TECHNICAL MEMORANDUM. Nathan D. Maier Consulting Engineers

Size: px
Start display at page:

Download "TECHNICAL MEMORANDUM. Nathan D. Maier Consulting Engineers"

Transcription

1 TECHNICAL MEMORANDUM To: John Hoppie, DART From: URS Corporation Peng Zhao, PE Chad Allen, PE Lakhbir Chauhan, PE Herb Miller, PE Nancy Stavish Nathan D. Maier Consulting Engineers Bill Wallace, PE Heidi Fischer, PE Date: February 6, 2012 RE: Cotton Belt Draft Pump Station Study for Deep Trench Concept in North Dallas General Planning Consultant Services - Dallas Area Rapid Transit (DART) Contract ID C Task Order #4: Cotton Belt PE/EIS URS Project Number: Introduction During the development of the DART 2030 Transit System Plan, the Dallas City Council passed a resolution with their recommendations for the plan. This included conditions specific to the Cotton Belt Corridor project, one of which was that the rail line be below grade from at least 1,500 feet east of Meandering Way to 2,000 feet west of Preston Road. In their resolution adopting the 2030 Transit System Plan in October 2006, the DART Board of Directors included a set of Corridor Development Conditions to guide planning efforts in the corridor, including an acknowledgement of the City s preference for a trench. As such, DART is examining a range of options to place the rail line below grade as part of the Preliminary Engineering (PE) effort. The purpose of this memorandum is to develop and analyze a concept for a deep trench option. The deep trench concept would depress the rail alignment at least 15 feet below grade. The handling of storm water drainage at creek crossings is the most critical challenge for this option. There are three creek crossings between Hillcrest on the east and Preston on the west: Osage Branch Crossing 1, located just east of Davenport Court; Osage Branch Crossing 2, located just south of Duffield Drive; and, McKamy Branch Crossing, approximately 300 feet north of Davenport Drive. 1

2 Implementation of a deep trench option would require that water in all three creeks be pumped past the trench. Photographs of existing conditions can be found in Appendix A. A shallow trench option has also been developed that avoids the need for pumps. The following sections outline the drainage concept for this deep trench option, including options for pumping stations, types of pumps, and use of submersible electric motors. This is followed by an analysis for each creek crossing, including design considerations, power needs, probable annual operating costs, and a summary of estimated capital costs. 2.0 Drainage Concept The primary objective of the drainage concept for the deep trench option is that the 100-year floodplain water surface elevations must be conserved in order to avoid adding new inundation areas or structures to the existing flood plain. Storm water velocities within the creek must also be controlled to avoid erosion and compromising the integrity of the creek banks. The drainage concept consists of capturing the water upstream of the alignment and pumping it under the tracks, over to the downstream side of the tracks. The following is a preliminary analysis of the transfer pumping under the tracks, as well as suggestions for the most economical transfer pumping systems suitable for the application. Several options are available for the pump station design: 1. Vertical line shaft axial flow, low head, high specific speed pumps with gear drives and electric motors as the prime movers. 2. Horizontal line shaft axial flow, low head, high specific speed pumps with gear drives and electric motors as the prime movers. 3. Vertical low head, high specific speed, line shaft axial pumps with submersible electric motors directly coupled and operating under water. 4. Horizontal line shaft axial flow, low head and high specific speed pumps with close coupled submersible electric motors as the drivers. 5. Horizontal line shaft axial flow, low head, high specific speed, axial flow pumps with hydraulic drives. The selection of the type of pump configuration impacts the layout and expense of the station. Vertical line shaft configurations require stations with elevated decks, specific design approach channels and load bearing decks and walls. The pump stations are designed based on Hydraulic Institute Standard recommendations and further verified with physical and numerical modeling. The decks support the gears and the drivers, with either diesel engines or electric motors being the most common. Another unique option available is the inline pumps, which eliminate the need for the conventional station altogether. However there are limits to the power input. These are very suitable for low head (water surface elevation differences between upstream and downstream side of the railroad tracks), high volume applications (4,550 CFs and 14,900 CFS), as in this case. 2

3 Using the electric motor eliminates the noise factor associated with the diesel equipment and is most suited to residential applications and for low head, large volume stations. Option 4 above is therefore the most economical choice, eliminating the need for a conventional station and using submersible electric motors, and meets the low-noise requirements of a residential neighborhood. The number of pumps and pump sizes described in this report at each of the creek crossings are approximated for the conveyance of the peak flow rate associated with the 100-year design storm event. During smaller storms and when the creek flow is less than the design peak flow, the number of pumps required to be operational will be less than the overall number of pumps provided at each of the crossings. The simultaneous operation of all pumps at a specific creek crossing will only rarely be required. 2.1 Types of Pumps The pumps most suited to the low head applications with large volumes of flow are high specific speed pumps. The specific speed is a type number and identifies the range of operation of different design pumps. Centrifugal pumps are low specific speed; the mixed flow pumps lie in the medium specific speed range; the axial flow pumps lie on the extreme high end range of the specific speed. The specific speed is defined as follows: Ns= Pump operating speed RPM Q= Rate of design flow in GPM H= Design Head in FT A large volume of flow and low heads would yield a high specific speed number. For axial flow pumps, the general range for the specific speed is 10,000 to 15,000 RPM. This application calls for a transfer of very large volumes against minimal heads caused by the water elevation difference between the suction and discharge sides of the system and losses through the transfer piping system. Because of the limits on the size of the pumps, several pumps of axial flow design would be required to handle the desired flow transfers. Electric motor drives would be used to minimize the noise impact on the neighborhood. The pumps used would be horizontal inline submersible electric pumps as shown on the exhibits in Appendix B. The design meets the unique requirement of the application and is ideally suited for inline application eliminating the need for a formal pump station, saving space and providing economic advantage in the process. 2.2 Submersible Electric Motors 3

4 The motors are designed for under water applications. The motors can effectively operate in a horizontal layout when adequately supported. The motors become a part of the pump bowl design and the water flows around the motor providing very effective cooling. The motors are directly coupled to the propeller through short shafts designed with seals to prevent leakage into the motor windings. Adequate alarms are provided to detect the presence of moisture in the motor windings. These motors also have bearings designed to take the thrust loads imposed by the propeller. 3.0 Osage Branch Creek Crossings 1 and 2 The following sections present the analysis for Osage 1 and 2 crossings. The total transfer rate is based on 4,550 CFS at each crossing with a minimal static lift. The head on the pump will include the losses though the piping and elbows and the dynamic losses. These total system losses are unknown at the moment and, therefore, are estimated. 3.1 General Analysis Submersible electric pumps installed in horizontal pipes of 96-inch to 120-inch diameter are proposed. These pumps can be installed in line with the pipeline, saving on the footprint of a pump station, as well as simplifying the installation and removal of the equipment without the use of very large cranes. A typical submersible electric pump cross-section is shown in Figure 1. The pumps become a part of the transfer pipe line. The pump consists of an axial flow pump suction, propeller, bowl and the submersible electric motor mounted to the bowl with appropriate supports and seals. The water flows over the motor providing all the cooling needed for the motor. Typical flow velocities around the motor are eight to 12 feet per second. Bearings in the motor take the thrust and provide alignment of the pump and motor shaft. Depending on the size of the motor available, theses pumps provide an ideal solution for low head applications, without the need for a formal pumping station. The pumps are non-intrusive and can be functional underground in the residential neighborhoods. Noise mitigation is provided by the use of electric power. Figure 1. Section of a typical Horizontal Submersible Electric Pump 4

