ATC Planning Zone 3 Generation Integration Screening Study. December, 2018

Size: px
Start display at page:

Download "ATC Planning Zone 3 Generation Integration Screening Study. December, 2018"

Transcription

1 Page 1 ATC Planning Zone 3 Generation Integration Screening Study December, 2018 ATC voluntarily performed a high level, steady-state screening of transmission facilities in ATC Planning Zone 3, which encompasses the southwestern portion of Wisconsin using the 2028 summer peak model from the Year Assessment. This was done to assist generation developers with the preliminary identification of potential locations where existing transmission facilities may be able to accommodate the addition of new and/or additional generation capacity. All potential locations were screened for single contingency 1, steady-state limitations. The study assumes single/nearby combination locations and does not include any generation presently in the MISO queue. Locations that could not accommodate 100 MW of generation for a single contingency were removed from the tables that were produced through this effort. ATC has not performed any analysis to identify the scope or cost of work to eliminate the limit(s) that were identified for any of the contingencies that were noted. ATC may choose to perform similar screening studies of other portions of its footprint in the future, as system conditions and circumstances warrant. Additional steady state, multiple contingency 2 analysis was performed for all 345 kv locations. Multiple contingency analysis was also performed for all 138 kv and 69 kv locations that appeared to be capable of hosting 100 MW or more of generation under steady-state single contingency conditions. Multiple contingency analyses resulted in reduced generation capacity as compared to single contingency screening. ATC has not performed any analysis to identify the scope or cost of work to eliminate the limit(s) that were identified for any of the contingencies that were noted. ATC s initial screening did not include stability analysis. Since different types of generating units have substantially different stability performance characteristics, a stability analysis would not be generally applicable for this type of screening study. Additionally, the stability analysis would result in different and likely less potential capability than what is depicted in this steady-state screening study. Finally, the study analyzed only one potential generation site at a time and, as such, the are not necessarily additive. Tables that follow below identify the location, screening (rounded to the next lowest 10 MW) and the Zone 3 sub-zone where the existing transmission facility is located. Figure 1 depicts six subzones to aid in identification of applicable locations, as follows: Table 1 illustrates the of the analysis for 345 kv sites. Table 2 and 3 provides the of the analysis for 161 and 138 kv sites respectively where the generation capability appeared to be greater than 100 MW under single contingency conditions. The multiple contingency column is listed as - when there was zero generation capability under multiple contingency conditions. This could occur when there are only two outlets at the site. Table 4 provides the of the analysis for 69 kv sites where the generation capability appeared to be greater than 100 MW under single contingency conditions. The multiple contingency column is listed as - when there was zero generation capability under multiple contingency conditions. This could occur when there are only two outlets at the site. This was a high-level screening study using a single steady-state model and a particular set of assumptions, as described herein. The study listed in the tables below may not be indicative of the that 1 refers to NERC Category P1s and No Load Loss Allowed P2s. 2 Multiple contingency refers to NERC Category P2.1 + P1 and P6s (P1 + P1).

2 Page 2 would be produced via the MISO Tariff Attachment X Generation Interconnection process. System stability, both angular and voltage, were not considered in this screening study. ATC makes no representations, either expressed or implied, that the scope of the interconnection facilities or transmission upgrades required to connect generation at these sites would be minimal, or even feasible. screening do not reflect any possible reductions required for multiple contingencies. The analysis considered 69 kv, 138 kv, 161 kv, and 345 kv nodes in the power flow model, but did not consider actual bus configuration or the existence of buses for constructability at the locations that were studied. Corresponding interconnection facilities and transmission upgrades will be determined by the MISO Tariff Attachment X process. For ATC TYA models, generally generation interconnections are only modeled if there is a signed GIA and generation retirements are only modeled if MISO has completed the associated Attachment Y-1 process. This non-binding, voluntary study is presented for informational purposes only and ATC makes no guarantee or warranty that the information presented herein is accurate or complete Steady-State Analysis Power Flow Assumptions Bay Lake projects in service Kittyhawk substation o Interconnection of J390 units Cardinal-Hickory Creek in service o Addition of Hill Valley substation Bain-Spring Valley-North Lake Geneva project in service Several rebuilds/uprates in the surrounding area T-D Projects in service o Northern Lights o Edgerton o Mt. Pleasant o State Line o Juneautown o Schofield Retirement of the following facilities o Nelson Dewey T32 transformer Bus/Line/Transformer reconfigurations o Lincoln o Racine o Arcadian o Williams Bay o Paddock o Columbia 345/138 transformers o Saukville

3 Page kv Site Table 1: Generation Capability at 345 kv Sites ATC Planning Zone 3 Multiple contingency Hill Valley B Cardinal C North Madison C Columbia D Rockdale E Kittyhawk/J F Paddock F

