Hydraulic Modeling: Pipe Network Analysis
|
|
- Maude Richard
- 6 years ago
- Views:
Transcription
1 Utah State University All Graduate Plan B and other Reports Graduate Studies Hydraulic Modeling: Pipe Network Analysis Trevor T. Datwyler Utah State University Follow this and additional works at: Part of the Civil and Environmental Engineering Commons Recommended Citation Datwyler, Trevor T., "Hydraulic Modeling: Pipe Network Analysis" (2012). All Graduate Plan B and other Reports This Report is brought to you for free and open access by the Graduate Studies at DigitalCommons@USU. It has been accepted for inclusion in All Graduate Plan B and other Reports by an authorized administrator of DigitalCommons@USU. For more information, please contact dylan.burns@usu.edu.
2 HYDRAULIC MODELING: PIPE NETWORK ANALYSIS by Trevor T. Datwyler A research report submitted in partial fulfillment Of the requirements for the degree of MASTER OF SCIENCE in Civil and Environmental Engineering Approved: Michael C. Johnson Major Professor Blake P. Tullis Committee Member Marvin W. Halling Committee Member UTAH STATE UNIVERSITY Logan, Utah 2012
3 TABLE OF CONTENTS Report Certification 1.0 Introduction/Executive Summary 1.1 Existing System Description 1.2 Proposed & Projected Additions and Improvements to the System 2.0 Sources & Facilities 2.1 Sources 2.2 Storage Facilities 2.3 Booster Stations 2.4 Distribution System 3.0 Existing and Future Connections 3.1 Service Area 3.2 ERC Evaluation 3.3 Growth Management Alternatives 4.0 Water Demand Criteria 4.1 Indoor Water Use Demand 4.2 Outdoor Water Use Demand 4.3 Fire Flow Requirements 4.4 Other Demand 4.5 Demand versus Existing (and/or Proposed) Capacity 5.0 Methodology and Analysis 5.1 Hydraulic Model Used 5.2 Hydraulic Model Input 5.3 Field Calibration Methodology 5.4 Hydraulic Model Analysis 6.0 Analysis Results and Conclusions 6.1 Hydraulic Model Results 6.2 Comparison of Field Measurements and Model Results 6.3 Conclusion of Project Impact from Model Results 6.4 Rule Compliance Conclusion References Appendices Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Existing Peak Day Demand Pressures Existing Peak Day Demand + Fireflow Pressures Existing Peak Day Demand + Fireflow at School Pressures Existing Peak Hour Demand Pressures 10 Year Future Peak Day Demand Pressures 10 Year Future Peak Day Demand + Fireflow Pressures ii
4 Appendix G Appendix H 10 Year Future Peak Day Demand + Fireflow at School Pressures 10 Year Future Peak Hour Demand Pressures LIST OF TABLES Table 1.1: Table 2.1: Table 2.2: Table 2.3: Table 3.1: Table 5.1: Table 5.2: Table 5.3: Summary of System Capacities Water sources and associated right number Storage Facilities List of pipes by diameter and HW Coefficient used for modeling List of High Volume Water Users and their associated ERCs List of pipes by diameter and HW Coefficient used for modeling Field calibration results Test Hydrant Field calibration results Adjacent Hydrant LIST OF FIGURES Figure 1.1: Figure 1.2: Figure 1.3: Figure 1.4: Figure 2.1: Figure 2.2: Figure 3.1: Figure 3.2: Figure 4.1: Figure 5.1: Figure 5.2: Proposed 8 line installation on 200 East from Center St. to 100 North Proposed 8 line installation on 100 West from 550 North to 750 North Proposed 10 line installation along 300 South Booster Station, interior view Upper Tank Booster Station, exterior view Zoning map with existing distribution system Zoning map with future distribution system Fire hydrant installation Indoor demand pattern Outdoor demand pattern iii
5 1.0 INTRODUCTION / EXECUTIVE SUMMARY Water modeling is becoming an increasingly important part of hydraulic engineering. One application of hydraulic modeling is pipe network analysis. Using programmed algorithms to repeatedly solve continuity and energy equations, computer software can greatly reduce the amount of time required to analyze a closed conduit system. Such hydraulic models can become a valuable tool for cities to maintain their water systems and plan for future growth. The Utah Division of Drinking Water regulations require cities to maintain hydraulic models of their culinary water systems, and before additional connections can be made to the water system, a licensed professional engineer must model the additions to water system and determine if the additional connections can be made without negatively impacting the existing system. This is known as the Hydraulic Modeling Rule, or R in the State Administrative Code. The State of Utah has set the minimum pressure and flow requirements a culinary water system must meet. Before cities can qualify for state or federal funding to complete water system improvement projects, they must first demonstrate through a hydraulic model that they are providing the required minimum flows and pressures for all the service connections within the system, or that their improvement project will remediate any deficiencies to comply with the State s pressure and flow requirements. The purpose of this study is to analyze an existing culinary water system and determine several important items: 1. Identify any deficiencies that exist and determine what repairs should be made to ensure that the system can provide the required flow and pressure. 2. Using growth projections from the State Governor s office and the City s planning and zoning maps, estimate where and when future growth will occur. 3. Using these growth projections, analyze the water system and determine the capacity of the water source, storage, and distribution system. Once the capacity is determined, decisions can be made as to when aspects of the water system should be further developed, upsized, or replaced. The water system selected for this analysis was Millville City, a small town located in Northern Utah. A brief description of the culinary water system is given below. 1.1 Existing System Description: The existing water system is divided into an upper and lower pressure zone. These two zones are connected by a pressure reducing valve (PRV) which only allows water to flow from the upper to lower zone in the event of a large water demand such as a fire flow in the lower zone. The system is fed by three sources: the Glen Ridge Well, the Park Well, and Garr Spring. These sources are allowed to produce a total flow of 972 gpm in the summer season and 1,333 gpm in the winter season according to the approved water right applications. In addition to the three sources, there are three storage 1
6 reservoirs. The Glen Ridge Tank has a 1 million gallon (MG) capacity. The Park Tank has a 300,000 gallon capacity. The Upper Tank has a 1 MG capacity. The culinary water system consists of approximately 82,060 feet of pipe. The types of pipes installed based on city records are P.V.C., Ductile Iron, and Galvanized Steel. These pipes are shown in Figure 3.1, and listed in Table Proposed & Projected Additions and Improvements to the System: The future scenarios modeled include projected expansion of the City. These projected developments were made using the future land use map for Millville City. The majority of the additions are assumed to be residential lots. There are three main improvements needed to remediate existing deficiencies within the system. The first is a low pressure area located along Center Street from 180 East to 250 East during a fire flow condition. This deficiency is planned to be resolved by replacing 1260 of 4 pipe with 8 along Center Street, and installing 580 of 8 pipe along 200 East (future road). See Figure 1.1 for the location of this improvement. Figure 1.1: Proposed 8 line installation on 200 East from Center St. to 100 North 2
