Progression of the Fukushima Accident

Size: px
Start display at page:

Download "Progression of the Fukushima Accident"

Transcription

1 Workshop on Advances in Understanding the Progression of Severe Accidents in Boiling Water Reactors Progression of the Fukushima Accident ~ Accident Progression at Unit 2 ~ July 17-21, 2017 Shinichi KAWAMURA, Ph.D. Shinya Mizokami, Ph.D. Takeshi HONDA Tokyo Electric Power Company

2 Overview of the 10-Unit Simultaneous Accidents Date (2011) 3/11 3/12 3/13 Fukushima Dai-ichi (1F) Fukushima Daini (2F) OPERATING OUTAGE OPERATING 15:27 1 st Tsunami, 15:35 2 nd Tsunami 15:22~ Tsunamis Station Blackout Water Injection: NO Heat Removal: NO 15:36 Unit 1 Explosion 11:01 Unit 3 Explosion 6:00-6:10 Unit 4 Explosion 3/12 8:13 D/G-6B Water Injection: YES Heat Removal: NO 1:24 RHR 17:00 7:13 RHR 3/12 12:15 Loss of Ultimate Heat Sink 1 15:42 RHR 7:15 3/ /19 5:00 RHR 3/19 22:14 RHR 3/20 3/20 15:46 P/C-2C 3/20 15:46 P/C-2C 3/22 10:36 P/C-4D 3/22 10:35 P/C-4D 3/20 14:30 3/20 19:27 Water Injection: YES Heat Removal: YES Cold Shutdown

3 Plant Status after Tsunami (1F2 : BWR-4/Mk-I) 2 Stack SRV Generator Off-site power D/W vent valve S/C vent valve SLC Reactor pressure vessel Primary containment vessel MSIV FDW Feedwater pump LPCP Turbine Condenser Sea Operational Circulating Water pump Main equipment inundated Seawater cooling lost Emergency AC power lost DC power lost HPCP Normal AC power lost Temporarily operational Batteries Core spray Heat exchanger RHR CRD RCIC HPCI MUWC CST Sea Power panels DDFP Filtered water RHRS Diesel generators Turbine-driven RCIC cooled the core for about 3 days Sea

4 RPV 原子炉水位 water level (m) (m) 1F2 RPV Water Level (March ) 8 6 RPV water level decreased after RCIC function failure RCIC was manually started 2 minutes before AC and DC power failures. RPV water level was maintained by RCIC for more than 2 days. Around 2 Mar 14 th Injection Started using Fire Trucks. TAF -2 燃料域水位計 Fuel range water (A) level (A) (measured) -4 燃料域水位計 Fuel range water (A)( level 補正 (A) ) (Corrected) 燃料域水位計 Fuel range water (B) level (B) (measured) -6 3/11 3/12 3/12 3/13 3/13

5 RPV 原子炉圧力 Pressure (MPa[abs]) 1F2 RPV Pressure Trend (March ) Rapid Depressurization by SRVs operation 原子炉圧力 RPV Pressure (A) (A) SRVs were operated in order to switch to injection by fire trucks after RCIC function failure 0 3/11 3/12 3/12 3/13 3/13

6 PCV 格納容器圧力 Pressure (MPa[abs]) 1F2 PCV Pressure Trend (March ) D/W Dry Well 圧力 Suppression S/C Chamber 圧力 PCV pressure increased by H 2 gas production with Zr-water reaction /11 3/12 3/12 3/13 3/13

7 1F2 Steam Discharging through the Blowout Panel 6 (Shot at 8:58 AM on March 15 th )

8 7 Analysis of Intermittent Reactor Pressure Spikes

9 Water level in RPV (m) RPV, D/W(x10) pressure (MPaa) Background 8 Observed 3-time intermittent re-pressurization can be related to (a) Water injection by fire trucks and induced Zr-water reaction (b) Core relocation followed by steam generation (c) SRV behavior (It is not clear whether SRV actually opened or closed) The amounts of steam and hydrogen generation were analyzed (Condensable or Non-condensable) to reproduce RPV and Dry Well pressure increases by GOTHIC Core melt progression scenario was studied RCIC stopped 6:00 TAF BAF SRV opened Water injection started by fire trucks? 6:

10 Postulated Process leading to RPV Pressurization On RPV depressurization, flashing caused the water level to drop steeply, completely exposing the core. Water level was restored by water injections from fire trucks. Steam generation caused Zr-water reaction, generating hydrogen and large amounts of heat, and causing RPV pressure to rise. Water injections from fire trucks were suspended due to the rise in RPV pressure. Steam generation decreased and let RPV pressure drop. Generated steam and H 2 could cause RPV pressure increase even if SRV was kept open

11 Injection 注水量 Rate (m 3 /h) (m 3 /h) Causes of Insufficient Core Cooling by Fire Trucks 10 The amount of water pumped by fire trucks was adequate to cool the cores of units 1 to Water injection using RCIC The injection rate needed to remove the decay heat DHRIR Estimated using the fire truck pump discharge pressure gauge and flow meter Pumping by fire trucks 海水 ( 減圧前 ) 海水 ( 減圧後 ) 必要注水量 Seawater (before pressure loss) Seawater (after pressure loss) Injected amount necessary 0 3/11 3/12 3/12 3/13 3/13 3/16 3/16 The amount of water from fire trucks and MDRIR (1F2 example) Assessed how much amount of water injected into the reactors and how those effects influenced accident progressions

12 Causes of Insufficient Core Cooling by Fire Trucks 11 Confirmed that there were paths that generated bypass flows to the main condenser and condensate storage tank -- Background to the identification of possible bypass flows -- At 1F2, core damaged after the start of water injection by fire trucks Late March 2011 Found out water accumulated in main condenser Suggested possible bypass flows existed Main paths generating bypass flows (example of Unit 1) Reactor building Valve seal Reactor Pressure vessel Condensate transfer pump Flow of water into the reactor Evaporator Condensate storage tank Condensate pump Bypass flow path Turbine building Main condenser Confirmed from piping drawings that there were paths that could generate bypass flows to the main condenser and the condensate storage tank during the accident Fire-extinguishing pump Fire truck pump discharge pressure gauge and flow meter Filtrate tank

13 RPV pressure (MPaa) D/W pressure (MPaa) Correlation between RPV and Dry Well Pressure Depressurization by manual SRV opening. RPV PCV RPV PCV RPV PCV :00 3:00 The 1st re-pressurization could be caused by SRV closure and re-open The 2nd re-pressurization could occur while SRV was kept open

14 Pressure (MPa[abs]) Simulation results Pressure Behavior RPV Press. (Measured) D/W Press. (Measured) RPV Press. (GOTHIC) D/W Press. (GOTHIC) S/C Press. (GOTHIC) :00 3:00 By tuning the steam and hydrogen generation rates, RPV and PCV pressure behaviors were reproduced by GOTHIC code.

