Panel Discussion: Planning for Today and Tomorrow

Size: px
Start display at page:

Download "Panel Discussion: Planning for Today and Tomorrow"

Transcription

1 Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO David Short, Power System Assessments, IESO Ahmed Maria, Senior Manager, Transmission Integration, IESO Angelo Boschetti, Supervisor, Engineering Department: Generation and Capacity Planning, Toronto Hydro Robert Reinmuller, Director, System Planning, Hydro One

2 GTA and Central Ontario Regional Forum Operations Perspective David Short Director, Power System Assessments December 11, 2017

3 Overview 2

4 Operating challenges Under peak load conditions, this area can be exposed to low voltages and thermal overloads requiring capacitors to be placed into service and generation to be dispatched. On occasion, load transfers may be required in Metro Toronto region. Under light load periods this area can be exposed to high voltages. 500 kv circuits along the Bowmanville SS to Lennox TS corridor have had to be taken out of service as a control action. Under high imports from New York Niagara interconnection, 230 kv circuits with the Hamilton to Burlington area may become congested. 3

5 Toronto Zone Historical Operating Conditions Summer Total Energy (June-Aug) Summer Peak Demand Annual Energy TWh 13.2 TWh 14.3 TWh 12.9 TWh 8723 MW 9229 MW 9649 MW 8619 MW 51.5 TWh 51.2 TWh 51.4TWh - 4

6 Greater Toronto and Central Ontario Near-term Outlook Transmission transfer capability in Toronto and Central area is expected to be sufficient for the purpose of serving load, with sufficient margin to allow for planned outages. Metro Toronto Manby East or Manby West TS loading Copeland TS is expected to be completed in 2018 GTA North Increased Vaughan loads GTA East Clarington TS will help improve the reliability of central and eastern GTA once Pickering retires High voltages are an issue during low transfer levels on the 500 kv transmission system 5

7 Toronto Zone Summer 2018 Capacity and Energy Picture Capacity Picture - Normal peak demand forecast for July 2018 is 9,414 MW - Internal supply for July 2018 is 6,712 MW Energy Picture - Energy demand forecast for July 2018 is 4,644 GWh. - Internal energy capability for July 2018 is 4,789 GWh. 6

8 Appendix: Peak Demand in Toronto Zone Annual Peak Toronto Zonal Demand (MW) 7

9 Appendix Toronto Zonal Demand 2014 to

10 Planning of the Ontario Electricity System Ahmed Maria, IESO December 11, 2017

11 Ontario s Electricity Sector Participants Regulation Transmission Planning, Market & System Operation Five Nations & others Ontario Electricity System and its Customers Distribution Generation Customers & other generators Hydro One Distribution & other local distribution utilities Residential Commercial Industrial 2

12 Three Levels of Electricity Planning Bulk System Planning Regional Planning Distribution Network Planning Long-term Energy Plan, Ontario Planning Outlook Integrated Regional Resource Plan, Regional Infrastructure Plan Distribution System Plan

13 Regions in GTA and Central Ontario 5 regions: 1. GTA West 2. GTA North 3. Toronto 4. GTA East 5. South Georgian Bay/Muskoka 4

14 Planning Considerations Infrastructure is aging In some regions, forecasted growth is exceeding supply capability In some regions, reliability of supply is a concern Expansion into greenfield areas away from electricity infrastructure is expected to occur Non-wire solutions may be an option to address electricity needs Municipal and community plans should be factored in There may be opportunities to maximize the use of existing assets 5

15 Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO David Short, Power System Assessments, IESO Ahmed Maria, Senior Manager, Transmission Integration, IESO Angelo Boschetti, Supervisor, Engineering Department: Generation and Capacity Planning, Toronto Hydro Robert Reinmuller, Director, System Planning, Hydro One