7 As seen on the previous page, Figure 1.1 shows the location of the proposed 8 line to provide better fire flow protection to the homes on the east end of Center Street. This solution for the low pressure area is preferred since the city already owns some property and has a right of way along this corridor for the future 200 East roadway. The second low pressure area is located at 700 North along Main Street. This deficiency may to be remediated by installing 1700 of 8 pipe along 100 West from 550 North to 750 North, creating a loop to in the system. See Figure 1.2 for the location of this improvement. Figure 1.2: Proposed 8 line installation on 100 West from 550 North to 750 north As seen above, Figure 1.2 shows the location of a proposed 8 line creating a loop to provide sufficient fire flow at the hydrant located at 750 North on Main Street. The final location of this pipe will be determined as development occurs in this area of Millville. The third low pressure area is located on the corner of 550 East and 300 South. This deficiency is planned to be remediated by connecting the three homes on the corner to the upper pressure zone. See Figure 1.3 for the location of this improvement. 3
8 Figure 1.3: Proposed 10 line installation along 300 South This improvement with a proposed 10 line from the upper pressure zone will eliminate the low pressure area located on the corner of 300 South and 550 East. It may also be used to pressurize a future irrigation system at the city park. Where sufficient data is available, the equivalent residential connection (ERC) or how much water an average household uses; is determined by analyzing the water use records over an extended period of time. High volume water users are removed from the data set, and an average water usage is determined in gallons per day. All connections to the water system are then referred to by the number of ERCs they represent. For example, a commercial business using a large amount of water may be said to be 4 ERCs, or use the equivalent amount of water of four average households. Based on current water use data, the total culinary water demand during a 24 hour period in the summer is 1,042,000 gallons. This is commonly referred to as a peak day demand. The springs and wells combined currently provide 1,490,400 gallons during a 24 hour peak day period. Assuming the same demands and household size for future estimates, the water system can support an additional 178 equivalent residential connections (ERCs) before reaching capacity. Continuing at a growth rate of 3.5% (Governor s Office of Planning and Budget 2008 Utah Baseline), this will take approximately 8 years to reach. The City is divided into an upper pressure zone and a lower pressure zone. The upper pressure zone has a 1 MG reservoir. The required storage based on the existing connections and 100% peak day emergency storage is 698,300 gallons. Based on existing water use records, there is capacity to support an additional 83 ERCs. Continuing at a growth rate of 3.5% this will take approximately 10 years to reach. The lower pressure zone has a 1.0 MG reservoir and a 300,000 gallon reservoir. The required storage based on the existing connections and fire flow is 1,212,000 gallons. These storage calculations assume that when there 4
9 is a fire in the lower pressure zone, the upper tank fire flow storage will be utilized since the increased demands will activate the PRV, allowing water from the upper zone to flow into the lower pressure zone. Based on existing water use records, an additional 189 ERCs can be made in the lower zone before reaching the capacity of 543 ERCs. Continuing at a growth rate of 3.5%, this will take approximately 12 years to reach. The booster station within the system currently provides approximately 600 gpm to the upper pressure zone. It typically runs 18 hours per day during peak day demand. Approximately 193 ERCs are fed by this booster pump. Based on current water use records, this pump can serve approximately 139 additional ERCs before reaching capacity. At a growth rate of 3.5%, this will take roughly 15 years. Figure 1.4: Booster Station, interior view Table 1.1: Summary of System Capacities Summary of System Capacities Item Max number of ERCs Existing Storage Future ERCs that can be served ERCs Capacity Source 725 (Entire System) Upper Zone Storage 276 (Upper Zone Only) MG Lower Zone Storage 543 (Lower Zone Only) MG Booster Pump 332 (Upper Zone Only) One item to note is the difference between the storage volume of the upper and lower zones and the number of ERC s that can be served by those reservoirs. The upper zone has 77% of the storage volume of the lower, yet it can only support 50% of the ERCs of the lower zone. This is due to the absence of irrigation or secondary water in the upper zone. This creates a large impact on the upper zone of the water system. 5
10 2.0 SOURCES AND FACILTIES 2.1 Sources: When analyzing any water system, it is critical to understand the sources supplying water to the system. Without adequate source, even the best designed water systems will fail to deliver the required flow to water users. Millville City has three sources for the culinary water system, and one source used for cemetery irrigation. The first is Garr Spring, which has four water right numbers. The second is the Glen Ridge Well and the third is the Park Well. The rights for the two wells are combined under one water right number. Skinner Spring water is leased to the cemetery district for irrigation. Table 2.1: Water sources and associated right number Source Water Right Number Garr Spring Garr Spring Garr Spring Garr Spring Park and Glenridge Wells Cache Valley Ranches Skinner Spring Dates From Oct. 1 to March 31 From Oct. 1 to March 31 From Oct. 1 to March 31 From April 1 to Sept. 30 Flow (cfs) Minimum Reliable Flow (cfs) Status Approved Approved Approved Approved Year Round 2 - Approved Year Round April 1 to Oct Ac-ft per year 15.6 Ac-ft per year - Approved 24 Ac-ft per year Diligence Claim Table 2.1 shows the peak supply during the summer months being approximately cfs, or 1.4 million gallons per day. Plus an additional 55.6 acre ft. to be used as needed. This is approximately 400,000 gallons per day more than the existing peak day demand. As Millville continues to grow, future potential sources include: Utilizing Garr Spring as shares are acquired through development Increasing capacity of the Park Well Implementing Aquifer Storage and Recovery (ASR). 6
11 2.2 Storage Facilities: Table 2.2: Storage Facilities The water system consists of three storage tanks as listed below: Tank Name Type of Material Diameter (ft) Depth (ft) Total Volume (gal) Glen Ridge Tank Concrete ,000,000 Park Tank Concrete ,000 Upper Tank Concrete ,000,000 Lowest level of Elevation of Tank Name equalization Outlet Elevation (ft) Overflow (ft) volume Glen Ridge Tank Park Tank Upper Tank Table 2.2 shows the storage capacity of the three reservoirs within the system. The city is currently divided into an upper and lower pressure zone. The Upper Tank feeds the upper pressure zone, and the Glen Ridge and Park Tanks feed the lower pressure zone. The upper pressure zone has an existing storage capacity of 1.0 MG. The lower pressure zone has an existing storage capacity of 1.3 MG. Figure 2.1: Upper Tank During Construction 7
12 2.3 Booster Stations: Millville City has one booster station which supplies 600 gpm to the Upper Zone. This booster pump is fed by the Park Tank and the lower pressure zone sources including Garr Spring, the Park Well and Glen Ridge Well. Figure 2.2: Booster Station, exterior view 2.4 Distribution System: The Millville City Water System consists of the following distribution pipes: Table 2.3: List of pipes by diameter and HW Coefficient used for modeling Diameter (in) Type Length (ft) HW Coefficient Used for Modeling 1.5 Galvanized Steel Galvanized Steel P.V.C Ductile Iron 8, Ductile Iron 22, Ductile Iron 25, P.V.C 1, Ductile Iron 16, P.V.C 1, Ductile Iron 4, P.V.C 1, Total 82,060 See Figure 3.1 for the location and diameter of these pipes. 8
