Banedanmark. Tenders, and upcoming projects in Banedanmark. Senior Market Consultant Cathrine Carøe at Nordiska leverantörsdagen
|
|
- Spencer York
- 6 years ago
- Views:
Transcription
1 Banedanmark Tenders, and upcoming projects in Banedanmark Senior Market Consultant Cathrine Carøe at Nordiska leverantörsdagen
2 Find tenders at also in English Online Tender Plan is updated continuously. Find new tenders published at TED (Tender Electronic Daily). Attend quarterly supplier dialogue meetings. Attend market dialogue meetings held in English. 2
3 Tender Plan Future, current and completed tenders at online Tender Plan Overview and description of each project in these 5 categories: Renewal & construction Operations & maintenance Technical advisory Consulting Goods and other services What, where, when, who 3
4 Details in Tender Plan also in English Subscribe to changes to the selected tender. Forward tender to others. Tender & project descriptions contact info, category, size of project 4
5 Budgets Projects for 1,64 Billion Euro (12,3 Billion DKK) Annual maintenance of approx. 170 Million Euro (1,3 Billion DKK). Major track possessions for works on tracks, platforms, and bridges: Projects in Projects in Projects in Projects in
6 Construction projects in 7,8 Billion DKK for 2019 and
7 #467 Track renewal Høje Tåstrup-Roskilde Station Budget: +250 M DKK. When: 2019 Where: East 10 km track renewal per track (= 40 km). Drainage. 12 switches. Station with works: Høje Tåstrup Derived works, interlocking, and adjustment of catenary system. 7
8 #467 Track renewal Cph-HT Station. Budget: 150 M DKK. When: 2020 Where: East 18 km per track. Station works. Drainage. Sleepers. Ballast. 27 switches. Catenary. 8
9 #468 Sporfornyelse Ringsted Korsør Budget: +600 M DKK. When: 2019 Where: East 22 km new track. 36 km new sleepers. 51 km ballast cleaning. 32 km new sub layer. 33 new switches. 23 removal of switches. New track layout. 3 km drainage. Track lowering on 8 different locations. Earth issues at Tjæreby and Forlev. Interlocking and catenary works due to track renewal. 9
10 # Track renewal Fyn Budget: TBD When: 2019 Where: East 22 km renewal of sleepers. 39 km ballast cleaning. 9 km renewal of sub layer. 2 switches. 1,3 km drainage. 3,5 km replacement of track cable. Associated works regarding catenary, interlocking and ATC. 10
11 #121 Udskiftning køreledningsanlæg bane 82 Budget: 100 M DKK. When: 2019 Where: East Renewal of the catenary system on the Urban DC-Rail of Copenhagen. 46 km 1:1 replacement of the catenary system between Holte and Østerport Station. The project includes replacement of approx. 700 poles, and masts, wires. Derived works; equally bonding and power supply cables The work is planned to be done in mostly train free intervals of 4 hour duration during the night. 11
12 # Favrholm, new station south of Hillerød. Budget: 140 M DKK for the main proposal. Besides an Option. When: 2019 Where: East The main proposal includes establising an interchange station for S-banen and Frederiksværkbanen; 2 new side platforms at the existing S-bane. 1 new platform at Frederiksværkbanen. Establishment of access routes and a forecourt with commuter parking. A proposal for compensating for facilities that will be affected. 12
13 #473 (Hobro)-Aalborg. Budget: 200 M DKK. When: 2020 Where: West 51 km track renewal. 44 switches renewal + 27 closure 65 km sleepers renewal. 102 km ballast cleaning + some sublayer. Drainage. HS upgrading. Moving track up to 1.5 meter sideways. 13