15 Steam generation (kg/s) H2 generation (kg/s) Evaluation of H 2 and Steam Generation Steam Hydrogen 2nd 3rd st re-press :00 From the relationship between H 2 generation and energy release by Zrwater reaction, it is estimated that majority of the fuel melted during the second spike. Calculation result shows that Zr in the core was almost consumed by the end of the second spike. 3:00 0.0

16 15 Analysis of SRV Behavior and Cause of Inoperability

17 1F2 Condition of SRVs after the Tsunami 16 格納容器内 格納容器外 Operations to open SRVs were tried consecutively to depressurize the RPV. ADS accumulators RV accumulators N2 Bottles DC power for excitation of solenoid valves failed due to the Tsunami, so used car batteries. HPIN system to supply N 2 gas from outside the PCV also failed due to the Tsunami, so N 2 accumulators were used. There were two kind of tanks; RV accumulators and ADS accumulators. N2 gas SOLV Steam Flow Not Available Due to Tsunami DC Power Portable Batteries

18 1F2 SRV Basic Information 17 No. SV function (Set Point) SRV Set Points at 1F2 RV function (Set Point) ADS function A 7.81 MPa[abs] 7.61 MPa[abs] Yes B 7.88 MPa[abs] 7.68 MPa[abs] Yes C 7.88 MPa[abs] 7.68 MPa[abs] Yes D 7.81 MPa[abs] 7.61 MPa[abs] No E 7.74 MPa[abs] 7.61 MPa[abs] Yes F 7.74 MPa[abs] 7.54 MPa[abs] No G 7.81 MPa[abs] 7.68 MPa[abs] Yes H 7.88 MPa[abs] 7.68 MPa[abs] Yes Set Points of RV for F and SVs for E, F are relatively low. SRVs other than D, F have ADS function.

19 原子炉圧力 (MPa[abs]) RPV Pressure (MPa[abs]) 1F2 RPV Pressure Trend and SRV Operations (1) Around 16:34 A, B, C, G(RV, ADS) (2) Around 18:02 E, D, F(RV) 原子炉圧力 RPV Pressure ( 実測値 (Measured) ) :00 14:00 15:00 16:00 日時 17:00 19: :00

20 1F2 SRV Operations around 16:34 and 18:02 19 Switch Solenoid valve Portable Batteries 12V 10 Solenoid valve Portable Batteries 12V 10 SRV Panel Lamp Red/Green Lamp Red/Green (1)16:34 Mar 14 th Power supplied to the whole circuits (2)18:02 Mar 14 th Power supplied only to solenoid valves Failed Successful Failures of RPV depressurization at 16:34 was highly likely to be caused by the shortage of the power supply voltage to the solenoid valves.

21 原子炉圧力 (MPa[abs]) RPV Pressure (MPa[abs]) 1F2 RPV Pressure Trend and SRVs Operations 原子炉圧力 RPV Pressure ( 実測値 (Measured) ) (3)Around 21:00 and 21:20 A, B (RV) (5) After A, B, E, G, H(ADS) (6) Around 1:00 C(ADS) : :00 22:00 日時 23:00 (4) After C, E, G (RV) 1:00 2:00 3:00

22 原子炉圧力 RPV Pressure (MPa[abs]) D/W D/W Pressure 圧力 (MPa[abs]) 1F2 SRV A, B Operations around 21:20 March Around 2 Start Injection (3) RPV D/W Discharge Pressure of Fire Trucks: 1MPa : :00 22:00 23:00 原子炉圧力 RPV Pressure 1:00 D/W 圧力 Pressure :00 3:00 Close Open Dry Well pressure rose with RPV pressure decrease around 21:20. It is likely to be caused by SRV opening and by hydrogen gas transfer from the RPV to the PCV, which was generated during core damage.

23 原子炉圧力 RPV Pressure (MPa[abs]) D/W D/W Pressure 圧力 (MPa[abs]) 1F2 RPV Pressure 2 nd Spike after Depressurization RPV D/W Around 2 Start Injection Discharge Pressure of Fire Trucks: 1MPa : :00 22:00 23:00 原子炉圧力 RPV Pressure 1:00 D/W 圧力 Pressure :00 3:00 Open Open When Pressure When Pressure Increase Decrease Both RPV pressure and Dry Well pressure increased. It is possible that SRVs were being kept open during the 2 nd spike since 21:20. Pressure increase was likely caused by vast amount of H 2 gas generation in the RPV. (Intense Zr-water reaction could have happened during the 2 nd spike.)

24 原子炉圧力 (MPa[abs]) RPV Pressure (MPa[abs]) 1F2 SRV Operations after March 15 (Point 4) 原子炉圧力 RPV Pressure ( 実測値 (Measured) ) (5) After A, B, E, G, H(ADS) (6) Around 1:00 C(ADS) (3)Around 21:00 and 21:20 A, B (RV) : :00 22:00 日時 23:00 (4) After C, E, G (RV) 1:00 2:00 SRV (C), (G) operations were halted because sparks were ignited when batteries were connected to the solenoid valves. 3:00

25 PN+PR, PP+PA 原子炉圧力 RPV Pressure (MPa[abs]) D/W D/W Pressure 圧力 (MPa[abs]) 1F2 SRV Operations after March 15 (Point 4) Around 2 Start Injection (4) Discharge Pressure of Fire Trucks: 1MPa : :00 22:00 23:00 原子炉圧力 RPV Pressure 1:00 D/W 圧力 Pressure :00 3:00 Close SRV (E) (RV) could not be opened because of the increased PCV pressure :00 Orange:P N (ADS function) +P R Red :P N (RV function) +P R Blue :P P +P A Moment to close Moment to close was bigger 2 21:00 22:00 23:00 (4) 1:00 Moment to open 2:00 3:00

26 原子炉圧力 (MPa[abs]) RPV Pressure (MPa[abs]) 1F2 SRV Operations after March 15 (Points 5, 6) 原子炉圧力 RPV Pressure ( 実測値 (Measured) ) (5) After A, B, E, G, H(ADS) (6) Around 1:00 C(ADS) (3)Around 21:00 and 21:20 A, B (RV) : :00 22:00 日時 23:00 (4) After C, E, G (RV) 1:00 2:00 3:00 Point 5: SRVs were tried to open consecutively but RPV pressure decrease was not confirmed. Point 6: RPV pressure decrease was confirmed when SRV (C) was operated.