16 Central Ontario Regional Forum December 11, 2017

17 Our Role Hydro One s Role in the Electric System TRANSMISSION DISTRIBUTION Electricity Generation Sources Transformer Transmission (Increased to System Higher voltage) Transformer (Decreased to Medium voltage) Distribution System 98% of capacity 75% of geography and 25% of end use customers Percentage of Ontario Market Transformer (Decreased to Lower voltage) Industrial, Residential, Commercial Customers 2

18 One of North America s Largest Electric Utilities Service Territory Pure electric transmission and distribution utility 30,000 circuit KMs of transmission lines across 98% of Ontario, home to 38% of Canadian population Largest local distribution company (LDC) in Ontario with 1.3 million end customers 99% of revenue from regulated operations Service area is larger than France or the State of Texas Combined transmission and distribution rate base of $17.83 billion Common shares traded on the TSX under ticker symbol H 3

19 Planning Considerations IESO LDC IESO TRANSMITTER 4

20 Major Transmission Projects Completed in Central Ontario Legend 500 kv 230 kv 115 kv Hearn SS, Leaside TS & Manby TS Switchyard (2013 & 2014) Manby TS: Reconfiguration (2014) Lakeshore Cable Refurbishment (2015) Midtown Tx Reinforcement (2016) YEC generation (2012) GATR (2016) Thornton Tx (2015) Kingston: Solar CGS (2015) Gardiner TS: T3/T4 (2009) Sidney TS: breakers (2017) Jarvis & Caledonia TS: Reactors ( ) Nebo TS: Breakers (2013) Burlington TS: Breakers (2016) TX replacement: Brantford TS (2013), Kenilworth TS (2014), Dundas TS (2015), Brant TS (2016) Clarington 5

21 Major Future Transmission Projects in Central Ontario Legend 500 kv 230 kv 115 kv Metrolinx Stations: Burlington Barrie Cityview Mimico Oshawa Scarborough Vaughan MTS #4 (2017) Holland breakers (2017) Markham MTS #5 (2023 Clarington TS (2018) Enfield TS (2019) Seaton MTS (2019) Amherst Island CGS (2018) Loyal Solar CGS (2018) Connect Napanee GS (2018) M20D/M21D Switches (2017) Brant 115 kv SS (2019) Kenilworth TS: EOL Tx (2021) Beach TS: HV Breakers/ Tx (2019) Middleport TS: HV breakers (2022) Nanticoke TS: HV breakers (2021) Gage TS: Reconfigure/EOL Tx (2019) Elgin TS: Reconfigure/EOL Tx (2019) Clarington Copeland MTS (2018) Runnymede TS New DESN K x W Line Upgrade (2018) Horner TS (2020) R x K Transmission (2022) Beck Beck Clarington 6

22 Goals Safe, Reliable, Efficient Facilitate the delivery of the Long Term Energy Plan Comply with stringent Reliability Standards Meet Customer Needs Meet Regional Planning Obligations Expand on System Monitoring and Analysis Continued Collaboration with Indigenous Communities Engagement and Transparency for all Customers Continue Innovation 7

23 Operational Excellence CANADIAN-BASED CHAMPION & LEADING NORTH AMERICAN UTILITY OPERATIONS 2020 VISION: Establish a culture of operational excellence with industry leading safety to deliver cost effective, reliable service for our customers. Create a repeatable platform for growth as the leading owner and operator of grid infrastructure in North America. Be an industry leader in SAFETY & ENVIRONMENT for our employees, contractors, and the public Deliver improved RELIABILITY to our customers, incorporating their input and priorities Provide COST EFFECTIVE service to our customers by improving our productivity Always be there for our CUSTOMERS with a seamless experience in all operations interactions Foundational OPERATING MODEL enabled by people, process, and technology 8

Panel Discussion: Planning for Today and Tomorrow

Panel Discussion: Planning for Today and Tomorrow Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO Nicola Presutti, Senior Manager, Control Room Operations, IESO Bob Chow,

More information

Burlington to Nanticoke REGIONAL INFRASTRUCTURE PLAN

Burlington to Nanticoke REGIONAL INFRASTRUCTURE PLAN Burlington to Nanticoke REGIONAL INFRASTRUCTURE PLAN February 7, 2017 2 [This page is intentionally left blank] Burlington to Nanticoke - Regional Infrastructure Plan February 7, 2017 Prepared and supported

More information

July 25, Karla Bailey Asset Management & Engineering Manager Thunder Bay Hydro 34 Cumberland St N, Thunder Bay, ON P7A 4L4. Dear Ms.

