1 Study on Economic Partnership Projects in Developing Countries in FY2010 Study on the Kiev Metro Line 4 in Kiev City, Ukraine SUMMARY March 2011 第 1 章 第 2 章 The Ministry of Economy, Trade and Industry Prepared by: Ernst & Young ShinNihon LLC Japan External Trade Organization (JETRO) Oriental Consultants Co., Ltd.

2 (1) Background and Necessity of the Project Kiev city has an area of about 830 km² (1.3 times the area of 23 Wards in Tokyo) and a population of around 2.7 million inhabitants. It is the hub of political and economic activities in Ukraine. It is estimated that the population of the city will be increased to 2.8 million by Recent tendencies in population growth show expansion to the east of the Dnipro River, which is the proposed location of Kiev Metro Line 4. The provision of transportation infrastructure to this area has become an important issue. The construction work on the section of the road/rail combined bridge commenced in 2004 and is scheduled for completion in 2016, however, this schedule has been delayed due to the collapse of the national economy in Because of this, Kiev Metro decided to request the Japanese side to conduct a study on Kiev Metro Line 4 in order to receive financial support. (2) Reviewing Necessary for Components of the Project Kiev city prepared and approved the Kiev Master Plan (2020) in Also, this Project was listed in the National Development Program for Subway Construction ( ) in 2006 and was approved as a high priority national plan. The new Metro Line 4 was accepted based on an increase in transport demand between the Central Business District and the Troieshchyna residential area, this new route incorporates part of Line 5 into Line 4, and it was approved by the Kiev Subway Network Scheme in (3) Outlines of the Project Plan The Study Team recommended dividing the scope of the Project into 2 phases: Phase 1 and Phase 2. Outlines of the Project plan for the recommended phases are summarized as follows:

3 (Table-1) Outlines of the Project Plan 1. Track Gauge 1,520 mm 2. Route Phase 1: Vulytsia Myloslavska Station ~ Podilska Station Phase 2: Podilska Station ~ Hlybochytska Station 3. Route Length Phase 1: Approx. 12km. Phase 2: Approx. 2km. 4. Number of Stations Phase 1: At grade - 5 stations, Elevated - 1 station, Underground - 2 stations. Phase 2: Underground - 1 station. 5. Demand Forecast (maximum section) Sudnobudivna Station ~ Podilska Station Number of Passengers Per Day in Maximum Section (person/day) 553,870(2015)/ 567,493(2020) Peak Hour Peak Direction Traffic (PHPDT) 62,775(2015)/ 64,660(2020) 6. Headway 2 minutes (2015 at the start) 1.5 minutes (after 2020) 7. Train Composition Initial Stage: 6 cars (4M + 2T) Ultimate Stage: 6 cars (4M + 2T) 8. Number of Rolling Stock Required Phase 1: 144 cars (24 trains) Phase 2: 72 cars to be added (36 trains) 9. Train Power Control System VVVF Inverter Control 10. Location of Depot and Workshop (Rate for investment in maintenance equipment) Depot Troieshchyna Phase 1: 42% Phase 2: 58% (4) Environmental and Social Considerations The EIA of the Project has already been done and reviewed in compliance with Ukrainian laws, rules and regulations. It was approved by related ministries, authorities, and finally the CMU (Cabinet Ministers of Ukraine) in March Matters to be completed by Kiev City to realize the Project are as follows: For land acquisition and resettlement of inhabitants and real estate, Kiev City (Kiev Metro owner and operator) shall promptly complete land acquisition without involuntarily resettlement in compliance with Kiev City s land acquisition plan. Prior to commencement of the construction, Kiev City shall prepare environmental management and monitoring plans to be used during construction and operation of the new Kiev Metro Line in order to obtain approvals from related authorities and stakeholders.