5 The advantages of this type of arrangement are numerous and listed below: 1. Least installation costs 2. Ease of pump access 3. Ease of use 4. Low maintenance 5. The need for a pump support structure and approach channels are eliminated 6. The pump house can be designed to allow for the pumping unit to stay dry and offer access for maintenance. The power source can be assured. In residential situations, power supply from two independent grids allows for assurance of needed power supply during inclement weather. Capital costs for diesel generator back-up power at each pump station have also been included in the cost estimates as part of this report (see Section 5.0). The pumps will typically be operated with electric power made available by the local utility. A pump house for the starters and control equipment built above the flood zone would provide suitable housing for the controls. Suitable noise attenuation will be provided to minimize the sound levels. 3.2 Design Considerations for Each Station Design considerations for each pump station are summarized below. Total flow = 4,550 CFS = 2,042,040 GPM Proposed number of pumps = 7 Proposed Pump size = 96-inch Rate of flow for each pump = 291,720 GPM Proposed transfer pipe size = 96-inch to 120-inch No of pipes = 7 Expected velocity through each pipe = 8-12 feet/sec Expected head on the pump = 5 feet Expected min efficiency for the pump = 80% Expected motor horsepower for each pump = 500 HP = 375 KW Total power required = 3 MW for one station Total power required = 6 MW for two stations Exhibits 1 and 2 in Appendix B detail the concept. The pumps will be mounted in the pipe on the suction side of the tracks for ease of access, removal and reinstallation of pump units. Control valves shall be provided as needed to isolate the pumps in the piping systems. The estimated size of the building to house the control equipment is 40 feet long by 30 feet wide by 20 feet high. The estimated cost of equipment including the motors, controls and 5

6 pumps is $8-12 million. The estimated cost of making the power available at the site would be $1-2 million. This estimate does not include the building costs. It is possible to use fewer pumps of larger size, if available, to possibly reduce the costs. 3.3 Rough Estimate on Power to Sites Expected motor horsepower for each pump = 500 HP = 375 KW Total power required = 3 MW/ per station Total power required for two stations= 6 MW 3.4 Estimated Operating Costs per Year The following operating costs are based on a daily basis, meaning that the pumps run for 24 hours a day. The costs for monthly/annual expenses can be computed by estimating the number of expected operating days in a year. The power consumption per hour of operation for each station = 3 MW Estimated cost per MW = $70/MW Hour Daily operating costs = $5,040/ per station Daily operating costs for two stations = $10,800 per day Assuming operation for 50 days a year, the annual costs to operate two stations would be estimated at $540,000 Estimated annual maintenance costs for two stations are $800,000 Total estimated annual operating costs for Osage Crossings 1 and 2 = $1,340,000 It should be noted that this is considered a conservative estimate of the yearly operating requirements related to power consumption because, as described earlier, all pumps at each crossing will not typically be required to be operating simultaneously. Instead, less than the total number of pumps will be operating during many of the 50 days of the year mentioned above. At the same time, it is known that local electricity providers may require the owner to pay a year-round demand surcharge which compensates the provider for the act of making the peak power demand available at all times. The amount of this anticipated demand surcharge is currently unknown, so the above information has been used in this report for the purposes of calculating the operating cost estimate. Layouts, plan and elevation views for the Osage Branch crossings can be found in Appendix B Exhibits 1 and McKamy Branch Creek Crossing This section documents the analysis of the McKamy Branch Creek crossing. The total flow transfer is based on 14,900 CFS with a minimal static lift. The head on each pump will include 6

7 the losses though the piping and elbows and the dynamic losses. The total losses are unknown at the moment and, therefore, are estimated. 4.1 General Analysis Submersible electric pumps installed in horizontal pipes of 144-inch diameter are proposed. The advantages of this arrangement are numerous: 1. Least installation costs 2. Ease of pump access 3. Ease of use 4. Low maintenance 5. Assured power supply from two substations allows for dependable operation 6. The need for a pump support structure and approach channels are eliminated 7. The pump house can be designed to allow for the pumping unit to stay dry and available access for maintenance. The pumps will typically be operated with electric power to be made available by the local utility. A pump house for the starters and control equipment built above the flood zone would provide suitable housing for the controls. Suitable noise attenuation shall be provided to minimize the sound levels. 4.2 Design Considerations Design considerations for this pump station are summarized below. Total flow = 14,900 CFS = 6,687,120 GPM Proposed number of pumps = 24 Proposed pump size = 96-inch Rate of flow for each pump = 278,630 GPM = 620 CFS Proposed transfer pipe size = 144-inch No of pipes = 24 Expected velocity through the pipe = 5.5 feet/sec Expected head on the pump = 4 feet Expected minimum efficiency for the pump = 80% Expected motor horsepower for the pump = 400 = 300 KW Total power demand = 7.5 MW Exhibit 3 in Appendix B details the concept for this crossing. The pumps will be mounted in the pipes on the suction side of the tracks for ease of access, removal and reinstallation of pump units. Control valves shall be installed to isolate the pumps for ease of removal. The estimated size of the building to house the generators and control equipment is 60 feet long by 30 feet wide by 20 feet high. The estimated cost of equipment including the motors, 7

8 controls and pumps is $28-34 million. This estimate does not include the building costs. Estimated cost to make the necessary power available would be approximately $3-4 million. 4.3 Rough Estimate on Power to Site Expected motor horsepower for each pump = 400 HP = 300 KW Total power required = 7.2MW 4.4 Estimated Operating Costs per Year The following operating costs are based on a daily basis, meaning that the pumps run for 24 hours a day. The costs for monthly/annual expenses can be computed by estimating the number of expected operating days in a year. The power consumption per hour of operation for the station = 7.5 MW Estimated cost per MW = $70/MW Hour Daily operating costs = $12,600 per day Assuming operation for 50 days a year, the annual costs to operate the station would be estimated at $630,000 Estimated annual maintenance costs are $800,000 Total estimated annual operating costs for McKamy = $1,430,000 Total estimated annual operating costs for all three stations = $2.77 million Again, it should be noted that this is considered a conservative estimate of the yearly operating requirements related to power consumption of this facility. The layout, plan and elevation view for McKamy Branch Crossing can be found in Appendix B Exhibit 3. The current layout shows pumps stacked vertically in two rows in order to contain the proposed pump improvements within the modified horizontal limits of the channel. Although this configuration is believed to be possible, it may not necessarily be the most optimum layout. The final layout might include pump placement more strategically spread out on the upstream side of the crossing or still stacked vertically but offset for easier access. The final pump size might also be increased to possibly remove the need for stacking of some or all of the pumps. All conceptual pump layouts and sizes provided in this memorandum should be verified for feasibility and optimized for operational purposes during final design by using both physical and computational fluid dynamic (CFD) modeling analysis. 5.0 Opinion of Probable Construction Cost The estimated cost of construction presented in this section is organized in the Federal Transportation Administration (FTA) standard cost categories as detailed in Appendix C. 8