July 25, Karla Bailey Asset Management & Engineering Manager Thunder Bay Hydro 34 Cumberland St N, Thunder Bay, ON P7A 4L4. Dear Ms. 483 Bay Street Tel: (416) 345-5420 13 th Floor, North Tower Fax: (416) 345-4141 Toronto, ON, M5G 2P5 ajay.garg@hydroone.com www.hydroone.com July 25, 2016 Karla Bailey Asset Management & Engineering Manager

More information

Utility Administration & Operation of Virtually Net-Metered Generation

Utility Administration & Operation of Virtually Net-Metered Generation Solar Canada 2017 Utility Administration & Operation of Virtually Net-Metered Generation Vinay Sharma Chair, EDA Dec 5, 2017 Electricity Distributors Association 2 The EDA is the voice of Ontario s local

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

Metro Toronto REGIONAL INFRASTRUCTURE PLAN

Metro Toronto REGIONAL INFRASTRUCTURE PLAN Metro Toronto REGIONAL INFRASTRUCTURE PLAN January 12, 2016 [This page is intentionally left blank] 2 Metro Toronto Regional Infrastructure Plan January 12, 2016 Prepared by: Hydro One Networks Inc. (Lead

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

March 21, Mr. James F. Brown, P.Eng. Director, Infrastructure EnWin Utilities Inc. 787 Ouellette Avenue, Windsor, Ontario N9A 5T7

March 21, Mr. James F. Brown, P.Eng. Director, Infrastructure EnWin Utilities Inc. 787 Ouellette Avenue, Windsor, Ontario N9A 5T7 Hydro One Networks Inc. 483 Bay Street Tel: (416) 345-5420 15 th Floor, South Tower Fax: (416) 345-4141 Toronto, ON M5G 2P5 ajay.garg@hydroone.com www.hydroone.com March 21, 2014 Mr. James F. Brown, P.Eng.

More information

Mr. Vince Mauceri General Manager Transportation Operations and Technology

Mr. Vince Mauceri General Manager Transportation Operations and Technology Mr. Vince Mauceri General Manager Transportation Operations and Technology METROLINX OVERVIEW AND MANDATE Established in 2006 to address the significant transportation challenges in the Greater Toronto

More information

November 28, Jim Klujber Manager of Operations Wellington North Power Inc. 290 Queen Street West, P.O. Box 359 Mount Forest, ON N0G 2L0

November 28, Jim Klujber Manager of Operations Wellington North Power Inc. 290 Queen Street West, P.O. Box 359 Mount Forest, ON N0G 2L0 483 Bay Street Tel: (416) 345-5420 6 th Floor, South Tower Fax: (416) 345-4141 Toronto, ON M5G 2P5 ajay.garg@hydroone.com www.hydroone.com November 28, 2014 Jim Klujber Manager of Operations Wellington

More information

CONNECTING THE REGION

CONNECTING THE REGION CONNECTING THE REGION GERRY CHAPUT VICE PRESIDENT, RAPID TRANSIT, METROLINX VALUE ANALYSIS CANADA SUMMIT KEYNOTE OCTOBER 16, 2017 Metrolinx was created in 2006 by the Province of Ontario to improve the

More information

May 20 th Mark Van de Rydt Supervisor Engineering Greater Sudbury Hydro Inc. 500 Regent Street P.O Box 250 Sudbury, ON P3E 3Y2

May 20 th Mark Van de Rydt Supervisor Engineering Greater Sudbury Hydro Inc. 500 Regent Street P.O Box 250 Sudbury, ON P3E 3Y2 Hydro One Networks Inc. 483 Bay Street Tel: (416) 345-5420 13 th Floor, North Tower Fax: (416) 345-4141 Toronto, ON, M5G 2P5 ajay.garg@hydroone.com www.hydroone.com May 20 th 2016 Mark Van de Rydt Supervisor