27 原子炉圧力 RPV Pressure (MPa[abs]) D/W D/W Pressure 圧力 (MPa[abs]) 1F2 SRV Operations after March 15 (Points 5, 6) :00? Close? Open? Around 2 Start Injection 2 21:00 22:00 23:00 (5) (6) 原子炉圧力 RPV Pressure 1:00 Discharge Pressure of Fire Trucks: 1MPa D/W 圧力 Pressure :00 3:00 SRV operations at (5),(6) using ADS accumulators Those operations should have been successful considering the pressure of ADS accumulators and Dry Well pressure. However, SRV open/close is still not clear because of complicated situations during core melt progression. Steam and H 2 generation could cause RPV pressurization. Possibility of leakage from the RPV to the Dry Well. Possibility of leakage from the Dry Well to the Reactor Bldg.

28 27 Interpretation of CAMS Data to understand Accident Progression

29 CAMS (Sv/h) Pressure (MPa[abs]) Background 28 Core melt progression scenario was studied using CAMS data trend, which could provide some insights to know the FP transport in the PCV 1E+3 A B C D 9 1E E+1 RPV Press. 1E E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C Press E-3 6:00 0 3/16

30 FP Gas Transport 3 1 RPV to S/C via SRV S/C to D/W via Vacuum Breaker 29 FDW MS 2 RPV leakage to D/W D/W to S/C via vent tube down comer 3 D/W leakage to Reactor Bldg. Vacuum Breaker

31 CAMS (Sv/h) Pressure (MPa[abs]) Accident Progression inferred from CAMS data 30 A: Core damage started, dose rates in D/W and S/C started to increase. FP flowed through the SRV from RPV into S/C, then into D/W through VB. 1E+3 1E+2 1E+1 1E+0 A E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C RPV Press E-3 6:00 0 3/16

32 CAMS (Sv/h) Pressure (MPa[abs]) Accident Progression inferred from CAMS data 31 A : Steep dose rate increase might be related to 2nd RPV re-pressurization. (i.e. large Zr-water reaction with SRV kept open) 1E+3 1E+2 1E+1 1E+0 A E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C RPV Press E-3 6:00 0 3/16

33 CAMS (Sv/h) Pressure (MPa[abs]) Accident Progression inferred from CAMS data 32 B: S/C dose rate decreased while D/W dose rate increased, which indicates the possibility that FP was leaking directly from the RPV to the D/W. 1E+3 1E+2 1E+1 1E+0 B E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C RPV Press E-3 6:00 0 3/16

34 CAMS (Sv/h) Pressure (MPa[abs]) Accident Progression inferred from CAMS data 33 D: No large dose rate change was observed in D/W and S/C, although measurement was interrupted in this period. 1E+3 1E+2 C E+1 6 1E E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C RPV Press E-3 6:00 0 3/16

35 CAMS (Sv/h) Pressure (MPa[abs]) Accident Progression inferred from CAMS data 34 E: D/W dose rates largely increased, which might be attributed to RPV rupture. 1E+3 1E+2 D Max 138 Sv/h E+1 6 1E E-1 1E-2 CAMS(D/W) D/W Press. CAMS(S/C) S/C RPV Press E-3 6:00 0 3/16

36 35 Thank you for your attention.

Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011)

Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011) Extract April 29, 2011 Nuclear and Industrial Safety Agency Seismic Damage Information (the 120th Release) (As of 15:00 April 29, 2011) Nuclear and Industrial Safety Agency (NISA) confirmed the current

More information

Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011)

Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011) Extract May 20, 2011 Nuclear and Industrial Safety Agency Seismic Damage Information (the 144th Release) (As of 15:00 May 20, 2011) Nuclear and Industrial Safety Agency (NISA) confirmed the current situation

More information

Fukushima Accident and Safety Assurance Measures for TEPCO NPP

Fukushima Accident and Safety Assurance Measures for TEPCO NPP Fukushima Accident and Safety Assurance Measures for TEPCO NPP IEEE NPEC N12-02 San Diego July 25, 2012 Yasushi Nakagawa Tokyo Electric Power Company All Rights Reserved 2012The Tokyo Electric Power Company,

More information

S. Y. Park (*), K. I. Ahn

S. Y. Park (*), K. I. Ahn IEM on Strengthening R&D Effectiveness in the Light of the Accident at the Fukushima Daiichi NPP, Vienna, 16-0 Feb. 015 Assessment of the Mitigative Strategy using External Coolant Injection for OPR-1000

More information

Event sequences Fukushima

Event sequences Fukushima Event sequences Fukushima 11032011 Event sequences in Fukushima Dai-ichi and Dai-ni following the Tohoku-Chihou-Taiheiyou-Oki earthquake on 11.03.2011 Fukushima 37 25 26.57 N, 141 1 56.87 E 11.03.2011

More information

Additional examination of station black-out due to tsunami

Additional examination of station black-out due to tsunami Attachment Earthquake-tsunami-2 Additional examination of station black-out due to tsunami 1. Introduction Relationships between the tsunami arrival time and loss of power sources have been examined and

More information

*TATSUYA KUNISHI, HITOSHI MUTA, KEN MURAMATSU AND YUKI KAMEKO TOKYO CITY UNIVERSITY GRADUATE SCHOOL

*TATSUYA KUNISHI, HITOSHI MUTA, KEN MURAMATSU AND YUKI KAMEKO TOKYO CITY UNIVERSITY GRADUATE SCHOOL Methodology of Treatment of Multiple Failure Initiating Events for Seismic PRA (2)Success Criteria Analysis for Multiple Pipe Break Accidents of a PWR *TATSUYA KUNISHI, HITOSHI MUTA, KEN MURAMATSU AND

More information

ANALYSIS OF BREST-OD-300 SAFETY DURING ANTICIPATED OPERATIONAL OCCURRENCES

ANALYSIS OF BREST-OD-300 SAFETY DURING ANTICIPATED OPERATIONAL OCCURRENCES ANALYSIS OF BREST-OD-300 SAFETY DURING ANTICIPATED OPERATIONAL OCCURRENCES D.V. Didorin, V.A. Kogut, A.G. Muratov, V.V. Tyukov, A.V. Moiseev (NIKIET, Moscow, Russia) 1. Brief description of the aim and

More information

Startup and Operation of SEE-THRU Nuclear Power Plant for Student Performance MP-SEE-THRU-01 Rev. 018

Startup and Operation of SEE-THRU Nuclear Power Plant for Student Performance MP-SEE-THRU-01 Rev. 018 Student Operating Procedure Millstone Station Startup and Operation of SEE-THRU Nuclear Power Plant for Student Performance Approval Date: 01/12/2011 Effective Date: 01/12/2011 TABLE OF CONTENTS 1. PURPOSE...3

More information

Current Status of the Melcor Nodalization for Atucha I Nuclear Power Plant. Zárate. S.M. and Valle Cepero, R.

