MAXIMIZATION OF ENERGY GENERATED AT THE POWER PLANTS
|
|
- Easter Cobb
- 5 years ago
- Views:
Transcription
1 MAXIMIZATION OF ENERGY GENERATED AT THE POWER PLANTS OF THE NORTHERN REGION OF THE BRAZILIAN INTERCONNECTED POWER SYSTEM THROUGH THE SPECIAL PROTECTION SYSTEM - SPS ASSOCIATED TO XINGU - ESTREITO HVDC LINK S.L.A. Sardinha G.Cardoso Junior E.F. Oliveira A.F.C. de Aquino A.G. Massaud A.M. Silva P.E.M. Quintão R.S. Gomes L.C. Soares F.M. Silva M.A.N. Silveira A.R. Nunes S.B. Martins R.V. Faria V.G.C. Salles M.F. Silva L.D. Penna F.C.S. Araujo J.M.F. Ferreira J.C. Oliveira R. Treistman 1 / 25
2 In order to minimize dispatch restrictions at this plant and to enable the first direct current bipolar to be commissioned at the beginning of Introduction The integration of Belo Monte Hydro Power Plant to the Brazilian Interconnected Power System (BIPS) occurred without the planned expansion of the AC transmission system, due to the delay in important transmission facilities under the responsibility of ABENGOA agent, which would establish an alternative path for the generation of the power plants of the Northern region, especially for Belo Monte HPP. Belo Monte HPP 18 x 611 MW In order to minimize dispatch limitations to Belo Monte HPP and to enable the commissioning of the HVDC link connecting Xingu (PA) and Estreito (MG) substations at the beginning of 2018, ONS has developed preoperational studies considering this new configuration of the BIPS with parallel AC and DC interconnections, which led to the definition of control and systemic protection actions, based on a Special Protection System. Label of author s Company 2 / 25
3 Investigated Contingencies For the development of the Special Protection System, the following set of contingencies was analyzed and their corresponding logics defined: Single outages (Logic 1) and double outage (Logic 2) of 500 kv Xingu Tucuruí transmission line; Logic 5 Logics 1 and 2 Bipole 1 blocking (Logic 3); Double outages at the North-Southeast interconnection (Logic 4); Logic 3 Logic 4 Tripping of generating units of Belo Monte HPP (Logic 5) Label of author s Company 3 / 25
4 Logic 3 - Bipole 1 blocking (blocking of the last pole) In the Exporting North scenario (power flow from Xingu to Estreito), the blocking of Bipole 1 will produce an increase of the power flow in the North-Southeast interconnection, that may lead to the loss of synchronism between the systems of the North / Northeast and South / Southeast regions, with the consequent actuation of the out-of-step protections of the North-Southeast and Southeast-Northeast interconnections. In this case, the only possible action is the generation drop in the power plants of the Northern region. In this way, the necessary generation drop at Belo Monte HPP was identified through simulations as a function of the power order in Bipole 1, so as to guarantee the stability of the system. For this, the application of a short-circuit in the DC line followed by blocking of the bipole with the drop of generating units at Belo Monte HPP after 150 ms were used as assumptions. It should be emphasized that the selection of the generating units to be dropped, as well as eventual priority changes in the dropping row, can be performed through Belo Monte HPP HMI. 4 / 25
5 Logic 3 - Bipole 1 blocking (blocking of the last pole) In order to optimize the generation drop, two communication channels were implemented for the transmission of digital signals from the Master PLC at Serra da Mesa substation, informing the power flow level in the North-Southeast interconnection (FNS) to the "Station Control" of Bipole 1 located at Xingu substation, thus defining three operational ranges: Bits generated by the Master PLC at Serra da Mesa Substation Power Flow in the North-Southeast Interconnection Canal 1 Canal FNS 1000 MW MW < FNS 2000 MW 0 0 FNS > 2000 MW Obs.: If one or both channels are lost, signal 0 (zero) will be assumed, so that the highest generation drop will be conservatively executed. Label of author s Company 5 / 25
6 Logic 3 - Bipole 1 blocking (blocking of the last pole) The following table summarizes the Logic of generation drop according to the power order of Bipole 1 and the transmission level in the North-Southeast interconnection (FNS), for the Exporting North scenario. Power Order Generation Drop (nº of GU at Belo Monte HPP) (MW) FNS 1000 MW 1000 < FNS 2000 MW 2000 < FNS 4000 MW > Logic 3 is automatically disabled if both circuits of the 500 kv Xingu-Tucuruí LT are unavailable absent (Belo Monte HPP connected asynchronously to the SIN). In the Exporting Southeast scenario (power flow Estreito Xingu) there is no possible action in case of Bipole loss, so it is necessary to impose an operative restriction for the sum of Bipole 1 power order and the total power flow in the circuits of the 500 kv Miracema Colinas TL (FMCCO). Label of author s Company 6 / 25