9 Osage #1 - $47,367,000 Osage #2 - $49,907,000 McKamy - $124,681,000 Associated railroad trench drainage $7,981,000 Diesel generator back-up for pump stations $55,178,000 Right-of-way and easement requirements - $3,000,000 Total capital costs for three pump stations and facilities = $288.1 million. 6.0 Environmental Issues 6.1 Water Resources U.S. Army Corps of Engineers would have jurisdiction over creeks and wetlands and would need to provide regulatory approval. Implementation of the pumps would result in substantial alteration to the watercourse beds and banks and riparian areas. Floodplain impacts would result, and the potential for downstream and upstream adverse effects would need to be considered. Due to the magnitude of the floodplain alterations, the process with the U.S. Army Corps of Engineers can be lengthy and no approval is guaranteed. 6.2 Aquatic Species There is the potential for negative impacts to aquatic life. 6.3 Vegetation/Wildlife Several acres of land would be cleared for construction of the pump station facilities. Land clearing would include removal of trees and other vegetation resulting in loss of habitat for wildlife. 7.0 Neighborhood Issues 7.1 Acquisitions and Displacements Installation of pump station facilities would result in property acquisitions and potential displacement of residents. Pump Stations would require several acres of land for ancillary buildings and parking areas. 7.2 Parkland/Section 4(f) Implementation of the Osage Branch #2 Pump Station would result in a property impact to Preston Green Park, a City of Dallas neighborhood park that features open space, a playground and a basketball court. Since this park is publicly owned, a statute known as Section 4(f) would apply. The statute provides protection to certain types of land and resources, such as 9

10 public parkland. Unless the use of Section 4(f) property is determined to have a de minimis impact, FTA must determine that no feasible and prudent alternative exists before approving the use of such land. 7.3 Visual Implementation of the pump stations would have an effect on the existing visual environmental. In addition to pumps being placed in the waterway, ancillary buildings would be required to house electrical equipment and maintenance supplies. 7.4 Noise and Air Quality The pump stations would produce noise associated with pumping activities. Sources of noise would include operating pump motors, generators and the sound of falling water. The implementation of the pump station would have the potential to emit air pollutants. Emissions from the pump motors or generators could produce carbon dioxide (CO 2 ). 7.5 Traffic/Parking Vehicle traffic to and from the pump station would be limited to trips associated with pump station maintenance and inspections. Each pump station would require a driveway and parking area to provide access. 8.0 Liability Issues The pumps could fail to function as designed due potentially to lack of proper maintenance or power outages which typically occur during major storm events. Failure of the pumps stations could result in flooding of the upstream properties, as well as the Cotton Belt passenger rail line. Public safety and life protection could be undermined. 9.0 Summary The above is a very preliminary development and analysis of a concept to convey storm water from the upstream side to the downstream side of the Cotton Belt in a deep trench configuration. The capital costs as well as the operating and maintenance costs are substantial, but are required under this option. A summary of rough order of magnitude cost elements are as follows: Annual operating costs - $2,770,000 Estimated capital costs (three pump stations and facilities) - $288,100,000 These costs are exclusive of the costs to place the alignment in the trench; these costs are only for the pumping requirements. Given the additional costs (both capital and annual operating), 10

11 DART developed a shallow trench option that eliminates the need for pumping. The shallow trench focuses on maintaining the natural environment and drainage systems as much as possible. The deep trench would significantly alter the natural setting and could affect wildlife and wetland habitats. More detailed development and analysis would be required to further evaluate the concept, specifically: Hydraulic backwater analysis for the creeks Physical and CFD analysis of pump layout and operation Possible pumping redundancy requirements to mitigate breakdown or emergencies Wetlands delineation and other environmental impacts Impacts to adjacent properties Easement and Right-of-Way requirements Impacts to proposed trail Regulatory and permitting requirements The design team has been evaluating several alignment alternatives in the North Dallas area. This memo has been developed in order to explore the costs involved in a deep trench alternative. The deep trench alternative, which requires pumping, is significantly more costly, both for construction and maintenance, than a shallow trench option. Additionally, the environmental impacts to the area could be substantial, and the potential risks and liability could undermine public safety. It is our professional opinion that pursuing an alternative that requires the placement of pump stations in fully developed residential areas is not in the best interest of the public. 11

12 Appendix A Existing Creek Condition Photos

13 Osage Branch crossing #1 panoramic view looking east at downstream face of RR bridge

14 Osage Branch crossing #1 looking north at upstream face of RR bridge

15 Osage Branch crossing #2 looking at downstream face of RR crossing, panoramic view spanning from looking northeast to looking southwest (Wing wall at bottom of picture is actually straight, distortion due to panoramic view see aerial)