Current Status of the Melcor Nodalization for Atucha I Nuclear Power Plant. Zárate. S.M. and Valle Cepero, R. Current Status of the Melcor Nodalization for Atucha I Nuclear Power Plant Zárate. S.M. and Valle Cepero, R. presentado en USNRC Cooperative Severe Accident Research Program (CSARP), Maryland, EE. UU.,

More information

Updated information of Fukushima Daiichi NPP. October Ki Sig Kang 1

Updated information of Fukushima Daiichi NPP. October Ki Sig Kang 1 Updated information of Fukushima Daiichi NPP October 18 2011 Ki Sig Kang 1 Tsunami Phenomenon 2 3 TEPCO ; Kashiwazaki Kariwa Nuclear Power Plants in Japan Tohoku EPC ; Higashidori J-Power EPDC ; Ohma Hokkaido

More information

Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version)

Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version) Axiomatic Design Aspect of the Fukushima-1 Accident: Electrical Control Interferes with All Mechanical Functions (Draft version) Masayuki Nakao (1), Kohei Kusaka, Kensuke Tsuchiya and Kenji Iino Abstract:

More information

East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant

East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant East Japan Earthquake on March 11, 2011 and Emergency Response at Fukushima Daini Nuclear Power Plant March, 2014 Naohiro Masuda Former Site Superintendent at Fukushima Daini NPP Overview of Fukushima

More information

NSTD Introductory Course

NSTD Introductory Course NSTD Introductory Course New Gen III+ Reactor Power Plant Designs Economic Simplified Boiling Water Reactor (ESBWR) ESBWR Overview 1 Disclaimer Information contained herein is derived exclusively from

More information

Appendix G Examples and Recommended Methods

Appendix G Examples and Recommended Methods Reporting Outages to the Generating Availability Data System (GADS) Introduction The examples in this appendix illustrate the reporting of outages and deratings to GADS. They are based on a fictional 600

More information

Fukushima Daiichi Accident Technical Causal Factor Analysis

Fukushima Daiichi Accident Technical Causal Factor Analysis Fukushima Daiichi Accident Technical Causal Factor Analysis 2012 TECHNICAL REPORT Fukushima Daiichi Accident Technical Causal Factor Analysis 1024946 Final Report, March 2012 EPRI Project Manager K. Huffman

More information

AP1000 European 7. Instrumentation and Controls Design Control Document

AP1000 European 7. Instrumentation and Controls Design Control Document 7.3 Engineered Safety Features AP1000 provides instrumentation and controls to sense accident situations and initiate engineered safety features (ESF). The occurrence of a limiting fault, such as a loss

More information

Current Status of Fukushima Daiichi Nuclear Power Station & Lessons Learned from Experiences of the Great East Japan

Current Status of Fukushima Daiichi Nuclear Power Station & Lessons Learned from Experiences of the Great East Japan These materials may contain sensitive information from TEPCO or other companies. Therefore, the usage of these materials outside of their intended goal is prohibited, alongside the showing or publication

More information

Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3

Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3 Fuel removal from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit 3 July 26, 2018 Tokyo Electric Power Company Holdings, Inc. Fukushima Daiichi D&D Engineering Company 1. Outline of

More information

TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY

TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY Introduction TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY TEPCO established its Nuclear Safety Reform Plan (full text of the plan may be viewed at http://www.tepco.co.jp/en/press/corp

More information

The Establishment and Application of TRACE/FRAPTRAN Model for Kuosheng Nuclear Power Plant

The Establishment and Application of TRACE/FRAPTRAN Model for Kuosheng Nuclear Power Plant The Establishment and Application of /FRAPTRAN Model for Kuosheng Nuclear Power Plant S. W. Chen, W. K. Lin, J. R. Wang, C. Shih, H. T. Lin, H. C. Chang, W. Y. Li Abstract Kuosheng nuclear power plant

More information

Earthquake & Smart Society

Earthquake & Smart Society 1 ICT as a Tool for Smart Society and Better Life Earthquake & Smart Society Toyota Info Technology Center, Co., Ltd. and The Telecommunication Technology Committee yuji@ttc.or.jp yuji@jp.toyota-itc.com

More information

HRSG Operational Challenges and Siemens Solutions

HRSG Operational Challenges and Siemens Solutions Intelligent Energy Solutions HRSG Operational Challenges and Siemens Solutions Gary Gong Ph.D P.E. Siemens Energy Inc 4400 N Alafaya Trl Orlando, FL 32766 Siemens Energy, Inc. Siemens 2010. All Energy,

More information

USER MANUAL. Uninterruptible power supply MODEL: 53965,

USER MANUAL. Uninterruptible power supply MODEL: 53965, USER MANUAL Uninterruptible power supply MODEL: 53965, 53966 www.qoltec.com Please check if the package contains: - UPS unit - Power cable (1 x SCHUKO) 1.2 m - User manual This UPS provides comprehensive

More information

1 of 7 12/18/2016 9:15 PM

1 of 7 12/18/2016 9:15 PM 1 of 7 12/18/2016 9:15 PM P0456-EVAP SYSTEM SMALL LEAK Special Tools: For a complete wiring diagram, refer to the Wiring Information. 2 of 7 12/18/2016 9:15 PM Theory of Operation 3 of 7 12/18/2016 9:15

More information

GE ABWR & ESBWR. Jeff Suggs ESBWR I&C April 17, Copyright 2006 by GE Energy / Nuclear

GE ABWR & ESBWR. Jeff Suggs ESBWR I&C April 17, Copyright 2006 by GE Energy / Nuclear GE ABWR & ESBWR Jeff Suggs ESBWR I&C April 17, 2007 Copyright 2006 by GE Energy / Nuclear GE Energy Gas Cleaner Coal Hydro Nuclear Wind Solar Biomass Fuel Cells Copyright 2006 by GE Energy / Nuclear 2

More information

CHAPTER 7: OVERALL UNIT CONTROL MODULE 2: BOILER PRESSURE CONTROL

CHAPTER 7: OVERALL UNIT CONTROL MODULE 2: BOILER PRESSURE CONTROL Chulalongkorn University MODULE OBJECTIVES: At the end of this module, you will be able to: CHAPTER 7: OVERALL UNIT CONTROL MODULE 2: BOILER PRESSURE CONTROL 1. Briefly explain, in writing, the role of

More information

IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA

IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA IMPLEMENTATION OF THE RCP SHIELD MECHANICAL SEAL MODEL IN THE COMANCHE PEAK PRA Nathan Larson Principal Engineer Daniel Tirsun Fellow Engineer Aaron Moreno Senior Engineer Glen Rose, TX SHIELD is a trademark

More information

Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23

Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23 Oconee Nuclear Station ALLOY 600 REPAIRS 1EOC23 We re requiring more inspections due to susceptibility of material to cracking Some utilities have implemented mitigative actions Stress improvement Weld

More information

AP1000 European 5. Reactor Coolant System and Connected Systems Design Control Document

AP1000 European 5. Reactor Coolant System and Connected Systems Design Control Document CHAPTER 5 REACTOR COOLANT SYSTEM AND CONNECTED SYSTEMS 5.1 Summary Description This section describes the reactor coolant system (RCS) and includes a schematic flow diagram of the reactor coolant system

More information

Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc.

Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc. Reference February 16, 2017 Tokyo Electric Power Company Holdings, Inc. Unit 2 Primary Containment Vessel Investigation at Fukushima Daiichi Nuclear Power Station (Investigation results by the self-propelled

More information

Development and Validation of Analysis Method for Reactor Performance and Safety Characteristics of HTGR

Development and Validation of Analysis Method for Reactor Performance and Safety Characteristics of HTGR Development and Valdaton of Analyss Method for Reactor Performance and Safety Characterstcs of HTGR Kunyosh TAKAMATSU HTGR Performance & Safety Demonstraton Group Japan Atomc Energy Agency 16 19 Aprl 2007

More information

Japanese Energy Industry Transformation

Japanese Energy Industry Transformation i-pcgrid2017 Japanese Energy Industry Transformation - Challenges to use facilities radically for extra efficiency Yasutomo Johraku Power System Protection Engineering Group Power System Operation Department

More information

LESSONS LEARNED FORSMARK EVENT Presented To IEEEE

LESSONS LEARNED FORSMARK EVENT Presented To IEEEE LESSONS LEARNED FORSMARK EVENT Presented To IEEEE Thomas Koshy Member of the Task Group on Forsmark Chief of Mechanical & Electrical Engineering Office of Research, USNRC Thomas.Koshy@nrc.gov 1 Agenda

More information

By: Eugenijus Uspuras Algirdas Kaliatka Sigitas Rimkevicius ASME 2012 Verification & Validation Symposium May 2-4, 2012, Las Vegas, NV

By: Eugenijus Uspuras Algirdas Kaliatka Sigitas Rimkevicius ASME 2012 Verification & Validation Symposium May 2-4, 2012, Las Vegas, NV Computer codes validation for transient analysis at nuclear power plants with RBMK-1500 reactor By: Eugenijus Uspuras Algirdas Kaliatka Sigitas Rimkevicius ASME 2012 Verification & Validation Symposium

More information

The IAEA does not normally maintain stocks of reports in this series.

The IAEA does not normally maintain stocks of reports in this series. IAEA-TECDOC- The IAEA does not normally maintain stocks of reports in this series. However, microfiche copies SAFETY ASPECTS OF STATION BLACKOUT AT NUCLEAR POWER PLANTS IAEA, VIENNA, 1985 IAEA-TECDOC-332

More information

EMISSION CONTROL (AUX. EMISSION CONTROL DEVICES) H4DOTC

EMISSION CONTROL (AUX. EMISSION CONTROL DEVICES) H4DOTC EMISSION CONTROL (AUX. EMISSION CONTROL DEVICES) H4DOTC SYSTEM OVERVIEW 1. System Overview There are three emission control systems, which are as follows: Crankcase emission control system Exhaust emission

More information

CC System B B 3.7 PLANT SYSTEMS. B Component Cooling Water (CC) System BASES

CC System B B 3.7 PLANT SYSTEMS. B Component Cooling Water (CC) System BASES CC System B 3.7.7 B 3.7 PLANT SYSTEMS B 3.7.7 Component Cooling Water (CC) System BACKGROUND The CC System provides a heat sink for the removal of process and operating heat from safety related components

More information

Status of HPLWR Development

Status of HPLWR Development Status of HPLWR Development Thomas Schulenberg SCWR System Steering Committee Karlsruhe Institute of Technology Germany What is a Supercritical Water Cooled Reactor? PH HP IP LP PH Produces superheated

More information

Fukushima Daiichi NPP. May , Ki Sig Kang

Fukushima Daiichi NPP. May , Ki Sig Kang Fukushima Daiichi NPP May 26 2011, Ki Sig Kang Tsunami Phenomenon 2 3 Nuclear Power Plants in Japan TEPCO ; Kashiwazaki Kariwa Tohoku EPC ; Higashidori Hokkaido EPC ; Tomari J-Power EPDC ; Ohma Hokuriku

More information

MULTIPOINT FUEL INJECTION (MPI) <4G9>

MULTIPOINT FUEL INJECTION (MPI) <4G9> MULTIPOINT FUEL INJECTION (MPI) 13C-1 MULTIPOINT FUEL INJECTION (MPI) CONTENTS GENERAL................................. 2 Outline of Changes............................ 2 GENERAL INFORMATION...................

More information

Nuclear L.L. C. 10 CFR 50.55a

Nuclear L.L. C. 10 CFR 50.55a 'I PSEG Nuclear LLC P.O. Box 236,, Hancocks Bridge, NJ 08038-0236 LR-N09-0046 March 05, 2009 0 PSEG Nuclear L.L. C. 10 CFR 50.55a U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington,

More information

User Manual WT Combi-S Pure Sinus Wave Inverter

User Manual WT Combi-S Pure Sinus Wave Inverter User Manual WT Combi-S Pure Sinus Wave Inverter Contents 1. Important Safety information 1.1. Safety Information part 1 1.2. Safety information part 2 2. General Features 2.1. Product overview 3. Connection

More information

Energy Saving Campaign and Its Effect After Fukushima Disaster in Japan Aya Mikami Osaka Gas Co., Ltd.

Energy Saving Campaign and Its Effect After Fukushima Disaster in Japan Aya Mikami Osaka Gas Co., Ltd. Energy Saving Campaign and Its Effect After Fukushima Disaster in Japan Aya Mikami Osaka Gas Co., Ltd. BECC Conference 2012, Sacramento, CA 14 November 2012 1 Background Damage by Tsunami Fukushima nuclear

More information

Adaptation of Existing Fuze Technology to Increase the Capability of the Navy s 2.75-Inch Rocket System

Adaptation of Existing Fuze Technology to Increase the Capability of the Navy s 2.75-Inch Rocket System Adaptation of Existing Fuze Technology to Increase the Capability of the Navy s 2.75-Inch Rocket System Presented By: Brian J. Goedert 2.75 /5.0 Warheads Engineer NSWC Indian Head Phone: 301-744-6176 Email:

More information

The evaluation of endurance running tests of the fuel cells and battery hybrid test railway train

The evaluation of endurance running tests of the fuel cells and battery hybrid test railway train The evaluation of endurance running tests of the fuel cells and battery hybrid test railway train K.Ogawa, T.Yamamoto, T.Hasegawa, T.Furuya, S.Nagaishi Railway Technical Research Institute (RTRI), TOKYO,

More information

13A-1 FUEL CONTENTS MULTIPOINT FUEL INJECTION (MPI) FUEL SUPPLY... 13B

13A-1 FUEL CONTENTS MULTIPOINT FUEL INJECTION (MPI) FUEL SUPPLY... 13B 13A-1 FUEL CONTENTS MULTIPOINT FUEL INJECTION (MPI)... 13A FUEL SUPPLY... 13B 13A-2 MULTIPOINT FUEL INJECTION (MPI) CONTENTS GENERAL INFORMATION... 3 SERVICE SPECIFICATIONS... 6 SEALANT... 6 SPECIAL TOOLS...

