Fukushima Accident and Safety Assurance Measures for TEPCO NPP

Size: px
Start display at page:

Download "Fukushima Accident and Safety Assurance Measures for TEPCO NPP"

Transcription

1 Fukushima Accident and Safety Assurance Measures for TEPCO NPP IEEE NPEC N12-02 San Diego July 25, 2012 Yasushi Nakagawa Tokyo Electric Power Company All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

2 Damage to the Power Supply Facilities by tsunami and earthquake at 1F and 2F site. Fukushma Daiichi(1F) Fukushma Daini(2F) Unit 5 Unit 1 Unit 2 Unit 3 Unit 4 Unit 6 4 Unit 3Unit Unit 2 Unit 1 All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 1

3 Plant Unit Overview of Fukushima Daiichi NPS (1F) and Fukushima Daini NPS (2F) In Operation Since Plant Type Power Output (MWe) Main Contractor Pre earthquake Status BWR GE Operating BWR GE/Toshiba Operating BWR Toshiba Operating 1F BWR Hitachi Planned Outage Full core offloaded to spent fuel pool BWR Toshiba Planned Outage BWR GE/Toshiba Planned Outage BWR Toshiba Operating 2F BWR Hitachi Operating BWR Toshiba Operating BWR Toshiba Operating All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 2

4 Power supply of Unit 1F after Tsunami Okuma Line 1L, 2L: Receiving circuit breaker damaged in earthquake Okuma Line 3L: Renovation work in progress Okuma Line 4L: Circuit breaker shutdown by protection relay activation Shutdown by earthquake Shutdown by Tsunami Ohkuma 4L Ohkuma 3L Ohkuma 2L Ohkuma 1L 3SB 3SA 2SB 2SA 1S 4B 4A 3B 3A 2B 2A 1B 1A 4D 4C 3D 3C 2D 2C 1D 1C 4E 2E 4B 4A 3B 3A 2B 2A 1B 1A The DGs lost the function due to either Switchgear failure, loss of sea water system, or DG main conponent failure. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 3

5 Power supply of Unit 1F after Tsunami 5C 5A For transmitting power 双双葉葉Futaba 線1L Futaba For 12L transmitting Lpower Yonomori 1L Yonomori 2L 5B 5SA-1 5SA-2 5SB-1 5SB-2 6A-1 6A-2 5D HPCS 6C Shutdown by earthquake Shutdown by Tsunami Survived after tsunami 5B HPCS 6A 線2L5A 6B-1 6B-2 6D 6B

6 Damages of transmission line & Shinfukushima substation by earthquake Collapse of bed soil & sand Transmission tower collapse Tower collapse Collapse (C)GeoEye - About 10 km away from both 1F and 2F site - Important switchgear station from which electricity of 1F & 2F is transmitted to Tokyo area 500kV Disconnector 275kV Circuit Breaker All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 5

7 2F Offsite Power was secured after the Tsunami Tomioka Line 500kV Offsite Power H STr One 500 kv line was available. 66 kv lines were outage because of scheduled Iwaido Line maintenance and substation trouble but recovered. Many power centers and motors were damaged 66kV because of the flooding. P : Cooling Pumps : Diesel Generator Unit #1, 2 STr Unit #3, 4 STr 6.9kV 6.9kV 6.9kV 6.9kV P P P P P P P P 1H 1A 1B 2H 2A 2B 3H 3A 3B 4H 4A 4B Emergency Power for Unit #1 Emergency Power for Unit #2 Emergency Power for Unit #3 Emergency Power for Unit #4 All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 6

8 Integrity of Power Supply System After the Tsunami at 1F and 2F Emergency Emergency use Regular use Regular use 125V DC use Emergency DG DG power 6.9KV M/C M/C 480V P/C PC DC supply Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel Can/can not be used Power panel DG 1A DG 2A DG 3A DG 4A DG 5A(*2) DG 6A (*2) DG 1A DG 2A (*2) DG 3A (*2) DG 4A (*2) DG 1B DG 2B (air-cooled) (*1) DG 3B DG 4B (air-cooled) (*1) DG 5B(*2) DG 6B (air-cooled) Can/can not be used DG 1B DG 2B (*2) DG 3B DG 4B (*2) HPCS DG (*2) DG 1H DG 2H (*2) DG 3H DG 4H M/C 1C M/C 2C M/C 3C M/C 4C M/C 5C M/C 6C M/C 1C M/C 2C M/C 3C M/C 4C M/C 1D M/C 2D M/C 3D M/C 4D M/C 5D M/C 6D M/C 1D M/C 2D M/C 3D M/C 4D - - M/C 2E - - M/C 4E - - M/C 1A M/C 1B 1F:No off-site power available Unit 1 Unit 2 M/C 2A M/C 2B M/C 3A M/C 3B Fukushima Daiichi Unit 3 Unit 4 Unit 5 Unit 6 M/C 4A M/C 5A M/C 4B HPCS DG M/C M/C 1H M/C 2H M/C 3H M/C 4H M/C 6A-1 M/C 1A-1 M/C 2A-1 M/C 3A-1 M/C 4A-1 M/C 6A-2 M/C 1A-2 M/C 2A-2 M/C 3A-2 M/C 4A-2 M/C 6B-1 M/C 1B-1 M/C 2B-1 M/C 3B-1 M/C 4B-1 M/C 6B-2 M/C 1B-2 M/C 2B-2 M/C 3B-2 M/C 4B-2 M/C 1S M/C 5SA-1 M/C 1SA-1 M/C 3SA-1 M/C 2SA M/C 3SA M/C 5SA-2 M/C 1SA-2 M/C 3SA M/C 5SB-1 M/C 1SB-1 M/C 3SB-1 M/C 2SB M/C 3SB M/C 5SB-2 M/C 1SB-2 M/C 3SB-2 - P/C 1C P/C 2C P/C 3C P/C 4C P/C 5C P/C 6C P/C 1C-1 P/C 2C-1 P/C 3C-1 P/C 4C-1 P/C 1D P/C 2D P/C 3D P/C 4D P/C 5D P/C 6D P/C 1C-2 P/C 2C-2 P/C 3C-2 P/C 4C P/C 2E - - P/C 4E - - P/C 6E P/C 1D-1 P/C 2D-1 P/C 3D-1 P/C 4D-1 P/C 1A P/C 2A P/C 3A P/C 4A P/C 5A P/C 6A-1 P/C 1D-2 P/C 2D-2 P/C 3D-2 P/C 4D-2 P/C 2A P/C 5A-1 P/C 6A-2 P/C 1A-1 P/C 2A-1 P/C 3A-1 P/C 4A-1 P/C 1B P/C 2B P/C 3B P/C 4B P/C 5B P/C 6B-1 P/C 1A-2 P/C 2A-2 P/C 3A-2 P/C 4A P/C 5B-1 P/C 6B-2 P/C 1B-1 P/C 2B-1 P/C 3B-1 P/C 4B-1 P/C 1S - - P/C 3SA - - P/C 5SA - - P/C 1B-2 P/C 2B-2 P/C 3B-2 P/C 4B P/C 5SA P/C 1SA P/C 3SA P/C 2SB P/C 3SB - - P/C 5SB - - P/C 1SB P/C 3SB - DC125V main DC125V P/C DC125V main DC125V main DC125V P/C DC125V DIST DC125V main DC125V main DC125V main DC125V main bus panel A 2A bus panel 3A bus panel 4A 5A CENTER 6A bus panel A bus panel A bus panel A bus panel A DC125V main DC125V P/C DC125V main DC125V main DC125V P/C DC125V DIST DC125V main DC125V main DC125V main DC125V main bus panel B 2B bus panel 3B bus panel 4B 5B CENTER 6B bus panel B bus panel B bus panel B bus panel B M/C 5B 2F:Off-site power survived Fukushima Daini Unit 1 Unit 2 Unit 3 Unit 4 Sea water system A RHRS A RHRS A RHRS A RHRS A RHRS A RHRS A RHRS A RHRS A RHRS A SW B RHRS B RHRS B RHRS B RHRS B RHRS B RHRS B RHRS B RHRS B RHRS B Sea Water System O: operable X: damaged *1 functionality lost due to inundation of power panels *2 functionality lost due to the damage of sea water system All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 7

