1 Washington Metropolitan Area Transit Authority Status Report Metrobus Capital Improvement Program FY06-11 P D E C Presented to the Board of Directors: Planning & Development Committee September 8, 2005

2 Contents I. Purpose II. III. IV. Background Bus Fleet Improvements Bus Maintenance Facilities V. Bus Onboard Systems VI. VII. VIII. Bus Stop Improvements Bus SmarTrip Fareboxes/Ridership Reporting Summary Appendices: A-1: Fleet Profile A-2: Capital Improvement Program Budget A-3: Project(s) Master Schedule 2

3 I. Purpose To brief the Planning and Development Committee on the current status of the Metrobus Capital Improvement Program, an $830M near term investment to achieve the full potential of the public s Metrobus system. The 1473-bus fleet (Appendix A-1) is the 5 th largest in the nation. This comprehensive, multi-year program of projects ranges from new buses for replacement and growth, to customer information features, such as arrival information at bus stops and other Intelligent Transportation Systems (ITS) advancements, to new and upgraded facilities. 3

4 II. Background The $830M funding for the Bus Capital Improvement Program includes $536M of funding from the Metro Matters Funding Agreement and $294M in other approved bus capital funding. Onboard Systems $74 (9%) Bus Stop Improvements $27 (3%) Maintenance Facility Improvements $128 (15%) Fleet Improvements $601 (73%) The program does not accommodate $45.5M in desirable but currently unfunded projects 4

5 III. Bus Fleet Improvements Projects Underway FY05-11: $338M Bus Replacement with 250 CNG Buses: $108M Purchase 250 CNG buses. Delivery began August 11 th and will be completed March Bus Replacement: FY06-08: $117M In May 2004, the Board authorized the staff to initiate and award procurement for new buses to include 50 hybrid electric buses in FY06, up to 117 advanced technology diesel buses in FY07, and 50 additional hybrid electric buses (contingent upon evaluation of initial 50) for delivery in FY08. Annual Vehicle Overhaul: FY05-10: $108M Capital funding provides for the annual mid-life overhaul of approximately 100 buses. Clean Fleet Program: FY01-06: $5M Completes the Clean Fleet Program adopted by the Board in September The soot filters reduce particulate matter emissions by 90% and eliminate visible smoke. Install soot filters on buses equipped with Cummins and Detroit Diesel engines (336 buses); the Cummins soot filters are complete (74 buses) and the EPA had advised not replacing the Detroit Diesel soot filters (262 Buses) until final EPA resolution. EPA has now resolved the issue and work is scheduled to be completed in December

6 III. Bus Fleet Improvements Upcoming Projects FY06-11: $263M Bus Expansion Metro Matters 185 Bus Program: $95M Purchase up to 185 buses for expansion After completion of the evaluation based on experience with the first 50 Hybrid buses, staff will recommend to the Board a selection of vehicle technology for the first 50 Metro Matters expansion buses. Remaining 135 buses will not be purchased until the bus network evaluation is complete (currently estimated to be Spring 2006), as required by the Metro Matters Funding agreement. Bus Replacement FY09-11: $168M Purchase 241 replacement buses Fleet mix of vehicle technology is under review with staff recommendation to be made based on experience with Hybrid buses starting Spring

7 III. Bus Fleet Improvements Bus Fleet Average Age The Board has established an average fleet age goal of 7.5 years. With the replacement purchases discussed here the average age will decline from the current level of 10.1 years to 7 years by FY07 and will continue to remain at or under 7.5 years through FY Average Age (Yrs) Board Goal FY '05 FY '06 FY '07 FY '08 FY '09 FY '10 FY '11 Fleet Size 1473 Fleet Size 1498 Fleet Size 1523 Fleet Size 1553 Fleet Size 1593 Fleet Size 1658 Fleet Size 1658 Graph reflects planned annual delivery schedule of 185 Metro Matters Expansion Buses; Fleet Average Age will be higher if MM 185 buses are not procured and fleet expansion occurs without additional new buses; Fluctuation in Average Fleet Age due to projected delivery rate of new buses vs. retirement of older buses in fleet. 7