4 Kiev City shall hold public consultations and hear the public s and stakeholders comments and opinions to reflect their comments and opinion on design, construction and operation. (5) Project Cost Estimate The Project cost for at grade structures, viaducts, underground structures, depots and other related facilities is estimated based on construction methods and Project quantities. An estimation of unit cost for each construction work is applied in order to compare with similar projects in India, Indonesia, Thailand, Bulgaria and other foreign countries. (Table-2) Project Cost (Phase 1 + Phase 2) (Table-3) Project Cost (Phase 1)

5 (Table-4) Project Cost (Phase 2) (6) Project Implementation Schedule Alternative-1 is that the Phase 1 section construct firstly including accomplishment of construction works and test running in the year 2015, and Phase 2 construction is planned to start after the commencement of the Phase 1, planned to be completed in Alternative-2 is planned that the construction of the entire section of Phase 1 and Phase 2 will be completed in Phase 1: The section from Vulytsia Myloslavska Station to Podilska Station (approx. 12km) and the Depot Troieshchyna. Phase 2: The section from Podilska Station to Hlybochytska Station (approx. 2km) and the expansion of the Depot Troieshchyna. (Table-5) Project Implementation Schedule Alternative Phase 1 SAPROF Study Conclusion of L/A Selection of Consultant Preparation of Tender Document Selection of Contractors Detailed Design by Contractors Civil Works Station Facilities E & M Works Depot and Workshop Works Rolling Stock Works Test and Commissioning Operation Phase 2 Construction and Operation

6 Alternative-2 Phase 1 SAPROF Conclusion of L/A Selection of Consultant Preparation of Tender Document Selection of Contractors Detailed Design by Contractors Civil Works Station Facilities E & M Works Depot and Workshop Works Rolling Stock Works Test and Commissioning Operation Phase 2 Construction and Operation (7) Economic and Financial Analysis The value of economic internal rate of return (EIRR) obtained 18.4% for Alternative 1 and 15.7% for Alternative 2, which are over the 10% of opportunity cost that is conceived as an opportunity cost of capital in Ukraine. EIRR values in this economic evaluation exceed this level. The above results of the cost benefit analysis show that the Project is economically feasible. The value of financial internal rate of return (FIRR) without interest cost does not show any viable results. To ensure enough cash flow for a sound financial basis, the subsidy required is UAH 135,063,000 (million JPY 1,427) and the Metro fare must be raised to UAH 2.9. (8) Feasibilities of the Project Implementation under Japanese Yen Credit Although this Project was originally planned to be implemented by the Ukrainian government and Kiev city, the construction schedule substantially fell behind due to the national economy failure in While the economic situation is showing signs of recovery, considering the urgency of this Project, Kiev city wishes to request Japanese Yen Credit.

7 (9) Project Location Map (Figure-1) Project Location Map Line 2 Study Route Line 4 Line 3 Line 1

Japanese ODA Loan. Ex-ante Evaluation

Japanese ODA Loan. Ex-ante Evaluation Japanese ODA Loan Ex-ante Evaluation 1.Name of the Project Country:Republic of the Philippines Project:Capacity Enhancement of Mass Transit Systems in Metro Manila Project Loan Agreement:27 March 2013

More information

Feasibility Study for Promotion of International Infrastructure Projects in FY2011

Feasibility Study for Promotion of International Infrastructure Projects in FY2011 Feasibility Study for Promotion of International Infrastructure Projects in FY2011 STUDY ON THE EXPANSION OF RAIL TRANSPORT CAPACITY FOR ROCK PHOSPHATE, THE KINGDOM OF MOROCCO FINAL REPORT SUMMARY November

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Delhi Mass Rapid Transport System Project Phase 2 (V) Loan Agreement: March 31, 2010 Loan Amount:

More information

STUDY ON THE DEVELOPMENT OF LEBAK BULUS STATION AREA IN JAKARTA THE REPUBLIC OF INDONESIA

STUDY ON THE DEVELOPMENT OF LEBAK BULUS STATION AREA IN JAKARTA THE REPUBLIC OF INDONESIA STUDY ON ECONIMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2012 STUDY ON THE DEVELOPMENT OF LEBAK BULUS STATION AREA IN JAKARTA THE REPUBLIC OF INDONESIA FINAL REPORT SUMMARY February 2013 Prepared

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Study for the Possibility of Application of Ultra Super Critical Steam Conditions for Coal Fired Power Plant in Vietnam

Study for the Possibility of Application of Ultra Super Critical Steam Conditions for Coal Fired Power Plant in Vietnam Feasibility Studies with the Aim of Developing a Bilateral Offset Credit Mechanism FY2011 Studies for Project Development and Organization Study for the Possibility of Application of Ultra Super Critical

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Java-Sumatra Interconnection Transmission Line Project (I) Loan Agreement: April 30, 2010 Loan Amount:

More information

Our mission is to be the best public service transporter for passengers in the city of Kigali using modern, clean and safe urban city buses.