14 # Track renewal Fredericia-Aarhus. Budget: 140 M DKK. When: 2020 Where: West 45 km track renewal. 10 km drainage. 16 km renewal of sleepers. 64 km ballast cleaning + some sublayer 29 switches. Catenary. Interlocking. ATC. 14
15 # NF/SI/0275 Fixed Transmission Network (FTN) Passive Budget: DKK +100 mill. When: Where: Denmark - - Renewal/redesign of FTN Passive infrastructure - Approx. 1,900 km. - Building supplies: Tubing Fiber optic cables Cable wells, ODF, etc. - Tender published on TED 18.th November
16 # Manuelle Spor. Budget: +100 M DKK. When: Where: Denmark Manual works on sleepers. Manual works on rails. Welding. One contract divided into six lots. Tender form; public tender with actual costs. Tender deadline 11. December Work March
17 # Outsourcing of Forestry services. Budget: M DKK When: Where: Denmark Forestry; manual and machine works on greenery (cut and crush). Along 4,000 km track side. Outsourcing Q One contract divided into three lots. Contract type: actual costs. Tender form is restricted invitation to tender. Work from September to May. 17
18 # Line tamping outsourcing of maintenance. Budget: TBD When: Where: Denmark Track analysis. Ballast maintenance. Line tamping 250 km per year for 2-3 years Line tamping at stations. Tender form to be decided. Tender in Q
19 One-Point-Of-Entry Please contact us at: 19
Railway Projects in Banedanmark
Railway Projects in Banedanmark Building Network Construction Conference 27.11.2018 Presented by Senior Market Analyst Cathrine Carøe 1 Facts about Banedanmark A Danish state-owned enterprise under the
More informationBanedanmark. Nordic Hour at Austria Advantage at INNOTRANS Th September 2018 presented by General Manager Rune Stenbæk Olsen, Banedanmark
Banedanmark Nordic Hour at Austria Advantage at INNOTRANS 2018 19.Th September 2018 presented by General Manager Rune Stenbæk Olsen, Banedanmark 1 Facts about Banedanmark A state-owned enterprise under
More informationCompetition in long distance train service between Eastand Westdenmark. Kontorchef Lasse Winterberg 9. februar 2011
Competition in long distance train service between Eastand Westdenmark Kontorchef Lasse Winterberg 9. februar 2011 Rail in Denmark Rail has 8 percent market share Every Dane travels about 1200 km by rail
More informationThe Signalling Programme
The Signalling Programme Jan Schneider-Tilli, Programme Director 1. June 2016 - DTU 1 Agenda 1. Background to the Signalling Programme 2. ERTMS 3. Way ahead 4. Programme Management, Collaboration & MSP
More informationJanice Fortunato Senior Director Business Partnerships
Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these
More informationSignalling Programme. Presentation of Banedanmarks ERTMS programme Programme Diretor Morten Søndergaard
Signalling Programme Presentation of Banedanmarks ERTMS programme 12.02.2013 Programme Diretor Morten Søndergaard Background of the Signalling Programme Rail Data 3.000+ trains/day 38.000 daily departures
More informationPresentation of the Baltimore Metro System
Presentation of the Baltimore Metro System Presenter: Michael S. Davis Deputy Administrator, Transit Operations Division March 2, 2010 Topics Early Planning for Rapid Rail Transit System Overview Section
More informationLarge experience in stage planning. Large knowledge on legal matters on tendering and contract management. Full professional proficiency in English.
