Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates

Size: px
Start display at page:

Download "Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates"

Transcription

1 Capital and Strategic Planning Committee Item III - A May 10, 2018 FY2018 Third Quarter Capital Program Updates Page 4 of 44

2 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: FY2018 Third Quarter Capital Program Update PRESENTATION SUMMARY: This presentation provides an overview of Metro s performance in executing the FY2018 Capital Program from both a project delivery and benefits to customers perspectives. The presentation highlights key investments that were delivered or progressed significantly during FY2018. PURPOSE: Management will update the Capital and Strategic Planning Committee on the status, delivery and success of the FY2018 Capital Program through the third quarter. DESCRIPTION: Key Highlights: $810 million of capital investments were made through Q3. Full year capital investment is forecasted between $1.17 and 1.25 billion, compared to a budget of $1.25 billion. Capital investments are a major contributor to Metro customers riding experience. Customers are experiencing less rail offloads due to power and equipment failures and an increase in bus on-time performance. Escalator and elevator availability have met or exceeded target. Background and History: Metro invested $810 million in its capital program through March, compared to a budget of $902 million. Full year capital investment is forecasted between $1.17 and $1.25 billion, compared to a budget of $1,250 million. Discussion: Programmatic investments in nine key focus areas represent 75% of capital investment in FY2018. Page 5 of 44

3 FUNDING IMPACT: Railcars Investment: Metro placed 520, 7000 series railcars into revenue service by March 30th. Railcar series 1000 and 4000 were disposed and 130, 5000 series railcars were removed from passenger service. Metro s railcars investments contributed to increased reliability with trains traveling 113,000 miles before an incident; and a nearly 37% decline in customer offloads due to equipment failure. Rail Infrastructure Power: Completed installation of 7,538 orange boots on the entire mainline and 8,651 linear feet of cables off the ground in the underground section. Metro installed six tie breakers, four traction power substations, and three uninterruptable power supply. The completion of power projects contributed to a 46% reduction in train offloads due to power issues. Rail Infrastructure Track and Structures Rehabilitation and Red Line Water Mitigation: Metro experienced a 48% reduction in speed restrictions due to improved track. As of third quarter of FY2018, Metro is above or on target with its planned deliverables for structural concrete poured, deck joints, grout pads, fastners, and running rail. Metro added Red Line Leak Mitigation to its FY2018 deliverables. Structural concrete poured and grout pads increased planned deliverable to address defects. Plannned deliverables for leak mitigation and drain rehabilitation are behind schedule due to reallocating resources to higher priorities. Cellular Phone and Radio System Upgrade: Customers benefited from underground cell phone service between Metro Center to Potomac Avenue, as well as Benning Road to Addison Road. Metro accelerated delivery of 450 multi-band radios for MTPD officers. The new radios will improve interoperability. Rail Station Lighting: Completed 55 of 61 mezzanine light improvements. Light levels improved at eight Blue/Orange Line Stations. New light fixtures produced a 67% energy savings. Rail Station Improvement - Escalators Replacement: Metro replaced 23 escalators. Escalator availability exceeded the 93% target. Rail Station Improvement - Elevator Replacement: Elevator availability met the target of 97%. Metro rehabilitated 9 elevators. Bus Investment: Delivery of bus replacements are slightly behind schedule due to new regulation requirements. Other bus projects, such as bus rehabilitations, energy storage system replacements and transmission assemblies, are on or ahead of schedule. Bus - Andrews Bus Garage: Work continues on the installation of mechanical, electrical, plumbing, interior finishes, and site security fencing. The project is 82% complete with a projected service date of July Information item only - no funding impact. TIMELINE: Page 6 of 44

4 Previous Actions Anticipated actions after presentation February FY2018 Second Quarter Capital Program Update September FY2018 Year-End Capital Program Update RECOMMENDATION: No action required -- information item only. Page 7 of 44

5 FY2018 Third Quarter Capital Program Update 1 Capital and Strategic Planning Committee 05/10/2018 Page 8 of 44

6 Purpose Provide FY2018 Third Quarter Capital Program update and highlight customer benefits of key capital projects 2 Page 9 of 44