8 IV. Bus Maintenance Facilities Projects Underway FY06-11: $128M The following projects are part of the Board-approved Infrastructure Renewal Program: Bus Work Equipment / Washers / Support Equipment: $43M This project includes the replacement of bus washers, bus lifts, and the replacement of brake testers and other miscellaneous equipment required to support the bus maintenance operation. Bladensburg CNG/Bus II Carmen Turner Facility: $14M The heavy overhaul portion of the Bladensburg facility must be converted to be CNG compliant. This will allow for heavy overhaul of the CNG fleet completed in August In addition, the project includes the build-out of the Bus II area of the Carmen Turner Facility at the bus body and paint shop. Project completion is targeted for December CNG Four Mile Upgrade: $22M This project involves the design, construction, operation, and maintenance of a CNG fueling facility to support 212 buses. Project completed August 2005 West Ox Maintenance Facility Metro Matters Bus Facility: $49M This is a proposed joint use facility for Fairfax County and WMATA in the western county pending Board approval. Capacity for an initial 75 Metrobuses from existing garages and Metro Matters can expand to 150 buses. Project completion is likely Spring The project is being managed by Fairfax County. 8

9 IV. Bus Maintenance Facilities APTA Peer Review made a general recommendation for facility improvements. The improvements detailed below have an estimated cost of $36M but are presently unfunded. In addition, a recommendation for the unfunded priorities will be made under the proposed FY CIP, in December Four Mile Run Montgomery Bladensburg Landover Royal Street* Arlington* Southeastern Southern Facilities Security Enhancements Western* All Facility Northern* Install paint facilities, renovate bathrooms and locker rooms. Replace lighting, HVAC system, bathrooms and locker rooms. Replace wash reclaim system, HVAC system, heating boilers, and paint booth, renovate bathrooms and locker rooms. Replace lighting, HVAC system, heating boilers, renovate bathrooms and locker rooms, repair/ repave roadway and parking lot. Upgrade lighting, renovate bathrooms and locker rooms, replace shop air compressors and dryers, replace overhead bay doors. Masonry structure requires structural repair to allow use of the second story areas. Replace brake testers and other brake equipment. Description Replace and repair aging and worn equipment; major rehabilitation of parking structure, lighting, overhead bay doors, bathrooms and locker rooms. Replace and repair aging and worn equipment and rehabilitation of entire HVAC system, shop air compressors and dryers, bathrooms and locker rooms. The open environment of our bus garages creates the potential for a myriad of safety and security problems. Enhancements such as guard booths, closed-circuit TV and alarm systems are necessary to mitigate these problems. Replace shop air compressors and dryers, HVAC system, and renovate bathrooms and locker rooms. $1.5M for the purchase and installation of mechanic s kiosks at all bus maintenance facilities to eliminate manual input errors and speed the input of data to produce more accurate and timely reporting for all users of the system. * Northern, Royal Street, Arlington, and Western are authorized for joint development consideration. 9

10 V. Bus Onboard Systems Projects Underway FY06: $59M Bus Radio System: $26.5M Motorola s ten-site above ground infrastructure was completed February 2005, and during testing, performed better than the contract specifications for coverage. All buses fleetwide have Motorola Radio Communications installed (December 2003); however, during the testing and acceptance period Motorola determined that a remediation effort was necessary due to excessive fuse failures on primary power and ignition sense circuits, microphone failures, antenna lockups and inconsistent automatic software uploads over wireless LAN. Motorola completed remediation at Arlington Garage in July; and Southeast and Four-Mile Run in August Motorola projects completion of all garages by December Bus AVL: $3.5M Automatic Vehicle Locator System (AVL) has been installed on all buses as part of Motorola s radio communication system through a special congressional security appropriation. This Orbital System identifies the location of all buses and communicates to the Bus Operations Command Center (OCC). Final acceptance is targeted for January Bus Fare System Replacement: $24M New fare boxes that validate currency, accept payment in cash and perform financial transactions via SmarTrip technology have been installed and tested. Installation of the system completed in August 2004 and is performing above the 99% level. Final acceptance of this system is targeted for December Scheduling and Dispatch System (Trapeze): $4M Install scheduling system at the ten bus divisions. Project completion targeted for December 2005 as part of the ITRP effort. Bus Systems Architecture and Standards: $1M Provide a framework for integration and standards for interoperability. A final draft was provided in June 2005 and a final report is due in September The guidelines complies with FTA Intelligent Transportation Systems (ITS) integration requirements. All future bus fleet and facility systems projects will comply with the integration guidelines. 10

11 V. Bus Onboard Systems Upcoming Projects FY06-08: $15M Implementing a series of onboard systems that, when fully iintergrated, will provide detailed information to: provide real-time information to our riders, provide a foundation for an integrated information system, and manage and control the bus system Projects required to do this are as follows: Integration of AVL, Farebox and Scheduling Systems: $1M This project contains constitutes Phase I of Bus Systems Integration to integrate the bus schedule and AVL systems by December Integration of these two systems will be expanded with the integration of the bus farebox by June Regional Bus Stop Inventory & Databases: $1.5M Inventory of Metro bus stop facilities and conditions to be completed by June 2006 Develop web-enabled regional bus stop database to share and maintain the data by June