More information

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning SERVICES INNOVATION Montreal Symposium March 29, 2017 Jack Simpson Director, Generation & Capacity Planning UTILITY LANDSCAPE IS CHANGING 2 Innovation CUSTOMER NEEDS ARE CHANGING GREATER RELIABILITY STORM

More information

GO Transit s deliverable: the 2020 Service Plan

GO Transit s deliverable: the 2020 Service Plan GO Transit s deliverable: the 2020 Service Plan GO Transit s 2020 Service Plan describes GO s commitment to customers, existing and new, to provide a dramatically expanded interregional transit option

More information

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012 ERCOT Overview Paul Wattles Senior Analyst, Market Design & Development Solar Energy Industries Association History of Electric Reliability Council of Texas, Inc. 1941 Utilities band together to aid war

More information

April 8 th Brenda L. Pinke Regulatory/CDM Manager InnPower Corporation 7251 Yonge Street Innisfil, Ontario, L9S 0J3. Dear Ms.

April 8 th Brenda L. Pinke Regulatory/CDM Manager InnPower Corporation 7251 Yonge Street Innisfil, Ontario, L9S 0J3. Dear Ms. 483 Bay Street Tel: (416) 345-5420 13 th Floor, North Tower Fax: (416) 345-4141 Toronto, ON, M5G 2P5 ajay.garg@hydroone.com www.hydroone.com April 8 th 2016 Brenda L. Pinke Regulatory/CDM Manager InnPower

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

April 28, Doug Curtiss Chief Executive Officer Grimsby Power Inc. 231 Roberts Road Grimsby, ON L3M 5N2. Dear Mr. Curtiss:

April 28, Doug Curtiss Chief Executive Officer Grimsby Power Inc. 231 Roberts Road Grimsby, ON L3M 5N2. Dear Mr. Curtiss: 483 Bay Street Tel: (416) 345 5420 13 th Floor, North Tower Fax: (416) 345 4141 Toronto, ON M5G 2P5 ajay.garg@hydroone.com www.hydroone.com April 28, 2015 Doug Curtiss Chief Executive Officer Grimsby Power

More information

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations SPP OVERVIEW Mike Ross Senior Vice President, Government Affairs and Public Relations 1 Our Mission Helping our members work together to keep the lights on today and in the future. 2 NORTH AMERICAN INDEPENDENT

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

2018 OPERABILITY ASSESSMENT

2018 OPERABILITY ASSESSMENT 2018 OPERABILITY ASSESSMENT Mohab Elnashar, PhD, P.Eng. Senior Engineer Performance Validation and Modeling January 8, 2019 What is an Operability Assessment? An Operability Assessment is a study of the

More information

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS June 18, 2015 E2Tech Presentation AGENDA Energy storage as a grid solution high level Specific CEP project examples The technology

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO Cam Carver CEO, Temporal Power Ltd. Corporate Overview Temporal Power, a Ontario based company, is a global leader in the development

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

NYISO Market Initiatives

NYISO Market Initiatives NYISO Market Initiatives Robb Pike Director Market Design New York Independent System Operator Ventyx Market Leadership Council Santa Clara, CA April 23, 2012 Topics Roles of the NYISO Smart Grid Integrating

More information

CONNECTING THE REGION

CONNECTING THE REGION CONNECTING THE REGION JUDY PFEIFER CHIEF COMMUNICATIONS & PUBLIC AFFAIRS OFFICER LESLIE WOO CHIEF PLANNING OFFICER, PLANNING & POLICY PRESENTED AT AMO INSIGHT BREAKFAST SESSION AUGUST 14, 2017 7:15AM 8:15AM

More information

Year Built: ,972 sq. ft. (including basement) Roof: Replaced in drive-in doors and 1 dock-door. Yes partial wet system (basement)