7 3 Page 10 of 44

8 Railcars Investments Project Description Acquire 748 new 7000 series railcars by summer 2019 Annual program of railcar preventive maintenance, rehabilitation, safety and reliability improvements Average Fleet Age FY18 Accomplishments 160 new cars placed in service in FY2018, for a total of 520 in service as of March 31 st Disposed 1000 and 4000 series railcars, oldest and least reliable vehicles Removed series cars from passenger service Benefits to Customers Railcars, on average, travelled more than 113,000 miles before an incident occurred that delayed passenger travel Customer offloads due to equipment have declined nearly 37% 100% eight-car trains on Green and Yellow Lines to meet peak ridership demand 4 Page 11 of 44

9 Rail Infrastructure Power Project Description Annual ongoing rehabilitation improvements critical to the safe and reliable electrical system performance, and ability to provide additional capacity for 8-car trains FY18 Accomplishments Installed 6 Tie Breaker Stations Installed 4 Traction Power Substations Installed 3 Uninterruptable Power Supply and accelerated system-wide installation Completed 7,538 Orange Boots on the mainline Completed 8,651 lf of cables off the ground (underground) Benefits to Customers 46% reduction in train offloads due to power issues 100% eight-car trains on Green and Yellow Lines 5 Page 12 of 44

10 Rail Infrastructure Track and Structures Rehabilitation / Red Line Water Mitigation Project Description Annual program to rehabilitate track and structures by replacing deteriorated components Pilot grouting solution near Medical Center to mitigate water infiltration in the tunnels without disturbance, removal, relocation, or replacement of any of the existing utilities, infrastructure or track components Benefits to Customers 48% reduction in speed restrictions due to improved track 6 FY18 Accomplishments Components Planned Actual to Date Structural Concrete Poured (sf) Forecast 1,200 1,797 2,000 Deck Joints Grout Pad Rehabilitation (lf) 8,200 7,696 13,000 Status Leak Mitigation (ea) 2,750 1,050 1,700 * Drain Rehabilitation (lf) 70,000 19,054 38,000 * Fasteners (ea) 23,500 17,797 23,500 Running Rail (mi) Red Line (around Medical Center) Leak Mitigation (ft) * Resources were reallocated to higher priority actions and less work required in Medical Center Tunnel 0 14,270 14,270 Page 13 of 44

11 Cellular Phone / Radio System Upgrade Project Description Replace existing comprehensive radio communication system with a new 700 MHz radio system, with interoperable capabilities with other jurisdictions by FY2020 Improves customer access and reliability to cellular service in underground tunnel system FY18 Accomplishments 13% of overall project complete through March and project is on schedule Complete factory acceptance test of all fixed network equipment for the 700MHz radio system (May 2018) Accelerated delivery of 450 multi-band radios for MTPD officers to improve interoperability Installed 140,000 linear feet of snake tray and more than 548,000 linear feet of cable Benefits to Customers Underground cell phone service provided from Metro Center to Potomac Avenue and Benning Road to Addison Road Cell phone service will be available from Addison Road to Largo Town Center and College Park to Gallery Place later this year 7 Page 14 of 44

12 Rail Station Lighting Investments Project Description Improve illumination, safety, and security in all Metrorail stations by installing new lighting systems that also require less energy, decrease maintenance, and improve system reliability 8 FY18 Accomplishments Awarded three-year contract to replace platform and track bed lights at all 48 underground stations 55 of 61 mezzanine lightings completed. Remaining six mezzanine lighting to be completed by June 30 th as planned Light levels improved at eight Blue/Orange Pre-Installation Line Stations, = 1.5 fc including 700% increase at Foggy Bottom and Farragut West New light fixtures produced a 67% energy savings New bulbs require replacement 50% to 80% less frequently Benefits to Customers Light levels improved at eight Blue/Orange Line Stations, including 700% increase at Foggy Bottom and Farragut West New light fixtures produced a 67% energy savings New bulbs require replacement 50% to 80% less frequently Foggy Bottom Passageway Foggy Bottom Passageway Post-Installation = 10.9 fc Page 15 of 44