13 3.0 EXISTING AND FUTURE CONNECTIONS 3.1 Service Area The current water system serves approximately 700 acres with 547 connections within the Millville City boundaries (See Figure 3.1 for a view of the city zoning and existing service area). Most of these connections are to residential lots. There are some small businesses within Millville including auto body, and manufacturing. At the projected growth rate of 3.5%, it is estimated that in 40 years, the number of connections will rise to 2,212. As new developments or growth come to Millville, the hydraulic model will be updated and output observed to ensure that water delivery requirements are met according to State Rules. The development or new connection(s) will not be approved until such time that required parameters are met for the situation. 9
14 10
15 11
16 Figures 3.1 and 3.2 show the existing and future distribution systems with the current zoning map. 3.2 ERC Evaluation: Where sufficient data is available, the equivalent residential connection (ERC) or how much water an average household uses; is determined by analyzing the water use records over an extended period of time. High volume water users are removed from the data set, and an average water usage is determined in gallons per day. All connections to the water system are then referred to by the number of ERCs they represent. For example, a commercial business using a large amount of water may be said to be 4 ERCs, or use the equivalent amount of water of four average households. The Millville City Water System currently serves 547 connections. Of those 547 connections, 265 irrigate with culinary water. Of the existing connections, there are only a few high volume water users. They account for 19.9 of the ERCs. The low volume water users such as the post office were conservatively assumed to require a full ERC. Table 3.1 shows a list of customers and their associated ERCs. The total number of ERCs served by the water system is 561. Table 3.1: List of High Volume Water Users and their associated ERCs Name ERCs Elementary School 1.45 LDS Church 7.74 Silicone Plastics 1.37 Residential Connection 3.27 Residential Connection 3.17 Residential Connection 2.94 The future scenario was also analyzed to estimate the number of ERCs that will likely be added to the city, and the estimated times at which the connections will occur. Presently, there are approximately 75 residential lots that the city has committed to serve, but have not yet physically connected to the infrastructure. These connections are assumed to each be one ERC. In the more distant future, a 40 year period was analyzed to assess the impacts future connections will have on the existing water system. With an annual growth rate of 3.5%, the total number of connections in 40 years would be 2,212. The demands for future growth areas were calculated using R , assuming a density of 3 connections per acre. 12
17 3.3 Growth Management Alternatives: As development occurs in Millville, extensions of system distribution lines are required to be installed by the developer. These lines are required to be installed to Millville City Standards. Developers are also required to bring water rights or shares to the City per ordinance. This allows for sustainability of water into the future. Where impacts from development are found in the water system, impact fees are collected by the City to improve storage, source and distribution lines to meet the requirements of the City and R
18 4.0 WATER DEMAND CRITERIA 4.1 Indoor Water Use Demand: Water audit records from 2003 to 2009 were used to determine the water consumption for Millville. The records indicate that the peak summer day indoor water use is approximately 160 gpd per capita. This compares with 220 gpd per capita using calculations from R309. With an average of 3.6 people per residential connection, an indoor demand of 160 x 3.6 = 576 gpd or 0.4 gpm. A factor of two was applied to the peak day demand to arrive at a peak instantaneous demand of 0.8 gpm. The peak instantaneous demand is used to size the distribution system. Indoor demand was simulated in the model in groups of users. These groups are in a geographically similar location with common water usage. These groups are called demand regions. All of the water demand from the users in the group are added together and used to represent demand on the water system from the demand region. 4.2 Outdoor Water Use Demand: The water audit records indicate that Millville residents use 532 gpd per capita of culinary water for irrigation use. With an average of 3.6 people per residential connection, an outdoor peak day demand is 532 x 3.6 = gpd or 1.33 gpm per ERC. An average lot size of 1/3 acre per ERC was assumed for the water model. This results in a peak day irrigation demand of 4 gpm/acre. In comparison R309 calculations show a peak day demand of 3.96 gpm per irrigated acre for zone 4 on the Irrigated Crop Consumptive Use Zones and Normal Annual Effective Precipitation map for Utah as prepared by the Soil Conservation Service. This map is available through the Utah Division of Drinking Water. The peak instantaneous demand was then determined by applying a factor of two to the peak day demand. The result is a peak instantaneous demand of 2.66 gpm per ERC. The same demand regions used for indoor demand are also used for outdoor demand. Again, the outdoor demand for the demand region is summed and applied together for each region to be used in the model. 14
19 4.3 Fire Flow Requirements: Fire flows were applied to the water system under the direction of the local fire authority (Cardell Nielsen (435) , 40 N 100 W Hyrum, UT), and in accordance with the International Fire Code and R-309. Fire hydrants exist within the Millville Water System and the majority were tested at 1000 gpm in the hydraulic model, noting the residual pressures. Figure 4.1: Fire hydrant installation Some structures in Millville required a higher fire flow based upon current codes. The largest of these structures was Millville Elementary. Based on the construction type and square footage of the structure, the required flow for this building applied to the model is 4,250 gpm for a duration of 4 hours. 4.4 Other Demand: There are no significant industrial or other types of water users in Millville City at this time. However, if a significant user were to develop in the community, the demands would be input into the water model for evaluation and impact on the water system. 4.5 Demand Versus Existing and/or Proposed Capacities The requirements in R were used to compare demands and capacities with regard to the source, storage, and distribution system. Based on current water use data, the total culinary water demand during a 24 hour period is 1,042,000 gallons. The springs and wells combined currently provide 1,490,400 gallons during a 24 hour peak day period. Assuming the same demands and household size for future estimates, the water system can 15
20 support an additional 178 ERCs before reaching capacity. At a growth rate of 3.5%, this will take approximately 8 years to reach. The City is divided into an upper pressure zone and a lower pressure zone. The upper pressure zone has a 1 MG reservoir. The required storage based on the existing connections and 100% peak day emergency storage is 698,300 gallons. Based on existing water use records, There is capacity to support an additional 231 ERCs. Continuing at a growth rate of 3.5% this will take approximately 10 years to reach. The lower pressure zone has a 1.0 MG reservoir and a 300,000 gallon reservoir. The required storage based on the existing connections and fire flow is 1,212,000 gallons. These storage calculations assume that when there is a fire in the lower pressure zone, the upper tank fire flow storage will be utilized since the increased demands will activate the PRV, allowing water from the upper zone to flow into the lower pressure zone. Based on existing water use records, an additional 189 ERCs can be made in the lower zone before reaching the capacity of 543 ERCs. Continuing at a growth rate of 3.5%, this will take approximately 12 years to reach. The booster station within the system currently provides approximately 600 gpm to the upper pressure zone. It typically runs 18 hours per day during peak day demand. Approximately 193 ERCs are fed by this booster pump. Based on current water use records, this pump can serve approximately 139 additional ERCs before reaching capacity. At a growth rate of 3.5%, this will take roughly 15 years. The distribution system was tested for minimum pressure requirements as defined in R under a peak instantaneous demand. The results of these tests are explained in section 5.4 of the report. 16