4 Page kv Site Table 2: Generation Capability at 161 kv Sites ATC Planning Zone 3 Multiple contingency Nelson Dewey B

5 Page 5 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone kv Site Multiple contingency Spring Green A Troy A Wyoming Valley A Albany B Bass Creek B Darlington B Edgerton B Eden B Falcon / Quiltblock B Hillman B Lancaster B Nelson Dewey B North Monroe B Potosi B Verona B American C Blount C Cardinal C Cross Country C Christiana C Colloday Point C Fitchburg C Femrite C Huiskamp C Kegonsa C McFarland C North Madison C Northern Lights C Oak Ridge C Pleasant View C Reiner C Sprecher C Sycamore C Vienna C Yahara River C

6 Page 6 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone 3 (continued) 138 kv Site Multiple contingency ACEC Lewiston D Artesian D Birchwood D Columbia D Dell Creek D Hamilton D Kilbourn D Kirkwood D Loch Mirror D Lake Delton Tap D Nishan D Portage D Rock Springs Tap / Rock Springs D Staff D Trienda D Zobel D Academy E Boxelder/Lakehead Waterloo E Butler Ridge Wind E Cambridge Tap/ Cambridge E Crawfish River E Fox Lake E Friesland E Fountain Prairie E Hubbard E Hustisford E Jefferson E London E Lakehead Cambridge Tap E North Beaver Dam / East Beaver Dam E North Randolph E Rockdale E Rubicon E Stony Brook E Tyranena E

7 Page 7 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone 3 (continued) 138 kv Site Multiple contingency Balsam F Brick Church F Blackhawk F Beloit Gateway F BOC Gas Tap F Bristol/Delevan F Colley Road F Dickinson F Elkhorn F Janesville F Lakehead Delevan Tap / Lakehead F Delevan McCue / Kennedy F Marine F North Lake Geneva F Northwest Beloit F Paddock F RC2 Bradford F RC2 LaPrairie F Rock River F Russell F Sunrise F Southwest Delevan F Townline F Tripp F Viking F Venture Tap / Venture F West Darien F Williams Bay F Wilcox F

8 Page 8 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 Multiple contingency 69 kv Site Boscobel Muni / Boscobel A Bris Bois / Hillside A Gran Grae A Muscoda A Muscoda Industrial Park A Spring Green A Stagecoach A Timberlane Tap A Bass Creek B Brodhead Switching Station B Darlington B East Lincoln Street / Mount Horeb B Eden B Harmony Tap/ Harmony B Hillman / Pioneer / Platteville / Pioneer B Tap / McGregor Idle Hour B La Mar B Monroe Central Tap / Monroe Central B North Monroe B North Stoughton / North Stoughton Tap 1 & B Oregon Red Hawk Tap / Red Hawk B B

9 Page 9 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 (continued) Multiple contingency 69 kv Site Rock Branch B Sheepskin B South Monroe B Spring Grove B Stoughton B Stoughton Muni East Tap / Stoughton Muni East B Sun Valley Tap / Sun Valley B Verona B Air Gas Tap / Air Gas C Burke Tap / Burke C Dane C De Forest C Femrite C Fitchburg C Kegonsa C North Madison C Pheasant Branch C Royster C Sun Prairie C Sycamore C Syene C Tokay C Waunakee C Waunakee Centennial Park C Waunakee Easy Street Tap C West Middleton C West Towne C Artesian / Reedsburg D Baraboo D Columbia D

10 Page 10 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 (continued) 69 kv Site Dam Heights North & South Tap / Dam Heights / Prairie du Sac Plant Multiple contingency D Kilbourn D Kirkwood D Lodi Tap D Merrimac Tap / Merrimac D Okee Tap D Portage Industrial Park / Portage D Poynette Tap / Poynette D Wyocena D Hubbard E North Beaver Dam E North Randolph E Rio E South Beaver Dam E Balsam F Brick Church F Colley Road F East Rockton F Enzyme Bio Systems F Katzenberg F McCue F North Lake Geneva F Park Avenue Tap / Park Avenue F RCEC Clinton F Richmond Road F Sharon Tap F Shaw F Tiger F Town Hall Road Tap F Twin Lakes F

11 Page 11

The physical boundaries of Zone 3 and transmission facilities located in Zone 3 are shown in Figure ZS 24.

The physical boundaries of Zone 3 and transmission facilities located in Zone 3 are shown in Figure ZS 24. September 00 0 Year Assessment www.atc0yearplan.com overview includes the Wisconsin counties of: Columbia Crawford (southern portion) Dane Dodge Grant Green Iowa Lafayette Jefferson Richland Rock Sauk

More information

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372

More information

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects

More information

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- -- ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014 MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

Highly Constrained Elements Within ATC Footprint

Highly Constrained Elements Within ATC Footprint Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market

More information

Utility Provider Phone Number Additional Direction and Notes

Utility Provider Phone Number Additional Direction and Notes Adams-Columbia Electric Cooperative (800) 831-8629 Algoma Utility Commission (920) 487-5556 Arcadia Electric & Water Utility (608) 323-3359 Ext. 23 Argyle Municipal Electric & Water Utility (608) 543-3335

More information

SUMMARY REPORT. 10 Year Transmission System Assessment

SUMMARY REPORT. 10 Year Transmission System Assessment 2018 SUMMARY REPORT 10 Year Transmission System Assessment Agility, flexibility needed to plan for Long term transmission planning has always been a complex undertaking, but it was relatively consistent

More information

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

AMERICAN TRANSMISSION COMPANY

AMERICAN TRANSMISSION COMPANY AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

Wisconsin Local Employment & Unemployment Estimates Released

Wisconsin Local Employment & Unemployment Estimates Released Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Wisconsin FDIC Insured Institutions Profitability First Quarter 2017

Wisconsin FDIC Insured Institutions Profitability First Quarter 2017 Wisconsin FDIC Insured Institutions Profitability First Quarter 2017 Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC Quarterly Data used as the source material.»