13 Rail Station Improvement Escalator Replacement Project Description Repair, rehabilitate or replace Metro s 618 escalators FY18 Accomplishments Replaced 23 escalators as of March 31 st, with another 5 planned by year end Judiciary Square escalator completed one month early allowing the acceleration of two Southern Avenue escalators by a month Benefits to Customers Escalators availability exceeded its target of 93% 9 Page 16 of 44

14 Rail Station Improvement Elevator Rehabilitation Project Description Repair or rehabilitate Metro s 278 elevators FY18 Accomplishments Rehabilitated 9 elevators as of March 31 st, with another 5 planned by year end Pentagon Franconia Springfield (2) Judiciary Square New Carrollton Woodley Park King Street (2) West Falls Church Service and Inspection Benefits to Customers Elevators availability met its target of 97% 10 Page 17 of 44

15 Bus Investments Project Description Replace on average 100 buses per year to maintain average fleet age of 7.5 years Annual program to rehabilitate another 100 buses annually to improve reliability and extend the useful life. Benefits to Customers Bus on-time performance improved across all days of the week and all service periods New buses are 100% low floor, improving accessibility and ease of boarding FY18 Accomplishments Components Planned Actual to Date Forecast Status Bus Replacement * Buses Rehabilitated Energy Storage Systems Replaced Engine Assemblies Rebuilt Transmission Assemblies Rebuilt Average Fleet Age * Delivery of new buses delayed due to mandated environmental testing of engines 11 Page 18 of 44

16 Bus Andrews Bus Garage Project Description Replace Southern Avenue Bus Garage with a 175 bus capacity garage and major overhaul maintenance facility by FY2020 FY18 Accomplishments Approximately 82% complete with a projected service date of July 2019 Continue to install fueling system, mechanical electrical plumbing (MEP), site paving, interior finishes, and acoustical ceilings, and site security fencing Benefits to Customers Increase maintenance capacity by ten additional bus bays to ensure that repairs are made in a timely manner 12 Page 19 of 44

17 Appendix 13 Page 20 of 44

18 Station Out-of-Service Date Return-to Service Date 14 1 U Street (2 Units) 4/3/2017 9/1/ Cleveland Park 6/5/2017 9/14/ Smithsonian 6/15/2017 9/21/ Naylor Road 5/30/ /4/ Eastern Market 6/14/ /23/ Friendship Heights 4/25/ /9/ Medical Center 4/24/ /15/ Stadium-Armory (2 Units) 5/15/ /18/ NoMa- Gallaudet U 8/7/ /20/ NoMa- Gallaudet U 9/11/ /29/ Smithsonian 9/21/2017 1/19/ Suitland 10/2/2017 1/22/ Suitland 10/4/2017 1/31/2018 Page 21 of 44

19 Station Out-of-Service Date Return-to Service Date 14 Naylor Road 10/04/17 02/27/18 15 Eastern Market 10/23/17 03/02/18 16 Cleveland Park 10/23/17 03/12/18 17 NoMa- Gallaudet U 11/20/17 03/16/18 18 Judiciary Square (2 Units) 11/13/17 04/02/18 19 NoMa- Gallaudet U 01/03/18 04/13/18 20 Friendship Heights 11/14/17 05/04/18 21 Suitland 01/31/18 05/18/18 22 Suitland 01/22/18 05/25/18 23 Congress Heights 12/04/17 05/28/18 24 Courthouse 01/16/18 06/11/18 25 Medical Center 11/20/17 06/11/18 15 Page 22 of 44