CV Niels@trailc.dk +45 2336 7248 Personal data: Name : Niels Thougård Pedersen Year of birth : 1965 Marital status : Married, 3 children ( 90, 92, 97) Address : Virumbakken 10, DK-2830 Virum Education:
More informationAxle Load Checkpoints (ALC) in Denmark
Axle Load Checkpoints (ALC) in Denmark 21.05.2013 Presented by Tom E. Thøgersen, Banedanmark, Teknisk Drift IT - Transition & Integration The Annual Danish Rail Convention 2013 Introductions Wheel/rail
More information$200 Million Investment in New Rail Maintenance Vehicles for Continued Safe, Reliable and Comfortable Journeys for MTR Passengers
PR056/15 10 June 2015 $200 Million Investment in New Rail Maintenance Vehicles for Continued Safe, Reliable and Comfortable Journeys for MTR Passengers They are big, they are yellow and they work only
More informationSustainable transport better infrastructure - The Danish Government s vision for green infrastructure
Sustainable transport better infrastructure - The Danish Government s vision for green infrastructure Maja Caroee Department of Civil and Environmental Engineering University of Hawaii at Manoa May 5th
More informationUPGRADING THE AMTRAK KEYSTONE CORRIDOR
UPGRADING THE AMTRAK KEYSTONE CORRIDOR Mark A. Wurpel Director Project Initiation & Development Amtrak 2005 AREMA Conference & Exposition Chicago, Illinois ABSTRACT: Upgrading the Amtrak Keystone Corridor
More informationCTA Capital Construction Update December 12, 2006
Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction
More informationOdense Tramway Construction Project
Odense Tramway Construction Project Odense Tramway has a clear Mission and Vision, both supported by tangible objectives that will be the reference during the tender process Mission, Vision and Objectives
More informationMODURBAN MODURBAN. Dan Otteborn, Member of the MODURBAN Supervisory Board
MODURBAN Modular Urban guided Rail systems Dan Otteborn, Member of the MODURBAN Supervisory Board V2 MODURBAN Brief project overview Total Budget: 20 million Project Duration: 51 Months - Jan 2005-March
More informationModernising the Great Western railway
Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western
More informationTechnology and maintenance of tracks at ÖBB
Technology and maintenance of tracks at ÖBB Dr. Michael Mach ÖBB Infrastructure Head of Railway Construction and Infrastructure Management Dr. Rudolf Schilder Former Head of Maintenance We plan, build,
More informationBaltic Marine Environment Protection Commission
Baltic Marine Environment Protection Commission Maritime Working Group Tallinn, Estonia, 6-8 September 2016 MARITIME 16-2016 Document title Information about remote sensing of SO 2 emissions from ships
More informationElected Officials Briefing. North Metro Rail Line Update. February 9, 2017
Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationPrecision Station Stopping Progress Update
Washington Metropolitan Area Transit Authority Precision Station Stopping Progress Update Presented to: The Board of Directors; Customer Service, Operations and Safety Committee By PlanninghDevelopmenthEngineeringhConstruction
More informationILLINOIS SUPPLEMENTAL PV PROCUREMENT PROGRAM (ROUND 3) JANUARY 13, 2016
ILLINOIS SUPPLEMENTAL PV PROCUREMENT PROGRAM (ROUND 3) JANUARY 13, 2016 SPEAKERS Tom MacKenty Associate, Environmental Markets Steven Eisenberg CEO 2 AGENDA Company Overview Program Overview SRECTrade
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationSmart Grid Update Supplier Conference. Kevin Dasso Senior Director Technology & Information Strategy. October 27, 2011
Smart Grid Update 2011 Supplier Conference Kevin Dasso Senior Director Technology & Information Strategy October 27, 2011 Agenda PG&E Smart Grid overview Implementation Approach Smart Grid Baseline Upcoming
More informationI-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019
I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate
More informationKEEPING HOUSTON AIRPORTS OPENING DAY FRESH
