1 PA RACT 2 Reasonably Available Control Technology Presented by Suzanne Dibert

2 Affected Facilities Facilities with potential emissions that exceed 100 tons per year (tpy) for NOx (nitrogen oxide) and 50 tpy for VOC (volatile organic compound) In existence before July 20, 2012, and for which a NOx and/or VOC requirement has not already been established in certain sections of 25 Pa. Code Chapter 129

3 Timeline April 23, 2016 October 24, 2016 Mid to Late November January 1, 2017 EQB Promulgated RACT 2 Requirements RACT 2 Proposal due to PA DEP Make MP Changes in CEMDPS Demonstrate Compliance with RACT 2 3

4 Any Extensions? Only possible for facilities that submit a Plan Approval Application (PAA) to install a control device, make a physical change, or change the method of operation to comply with applicable RACT 2 requirements Compliance date is extended to 3 years from date of issuance of a resulting Plan Approval Maximum extension is 4.5 years (18 month maximum for PADEP to review a PAA plus the 3 year extension from the date of final Plan Approval issuance)

5 Demonstrating Compliance Facility with continuous emission monitoring system (CEMS) must use CEMS to demonstrate compliance Existing emission and data availability standards continues Facilities without CEMS must conduct source testing

6 30 Operating Day Rolling Average Emission Rate Sources with CEMS compliance will be demonstrated with a 30 operating day rolling average emission rate. Operating day is defined as 24-hour period beginning at 12:00 midnight during which the source operates at any time and produces emissions. Includes startups, shutdowns, or malfunctions. Data substitution is required for invalid hours in which monitoring is required. 6

7 30 Day Averaging for Combustion Units A. The total pounds of pollutant emitted from the combustion unit for each operating hour for the current operating day and the previous 29 operating days will be summed B. The total heat input to the combustion unit in million Btu (Mbtu) for each operating hour for the current operating day and the previous 29 operating days will be summed C. Divide A (above) by B (above) to determine the emissions rate (lbs/mbtu)

8 30-day averages for Combustion Turbines A. Sum the valid operating hours NOX 15% O 2 emitted from the combustion unit for the current operating day and the previous 29 operating days B. Sum the number of operating hours for the combustion turbine for the current operating day and the previous 29 operating days (Do not include hours where the NOX corrected was invalid) C. Divide A (above) by B (above) to determine the emissions rate

9 Units Firing Multiple Fuels Emission limit shall be determined on a total heat input fuel weighted basis A fuel representing < 1% of the unit s annual fuel consumption on a heat input basis is excluded when determining the emission limit The unit must demonstrate this exclusion over a 12-calendar month period, rolling by 1-month Information should be included in the cover letter if the exclusion is utilized The owner may petition the Department to include a fuel representing <1% of the unit s annual fuel consumption on a heat input basis in the emission limit. 9

10 Emissions Averaging Plans Sites may use CEMDPS to demonstrate compliance on a facilitywide basis if the following criteria are met: All underlying emission results, CEMS, and analyzers conform to the requirements of the Manual. The Department may approve the use of analyzers that have been certified under an applicable Federal program. Those not meeting the above must submit a quarterly compliance report to the applicable DEP Regional Office to demonstrate compliance.

11 Emission Averaging Plans PA DEP is not sure how reporting in CEMDPS will be handled for facility-wide averaging. May or may not need to have a new facility-wide ID. Chuck Zadakis said to check back in a few weeks. All demonstrations of compliance on a system-wide basis should be submitted as a quarterly compliance report to the applicable DEP Regional Office. If more than one DEP Region is involved, a copy of the report must be submitted to each. 11

12 PA CEMDPS

13 DEPGreenport CEMDPS (CEM Data Processing System) 13

14 MP CEMDPS (CEM Data Processing System) Combustion Unit or process Heater Include new emission result and CEMS for hourly NOx mass emissions (lbs), hourly heat input (MBtu), and hourly NOx (lbs/mbtu) Include new emission result and CEMS for allowable hourly emission rate (lbs/mbtu) for those that have a variable emission standard