7 Logic 3 - Bipole 1 blocking (blocking of the last pole) At the end of the wet season in the Northern region, Belo Monte Hydroelectric Plant, due to its run-of-river characteristic, is prone to operate with its generating units converted to synchronous compensators, while Tucuruí HPP, due to the storage capacity of its reservoir, will still continue with some generation capacity. If the number of generating units operating as generators at Belo Monte HPP is not sufficient to meet the necessary generation drop, Logic 3 will promote a complementary trip of machines at Tucuruí HPP. Considering that 2 units of Tucuruí HPP correspond approximately to 1 generating unit of Belo Monte HPP, the following strategy was adopted: - when the difference between the number of units to be dropped at Belo Monte HPP and the number of its units operating as generators is equal to 1, a digital signal is sent to make a complementary trip of 2 generating units at Tucuruí HPP - when the difference between the number of units to be dropped at Belo Monte HPP and the number of its units operating as generators is greater than 1, a digital signal is sent to make a complementary trip of 4 generating units at Tucuruí HPP. Tucuruí. 7 / 25
8 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Xingu to Tucuruí - Single outages at 500 kv Xingu-Tucuruí (Logic 1.a.1) This Logic performs a Run-up action on the bipole in order to limit the loading of the Fixed Series Capacitor of the remaining circuit to 2600 MW to meet its 2723 MVA overload limit. The Run-up action will be complemented by generation drop at Belo Monte HPP: - in case of exhaustion of the bipole overload capacity (33%) or other limitations in the AC / DC systems - if the telecontrol between Bipole Interface 2 and the Station Control is unavailable 8 / 25
9 Label of author s Company 9 / 25
10 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Xingu to Tucuruí - Single outages at 500 kv Xingu-Tucuruí TL (Logic 1.a.1) Should generation drop be executed, in addition to the Run-up action, if the amount of power to be dropped (Delta Power) does not correspond to an exact number of machines, Logic 1 uses the "over-trip" option. In case of total unavailability of Bipole 1, only generation drop action is performed. Label of author s Company 10 / 25
11 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Xingu to Tucuruí - Double outage of circuits at 500 kv Xingu-Tucuruí TL (Logic 2.a.1) This Logic performs a Run-up action on the bipole, in an amount equal to the total previous power flow on the circuits of Xingu-Tucuruí TL. If Bipole 1 does not have enough margin to fully perform the Run-up action, either due to the exhaustion of its overload capacity (33%) or limitations in the AC / DC systems, or if the telecontrol between Bipole Interface 2 and the Station Control is unavailable, the Run-up action will be complemented by generation drop at Belo Monte HPP. 11 / 25
12 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Xingu to Tucuruí - Double outage of circuits at 500 kv Xingu-Tucuruí TL (Logic 2.a.1) Should generation drop be executed, in addition to the Run-up action, if the amount of power to be dropped (Delta Power) does not correspond to an exact number of machines, Logic 2 uses the under-trip option. In case of total unavailability of Bipole 1, only generation drop action is performed. Obs.: Once both circuits of Xingu-Tucuruí TL are opened, the generation drop actions at Belo Monte HPP promoted by Logic 3 and the Run-up / generation drop actions promoted by Logic 4 are inhibited, since they would be innocuous, as Xingu substation and, as a consequence, Belo Monte HPP will be separated from the Brazilian Label of author s Interconnected Power System. Company 12 / 25
13 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Tucuruí to Xingu - Single outages at 500 kv Xingu-Tucuruí TL (Logic 1.a.2) This Logic performs a Run-back action on the bipole in order to limit the loading on the Fixed Series Capacitor of the remaining circuit to 2600 MW to meet its 2723 MVA overload limit. This action is limited to the minimum power order of the bipole (10% P nom ). If the telecontrol between Bipole 2 Interface and the Station Control is unavailable, there will be no Run-back action. In this case, the total power flow in the circuits of 500 kv Xingu-Tucuruí TL, from Tucuruí to Xingu, should be limited to 2600 MW through Operating Instructions. Label of author s Company 13 / 25