KEEPING HOUSTON AIRPORTS OPENING DAY FRESH Devon Tiner, P.E., PMP Assistant Director Asset Engineering June 9, 2016 VISION AND MISSION STATEMENT MISSION: WE EXIST TO CONNECT PEOPLE, BUSINESSES, CULTURES
More informationMunicipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation
Municipal Road and Bridge Revolving Loan Fund 2014 Program Summary Rhode Island Department of Transportation The Basics The FY2014 Budget passed by the Rhode Island General Assembly included Article 20,
More informationCapital Needs Assessment Riders Advisory Council July2, 2008
Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair
More informationSustainability Transport Innovation Energy efficiency the key to railway innovation
Sustainability Transport Innovation Energy efficiency the key to railway innovation Mads Bergendorff macroplan.dk Banekonferencen København 9. maj 2012 Macroplan in brief Founded in 2006 by Mads Bergendorff
More informationNew Haven-Hartford-Springfield Rail Project Gateway to New England. Program Update March 14, 2011 Revised & Updated March 31, 2011
New Haven-Hartford-Springfield Rail Project Gateway to New England Program Update March 14, 2011 Revised & Updated March 31, 2011 1 New Haven-Hartford-Springfield Rail Corridor Glory Days: 1925-1955 22
More informationNetwork Safeworking Rules and Procedures
Network Safeworking Rules and Procedures Setting Back or Propelling on Running Lines Rule Number: 4015 Version 1.0, 31 March 2016 Setting Back or Propelling on Running Lines Rule Number: 4015 Document
More informationTER WP2 Transport Challenges and Global Crisis. Dr. Klaus Schierhackl, CFO Bad Gastein,
TER WP2 Transport Challenges and Global Crisis Dr. Klaus Schierhackl, CFO Bad Gastein, 23.4.2009 1 ASFINAG Group is the 3rd largest concessionaire in Europe responsible for a network of more than 2.100
More informationAppendix 1B: Ferry statistics
The Danish Road Directorate Page 1 The following pages contain an overview of the development in the number of transferred ordinary vehicles and s in 2009 and 2010 on the following routes: Elsinore - Helsingborg
More informationGREATER CLEVELAND REGIONAL TRANSIT AUTHORITY FFY 2017 GRANT PROGRAM PROJECT DESCRIPTIONS
Section 5307 Capital Formula (OH-2017-XXXX) Information Technology Program This program is to purchase ADP hardware, ADP software and third party support for the upgrade of our Network Infrastructure,
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationPRICE LIST OF FEES FOR USING THE 1435 MM TRACK GAUGE RAILWAY INFRASTRUCTURE MANAGED BY PKP POLSKIE LINIE KOLEJOWE S.A. EFFECTIVE FROM 9 DECEMBER 2018
PRICE LIST OF FEES FOR USING THE 1435 MM TRACK GAUGE RAILWAY INFRASTRUCTURE MANAGED BY PKP POLSKIE LINIE KOLEJOWE S.A. EFFECTIVE FROM 9 DECEMBER 2018 TAKING INTO ACCOUNT THE MODIFICATIONS ADOPTED BY RESOLUTION
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More information2012 MULTIMODAL OPERATIONS WORKSHOP
New Haven-Hartford-Springfield Rail Program Gateway to New England Jeffrey T. Schultz, PMP Senior Principal Technical Specialist Parsons Brinckerhoff Glastonbury, CT July 31, 2012 2012 MULTIMODAL OPERATIONS
More informationElected Officials Briefing North Metro Rail Line Update. November 10, 2016
Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension
Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationTrakcja Polska S.A. A Leading Provider of Construction and Installation Services to Railway Sector in Poland. July 2009
Trakcja Polska S.A. A Leading Provider of Construction and Installation Services to Railway Sector in Poland July 29 Leading Provider of Construction and Installation Services to the Railway Sector in
More informationSummary of Energinet's RUS plan 2016 (reinvestment, expansion, restoration)
Summary of Energinet's RUS plan 2016 (reinvestment, expansion, restoration) 1. Summary Energinet's RUS (reinvestment, expansion, restoration) plan is the first overall plan for the electricity transmission
More informationLegal Aid Reform: what is supposed to happen when?