9 Overview of the Fukushima Accident The Tohoku-Chihou-Taiheiyou-Oki Earthquake around 14:46, Mar. 11 th Reactor SCRAM due to the Earthquake (Emergency Shutdown) Loss of External Power Start-up *1 Post-SCRAM Operation Post- SCRAM Operation Tsunami struck Fukushima-Daiichi & Fukushima-Daini NPPs around 15:20~, Mar. 11 th Fukushima-Daiichi Unit 4 Units 1~3 Units 5,6 [Power] No AC power, No [Seawater system] Not available [Power] 6B start-up [Seawater system] Not available Fukushima-Daini [Power] AC Power available [Seawater system] Unit 3 available *2 Water injection & heat removal via HP system Water injection via LP system: fire engine (Freshwater & Seawater) Power supply from Unit 6 to Unit 5 Water injection via HP (Steam-driven) & LP systems Water injection via LP system No route ensured for heat removal, response for stabilization Cold Shutdown Condition (Dec. 16) Heat removal ensured by temporary power source & seawater pump Heat removal ensured by temporary power source & motor replacement etc. Cold Shutdown (Mar. 20) Cold Shutdown (Mar. 15)*3 Fukushima-Daiich 1~4 Fukushima-Daiichi 5,6 Fukushima-Daini 1~4 *1 :Emergency Diesel Generator *2 RHR Seawater System *3 Fukushima-Daini Emergency State was Lifted on Dec.26 All Rights Reserved 2012The Tokyo Electric Power Company, Inc. tth 8 8

10 Recovery of Electrical equipment and Power Supply during Fukushima accident All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 9

11 Restoration of lights and I&Cs in Control 1F Temporary lights The Compact type generators were carried from the contractor s warehouse and supply power to temporary lights in the Main Control Room. Temporary power supply Connect temporary batteries to recover I&C. e.g. Reactor water level indicator SRV contrrol circuit All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 10

12 Temporary Power Source (Power Supply car) Recovering Power 1F Unit 5 Unit 5 Unit 6 M/C 6C External Power M/C 6D External Power Operable since 18 th March P/C 6C G 6A P/C 6D M/C 6E G 6B 5U RHR MCC T/B MCC 6C-2 T/B MCC 6C-1 Temporary Underwater Pump (Substitute of RHR )RHR Pump 5C (18 Mar) (18 Mar) DC125V Charger Control Panel 5A DC125V Charger Control Panel 5B Connection Line for accident management Control Room Lighting (12 Mar) (15 Mar) (21 Mar) MUW 5A (13 Mar) SGTS 5A Space Heater SGTS 5A (13 Mar) (13 Mar) Directly connected to the motor Temporary Cables All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 11

13 Recovering of Electrical 2F Pumps of RHR cooling systems (RHRC, RHRS, EECW) were inspected. Motors were replaced for pumps in RHRC and EECW. In order to restore the inundated electrical buses, temporary cable and high voltage mobile power vehicles were prepared. Temporary cable was laid from survived power cubicles in Rad-Waste Building to survived power cubicles in Unit 3 Heat Exchanger Building. Drawing made at TSC for temporary cable laying Motor replacement All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 12

14 Recovering Power 2F Temporary cable of 9 km length was laid by about 200 personnel within a day. Usually this size of cables laying requires 20 personnel and more than 1 month period. After the pumps for RHR cooling systems were restored and temporary cable was laid, RHR (B) of Unit 1 started up at 1:24 on March 14 and other units followed. Finally at 15:42 on March 14 with the start up of Unit 4 RHR, RHR of all four reactors started operation in Fukushima Daini NPS. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 13

15 Temporary Power Supply and Motor Unit #4 Hx Building Unit #3 Hx Building Unit #2 Hx Building Unit #1 Hx Building Mobile Power Supply Truck (500kVA) Unit #4 Turbine Unit #4 Reactor 6.6kV/480V Transformer Unit #3 Turbine Unit #3 Reactor Mobile Power Supply Truck (500kVA) Unit #2 Turbine Unit #2 Reactor 6.6kV/480V Transformer Unit #1 Turbine Unit #1 Reactor Temporar y Cables Rad-Waste Building TSC Main Office All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 14

16 Safety Assurance Measures for TEPCO NPP All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 15

17 Basic Concept of Safety Assurance Measures for TEPCO NPP Flooding protection measures to cope with tsunami In order to prevent tsunami causing the submergence of safety critical equipment and functional loss, flooding protection measures are taken mainly for reactor buildings. Drainage systems are also provided as a precaution. Fuel damage prevention measures during SBO or loss of heat sink Materials and equipment are stored at high places in plant premises to prevent damage to the fuels in reactors and SFPs even during SBO or LUHS, and flexible procedures provided for an effectively use of these materials and equipment. Effect mitigation measures provided as a precaution for fuel damage A top vent is installed for preventing hydrogen explosions following a bare possibility of fuel damage. For ensuring preparations, a filter vent is also installed to mitigate radiation impact on the environment. Common measures Materials and equipment critical for supporting the restoration of reactor facilities following an accident, and a system of using them are provided. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 16