16 Osage Branch crossing #2 panoramic view looking southwest at the upstream face of the RR crossing

17 McKamy Branch - looking north at downstream face of RR bridge

18 McKamy Branch panoramic view looking southeast at upstream face of RR bridge

19 Appendix B Conceptual Pump Layout Exhibits

20

21

22

23 Appendix C Rough Order of Magnitude Capital Cost Estimates for Three Pump Stations

24 DART - Cotton Belt Regional Rail North Dallas Trench Option Pump Stations Rough Order of Magnitude Cost Estimate Estimate prepared by URS Date of Estimate : 12/22/2011 Osage Branch Crossing #1 Pump Station UoM Quanity Unit Price Amount Comments Earthwork Channel CY 80,000 $ $ 800,000 Clearing and grubbing of channel and work sites Tree/Wetlands Mitigation SF 261,360 $ 3.00 $ 784,080 6 acres = 6 x sf = SF Headworks concrete w/ trash racks CY 175 $ $ 87,500 concrete cost - depends on # of pipes Outlet works concrete w/ trash racks CY 175 $ $ 87,500 concrete cost - depends on # of pipes " subm. Elec. Pump EA 7 $ 1,300, $ 9,100,000 7 each 96" sbm. Elec. Pumps incl. 1 generator per pump Structural excavation Pipe & Pump Str. CY 11,167 $ $ 256, '+56' long x 150' wide x depth 10' for pipe and pump house Concrete Pipe, Prestressed (PCCP), 150,PSI, 96" LF 1015 $ $ 959,175 96" Pipe Structural excavation Power & Control Rm CY 444 $ $ 10,222 80' long x 30' wide x depth 5' for Power & Control Rm Stone Gabion Retaining Walls SY 2,070 $ $ 322,920 Gabion Box Systems,Gabions, galvanized steel mesh mats or boxes, stone filled Pump house 146'x56' + foundation SF 8,176 $ $ 5,723,200 $200/sf building + $500/sf foundation Power & Control House 80'x30' + foundation SF 2,400 $ $ 1,680,000 $200/sf building + $500/sf foundation Siphon / Environmental Flow Conduits LS 1 $ 100, $ 100,000 Siphon and conduits for einvironmental / low flow purposes Bring Electrical Power to Station AL 1 $ 1,000, $ 1,000,000 Osage Branch Crossing #1 Pump Station - Sub Total $ 20,911, % Contractor General Conditions % 30% (Subtotal of Amounts) $ 6,273, =(0.30 x subtotal) = A DART Add-On Allowance Contingencies % 32% (Subtotal of Amounts) $ 8,699, =(0.32 x [A+subtotal])=B Allocated Contingency % 20% (Subtotal of Amounts) $ 7,176, =(0.20 x [A+B+subtotal])=C Unallocated Contingency % 10% (Subtotal of Amounts) $ 4,306, =(0.10 x [A+B+C+subtotal]) Osage Branch Crossing #1 Pump Station - Total $ 47,366,900 Osage Branch Crossing #2 Pump Station UoM Quanity Unit Price Amount Comments Earthwork Channel CY 50,000 $ $ 500,000 Clearing and grubbing of channel and work sites Tree/Wetlands Mitigation SF 261,360 $ 3.00 $ 784,080 6 acres = 6 x sf = SF Headworks concrete w/ trash racks CY 175 $ $ 87,500 concrete cost - depends on # of pipes Outlet works concrete w/ trash racks CY 175 $ $ 87,500 concrete cost - depends on # of pipes " subm. Elec. Pump EA 7 $ 1,300, $ 9,100,000 7 each 96" sbm. Elec. Pumps incl. 1 generator per pump Structural excavation Pipe & Pump Str. CY 19,500 $ $ 448, '+56' long x 150' wide x depth 10' for pipe and pump house Concrete Pipe, Prestressed (PCCP), 150,PSI, 96" LF 2455 $ $ 2,319,975 96" Pipe Structural excavation Power & Control Rm CY 667 $ $ 15, ' long x 30' wide x depth 5' for Power & Control Rm Stone Gabion Retaining Walls SY 3,583 $ $ 558,948 Gabion Box Systems,Gabions, galvanized steel mesh mats or boxes, stone filled Pump house 156'x49' + foundation SF 7,644 $ $ 5,350,800 $200/sf building + $500/sf foundation Power & Control House 80'x30' + foundation SF 2,400 $ $ 1,680,000 $200/sf building + $500/sf foundation Siphon / Environmental Flow Conduits LS 1 $ 100, $ 100,000 Siphon and conduits for einvironmental / low flow purposes Bring Electrical Power to Station AL 1 $ 1,000, $ 1,000,000 Osage Branch Crossing #2 Pump Station - Sub Total $ 22,032, % Contractor General Conditions % 30% (Subtotal of Amounts) $ 6,609, =(0.30 x subtotal) = A DART Add-On Allowance Contingencies % 32% (Subtotal of Amounts) $ 9,165, =(0.32 x [A+subtotal])=B Allocated Contingency % 20% (Subtotal of Amounts) $ 7,561, =(0.20 x [A+B+subtotal])=C Unallocated Contingency % 10% (Subtotal of Amounts) $ 4,536, =(0.10 x [A+B+C+subtotal]) Osage Branch Crossing #2 Pump Station - Total $ 49,906,565 McKamy Branch Pump Station UoM Quanity Unit Price Amount Comments Earthwork Channel CY 150,000 $ $ 1,500,000 Clearing and grubbing of channel and work sites Rock Environment Tree/Wetlands Mitigation SF 409,464 $ 3.00 $ 1,228, acres Headworks concrete w/ trash racks CY 720 $ $ 360,000 concrete cost - depends on # of pipes Outlet works concrete w/ trash racks CY 720 $ $ 360,000 concrete cost - depends on # of pipes " subm. Elec. Pump EA 24 $ 1,300, $ 31,200, each 96" sbm. Elec. Pumps incl. valves Structural excavation Pipe & Pump Str. CY 38,400 $ $ 883,200 For pipe and pump house Concrete Pipe, Prestressed (PCCP), 150,PSI, 144" LF 3,840 $ 1, $ 7,584, " Pipe Structural excavation Power & Control Rm CY 694 $ $ 15,962 Power & Control Rm Stone Gabion Retaining Walls SY 2,333 $ $ 363,948 Gabion Box Systems,Gabions, galvanized steel mesh mats or boxes, stone filled Pump house + foundation SF 8,176 $ $ 5,723,200 $200/sf building + $500/sf foundation Power & Control House + foundation SF 3,750 $ $ 2,625,000 $200/sf building + $500/sf foundation Siphon / Environmental Flow Conduits LS 1 $ 200, $ 200,000 Siphon and conduits for einvironmental / low flow purposes Bring Electrical Power to Station AL 1 $ 3,000, $ 3,000,000 McKamy Branch Pump Station - Sub Total $ 55,043, % Contractor General Conditions % 30% (Subtotal of Amounts) $ 16,513, =(0.30 x subtotal) = A

25 DART - Cotton Belt Regional Rail North Dallas Trench Option Pump Stations Rough Order of Magnitude Cost Estimate Estimate prepared by URS Date of Estimate : 12/22/2011 DART Add-On Allowance Contingencies % 32% (Subtotal of Amounts) $ 22,898, =(0.32 x [A+subtotal])=B Allocated Contingency % 20% (Subtotal of Amounts) $ 18,890, =(0.20 x [A+B+subtotal])=C Unallocated Contingency % 10% (Subtotal of Amounts) $ 11,334, =(0.10 x [A+B+C+subtotal]) McKamy Branch Pump Station - Total $ 124,680,590 Rail Trench Drainage UoM Quanity Unit Price Amount Comments Earthwork Channel CY 5,000 $ $ 50,000 Clearing and grubbing of channel and work sites Rock Environment Tree/Wetlands Mitigation SF 50,000 $ 3.00 $ 150, acres Rail Trench Drainage - Headworks concrete w/ trash racks CY 75 $ $ 37,500 concrete cost - depends on # of pipes Rail Trench Drainage - Outlet works concrete w/ trash racks CY 75 $ $ 37,500 concrete cost - depends on # of pipes Rail Trench Drainage - 96" subm. Elec. Pump EA 1 $ 1,300, $ 1,300,000 1 each 96" sbm. Elec. Pumps incl. valves Rail Trench Drainage - Structural excavation Pipe & Pump Str. CY 250 $ $ 5,750 For pipe and pump house Rail Trench Drainage - Concrete Pipe, Prestressed (PCCP), 150,PSI, 96" LF 100 $ $ 94,500 96" Pipe Rail Trench Drainage - Pump house + foundation SF 1,100 $ $ 770,000 $200/sf building + $500/sf foundation Stone Gabion Retaining Walls SY 500 $ $ 78,000 Gabion Box Systems,Gabions, galvanized steel mesh mats or boxes, stone filled Bring Electrical Power to Station AL 1 $ 1,000, $ 1,000,000 Trench Drain - Sub Total $ 3,523, % Contractor General Conditions % 30% (Subtotal of Amounts) $ 1,056, =(0.30 x subtotal) = A DART Add-On Allowance Contingencies % 32% (Subtotal of Amounts) $ 1,465, =(0.32 x [A+subtotal])=B Allocated Contingency % 20% (Subtotal of Amounts) $ 1,209, =(0.20 x [A+B+subtotal])=C Unallocated Contingency % 10% (Subtotal of Amounts) $ 725, =(0.10 x [A+B+C+subtotal]) Rail Trench Drainage - Total $ 7,980,584 Diesel Generator Backup for Pump Stations UoM Quanity Unit Price Amount Comments Clearing and grubbing of work site SF 50,000 $ 3.00 $ 150, acres Diesel Generator Building SF 24,750 $ $ 17,325,000 $200/sf building + $500/sf foundation (90' x 275') Diesel Powered Generator EA 1 $ 201, $ 201, kW Cummings Powered Diesel Generator Diesel Powered Generator EA 9 $ 456, $ 4,104, kW Cummings Powered Diesel Generator Diesel Fuel Storage Tank - 24 Full load Hrs EA 1 $ 100, $ 100,000 Horizontal,steel,double wall,above ground Fuel Storage Tank - 32,000 gallon capacity = 24 Full load Hrs Foundation for Diesel Storage tank SF 1,600 $ $ 480,000 $300/sf foundation Underground Power feed to Pump, Control from Back-up DG LS 1 $ 1,000, $ 1,000, Bring Electrical Power to Station AL 1 $ 1,000, $ 1,000,000 Diesel Generator Backup for Pump Stations - Sub Total $ 24,360, % Contractor General Conditions % 30% (Subtotal of Amounts) $ 7,308,000 =(0.30 x subtotal) = A DART Add-On Allowance Contingencies % 32% (Subtotal of Amounts) $ 10,133, =(0.32 x [A+subtotal])=B Allocated Contingency % 20% (Subtotal of Amounts) $ 8,360, =(0.20 x [A+B+subtotal])=C Unallocated Contingency % 10% (Subtotal of Amounts) $ 5,016, =(0.10 x [A+B+C+subtotal]) Diesel Generator Backup for Pump Stations - Total $ 55,178,323 Right-of-Way and Easement Requirements UoM Quanity Unit Price Amount Comments Right-of-Way and Easement Requirements LS 1 $ 3,000, $ 3,000,000 Right-of-Way and Easement Requirements - Total $ 3,000,000 Summary Amount Osage Branch Crossing #1 Pump Station - Total $ 47,366,900 Osage Branch Crossing #2 Pump Station - Total $ 49,906,565 McKamy Branch Pump Station - Total $ 124,680,590 Rail Trench Drainage - Total $ 7,980,584 Diesel Generator Backup for Pump Stations - Total $ 55,178,323 Right-of-Way and Easement Requirements - Total $ 3,000,000 Total $ 288,112,962