Year Built: ,972 sq. ft. (including basement) Roof: Replaced in drive-in doors and 1 dock-door. Yes partial wet system (basement) FOR SALE / LEASE 415 BASELINE RD., BOWMANVILLE OFFICE BUILDING 34,972 SQ.FT ON 2.87 ACRES For further information contact: Robert Bellissimo President, Broker of Record rbellissimo@strategicpm.ca Jeff

More information

Western NY Public Policy Transmission Report

Western NY Public Policy Transmission Report Western NY Public Policy Transmission Report Dawei Fan Supervisor, Public Policy and Interregional Planning ESPWG/TPAS July 20, 2017, KCC Agenda Public Policy Transmission Planning Process Western NY Public

More information

Roadmap for high RES penetration in Greek Non Interconnected Islands

Roadmap for high RES penetration in Greek Non Interconnected Islands Roadmap for high RES penetration in Greek Non Interconnected Islands European Forum on Clean Energy for Islands Prof. Nikos Chatziargyriou Chairman Naxos,9-11 of July 2018 Who we are and what we do 7,000

More information

Impact of Energy Efficiency and Demand Response on Electricity Demand

Impact of Energy Efficiency and Demand Response on Electricity Demand October 26, 2009 Impact of Energy Efficiency and Demand Response on Electricity Demand Perspectives on a Realistic United States Electric Power Generation Portfolio: 2010 to 2050 Presented by Lisa Wood

More information

Transportation Electrification Public Input Workshop. August 3, 2016

Transportation Electrification Public Input Workshop. August 3, 2016 Transportation Electrification Public Input Workshop August 3, 2016 1 Agenda Welcome and Introductions Company Overview Existing Transportation Electrification Initiatives Accelerating Transportation Electrification

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

Building Collaboration Between East African Nations via Transmission Interconnectors

Building Collaboration Between East African Nations via Transmission Interconnectors Building Collaboration Between East African Nations via Transmission Interconnectors Eng. Christian M.A. Msyani Ag. DEPUTY MANAGING DIRECTOR TRANSMISSION - TANESCO CONTENTS 1. TANESCO - Existing Power

More information

Distributed Generation

Distributed Generation Distributed Generation Presented by: Doug Fairchild & Chris Cooper 1 Agenda Hydro One Overview The state of DG in the Province of Ontario Technical Issues Operational Requirements Overview Control Room

More information

Office of Electric Transmission and Distribution. Transforming the Grid to Revolutionize Electric Power in North America

Office of Electric Transmission and Distribution. Transforming the Grid to Revolutionize Electric Power in North America Office of Electric Transmission and Distribution Transforming the Grid to Revolutionize Electric Power in North America Electricity and Economic Growth If the electricity infrastructure of this country

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

ABB Next Level Big shift in power attractive opportunities

ABB Next Level Big shift in power attractive opportunities Bernhard Jucker and Claudio Facchin, Capital Markets Day, London, ABB Next Level Big shift in power attractive opportunities Slide 1 Agenda Profitably growing ABB s power business Shifting the center of

More information

Energy Plan. Public Forum Presentation January 25, 2011

Energy Plan. Public Forum Presentation January 25, 2011 Energy Plan Public Forum Presentation January 25, 2011 Today s Methods 2 Where is Electricity Required? Today 17% 65% 18% 3 Bermuda s Demand Profile & Peaks 2010 140 Winter Summer 120 100 shift Demand

More information

Alfen acquires Elkamo in Finland A platform for expansion in the Nordics

Alfen acquires Elkamo in Finland A platform for expansion in the Nordics Alfen acquires Elkamo in Finland A platform for expansion in the Nordics 2 July 2018 Disclaimer This communication may include forward-looking statements. All statements other than statements of historical

More information

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015 ADB Knowledge Partnership Week Hirokazu Yamaguchi May, 2015 TEPCO AT A GLANCE 1 THE 10 ELECTRIC POWER COMPANIES BY SERVICE AREA In Japan, 10 regional privately owned and managed General Electricity Utilities