21 5.0 METHODOLOGY AND ANALYSIS 5.1 Hydraulic Model Used: When creating a hydraulic model of a pressurized pipe network, a decision has to be made regarding the complexity of the model needed. When the system being modeled does not have a combination of pressure boosting station and pressure reducing valves, an instantaneous model is developed. This consists of a snapshot of the demands on a model in a static scenario. Due to the significant fire suppression demand created by the Millville Elementary School, an extended period simulation is deemed necessary to assess the impact the demand will have on the distribution system as well as the storage facilities. This extended period model was created using computer software known as InfoWATER (MWHSoft). InfoWATER uses programmed algorithms to repeatedly solve the continuity and energy equations to determine the flow and residual pressures at specific nodes in the pipe network. The Hazen-Williams equation is used to calculate the friction losses in the pipes. Typical time patterns (Figures 5.1 and 5.2) were applied to the indoor and outdoor demands on the system to simulate the fluctuations in demand commonly seen on culinary water systems. This simulation was run over a one week period in order to allow the model to stabilize and show routine operation. The significant fire flow demand created by the elementary school was applied over a four hour period, with peak day demands applied on the rest of the system. 5.2 Hydraulic Model Input: Using the 2006 HRO aerial images from the Utah GIS Portal, connections were identified visually. Then using the water audit records, average daily demands were calculated and applied to the identified connections. Using the water system as built plans from the city, pipes were drawn into the model with their associated diameters and friction coefficients. A list of the pipe lengths by diameter is shown below: 17
22 Table 5.1: List of pipes by diameter and HW Coefficient used for modeling Diameter (in) Type Length (ft) HW Coefficient Used for Modeling 1.5 Galvanized Steel Galvanized Steel P.V.C Ductile Iron 8, Ductile Iron 22, Ductile Iron 25, P.V.C 1, Ductile Iron 16, P.V.C 1, Ductile Iron 4, P.V.C 1, Total 82,060 Table 5.1 shows the different pipe sizes with their associated lengths and material types, as well as the Hazen Williams Coefficient used for the model. Demand regions were added to the model with a demand node in each region. Elevations for the demand regions in the model were obtained from a Digital Elevation Model (DEM) file from the Utah GIS Portal. Elevations for the tanks and PRV were determined from surveyed measurements. For the existing scenarios, the number of ERCs within the demand regions were summed and applied to their respective regions. For the future scenarios, the demands were calculated by determining the projected growth within the next ten years and estimating where this development is most likely to occur. These additional ERCs were then evenly distributed over their respective areas. The build out scenario was also modeled using future land use planning maps. Since build out for the City is far into the future, a brief review of the system needs was made. A detailed description of the scenarios modeled is included in section Field Calibration Methodology: Field calibration was performed by flowing six fire hydrants within the city. The selected test hydrants were first tested for static pressure. The static pressure is then taken on an adjacent hydrant. The test hydrant is then opened to full flow and the residual pressure is observed on the adjacent hydrant. A pitot gauge is used to measure the pressure in the flowing hydrant to calculate the flow. These flows are then applied to their corresponding locations in the model and the static and residual pressures are compared to ensure that the model is calibrated to what actually happens in the field. The calibration results are shown below in Tables 5.2 and
23 Table 5.2: Field calibration results - Test Hydrant Measured Static Pressure Measured Residual Pressure Model Residual Pressure* Test # Date Time Description of test hydrant Model Static Pressure* Δ Δ 1 6/22/ : N. 350 E /22/ : N. Main /22/ : E. 100 N /22/ :30 Center 180 E /22/ : N. 100 W /22/ : W. 200 S Table 5.3: Field calibration results - Adjacent Hydrant Measured Static Pressure Model Static Pressure* Measured Residual Pressure Model Residual Pressure* Test # Description of adjacent hydrant Δ Δ N. 350 E N. Main E. 100 N Center 100 E N. Main W. 200 S *Model was calibrated in a steady state (constant demand) condition. Tables 5.2 and 5.3 show how well the computer model compares with what actually occurs in the field. The static pressure columns show the pressure at the corresponding hydrants before the hydrants are opened. The residual pressure columns show the pressure at the hydrants while the test hydrant is open. The test hydrant is the hydrant that is actually opened, and the adjacent hydrant is a hydrant usually a block away where the pressures are observed before and during the flow test. The Δ column shows the difference between the computer model and the field test results. With the exception of test number 6, all the model calibrations compared fairly well with what was seen in the field. This outlier could be caused by an erroneous elevation at that location from the DEM file, or an unseen demand occurring on the system near the location of the test hydrant at the time the test was performed. 5.4 Hydraulic Model Analysis: Since the water distribution system supplies water for indoor as well as outdoor use, an extended period simulation was used to account for these two different demands. The time patterns used over a 24 hour period are shown below. The peak of the demand pattern shown as 100% corresponds to the peak instantaneous demand on the system. Time zero in the pattern corresponds to midnight. 19
24 Percent of Peak Day Demand Percent of Peak Day Demand Figure 5.1: Indoor demand pattern Indoor Demand Pattern 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Time (hr) Figure 5.1 shows the peak indoor demands on the system occurring at 7-8:00 a.m. with another spike corresponding to 6:00 p.m. These peak times simulate the demands created by people getting ready, showering etc. in the morning, and preparing dinner, bathing children etc. in the evening. Figure 5.2: Outdoor demand pattern Outdoor Demand Pattern 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Time (hr) Figure 5.2 shows the peak outdoor demands on the system occurring at 6-7:00 a.m., with another spike occurring at 9:00 p.m. These peak times simulate the actual demands created by people watering their lawns in the evening and early morning. Millville City does not currently have real time flow measuring devices, so the time series curves represented above are estimates based on the demands typically seen on culinary water systems. 20