14 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 1) Exporting North Scenario (Power flow Xingu Estreito) - Power flow from Tucuruí to Xingu - Double outage of circuits at 500 kv Xingu-Tucuruí TL (Logic 2.a.2) This Logic performs a Run-back action on the bipole, in an amount equal to the total previous power flow on the circuits of Xingu-Tucuruí TL. Since the minimum power order of the Bipole is equal to 10% Pnom, if the difference between Bipole power order and the total power flow in Xingu-Tucuruí TL is less than this minimum value or if the telecontrol between Bipole 2 Interface and the Station Control is unavailable, the Run-back action cannot be fully performed and the Bipole 1 will be blocked. - If Bipole Tuc-Xgu < 10% P nom : Bipole blocking - If Bipole Tuc-Xgu 10% P nom : Run-back equal to the total previous power flow in the circuits of Xgu-Tuc TL Note: In order to guarantee the stability of the N-SE interconnection, if Tucuruí-Xingu power flow exceeds 400 MW, 2 generating units are tripped at Tucuruí HPP. If it exceeds 600 MW, 4 generating units are tripped at Tucuruí HPP. Label of author s Company 14 / 25
15 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 2) Exporting Southeast Scenario (Power flow Estreito Xingu) - Power flow from Xingu to Tucuruí In this scenario, the power flow at 500 kv Xingu-Tucuruí TL will always run from Xingu to Tucuruí. - Single outages at 500 kv Xingu-Tucuruí (Logic 1.b.1) This Logic performs a Run-back action on the bipole in order to limit the loading on the Fixed Series Capacitor of the remaining circuit to 2600 MW to meet its 2723 MVA overload limit. This action is limited to the minimum power order of the bipole (10% P nom ). If the telecontrol between Bipole 2 Interface and the Station Control is unavailable or if there is no communication between Xingu and Estreito terminals, there will be no Run-back action. In this case, the total power flow at the circuits of 500 kv Xingu-Tucuruí TL, from Xingu to Tucuruí, should be limited to 2600 MW through Operating Instructions. 15 / 25
16 Logics 1 and 2 - Single and double outages of 500 kv Xingu Tucuruí transmission line 2) Exporting Southeast Scenario (Fluxo Estreito Xingu) - Power flow from Xingu to Tucuruí - Double outage of circuits at 500 kv Xingu-Tucuruí TL (Logic 2.b.1) This Logic performs a Run-back action on the bipole, in an amount equal to the total previous power flow on the circuits of Xingu-Tucuruí TL. Since the minimum power order of the Bipole is equal to 10% Pnom, if the difference between Bipole power order and the total power flow in Xingu-Tucuruí TL is less than this minimum value or if the telecontrol between Bipole 2 Interface and the Station Control is unavailable, the Run-back action cannot be fully performed and the Bipole 1 will be blocked. - If Bipole Xgu-Tuc < 10% P nom : Bipole blocking - If Bipole Xgu-Tuc 10% P nom : Run-back equal to the total previous power flow in the circuits of Xgu-Tuc TL 16 / 25
17 Logic 4 Double outages at the North Southeast Interconnection Currently, an Emergency Control Scheme is implemented in the North - Southeast interconnection, composed of a network of PLC installed in several substations on its path and a Master PLC located at Serra da Mesa substation. Since Bipole 1 is embedded in the AC transmission system, running in parallel with the North-Southeast interconnection, it offers the possibility of contributing to the pre-existing Emergency Control Scheme, through a Run-up action, for the elimination of overloads on the remaining circuits for contingencies in any of its segments. Thus, should double outages occur in the North-Southeast interconnection (or single outages in case of unavailability of circuits), Logic 4 promotes the following actions, in complement to the previously mentioned Emergency Control Scheme: - In the Exporting North Scenario (from Xingu to Estreito): Run-up in the Bipole/ generation drop at Belo Monte - In the Exporting Southeast Scenario (from Estreito to Xingu): Run-up in the Bipole.. Scenario Digital Signal (Pulse) (MW) Logic 4 Action Exp N Type Run-up / Gen Drop (*) Type Run-up Exp SE Type Run-up (*) the actions of Run-up and generation drop (if the Run-up margin is not sufficient) are executed simultaneously 17 / 25
18 Logic 4 Double outages at the North Southeast Interconnection 1) Exporting North Scenario (Power flow Xingu Estreito) 1.A Double outages at the North Southeast Interconnection As previously mentioned, its is currently implemented in the North - Southeast interconnection an Emergency Control Scheme, composed of a network of PLC installed in several substations on its path and a Master PLC located at Serra da Mesa substation. This ECS promotes generation drop actions at Serra da Mesa, Tucuruí, Estreito, Lajeado and Peixe Angical Hydro Power Plants, in addition to the tripping of one generating unit at Belo Monte HPP. With the installation of Bipole 1, the current tripping of 4 generating units at Tucurui HPP was maintained and a Run-up action was implemented to replace the generation drop at Belo Monte HPP (Type 1 signal). The generation drop at Belo Monte HPP by Logic 4 will only be executed in case of unavailability of the bipole or if the remote control between Bipole 2 Interface and the Station Control is unavailable. 18 / 25