26 M A I N W O R K S H E E T - ROUGH ORDER OF MAGNITUDE COST ESTIMATE (Rev.13, June 1, 2010) DART - Cotton Belt Regional Rail Today's Date 12/22/11 North Dallas Trench Option Yr of $ 2011 Osage Branch Crossing #1 Pump Station Estimate Prepared by URS Yr of Revenue Ops Quantity w/o Contingency Allocated Contingency TOTAL Unit Cost Percentage of Construction Cost Percentage of Total Project Cost YOE Total 10 GUIDEWAY & TRACK ELEMENTS (route miles) $ - 0% 0% Guideway: At-grade exclusive right-of-way Guideway: At-grade semi-exclusive (allows cross-traffic) Guideway: At-grade in mixed traffic Guideway: Aerial structure Guideway: Built-up fill Guideway: Underground cut & cover Guideway: Underground tunnel Guideway: Retained cut or fill Track: Direct fixation Track: Embedded Track: Ballasted Track: Special (switches, turnouts) Track: Vibration and noise dampening STATIONS, STOPS, TERMINALS, INTERMODAL (number) $ - 0% 0% At-grade station, stop, shelter, mall, terminal, platform Aerial station, stop, shelter, mall, terminal, platform Underground station, stop, shelter, mall, terminal, platform Other stations, landings, terminals: Intermodal, ferry, trolley, etc Joint development Automobile parking multi-story structure Elevators, escalators SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $ - 0% 0% Administration Building: Office, sales, storage, revenue counting Light Maintenance Facility Heavy Maintenance Facility Storage or Maintenance of Way Building Yard and Yard Track SITEWORK & SPECIAL CONDITIONS ,185 5,437 32,622 $ - 100% 0% 32, Demolition, Clearing, Earthwork Site Utilities, Utility Relocation 1, ,200 1, Haz. mat'l, contam'd soil removal/mitigation, ground water treatments Environmental mitigation, e.g. wetlands, historic/archeologic, parks Site structures including retaining walls, sound walls 18,327 3,665 21,993 21, Pedestrian / bike access and accommodation, landscaping Automobile, bus, van accessways including roads, parking lots Temporary Facilities and other indirect costs during construction 6,273 1,255 7,528 7, SYSTEMS $ - 0% 0% Train control and signals Traffic signals and crossing protection Traction power supply: substations Traction power distribution: catenary and third rail Communications Fare collection system and equipment Central Control Construction Subtotal (10-50) ,185 5,437 32,622 $ - 100% 0% 32, ROW, LAND, EXISTING IMPROVEMENTS $ - 0% Purchase or lease of real estate Relocation of existing households and businesses VEHICLES (number) $ - 0% Light Rail Heavy Rail Commuter Rail Bus Other Non-revenue vehicles Spare parts PROFESSIONAL SERVICES (applies to Cats ) ,699 1,740 10,439 $ - 32% 0% 10, Preliminary Engineering % Final Design 2, , % 3, Project Management for Design and Construction 2, , % 2, Construction Administration & Management 1, , % 2, Professional Liability and other Non-Construction Insurance , % 1, Legal; Permits; Review Fees by other agencies, cities, etc % Surveys, Testing, Investigation, Inspection % Start up % 0 Subtotal (10-80) ,884 7,177 43,061 $ - 0% 43, UNALLOCATED CONTINGENCY 4,306 0% 4, Contingency 3, ,306 Subtotal (10-90) ,367 $ - 0% 47, FINANCE CHARGES 0 0% 0 Total Project Cost (10-100) ,367 $ - 0% 47,367 Allocated Contingency as % of Base Yr w/o Contingency 20.00% Unallocated Contingency as % of Base Yr w/o Contingency 12.00% Total Contingency as % of Base Yr w/o Contingency 32.00% Unallocated Contingency as % of Subtotal (10-80) 10.00% YOE Construction Cost per Mile $0 YOE Total Project Cost per Mile Not Including Vehicles $0 YOE Total Project Cost per Mile $0

27 M A I N W O R K S H E E T - ROUGH ORDER OF MAGNITUDE COST ESTIMATE (Rev.13, June 1, 2010) DART - Cotton Belt Regional Rail Today's Date 12/22/11 North Dallas Trench Option Yr of $ 2011 Osage Branch Crossing #2 Pump Station Estimate Prepared by URS Yr of Revenue Ops Quantity w/o Contingency Allocated Contingency TOTAL Unit Cost Percentage of Construction Cost Percentage of Total Project Cost YOE Total 10 GUIDEWAY & TRACK ELEMENTS (route miles) $ - 0% 0% Guideway: At-grade exclusive right-of-way Guideway: At-grade semi-exclusive (allows cross-traffic) Guideway: At-grade in mixed traffic Guideway: Aerial structure Guideway: Built-up fill Guideway: Underground cut & cover Guideway: Underground tunnel Guideway: Retained cut or fill Track: Direct fixation Track: Embedded Track: Ballasted Track: Special (switches, turnouts) Track: Vibration and noise dampening STATIONS, STOPS, TERMINALS, INTERMODAL (number) $ - 0% 0% At-grade station, stop, shelter, mall, terminal, platform Aerial station, stop, shelter, mall, terminal, platform Underground station, stop, shelter, mall, terminal, platform Other stations, landings, terminals: Intermodal, ferry, trolley, etc Joint development Automobile parking multi-story structure Elevators, escalators SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $ - 0% 0% Administration Building: Office, sales, storage, revenue counting Light Maintenance Facility Heavy Maintenance Facility Storage or Maintenance of Way Building Yard and Yard Track SITEWORK & SPECIAL CONDITIONS ,642 5,728 34,371 $ - 100% 0% 34, Demolition, Clearing, Earthwork Site Utilities, Utility Relocation 1, ,200 1, Haz. mat'l, contam'd soil removal/mitigation, ground water treatments Environmental mitigation, e.g. wetlands, historic/archeologic, parks Site structures including retaining walls, sound walls 19,749 3,950 23,698 23, Pedestrian / bike access and accommodation, landscaping Automobile, bus, van accessways including roads, parking lots Temporary Facilities and other indirect costs during construction 6,610 1,322 7,932 7, SYSTEMS $ - 0% 0% Train control and signals Traffic signals and crossing protection Traction power supply: substations Traction power distribution: catenary and third rail Communications Fare collection system and equipment Central Control Construction Subtotal (10-50) ,642 5,728 34,371 $ - 100% 0% 34, ROW, LAND, EXISTING IMPROVEMENTS $ - 0% Purchase or lease of real estate Relocation of existing households and businesses VEHICLES (number) $ - 0% Light Rail Heavy Rail Commuter Rail Bus Other Non-revenue vehicles Spare parts PROFESSIONAL SERVICES (applies to Cats ) ,166 1,833 10,999 $ - 32% 0% 10, Preliminary Engineering % Final Design 2, , % 3, Project Management for Design and Construction 2, , % 2, Construction Administration & Management 2, , % 2, Professional Liability and other Non-Construction Insurance 1, , % 1, Legal; Permits; Review Fees by other agencies, cities, etc % Surveys, Testing, Investigation, Inspection % Start up % 0 Subtotal (10-80) ,808 7,562 45,370 $ - 0% 45, UNALLOCATED CONTINGENCY 4,537 0% 4, Contingency 3, ,537 Subtotal (10-90) ,907 $ - 0% 49, FINANCE CHARGES 0 0% 0 Total Project Cost (10-100) ,907 $ - 0% 49,907 Allocated Contingency as % of Base Yr w/o Contingency 20.00% Unallocated Contingency as % of Base Yr w/o Contingency 12.00% Total Contingency as % of Base Yr w/o Contingency 32.00% Unallocated Contingency as % of Subtotal (10-80) 10.00% YOE Construction Cost per Mile $0 YOE Total Project Cost per Mile Not Including Vehicles $0 YOE Total Project Cost per Mile $0