25 Both the indoor and outdoor demands were applied simultaneously over a 24 hour period. This pattern repeats itself over a 7 day period to give the model time to stabilize and observe the overall effects of the peak demands on the water system. The State of Utah requires the hydraulic model be analyzed under various scenarios to mimic the different lengths and intensities of demands placed on the water system. For each scenario, there are minimum pressure requirements to be met. A hydraulic analysis was performed for eight different scenarios, described below: 1. Existing Peak Day Demand: A peaking factor of 2.0 was applied to the average day demand, then these demands were applied to the existing water system model. Any problem areas where the pressure dropped below 40 psi were noted. 2. Existing Peak Day Demand + Fire Flow: A peaking factor of 2.0 was applied to the average day demand, then these demands were applied to the existing water system. At the same time, a fire flow of 1000 gpm was applied at the critical junctions throughout the system (one at a time). The residual pressures were noted, flagging any problem areas where the pressure dropped below 20 psi. 3. Existing Peak Day Demand + Fire Flow at School: A peaking factor of 2.0 was applied to the average day demand, then these demands were applied to the existing water system. At the same time, a fire flow of 4,250 gpm was applied at the Millville Elementary School for a duration of 4 hours. The residual pressures were noted, flagging any problem areas where the pressure dropped below 20 psi. 4. Existing Peak Instantaneous Demand: A peaking factor of 2.0 was applied to the peak day demand to arrive at the peak instantaneous demand. These demands were then applied to the existing water system. The pressures were noted, flagging any problem areas where the pressure dropped below 30 psi. 5. Future Peak Day Demand: A peaking factor of 2.0 was applied to the average future day demand, then these demands were applied to the future water system models. Any problem areas where the pressure dropped below 40 psi were noted. 6. Future Peak Day Demand + Fire Flow: A peaking factor of 2.0 was applied to the average day demand, then these demands were applied to the future water system. At the same time, a fire flow of 1000 gpm was applied at the critical junctions throughout the future system (one at a time). The residual pressures were noted, flagging any problem areas where the pressure dropped below 20 psi. 21
26 7. Future Peak Day Demand + Fire Flow at School: A peaking factor of 2.0 was applied to the average day demand, then these demands were applied to the future water system. At the same time, a fire flow of 4,250 gpm was applied at the Millville Elementary School for a duration of 4 hours. The residual pressures were noted, flagging any problem areas where the pressure dropped below 20 psi. 8. Future Peak Instantaneous Demand: A peaking factor of 2.0 was applied to the peak day demand to arrive at the peak instantaneous demand. These demands were then applied to the future water system model. The pressures were noted, flagging any problem areas where the pressure dropped below 30 psi. 22
27 6.0 ANALYSIS RESULTS & CONCLUSION 6.1 Hydraulic Model Results: A list of the results for the eight scenarios modeled is included below. 1. Existing Peak Day Demand: The only concern under this scenario is the area on the corner of 300 S and 550 E. The pressure drops to 25 psi. This problem will be remediated in the future by connecting this line to the upper pressure zone and installing a pressure reducing valve. At that time, the pressures under this scenario will all meet the 40 psi minimum. See Figure 1.3 for the location of this planned improvement. 2. Existing Peak Day Demand + Fire Flow: There are two main improvements needed to remediate existing deficiencies. The first is a low pressure area located along Center Street from 180 East to 250 East. This deficiency is planned to be resolved by replacing 670 of 4 pipe with 8 along center street, and installing 780 of 8 pipe along 200 East (future road) creating a loop in the system. The second low pressure area is located at 700 North along Main Street. This deficiency may be remediated by installing 1700 of 8 pipe along 100 West from 550 North to 750 North, creating a loop to in the system. See Figures 1.1 and 1.2 for the locations of these planned improvements. 3. Existing Peak Day Demand + Fire Flow at School: There are no problems meeting the existing peak day demand and fire flow at the school (4250 gpm for 4 hours). 4. Existing Peak Instantaneous Demand: The same problem under the existing peak day demand exists under this scenario. The future improvements mentioned above will resolve this deficiency as well. 5. Future Peak Day Demand: There are no problems meeting the peak day demand in the 10 year future or the build out scenarios once the above mentioned improvements are made. 6. Future Peak Day Demand + Fire Flow: There are no problems meeting the peak day demand + fire flow in the future ten year or build out scenarios once the above mentioned improvements are made. 7. Future (10 Year) Peak Day Demand + Fire Flow at School: There are no problems meeting the peak day demand gpm fire flow at the school in the 10 year future scenario once the above mentioned improvements are made. A build out scenario was not modeled for peak day demand + fire flow at the school since the probability is very 23
28 low that the same school building will still be in operation at the time the city reaches build out capacity. 8. Future Peak Instantaneous Demand: There are no problems meeting the peak instantaneous demand in the 10 year future and build out scenarios once the above mentioned improvements are made. 6.2 Comparison of Field Measurements and Model Results: Once the existing model was calibrated, it was analyzed with the help of the system operator Gary Larsen to ensure that the model accurately portrayed what was occurring in the water system. See Tables 5.2 and 5.3 for a comparison of the results. 6.3 Conclusion of Project Impact from Model Results: By following the list of proposed projects listed in this plan, the City will be able to service their citizens with adequate pressure and flow of water. Future developments will be evaluated for effects using this model so the system can maintain its high level of operation. 6.4 Rule Compliance Conclusion With the designed improvements, all existing and new water users will be provided the quantity of water at pressures compliant with State rules (R Administration: General Requirements of Public Water Systems Minimum Water Pressure), in Millville City. 24
29 References "Utah Administrative Code." Utah Administrative Code. Web. 13 Sept < Bennett, John F. "2008 Utah Baseline." Envision Utah. Utah.gov, Web. 12 Sept Nielsen, Cardell. Personal Interview. June 2, 2011 Soil Conservation Service. "Utah: DEQ: DDW: Irrigation Zone Map." Map. Utah: DEQ: DDW: Irrigation Zone Map. N.p., n.d. Web. 11 Oct <
30 NODE Appendix A Existing Peak Day Demand Pressures ELEVATION INDOOR DMD OUTDOOR DMD MIN_PRESS Comments Not a service connection Not a service connection Not a service connection Not a service connection Not a service connection Not a service connection Not a service connection To be resolved by connecting to high pressure line To be resolved by connecting to high pressure line Not a service connection Not a service connection Not a service connection Not a service connection
31
32
33
34
35 ID Appendix B Existing Peak Day Demand + Fireflow Pressures Total Demand (gpm) Critical Node 1 ID Critical Node 1 Pressure (psi) Critical Node 1 Head (ft) Adjusted Fire- Flow (gpm) Available Flow at Hydrant (gpm) Notes: 60 1, ,535-22, No Hydrant here 44 1, ,834-6, No Hydrant here 88 1, ,399 1, No Hydrant here 50 1, , No Hydrant here 18 1, , No Hydrant here 20 1, , No Hydrant here 52 1, , No Hydrant here J262 1,000 J , Future line to north will resolve 12 1, , No Hydrant here 10 1, , No Hydrant here 14 1, , No Hydrant here 240 1, , No Hydrant here 16 1, , ,001 No Hydrant here 124 1, , No Hydrant here J146 1,000 J , No Hydrant here 194 1,003 J , No Hydrant here J96 1,001 J , , , , ,000 J ,779 1,126 1, , ,782 1,419 1, , ,782 1,656 2, , ,782 1,637 1,612 J48 1, ,782 1,654 1, , ,783 1, , ,783 1,799 4,032 J188 1, ,783 2,019 1, , ,783 2,004 4, , ,783 2,004 2,292 J12 1, ,783 2,123-5, , ,783 2,391 3, , ,783 2,449 4,205 J252 1, ,783 2,737 4,540 J138 1, ,783 3,022 5, , ,783 3,179 4, , ,783 3,226 6,106