: what is supposed to happen when? Updated 9.2.07 The table below sets out various statements made by the DCA/LSC about the timing of the proposed changes in relation to non-family civil matters. Since
More informationKreis Ostholstein, the Fehmarnbelt Committee, municipalities, tourist attractions and transport enterprises in the Fehmarnbelt Region
PASSAGE Action Plan Institution: Other partners: Femern Belt Development Kreis Ostholstein, the Fehmarnbelt Committee, municipalities, tourist attractions and transport enterprises in the Fehmarnbelt Region
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationEast Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015
1 East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 Today s Agenda Safety Eagle P3 Project Commuter rail vehicle East Rail Line Economic impacts DBE/SBE/WIN status Progress
More informationThe Potential for Regional Express Trains when Introducing High speed Operation
The Potential for Regional Express Trains when Introducing High speed Operation Alex Landex DTU Transport Bygningstorvet 116V 2800 Kgs. Lyngby e-mail: al@transport.dtu.dk 1. Abstract When improving railway
More informationIMPROVING CITIES THROUGH PUBLIC-PRIVATE PARTNERSHIPS. Toronto Forum For Global Cities December 2008
IMPROVING CITIES THROUGH PUBLIC-PRIVATE PARTNERSHIPS Toronto Forum For Global Cities December 2008 TORONTO S CHALLENGE GTA suffers from traffic congestion The average Torontonian spends seven hours a week
More information1 Downtown LRT Connector: Draft Concept
Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half
More informationHorns Rev 3 & Kriegers Flak Platform Interfaces
Horns Rev 3 & Kriegers Flak Platform Interfaces Technical Dialog Meeting 10 September 2013 HR3 and Krigers Flak - AC platforms Technical Dialog Meeting 10 September 2013 1 Agenda 1. Location of platforms
More informationTEMPLATE OF THE NATIONAL REPORT
TEMPLATE OF THE NATIONAL REPORT TO BE PRESENTED BY EACH DELEGATION DURING THE ASECAP STUDY AND INFORMATION DAYS PARIS, 29-31 MAY 2017 Network length In 2017 the total length of the motorway and express
More informationProposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1
Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation
More informationInformation about the project Construction of the light rail transit line in Almaty
Department of Almaty LRT Project, 2018 Information about the project Construction of the light rail transit line in Almaty Version for potential private partners 1 2017 year is a new starting point for
More informationMemo. Soil & Waste File no. MST Ref. pehem/ jehni/lived 29 September Memo for Dialogue forum
Memo Memo for Dialogue forum Local authority reporting of costs for collection of waste portable batteries and accumulators in 2010 Soil & Waste File no. MST-7034-00001 Ref. pehem/ jehni/lived 29 September
More informationEnergy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director
Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D
More informationCity of San Juan Capistrano Agenda Report
12/16/214 82 City of San Juan Capistrano Agenda Report TO: FROM: DATE: SUBJECT: Karen P. Brust, City Manag4(?1-- Keith Van Der Maaten, P.E., Public Works and Utilities Directo Prepared by: George Alvarez,
More informationScarborough Subway Extension. Stakeholder Advisory Meeting February 28, 2017
Scarborough Subway Extension Stakeholder Advisory Meeting February 28, 2017 City Council Direction The Scarborough Subway Extension (SSE) project and budget were approved by City Council in 2013, prior
More informationA Guide to Key Railroad Terminology for the Northeast Corridor
A Guide to Key Railroad Terminology for the Northeast Corridor Index of terms Approach signal, 8 Diverging route, 5 Ladder, 6 Section break, 12, 13 Tie replacement, 7 Ballast, 3, 4, 7 Double slip switch,
More informationNetwork Safeworking Rules and Procedures
Network Safeworking Rules and Procedures s Rule Number: 3025 Version 1.0, 31 March 2016 Temporary Speed Restrictions Rule Number: 3025 Document Control Identification Document title Number Version Date
More informationHead of Division for Road Traffic Technology; Road Infrastructure Safety; Routine Road Maintenance Management
BDir Dipl Ing Manfred Silvanus Head of Division for Road Traffic Technology; Road Infrastructure Safety; Routine Road Maintenance Management www.bmvi.de AGENDA - Federal Ministry of Transport and Digital
More informationLocation Concept Plan Amendment Recommendation Approved 2011 Concept Plan
Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West
More informationSOUTH TEXAS COMMISSION MEETING
SOUTH TEXAS COMMISSION MEETING September 26, 2013 Pharr District Commission Meeting Pharr District: Overview The Pharr District plans, designs, builds, operates and maintains the state transportation system
More informationABB s supplier qualification process: Achilles and Power &Tech Frequently Asked Questions (FAQs)
ABB s supplier qualification process: Achilles and Power &Tech Frequently Asked Questions (FAQs) June 2013 Overview Why is ABB introducing Achilles? ABB operates in approximately 100 countries. This means
More informationSafety and Operations Committee. Action Item III-A. December 13, 2018
Safety and Operations Committee Action Item III-A December 13, 2018 Preventive Maintenance Update Page 3 of 46 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationConverting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada
Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population
More informationSTREET LIGHTING Municipality Zupa Dubrovacka
STREET LIGHTING Municipality Zupa Dubrovacka Jelena Kremenjaš UNDP Croatia MUNICIPALITY ŽUPA DUBROVAČKA The Municipality of Župa Dubrovnik is situated in the county of Dubrovnik-Neretva in the south-east
More informationsystem performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.
