Need for new buses Garage And a new buses facility Problems Garages
More informationI-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY
EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented
More informationPresentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.
Presentation on Behalf of the Major Mackenzie & 48 Land Owners Group 1 Stouffville Corridor Rail Service Expansion Class Environmental Assessment City of Markham Development Services Committee 10 September
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 30, 2010 SUBJECT: PROCUREMENT AUTHORIZATION AMENDMENT - LOW FLOOR LIGHT RAIL VEHICLE OPTIONS: SURFACE VEHICLE SAFETY
More informationCANADA LINE a Canadian P3 Success Story
CANADA LINE a Canadian P3 Success Story Project Context The Canada Line An automated light rail rapid transit system linking downtown Vancouver with both Richmond and Vancouver International Airport Construction
More informationCREATING CONNECTIONS IN THE CITY OF KITCHENER
CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION
More informationThe Engineering Department recommends Council receive this report for information.
CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision
More informationCentral City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014
Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing July 24, 2014 Project Description The Central City Line is a High Performance Transit project that will extend from Browne
More information4.0 TIER 2 ALTERNATIVES
4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation
More informationPROJECT BACKGROUND 3
AGENDA 1. Welcome & Introductions 2. Project Background 3. Project Approach & Schedule 4. Draft Long List of Options 5. Evaluation Process 6. Next Steps 2 PROJECT BACKGROUND 3 OUR RAPID TRANSIT NETWORK
More informationSTAFF REPORT ACTION REQUIRED
Insert TTC logo here STAFF REPORT ACTION REQUIRED Overhaul of 30 Canadian Light Rail Vehicles (CLRV) and Maintaining non-overhauled Streetcars in a State of Good Repair Date: March 23, 2016 To: From: TTC
More informationCity-wide LED Street Light Conversion Program
City-wide LED Street Light Conversion Program Arts & Innovation Board of Public Utilities July 25, 2016 Project Description Utility 2.0 Multi-phase implementation of city-wide street light conversion program
More informationAppendix A-M Public Information Centre 4 Materials
Appendix A-M Public Information Centre 4 Materials NOTICE OF PUBLIC INFORMATION CENTRE #4 RAPID TRANSIT CORRIDORS MASTER PLAN ENVIRONMENTAL ASSESSMENT STUDY The City of London is entering a new chapter
More informationOttawa LRT Stage 2. McKellar Park Information Session
Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationReport for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer
Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.
More informationMETRO Light Rail Update
American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)
More informationBayshore Station to Moodie Drive LRT Extension Environmental Assessment Studies. Public Meeting 22 March 2017
Bayshore Station to Moodie Drive LRT Extension Environmental Assessment Studies Public Meeting 22 March 2017 Overview Introductions Background and Scope Network Options Bus Rapid Transit (BRT) conversion
More informationBroward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA
Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional
More informationJapanese ODA Loan. Ex-ante Evaluation
Japanese ODA Loan Ex-ante Evaluation 1.Name of the Project Country:Republic of the Philippines Project:Capacity Enhancement of Mass Transit Systems in Metro Manila Project Loan Agreement:27 March 2013
More informationWillamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee
Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee 05.28.09 09 Bridge Type - Cost Vertical Clearance Bicycle Pedestrian Path Width Bridge Type - Cost WRBAC
More informationMOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses
MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: December 16, 2009 SUBJECT: CANADIAN CONTENT BUS PROCUREMENTS ACTION ITEM RECOMMENDATION It is recommended that the Commission
More informationSTAFF REPORT INFORMATION ONLY
Insert TTC logo here STAFF REPORT INFORMATION ONLY Presentation: Subway Closures - 2016 Year In Review and 2017 Forecast Date: January 18, 2017 To: From: TTC Board Chief Executive Officer Summary The purpose
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase 285 Forty Foot Low Floor Clean Diesel City Buses Date: November 30, 2016 To: From: TTC Board Chief Executive Officer Summary This
More informationSUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update
MEETING DATE: August 31, 2005 SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update RECOMMENDATION It is recommended that the Commission: i) Receive for information
More information2.1 TRANSIT VISION 2040 FROM VISION TO ACTION. Expand regional rapid transit networks STRATEGIC DIRECTION
TRANSIT VISION 2040 FROM VISION TO ACTION TRANSIT VISION 2040 defines a future in which public transit maximizes its contribution to quality of life with benefits that support a vibrant and equitable society,
More informationTRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury
TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationThe Regional Municipality of York. Purchase of Six Battery Electric Buses
1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric
More informationAlternatives Analysis Findings Report
6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop
More informationUpdate on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:
Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community
More informationBusiness Advisory Committee. November 3, 2015
Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal
More informationYonge Subway Extension Breakfast Meeting
Yonge Subway Extension Breakfast Meeting May 12, 2011 1 breakfast meeting overview 1. Welcome 2. Rapid Transit overview Yonge Subway Funding Call to action 3. Commentary 4. Open discussion 5. Closing remarks
More informationEMERGING REQUIREMENTS
Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This
More information5 New GO Stations in York Region to Support Regional Express Rail
Clause 5 in Report No. 14 of Committee of the Whole was adopted by the Council of The Regional Municipality of York at its meeting held on October 20, 2016 with the following additional recommendation:
More informationWelcome. The purpose of today s session is to:
Welcome The purpose of today s session is to: Update you on what we ve heard from the community Share the preferred Rapid Transit network solution Present the draft Rapid Transit Master Plan Representatives
More informationAccessible Transit Services Plan
- 1 Accessible Transit Services Plan 2006 Status Report - 2 Accessible Transit Services Plan 2006 Status Report 1.0 Introduction This report provides an update on activities the TTC has undertaken between
More informationPolicy Advisory Committee Meeting November 13, 2013
Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationRegional Express Rail: Kipling Station Project Update. Ryah Kazman, Community Relations Specialist Metrolinx
Regional Express Rail: Kipling Station Project Update Ryah Kazman, Community Relations Specialist Metrolinx GRIDLOCK COSTS OUR ECONONY Residents could spend 109 minutes per day in traffic METROLINX PLAN
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: SCHEDULE STATUS UPDATE ACTION ITEM RECOMMENDATION It is recommended that the Commission: 1. Receive
More information5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS
5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS The Transportation Services Committee recommends the adoption of the recommendations contained in the following report
More informationEast Turnaround. Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan.
East Turnaround Options at Fanshawe College Ayreswood Access Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan. To mitigate the impacts
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationTransit Project Delivery Status Report. Significant Issues
Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationConfederation Line West Queensway Terrace North. May 27, 2017
Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement
More information