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs 7.7 Southeast Zone The following table provides a list of transmission needs identified in the Southeast Zone and the map on the following page shows the location of each item in the table. Southeast Zone

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

VERMONT ELECTRIC POWER COMPANY (VELCO)

VERMONT ELECTRIC POWER COMPANY (VELCO) TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

RENEWABLE ENERGY SUMMIT 2019

RENEWABLE ENERGY SUMMIT 2019 RENEWABLE ENERGY SUMMIT 2019 Scaling Up for the Job Ahead 01.17.2019 Monona Terrace and Convention Center Madison, WI SUMMIT Champions Lunch Sponsors SUMMIT Partners Supporting our keynote & panel sessions

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Wisconsin FDIC Insured Institutions Assets Quality First Quarter 2017

Wisconsin FDIC Insured Institutions Assets Quality First Quarter 2017 Wisconsin FDIC Insured Institutions Quality First 2017 Data compiled by: Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC ly Data used as the source material.»

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Summary Report. September The Future Grid. 10-Year Transmission System Assessment.

Summary Report. September The Future Grid. 10-Year Transmission System Assessment. Summary Report September 2012 he Future Grid 10-Year ransmission System Assessment www.atc10yearplan.com Regional and inter-regional planning achieves results ransmission investments solve problems, save

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85

Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85 Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85, Inc. Introduction The following impact study results are from the Progress Energy Inc., Carolinas (PEC) internal power-flow

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Sub Regional RTEP Committee - Southern

Sub Regional RTEP Committee - Southern Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN-12-1053 OAH DOCKET NO. 60-2500-30782 REBUTTAL TESTIMONY OF RANDALL PORTER, PE SUBMITTED ON BEHALF OF: WIND ON THE

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Southeastern Regional Transmission Planning (SERTP)

Southeastern Regional Transmission Planning (SERTP) Southeastern Regional Transmission Planning (SERTP) December 2014 Regional Transmission Planning Analyses I. Overview of Regional Analyses SERTP sponsors plan and expand the transmission system to reliably

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

AMERICAN ELECTRIC POWER (AEP)

AMERICAN ELECTRIC POWER (AEP) AMERICAN ELECTRIC POWER (AEP) Company Background: AEP is one of the largest electric utilities in the United States, delivering electricity to more than five million customers in 11 states. AEP s service

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South Sub Regional RTEP Committee South December 18, 2017 Baseline Reliability and Supplemental Projects Second Review 2 Date Project Last Presented: 10/30/2017 SRRTEP Problem Statement: DOM End of Life Criteria

More information

ERCOT Independent Review of Houston Import RPG Project

ERCOT Independent Review of Houston Import RPG Project ERCOT Independent Review of Houston Import RPG Project ERCOT System Planning 2014 Electric Reliability Council of Texas, Inc. ERCOT Regional Planning ERCOT Independent Review of Houston Import Project

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado System Impact Study T-2007-3 Final.doc System Impact Study Report Request # T-2007-3 900 MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado Executive Summary PSCo Transmission

More information

Tri-State December 2013 Board Meeting

Tri-State December 2013 Board Meeting 1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

Market Efficiency Planning Study

Market Efficiency Planning Study Market Efficiency Planning Study West SPM June 12, 2013 SPM : Market Efficiency Planning Study Update March 25, 2012 Market Efficiency Planning Study Recap Objective is to execute an annual structured

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

2016 SDG&E Grid Assessment Results

2016 SDG&E Grid Assessment Results 2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Jay Caspary Director Research, Development & Tariff Services

Jay Caspary Director Research, Development & Tariff Services Interconnection Seams Study Update CIGRE GOTF October 23, 2017 Jay Caspary Director Research, Development & Tariff Services jcaspary@spp.org 2 Disclaimer This deck includes materials which were presented

More information

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions

More information

R=Right, L=Left, C=Continue, S=Straight, BL= Bear Left, Super 8, 518 Borg Rd Delavan, WI. BR=Bear Right, SS=Stop sign, T=T intersection, Start 6:00 AM

R=Right, L=Left, C=Continue, S=Straight, BL= Bear Left, Super 8, 518 Borg Rd Delavan, WI. BR=Bear Right, SS=Stop sign, T=T intersection, Start 6:00 AM The Swiss Miss 600k R=Right, L=Left, C=Continue, S=Straight, BL= Bear Left, Super 8, 518 Borg Rd Delavan, WI BR=Bear Right, SS=Stop sign, T=T intersection, Start 6:00 AM us=unsigned Section 1 Section 2

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information