28 M A I N W O R K S H E E T - ROUGH ORDER OF MAGNITUDE COST ESTIMATE (Rev.13, June 1, 2010) DART - Cotton Belt Regional Rail Today's Date 12/22/11 North Dallas Trench Option Yr of $ 2011 McKamy Branch Pump Station Estimate Prepared by URS Yr of Revenue Ops Quantity w/o Contingency Allocated Contingency TOTAL Unit Cost Percentage of Construction Cost Percentage of Total Project Cost YOE Total 10 GUIDEWAY & TRACK ELEMENTS (route miles) $ - 0% 0% Guideway: At-grade exclusive right-of-way Guideway: At-grade semi-exclusive (allows cross-traffic) Guideway: At-grade in mixed traffic Guideway: Aerial structure Guideway: Built-up fill Guideway: Underground cut & cover Guideway: Underground tunnel Guideway: Retained cut or fill Track: Direct fixation Track: Embedded Track: Ballasted Track: Special (switches, turnouts) Track: Vibration and noise dampening STATIONS, STOPS, TERMINALS, INTERMODAL (number) $ - 0% 0% At-grade station, stop, shelter, mall, terminal, platform Aerial station, stop, shelter, mall, terminal, platform Underground station, stop, shelter, mall, terminal, platform Other stations, landings, terminals: Intermodal, ferry, trolley, etc Joint development Automobile parking multi-story structure Elevators, escalators SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $ - 0% 0% Administration Building: Office, sales, storage, revenue counting Light Maintenance Facility Heavy Maintenance Facility Storage or Maintenance of Way Building Yard and Yard Track SITEWORK & SPECIAL CONDITIONS ,557 14,311 85,868 $ - 100% 0% 85, Demolition, Clearing, Earthwork 1, ,800 1, Site Utilities, Utility Relocation 3, ,600 3, Haz. mat'l, contam'd soil removal/mitigation, ground water treatments Environmental mitigation, e.g. wetlands, historic/archeologic, parks 1, ,474 1, Site structures including retaining walls, sound walls 49,315 9,863 59,178 59, Pedestrian / bike access and accommodation, landscaping Automobile, bus, van accessways including roads, parking lots Temporary Facilities and other indirect costs during construction 16,513 3,303 19,816 19, SYSTEMS $ - 0% 0% Train control and signals Traffic signals and crossing protection Traction power supply: substations Traction power distribution: catenary and third rail Communications Fare collection system and equipment Central Control Construction Subtotal (10-50) ,557 14,311 85,868 $ - 100% 0% 85, ROW, LAND, EXISTING IMPROVEMENTS $ - 0% Purchase or lease of real estate Relocation of existing households and businesses VEHICLES (number) $ - 0% Light Rail Heavy Rail Commuter Rail Bus Other Non-revenue vehicles Spare parts PROFESSIONAL SERVICES (applies to Cats ) ,898 4,580 27,478 $ - 32% 0% 27, Preliminary Engineering % Final Design 7,299 1,460 8, % 8, Project Management for Design and Construction 5,796 1,159 6, % 6, Construction Administration & Management 5,009 1,002 6, % 6, Professional Liability and other Non-Construction Insurance 2, , % 3, Legal; Permits; Review Fees by other agencies, cities, etc % Surveys, Testing, Investigation, Inspection 1, , % 1, Start up % 0 Subtotal (10-80) ,455 18, ,346 $ - 0% 113, UNALLOCATED CONTINGENCY 11,335 0% 11, Contingency 9,445 1,889 11,335 Subtotal (10-90) ,681 $ - 0% 124, FINANCE CHARGES 0 0% 0 Total Project Cost (10-100) ,681 $ - 0% 124,681 Allocated Contingency as % of Base Yr w/o Contingency 20.00% Unallocated Contingency as % of Base Yr w/o Contingency 12.00% Total Contingency as % of Base Yr w/o Contingency 32.00% Unallocated Contingency as % of Subtotal (10-80) 10.00% YOE Construction Cost per Mile $0 YOE Total Project Cost per Mile Not Including Vehicles $0 YOE Total Project Cost per Mile $0

29 M A I N W O R K S H E E T - ROUGH ORDER OF MAGNITUDE COST ESTIMATE (Rev.13, June 1, 2010) DART - Cotton Belt Regional Rail Today's Date 12/22/11 North Dallas Trench Option Yr of $ 2011 Rail Trench Drainage Estimate Prepared by URS Yr of Revenue Ops Quantity w/o Contingency Allocated Contingency TOTAL Unit Cost Percentage of Construction Cost Percentage of Total Project Cost YOE Total 10 GUIDEWAY & TRACK ELEMENTS (route miles) $ - 0% 0% Guideway: At-grade exclusive right-of-way Guideway: At-grade semi-exclusive (allows cross-traffic) Guideway: At-grade in mixed traffic Guideway: Aerial structure Guideway: Built-up fill Guideway: Underground cut & cover Guideway: Underground tunnel Guideway: Retained cut or fill Track: Direct fixation Track: Embedded Track: Ballasted Track: Special (switches, turnouts) Track: Vibration and noise dampening STATIONS, STOPS, TERMINALS, INTERMODAL (number) $ - 0% 0% At-grade station, stop, shelter, mall, terminal, platform Aerial station, stop, shelter, mall, terminal, platform Underground station, stop, shelter, mall, terminal, platform Other stations, landings, terminals: Intermodal, ferry, trolley, etc Joint development Automobile parking multi-story structure Elevators, escalators SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $ - 0% 0% Administration Building: Office, sales, storage, revenue counting Light Maintenance Facility Heavy Maintenance Facility Storage or Maintenance of Way Building Yard and Yard Track SITEWORK & SPECIAL CONDITIONS , ,496 $ - 100% 0% 5, Demolition, Clearing, Earthwork Site Utilities, Utility Relocation 1, ,200 1, Haz. mat'l, contam'd soil removal/mitigation, ground water treatments Environmental mitigation, e.g. wetlands, historic/archeologic, parks Site structures including retaining walls, sound walls 2, ,788 2, Pedestrian / bike access and accommodation, landscaping Automobile, bus, van accessways including roads, parking lots Temporary Facilities and other indirect costs during construction 1, ,268 1, SYSTEMS $ - 0% 0% Train control and signals Traffic signals and crossing protection Traction power supply: substations Traction power distribution: catenary and third rail Communications Fare collection system and equipment Central Control Construction Subtotal (10-50) , ,496 $ - 100% 0% 5, ROW, LAND, EXISTING IMPROVEMENTS $ - 0% Purchase or lease of real estate Relocation of existing households and businesses VEHICLES (number) $ - 0% Light Rail Heavy Rail Commuter Rail Bus Other Non-revenue vehicles Spare parts PROFESSIONAL SERVICES (applies to Cats ) , ,759 $ - 32% 0% 1, Preliminary Engineering % Final Design % Project Management for Design and Construction % Construction Administration & Management % Professional Liability and other Non-Construction Insurance % Legal; Permits; Review Fees by other agencies, cities, etc % Surveys, Testing, Investigation, Inspection % Start up % 0 Subtotal (10-80) ,046 1,209 7,255 $ - 0% 7, UNALLOCATED CONTINGENCY 726 0% Contingency Subtotal (10-90) ,981 $ - 0% 7, FINANCE CHARGES 0 0% 0 Total Project Cost (10-100) ,981 $ - 0% 7,981 Allocated Contingency as % of Base Yr w/o Contingency 20.00% Unallocated Contingency as % of Base Yr w/o Contingency 12.00% Total Contingency as % of Base Yr w/o Contingency 32.00% Unallocated Contingency as % of Subtotal (10-80) 10.00% YOE Construction Cost per Mile $0 YOE Total Project Cost per Mile Not Including Vehicles $0 YOE Total Project Cost per Mile $0