20 Station Out-of-Service Date Return-to Service Date 1 Pentagon 03/24/17 07/14/17 2 Franconia Springfield (Unit J03X05) 05/23/17 09/27/17 3 Franconia Springfield (Unit J03X06) 05/10/17 09/27/17 4 Judiciary Square 07/07/17 10/21/17 5 New Carrollton 06/22/17 11/02/17 6 Woodley Park 07/25/17 11/09/17 7 King Street (Unit C13N01) 10/18/17 01/02/18 8 King Street (Unit C13N02) 01/02/18 03/02/18 West Falls Church Service & 9 Inspection 01/16/18 04/30/18 10 West Falls Church Facility MNT 10/25/18 5/11/18 11 Gallery Place 11/08/17 05/19/18 12 Prince George s Plaza (2) 03/05/18 05/28/18 16 Page 23 of 44

21 Pre-Foot Candle Readings Post-Foot Candle Readings with Tile Foot Candle Increase Foot Candle Increase 1 McPherson (East) x 2 McPherson (West) x 3 Arlington Cemetery x 4 Crystal City (Passageway) x 5 Foggy Bottom (Passageway) x Foggy Bottom (Under Mezzanine) 3.5x 7 Smithsonian (South) x 8 Farragut West (West) x 9 Farragut West (East) x 10 Pentagon (Lower Level) x 11 Pentagon (Passageway) x 1217 L'Enfant Plaza (7th & MD) WASHINGTON METROPOLITAN AREA TRANSIT 6.1AUTHORITY x Page 24 of 44

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan

Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan Page 72 of 96 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Proposed FY2015 Budget and Fare Increase

Proposed FY2015 Budget and Fare Increase Washington Metropolitan Area Transit Authority Proposed FY2015 Budget and Fare Increase Riders Advisory Council January 8, 2014 1 Washington Metropolitan Area Transit Authority What will riders see from

More information

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan Page 54 of 96 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

SafeTrack Plan. DRAFT May 6, 2016 Public Reference Document

SafeTrack Plan. DRAFT May 6, 2016 Public Reference Document SafeTrack Plan May 6, 2016 Public Reference Document 1 Track Access Demands Continue to Increase Productive 10% Setup 5% Trains Operating 85% NTSB Recommendations Deferred Maintenance FTA Safety Directives

More information

Safety and Operations Committee. Action Item III-A. December 13, 2018

Safety and Operations Committee. Action Item III-A. December 13, 2018 Safety and Operations Committee Action Item III-A December 13, 2018 Preventive Maintenance Update Page 3 of 46 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information

More information

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017 Customer Service, Operations and Security Committee Information Item III-A January 12, 2017 Train Reliability Program Page 4 of 19 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Briefing on Metro Matters Projects

Briefing on Metro Matters Projects Customer Services, Operations, and Safety Committee Board Information III-D March 13, 2008 Briefing on Metro Matters Projects Washington Metropolitan Area Transportation Authority Board Action/Information

More information

Metrorail Line Load Application

Metrorail Line Load Application Metrorail Line Load Application Presented to Travel Demand Forecasting Subcommittee Wendy Jia & Tom Harrington, WMATA Bassel Younan & Jeff Bruggeman, AECOM November 20, 2009 Metrorail Line Load Application

More information

Briefing on Metro Matters Projects

Briefing on Metro Matters Projects Planning, Development and Real Estate Committee Board Information Item III-A March 27, 2008 Briefing on Metro Matters Projects Washington Metropolitan Area Transportation Authority Board Action/Information

More information

Customer Service, Operations and Security Committee. Information Item III-C. June 8, 2017

Customer Service, Operations and Security Committee. Information Item III-C. June 8, 2017 Customer Service, Operations and Security Committee Information Item III-C June 8, 2017 SafeTrack and FY18 Preventive Maintenance and Major Capital Projects Page 33 of 71 Washington Metropolitan Area Transit

More information

Minnesota Avenue Station Parking Garage Repair Project

Minnesota Avenue Station Parking Garage Repair Project Finance & Administration Committee Action Item III-B July 10, 2014 Minnesota Avenue Station Parking Garage Repair Project Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority BUS PROCUREMENT PROGRAM REPROGRAMMING OF FUNDING P D E C PLANNING DEVELOPMENT ENGINEERING CONSTRUCTION Presented to the Board of Directors: Budget Committee

More information

CTA Capital Construction Update December 12, 2006

CTA Capital Construction Update December 12, 2006 Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction

More information

Improving Accessibility of Regional Bus Stops and Pathways

Improving Accessibility of Regional Bus Stops and Pathways Customer Service and Operations Committee Board Information Item III-A March 13, 2014 Improving Accessibility of Regional Bus Stops and Pathways Page 3 of 17 Washington Metropolitan Area Transit Authority

More information

Safety Performance Indicators

Safety Performance Indicators Customer Services, Operations, and Safety Committee Board Information Item V-B October 2, 28 Safety Performance Indicators Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

7000 Series Railcar Program Overview

7000 Series Railcar Program Overview Finance, Administration and Oversight Committee Information Item IV-B November 6, 2008 7000 Series Railcar Program Overview Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Transit Maintenance Equipment. Maintenance Facilities FY

Transit Maintenance Equipment. Maintenance Facilities FY Transit Maintenance Equipment TIP ID: 5861 Fed/St/Loc Title: Maintenance Equipment 2015-2020 Local 0/0/100 4,300 e 42,635 e 58,414 e 41,428 e 35,820 e 15,805 e 198,401 PRIIA 50/0/50 24,290 e 27,144 e 20,409

More information

Precision Station Stopping Progress Update

Precision Station Stopping Progress Update Washington Metropolitan Area Transit Authority Precision Station Stopping Progress Update Presented to: The Board of Directors; Customer Service, Operations and Safety Committee By PlanninghDevelopmenthEngineeringhConstruction

More information

Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan. Virginia Square Site

Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan. Virginia Square Site Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan Virginia Square Site Staff Presentation October 1, 2013 Meeting Agenda Introductions Analysis of Office Uses in Virginia Square

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Safety Report PURPOSE: To present to the Board of Directors a report

More information

Customer Services, Operations, and Safety Committee Board Information Item III-A May 13, 2010 Safety Report

Customer Services, Operations, and Safety Committee Board Information Item III-A May 13, 2010 Safety Report Customer Services, Operations, and Safety Committee Board Information Item III-A May 13, 2010 Safety Report Page 4 of 96 Washington Metropolitan Area Transportation Authority Board Action/Information Summary

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

CTA Capital Construction Update May 17, 2007

CTA Capital Construction Update May 17, 2007 Block 37 Signals Project Brown Line Howard CTA Capital Construction Update May 17, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

Purple Line Light Rail P3 Project

Purple Line Light Rail P3 Project Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

RTSP Phase II Update

RTSP Phase II Update Washington Metropolitan Area Transit Authority RTSP Phase II Update Presentation to the Technical Advisory Group July 18, 2013 Meeting 1 Presentation Outline RTSP Integration with Momentum RTSP Process

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010 BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1

More information

Metro Performance Report ǀ Page 1

Metro Performance Report ǀ Page 1 2 FY2019 Metro Performance Report The following is Metro s system-wide performance for Q2/FY2019 in the areas of quality service, safety, security and financial responsibility. Performance is compared

More information

FOR IMMEDIATE RELEASE January 17, CONTACT: Mayor s Press Office

FOR IMMEDIATE RELEASE January 17, CONTACT: Mayor s Press Office FOR IMMEDIATE RELEASE January 17, 2012 CONTACT: Mayor s Press Office 312.744.3334 press@cityofchicago.org MAYOR EMANUEL OPENS NEWLY-RENOVATED GRAND AVENUE RED LINE STATION Announces New Green Line Station

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

Increase Rail Service to the Mid City Green Line Stations

Increase Rail Service to the Mid City Green Line Stations Washington Metropolitan Area Transit Authority Increase Rail Service to the Mid City Green Line Stations P D E C Presented to the Board of Directors: Planning and Development Committee by Planning, Development,

More information

ANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS

ANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS ANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS RAIL OPERATIONS: Rail Passenger injuries increased from 34 in FY04 to 41 in FY05. The Woodley Park collision accounted for

More information

TESTIMONY of RICHARD SARLES Before the Council of the District of Columbia s Committee on Economic Development February 19, 2014