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

ISO on Background. Energy-efficiency forecast. Anne George. Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING DECEMBER 12, 2012

ISO on Background. Energy-efficiency forecast. Anne George. Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING DECEMBER 12, 2012 DECEMBER 12, 2012 ISO on Background Energy-efficiency forecast Anne George VICE PRESIDENT, EXTERNAL AFFAIRS &CORPORATE COMMUNICATIONS Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING Agenda 11:00-11:05

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Looking Towards the Future: Advantages of 765-kV Transmission Technology Looking Towards the Future: Advantages of 765-kV Transmission Technology In the electric transmission business, design plays a key role in the efficiency and productivity of the nation s energy delivery

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

The Regional Transportation Plan PLAN BUILD OPERATE

The Regional Transportation Plan PLAN BUILD OPERATE WHO IS METROLINX? Metrolinx was created in 2006 by the Province of Ontario as the first Regional Transportation Agency for the Greater Toronto and Hamilton Area (GTHA). The Regional Transportation Plan

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

Accommodating High Levels of Variable Generation. EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009

Accommodating High Levels of Variable Generation. EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009 Accommodating High Levels of Variable Generation EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009 Agenda About NERC About the Integration of Variable Generation Task Force

More information

Electric Power Infrastructure Services Duke Austin, President & Chief Executive Officer B.J. Ducey, Senior Vice President Operations

Electric Power Infrastructure Services Duke Austin, President & Chief Executive Officer B.J. Ducey, Senior Vice President Operations Electric Power Infrastructure Services Duke Austin, President & Chief Executive Officer B.J. Ducey, Senior Vice President Operations Key Takeaways Quanta is the largest electric utility solutions provider

More information

Efficiency Challenges for the European Utilities A view from Enel

Efficiency Challenges for the European Utilities A view from Enel Intelligent Energy, Smart Grids and the Efficiency Challenges for the European Utilities A view from Enel Livio Gallo, Managing Director of Enel Infrastructure and Networks Division, CEO Enel Distribuzione

More information

Northwest Ontario REGIONAL INFRASTRUCTURE PLAN

Northwest Ontario REGIONAL INFRASTRUCTURE PLAN Northwest Ontario REGIONAL INFRASTRUCTURE PLAN June 9, 2017 [This page is intentionally left blank] 2 Prepared by: Hydro One Networks Inc. (Lead Transmitter) With support from: Company Atikokan Hydro Inc.

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Share with the GHSEA. Smart Energy Initiatives. Collaboration and a partner eco-system to achieve results

Share with the GHSEA. Smart Energy Initiatives. Collaboration and a partner eco-system to achieve results Share with the GHSEA on behalf of the DSEA - learning and experience Color variant: Siemens Cool Gray Smart Energy Initiatives Collaboration and a partner eco-system to achieve results Realizing a Community-centric

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic 1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision is for solar energy to be

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Da Afghanistan Breshna Sherkat

Da Afghanistan Breshna Sherkat Da Afghanistan Breshna Sherkat DABS PRESENTATION 14 September 2014 DABS Home Office Kabul, Afghanistan www.dabs.af 1 AFGHANISTAN ENERGY SECTOR Afghanistan Energy Infrastructure, generation, transmission

More information

CREATING CONNECTIONS IN EAST GWILLIMBURY

CREATING CONNECTIONS IN EAST GWILLIMBURY CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK

More information

Regional Market Trends Forum April 21, 2016 Hartford, CT. Mike Dirrane Director, Northeast Marketing

Regional Market Trends Forum April 21, 2016 Hartford, CT. Mike Dirrane Director, Northeast Marketing Regional Market Trends Forum April 21, 2016 Hartford, CT Mike Dirrane Director, Northeast Marketing Spectra Energy s Portfolio of Assets Based in Houston, TX with operations in 30 states Transports 15%

More information

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015 Development Services Committee June 23, 2015 Building Markham s Future Together Transit Update Presentation: 1. Overview of Metrolinx 2. The Big Move 3. Projects Update 4. Investment Strategy 5. Next Steps