18 Safety Measures at Kashiwazaki-Kariwa NPS Completed at K-1,7 Enhancement of injection and heat removal - Submerged pump - Heat exchanger truck - Mobile Power Truck - Spare hose Completed at K-1,7 Prevention of accumulating Hydrogen (1)Top vent on Reactor Building In progress Enhancement of injection and heat removal (2)On-site Reservoir To RHR To SFP Off site power line Sea Filtered water tank & Purified water tank Filtered water tank In progress Heat exchange building Enhancement of protection for flooding (1)Embankment (2)Wall (3)Water-tight doors in Reactor Building Turbine building Completed at K-1,7 Reactor building Enhancement of power supply source (1)GT-driven generator truck (2)Emergency high voltage switchgear (3)Cable from emergency high voltage switchgear for RHR (4)Undergroud light oil storage tanks Completed (1) Additional monitoring cars (2) Additional warehouse for emergency materials on the hill All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 17

19 Completed To supply power during SBO - High voltage power trucks - Portable generators - spare cables Safety Measures at Kashiwazaki-Kariwa NPS Submerged pump Sea Spare gas cylinder Motor Control CenterCharger To open SRV -Spare gas cylinders -Spare batteries Fuel pool cooling pump Heat Ex Heat Ex SRV Completed PCV Reactor Clean up pump Reactor Building Spent Fuel Pool Completed To monitor SFP Water Level -Additional instruments Completed To inject water into RPV and SFP -Fire trucks -Spare hoses Completed Status at K-1,7 To Transfer water Filtered or Purified Water Tank to CST - Fire trucks Mobile power trucks Completed To vent PCV - Spare gas cylinders Low voltage Distribution PNL Battery Control Panel To Turbine Spare gas cylinder Containment Vent valve RPV Stand by Liquid Control System Pump RCIC pump Condensate Storage Tank Make-up water pump Diesel driven fire protection pump Purified water Transfer pump Legend Fire protection sys. Make-up water sys. RCIC Fire Truck Filtered water Tank Purified water Tank Fuel pool cooling sys. Reactor Clean up Water sys. Power line Sea All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 18

20 Emergency AC Power Source during SBO or loss of heat sink Status at K-1,7: Completed Assuring AC power supply in case of loss of existing power supply (offsite power/emergency diesel generator) 1)An emergency switchgear (HV switchboard) has been installed on a high ground with an air-cooled gas turbine generator car to supply power to the safety-related switchgear in the plant. 2)A power supply vehicle is prepared to supply power directly to the emergency switchgear or the safety-related switchgear in reactor building. 3)Procedures, tools and equipments are provided for the direct connection of power supply between the power supply vehicle and safety-related pump-motors in case of failure to implement 1) and 2). Seawater equipment building Turbine bldg. Pump ポンプモータ motor P/C 1) Power supply from air-cooled GTG via emergency M/C Reactor bldg. RHR Switchgear 3)Direct power supply to pump motor 500 kva power source vehicle 500kV 電源車 Emergency Switchgear * GTG: Gas turbine generator car 500 kva power source vehicle Air-cooled GTG 2) Power supply from power source car to switchboard in Reactor building All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 19

21 Emergency DC Power Source during SBO or loss of heat sink Status at K-1,7 : In progress RCIC is designed to operate for around 8 hours with DC power during SBO. TEPCO considered measures to extend the life of batteries to operate RCIC for long time. TEPCO evaluated that RCIC can actually continue operating for about 38 hours only with the battery (A) after assessing load of battery (A) in detail. RCIC can continue operating for about 72 hours with following steps 1) to 4). MCC 1H 125VDC Main bus board 1H 125VDC Battery 1H 500Ah MCC 1C VDC charging board 1A [DC power enhancement] 125VDC Battery 1A 4000Ah MCC 1C VDC main bus board 1A MCC 1D-1-1 Link with B system (Proposed - via aux. charging board ) AUX. AUX. AUX. Link with H system (Newly tied with a cable) 125VDC Charging board Aux. Connection of a temporary battery 仮設蓄電池 Temporary battery 125VDC Battery 1B 1600Ah MCC 1D VDC Main bus board 1B 1) To disconnect CVCF(A) from battery (A) 1 hour later, and disconnect DC lighting 8 hours later. 2) To disconnect CVCF(B) from battery (B) 1 hour later. 3) To connect tie-line between battery (A) and battery (B), 8 hours later, and connect tie-line between battery (A) and battery (H) about 36 hours later. 4) To add temporary batteries when the existing batteries are used up. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 20

22 Emergency DC Power Source during SBO or loss of heat sink Status at K-1,7 : Complete The safety relief value (SRV) is opened to depressurize the reactor. Spare nitrogen cylinders are prepared in addition to the existing cylinders to supply compressed air for opening the valve. The portable battery is prepared as an alternative means in case that the power to open the SRV is lost. SRV Main Control Room or Reactor bldg. Temporary operation switch (SW) Temporary power supply Accumulato r SW + cable (Length: 30 m) 12VDC battery (Capacity: 56 Ah) Opening SRV using a battery All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 21

23 Further enhancement of power supply functions Status: Planning In addition to safety measures, TEPCO is planning to further enhance power supply function to extend SBO coping time without portable devices. Power source vehicle Install additional 125V batteries Emergency Switchgear Install additional generator, charger and batteries on the higher floor Reactor Bldg Prepared Control Bldg Additional special generator Special Charger 125V battery Control Room charger Additional 125V batteries (A) 125V battery (A) P/C(C) B1 MB2 B2 Seal type 125V batteries 250V Battery Main bus panel DC MCC M/C(C) Replace existing vent type 250V batteries with seal type 250V batteries for ensuring the room for additional 125V batteries All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 22

24 Further enhancement of power supply function (Plan) Status: Planning Load ~1h ~8h ~24h 24h~ ~72h RCIC auxiliary equipment Vital AC Power CVCF Power Non Safety I&C Safety I&C disconnect disconnect AC lighting Power Supply Battery (A) increased capacity Additional battery on the higher place Additional generator charger Supply Power disconnect Supply Power Supply Power All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 23