More information

Forsmark 12. S3K Applications. Thomas Smed US User Group Meeting Arizona, October 2008

Forsmark 12. S3K Applications. Thomas Smed US User Group Meeting Arizona, October 2008 Forsmark 12 S3K Applications Thomas Smed US User Group Meeting Arizona, October 2008 Introduction It is well-known that we have vast experience in providing S3R (and RAMONA) to training simulators It may

More information

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit Exercise 3-1 Basic Hydraulic Circuit EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with the hydraulic schematic and components of the nacelle trainer. You will identify

More information

Development of Large Scale Recuperator for Gas Turbine

Development of Large Scale Recuperator for Gas Turbine Proceedings of the International Gas Turbine Congress 23 Tokyo November 2-7, 23 IGTC23Tokyo TS-112 Development of Large Scale Recuperator for Gas Turbine Ryo AKIYOSHI 1, Kiwamu IMAI 2, Tatsuya SIODA 3,

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER E: THE REACTOR COOLANT SYSTEM AND RELATED SYSTEMS

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER E: THE REACTOR COOLANT SYSTEM AND RELATED SYSTEMS PAGE : 1 / 13 4. PRESSURISER 4.1. DESCRIPTION The pressuriser (PZR) is a pressurised vessel forming part of the reactor coolant pressure boundary (CPP) [RCPB]. It comprises a vertical cylindrical shell,

More information

Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~

Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~ Fukushima Nuclear Accident ~Personal Perspective on The Human Impact~ National Radiological Emergency Preparedness Conference Austin, Texas April 8 th, 2013 Kenji Tateiwa Manager, Nuclear Power Programs

More information

Severe Service Hydraulic Actuators for the Nuclear Power Industry. Enertech Nuclear Qualified Electro-Hydraulic Actuators

Severe Service Hydraulic Actuators for the Nuclear Power Industry. Enertech Nuclear Qualified Electro-Hydraulic Actuators Severe Service Hydraulic Actuators for the Nuclear Power Industry Enertech Nuclear Qualified Electro-Hydraulic Actuators Engineered Solutions for the Nuclear Power Industry Enertech, formerly Paul Munroe

More information

4.2 Component Identification

4.2 Component Identification Digital Control Panels Deep Sea Electronics 5220 4.1 General 4.2 Component Identification 4.3 The YML5220 Controller 4.4 Description of Controls 4.5 Navigation 4.5.1 General Navigation 4.5.2 The Event

More information

Re evaluation of Maximum Fuel Temperature

Re evaluation of Maximum Fuel Temperature IAEA Technical Meeting on on Re evaluation of Maximum Operating Temperatures and Accident Conditions for High Temperature Reactor Fuel and Structural Materials, 10 12 July 2012, Vienna, Austria Re evaluation

More information

Battery Power Inverters

Battery Power Inverters Battery Power Inverters Renogy 500W 1000W 2000W Pure Sine Wave Inverter Manual 2775 E. Philadelphia St., Ontario, CA 91761 1-800-330-8678 1 Version 1.4 Important Safety Instructions Please save these instructions.

More information

Summary. IEEJ: November 2011 All Rights Reserved. Yu Nagatomi *

Summary. IEEJ: November 2011 All Rights Reserved. Yu Nagatomi * Estimate of the Electricity-Saving Effects Taking Account of Change Effects in the Service Areas of Tokyo Electric Power Company and Tohoku Electric Power Company Yu Nagatomi * Summary Power generation

More information

ABWR Design and Its Evolution - Primary System Design of ABWR and ABWR-II -

ABWR Design and Its Evolution - Primary System Design of ABWR and ABWR-II - GENES4/ANP2003, Sep. 15-19, 2003, Kyoto, JAPAN Paper 1161 ABWR Design and Its Evolution - Primary System Design of ABWR and ABWR-II - Katsumi Yamada 1*, Satoko Tajima 1, Masaaki Tsubaki 2 and Hideo Soneda

More information

Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel

Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel Fuel Reliability: Achieving Zero Failures and Minimizing Operational Impacts Rob Schneider, Senior Engineer/Technologist, Global Nuclear Fuel In March 2013, Global Nuclear Fuel (GNF) met the INPO challenge

More information

IDENTIFICATION OF FUEL INJECTION CONTROL SYSTEM IN A GDI ENGINE

IDENTIFICATION OF FUEL INJECTION CONTROL SYSTEM IN A GDI ENGINE Journal of KONES Powertrain and Transport, Vol. 17, No. 4 21 IDENTIFICATION OF FUEL INJECTION CONTROL SYSTEM IN A GDI ENGINE Zbigniew Wo czy ski Technical University of Radom Chrobrego Av. 45, 26-6 Radom,

More information

Control of PCCI Combustion using Physical and Chemical Characteristics of Mixed Fuel

Control of PCCI Combustion using Physical and Chemical Characteristics of Mixed Fuel Doshisha Univ. - Energy Conversion Research Center International Seminar on Recent Trend of Fuel Research for Next-Generation Clean Engines December 5th, 27 Control of PCCI Combustion using Physical and

More information

INSTRUCTION MANUAL OIL SEALED ROTARY VACUUM PUMP MODEL PKS-016 PKS-030 PKS-070

INSTRUCTION MANUAL OIL SEALED ROTARY VACUUM PUMP MODEL PKS-016 PKS-030 PKS-070 INSTRUCTION MANUAL OIL SEALED ROTARY VACUUM PUMP MODEL PKS-016 PKS-030 PKS-070 Components division ULVAC, Inc. Table of Contents 1. Inspection 4 2. Mounting 5 3. Oil filling 5 4. Electrical connections

More information

IV. PROOF OF PURCHASE: A warranty claim must be accompanied by proof of the date of purchase.

IV. PROOF OF PURCHASE: A warranty claim must be accompanied by proof of the date of purchase. PD9100 / 9200 SERIES POWER CONVERTER OWNERS MANUAL PROGRESSIVE DYNAMICS, INC. POWER CONVERTER LIMITED WARRANTY I. LIMITED WARRANTY: Progressive Dynamics, Inc. warrants its power converter to be free from