19 Logic 4 Double outages at the North Southeast Interconnection 1) Exporting North Scenario (Power flow Xingu Estreito) 1.B Loss of large generation blocks in the Southeastern and Southern regions The loss of large generation blocks in the Southeastern and Southern regions (e.g., loss of bipole from the Madeira River Complex or 765 kv transmission elements associated with Itaipu HPP) may lead to the opening of the North / Southeast and North /Northeast interconnections. In order to reduce the energy transfer limitations from the Northern subsystem (Exporting North scenario), an additional logic was implemented, consisting on the implementation and activation of an Out-of-Step Protection on circuit C1 of the 500kV Gurupi - Serra da Mesa TL, at Gurupi substation, sending a signal to trip four generating units at Tucuruí HPP. This signal was also incorporated into Logic 4 of the SPS (Type 1 signal). 19 / 25
20 Logic 4 Double outages at the North Southeast Interconnection 2) Exporting Southeast Scenario (Power flow Estreito Xingu) In order to face the single outage of elements of the North-Southeast interconnection, the total power flow at Miracema-Colinas 500 kv TL circuits (FMCCO) was limited to 4000 MW. In the event of a double outage in this interconnection (or a single outage being one circuit unavailable), depending on the transmitted power level, a Run-up action on the Bipole 1 will be necessary in order to limit the loading on the Fixed Series Capacitor of the remaining circuit of 500 kv Colinas Miracema TL to 1950 MVA (50% overload), so that it does not evolve to a triple loss. In order to optimize the Run-up action, two communication channels were implemented for the transmission of digital signals from the Master PLC at Serra da Mesa substation, informing the power flow level in the North-Southeast interconnection (FMCCO) to the "Station Control" of Bipole 1 located at Xingu substation,. 20 / 25
21 Logic 4 Double outages at the North Southeast Interconnection 2) Exporting Southeast Scenario (Power flow Estreito Xingu) Notes: 1) In this scenario, if the bipole is out of operation, the generation drop action promoted by Logic 4 at Belo Monte HPP should be inhibited so as not to compromise the stability of the North - Southeast interconnection. Thus, when this scenario is configured and bipole is out of operation, Logic 4 must be disabled by means of a switch accessible in the HMI, following an Operation Instruction. 2) In order to avoid that the blocking of the bipole may cause an undesirable actuation of the out-of-step protection installed on circuit C1 of 500 kv Gurupi-Serra da Mesa TL, tripping four generating units at Tucuruí HPP, a communication channel between Xingu and Tucuruí substations was used to inhibit for 10 s this generation tripping. This delay was defined based on dynamic simulations to identify the excursion time of the electric center within the out-of-step protection characteristic when the blocking of the bipole occurs. 21 / 25
22 Logic 5 - Tripping of generating units of Belo Monte HPP When both 500 kv Xingu-Tucuruí LT circuits are out of operation, Manaus / Macapá area, together with Belo Monte HPP, stay connected asynchronously to the Brazilian Interconnected Power System through Bipole 1. In this configuration, in the event of tripping of generating units of Belo Monte HPP, Logic 5 executes a Run-back action on Bipole 1 in an amount equal to the lost generation, in order to reestablish the load- generation balance in the islanded area. In this configuration, until the AC interconnection is re-established, the generation drop actions promoted by Logic 3 and Run-up / generation drop promoted by Logic 4 will be unnecessary and should therefore be inhibited.. 22 / 25
23 Logic 5 - Tripping of generating units of Belo Monte HPP As previously mentioned, in case of double outage of circuits of 500 kv Xingu-Tucuruí TL, with the power flow running from Xingu to Tucuruí, a Run-up action will be promoted in Bipole 1 (Logic 2.a.1) and, if there is not enough margin for the execution of this action, it wiil be complemented with generation drop at Belo Monte HPP. In order to prevent this generation drop from giving rise to an undue Run-back action by Logic 5, a 10 s delay was introduced when the double loss of Xingu-Tucuruí is characterized. 23 / 25