25 Summary The Fukushima accident was caused by the simultaneous loss of multiple safety functions due to far beyond design basis of tsunami. The main factors of the accident are the simultaneous loss of total AC power and DC power for a extended period of time and the loss of the heat removal function of the emergency seawater system for a extended period of time. Various countermeasures such as installation of Reactor Building Top vent, and preparation of mobile power vehicle and heat exchanger vehicle start to be implemented at Units 1 and 7 in Kashiwazaki Kariwa NPS. In those countermeasures, TEPCO enhanced or will enhance the power supply function to extend SBO coping time at Kashiwazaki Kariwa NPS. TEPCO is prepared to contribute to developing or revise IEEE standards in order to further enhance world-wide nuclear safety. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 24

26 Thank you for your attention. All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 25

27 Website Information TEPCO English website TEPCO Internal Investigation Committee Final Report (June 20 th, 2012) English version will be on the following website soon. TEPCO Internal Investigation Committee Interim Report (Dec. 2 nd, 2011) Mid- to Long-Term Road Map Towards Decommissioning of 1F Units 1-4 (Dec. 21 st, 2011) INPO Special Report on Fukushima Daiichi Nuclear Power Station EPRI Fukushima Daini Independent Review and Walkdown NEI Article on Fukushima Daini All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 26

28 References All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 27

29 Inundated Areas at 1F Inundation throughout almost all areas where main buildings sited Units 1~4: Inundation height in areas where principal buildings sited: OP approx. 11.5m~15.5m (Localized inundation height in southwest area: OP approx. 16m~17m) Unit 5 & 6: Inundation height in areas where principal buildings sited: OP approx. 13m~14.5m Almost whole area was flooded Fukushima Daiichi Unit 6 Unit 5 Unit 1 Unit 2 Unit 3 Unit 4 Elevation of major Unit-5,6 buildings: O.P.13m Elevation of major Unit-1-4 buildings: O.P.10m Radwaste Processing building (C)GeoEye All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 28

30 Location of Openings from which Sea Water could Flow into Main Buildings (Fukushima Daiichi Nuclear Power Station) O.P.+4m O.P.+4m 6 号機 5 号機 Unit 6 6 号機 DG 建屋 Unit 5 O.P.+13m Unit 6 building Turbine building タービン建屋 原子炉建屋 Reactor building 1 号機 2 号機 3 号機 4 号機 Unit 1 Unit 2 Unit 3 Unit 4 O.P.+10m 運用補助共用建屋 : Openings at the ground level from which sea water could flow into buildings :Openings connected to underground trenches/ducts where sea water could flow into buildings 3u Emergency air inlet louver All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 29

31 Inundated Areas at 2F Inundation occurred throughout all areas along the sea, but it was not observed to have inundated over the slope and into areas where major buildings are sited. Run up of tsunami centered on the south side of Unit 1 Inundation height in sea side area: OP approx. +7.0~7.5m Inundation height in areas where principal buildings sited: OP approx. 12~14.5m Inundation height in area south of Unit 1: OP approx. + 15~16m Limited area was flooded Inflowed intensively Unit 4 Unit 3 Unit 2 Unit 1 Elevation of major Unit-1-4 buildings: O.P.12m (C)GeoEye All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 30

32 Location of Openings from which Sea Water could flow into Main Buildings (Fukushima Daini Nuclear Power Station) Inside Unit 1 heat exchanger building Units 3 & 4 Sea side of turbine building Heat exchanger building Turbine building Unit 4 Unit 3 Unit 2 Unit 1 Reactor building :Openings at the ground level from which sea water could flow into buildings :Openings connected to underground trenches/ducts where sea water could flow into buildings All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 3131

33 Intensity of the earthquake at the power stations In Fukushima Daiichi the observed data partially exceeded the maximum response acceleration with respect to the design-basis earthquake, however most data was below the baseline Observation Point (The lowest basement of reactor buildings) Horizontal (N-S) Observed Data Maximum Response Acceleration (gal) Horizontal (E-W) Vertical Maximum Response Acceleration against Basic Earthquake Ground Motion (Gal) Horizontal (N-S) Horizontal (E-W) Vertical Unit * 447 * 258 * Unit * 550 * 302 * Fukushima Daiichi Unit * 507 * 231 * Unit * 319 * 200 * Unit * 548 * 256 * Unit * 444 * Unit * Fukushima Daini Unit * 232 * Unit * 216 * 208 * Unit * 205 * 288 * *: The records were stopped approximately seconds after recording started. Note) Standard ground motion Ss: Seismic motion that was newly established to evaluate seismic safety, taking into account the earthquakes, etc., that could occur around the power station, based on the revised seismic design review guidelines. All Rights Reserved 2012The Tokyo Electric Power Company, Inc

34 Tsunami and 2F The new design basis Tsunami height for 1F & 2F were evaluated based on the JSCE Tsunami assessment methodology. (1F: O.P.+5.7m, 2 F: O.P.+5.2m) The countermeasures were implemented at both NPSs, such as pump motor elevation and openings that were all equivalent from the viewpoint of resistance against Tsunami hazard. The 15m class Tsunami caused by M9.0 class earthquake that accidentally attacked 1F was far beyond design basis and whatever evaluation and whatever countermeasures did not matter at this time. 1F 4 月 9 日記者発表 Design basis tsunami Assumed height highest tsunami O.P.+5.7m water level O.P. +5.7m - Base level O.P. 0m - 2F Design basis tsunami height O.P.+5.2m Ocean-side area Inundation height apx. O.P m Safety measures has taken against 5.2m Tsunami height Site level O.P. +4m Hx building Main building area Turbine building Reactor building Base level O.P.0m breakwater Water intake Site level O.P. +12m O.P.:Onahama Point All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 33

35 Permitted Design Basis Tsunami assessment Historical tsunamis of Iwate and Miyagi coast were larger than that of Fukushima Approved design basis at Fukushima NPS was m Historical tsunami heights (m) tsunami heights (m) Inundation Run-up Fukushima NPSs Fukushima NPSs Preliminary results by The 2011 Tohoku Earthquake Tsunami Joint Survey Group( 07 May 2011 Tsunami assessment in construction permit Unit Ground Level Tsunami Height m R/B,Tb/B m Pumps m Design Basis Modified in 2002 (2009) 11 march F (6.1) F F All Rights Reserved 2012The Tokyo Electric Power Company, Inc. 34

Report regarding Collection of Reports pursuant to the Provisions of Article 106, Paragraph 3 of the Electricity Business Act

Report regarding Collection of Reports pursuant to the Provisions of Article 106, Paragraph 3 of the Electricity Business Act Report regarding Collection of Reports pursuant to the Provisions of Article 106, Paragraph 3 of the Electricity Business Act May 16 th, 2011 Tokyo Electric Power Company Contents 1. Record of damages