12 V. Bus Onboard Systems Upcoming Projects FY06-08: $15M (cont d) System Integration / Single Sign On: $4M This is the final step (Phase II) to complete the overall onboard systems integration to allow for simplified sign-on. These systems include: AVL, scheduling, radios, fare collection, etc. Completion targeted for March Data Warehouse & Reporting: $2.5M Complete a bus operations warehouse that will integrate, store and analyze operations data for management and planning purposes. The information that is collected may be used to analyze bus route performance and to update and maintain bus schedules. Completion targeted for March Real Time Passenger Information: $6M Interim phase of the real-time bus service information that can be accessed initially by phones, internet and displays at the high ridership locations such as; Pentagon, Silver Spring, Friendship Heights, Anacostia, and 7 th and 8 th Streets NW. 25% of the bus passengers will benefit from these displays. Completion is scheduled for June Integration of Trip Planner, IVR, and complete Customer Information System (CIS): $5M unfunded The integration of these projects is extremely complex and will require 3 to 4 years to complete a full comprehensive real time passenger information system including Trip Planner an IVR (Interactive Voice Response System) which is currently unfunded. Action item incorporating these projects into one integrated program follows this presentation 12

13 V. Bus Onboard Systems Upcoming Projects FY06-08: $4.5M APTA Peer Review made a general recommendation for technology improvements. The improvements detailed below have an estimated cost of $4.5M but are presently unfunded. Automatic Passenger Counters (APC): $2M (currently unfunded) Recent fleet procurements have included the hardware for an automatic passenger counting system. No software program has been secured to retrieve or analyze passenger data. The capability is currently on 289 existing buses, and will be integrated into all future bus deliveries starting in March 2006 and will be retrofitted on all new buses delivered prior to March Fleetwatch: $2.5M (unfunded) $2.5M for the procurement and installation of the FLEETWATCH system at all facilities that dispense fuels and fluids. Provides the input required for Materials Maintenance Management System along with increased security of petroleum products. 13

14 VI. Bus Stop Improvements Projects Underway; $6.3M Bus Map Enhancements (Phase1): $1.6M Install 822 sub-regional site-specific bus system maps on all WMATA-owned bus shelters (343 bus shelters at 49 Metrorail stations, 479 on-street bus shelters owned by WMATA), and 125 bus maps in Metrorail station mezzanines. Project completion is scheduled for Summer Transit Center Improvements - $4.7M On-going bus transit center improvements at Shirlington (construction completion in 2006) and White Oak (planning/engineering completion in 2006) and miscellaneous prior-year bus project development. Upcoming Projects FY06-10; $20.5M Bus Map Enhancements (Phase 2): $1M Annually fabricate up to 500 additional sub-regional site-specific bus system maps for on-street bus shelters and replacement maps for WMATA-owned shelters. Funding level of $250,000 annually for four years, or approximately 2,000 new or replacement maps between FY07-FY10. Comprehensive Bus Stop Improvements: $3M Package the FY06 Board-approved Bus Stop Information Program (BSIP), that will maintain the information panels in the 6,500 existing display cases, into a comprehensive program that includes the following capital improvements: Replace and maintain 343 bus shelters at Metrorail station (to complete Winter 2007) Replace and maintain 163 bus shelters at on street locations. The District of Columbia recently announced a franchise program that would include 244 shelters that are currently WMATA-owned; Montgomery County has developed a similar agreement that would replace 72 WMATA-owned shelters (to complete Winter 2007) Install up to 6,000 additional bus stop display cases in addition to maintaining the existing cases (to complete Fall 2006); Install regional bus stop ID labels on all stop flag poles and shelters to be used for region-wide implementation of real-time bus information (to complete Winter 2007); Capital and operating will be offset by revenue received in exchange for exclusive rights to sell and display advertising in bus shelters at Metrorail stations. 14

15 VI. Bus Stop Improvements Upcoming Projects FY06-10: cont d Premium Bus Branding: $1M Design the graphic scheme and develop service criteria for a single premium bus brand to be used in the region. Quantify the fleet and operating cost implications of branded service. Design a bus stop flag demarcating stops served by premium bus service. Design marketing materials and strategies to promote premium bus service and to build ridership on these services. Priority Corridors & Centers: $15.5M Following the recommendations of the Regional Bus Study, WMATA has worked in close coordination with local jurisdiction staff to identify 13 priority corridors and centers where the following improvements would be made: Transit Signal Priority (TSP) and running way improvements; Passenger facilities including bus shelters at, fare vending machines, lighting, etc. (50 electronic displays for real time information are included in the onboard systems section). The list of priority corridors, budget and schedule for implementation is shown on the next page. 15