24 Implementation Aspects and Field Tests of the Special Protection System Given the urgency of the Xingu - Estreito HVDC link start-up and the short time available for the implementation of the Special Protection System, it was necessary to find solutions based on the existing infrastructure, involving, consequently, numerous installations, with the participation of several generation and transmission agents (FURNAS, ELETRONORTE, TAESA, TBE, ISOLUX / LXTE, BMTE and NESA). With this objective, the PLC network installed along the North - Southeast interconnection and the existing communication infrastructure starting from Marabá substation was used. It is worth mentioning the enormous effort and praiseworthy proactivity of the Agents to overcome obstacles to the achievement of this objective. The five Logics that make up the Special Protection System were tested on the Real Time Simulator and commissioned in the field, through exhaustive tests carried out on December 08 and 09, As a result of these tests and due to the complementary dynamic studies developed, improvements were introduced, which were once again tested on RTDS and field-tested in the period from March 17 to 19, 2000, comprising 34 tests. This SEP will be expanded to incorporate the 2nd bipole (Xingu - Rio Terminal). 24 / 25
25 Thanks. 25 / 25
Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution
Centro de Pesquisas de Energia Elétrica - CEPEL Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution SEMINARIO Planificación Energética y de Expansión de la Transmisión
More informationComparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System
Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System John Graham* Sergio E Santo Abhay Kumar ABB Ltda Eletrobras-Furnas ABB AB, HVDC Brazil Brazil Sweden *Corresponding
More informationQuestion Question 1.2-8
Question 1.2-7 A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to
More informationNIPS Oscillations Investigations
Alexandre Massaud Renan Giovanini NIPS Oscillations Investigations Rio de Janeiro - RJ December, 2013 2 The National Interconnected System (NIPS) The National Interconnected System (NIPS) 765 kv 3 The
More informationSSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -
SSF Update December 2017 Summary of Changes This table only mentions SSF chapters that were updated. All other SSF chapters were checked and confirmed as still being uptodate. SSF Section Location of Change
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationReport. the feasibility of
Report on the feasibility of Additional Interconnection between India and Bangladesh Joint Technical Team (JTT) of India and Bangladesh July 2016 Contents 1.0 Background 1 2.0 Additional power export to
More informationHVDC. TMT&D provides the best and most economical HVDC system.
HVDC TMT&D HVDC TMT&D provides the best and most economical HVDC system. In 1955, TMT&D started the development of HVDC and is the leading HVDC supplier in Japan. TMT&D has continued to develop HVDC technology
More informationi-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development
i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development Innovations in Protection and Control in Ecuador Power System March 26-28, 2013 1 ECUADOR - OVERVIEW Location: South America
More informationREDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION
REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationSTABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL
STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL Montree SENGNONGBAN Komsan HONGESOMBUT Sanchai DECHANUPAPRITTHA Provincial Electricity Authority Kasetsart University Kasetsart University
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationHVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector
HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector
More informationHVDC Back-to-Back Interconnections Enabling reliable integration of power system
HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for
More informationJicable'15 Welcome Lecture Josias Matos de Araujo Eletrobras June, 2015
Jicable'15 Welcome Lecture Josias Matos de Araujo Eletrobras June, 2015 Regulatory framework in Brazil Regulatory Framework in Brazil Politics National Congress President of the Republic of Brazil National
More informationHVDC Systems in India
HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationPower System HVDC Applications
20 years Itaipu / 50 years HVDC anniversary John Graham ABB Brazil Power System HVDC Applications 2002 ABB Utilities - 1 What are the applications for HVDC in power systems? Long Distance Overhead Line
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationTURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)
TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) 1 CONTENT MAIN FUNCTIONS OF TEIAS TURKISH POWER SYSTEM OVERVIEW EXISTING
More informationElectricity industry structure and key players
Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and
More informationHawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER
1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview
More informationSTATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.
STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER
More informationNEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1
Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationDISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.
DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. N. Lettas*, A. Dagoumas*, G. Papagiannis*, P. Dokopoulos*, A. Zafirakis**, S. Fachouridis**,
More informationNext Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden
Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC
More informationUnrestricted. Air Core Reactor Applications Current Limiting Reactors
Unrestricted Air Core Reactor Applications Current Limiting Reactors Faults on Electrical System - Basic Concepts Three major concerns arise from this scenario: 1- The mechanical stresses on the transformer
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationOperational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks
Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and
More informationCEPEL - Centro de Pesquisas de Energia Elétrica
VII SEPOPE May - 21st to 26th - 2000 CURITIBA (PR) - BRASIL A Small-Signal Signal Stability Program Incorporating Advanced Graphical User Interface Nelson Martins Paulo E.M. Quintão Herminio J.C.P. Pinto
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationFinal Remarks. Grajau SC Reactive Power
Previous Reports A Knowledge-Based System for Supervision and Control of Regional Voltage Profile and Security Alessandro B. Marques Glauco N. Taranto Petrobras Formely with FURNAS Brazil TF 8.. Report
More informationIntroduction to PowerWorld Simulator: Interface and Common Tools
Introduction to PowerWorld Simulator: Interface and Common Tools I10: Introduction to Contingency Analysis 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationAlves, F.R.M. Henriques, R.M. Passos Fº, J.A. Gomes Jr., S. Borges, C.L.T. CEPEL UFJF UFJF CEPEL UFRJ
1 Integrating Solution Engines Under a Distributed Processing Environment: An Alternative Approach for Static and Dynamic Security Assessment of Large Scale Power Systems Alves, F.R.M. Henriques, R.M.
More informationUse of Microgrids and DERs for black start and islanding operation
Use of Microgrids and DERs for black start and islanding operation João A. Peças Lopes, FIEEE May 14 17, 17 Wiesloch The MicroGrid Concept A Low Voltage distribution system with small modular generation
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationTHE INFLUENCE OF THE INDEPENDENT POWER PRODUCERS IN THE DYNAMIC PERFORMANCE OF THE ELECTRIC SYSTEMS
THE INFLUENCE OF THE INDEPENDENT POWER PRODUCERS IN THE DYNAMIC PERFORMANCE OF THE ELECTRIC SYSTEMS M.M. SEVERINO *, F.D. FREITAS, I.M.T. CAMARGO and M. SILVA University of Brasilia (UnB) Manaus Energia
More informationNordic co-operation when meeting System challenges
Nordic co-operation when meeting System challenges Evolving the market conference Ulla Sandborgh CEO Agenda > System challenges > System development plan > Strategies > Grid development > Tariff development
More informationGuide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.
Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...
More informationMVDC PLUS Managing the future grid
MVDC PLUS Managing the future grid Bridge the distance How should we connect Islands, platforms, and remote areas? Connecting weak or unstable grids How will we integrate and stabilize grids? Reduce footprint
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationHVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University
HVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University Why has HVDC taken off? HV is needed to transmit DC
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationSeabrook Substation Reliability Improvement Project
New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationThe Physical Layer of Energy Systems. Announcement!!!