36 120 1, ,783 3,227 5,736 J72 1, ,783 3,265 5,557 J78 1, ,783 3,265 4,749 J70 1, ,783 3,302 4,954 J74 1, ,783 3,302 4, , ,783 3,346 1,822 J76 1, ,783 3,332 3,700 J68 1, ,783 3,334 5,453 J94 1, ,783 3,401 3, , ,783 3,444 3, , ,783 3,421 6, , ,783 3,444 6, , ,783 3,625 6, , ,783 3,834 6, , ,783 3,880 6, , ,783 3,892 4, , ,783 3,961 5, , ,783 3,980 2, , ,783 4,103 6, , ,783 3,404-14, , ,783 4,197 3, , ,783 4,238 1, , ,783 4,242 1, , ,783 4,270 2, , ,783 4,288 1, , ,783 4,278 6, , ,783 4,286 4, , ,783 4,327 6,637 J264 1, ,783 4,359 1,213 J152 1, ,783 4,363 1, , ,783 4,359 4,319 J174 1, ,783 4,359 2,865 J182 1, ,783 4,359 1, , ,783 4,409 6, , ,783 4,443 6, , ,783 4,516 4, , ,783 4,726 1, , ,783 4,724 2, , ,783 4,757 4, , ,783 4,779 5, , ,783 4,813 7,082
37 58 1, ,783 4,846 7, , ,783 5,502 3, , ,783 5,704 8, , ,783 5,626 8, , ,783 5,620 7, , ,783 5,968 4, , ,783 6,357 2, , ,783 6,403 2, , ,783 7,002 2, , ,783 7,017 7, , ,783 6,413 7, , ,783 8,076 6, , ,783 6,743 2, , ,783 6,985 5,717 J52 1, ,783 7,027 5, , ,783 7,241 4, , ,783 7,302 1, , ,783 7,300 3,700 J178 1, ,783 7,308 1, , ,783 7,310 3, , ,783 10,225 3, , ,783 7,418 4,876 J180 1, ,783 7,539 3,449 J86 1, ,783 7,745 4,059 J42 1, ,783 7,747 3, , ,783 7,906 4, , ,783 7,916 3, , ,783 8,010 4, , ,783 13,561 6,090 J54 1, ,783 2,422 J60 1, ,783 2,554 J62 1, ,783 2,678 J84 1, ,783 2, , ,783 3, , ,783 2,773 J58 1, ,783 2,632 J40 1, ,783 2,597 J38 1, ,783 2, , ,783 1, , ,783 2,875 J32 1, ,783 2,780
38 144 1, ,783 2,955 J26 1, ,783 2, , ,783 3, , ,783 2,903 J156 1, ,783 2,444 J158 1, ,783 2, , ,783 2,576 J154 1, ,783 2,463 J140 1, ,783 5, , ,783 2,901 J16 1, ,783 3, , ,783 2, , ,783 2,987 J18 1, ,783 3, , ,783 3, , ,783 3, , ,783 3,127 J20 1, ,783 2,878 J22 1, ,783 3,611 J24 1, ,783 3, , ,783 3,081 J10 1, ,783 3, , ,783 2, , ,783 2,456 J28 1, ,783 2,590 J30 1, ,783 3, , ,783 2,711 J36 1, ,783 3, , ,783 2, , ,783 2, , ,783 2,290 J44 1, ,783 2, , ,783 2, , ,783 3, , ,783 5,334 J56 1, ,783 2, , ,783 8, , ,783 2, , ,783 3,137 J64 1, ,783 2,740 J66 1, ,783 2,811
39 140 1, ,783 1, , ,783 2, , ,783 3, , ,783 2, , ,783 3, , ,783 2,625 J80 1, ,783 2,461 J82 1, ,783 2, , ,783 3, , ,783 2,871 J90 1, ,783 2,710 J92 1, ,783 2, , ,783 2, , ,783 3,107 J98 1, ,783 4,188
40 Appendix C Existing Peak Day Demand + Fireflow at School Pressures NODE ELEVATION INDOOR DMD FIREFLOW DMD MIN_PRESS Notes Not a service connection Not a service connection Not a service connection Not a service connection Node at School
41
CONCEPTUAL UTILITY REPORT FOR THE CANYONS PHASE 1 CITY OF CASTLE PINES, CO
CONCEPTUAL UTILITY REPORT FOR THE CANYONS PHASE 1 CITY OF CASTLE PINES, CO PREPARED FOR: SHEA HOMES 9380 STATION ST., SUITE 600 LONE TREE, CO 80124 PHONE: 303-791-8180 CONTACT: RYAN MCDERMED PREPARED BY:
More informationFINAL UTILITY REPORT Eastcreek Farm Thornton, CO
FINAL UTILITY REPORT Eastcreek Farm Thornton, CO October 14, 2016 JN: 13049 Prepared for: York 80, LLC 12460 1 st Street Eastelake, CO 80614 P: 303.457.2966 Prepared by: Jansen Strawn Consulting Engineers
More information2005 City of Santa Paula Potable Water System Master Plan Amendment
2005 City of Santa Paula Potable Water System Master Plan Amendment City of Santa Paula Project Engineer Randy Toedter, PE Brian Yanez June, 2012 970 Ventura Street Santa Paula, CA 93060 PURPOSE OF THE
More informationDowntown Lee s Summit Parking Study
Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis
More informationUS 81 Bypass of Chickasha Environmental Assessment Public Meeting
US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments
More informationAlpine Highway to North County Boulevard Connector Study
Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationSTAFF REPORT. To: Planning Commission Meeting date: April 12, 2017 Item: UN Prepared by: Robert Eastman
# 5 ) UN-15-17 LA SIERRA AUTO SALES SPECIAL USE PERMIT VEHICLE SALES PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: April 12, 2017 Item: UN-15-17 Prepared by: Robert Eastman GENERAL
More informationWATER SYSTEM SIZING Introduction Residential Water System Sizing
WATER SYSTEM SIZING Introduction It is crucial that water supply systems are properly sized. Well owners are often concerned about whether or not there will be enough water for their needs. The area geology
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS
ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS TABLE OF CONTENTS SECTION PAGE 8.1 GENERAL STANDARDS...8-2 8.2 PRIVATE DRIVEWAY PROVISIONS...8-4 8.3 OFF-STREET PARKING STANDARDS...8-5 8.4 OFF-STREET
More informationPASCO COUNTY UTILITIES SERVICE CONNECTION APPLICATION Single Residential or Commercial
X IX V IVII XI XI I VI I IV V II III Pasco County Utilities Depart. Administration Building 1942 Central Boulevard Land O Lakes, Fl. 34637 PASCO COUNTY UTILITIES SERVICE CONNECTION APPLICATION Single Residential
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationEnergy Performance Information Request Timeline
Energy Performance Information Request Timeline Project Title: UT Project # Project Manager: Submitted by: Day Submitted: The timeline below outlines a comprehensive list of required documents and when
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationTABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES...
Transportation Impact Fee Study September 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS......4 POTENTIAL FUNDING SOURCES...7 PROPOSED
More informationTravel Forecasting Methodology
Travel Forecasting Methodology Introduction This technical memorandum documents the travel demand forecasting methodology used for the SH7 BRT Study. This memorandum includes discussion of the following:
More informationAppendix E Water Supply Modeling
Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over
More informationWOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations
More informationA Salt Marsh Advancement Zone Assessment of Greenwich, Connecticut
A Salt Marsh Advancement Zone Assessment of Greenwich, Connecticut Front cover image: Open space and unprotected parcels critical to the conservation of marsh advancement corridors in Greenwich; from the
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationParks and Transportation System Development Charge Methodology
City of Sandy Parks and Transportation System Development Charge Methodology March, 2016 Background In order to implement a City Council goal the City of Sandy engaged FCS Group in January of 2015 to update
More informationRecommended Vision for the Downtown Rapid Transit Network
Recommended Vision for the Downtown Rapid Transit Network April 2008 Presentation Overview Context Transit options Assessment of options Recommended network Building the network 2 1 Rapid Our Vision Reliable
More informationGreen Line LRT: Beltline Segment Update April 19, 2017
Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street
More informationSCAN Land Use and Transportation Committee Report June 10, 2015
DRAFT DRAFT DRAFT Exhibit A to SCAN Minutes - June 10, 2015 SCAN Land Use and Transportation Committee Report June 10, 2015 Gaiety Hollow In April the Committee provided testimony in support of the Lord
More informationInternal Audit Report. Fuel Consumption Oversight and Coordination TxDOT Internal Audit Division
Internal Audit Report Fuel Consumption Oversight and Coordination TxDOT Internal Audit Division Objective To determine if a process exists to ensure retail fuel consumption is appropriately managed and
More informationMr. John Aitken June 6, 2017 Page 2
Mr. John Aitken June 6, 2017 Page 2 quarterly period of 2016. Fluctuations in noise exposure from reporting period to reporting period are to be expected due to ongoing changes in aircraft activity levels,
More informationNPCC Natural Gas Disruption Risk Assessment Background. Summer 2017
Background Reliance on natural gas to produce electricity in Northeast Power Coordinating Council (NPCC) Region has been increasing since 2000. The disruption of natural gas pipeline transportation capability
More informationTRAVEL DEMAND FORECASTS
Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) TRAVEL DEMAND FORECASTS A. Introduction 1. The purpose of the travel demand forecasts is to assess the impact of the project components
More informationTown of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology
Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology Prepared by the Londonderry Community Development Department Planning & Economic Development Division Based
More informationSALLAL WATER ASSOCIATION
P.O. Box 378 North Bend, WA 98045-0378 (425) 888-3650 Fax (425) 831-5392 Member Owned Co-op email: info@sallal.com SALLAL WATER ASSOCIATION MASTER RATE SCHEDULE - 2018 (Effective 01/01/18) SALLAL WATER
More informationHighway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary
Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared
More informationTemporary Sales Trailer Application
Development Services Department Building Division 311 Vernon Street Roseville, California 95678-2649 Temporary Sales Trailer Application General: Requests for temporary sales trailers, which comply with
More informationSTATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted June 20, 2013)
RULE 9610 STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted June 20, 2013) 1.0 Purpose The purpose of this rule is to provide an administrative mechanism
More informationAct 229 Evaluation Report
R22-1 W21-19 W21-20 Act 229 Evaluation Report Prepared for Prepared by Table of Contents 1. Documentation Page 3 2. Executive Summary 4 2.1. Purpose 4 2.2. Evaluation Results 4 3. Background 4 4. Approach
More informationSpacing and Pattern Effects on DU LQ of Spray Nozzles
Spacing and Pattern Effects on DU LQ of Spray Nozzles Introduction Brent Q. Mecham 1 September 11, 2006 One of the current Turf and Landscape Best Management Practices published by the Irrigation Association
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationAppendix 5. Haymeadow Interim Traffic Analysis
Appendix 5 Haymeadow Interim Traffic Analysis 20 MEMORANDUM To: From: Rick Pylman Gary Brooks Bill Fox Date: September 15, 2016 Project: Subject: Haymeadow Evaluation of interim access configuration Currently
More informationMissouri Seat Belt Usage Survey for 2017
Missouri Seat Belt Usage Survey for 2017 Conducted for the Highway Safety & Traffic Division of the Missouri Department of Transportation by The Missouri Safety Center University of Central Missouri Final
More information11 October 12, 2011 Public Hearing APPLICANT:
11 October 12, 2011 Public Hearing APPLICANT: CARING TRANSITIONS PROPERTY OWNER: HARDEE REALTY CORPORATION REQUEST: Conditional Use Permit (motor vehicle rental) STAFF PLANNER: Leslie Bonilla ADDRESS /
More informationTexas Tech University Energy Savings Program October 2009 Update
Texas Tech University Energy Savings Program October 2009 Update The Texas Tech Energy Savings Update is being submitted in accordance with Governor s Executive Order RP 49, Electric Conservation by State
More informationVDOT Unused Facilities
VDOT Unused Facilities Appropriation Act Item 457 K.1 (2010) Report to the Chairmen of House Appropriations and Senate Finance Committees Virginia Department of Transportation 1401 East Broad Street Richmond,
More informationTable of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
More informationTransportation Statistical Data Development Report BAY COUNTY 2035 LONG RANGE TRANSPORTATION PLAN
Transportation Statistical Data Development Report BAY COUNTY 2035 LONG RANGE TRANSPORTATION PLAN Prepared for Bay County Transportation Planning Organization and The Florida Department of Transportation,
More informationANDERSON PROPERTY SITE ANALYSIS
ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion
More informationRURAL ROAD MAINTENANCE POLICY
Government of Yukon RURAL ROAD MAINTENANCE POLICY (Updated April 01, 2003 to reflect Department name change from Infrastructure to Highways and Public Works. No change to Policy.) November 1991 TABLE OF
More informationTransient Effects on Dynamic Torque for Butterfly Valves
Utah State University DigitalCommons@USU All Graduate Plan B and other Reports Graduate Studies 5-2013 Effects on Dynamic for Butterfly Valves Trevor N. Price Follow this and additional works at: https://digitalcommons.usu.edu/gradreports
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationSummer Reliability Assessment Report Electric Distribution Companies Perspective
Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.
More informationA Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012
A Guide to the medium General Service Conservation Rate BC Hydro Last Updated: February 24, 2012 Executive summary The way Medium General Service (MGS) accounts pay for electricity is changing. MGS is
More informationPublic Information Workshop
Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)
More informationPROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA
PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA Assessment of Helicopter Noise A report Prepared on behalf of: JamCo Constructions Pty Ltd PO Box 631 Yarraville Victoria 3013 Ref: 11573-3jg March 2015
More informationInternational Aluminium Institute
THE INTERNATIONAL ALUMINIUM INSTITUTE S REPORT ON THE ALUMINIUM INDUSTRY S GLOBAL PERFLUOROCARBON GAS EMISSIONS REDUCTION PROGRAMME RESULTS OF THE 2003 ANODE EFFECT SURVEY 28 January 2005 Published by:
More informationAbstract. Executive Summary. Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County
Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County Abstract The purpose of this investigation is to model the demand for an ataxi system in Middlesex County. Given transportation statistics for
More informationApplicable California Vehicle Code Sections, 2015 Edition
Applicable California Vehicle Code Sections, 2015 Edition Speed limits in California are governed by the California Vehicle Code (CVC), Sections 22348 through 22413; also, pertinent sections are found
More informationSolar*Rewards Frequently asked questions system size and customer usage
Solar*Rewards 1. Will a PV system work with my home? 2. Am I eligible to participate in the Solar*Rewards program? 3. What size system should I get? 4. Can a customer at a service location apply for the
More informationTHE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO
THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,
More informationDOWNTOWN DUNEDIN WALKER PARKING CONSULTANTS FEASIBILITY ANALYSIS FOR DOWNTOWN PAID PARKING
JUNE 18,2015 PROJECT # 15-2047.00 EXECUTIVE SUMMARY Parking in Downtown Dunedin has been and continues to be a growing point of concern. In an effort to address the parking issues, the City retained Walker
More informationThe Reduction of Parking Restrictions around Fire Hydrants:
The Reduction of Parking Restrictions around Fire Hydrants: An Examination of Parking Distances and Setback Regulations Len Garis, John Lehmann, and Alex Tyakoff January 2017 Executive Summary Fire hydrants
More informationAppendix G Aquilla Lake Pool Rise Recreational Resources
Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting
More informationWhich fuels do you use? 96% 34% 8% 5% 5% 1% 0.5% 2014 EQUIPMENT SURVEY
2014 EQUIPMENT SURVEY Diesel Still Dominates SBF s Equipment Survey finds that 96% of operations run some or all of their buses on diesel, while propane is the mostly widely used alternative fuel. Our
More informationCentral Oregon Association of REALTORS
Central Oregon Association of REALTORS 218 Quarter 3 Report www.coar.com 541-382-627 info@coar.com The Central Oregon housing market continued to see home price appreciation across most of the region in
More informationCommunity Advisory Committee. October 5, 2015
Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting
More informationDesignation of a Community Safety Zone in Honey Harbour in the Township of Georgian Bay
TO: FROM: Chair and Members Engineering and Public Works Committee Mark Misko, C.E.T. Manager, Roads Maintenance and Construction DATE: March 23, 2016 SUBJECT: REPORT NO: Designation of a Community Safety
More informationTraffic Impact Statement (TIS)
Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205
More informationLIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 11th Revised CPUC Sheet No. 80 Canceling 10th Revised CPUC Sheet No.