Our mission is to be the best public service transporter for passengers in the city of Kigali using modern, clean and safe urban city buses. Kigali Bus Services Ltd. was incorporated in January 2006 in Kigali Rwanda. The Company started operations in March 2007 with just a few buses! We now operate a fleet of 50 Buses throughout Kigali City

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Cobenefit of Urban Railway Development Funded by Japanese ODA Loans

Cobenefit of Urban Railway Development Funded by Japanese ODA Loans Cobenefit of Urban Railway Development Funded by Japanese ODA Loans ~ Addressing Climate Change ~ UCHIDA Tsutomu Deputy Director General Japan Bank for International Cooperation 18 March 2008 Contents

More information

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa

Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Back ground Founded in 1887, and has expanded rapidly Altitude about 2500 meters above MSL Now among the ten largest cities in Sub Saharan Africa Annual growth rate is 3.8% By 2020 population growth would

More information

Joint investment in gas distribution company in Indonesia

Joint investment in gas distribution company in Indonesia October 17, 2017 Joint investment in gas distribution company in Indonesia Tokyo Gas Co., LTD Tokyo Gas Asia Pte. Ltd. Development Bank of Japan Inc. Tokyo Gas Asia Pte., Ltd (: Nobuhisa Kobayashi, "Tokyo

More information

TRAVEL DEMAND FORECASTS

TRAVEL DEMAND FORECASTS Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) TRAVEL DEMAND FORECASTS A. Introduction 1. The purpose of the travel demand forecasts is to assess the impact of the project components

More information

1 Balboa (B/.) = 99.7 Yen (JPY) 1 Yen = Balboa 1 US Dollar (US$) = 99.7 Yen 1 US$ = 1 Balboa

1 Balboa (B/.) = 99.7 Yen (JPY) 1 Yen = Balboa 1 US Dollar (US$) = 99.7 Yen 1 US$ = 1 Balboa Exchange Rate (October 2013) 1 Balboa (B/.) = 99.7 Yen (JPY) 1 Yen = 0.01003 Balboa 1 US Dollar (US$) = 99.7 Yen 1 US$ = 1 Balboa Panama city Burunga Autopista Nuevo Chorrillo Panamericana Republic of

More information

Investing in the city Lessons from 47 light-rail projects

Investing in the city Lessons from 47 light-rail projects Investing in the city Lessons from 47 light-rail projects Niels van Oort Assistant professor public transport Transport and Planning Public Transport Consultant Goudappel Coffeng Rob v/d Bijl Independent

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

4. Good Practice Example: Automatic light metro system (Brescia, Italy)

4. Good Practice Example: Automatic light metro system (Brescia, Italy) 4. Good Practice Example: Automatic light metro system (Brescia, Italy) Keywords Sustainable mobility, automatic light metro system Name and location Automatic light metro system, Brescia, Italy Brescia

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

What We Heard Report - Metro Line NW LRT

What We Heard Report - Metro Line NW LRT What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail

More information

The Indian Infrastructure Industry

The Indian Infrastructure Industry n The Indian Infrastructure Industry DIBD OMII Own Man In India October 2010 Introduction to the Indian Infrastructure Industry Macro level Key drivers Government initiatives Future projects Danish infrastructural

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT

COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT MINISTRY OF ENERGY AND MINERAL DEVELOPMENT COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT Dr. Stephen Robert Isabalija PERMANENT SECRETARY 13 th -15

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

THE WAY WE MOVE LRT FOR EVERYONE

THE WAY WE MOVE LRT FOR EVERYONE THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an

More information

Towards a new Electricity Market of Ukraine: legislative, organizational, financial and technological basis for implementation

Towards a new Electricity Market of Ukraine: legislative, organizational, financial and technological basis for implementation Towards a new Electricity Market of Ukraine: legislative, organizational, financial and technological basis for implementation Stanislav Masevyh, World Bank electricity market specialist at the Ministry

More information

Haramain High Speed Rail

Haramain High Speed Rail Presented by: Mahmoud Cheikh 8 th th UIC-World Congress on High Speed Rail Philadelphia, United States 11 th 13 th July 2012 1 Haramain High Speed Rail The location 2 3 Short History of the Project Haramain