system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationHutchinson WWTF Solar PV EP4-41
Hutchinson WWTF Solar PV EP4-41 John Paulson Project/Environmental/Regulatory Manager April 12, 2016 Site Preparation Panoramic 2 Site Preparation Aerial 3 Ballast Piers 18 H x 30 D - 410 total 4 5 6 7
More informationSustainable Transportation At Stony Brook University Friday, September 21, 2012 SUNY Sustainability Conference Syracuse Center of Excellence
Sustainable Transportation At Stony Brook University Friday, September 21, 2012 SUNY Sustainability Conference Syracuse Center of Excellence James O Connor, Director of Sustainability & Transportation
More informationSouth West Wales Best Practice Club with ABC Electrification Swansea 7 th July 2015
South West Wales Best Practice Club with ABC Electrification Swansea 7 th July 2015 Welcome Martin Nicholls Chair South West Wales Best Practice Club Great Western Route Modernisation (GWRM) CEW Breakfast
More informationLinu Mathew Philip. Centre for Trade and Development (Centad), New Delhi, India
Linu Mathew Philip Centre for Trade and Development (Centad), New Delhi, India Regional Dialogue in Biofuels in Asia 9-10 November 2009 Relevance of Biofuel in the new context Trends Production Consumption
More informationGold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014
Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationCommuter Services Updates. Parking Coordinators Meeting July 2018
2018 2019 Commuter Services Updates Parking Coordinators Meeting July 2018 Agenda Construction impacts Parking enhancements, renewal process Rate updates Parking application preview Q&A Raffle! Introductions
More informationDriverless Train Operation
Driverless Train Operation siemens.com.cn/ingenuityforlife Table of content Grade of Automation 3 Passengers expectations of driverless operation 4 Operators expectations of driverless operation 5 Siemens
More informationSan Diego Metropolitan Transit System. William R. Spraul Chief Operating Officer, Transit Services
San Diego Metropolitan Transit System William R. Spraul Chief Operating Officer, Transit Services Overview of San Diego Metropolitan Transit System (MTS) MTS provides light rail and bus services through
More informationI-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange
I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet
More informationCity of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015
City of Beverly Hills North Santa Monica Blvd Reconstruction Traffic & Parking Commission June 04, 2015 1 Overview of June 4 TPC Overview of Possible Traffic Mitigation Measures Toolbox During Construction
More informationTHE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY. PARTIAL STREET LIGHTING SERVICE RATE 117 Page 1 of 5
Page 1 of 5 AVAILABLE for municipal street and highway lighting for dusk to dawn or midnight lighting services as provided below within the Company service area where all street lighting equipment within
More informationUN-ECE / WP.29-AC3 HFCV - SGS. Federal Ministry of Transport, Building and Urban Affairs
Federal Ministry of Transport, Building and Urban Affairs Christoph Albus Head of Division S 34 Vehicle Engineering / Environment GRPE / WP.29 Project Management of HFCV project Informal document No. GRSP-41-30
More informationInfraGuidER Workshop Requirements for the guidelines an infrastructure managers view June 8 th, 2010, UIC Paris Dr. Andreas Oberhauser Maintenance
InfraGuidER Workshop Requirements for the guidelines an infrastructure managers view June 8 th, 2010, UIC Paris Dr. Andreas Oberhauser Maintenance Process Manager Track Department B63, Wiener Linien GmbH
More informationPlanning Commission Travis Parker, Planning Director DATE: March 7, 2018 SUBJECT: Lakewood Zoning Amendments - Parking
MEMORANDUM TO: FROM: Planning Commission Travis Parker, Planning Director DATE: March 7, 2018 SUBJECT: Lakewood Zoning Amendments - Parking In August 2017, the Lakewood Development Dialogue process began
More informationLoad profiling for balance settlement, demand response and smart metering in Finland
Load profiling for balance settlement, demand response and smart metering in Finland Seppo Kärkkäinen Elektraflex, Finland Is DSM the Answer? Workshop in the connection of IEA DSM EXCO, Chester 21st October
More informationThe $600 Million Rebirth of San Diego Trolley
The $600 Million Rebirth of San Diego Trolley E. Wayne Terry Chief Operating Officer MTS Rail APTA Rail Conference - 2010 1919 San Diego and Arizona Eastern Railroad The Bones of the Original South and
More informationOHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.
OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Strawser Construction Project Team Chris Anspaugh Regional
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 11, 2018 To: The Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee
More informationEast Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary
East Link Extension September 16, 2014 Bel-Red Conclusion to Final Design Open House Public Involvement Summary Table of contents 1 Background 2 Overview 2 Notification 3 Open House Overview 4 Comment
More informationTransit in Bay Area Blueprint
Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART
More informationCity of Austin. Airport Leadership Eliminates GSE Emissions
City of Austin Airport Leadership Eliminates GSE Emissions Topics Motivation for Installing Fast Charging Electric GSE Stations Procurement Methodology DERA Grant Project Highlights Overall Benefits ABIA
More informationMassachusetts Department of Environmental Protection Underground Storage Tank Program
Massachusetts Department of Environmental Protection Underground Storage Tank Program Tom DeNormandie, Chief Underground Storage Tank and Stage I/II Branch 2016 New England Storage Tank Conference Westborough,
More informationMonthly Economic Letter
Monthly Economic Letter Cotton Market Fundamentals & Price Outlook RECENT PRICE MOVEMENT Most cotton prices were stable over the past month. Chinese prices moved slightly higher. Indian prices moved slightly
More informationRailway Obsolescence Management Contract
Railway Obsolescence Management Contract Olivier Vivancos, Alstom IIOM Conference, June 2017 A complete range of transport solutions ROLLING STOCK Tram, metro, suburban/regional, high speed, very high
More informationAn Overview of Transportation Responsibility
1 An Overview of Transportation Responsibility Fast Facts Our Business History of Budget Cuts (2007 2013) Benchmark Comparison Proposed Budget Cuts for FY14 Community Input Peer Comparison 2 Mission Statement:
More informationOne-Fit,UFES, Reyrolle LM
EPDS SERVICE, SOUTH AFRICA, FRANS BOUWER, 2018. Retrofit Solutions One-Fit,UFES, Reyrolle LM AMEU Namibia,March 2018 Retrofit Agenda 1. Safety 2. One-Fit overview 3. UFES overview 4. Reyrolle LM-Switchgear
More informationUpdate of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI
Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative
More informationon Motorways and on Main Roads The German GNSS Toll System Hanns-Karsten Kirchmann CEO, Toll Collect GmbH
Skatteudvalget SAU alm. del - Bilag 199 Offentligt The German GNSS Toll System on Motorways and on Main Roads Hanns-Karsten Kirchmann CEO, Toll Collect GmbH 20th of June 2007 The German Motorway Toll Act
More informationGPP in Copenhagen - Sharing experiences on Sustainable Mobility and GPP. Webinar, EU NGO Network on GPP, Jan 2018
GPP in Copenhagen - Sharing experiences on Sustainable Mobility and GPP Webinar, EU NGO Network on GPP, Jan 2018 Agenda General introduction to GPP in Copenhagen (5 min) How we work with transportation
More information