SOUTH LAKE TAHOE, CALIFORNIA 11th Revised CPUC Sheet No. 80 Canceling 10th Revised CPUC Sheet No. 80 APPLICABILITY TERRITORY This time-of-use rate schedule is optional for Customers for whom Schedule D-1
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationRe: 233 Armstrong Street Residential Condominium Traffic Brief
1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com August 8, 2008 TO3031TOP00 BY E-MAIL: gerry.lalonde@rogers.com Spencedale Properties 7 Cobb Court Ottawa,
More informationPump Station 7 Improvements
Project Business Case ID: C04 2/18/2017 Pump Station 7 Project Purpose: The purpose of this project is to ensure that Pump Station 7 continues to operate in an efficient and effective manner following
More informationCedar View Subdivision No. 2 Hillcrest Dr. Montrose, Colorado 81401
Cedar View Subdivision No. 2 Hillcrest Dr. 81401 Property Information Packet John Renfrow * Jim Renfrow M b f Renfrow Realty Member of: Rocky Mountain Commercial Brokers www.rmcbrokers.com Page 1 Executive
More informationARTICLE 7 OFF-STREET PARKING AND LOADING/UNLOADING 7.02 OFF STREET PARKING AND LOADING SPACE REQUIREMENTS
ARTICLE 7 OFF-STREET PARKING AND LOADING/UNLOADING 7.01 STORAGE IN FRONT YARD Nothing in this Ordinance shall permit the storage or parking of any vehicle or non-permanent structure within the required
More informationRate Schedules. Effective 1/1/2019
Rate Schedules 2019 Effective 1/1/2019 SUMMARY OF RATE SCHEDULES REVISIONS FOR RATES EFFECTIVE JANUARY 1, 2019 (1) Rate component changes for Residential and Heating Service rate schedules. (2) General
More informationAppendix B CTA Transit Data Supporting Documentation
RED ED-PURPLE BYPASS PROJECT ENVIRONMENTAL ASSESSMENT AND SECTION 4(F) EVALUATION Appendix B CTA Transit Data Supporting Documentation 4( Memorandum Date: May 14, 2015 Subject: Chicago Transit Authority
More informationBi-County Transitway/ Bethesda Station Access Demand Analysis
Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction
More informationTraffic Engineering Study
Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
Date: March 26, 2013 CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM To: From: The Honorable City Council c/o City Clerk, Room 395 Attention: Honorable Mitchell Englander, Chair, Public Safety Committee
More informationApril 2010 April 2010 Presented by Alan Eirls
April 2010 April 2010 Presented by Alan Eirls A Partnership Between the Coeur d Alene Tribe, the State of Idaho, the KMPO, and Kootenai County. Current System The Citylink system began on the Coeur d Alene
More informationRight-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001
Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas
More informationCraig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject
TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022
More informationJCP&L Verbatim Response to Middletown Township s Questions
JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses
More informationInterstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Output
NDSU Dept #2880 PO Box 6050 Fargo, ND 58108-6050 Tel 701-231-8058 Fax 701-231-6265 www.ugpti.org www.atacenter.org Interstate Operations Study: Fargo-Moorhead Metropolitan Area 2015 Simulation Output Technical
More informationKing Soopers #116 Thornton, Colorado
Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. T R A F F I C I M P A C T S T U D Y King Soopers #116 Thornton, Colorado Prepared for Galloway & Company
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationCOUNTY ROAD SPEED LIMITS. Policy 817 i
Table of Contents COUNTY ROAD SPEED LIMITS Policy 817.1 PURPOSE... 1.2 APPLICABILITY... 1.3 DEFINITIONS... 1.4 STATE ENABLING LEGISLATION... 2.5 SPEED LIMITS ON COUNTY ROADS (CCC 11.04)... 2.6 ESTABLISHING
More informationConstruction Realty Co.
MEMORANDUM TO: FROM : Jeff Pickus Construction Realty Co. Luay R. Aboona, PE Principal 9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 DATE: May 22, 2014 SUBJECT:
More informationAssessing Your Sprinkler Irrigation System
Assessing Your Sprinkler Irrigation System Andrew Petersen, P. Ag Regional Resource Specialist B.C. Ministry of Agriculture Outline 1. Water Supply 2. System Sketch 3. Sprinkler spacing 4. Nozzle size
More informationCordova Psychrophiles Bio-Digester. Benefit-Cost and Sensitivity Analysis
Cordova Psychrophiles Bio-Digester Benefit-Cost and Sensitivity Analysis December 2012 Prepared by: Sohrab Pathan, Alejandra Villalobos Meléndez and Ginny Fay Institute of Social and Economic Research
More informationENERGY EFFICIENCY NATIONAL BUILDING REGULATIONS. Development Management Department 1 of 49
ENERGY EFFICIENCY NATIONAL BUILDING REGULATIONS 1 of 49 BACKGROUND 2 of 49 National Energy Efficiency Strategy of the Republic of South Africa March 2005 ( Reviewed 2008 / 2011 ) 3 of 49 OBJECTIVES Develop
More informationAppendix H TRAFFIC IMPACT ANALYSIS
Appendix H TRAFFIC IMPACT ANALYSIS Teichert Boca Quarry Expansion Traffic Impact Analysis Prepared for Teichert Aggregates Prepared by TRANSPORTATION CONSULTANTS, INC. LSC Transportation Consultants, Inc.
More informationLIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 20th Revised CPUC Sheet No. 84 Canceling 19th Revised CPUC Sheet No.
SOUTH LAKE TAHOE, CALIFORNIA 20th Revised CPUC Sheet No. 84 Canceling 19th Revised CPUC Sheet No. 84 APPLICABILITY This rate schedule is applicable to all domestic power service to separately metered single
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationMEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:
MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed
More informationSpeed Evaluation Saw Mill Drive
Speed Evaluation Saw Mill Drive Prepared for: Mount Laurel Township Burlington County, New Jersey Prepared by: Dana Litwornia Litwornia & Associates, Inc. Transportation, Traffic & Environmental Engineering
More informationMaine Medical Center Campus-Wide Parking Study
Overview Maine Medical Center (MMC) retained VHB to conduct a campus-wide parking study that includes an analysis of demand and supply for patient, visitor, and employee parking on MMC s Bramhall Campus.
More informationPurpose: General Provisions:
10-19-1 Purpose: The purpose of off-street parking requirements is to promote traffic/pedestrian safety and efficiency and to minimize hard surfaced areas to reduce storm water run-off and visual impacts
More informationFederal Way Link Extension
Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate
More informationEXHIBIT A EAST VALLEY WATER DISTRICT SCHEDULE OF WATER AND WASTEWATER RATES AND CHARGES
EXHIBIT A EAST VALLEY WATER DISTRICT SCHEDULE OF WATER AND WASTEWATER RATES AND CHARGES UPDATED MAY 24, 2017 Table of Contents Section 1: Water Service Charges... 2 Monthly Water System Charge... 2 Commodity
More informationWildland Solutions RDM Monitoring Procedure Keith Guenther November 2007 version
Wildland Solutions RDM Monitoring Procedure Keith Guenther November 2007 version Annually create an RDM zone map and a pasture success map with supporting information collected at monitoring reference
More information