More information

BRTS IN DHAKA: DESIGNING UNDER CONSTRAINTS

BRTS IN DHAKA: DESIGNING UNDER CONSTRAINTS BRTS IN DHAKA: DESIGNING UNDER CONSTRAINTS Noor E Alam, Ministry of Road Transport and Bridges, Bangladesh 2 nd ASIA BRTS, Ahmedabad, India Today s Overview 1 Dhaka and Mobility Pattern 2 Strategic Transport

More information

Toward the Realization of Sustainable Mobility

Toward the Realization of Sustainable Mobility GIES 2008 Toward the Realization of Sustainable Mobility March 13, 2008 Toyota Motor Corporation Senior Technical Executive Hiroyuki Watanabe 1 CO 2 Emission from Transportation Sector Distribution by

More information

Eco-Driving by Utilizing a Digital Tachograph System

Eco-Driving by Utilizing a Digital Tachograph System JCM Projects In Asia Eco-Driving by Utilizing a Digital Tachograph System Nippon Express Co., Ltd. March 19, 2015 Tokyo, Japan 0 Contents 1. About Nippon Express 2. Digital Tachograph System 3. Why Promote

More information

Study on Economic Partnership Projects. in Developing Countries in FY kV Lines in West Java, in Indonesia SUMMARY.

Study on Economic Partnership Projects. in Developing Countries in FY kV Lines in West Java, in Indonesia SUMMARY. Study on Economic Partnership Projects in Developing Countries in FY2007 Study on Upgrading Transmission Capacity of Existing 500kV Lines in West Java, in Indonesia SUMMARY March 2008 Tokyo Electric Power

More information

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd.

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. 2016Fuji Electric Co., Ltd. All rights reserved. 1 Summary of Consolidated Financial Results for 1Q FY2016 (YoY Comparison)

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS 1. The proposed project primarily aims at capacity

More information

IKORODU- CMS BRT EXTENSION PROJECT

IKORODU- CMS BRT EXTENSION PROJECT IKORODU- CMS BRT EXTENSION PROJECT A Presentation by SENIOR Environmental Specialist, Lagos Metropolitan Area Transport Authority Mr Omoniyi Isaac, at The Regional consultation on Air Quality, Clean Vehicles

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

Meeting Materials for FY2011

Meeting Materials for FY2011 Meeting Materials for FY2011 (Year ended March 31, 2012) May 17, 2012 Masao Usui Representative Director, President Executive Officer KYB Corporation Meeting Materials for FY2011 May 17, 2012, KYB Corporation

More information

DMB Proposed Toll Increase

DMB Proposed Toll Increase DMB Proposed Toll Increase December 2018 The Delaware River and Bay Authority Bi-state agency established in 1962 Provides Crossings between Delaware and New Jersey Economic development benefitting the

More information

History of Subway in Kyoto

History of Subway in Kyoto TO: Board Members FROM: Yasuyo Tsukamoto DATE: May 6, 2016 SUBJECT: Alternative Plan to Increasing Fares in Kyoto City I am strongly against the idea that the (KMTB) increase the subway fare. Although

More information

PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES

PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport Office of the Minister of Energy and Resources PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES

More information

HCM will expand the production capacity and sales support, such as dealer empowerment, etc. in Chinese market.

HCM will expand the production capacity and sales support, such as dealer empowerment, etc. in Chinese market. 1 2 For the market environment in FY 2010, the growth rate of GDP(yearon-year)and fixed asset investment are both doing well. Construction machinery market has been rapidly increasing. In FY2010, demand

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Road Map for Sustainable Transport Strategy for Colombo Metropolitan Region with Cleaner Air, through Experience

Road Map for Sustainable Transport Strategy for Colombo Metropolitan Region with Cleaner Air, through Experience Workshop on Air Quality and Environmentally Sustainable Transport April 28 th 2011 Don S. Jayaweera Road Map for Sustainable Transport Strategy for Colombo Metropolitan Region with Cleaner Air, through

More information

Management Plan for FY2013

Management Plan for FY2013 for April 26, 2013 Fuji Electric Co., Ltd. 1 Looking back from FY2010 to Establish profitable structure by business restructuring ED&C, Magnetic Disks, Vending Machines, Drives, Power Semiconductors and

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

Study on Economic Partnership Projects. in Developing Countries in FY2009. Study for Manila LRT Line 2 East and West Extension

Study on Economic Partnership Projects. in Developing Countries in FY2009. Study for Manila LRT Line 2 East and West Extension Study on Economic Partnership Projects in Developing Countries in FY2009 Study for Manila LRT Line 2 East and West Extension Project in Republic of the Philippines SUMMARY March 2010 Marubeni Corporation