More information

Current Status of Fukushima Daiichi Nuclear Power Station & Lessons Learned from Experiences of the Great East Japan

Current Status of Fukushima Daiichi Nuclear Power Station & Lessons Learned from Experiences of the Great East Japan These materials may contain sensitive information from TEPCO or other companies. Therefore, the usage of these materials outside of their intended goal is prohibited, alongside the showing or publication

More information

Fukushima Daiichi Accident Technical Causal Factor Analysis

Fukushima Daiichi Accident Technical Causal Factor Analysis Fukushima Daiichi Accident Technical Causal Factor Analysis 2012 TECHNICAL REPORT Fukushima Daiichi Accident Technical Causal Factor Analysis 1024946 Final Report, March 2012 EPRI Project Manager K. Huffman

More information

Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011)

Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011) Extract May 20, 2011 Nuclear and Industrial Safety Agency Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011) Nuclear and Industrial Safety Agency (NISA) confirmed the current situation

More information

Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011)

Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011) Extract April 29, 2011 Nuclear and Industrial Safety Agency Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011) Nuclear and Industrial Safety Agency (NISA) confirmed the current

More information

Updated information of Fukushima Daiichi NPP. October Ki Sig Kang 1

Updated information of Fukushima Daiichi NPP. October Ki Sig Kang 1 Updated information of Fukushima Daiichi NPP October 18 2011 Ki Sig Kang 1 Tsunami Phenomenon 2 3 TEPCO ; Kashiwazaki Kariwa Nuclear Power Plants in Japan Tohoku EPC ; Higashidori J-Power EPDC ; Ohma Hokkaido

More information

East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant

East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant March, 2014 Naohiro Masuda Former Site Superintendent at Fukushima Daini NPP Overview of Fukushima

More information

Progression of the Fukushima Accident

Progression of the Fukushima Accident Workshop on Advances in Understanding the Progression of Severe Accidents in Boiling Water Reactors Progression of the Fukushima Accident ~ Accident Progression at Unit 2 ~ July 17-21, 2017 Shinichi KAWAMURA,

More information

Additional examination of station black-out due to tsunami

Additional examination of station black-out due to tsunami Attachment Earthquake-tsunami-2 Additional examination of station black-out due to tsunami 1. Introduction Relationships between the tsunami arrival time and loss of power sources have been examined and

More information

TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY

TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY Introduction TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY TEPCO established its Nuclear Safety Reform Plan (full text of the plan may be viewed at http://www.tepco.co.jp/en/press/corp

More information

Masaru Takei - The Tokyo Electric Power Company, Inc. Executive Vice President

Masaru Takei - The Tokyo Electric Power Company, Inc. Executive Vice President Meeting Transcript (Presentation) Event Date/Time: August 9, 2011 / 06:00PM JST Event Name: TEPCO Investor Meeting for FY2011 1 st Quarter Earnings Results Corporate Participants: Masaru Takei The Tokyo

More information

LESSONS LEARNED FORSMARK EVENT Presented To IEEEE

LESSONS LEARNED FORSMARK EVENT Presented To IEEEE LESSONS LEARNED FORSMARK EVENT Presented To IEEEE Thomas Koshy Member of the Task Group on Forsmark Chief of Mechanical & Electrical Engineering Office of Research, USNRC Thomas.Koshy@nrc.gov 1 Agenda

More information

Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures

Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures September 2007 The Tokyo Electric Power Company, Inc.

More information

Fukushima Daiichi NPP. May , Ki Sig Kang

Fukushima Daiichi NPP. May , Ki Sig Kang Fukushima Daiichi NPP May 26 2011, Ki Sig Kang Tsunami Phenomenon 2 3 Nuclear Power Plants in Japan TEPCO ; Kashiwazaki Kariwa Tohoku EPC ; Higashidori Hokkaido EPC ; Tomari J-Power EPDC ; Ohma Hokuriku

More information

Fukushima Nuclear Accident Analysis Report <Summary Attachment> June 20, 2012 Tokyo Electric Power Company, Inc.

Fukushima Nuclear Accident Analysis Report <Summary Attachment> June 20, 2012 Tokyo Electric Power Company, Inc. Fukushima Nuclear Accident Analysis Report June 20, 2012 Tokyo Electric Power Company, Inc. This material reorganizes the contents of the Summary of the Fukushima Nuclear Accident

More information

JAMES F. GLEASON, P.E. CHAIRMAN QUALIFICATION COMMITTEE

JAMES F. GLEASON, P.E. CHAIRMAN QUALIFICATION COMMITTEE JAMES F. GLEASON, P.E. CHAIRMAN QUALIFICATION COMMITTEE Presented ese ted at NPEC C Ju July y 27, 7, 2011 0 NPEC Most Nuclear Power Countries Use IEEE NPEC Standards Administrative Qualification Operations,

More information

Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~

Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~ Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~ National Radiological Emergency Preparedness Conference Austin, Texas April 8 th, 2013 Kenji Tateiwa Manager, Nuclear Power Programs

More information

Event sequences Fukushima

Event sequences Fukushima Event sequences Fukushima 11032011 Event sequences in Fukushima Dai-ichi and Dai-ni following the Tohoku-Chihou-Taiheiyou-Oki earthquake on 11.03.2011 Fukushima 37 25 26.57 N, 141 1 56.87 E 11.03.2011

More information

Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3

Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3 Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3 July 26, 2018 Tokyo Electric Power Company Holdings, Inc. Fukushima Daiichi D&D Engineering Company 1. Outline of

More information

Next Phase of Fukushima Daiichi D&D (Enhanced institutional and technical efforts by Team Japan )

Next Phase of Fukushima Daiichi D&D (Enhanced institutional and technical efforts by Team Japan ) Nuclear Damage Compensation and Decommissioning Facilitation Corporation Next Phase of Fukushima Daiichi D&D (Enhanced institutional and technical efforts by Team Japan ) IAEA General Conference Side Event

More information

APR1400 Electric System Design. KHNP KEPCO E&C November 29, 2017

APR1400 Electric System Design. KHNP KEPCO E&C November 29, 2017 APR1400 Electric System Design KHNP KEPCO E&C November 29, 2017 Contents 1. Introduction 2. Offsite Power System Design 3. Onsite Power System Design Auxiliary Power System DC & IP System Onsite Power

More information

S. Y. Park (*), K. I. Ahn

S. Y. Park (*), K. I. Ahn IEM on Strengthening R&D Effectiveness in the Light of the Accident at the Fukushima Daiichi NPP, Vienna, 16-0 Feb. 015 Assessment of the Mitigative Strategy using External Coolant Injection for OPR-1000