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative PRELIMINARY ORDER OF MAGNITUDE CAPITAL COST ESTIMATING METHODOLOGY Technical Memorandum December 2011 Prepared for: Metropolitan Atlanta Rapid Transit Authority Atlanta, GA

More information

Durham-Orange County Corridor Alternatives Analysis JULY Prepared by: U R S Team

Durham-Orange County Corridor Alternatives Analysis JULY Prepared by: U R S Team Durham-Orange County Corridor Alternatives Analysis Volume 3: Capital Cost Estimates Operations and Maintenance Cost Estimates Travel Time and Distance Calculations Ridership Summaries and Station to Station

More information

NJ TRANSIT West Trenton Rail Line Passenger Service Rail Study West Trenton, NJ to Manville, NJ 10/26/2007 PREFERRED ALTERNATIVE CAPITAL COST ESTIMATE

NJ TRANSIT West Trenton Rail Line Passenger Service Rail Study West Trenton, NJ to Manville, NJ 10/26/2007 PREFERRED ALTERNATIVE CAPITAL COST ESTIMATE NJ TRANSIT West Trenton Rail Line Passenger Service Rail Study West Trenton, NJ to Manville, NJ 10/26/2007 PREFERRED ALTERNATIVE CAPITAL COST ESTIMATE Table of Contents FTA Main Worksheet.................................................

More information

Cost to extending KC Streetcar north approximately ½ mile

Cost to extending KC Streetcar north approximately ½ mile Technical Memorandum September 22, 2015 Attention: Jason Waldron, PE From: Lucas L. Olson, PE; Cory Imhoff, PE RE: Cost to extending KC Streetcar north approximately ½ mile HDR was asked for their opinion

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL No. 2015-44 DATE: October 16, 2015 TO: FROM: Technical Advisory Committee TAC Funding and Programming Committee

More information

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014 TBARTA USF to Wesley Chapel Express Bus Service Operating Plan Draft 3/25/2014 March 2014 Table of Contents 1.0 Introduction... 1 2.0 Study Area... 1 3.0 Existing Available Service... 3 4.0 Proposed Service...

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension

Appendix C. 5% Design Plan and Profile Drawings/ Additional Design Information. South Oak Cliff Corridor Blue Line Extension Appendix C 5% Design Plan and Profile Drawings/ Additional Design Information The 5% plan and profile drawings were provided in a separate volume with the Draft Local EA and have not changed. Hard copies

More information

WEST CONTRA COSTA HIGH-CAPACITY TRANSIT STUDY TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE

WEST CONTRA COSTA HIGH-CAPACITY TRANSIT STUDY TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE PRELIMINARY ESTIMATE OF PROBABLE CONSTRUCTION COST (AN OPINION OF PROBABLE CONSTRUCTION COST) BASED ON DRAFT TM #11 ALTERNATIVE REFINEMENT

More information

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented

More information

4.2 Series Station Option Description

4.2 Series Station Option Description 4.2 Series Station Option Description The series station proposal features a new set of side platforms constructed approximately 250 feet north of the existing platforms. The two new platforms would extend

More information

Treasure Island Mobility Management Program

Treasure Island Mobility Management Program Treasure Island Mobility Management Program Preliminary Toll Policy Recommendations For Buildout Year (2030) Draft TIDA CAB June 2, 2015 About the Treasure Island Mobility Management Program 2003 2008

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

Appendix E: Basis for Comparative Cost Analysis

Appendix E: Basis for Comparative Cost Analysis DRAFT Technical Report RAILYARD ALIGNMENT AND BENEFITS STUDY Appendix E: Basis for Comparative Cost Analysis Estimated Probable Construction Costs DTX Future with Surface Rail (2026) Pennsylvania Avenue

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV-- 0 0 TESTIMONY OF DAVID M. CAMPILII,

More information

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street

More information

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E. (Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

17.8 acres site 4.6 acres in floodplain & wetlands 3.5 acres of surface parking 9 acres of open space

17.8 acres site 4.6 acres in floodplain & wetlands 3.5 acres of surface parking 9 acres of open space Peter Allen Associates, Inc. Nederveld, Inc. Ann Arbor/Grand Rapids Riverfront Village LLC 17.8 acres site 4.6 acres in floodplain & wetlands 3.5 acres of surface parking 9 acres of open space 17,000 Hospital

More information

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital Needs Assessment Riders Advisory Council July2, 2008 Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair

More information

Schematic Layout Development

Schematic Layout Development Schematic Layout Development Northeast Hangar Area Manassas Regional Airport Manassas, Virginia November 2015 Introduction In response to the continuing development demand at Manassas Regional Airport,

More information

Public Information Centre

Public Information Centre Junction Street Wastewater Pumping Station & Forcemain Schedule B Municipal Class Environmental Assessment Study Public Information Centre June 28, 2017. 6:00 to 8:00 pm. The Burlington Performing Arts

More information

Appendix C Capital Improvement Program Project Descriptions and Details

Appendix C Capital Improvement Program Project Descriptions and Details Appendix C Capital Improvement Program Project Descriptions and Details GIG HARBOR WW COMP PLAN DRAFT CAPITAL IMPROVEMENT PROGRAM LIFT STATION COST ESTIMATE Lift Station 1 Item Qty Units Unit Cost Extended

More information

TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County. February 26, 2018

TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County. February 26, 2018 TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County February 26, 2018 Agenda Review Committee Purpose Review Project Map Discuss Service Alternatives Capital Costs (Stations, Track,

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information

Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014

Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014 Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing July 24, 2014 Project Description The Central City Line is a High Performance Transit project that will extend from Browne

More information

GENERAL PLANNING GUIDELINES MULTI-BAY CAR WASH

GENERAL PLANNING GUIDELINES MULTI-BAY CAR WASH GENERAL PLANNING GUIDELINES MULTI-BAY CAR WASH Information to be considered when planning your Multi-Bay Car Wash. The information presented id for a 4 6 bay coin operated car wash. It is based on past

More information

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019.