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

Yukon Resource Gateway Project

Yukon Resource Gateway Project Yukon Resource Gateway Project Summary Application for National Infrastructure Component Funding January 2016 Introduction The Government of Yukon is seeking endorsement of the Yukon Resource Gateway

More information

Philippines Metro Manila Rail Commuter Maintenance Depot Construction Project

Philippines Metro Manila Rail Commuter Maintenance Depot Construction Project Philippines Metro Manila Rail Commuter Maintenance Depot Construction Project 1. Project Profile and Japan s ODA Loan Report date: March 2001 Field survey: September 2000 MANILA BAY CALOOCAN MANILA PACO

More information

Contents 1. Country Background 2. Lao Power Sector 3. Power Sector Policy 4. Current Electric Power Situation (statistics) 5. Demand Forecasting 6. Ex

Contents 1. Country Background 2. Lao Power Sector 3. Power Sector Policy 4. Current Electric Power Situation (statistics) 5. Demand Forecasting 6. Ex Training and Dialogue on Energy Policy 04 to 24 April 2010, Tokyo, Japan. Country Report Presentation By: Viengsay CHANTHA Chief of Lao Electric Power Technical Standards (LEPTS) Regulatory Unit Department

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

World Bank Support to Urban Transport in India

World Bank Support to Urban Transport in India World Bank Support to Urban Transport in India A Proposed Framework for Bank Engagement in UT New Delhi, November 25 2006 Outline Key UT issues Government of India s leading efforts Objectives of Bank

More information

Valley Metro Overview. ITE/IMSA Spring Conference March 6, 2014

Valley Metro Overview. ITE/IMSA Spring Conference March 6, 2014 Valley Metro Overview ITE/IMSA Spring Conference March 6, 2014 Valley Metro Who Are We? Operate Regional Transit Services Valley Metro and Phoenix are region s primary service providers Light Rail and

More information

Financing by International Finance Institutions the Sofia case. Metodi AVRAMOV Public Transport Company - Sofia

Financing by International Finance Institutions the Sofia case. Metodi AVRAMOV Public Transport Company - Sofia Financing by International Finance Institutions the Sofia case Metodi AVRAMOV Public Transport Company - Sofia Leipzig, 18 April 2008 SOFIA Area 1 194 sq.км. Population 1 400 000 inhabitants Number of

More information

Laboratory worker at Goedgevonden Coal Mine

Laboratory worker at Goedgevonden Coal Mine 82 Laboratory worker at Goedgevonden Coal Mine Integrated Annual Report 2013 Operational review ARM Coal 83 ARM Coal F2013 F2012 % change ARM Coal attributable sales volumes (000t) Headline earnings Rm

More information

Regional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner

Regional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner Regional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner Presentation Outline Transit System Facts Economic Challenges in the Truckee Meadows RTC Transit

More information

Agenda. Review. Strategy. Outlook

Agenda. Review. Strategy. Outlook 1 Agenda Review 2006 Strategy Outlook 2007 2 Highlights 2006 Focus on Transport-Related Engineering Strong operational performance in all business areas Strong market environment Initiative taken for truck

More information

Automotive Division. Tryggve Sthen President, Automotive Division

Automotive Division. Tryggve Sthen President, Automotive Division Automotive Division Tryggve Sthen President, Automotive Division SKF Capital Markets Day 10 May 2011 Presentation outline Automotive Division update Division overview Key financials Business outlook The

More information

O-Train Confederation Line Stage 1

O-Train Confederation Line Stage 1 O-Train Confederation Line Stage 1 Presented to: Regional Public Works Commissioners of Ontario June 23, 2017 by Steve Cripps, Director, O-Train Construction The Need Ottawa s population is projected to

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Second Jharkhand State Road Project (RRP IND 49125) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves capacity augmentation and rehabilitation of four state highway sections in the

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE 10 MAY 2018 Page 1 of 19 TABLE OF CONTENTS Introduction... 6 Applicable Law... 6 The Methodology... 6 Decision-Making