More information

AP1000 Plant Overview

AP1000 Plant Overview AP1000 Plant Overview Westinghouse IEEE Subcommittee on Qualification Tom Hayes Passive Plant Projects hayestp@westinghouse.com 1-412-374-4420 Slide 1 Westinghouse Passive Plants Meet Power Company Needs

More information

US Japan Energy Opportunities. May 15, 2013 NEDO Silicon Valley Office Osamu Onodera

US Japan Energy Opportunities. May 15, 2013 NEDO Silicon Valley Office Osamu Onodera US Japan Energy Opportunities May 15, 2013 NEDO Silicon Valley Office Osamu Onodera Strategic Energy Plan of Japan (before Tohoku) Renewable and Nuclear were to be increased to reduce Co2 emissions but

More information

Japan s Decontamination Efforts and its Effects

Japan s Decontamination Efforts and its Effects Japan s Decontamination Efforts and its Effects Jan. 8, 2015 Ministry of the Environment Outline 1. Policy Framework 2. Progress in Special Decontamination Area 3. Progress in Intensive Contamination Survey

More information

Thursday 1 November. Friday 2 November

Thursday 1 November. Friday 2 November Thursday 1 Report on the impact of the Niigata-Chuetsu Oki Earthquake on the Kashiwazaki-Kariwa Nuclear Plant and response by Tokyo Electric Power Company (TEPCO), national and local governments and other

More information

Information (15:00), December 1, 2017

Information (15:00), December 1, 2017 Information (15:00), December 1, 2017 To All Missions (Embassies, Consular posts and International Organizations in Japan) Report on the discharge record and the seawater monitoring results at Fukushima

More information

Improvements in EPR arrangements in Slovenia

Improvements in EPR arrangements in Slovenia REPUBLIC OF SLOVENIA Improvements in EPR arrangements in Slovenia Marjan Tkavc Head, Emergency Preparedness Division Slovenia - The Smallest Nuclear Country TRIGA The Krško NPP 2 EPR is not proportional

More information

Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version)

Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version) Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version) Masayuki Nakao (1), Kohei Kusaka, Kensuke Tsuchiya and Kenji Iino Abstract:

More information

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved. Factbook Tokyo Electric Power Company Holdings, Inc. August 2018 (Note) Please note that the following to be an accurate and complete translation of the original Japanese version prepared for the convenience

More information

The IAEA does not normally maintain stocks of reports in this series.

The IAEA does not normally maintain stocks of reports in this series. IAEA-TECDOC- The IAEA does not normally maintain stocks of reports in this series. However, microfiche copies SAFETY ASPECTS OF STATION BLACKOUT AT NUCLEAR POWER PLANTS IAEA, VIENNA, 1985 IAEA-TECDOC-332

More information

GE ABWR & ESBWR. Jeff Suggs ESBWR I&C April 17, Copyright 2006 by GE Energy / Nuclear

GE ABWR & ESBWR. Jeff Suggs ESBWR I&C April 17, Copyright 2006 by GE Energy / Nuclear GE ABWR & ESBWR Jeff Suggs ESBWR I&C April 17, 2007 Copyright 2006 by GE Energy / Nuclear GE Energy Gas Cleaner Coal Hydro Nuclear Wind Solar Biomass Fuel Cells Copyright 2006 by GE Energy / Nuclear 2

More information

AP1000 European 7. Instrumentation and Controls Design Control Document

AP1000 European 7. Instrumentation and Controls Design Control Document 7.3 Engineered Safety Features AP1000 provides instrumentation and controls to sense accident situations and initiate engineered safety features (ESF). The occurrence of a limiting fault, such as a loss

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

WELCOME AND INTRODUCTORY REMARKS

WELCOME AND INTRODUCTORY REMARKS WELCOME AND INTRODUCTORY REMARKS Robust Power Workshop 2017-05-03, Per Lamell, F-0051167 1 SAFETY FIRST Please note where the nearest emergency exits, fire extinguishers, gathering place and defibrillators

More information

TEPCO's operational technologies to prevent cascading outage

TEPCO's operational technologies to prevent cascading outage 1 CIGRE TNC Technical Seminar Future Renewable Energy and Smart Grid Technologies TEPCO's operational technologies to prevent cascading outage Shinichi Imai, P.E. THE Power Grid Solution, Inc. June 20,

More information

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 1 of 5. Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 2 Definitions 2 Not seen the definition for Inspector. But with, - Qualifications,

More information

Measures for improving the work environment in the Fukushima Daiichi nuclear power station

Measures for improving the work environment in the Fukushima Daiichi nuclear power station Measures for improving the work environment in the Fukushima Daiichi nuclear power station November 10, 2015 Tokyo Electric Power Company, Incorporated. All rights reserved TEPCO 1 1-1 Implementing measures

More information

Presented at SC-2, Meeting October 5-6, 2010,, Seattle, WA

Presented at SC-2, Meeting October 5-6, 2010,, Seattle, WA U.S. EPR EQ Program Update Nissen M. Burstein Technical Consultant Presented at SC-2, Meeting 10-02 October 5-6, 2010,, Seattle, WA EPR is a trademark of the AREVA Group. Overview of U.S. EPR Reactor Redundant

More information

Appendix G Examples and Recommended Methods

Appendix G Examples and Recommended Methods Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600

More information

ELECTRICAL PART OF EPR DESIGN, APPLIED STANDARDS AND POSSIBILITY OF COOPERATION WITH POLISH INDUSTRY SUPPLIERS

ELECTRICAL PART OF EPR DESIGN, APPLIED STANDARDS AND POSSIBILITY OF COOPERATION WITH POLISH INDUSTRY SUPPLIERS ELECTRICAL PART OF EPR DESIGN, APPLIED STANDARDS AND POSSIBILITY OF COOPERATION WITH POLISH INDUSTRY SUPPLIERS BRUNO BLOTAS, VP BUSINESS DEVELOPMENT FOR POLAND ANDREA ACEVEDO, SUPPLY CHAIN DEVELOPMENT

More information

132/11 kv, 25 MVA MOBILE SUBSTATION

132/11 kv, 25 MVA MOBILE SUBSTATION File name: Mob EN katalog1 Zagreb, 11.11.2014. Page: 1 od 9 Summary Mobile substation consists of two semitrailers. One trailer is for 132 kv equipment (HV equipment) and another trailer is for medium

More information

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd)

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd) Appendix 11 RETURN TO APPENDICES LIST High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd) GLADSTONE AREA WATERBOARD AWOONGA DAM HIGH VOLTAGE POWER SUPPLY UPGRADE Document: GJ543-RP-02B Submission

More information

Modular integrated transportable substation (MITS)

Modular integrated transportable substation (MITS) Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................