More information

1: CANDU Reactor. B. Rouben McMaster University Nuclear Reactor Physics EP 4D03/6D Sept-Dec September 1

1: CANDU Reactor. B. Rouben McMaster University Nuclear Reactor Physics EP 4D03/6D Sept-Dec September 1 1: CANDU Reactor B. Rouben McMaster University Nuclear Reactor Physics EP 4D03/6D03 2015 Sept-Dec 2015 September 1 Outline A quick look at the design of CANDU Reactors: Reactor Assembly Pressure Tubes

More information

Streamlined RI-ISI. Patrick O Regan EPRI

Streamlined RI-ISI. Patrick O Regan EPRI Streamlined RI-ISI Patrick O Regan EPRI poregan@epri.com Introduction Background Streamlined RI-ISI Methodology Results Discussion, Lessons Learned, Improvements Summary Background GOAL: Based upon the

More information

Generator, Unit Hydrogen, Seal Oil, Stator Coolant, Demin Water Plant Operations Training Huntly Power Station: Units 1-4 Assessment ID: 8014, 8012, 8009, 8015, 8016 NZQA Unit Standard: 17413 Assessment

More information

10A / 15A / 20A Solar Charge Controller. PU1024 / PU1524 / PU2024 series INSTRUCTION MANUAL

10A / 15A / 20A Solar Charge Controller. PU1024 / PU1524 / PU2024 series INSTRUCTION MANUAL 10A / 15A / 20A Solar Charge Controller PU1024 / PU1524 / PU2024 series INSTRUCTION MANUAL Dear Customer, Thank you very much for choosing our product. This manual contains important information about

More information

GENERATOR SEAL OIL SYSTEM

GENERATOR SEAL OIL SYSTEM GENERATOR SEAL OIL SYSTEM Eskom power utility utilized Flownex SE simulation capabilities to mitigate system shutdowns caused by generator hydrogen (H 2 ) seal ring failures. Engineers modelled the hydrogen

More information

Battery. Student booklet

Battery. Student booklet Battery Student booklet Battery - INDEX - 2006-04-07-12:51 Battery Batteries are all over the place, in our cars, our PCs, laptops, portable MP3 players and cell phones. A battery is essentially a can

More information

PLANT HATCH FEEDWATER SYSTEM OPERATING EXPERIENCE. Significant events from 2015

PLANT HATCH FEEDWATER SYSTEM OPERATING EXPERIENCE. Significant events from 2015 PLANT HATCH FEEDWATER SYSTEM OPERATING EXPERIENCE Significant events from 2015 ICES Report #315779 Hatch Unit 2 March 10, 2015 Startup from 2R23 refueling outage Feedwater Control System (RWL Control)

More information

PEIRCE SMITH CONVERTER HOOD IMPROVEMENTS AT BHP COPPER

PEIRCE SMITH CONVERTER HOOD IMPROVEMENTS AT BHP COPPER PEIRCE SMITH CONVERTER HOOD IMPROVEMENTS AT BHP COPPER Ovidiu Pasca and John Bryant BHP Copper Arizona, USA Paykan Safe and Brian Wiggins Gas Cleaning Technologies Dallas, USA ABSTRACT Several improvements

More information

Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP

Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP Probabilistic Risk Assessment for Spent Fuel Pool Decommissioning in the J. Bohunice V1 NPP by Zoltán Kovács, Robert Spenlinger and Helena Novakova RELKO Ltd, Engineering and Consulting Services Račianska

More information

SUCCESSFUL DIESEL COLD START THROUGH PROPER PILOT INJECTION PARAMETERS SELECTION. Aleksey Marchuk, Georgiy Kuharenok, Aleksandr Petruchenko

SUCCESSFUL DIESEL COLD START THROUGH PROPER PILOT INJECTION PARAMETERS SELECTION. Aleksey Marchuk, Georgiy Kuharenok, Aleksandr Petruchenko SUCCESSFUL DIESEL COLD START THROUGH PROPER PILOT INJECTION PARAMETERS SELECTION Aleksey Marchuk, Georgiy Kuharenok, Aleksandr Petruchenko Robert Bosch Company, Germany Belarussian National Technical Universitry,

More information

Main Steam Isolation Valves (MSIV) in Nuclear Power Plants with PWR

Main Steam Isolation Valves (MSIV) in Nuclear Power Plants with PWR Main Steam Isolation Valves (MSIV) in Nuclear Power Plants with PWR FD2 1 E 02/2000 1 Introduction As isolating valve in the main steam line of nuclear power stations different designs are known. Beside

More information

R&D on a Medium-speed, Four-cycle Diesel Engine Using Heavy fuel oil

R&D on a Medium-speed, Four-cycle Diesel Engine Using Heavy fuel oil 1999C.4.1.11 R&D on a Medium-speed, Four-cycle Diesel Engine Using Heavy fuel oil 1. R&D contents 1.1 Background and R&D objectives In order to meet increasing demand for light oil and intermediate fraction,

More information

16000SIII Automatic Grease System

16000SIII Automatic Grease System Manual # 99905495 16000SIII Automatic Grease System Effective 20120716 IOWA MOLD TOOLING CO., INC. PO Box 189 Garner, IA 50438 Tel: 641-923-3711 FAX: 641-923-2424 Website: http://www.imt.com Copyright

More information

Today, we re going to talk about battery safety. We ll discuss all the key issues associated with using batteries safely, including battery hazards,

Today, we re going to talk about battery safety. We ll discuss all the key issues associated with using batteries safely, including battery hazards, Today, we re going to talk about battery safety. We ll discuss all the key issues associated with using batteries safely, including battery hazards, battery charging, and battery maintenance. Although

More information

Control. Part B, Section 2. This section covers the following unit configurations. 3400V 3500V. Voltage 4. Pump Piston (E, F, G)

Control. Part B, Section 2. This section covers the following unit configurations. 3400V 3500V. Voltage 4. Pump Piston (E, F, G) Part B, Section 2 Model This section covers the following unit configurations. Voltage 4 3100V 3400V 3500V Pump Piston (E, F, G) Manifold 4-Port (A) 6-Port (B, C) 2-Port (S, T) Vista Standard (V) B 2-0

More information

WELCOME AND INTRODUCTORY REMARKS

WELCOME AND INTRODUCTORY REMARKS WELCOME AND INTRODUCTORY REMARKS Robust Power Workshop 2017-05-03, Per Lamell, F-0051167 1 SAFETY FIRST Please note where the nearest emergency exits, fire extinguishers, gathering place and defibrillators