16 VI. Bus Stop Improvements Current Schedule - Washington, DC - Maryland - Virginia FY06 FY07 FY08 FY Priority Corridors & Centers DC - Georgia Ave/7th Street Rapid DC H Street/ Benning Rd DC - Pennsylvania Avenue DC - Wisconsin Avenue DC -Calvert/ U Street / Florida MD - Veirs Mill Road MD -Langley Park Transit Center ( $6.7M, TIFF funding) MD University Blvd/ US-1/ MD 450 Bus Stop Improvements VA -US-1/Jeff. Davis Hwy ($.813M other funding ) VA -REX/ Richmond Highway VA- I-66 Park & Ride Facilities VA- Columbia Pike/Pentagon Transit Center VA US 50/ VA 7/ US29 Bus Stop Improvements 16

17 VII. Bus SmarTrip Fareboxes/ Ridership Reporting The new fareboxes have been installed as of August 2004 and the software modifications and communication updates were completed by late fall The revenue testing and verification were completed throughout the remainder of the year. Revenue Collection, Reporting and Reconciliation Revenue Collection data is more detailed than the data from the previous style fareboxes Accuracy has been verified during testing and certification by WMATA Revenue and Audit Ridership Comparison Verified that new farebox line/route ridership is more accurate than the data from the old farebox New farebox systemwide ridership is lower than previously reported, but information is more reliable Have begun using new riderhip numbers in FY06 for reporting and in FY06 & 07 budget development 17

18 VIII. Summary Bus Fleet program ($601M) to purchase buses to reduce the average fleet age to no more then 7.5 years. Maintenance program ($128M) to keep bus facilities in good operating condition and capable of maintaining the expanded fleet. Onboard systems program ($72M) to upgrade and integrate all onboard systems (AVL, radio, Trapeze, etc.). Bus Stop Improvements program ($29M) to include improvements in priority corridors and at transit centers that are of vital importance as part of a coordinated regional bus strategy to improve service reliability, customer safety and convenience, access for all customers, and the quality of bus service information. There is currently $45.5M in unfunded needs, with $29M in Maintenance Facility upgrades as the first priority, pursuant to the APTA Bus Peer Review. A recommended approach to the unfunded needs will be made under the proposed FY CIP, in December. 18

19 Metrobus Capital Improvement Program: FY06-11 Appendices A-1: Active Bus Fleet Profile A-2: Bus Capital Program Budget A-3: Project(s) Master Schedule 19

20 Appendix A-1: Active Fleet Profile as of July 31, 2005 Manufacturer Number Range Production Date Range Number of Buses % of Total Fleet Cummins % Flxible Detroit % % Cummins % Orion Detroit % 33.4% New Flyer Cummins % John Deere % Cummins % Other Detroit % Ford (Cutaway) C001-C % Total % 20

21 Appendix A-2: Capital Program Budget (millions $) Non-MM NOTES Projects Upcoming Underway - Non-Metro pre Metro Matters Matters Projects Upcoming Metro Matters Projects MM NOTES Total Upcoming Projects Total Program Budget Total Remaining Available Project Funds Non-MM NOTES Projects Underway - pre Metro Matters I. Bus Fleet Improvements III. Onboard Systems A. Bus Replacements A. Bus Radio System (5) CNG Buses B Bus AVL FY ; up to 117 Advanced Technology Diesel & 100 Hybrid C. Electric Buses Bus Fare System Replacement Clean Fleet Program D. Scheduling & Dispatch System (5) FY ; 241 Buses E. System Integration - Phase I F Regional Bus Stop Inventory & B. Annual Vehicle Overhaul Database C. MM 185 Expansion Bus Program G Data Warehouse & Reporting H System Integration - Phase II (Single Sign On) I Real-time Passenger Information J Automatic Passenger Counters (3) Bus Fleet Improvements $ $ $ $ $ $ Onboard Systems $ $ - $ (4) $ $ $ II. Maintenance Facilities IV. Bus Stop Improvements A. IRP Rehabilitations A. Bus Maps Enhancement Program Bus Work B. Comprehensive Bus Stop Equipment/Washers/Support Improvements i. Northern Bus Garage ii. Emergency Construction Facilities & Construction C. Premium Bus Branding i. Bladensburg CNG / Bus II CTF D. Priority Corridors & Centers ii. CNG 4 Mile Run Upgrade B. MM Bus Program - VA Garage (West Ox) C. Bus Facilities Upgrade (APTA Peer Review) (3) Maintenance Facilities $ $ $ $ $ $ Bus Stop Improvements $ $ $ (4) $ $ $ (millions $) Upcoming Non-Metro Matters Projects Upcoming Metro Matters Projects MM NOTES Total Upcoming Projects Total Program Budget Total Remaining Available Project Funds Notes: Total Bus CIP Budget $ $ $ $ $ $ (1) General Note - FY programming subject to annual availability of funds as defined by the annual budget approval process; and values displayed are as of May 30, (2) General Note - All IRP funds not committed within the approval year are subject to reprogramming per Board Resolution (3) Currently unfunded; scope not included within Metro Matters Funding Agreement (4) of all (4) notes = $28M; the total FY Metro Matters expenditures provided for in category "Customer Facilities" of the Bus Program (MMFA Attachment 3(C)) (5) Values provided by project manager