More information

Mid-to-long Term Policy for on site Decontamination and the Performance

Mid-to-long Term Policy for on site Decontamination and the Performance Mid-to-long Term Policy for on site Decontamination and the Performance August 27, 2013 TOKYO ELECTRIC POWER COMPANY RADIATION PROTECTION & MANAGEMENT GROUP TORU FURUKAWA 1 1 Contents Current picture at

More information

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015 ADB Knowledge Partnership Week Hirokazu Yamaguchi May, 2015 TEPCO AT A GLANCE 1 THE 10 ELECTRIC POWER COMPANIES BY SERVICE AREA In Japan, 10 regional privately owned and managed General Electricity Utilities

More information

Progress on Offsite Cleanup Efforts in Japan

Progress on Offsite Cleanup Efforts in Japan Progress on Offsite Cleanup Efforts in Japan Takeshi SEKIYA Ministry of the Environment, Japan UK-Japan Annual Nuclear Dialogue, Oct. 4, 2012 1 Radioactive Pollution caused by the accident at Fukushima

More information

Statistics on Radiation Exposure Doses of Decontamination Workers and Other Items

Statistics on Radiation Exposure Doses of Decontamination Workers and Other Items Statistics on Radiation Exposure Doses of Decontamination Workers and Other Items 15 April 215 System of registration and management of radiation exposure doses for decontamination and related works Objective

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Modular Standardized Electrical and Control Solutions for Fast Track Projects Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP

Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP by Zoltán Kovács, Robert Spenlinger and Helena Novakova RELKO Ltd, Engineering and Consulting Services Račianska

More information

UK ABWR Generic Design Assessment. Generic PCSR Chapter 15 : Electrical Power Supplies

UK ABWR Generic Design Assessment. Generic PCSR Chapter 15 : Electrical Power Supplies Form10/00 Document ID Document Number Revision Number : : : GA91-9101-0101-15000 XE-GD-0648 C Generic Design Assessment Generic PCSR Chapter 15 : Electrical Power Supplies Hitachi-GE Nuclear Energy, Ltd.

More information

SGT5-8000H / Irsching 4 Siemens H class gas turbine Pioneering efficiency with world class flexibility

SGT5-8000H / Irsching 4 Siemens H class gas turbine Pioneering efficiency with world class flexibility SGT5-8000H / Irsching 4 Siemens H class gas turbine Pioneering efficiency with world class flexibility W. Fischer Program Director 8000H Evolution of Siemens Combined Cycle Technology 1991 1996 2007 2011

More information

Japanese Energy Industry Transformation

Japanese Energy Industry Transformation i-pcgrid2017 Japanese Energy Industry Transformation - Challenges to use facilities radically for extra efficiency Yasutomo Johraku Power System Protection Engineering Group Power System Operation Department

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle.

Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle. SECURITY OF ELECTRICAL SUPPLY SYSTEMS INCLUDING STANDBY SUPPLIES Eur.Ing J.A. McLean B.Sc. C.Eng. MIEE. FIOSH Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle.

More information

Appendix L-1 Calculating Combined-Cycle and Cogeneration

Appendix L-1 Calculating Combined-Cycle and Cogeneration Appendix L-1 Calculating Combined-Cycle and Cogeneration Block Data Using the Synthesis Event and Performance Method When Reporting Each Gas Turbine/Steam Turbine Unit Overview This document will explain

More information

Experience on Deterioration Survey of Aged 550 kv GIS and Optimized Evaluation Model in Thailand

Experience on Deterioration Survey of Aged 550 kv GIS and Optimized Evaluation Model in Thailand PS1 Experience on Deterioration Survey of Aged 550 kv GIS and Optimized Evaluation Model in Thailand S. Singharerg T. Watanabe Electricity Generating Authority of Thailand Chubu Electric Power Co., Inc.

More information

78-EL-CS-E-1994 Senior Electrical Engineer. PERSONAL DATA Nationality : Egyptian

78-EL-CS-E-1994 Senior Electrical Engineer. PERSONAL DATA Nationality : Egyptian 78-EL-CS-E-1994 Senior Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and a Diploma of Electrical Switchgear and Protection. Has 16 years experience in construction, commissioning,

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Demonstration Project utilizing Hybrid Storage Battery System in the Oki-islands

Demonstration Project utilizing Hybrid Storage Battery System in the Oki-islands Demonstration Project utilizing Hybrid Storage Battery System in the Oki-islands Subsidized project of Ministry of the Environment June 16, 2016 Power System Division The Chugoku Electric Power Co., Inc.

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Nuclear L.L. C. 10 CFR 50.55a

Nuclear L.L. C. 10 CFR 50.55a 'I PSEG Nuclear LLC P.O. Box 236,, Hancocks Bridge, NJ 08038-0236 LR-N09-0046 March 05, 2009 0 PSEG Nuclear L.L. C. 10 CFR 50.55a U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington,

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Streamlined RI-ISI. Patrick O Regan EPRI

Streamlined RI-ISI. Patrick O Regan EPRI Streamlined RI-ISI Patrick O Regan EPRI poregan@epri.com Introduction Background Streamlined RI-ISI Methodology Results Discussion, Lessons Learned, Improvements Summary Background GOAL: Based upon the

More information

Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23

Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23 Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23 We re requiring more inspections due to susceptibility of material to cracking Some utilities have implemented mitigative actions Stress improvement Weld

More information

CSR Report Highlight CSR

CSR Report Highlight CSR CSR CSR > Previous Reports > 2011Report > CSR Report Highlight CSR Report Highlight To assist in rebuilding, the supply of trucks such as dump trucks for rubble removal and construction, concrete pump

More information

Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc.

Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc. Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc. Unit 2 Primary Containment Vessel Investigation at Fukushima Daiichi Nuclear Power Station (Investigation results by the self-propelled

More information

(3) 2-Loop B&W PWR s Unit 1- Commissioned 7/5/1973 Unit 2- Commissioned 9/9/1974 Unit 3- Commissioned 12/16/ MW per unit for a total of 2880 MW

(3) 2-Loop B&W PWR s Unit 1- Commissioned 7/5/1973 Unit 2- Commissioned 9/9/1974 Unit 3- Commissioned 12/16/ MW per unit for a total of 2880 MW C. Edmond Allen - Steam Generator Project Mgr June 2017 (3) 2-Loop B&W PWR s Unit 1- Commissioned 7/5/1973 Unit 2- Commissioned 9/9/1974 Unit 3- Commissioned 12/16/74 960 MW per unit for a total of 2880

More information

Earthquake & Smart Society

Earthquake & Smart Society 1 ICT as a Tool for Smart Society and Better Life Earthquake & Smart Society Toyota Info Technology Center, Co., Ltd. and The Telecommunication Technology Committee yuji@ttc.or.jp yuji@jp.toyota-itc.com

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

Advanced Digital Valve Controller

Advanced Digital Valve Controller Advanced Digital Valve Controller................................................... By Stan Miller, CCI; Presented at AUG January 8-12, 2007 22591 Avenida Empresa Rancho Santa Margarita, CA 92688 949.858.1877

More information

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD June 1, 2018 Table of Contents 1.0 Introduction...3 2.0 Summary...3 3.0 Purpose...3 4.0 Definitions...4 5.0 Analysis...5

More information

IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA

IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA Nathan Larson Principal Engineer Daniel Tirsun Fellow Engineer Aaron Moreno Senior Engineer Glen Rose, TX SHIELD is a trademark

More information

Power Transmission Solutions Grid Access

Power Transmission Solutions Grid Access Power Transmission Solutions Grid Access Connecting the 500 MW Greater Gabbard Offshore Wind Farm to the Grid Dietmar Retzmann Alberto Schultze Siemens AG 2009 Energy Sector 1 04-2009 E T PS SL/Re Global

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Engineers Ireland Site Visit 23 rd March 2010

Engineers Ireland Site Visit 23 rd March 2010 Whitegate Independent Power Plant CER Site Visit 24 th October 2008 CER Site Visit 24 th October 2008nt Engineers Ireland Site Visit 23 rd March 2010 Agenda Presentation of project and progress to date.

More information

The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~

The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~ The Great East Japan Earthquake and Lessons Learned ~Oil and Electricity~ 4 November, 2014 Kazushige Tanaka Energy Advisor/Counsellor Permanent Delegation of Japan to the OECD 1. Oil Supply in Emergency

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BALANCE OF PLANT GENERATOR DIESEL ENGINE

Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BALANCE OF PLANT GENERATOR DIESEL ENGINE Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES Electrical 3600-3690 Power Station Switchyard 3700-3730 Generator 4500-4580 Exciter 4600-4609 Cooling System 4610-4650 Controls 4700-4750 Miscellaneous

More information

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast.

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast. ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW High performance alternative to air

More information

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS Rachel Mueller, Mayo Clinic Timothy Coyle, PCT, Inc. Presented to: Minnesota Power

More information

An Application of the Fault Tree Analysis for the Power System Reliability Estimation

An Application of the Fault Tree Analysis for the Power System Reliability Estimation An Application of the Fault Tree Analysis for the Power System Reliability Estimation ABSTRACT Andrija Volkanovski, Marko Čepin, Borut Mavko Reactor Engineering Division Jožef Stefan Institute Jamova 39,

More information

2015 WDC Disturbance and Protection Standards Overview

2015 WDC Disturbance and Protection Standards Overview NERC Update 2015 WDC Disturbance and Protection Standards Overview Rich Bauer Senior Manager Reliability Risk Management / Event Analysis IEEE PSRC meeting Denver, Co May 12, 2016 2 System Protection and

More information

Appendix B6 Gas Turbine Unit Cause Codes

Appendix B6 Gas Turbine Unit Cause Codes Appendix B6 Gas Turbine Unit Cause Codes GAS TURBINE UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES (Unit Codes 300 399 and 700 799) Cause Code BALANCE OF PLANT Ranges Page No. GENERATOR GAS TURBINE Electrical

More information

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Schedules 1 to 4, Lot B: Extension of the Lessos Substation 1.0 LIGHTNING ARRESTORS 1.1 ZNO lightning arrester, 192 kv rated voltage, 10 ka nominal discharge current 2.0 CAPACITIVE VOLTAGE TRANSFORMER ea. 45 2.1 220 kv capacitive voltage transformer 220/ 3 / 0.11/

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

DECONTAMINATE BY PRIORITY Items such as wheeled vehicles, forklifts, and railcars, which are critical to the site s overall mission, will need to rece

DECONTAMINATE BY PRIORITY Items such as wheeled vehicles, forklifts, and railcars, which are critical to the site s overall mission, will need to rece CHAPTER 5 DECONTAMINATION The idea behind decontamination is relatively the same for a fixed site as for a tactical unit. Personnel need to decontaminate to reduce the hazard and spread of a contaminating

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Fukushima Daiichi Status Report 27 July 2012

Fukushima Daiichi Status Report 27 July 2012 Fukushima Daiichi Status Report 27 July 2012 The IAEA issues regular status reports to the public on the current status of the Fukushima Daiichi Nuclear Power Plant, including information on environmental

More information

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0 S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s Revision 3.0 July 21, 2016 Revision History Version Number Author Change Description Comments 1.0

More information

Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting from Natural Disasters

Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting from Natural Disasters Volume 3 Number 1 International Journal for Nuclear Security International Journal of Nuclear Security 11-20-2017 Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Progress on Off-site Cleanup Efforts in Japan. July 17th, 2013 Ministry of the Environment, Japan

Progress on Off-site Cleanup Efforts in Japan. July 17th, 2013 Ministry of the Environment, Japan Progress on Off-site Cleanup Efforts in Japan July 17th, 2013 Ministry of the Environment, Japan 1 Outline Framework of Decontamination Progress in Special Decontamination Area Progress in Intensive Contamination

More information

Life Extension Testing of Electrical Penetration Assemblies

Life Extension Testing of Electrical Penetration Assemblies Nuclear Division Life Extension Testing of Electrical Penetration Assemblies EQ Conference Oct 31 Nov 2, 2018 Steve Benesh, Curtiss-Wright Nuclear 1 October 22, 2018 Curtiss-Wright Summary Life Extension

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Diversifying into Marine Energy. ABB March 2015

Diversifying into Marine Energy. ABB March 2015 Diversifying into Marine Energy ABB March 2015 Structure Integrity, Construction and Manufacturing Solutions for the Process & Marine markets Process & Equipment Marine & Logistics Equipment Manufacturing

More information

UK Nuclear Renaissance. Myth or Reality?

UK Nuclear Renaissance. Myth or Reality? UK Nuclear Renaissance Myth or Reality? Simon Marshall Westinghouse Electric Company May 2013 AP1000 is a trademark or registered trademark of Westinghouse Electric Company LLC, its affiliates and/or its

More information