More information

AP1000 Plant Overview

AP1000 Plant Overview AP1000 Plant Overview Westinghouse IEEE Subcommittee on Qualification Tom Hayes Passive Plant Projects hayestp@westinghouse.com 1-412-374-4420 Slide 1 Westinghouse Passive Plants Meet Power Company Needs

More information

THE FUKUSHIMA ACCIDENT: CAUSES, RESULTS AND IMPLICATIONS FOR EUROPE

THE FUKUSHIMA ACCIDENT: CAUSES, RESULTS AND IMPLICATIONS FOR EUROPE THE FUKUSHIMA ACCIDENT: CAUSES, RESULTS AND IMPLICATIONS FOR EUROPE Steven C. Sholly, Senior Scientist Institute of Safety and Risk Sciences Department of Water, Atmosphere & Environment University of

More information

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI 621213 QUESTION BANK --------------------------------------------------------------------------------------------------------------- Sub. Code : EE2402 Semester

More information

Catalytic Failures. Engine running too hot.

Catalytic Failures. Engine running too hot. Catalytic Failures It is not uncommon for technicians to misdiagnose a driveability or emissions issue by blaming the converter. In many cases, it s not the converter s fault, but rather one of the engine

More information

Power Inverter. User s Manual. Diamond Series CPD1200EILCD

Power Inverter. User s Manual. Diamond Series CPD1200EILCD Power Inverter Diamond Series CPD1200EILCD User s Manual 2 TABLE OF CONTENTS 1 IMPORTANT SAFETY INSTRUCTIONS..4 2 INSTALLATION....5 2-1 Unpacking...5 2-2 Product Overview & Outlook..5 2-3 Power Requirements

More information

Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures

Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures Impact of the Niigata Chuestu-oki Earthquake on the Tokyo Electric Power Company (TEPCO) Kashiwazaki-Kariwa Nuclear Power Station and Countermeasures September 2007 The Tokyo Electric Power Company, Inc.

More information

CHAPTER 6: HEAT TRANSPORT CONTROL SYSTEMS MODULE 3: HEAT TRANSPORT BLEED CONTROL

CHAPTER 6: HEAT TRANSPORT CONTROL SYSTEMS MODULE 3: HEAT TRANSPORT BLEED CONTROL Chapter 6: Heat Transport Con,,,J! Systems CHAPTER 6: HEAT TRANSPORT CONTROL SYSTEMS MODULE 3: HEAT TRANSPORT BLEED CONTROL Introduction Any bleed flow from the Heat Transport System as. a result of either

More information

VALEO HEVAC (P38 NRR) - System Overview

VALEO HEVAC (P38 NRR) - System Overview VALEO HEVAC (P38 NRR) - System Overview Custom Manufactured by Valeo for the P38 Range Rover as an Air condition control module option on everything except the very base model, which has only 3 rotary

More information

Development of a virtual reality education program for hydrogen fueling station

Development of a virtual reality education program for hydrogen fueling station Development of a virtual reality education program for hydrogen fueling station Mary Kay O Connor Process Safety Center International Symposium Beyond Regulatory Compliance, Making Safety Second Nature

More information

Purging Air From Divider Block Lubrication Systems

Purging Air From Divider Block Lubrication Systems FROST ENGINEERING SERVICE Purging Air From Lubrication Systems A D I V I S I O N O F G E C S E Y S A L E S & S E R V I C E DESCRIPTION Divider block lubrication systems operate correctly only when all

More information

Automatic drain valves

Automatic drain valves driving commercial vehicles If you notice more than a few drops of water when you drain the supply reservoir, the air dryer or compressor may need servicing. fast fact Even if the air brake system includes

More information

Module 7: Cooling System Components

Module 7: Cooling System Components  Â  Basic Cooling System Components Radiators Common Types of Radiators Coolant Hoses Water Pumps Centrifugal Force Types of Drives for Water Pumps Types of Drive Belts Basic Cooling System Components

More information

Solar Charge Controller

Solar Charge Controller Table 3: Charging voltage for 4 types of battery Battery Type Battery Type Code SC-600W MPPT Bulk Voltage Floating Voltage Vented 01 28.6 V 26.4 V Sealed 02 28.6 V 26.8 V Gel 03 28.6 V 27.4 V NiCd 04 28.6

More information

Diagnosis of fuel tank systems with fuel tank leak diagnosis module (DMTL)

Diagnosis of fuel tank systems with fuel tank leak diagnosis module (DMTL) Page 1 of 10 SIT-SIT-SI2002-160102890 Diagnosis of fuel tank systems with fuel tank leak diagnosis module (DMTL) All US models VIN: XXXXXXX Vehicle: 6'/E64/CONVERTIBLE/650i/N62/AUTO/USA/LL/2007/05 System

More information

Masaru Takei - The Tokyo Electric Power Company, Inc. Executive Vice President

Masaru Takei - The Tokyo Electric Power Company, Inc. Executive Vice President Meeting Transcript (Presentation) Event Date/Time: August 9, 2011 / 06:00PM JST Event Name: TEPCO Investor Meeting for FY2011 1 st Quarter Earnings Results Corporate Participants: Masaru Takei The Tokyo

More information

High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd.

High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd. Hitachi Review Vol. 53 (2004), No. 3 121 High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd. Hiroaki Yamada Kiyoshi

More information

Investigation and Resolution of Intermittent Loss of Flow in a Diaphragm Metering Pump. Gregory Frantz. DuPont

Investigation and Resolution of Intermittent Loss of Flow in a Diaphragm Metering Pump. Gregory Frantz. DuPont Investigation and Resolution of Intermittent Loss of Flow in a Diaphragm Metering Pump Gregory Frantz DuPont 2 Background Pump adds an ingredient to a reaction vessel. Both short periods of loss of flow

More information

Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting from Natural Disasters

Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting from Natural Disasters Volume 3 Number 1 International Journal for Nuclear Security International Journal of Nuclear Security 11-20-2017 Solar System Battery Backups for Reactor Coolant Pumps During Electricity Outages Resulting

More information

Information Bulletin. Fire Pump Battery Failures. Version 1.1 Approved for release August 2011

Information Bulletin. Fire Pump Battery Failures. Version 1.1 Approved for release August 2011 Version 1.1 Approved for release August 21 1.0 Purpose Statement The purpose of this is to raise awareness amongst stakeholders about concerning industry trends associated with batteries supporting fire

More information

INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS

INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS CONTENTS Introduction Safety Operating Principle System Installation Initial Startup System Operations Troubleshooting Maintenance

More information

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit Exercise 3-1 Basic Hydraulic Circuit EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with the hydraulic schematic and components of the nacelle trainer. You will identify

More information