More information

LONDON!!!!!!!!!!!!!!!!!! Regional Infrastructure Plan 09 January London Area REGIONAL INFRASTRUCTURE PLAN

LONDON!!!!!!!!!!!!!!!!!! Regional Infrastructure Plan 09 January London Area REGIONAL INFRASTRUCTURE PLAN LONDON!!!!!!!!!!!!!!!!!! Regional Infrastructure Plan 09 January 2017 London Area REGIONAL INFRASTRUCTURE PLAN August 25th, 2017 [This page is intentionally left blank] 2 Prepared by: Hydro One Networks

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

OVERVIEW OF UNIFORM TRANSMISSION RATES

OVERVIEW OF UNIFORM TRANSMISSION RATES Exhibit H1 Tab 1 Schedule 1 Page 1 of 2 1 OVERVIEW OF UNIFORM TRANSMISSION RATES 2 3 4 5 6 7 8 9 Transmission rates in Ontario have been established on a uniform basis for all transmitters in Ontario since

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative AMEREN ILLINOIS UTILITIES Stimulus Package July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative Ron Pate Vice President, Regional Operations Jackie Voiles Director, Regulatory

More information

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016 The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016

More information

Developments in Electrification and Implications for the United States Electric Industry U.S. Department of Energy Perspective

Developments in Electrification and Implications for the United States Electric Industry U.S. Department of Energy Perspective Developments in Electrification and Implications for the United States Electric Industry U.S. Department of Energy Perspective Katie Jereza, Deputy Assistant Secretary October 18, 2017 U.S. Department

More information

Electric Transportation and Energy Storage

Electric Transportation and Energy Storage Electric Transportation and Energy Storage Eladio M. Knipping, Ph.D. Senior Technical Manager, Environment April 24, 2009 Fate of U.S. Electricity Production Generation Transmission Distribution Residence/

More information

2018 Load & Capacity Data Report

2018 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

GTA West Corridor Planning and EA Study Stage 1

GTA West Corridor Planning and EA Study Stage 1 GTA West Corridor Planning and EA Study Stage 1 Draft Development Strategy Presentation to Peel Goods Movement Task Force April 8 2011 Study Areas 2 Unique Approach Unprecedented two-stage EA process:

More information

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee. Presentation on Behalf of the Major Mackenzie & 48 Land Owners Group 1 Stouffville Corridor Rail Service Expansion Class Environmental Assessment City of Markham Development Services Committee 10 September

More information

Impact of Distributed Energy Resources on Transmission System Reliability

Impact of Distributed Energy Resources on Transmission System Reliability S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A

More information

General Overview. Ernesto Macias ARE President MUNICH Copyright Alliance for Rural Electrification. All rights reserved.

General Overview. Ernesto Macias ARE President MUNICH Copyright Alliance for Rural Electrification. All rights reserved. General Overview Ernesto Macias ARE President MUNICH - 2017 Copyright Alliance for Rural Electrification. All rights reserved. 1 Who are we Established in 2006, the Alliance for Rural Electrification (ARE)

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

Energy Policy Implications: PJM Planning

Energy Policy Implications: PJM Planning Energy Policy Implications: PJM Planning Chicago, Illinois November 14, 2012 Steven R. Herling Vice President, Planning PJM Interconnection PJM as Part of the Eastern Interconnection 26% of generation

More information

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016 Metrolinx: Transforming the Way We Move - A Network Wide Approach Greg Percy, Chief Operating Officer November 1, 2016 2 Greater Toronto & Hamilton Area Total Population in the GTHA Total Population 2001-2041

More information

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity

More information

The impact on the data center Industry

The impact on the data center Industry DATA CENTRE WORLD LONDON 12-13 TH MARCH 2019 The transformation of power systems The impact on the data center Industry Stephen Jones : Grid Edge Technology Intelligent data needs intelligent power ABB