22 Appendix A-3: Project(s) Master Schedule Engineering/Design Solicitation/ Award Implementation FY06 FY07 FY08 FY09 FY10 FY Bus Replacement CNG 250 Bus Replacement FY06-08 Annual Vehicle Overhaul Clean Fleet Program Bus Network Evaluation Bus Expansion Metro Matters 185 Bus Replacement FY09-FY11 Bus Maps Enhancement Program Phase 1 Bus Maps Enhancement Phase 2 Comprehensive Bus Stop Improvement Priority Bus Branding Priority Corridors & Centers Scheduling and Dispatch (Trapeze) System Integration AVL, Farebox & Trapedez Bus Fare System Replacement Bus Radio Communication System Bus AVL Regional Bus Stop Inventory and Database Data Warehouse & Reporting System Integration (Single Sign-on) Interim Real Time Passenger Information Unfunded Automatic Passenger Counters (APC) Bus Work Equipment Bladensburg CNG/Bus II CTF CNG Four Mile Upgrade West Ox Maintenance Facility Unfunded Upgrades to Bus Garages Unfunded Trip Planner and IVR 22

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority BUS PROCUREMENT PROGRAM REPROGRAMMING OF FUNDING P D E C PLANNING DEVELOPMENT ENGINEERING CONSTRUCTION Presented to the Board of Directors: Budget Committee

More information

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Page 72 of 96 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

Update on Bus Stop Enhancements

Update on Bus Stop Enhancements Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Report by Planning, Development & Real Estate Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Report by Planning, Development & Real Estate Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary Report by Planning, Development & Real Estate Committee (B) 06-26-08 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 100027 Resolution: Yes

More information

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses Presented to the Board of Directors Planning & Development Committee by

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Executive Summary: Metrobus Network Evaluation and Future Fleet Needs Presented to: Washington Metropolitan Area Transit Authority Submitted by: In Association with P 2 D Joint Venture Introduction Metrobus

More information

Proposed FY2015 Budget and Fare Increase

Proposed FY2015 Budget and Fare Increase Washington Metropolitan Area Transit Authority Proposed FY2015 Budget and Fare Increase Riders Advisory Council January 8, 2014 1 Washington Metropolitan Area Transit Authority What will riders see from

More information

Briefing on Metro Matters Projects

Briefing on Metro Matters Projects Planning, Development and Real Estate Committee Board Information Item III-A March 27, 2008 Briefing on Metro Matters Projects Washington Metropolitan Area Transportation Authority Board Action/Information

More information

Briefing on Metro Matters Projects

Briefing on Metro Matters Projects Customer Services, Operations, and Safety Committee Board Information III-D March 13, 2008 Briefing on Metro Matters Projects Washington Metropolitan Area Transportation Authority Board Action/Information

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number:

Washington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number: Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 100745 Resolution: Yes No TITLE: Approval of 2010 Metrobus Fleet Management Plan PURPOSE:

More information

Precision Station Stopping Progress Update

Precision Station Stopping Progress Update Washington Metropolitan Area Transit Authority Precision Station Stopping Progress Update Presented to: The Board of Directors; Customer Service, Operations and Safety Committee By PlanninghDevelopmenthEngineeringhConstruction

More information

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan Page 54 of 96 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR

More information

JOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm

JOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm ART and APS Bus Parking Informational Session July 27, 2017 7 8:30 pm 2 Agenda Introductions & overview APS Bus Parking APS Bus Facts APS Bus Operations ART Bus Parking Story of ART and its role in County

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information

Improving Accessibility of Regional Bus Stops and Pathways

Improving Accessibility of Regional Bus Stops and Pathways Customer Service and Operations Committee Board Information Item III-A March 13, 2014 Improving Accessibility of Regional Bus Stops and Pathways Page 3 of 17 Washington Metropolitan Area Transit Authority