TESTIMONY of RICHARD SARLES Before the Council of the District of Columbia s Committee on Economic Development February 19, 2014 TESTIMONY of RICHARD SARLES Before the Council of the District of Columbia s Committee on Economic Development February 19, 2014 Good Morning, Chairperson Bowser and members of the Committee on Economic

More information

Update on Bus Stop Enhancements

Update on Bus Stop Enhancements Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information

More information

The $600 Million Rebirth of San Diego Trolley

The $600 Million Rebirth of San Diego Trolley The $600 Million Rebirth of San Diego Trolley E. Wayne Terry Chief Operating Officer MTS Rail APTA Rail Conference - 2010 1919 San Diego and Arizona Eastern Railroad The Bones of the Original South and

More information

Keeping Seattle Moving Seattle City Council February 2013

Keeping Seattle Moving Seattle City Council February 2013 Keeping Seattle Moving Seattle City Council February 2013 Seattle City Council February 2013 1 Mobility Challenges Ahead Viaduct mitigation expires June 2014 Potential system-wide service cuts begin in

More information

Customer Service, Operations and Safety Committee. Rail Car Deployment Strategies

Customer Service, Operations and Safety Committee. Rail Car Deployment Strategies Customer Service, Operations and Safety Committee Rail Car Deployment Strategies July 21, 2005 Department of Operations Table of Contents Purpose Metro Matters Power Upgrade Schedule Current Service Possible

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

Presentation of the Baltimore Metro System

Presentation of the Baltimore Metro System Presentation of the Baltimore Metro System Presenter: Michael S. Davis Deputy Administrator, Transit Operations Division March 2, 2010 Topics Early Planning for Rapid Rail Transit System Overview Section

More information

The Future of Rail in Maryland. Kevin B. Quinn, Jr. Administrator

The Future of Rail in Maryland. Kevin B. Quinn, Jr. Administrator The Future of Rail in Maryland Kevin B. Quinn, Jr. Administrator The Future of Rail in Maryland Rolling Stock Metro Railcar Replacement Under the project, MDOT MTA is replacing the metro fleet with 78

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer

More information

An Asset Management Plan for Transit And Access Transit Fleet

An Asset Management Plan for Transit And Access Transit Fleet Header Title ATTACHMENT 1 Building Better Transit: An Asset Management Plan for Transit And Access Transit Fleet 2 June 2016 Transit & Access Transit Fleet INTRODUCTION The Saskatoon Transit fleet is currently

More information

Commuter Rail Update. October 25, 2018

Commuter Rail Update. October 25, 2018 Commuter Rail Update October 25, 2018 2 page page 3 State of Commuter Rail Network, July 2014 The 2014 Commuter Rail network had multiple issues and a history of neglect & under-investment FIRST UP? UPGRADES

More information

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Executive Summary: Metrobus Network Evaluation and Future Fleet Needs Presented to: Washington Metropolitan Area Transit Authority Submitted by: In Association with P 2 D Joint Venture Introduction Metrobus

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

Status Report Metrobus Capital Improvement Program FY06-11

Status Report Metrobus Capital Improvement Program FY06-11 Washington Metropolitan Area Transit Authority Status Report Metrobus Capital Improvement Program FY06-11 P D E C Presented to the Board of Directors: Planning & Development Committee September 8, 2005

More information

Metropolitan Council Budget Overview SFY

Metropolitan Council Budget Overview SFY Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows

More information

Report by Planning, Development & Real Estate Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Report by Planning, Development & Real Estate Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary Report by Planning, Development & Real Estate Committee (B) 06-26-08 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 100027 Resolution: Yes

More information

STAFF REPORT INFORMATION ONLY

STAFF REPORT INFORMATION ONLY Insert TTC logo here STAFF REPORT INFORMATION ONLY Presentation: Subway Closures - 2016 Year In Review and 2017 Forecast Date: January 18, 2017 To: From: TTC Board Chief Executive Officer Summary The purpose