More information

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

PARTNERSHIPS FOR AN ENERGY TRANSITION: TRANSFORMING THE SAN ANDRÉS ARCHIPELAGO

PARTNERSHIPS FOR AN ENERGY TRANSITION: TRANSFORMING THE SAN ANDRÉS ARCHIPELAGO PARTNERSHIPS FOR AN ENERGY TRANSITION: TRANSFORMING THE SAN ANDRÉS ARCHIPELAGO Date: March 17 th, 2016 Location: Electri International Cartagena, Colombia Presenter: Luci Restrepo, SOPESA OUTLINE OF PRESENTATION

More information

Policy Coordination in Urban Transport Planning: Some Experience from Asia- Nepal and Japan

Policy Coordination in Urban Transport Planning: Some Experience from Asia- Nepal and Japan Regional Expert Group Meeting on Policy Options for Sustainable Transport Development 27-29 November 2013, Incheon Policy Coordination in Urban Transport Planning: Some Experience from Asia- Nepal and

More information

Attachment 5. High Speed Transit Planning Study REPORT SUMMARY. Prepared by: City of Edmonton Transportation Planning Branch. Stantec Consulting Ltd.

Attachment 5. High Speed Transit Planning Study REPORT SUMMARY. Prepared by: City of Edmonton Transportation Planning Branch. Stantec Consulting Ltd. Attachment 5 High Speed Transit Planning Study Prepared by: City of Edmonton Transportation Planning Branch Stantec Consulting Ltd. Transportation Management & Design, Inc. with Lea Consulting Ltd. [135-35130]

More information

NISSAN REVIVAL PLAN. TOKYO October 18, 1999

NISSAN REVIVAL PLAN. TOKYO October 18, 1999 NISSAN REVIVAL PLAN TOKYO October 18, 1999 REVIVAL PLAN OUTLINE I) Diagnosis II) III) Introduction Past Performance: Facts/Figures Past Performance: Analysis + Opportunities Revival Plan Elaboration Key

More information

Aim: Integration of Road Infrastructure of Georgia with European Standards and effective satisfaction of the Road User needs. Annual Report 2013

Aim: Integration of Road Infrastructure of Georgia with European Standards and effective satisfaction of the Road User needs. Annual Report 2013 www.georoad.ge Annual Report 2013 Aim: Integration of Road Infrastructure of Georgia with European Standards and effective satisfaction of the Road User needs Objectives: Improvement of road safety Reduction

More information

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population

More information

ALMEC CORPORATION Inception Meeting 10/07/2013

ALMEC CORPORATION Inception Meeting 10/07/2013 Transport Sector s Study Plan ALMEC CORPORATION Inception Meeting 10/07/2013 1 Introduction of ALMEC Company name ALMEC CORPORATION Foundation October, 1971 Head office Branch office Organization 5-5-3,

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

METI Ministry of Economy, Trade and Industry. METI s Automated driving Demo

METI Ministry of Economy, Trade and Industry. METI s Automated driving Demo METI Ministry of Economy, Trade and Industry METI s Automated driving Demo Table of contents 1.Background 2.Roadmap 3.Demonstration projects 1Mobility service in rural area 2Providing information for operators

More information

Volvo Group THIRD QUARTER 2015 JAN GURANDER. Volvo Group Headquarters Third quarter

Volvo Group THIRD QUARTER 2015 JAN GURANDER. Volvo Group Headquarters Third quarter Volvo Group THIRD QUARTER 2015 JAN GURANDER 1 VOLVO GROUP Third quarter highlights NET SALES SEK bn 12 months 310 bn IMPROVED PROFITABILITY ON FLAT VOLUMES UNDERLYING OPERATING MARGIN 6.9% 67 73 OPERATING

More information

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019.

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019. EXECUTIVE SUMMARY PURPOSE To report the findings of the Feasibility Study for an Underground Utility District along Segment C of the proposed Park to Playa Trail. BACKGROUND The City of Los Angeles Department

More information

Pump Station 7 Improvements

Pump Station 7 Improvements Project Business Case ID: C04 2/18/2017 Pump Station 7 Project Purpose: The purpose of this project is to ensure that Pump Station 7 continues to operate in an efficient and effective manner following

More information

AIR POLLUTION: Policy, actions and short term countermeasures to reduce air pollution of Ulaanbaatar city

AIR POLLUTION: Policy, actions and short term countermeasures to reduce air pollution of Ulaanbaatar city AIR POLLUTION: Policy, actions and short term countermeasures to reduce air pollution of Ulaanbaatar city Presented by Mr. Ganbaatar B. Director Department of fuel policy and regulation Ministry of Fuel

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling.