More information

SamTrans Business Plan Update May 2018

SamTrans Business Plan Update May 2018 SamTrans Business Plan Update May 2018 SamTrans Business Plan Core Principles: 1. Sustain and enhance services for the transit-dependent 2. Expand and innovate mobility services 3. Promote programs that

More information

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: LRT and Streetcar Interoperability Study PURPOSE: To brief the

More information

Increase Rail Service to the Mid City Green Line Stations

Increase Rail Service to the Mid City Green Line Stations Washington Metropolitan Area Transit Authority Increase Rail Service to the Mid City Green Line Stations P D E C Presented to the Board of Directors: Planning and Development Committee by Planning, Development,

More information

The Case for. Business. investment. in Public Transportation

The Case for. Business. investment. in Public Transportation The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend

More information

Background Information about the Metrobus 29 Lines Study

Background Information about the Metrobus 29 Lines Study Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and

More information

Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates

Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates Capital and Strategic Planning Committee Item III - A May 10, 2018 FY2018 Third Quarter Capital Program Updates Page 4 of 44 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer

More information

CHAPTER 5 CAPITAL ASSETS

CHAPTER 5 CAPITAL ASSETS CHAPTER 5 CAPITAL ASSETS This chapter describes the capital assets of GCTD, including revenue and nonrevenue vehicles, operations facilities, passenger facilities and other assets. VEHICLE REVENUE FLEET

More information

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017 US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

The Regional Municipality of York. Purchase of Six Battery Electric Buses

The Regional Municipality of York. Purchase of Six Battery Electric Buses 1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric

More information

Mississauga Transit 2009 Budget

Mississauga Transit 2009 Budget Mississauga Transit 2009 Budget Budget Committee Presentation December 2, 2008 Revenue Ridership Forecasted 2008 Total Rides Including transfers 11% growth in the last 24 months Transit Service Area Business

More information

Metropolitan Council Transit Capital Improvement Plan. September 23, 2009

Metropolitan Council Transit Capital Improvement Plan. September 23, 2009 1 Metropolitan Council 2010-2015 Transit Capital Improvement Plan September 23, 2009 2 Current Situation Capital facilities require longer range view Recent infusion of UPA, CTIB, and State funds have

More information

An Asset Management Plan for Transit And Access Transit Fleet

An Asset Management Plan for Transit And Access Transit Fleet Header Title ATTACHMENT 1 Building Better Transit: An Asset Management Plan for Transit And Access Transit Fleet 2 June 2016 Transit & Access Transit Fleet INTRODUCTION The Saskatoon Transit fleet is currently

More information

A Transit Plan for the Future. Draft Network Plan

A Transit Plan for the Future. Draft Network Plan A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year

More information

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

PARTIAL PROGRAM OF PROJECTS FFY

PARTIAL PROGRAM OF PROJECTS FFY PARTIAL PROGRAM OF PROJECTS FFY 2016-17 The proposed Partial Program of Projects for FFY 2016-17 is attached. The proposed Partial Program of Projects was introduced at the SCTA Board at its meeting on

More information

Late Starter. Tuesday, November 6, 2018

Late Starter. Tuesday, November 6, 2018 Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who

More information

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.

More information

Asset Class 2019 Target 2020 Target 2021 Target 2022 Target 2023 Target REVENUE VEHICLES AB - Articulated Bus N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

Asset Class 2019 Target 2020 Target 2021 Target 2022 Target 2023 Target REVENUE VEHICLES AB - Articulated Bus N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A TheBus - Hernando County, Florida Transit Asset Management Plan Ronald F. Pianta, AICP, Accountable Executive Last modified by Mary Elwin on 14 Aug 18 at 10:13 Introduction TheBus is a TAM Tier II transit

More information

7000 Series Railcar Program Overview

7000 Series Railcar Program Overview Finance, Administration and Oversight Committee Information Item IV-B November 6, 2008 7000 Series Railcar Program Overview Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

1.0 Detailed Definition of Alternatives

1.0 Detailed Definition of Alternatives 1.0 Detailed Definition of Alternatives 1.1 Introduction This chapter provides supplemental information on the four alternatives, including both physical and operational characteristics (e.g. service plans)

More information

I-26 Fixed Guideway Alternatives Analysis

I-26 Fixed Guideway Alternatives Analysis I-26 Fixed Guideway Alternatives Analysis Public Meetings: North Charleston, January 25, 2016 Charleston: January 26, 2016 Summerville: January 28, 2016 Agenda I. Project Update II. III. IV. Screen Two