More information

Energy Outlook for Asia and the Pacific

Energy Outlook for Asia and the Pacific Energy Outlook for Asia and the Pacific Aiming Zhou Senior Energy Specialist Asian Development Bank 25-29 Nov, 2013 Coverage of the Outlook Time Frame: 2010 2035 Geographic Coverage: Developing Asia o

More information

Ron Schoff Senior Program Manager, EPRI. USEA Energy Supply Forum Washington, DC October 2, 2014

Ron Schoff Senior Program Manager, EPRI. USEA Energy Supply Forum Washington, DC October 2, 2014 Ron Schoff Senior Program Manager, EPRI USEA Energy Supply Forum Washington, DC October 2, 2014 2014 Electric Power Research Institute, Inc. 2014 Electric Power Research All rights reserved. Institute,

More information

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Deloitte Utility Electric Vehicle Survey

Deloitte Utility Electric Vehicle Survey Deloitte Utility Electric Vehicle Survey The Deloitte Utility EV Survey was conducted in 2017 and was previewed in Deloitte s report, Powering the future of mobility: How the electric power sector can

More information

Review of U.S. market reforms for renewable integration, flexibility, and storage

Review of U.S. market reforms for renewable integration, flexibility, and storage Review of U.S. market reforms for renewable integration, flexibility, and storage Eric Hsieh Director Office of Energy Finance and Incentives Analysis U.S. Department of Energy 14 July 2017 Transformations

More information

Mississauga Moves: A City in Transformation icity Symposium Hamish Campbell

Mississauga Moves: A City in Transformation icity Symposium Hamish Campbell Mississauga Moves: A City in Transformation 2018 icity Symposium Hamish Campbell Outline Mississauga: A City in Transformation Planning for a Transformative Future Transportation Master Plan Parking Master

More information

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK Grid Operations and the Increasing Challenges of Balancing Renewable Energy JANUARY 18 ALBUQUERQUE QUALITY NETWORK JANUARY 18, 2018 AGENDA Overview and History of PNM Grid Operation Challenges Generation

More information

Envisioning Future Energy Technologies Aaron Melda Tennessee Valley Authority

Envisioning Future Energy Technologies Aaron Melda Tennessee Valley Authority Envisioning Future Energy Technologies Aaron Melda Tennessee Valley Authority Where We Are Today GWh 200,000 Energy Forecast Plan CAGR FY11 Budget 1.4% 180,000 FY15 Budget 0.9% 160,000 FY17 Budget 0.3%

More information

Lennox GS Deregistration Analysis

Lennox GS Deregistration Analysis PUBLIC Lennox GS Deregistration Analysis Independent Electricity System Operator Issue 2.0 Final REPORT Project: Lennox GS Reliability Must Run Contract Period: October 2006 to September 2007 Transmission

More information

Microgrid solutions Delivering resilient power anywhere at any time

Microgrid solutions Delivering resilient power anywhere at any time Microgrid solutions Delivering resilient power anywhere at any time 2 3 Innovative and flexible solutions for today s energy challenges The global energy and grid transformation is creating multiple challenges

More information

21st Century Power Grids: Reliable, Controllable and Resilient

21st Century Power Grids: Reliable, Controllable and Resilient 21st Century Power Grids: Reliable, Controllable and Resilient Terry Boston President & CEO PJM Interconnection NAESO February 5, 2014 Greatest Engineering Achievements of the 20 th Century 10. Air Conditioning/

More information

LDC 2.0 EVs, DER, Transactive Energy

LDC 2.0 EVs, DER, Transactive Energy MITL Symposium November 29 2018 LDC 2.0 EVs, DER, Transactive Energy Dan Guatto, P. Eng. COO VP Engineering and Operations Changing Consumers Decarbonization We know the future and so do you Transportation

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Power Systems Fundamentals

Power Systems Fundamentals Power Systems Fundamentals Yachi Lin Senior Manager, Transmission Planning New York Independent System Operator Market Overview Course September 20, 2017 Rensselaer, NY 2017 New York Independent System

More information