Schedule Based on the City of Los Angeles, the District should be formed by April 2016 to allow the design and construction to be complete by 2019. EXECUTIVE SUMMARY PURPOSE To report the findings of the Feasibility Study for an Underground Utility District along Segment C of the proposed Park to Playa Trail. BACKGROUND The City of Los Angeles Department

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

Memorandum October 5, 2017

Memorandum October 5, 2017 614 Magnolia Avenue Ocean Springs, Mississippi 39564 228.818.9626 Memorandum October 5, 2017 To: Gary Miller, U.S. Environmental Protection Agency From: David Keith, John Laplante, Matt Henderson, and

More information

Appendix G Aquilla Lake Pool Rise Recreational Resources

Appendix G Aquilla Lake Pool Rise Recreational Resources Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee 05.28.09 09 Bridge Type - Cost Vertical Clearance Bicycle Pedestrian Path Width Bridge Type - Cost WRBAC

More information

Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM

Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM This chapter presents the proposed Capital Improvement Program (CIP) for the District based on the findings of this Master Plan. The Master Plan primarily

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

PROPOSAL OF HIGH CAPACITY URBANAUT PUGET SOUND REGIONAL MONORAIL MASTERPLAN WASHINGTON STATE, USA

PROPOSAL OF HIGH CAPACITY URBANAUT PUGET SOUND REGIONAL MONORAIL MASTERPLAN WASHINGTON STATE, USA PROPOSAL OF HIGH CAPACITY URBANAUT PUGET SOUND REGIONAL MONORAIL MASTERPLAN WASHINGTON STATE, USA Not to be copied in part without reference to author Urbanaut Company Inc. Monorail Tel: 425 434-6570 Fax:

More information

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7 Presentation Tappan Zee Bridge/I-287 Corridor Environmental Review December 4, 2008 Slide 1 Title Slide Slide 2 This presentation discusses the contents of the Transit Mode Selection Report. Slide 3 The

More information

The purpose of this project is to replace the influent screens and screenings handling equipment.

The purpose of this project is to replace the influent screens and screenings handling equipment. Headworks Screening Project Purpose: The purpose of this project is to replace the influent screens and screenings handling equipment. Project History and Status: Constructed as part of the Plant s Tenth

More information

FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST)

FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST) FRESNO COUNTY SUBSECTION OF THE CALIFORNIA HIGH- SPEED TRAIN (HST) The Fresno County subsection of the California High- Speed Train System (HST) is analyzed in two separate EIR/EISs the Merced-Fresno EIR/EIS

More information

JCP&L Verbatim Response to Middletown Township s Questions

JCP&L Verbatim Response to Middletown Township s Questions JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta Overview Commuter rail service between Lovejoy and Atlanta is ready for implementation: $87.08 Million is in

More information

WARES. October, 2018

WARES. October, 2018 WARES October, 2018 1 Project Overview A new 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County Operates mostly on the surface with 21

More information

Report Date: May 18, 2012 Contact: Al Zacharias Contact No.: RTS No.: 9587 VanRIMS No.: Meeting Date: June 12, 2012

Report Date: May 18, 2012 Contact: Al Zacharias Contact No.: RTS No.: 9587 VanRIMS No.: Meeting Date: June 12, 2012 A5 ADMINISTRATIVE REPORT Report Date: May 18, 2012 Contact: Al Zacharias Contact No.: 604.873.7214 RTS No.: 9587 VanRIMS No.: 08-2000-21 Meeting Date: June 12, 2012 TO: FROM: SUBJECT: Vancouver City Council

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

FEASIBILITY REPORT. 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY. October 2, 2017

FEASIBILITY REPORT. 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY. October 2, 2017 FEASIBILITY REPORT 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY October 2, 2017 Prepared for: City of Inver Grove Heights 8150 Barbara Avenue Inver Grove Heights,

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site. Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

PUBLIC TRANSPORTATION

PUBLIC TRANSPORTATION PUBLIC TRANSPORTATION An Overview of the Industry, Key Federal Programs, and Legislative Processes American Public Transportation Association 1 The Public Transportation Industry: What is "public transportation"?

More information

appendix 4: Parking Management Study, Phase II

appendix 4: Parking Management Study, Phase II appendix 4: Parking Management Study, Phase II A4-1 A4-2 Eastlake Parking Management Study Final Phase 2 Report Future Parking Demand & Supply January 6, 2017 Submitted by Denver Corp Center III 7900 E.

More information

Information Meeting Transfer Station Options. September 30, 2014

Information Meeting Transfer Station Options. September 30, 2014 Information Meeting Transfer Station Options September 30, 2014 Outline of Presentation Why we are looking at changes Background on current Transfer Station Options that were considered need, function

More information

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone.

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone. Meeting Objective 1. Who are we? 2. Review Commercial Solar Industry 3. Who are the ideal candidates for solar? 4. Key Site Conditions 5. Typical Upfront and On-going Costs Grasshopper Vision Accelerate

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Kake - Petersburg Intertie Update

Kake - Petersburg Intertie Update Kake - Petersburg Intertie Update September 18, 2013 Sitka Southeast Conference Annual Meeting Trey Acteson CEO, SEAPA Mark Schinman, P.E. Commonwealth Associates There is a Need for the Intertie Kake

More information

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at Overview Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at www.garail.com Commuter rail service between Lovejoy and Atlanta is ready for implementation:

More information

HYDROLOGIC/HYDRAULIC ANALYSIS REPORT FOR THE TROLLEY BROOK CULVERT ASHLAND, MA

HYDROLOGIC/HYDRAULIC ANALYSIS REPORT FOR THE TROLLEY BROOK CULVERT ASHLAND, MA HYDROLOGIC/HYDRAULIC ANALYSIS REPORT FOR THE TROLLEY BROOK CULVERT ASHLAND, MA Prepared for: THE TOWN OF ASHLAND BOARD OF SELECTMEN AND PLANNING DEPARTMENT Prepared by: June 3, 216 Hydrologic/Hydraulic

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) A: 2014 SFMTA TRANSIT SERVICE INFORMATION B: SFMTA TRAFFIC COUNT DATA C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) E: LAND USE AND VALUE

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

A Presentation to: Project Advisory Group Meeting #10

A Presentation to: Project Advisory Group Meeting #10 A Presentation to: Project Advisory Group Meeting #10 October 21, 2015 Agenda Introductions Action Items From Last PAG Meeting (August 26, 2015) Recent Agency Involvement Update on Refined Alternative

More information

CI Number: ACE CI Page 1 of 9. Title: Metro Voltage Support - Add Capacitor Bank

CI Number: ACE CI Page 1 of 9. Title: Metro Voltage Support - Add Capacitor Bank 216 ACE CI 46587 Page 1 of 9 CI Number: 46587 Title: Metro Voltage Support Add Capacitor Bank Start Date: 215/6 InService Date: 216/12 Final Cost Date: 217/6 Function: Transmission Forecast Amount: 3,373,511

More information

Appendix C. Parking Strategies

Appendix C. Parking Strategies Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed

More information

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report REVISIONS 1. Table 39: New Public Investments for Operation and Maintenance Costs 2. Appendix A-10: Passenger Rail Service - Operations

More information

2005 City of Santa Paula Potable Water System Master Plan Amendment

2005 City of Santa Paula Potable Water System Master Plan Amendment 2005 City of Santa Paula Potable Water System Master Plan Amendment City of Santa Paula Project Engineer Randy Toedter, PE Brian Yanez June, 2012 970 Ventura Street Santa Paula, CA 93060 PURPOSE OF THE

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information