More information

Feasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study

Feasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study Feasibility Study Community Meeting March, 2017 1 Agenda 1. Welcome / Introductions 2. Background / Meeting Purpose 3. Progress to Date Options Evaluated Capital/Operating Costs Ridership 4. Financial

More information

Authorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County

Authorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County Customer Services, Operations, and Safety Committee Board Action Item IV-A October 2, 2008 Authorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County Washington

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min. AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome

More information

Dismantling the Streetcar System:

Dismantling the Streetcar System: Dismantling the Streetcar System: What Have We Learned? By John Hillegass 42 Line - Courtesy of National Capital Trolley Museum Historic Context DC Streetcar System Agenda Analysis Plan to Convert to Buses

More information

Paid Parking at Park & Ride Lots: Framing the Issues. Capital Programs Committee May 2014

Paid Parking at Park & Ride Lots: Framing the Issues. Capital Programs Committee May 2014 Paid Parking at Park & Ride Lots: Framing the Issues Capital Programs Committee May 2014 Outline Current Status Industry Review DART Case Study Issues Alternatives Mechanics 2 Current Status: All Lots

More information

4 YORK REGION TRANSIT COMPUTER AIDED DISPATCH/AUTOMATIC VEHICLE LOCATION SYSTEM FOR CONVENTIONAL TRANSIT BUSES - UPDATE

4 YORK REGION TRANSIT COMPUTER AIDED DISPATCH/AUTOMATIC VEHICLE LOCATION SYSTEM FOR CONVENTIONAL TRANSIT BUSES - UPDATE 4 YORK REGION TRANSIT COMPUTER AIDED DISPATCH/AUTOMATIC VEHICLE LOCATION SYSTEM FOR CONVENTIONAL TRANSIT BUSES - UPDATE The Transit Committee recommends: 1. The presentation by Rajeev Roy, Manager, Transit

More information

Transit Maintenance Equipment. Maintenance Facilities FY

Transit Maintenance Equipment. Maintenance Facilities FY Transit Maintenance Equipment TIP ID: 5861 Fed/St/Loc Title: Maintenance Equipment 2015-2020 Local 0/0/100 4,300 e 42,635 e 58,414 e 41,428 e 35,820 e 15,805 e 198,401 PRIIA 50/0/50 24,290 e 27,144 e 20,409

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

Milwaukee County Transit System

Milwaukee County Transit System Milwaukee County Transit System 2018 Proposed Transit Budget for Paratransit and Fixed Route Transit Operations and Capital Projects August 2017 Total Transit Budget State $ Federal $ Transit Rev. $ Vehicle

More information

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action MOTION NO. M2018-160 Purchase of Thirteen 42-foot Double Deck Expansion Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee PROPOSED ACTION 12/06/2018 12/20/2018 Recommend to Final

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

Valley Metro: Past, Present and Future. September 11, 2014

Valley Metro: Past, Present and Future. September 11, 2014 Valley Metro: Past, Present and Future September 11, 2014 Valley Metro Who are We? Two Boards of Directors Regional Public Transportation Authority Fund and operate regional transit services Valley Metro

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION MOTION No. M2015-71 Purchase of Five 40-foot Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 08/06/2015 Final Action Bonnie Todd, Executive Director of Operations

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Equipment Management Department. Council Budget Presentation

Equipment Management Department. Council Budget Presentation Equipment Management Department Council Budget Presentation Presented: March 15, 2012 Council Inquiries 1. Please provide a brief summary of shifts in your department s operating budget and staffing levels

More information

DRAFT Evaluation Scores. Transit

DRAFT Evaluation Scores. Transit DRAFT Evaluation s The criteria for evaluating applications for new funding commitments are used to measure how well they advance the six goals identified for the MTP. Through transportation: Reduce per

More information

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 Project Facts 4-mile route, 23 stops 8 made in USA modern streetcars All electric and green Voter-approved project Connects

More information

Columbia Pike Transit Stations

Columbia Pike Transit Stations Public Open House Arlington County Department of Environmental Services April 28, 2015 1 Meeting Purpose Review project goals Update on project status and scope of current work Address next steps and timeline

More information

2010 Sustainability & Public Transportation Workshop:

2010 Sustainability & Public Transportation Workshop: Greening Operations at CUMTD 2010 Sustainability & Public Transportation Workshop: Creating a Culture of Sustainability: Forming New Partnerships With and Within Public Transportation July 26, 2010 Cynthia

More information

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation

More information

Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area. DRAFT Project Summaries

Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area. DRAFT Project Summaries Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area DRAFT Project Summaries May 2009 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROJECTS... 3 2.1

More information

Alternative and Renewable Fuel and Vehicle Technology Program. Advisory Committee Meeting

Alternative and Renewable Fuel and Vehicle Technology Program. Advisory Committee Meeting Alternative and Renewable Fuel and Vehicle Technology Program Advisory Committee Meeting December 4, 2012 California Energy Commission Hearing Room A 1 Meeting Agenda 10:00 Introductions and Opening Remarks

More information

Fleet Sustainability Policy

Fleet Sustainability Policy Fleet Sustainability Policy Scope: CITYWIDE Policy Contact Mark Stevens Fleet Manager Department of Public Works (916) 808-5869 MStevens@cityofsacramento.org Table of Contents A. Emissions Reductions B.