More information

End-of-Year Performance Report FY Community Relations Committee December 5, 2018

End-of-Year Performance Report FY Community Relations Committee December 5, 2018 End-of-Year Performance Report FY 2018 Community Relations Committee December 5, 2018 Annual Summary Shuttles Ridership All Modes Performance Statistics Highlights All Modes Initiatives 2 Bus Ridership

More information

Dallas CBD Second Light Rail Alignment (D2)

Dallas CBD Second Light Rail Alignment (D2) Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement Stakeholder Meeting December 7, 2016 Discussion Items Background Schedule Public/Stakeholder Involvement Comments/Questions from Audience

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

WMATA Quarterly Progress Report Q2 Fiscal Year 2018

WMATA Quarterly Progress Report Q2 Fiscal Year 2018 Table of Contents I. Highlights... 3 II. Operating Results... 6 A. Summary... 6 B. Ridership and Revenue... 6 C. Operating Expenses... 10 III. Capital Programs... 12 A. Railcar Investments... 12 1. Railcar

More information

Transit in Bay Area Blueprint

Transit in Bay Area Blueprint Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the, and double deck ( dd) analysis Including: Description of the Vehicles

More information

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017 Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,

More information

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only METRONext Vision & Moving Forward Plans Board Workshop December 11, 2018 Disclaimer This presentation is being provided solely for discussion purposes by the Board of Directors of the Metropolitan Transit

More information

CPG is pleased to report the following accomplishments this quarter:

CPG is pleased to report the following accomplishments this quarter: MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

1.0 Detailed Definition of Alternatives

1.0 Detailed Definition of Alternatives 1.0 Detailed Definition of Alternatives 1.1 Introduction This chapter provides supplemental information on the four alternatives, including both physical and operational characteristics (e.g. service plans)

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Presentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS

Presentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS Presentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS May 19, 2005 Department of Operations 100 95 90 85 80 75 70 65 A B C D RAIL PERFORMANCE INDEX FY

More information

Commuter Rail Vehicle Technology Analysis

Commuter Rail Vehicle Technology Analysis Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the EMU, DMU and DMU double deck (DMU dd) analysis Including: Description

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the

More information

PRASA Challenges & Opportunities Standing Committee on Appropriations 25 th March 2015

PRASA Challenges & Opportunities Standing Committee on Appropriations 25 th March 2015 PRASA Challenges & Opportunities Standing Committee on Appropriations 25 th March 2015 Agenda A Introduction to PRASA B Funding Allocation and Spending Performance C Strategic Plan D Rail Modernisation

More information

BART s Transbay Core Capacity Project

BART s Transbay Core Capacity Project BART s Transbay Core Capacity Project Duncan Watry, Principal Planner Bay Area Rapid Transit Oakland, CA dwatry@bart.gov Donald Emerson, Principal Consultant WSP Parsons Brinckerhoff San Francisco, CA

More information

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min. AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome

More information

Sound Transit Operations July 2016 Service Performance Report. Ridership

Sound Transit Operations July 2016 Service Performance Report. Ridership Ridership Total Boardings by Mode Mode Jul-15 Jul-16 % YTD-15 YTD-16 % ST Express 1,618,779 1,545,852-4.5% 10,803,486 10,774,063-0.3% Sounder 333,000 323,233-2.9% 2,176,914 2,423,058 11.3% Tacoma Link

More information

The Case for. Business. investment. in Public Transportation

The Case for. Business. investment. in Public Transportation The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend

More information

SEPTA Public Open House. FY 2019 Capital Budget Development January 24, 2018

SEPTA Public Open House. FY 2019 Capital Budget Development January 24, 2018 SEPTA Public Open House FY 2019 Capital Budget Development January 24, 2018 SEPTA Public Open House FY 2019 Capital Budget Development January 24, 2018 FY 2018 Capital Budget and 12-Year Capital Program

More information

CLRP. Performance Analysis of The Draft 2014 CLRP. Long-Range Transportation Plan For the National Capital Region

CLRP. Performance Analysis of The Draft 2014 CLRP. Long-Range Transportation Plan For the National Capital Region NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD Item 12 CLRP Financially Constrained Long-Range Transportation Plan For the National Capital Region 2014 Performance Analysis of The Draft 2014 CLRP