The Physical Layer of Energy Systems Randy H. Katz University of California, Berkeley Berkeley, CA 94720-1776 31 August 2009 Announcement!!! Power Delivery System Tutorial Alexandra von Meier, Sonoma State
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationMidway/Monument Area TTC Study
Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny
More informationPower Grid & Blackouts. Prof. Ramzy R. Obaid
Power Grid & Blackouts Prof. Ramzy R. Obaid With many thanks and appreciation to Professor Mohamed A. El Sharkawi Power System The electric power systems in the North America and Europe are probably the
More informationTransmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui
Transmission Grid Reinforcement with Embedded VSC-HVDC Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Outline Introduction HVDC-Light Transmission Technologies Embedded VSC-HVDC for AC Grid
More informationAlternatives for meeting the need for transmission improvement described
Alternatives for meeting the need for transmission improvement described 240 kv Alternative Looped System Southern Alberta Transmission Reinforcement For more information please contact the AESO at 1.888.866.2959,
More informationVariable frequency transformer for asynchronous power transfer
Variable frequency transformer for asynchronous power transfer by Einar Larsen, Richard Piwko and Donald McLaren, GE Energy A new power transmission technology has been developed. The variable frequency
More informationEl PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS
El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationPRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES
PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected
More informationSheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017
Sheffield-Highgate Export Interface SHEI VSPC Quarterly Meeting October 18, 2017 Northern Vermont Export Study Update VELCO is providing information to enable evaluation of potential solutions Incremental
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationfor DRECP Alternatives
Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationNew Mexico Transmission Expansion Concepts For Wind Resources
New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission
More informationFunctional Algorithm for Automated Pedestrian Collision Avoidance System
Functional Algorithm for Automated Pedestrian Collision Avoidance System Customer: Mr. David Agnew, Director Advanced Engineering of Mobis NA Sep 2016 Overview of Need: Autonomous or Highly Automated driving
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More information3 Existing National Grid
3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load
More informationCITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS
CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationApplication Note. First trip test. A circuit breaker spends most of its lifetime conducting current without any
Application Note First trip test A circuit breaker spends most of its lifetime conducting current without any operation. Once the protective relay detects a problem, the breaker that was idle for maybe
More informationThe Application of Power Electronics to the Alberta Grid
The Application of Power Electronics to the Alberta Grid Peter Kuffel, Michael Paradis ATCO Electric APIC May 5, 2016 Power Electronics Semiconductor devices used in power transmission systems Types: Thyristor
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationContingency Analysis
Contingency Analysis Power systems are operated so that overloads do not occur either in real-time or under any statistically likely contingency. This is often called maintaining system security Simulator
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationTOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY
More informationThe Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak
The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak Evolution of System Protection Scheme UFLS- Under Frequency
More informationExpected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)
Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li
More informationTransient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager
Transient Stability Analysis Tool (TSAT) Update April 11, 2016 Hongming Zhang EMS Network Applications Manager Agenda Peak Online TSAT Introduction: Where we are on Wide-wide System Model (WSM) -TSAT online
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationOCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC
OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC
More informationELECTRIC GENERATION AND TRANSMISSION IN THE RAILBELT
ELECTRIC GENERATION AND TRANSMISSION IN THE RAILBELT Joe Griffith General Manager, MEA Chief Executive Officer, ARCTEC Commonwealth North November 15, 2013 1 RAILBELT MAKEUP Electrical utilities are all
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationIslanding of 24-bus IEEE Reliability Test System
Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................
More informationADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE
ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE IMPLEMENT ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE Gemitech was founded in 1990 and, in just a few short years, grew to be recognized as medium and IMPLEMENT
More informationS-PPC. Product Brief. Power Plant Controller Solutions for Energy Storage Systems
S-PPC Product Brief Power Plant Controller Solutions for Energy Storage Systems Recently, new energy storage technologies are experiencing increasing penetration in the renewable/electricity market. With
More informationWESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM
1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.
More informationTable of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure
No. 6930 Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,
More informationSEVILLA, APRIL Microgeneration and Microgrids (modeling, islanding operation, black start, multi-microgrids) J. Peças Lopes Power Systems Unit
SEVILLA, APRIL 2010 Campus da FEUP Rua Dr. Roberto Frias, 378 4200-465 Porto Portugal T +351 222 094 000 F +351 222 094 050 cmoreira@inescporto.pt www.inescporto.pt Microgeneration and Microgrids (modeling,
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationGrid-Friendly Utility-Scale PV Plants
White Paper Grid-Friendly Utility-Scale PV Plants Mahesh Morjaria & Dmitriy Anichkov, First Solar, Tempe, Arizona, USA 13 August 2013 Table of Contents Introduction.... 3 Power Plant Controller Architecture...
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationJemena Electricity Networks (Vic) Ltd
Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...
More informationElectrical grid stability with high wind energy penetration
ECOWAS Regional Workshop on WIND ENERGY Praia, Cape Verde. November 4 5, 2013 Electrical grid stability with high wind energy penetration Fernando CASTELLANO HERNÁNDEZ Head of Wind Energy Section Renewable
More informationDistributed Energy Resources
Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired
More informationCONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012
CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length
More information