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling. Mode Selection Report 7 Cost Evaluation The cost evaluation criteria used in the evaluation of the transit modes are: Capital cost. operating costs. Fare revenue. Net cost per passenger/passenger-mile.

More information

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016 Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call November 9, 2016 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of Section 27A of the

More information

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease

More information

Smart Islands Smart Networks European Forum on Clean Energy for Islands Naxos, 9-11 of July 2018

Smart Islands Smart Networks European Forum on Clean Energy for Islands Naxos, 9-11 of July 2018 Smart Islands Smart Networks European Forum on Clean Energy for Islands Naxos, 9-11 of July 2018 Eirini Stavropoulou Director of ISLANDS NETWORK OPERATION DEPARTMENT HEDNO S Role as NII Electrical System

More information

Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology

Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology Prepared by the Londonderry Community Development Department Planning & Economic Development Division Based

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~

The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~ The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~ 4 November, 2014 Kazushige Tanaka Energy Advisor/Counsellor Permanent Delegation of Japan to the OECD 1. Oil Supply in Emergency

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Recommended Vision for the Downtown Rapid Transit Network

Recommended Vision for the Downtown Rapid Transit Network Recommended Vision for the Downtown Rapid Transit Network April 2008 Presentation Overview Context Transit options Assessment of options Recommended network Building the network 2 1 Rapid Our Vision Reliable

More information

Seoul. (Area=605, 10mill. 23.5%) Capital Region (Area=11,730, 25mill. 49.4%)

Seoul. (Area=605, 10mill. 23.5%) Capital Region (Area=11,730, 25mill. 49.4%) Seoul (Area=605, 10mill. 23.5%) Capital Region (Area=11,730, 25mill. 49.4%) . Major changes of recent decades in Korea Korea s Pathways at a glance 1950s 1960s 1970s 1980s 1990s 2000s Economic Development

More information

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION THE CITIZENS UTILITY BOARD ) and ) THE ENVIRONMENTAL DEFENSE FUND ) ) Docket No. 14- Proceeding to Adopt a GHG Metric for ) Smart Grid Advanced Metering Infrastructure

More information

Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India

Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India South Asia Transport Team Presented by Prodyut Dutt Asian Development

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Quarterly Activities Report

Quarterly Activities Report Quarterly Activities Report Three months ended 31 December 2017 31 January 2018 Frontier Diamonds Limited (ASX: FDX) (Frontier or the Company) is pleased to provide an overview of its key activities for

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

Overview of Global Fuel Economy Policies

Overview of Global Fuel Economy Policies Overview of Global Fuel Economy Policies Zifei Yang Researcher 2018 APCAP Joint Forum and Clean Air Week Theme: Solutions Landscape for Clean Air Bangkok, Mar 20, 2018 What is ICCT? ICCT is an independent

More information

JCP&L Verbatim Response to Middletown Township s Questions

JCP&L Verbatim Response to Middletown Township s Questions JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses

More information

A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka

A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka Menaka Rajaguru Department of External Resources Ministry of National Policies and Economic Affairs Country Profile Country Profile

More information

Applicability for Green ITS of Heavy Vehicles by using automatic route selection system

Applicability for Green ITS of Heavy Vehicles by using automatic route selection system Applicability for Green ITS of Heavy Vehicles by using automatic route selection system Hideyuki WAKISHIMA *1 1. CTI Enginnering Co,. Ltd. 3-21-1 Nihonbashi-Hamacho, Chuoku, Tokyo, JAPAN TEL : +81-3-3668-4698,

More information

Please visit the stations to provide your input: EV Charging Location Map EV Adoption ZEV Drivers Other Ideas

Please visit the stations to provide your input: EV Charging Location Map EV Adoption ZEV Drivers Other Ideas Welcome! Thank you for joining us. Please visit the stations to provide your input: EV Charging Location Map EV Adoption ZEV Drivers Other Ideas A brief presentation will begin at 6pm. Table activities

More information

India-Japan Energy Forum 2017 "Conference"

India-Japan Energy Forum 2017 Conference India-Japan Energy Forum 2017 "Conference" Energy Saving for Steel Plant by FUJI Energy Center January 9 th, 2017 Fuji Electric Co., Ltd Pacific Consultants Co., Ltd. Fuji Electric Co., Ltd. All rights

More information