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Vision Vision to Action: 2012 Progress. Community Perspectives. customer focus

Vision Vision to Action: 2012 Progress. Community Perspectives. customer focus Community Perspectives service customer focus Transit Vision 2040 Vision to Action: 2012 Progress Summary Report GREENING FUNDING BACKGROUND THEME 1: Putting Transit at the Centre of Communities Transit

More information

Denver Metro Association of Realtors

Denver Metro Association of Realtors Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

Rail On-Time Performance 88 % Target 75% on-time. Customer Satisfaction Rail 74 % Rail Fleet Reliability 86,814. Target 75,000 miles between delay

Rail On-Time Performance 88 % Target 75% on-time. Customer Satisfaction Rail 74 % Rail Fleet Reliability 86,814. Target 75,000 miles between delay Vital Signs 1 July-September 2017 Published: November 2017 Key Performance Indicators Bus On-Time Performance 79 % Target 79% on-time Customer Satisfaction Bus 76 % Rail On-Time Performance 88 % Target

More information

AWARD CONTRACT FOR LINE BREAKERS

AWARD CONTRACT FOR LINE BREAKERS @ Metro Metropolitan Transportation Authority 45 One Gateway Plaza 213.922.2000 Los Angeles, CA 90012-2952 metro.net OPERATIONS COMMITTEE JULY 16,2009 SUBJECT: LINE BREAKERS ACTION: AWARD CONTRACT FOR

More information

Maryland Gets to Work

Maryland Gets to Work I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal

INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal PATCO High Speed Line Power Infrastructure Renewal Page 1 of 5 INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal This Engineering Excellence Award entry

More information

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses Presented to the Board of Directors Planning & Development Committee by

More information

APPROVE CONTRACT MODIFICATION AWARD

APPROVE CONTRACT MODIFICATION AWARD 5 One Gateway Plaza Los Angeles, CA 9 012.2952 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE SEPTEMBER 20, 2012 SUBJECT: ACTION: ENGINE REBUILD KITS APPROVE CONTRACT MODIFICATION AWARD

More information

WARES. October, 2018

WARES. October, 2018 WARES October, 2018 1 Project Overview A new 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County Operates mostly on the surface with 21

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

MIDDAY STORAGE. VRE has temporarily used Ivy City Coach Yard since 1992 Insufficient today Restricts further growth

MIDDAY STORAGE. VRE has temporarily used Ivy City Coach Yard since 1992 Insufficient today Restricts further growth MIDDAY STORAGE VRE has temporarily used Ivy City Coach Yard since 1992 Insufficient today Restricts further growth Will diminish to zero Agreement allows reduction in VRE storage starting July 2018 Washington

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

Good morning, Chairman Lautenberg, Ranking Member Wicker, and other members of the Committee.

Good morning, Chairman Lautenberg, Ranking Member Wicker, and other members of the Committee. 1 Testimony of Joseph J. Lhota Chairman and CEO of the New York Metropolitan Transportation Authority to the U.S. Senate Subcommittee on Surface Transportation and Merchant Marine Infrastructure December

More information

Overview of Transit Projects in the Transportation Investment Act in MARTA Jurisdictions. June 11, 2012

Overview of Transit Projects in the Transportation Investment Act in MARTA Jurisdictions. June 11, 2012 Overview of Transit Projects in the Transportation Investment Act in MARTA Jurisdictions June 11, 2012 TIA-023: I-20 East $ 225 million Project will construct bus P&R intended to be future rail stations

More information

Asset Class 2019 Target 2020 Target 2021 Target 2022 Target 2023 Target REVENUE VEHICLES AB - Articulated Bus N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

Asset Class 2019 Target 2020 Target 2021 Target 2022 Target 2023 Target REVENUE VEHICLES AB - Articulated Bus N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A TheBus - Hernando County, Florida Transit Asset Management Plan Ronald F. Pianta, AICP, Accountable Executive Last modified by Mary Elwin on 14 Aug 18 at 10:13 Introduction TheBus is a TAM Tier II transit

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information