More information

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

Metropolitan Council Budget Overview SFY

Metropolitan Council Budget Overview SFY Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows

More information

Oakland County Board of Commissioners General Government Committee April 23, SMART Services in Oakland County

Oakland County Board of Commissioners General Government Committee April 23, SMART Services in Oakland County Oakland County Board of Commissioners General Government Committee April 23, 2018 SMART Services in Oakland County Today s Presentation SMART in Oakland County Promises Kept Fixed Route Buses Small Buses

More information

Solano County Transit

Solano County Transit AGENDA ITEM: 9 BOARD MEETING DATE: FEBRUARY 18, 2016 Solano County Transit TO: PRESENTER: SUBJECT: ACTION: BOARD OF DIRECTORS ALAN PRICE, PROGRAM ANALYST II REVIEW AND APPROVE IMPLEMENTATION OF THE FUELING

More information

Safety and Operations Committee. Action Item III-A. December 13, 2018

Safety and Operations Committee. Action Item III-A. December 13, 2018 Safety and Operations Committee Action Item III-A December 13, 2018 Preventive Maintenance Update Page 3 of 46 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

The City of Toronto s Transportation Strategy July 2007

The City of Toronto s Transportation Strategy July 2007 The City of Toronto s Transportation Strategy July 2007 Presentation Outline Transportation Statistics Transportation Building Blocks Toronto s Official Plan Transportation and City Building Vision Projects

More information

2013/2014 Strategic Priorities Fund Application Overview

2013/2014 Strategic Priorities Fund Application Overview 2013/2014 Strategic Priorities Fund Application Overview Bob Paddon, Executive Vice President Strategic Planning and Public Affairs TransLink 3 December 2013 Strategic Priorities Fund Application Context

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

WARES. October, 2018

WARES. October, 2018 WARES October, 2018 1 Project Overview A new 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County Operates mostly on the surface with 21

More information

Public Works Department

Public Works Department Public Works Department Fleet Maintenance Mission: To establish and maintain efficient and effective delivery of fleet services by providing customer departments with safe, reliable, economical and environmentally

More information

Strategic Planning for Metro s Transition to Zero Emission Buses. October 2017

Strategic Planning for Metro s Transition to Zero Emission Buses. October 2017 Strategic Planning for Metro s Transition to Zero Emission Buses October 2017 Requirements and Guidelines/Guiding Principles Continue to replace Aging Bus Fleet (~200 Buses per Year) Upgrade current CNG

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

10/4/2016. October 6, Item #1 CITIZENS PARTICIPATION

10/4/2016. October 6, Item #1 CITIZENS PARTICIPATION October 6, 2016 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 WELCOME 2 Item #4 TRAC ROADWAY RECOMMENDATIONS UPDATE Item #4 Completed Jurisdiction Presentations Boulder City August

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,

More information

Bus Stop Optimization Study

Bus Stop Optimization Study Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:

More information

4 Case Study of the Washington Metropolitan Area Transit Authority

4 Case Study of the Washington Metropolitan Area Transit Authority 4 Case Study of the Washington Metropolitan Area Transit Authority RONALD F. KIRBY The Washington Metropolitan Area Transit Authority (WMATA) was formed in 1967 through a congressionally approved interstate

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 19, 2008 DATE: July 10, 2008 SUBJECT: Enactment of an Ordinance to amend, reenact and recodify Section 25-14 (Rates of Fare) of Chapter

More information

Chapter 6 - Capital Improvement Program

Chapter 6 - Capital Improvement Program Chapter 6 - INTRODUCTION This chapter outlines the capital infrastructure projects needed to implement the service recommendations described in Chapter 5. The (CIP) provides the basis for CSPDC s requests

More information

PUBLIC TRANSPORTATION

PUBLIC TRANSPORTATION PUBLIC TRANSPORTATION An Overview of the Industry, Key Federal Programs, and Legislative Processes American Public Transportation Association 1 The Public Transportation Industry: What is "public transportation"?

More information