15 MP CEMDPS Combustion Turbine Include new emission result and CEMS for hourly concentration emissions 15% O2) Include new emission result and CEMS for allowable hourly emission rate (PPM@ 15% O2) and hourly heat input (MBtu) for those that have a variable emission standard

16 MP CEMDPS Portland Cement Kiln or Municipal Waste Combustor Include new emission result and CEMS for hourly mass emissions (lbs), hourly clinker production (tons), and hourly (lbs/tonclinker). Each CEMS should be associated with the appropriate analyzer(s) Municipal Waste Combustor submit a MP only if a new daily average NOx emission standard must be added

17 Performance Testing and Certification - CEMS After MP has been approved by PADEP Data acquisition and accuracy check (CEMDPS) Sample hours of emissions data (under various scenarios) Sample quarterly report for new emission results (submit in CEMDPS) Quarterly Emission Reports Submit hourly emissions data in CEMDPS starting with first quarter 2017 As always, submit once PA DEP has approved for submittal

18 STACKVISION

19 Configuration in SV Add new reportable parameters Configure 30 operating day rolling average Possibly add new parameters to Pennsylvania Settings list in StackStudio 19

20 Import CEMDPS Monitoring Plan to SV

21 SV PADEP Parameter Mapping

22 SV PADEP EDR Generation

23 RACT PADEP EDR Example 1646 NOXLBS 1647 HEATN 3033 Allowable NOX Rate 23

24 Sneak Peak SV PADEP Changes 24

25 DAS VALIDATION IN CEMDPS

26 PADEP DAS Validation 26

27 PADEP DAS Validation 27

28 PADEP DAS Validation 28

29 PADEP DAS Validation 29

30 SAMPLE DATA SPREADSHEET

31 Sample Data This spreadsheet includes Different operating scenarios: Normal hours, invalid hours, calibration, maintenance, partial hours, substituted hours The spreadsheet compares the calculated hourly values (from minute data) to the DAS calculated hourly values for your reported parameters 31

32 32

33 33

34 34

35 References Revised Final Form RACT 2 Rule DEP>Business>Air>Bureau of Air Quality>Permits DEP Greenport 35

36

RULE 4352 SOLID FUEL FIRED BOILERS, STEAM GENERATORS AND PROCESS HEATERS (Adopted September 14, 1994; Amended October 19, 1995; Amended May 18, 2006)

RULE 4352 SOLID FUEL FIRED BOILERS, STEAM GENERATORS AND PROCESS HEATERS (Adopted September 14, 1994; Amended October 19, 1995; Amended May 18, 2006) RULE 4352 SOLID FUEL FIRED BOILERS, STEAM GENERATORS AND PROCESS HEATERS (Adopted September 14, 1994; Amended October 19, 1995; Amended May 18, 2006) 1.0 Purpose The purpose of this rule is to limit emissions

More information

3.1 Air Pollution Control Officer (APCO): as defined in Rule 1020 (Definitions).

3.1 Air Pollution Control Officer (APCO): as defined in Rule 1020 (Definitions). RULE 4352 SOLID FUEL FIRED BOILERS, STEAM GENERATORS AND PROCESS HEATERS (Adopted September 14, 1994; Amended October 19, 1995; Amended May 18, 2006; Amended December 15, 2011) 1.0 Purpose The purpose

More information

The Premcor Refining Group, Inc. Delaware City Refinery 4550 Wrangle Hill Rd. EXHIBIT A Delaware City, DE 19706

The Premcor Refining Group, Inc. Delaware City Refinery 4550 Wrangle Hill Rd. EXHIBIT A Delaware City, DE 19706 DRAFT Permit: APC-2004/0721-CONSTRUCTION (NSPS) Two Package Boilers The Premcor Refining Group, Inc. Delaware City Refinery 4550 Wrangle Hill Rd. EXHIBIT A Delaware City, DE 19706 ATTENTION: Andrew Kenner

More information

ELECTRICAL GENERATING STEAM BOILERS, REPLACEMENT UNITS AND NEW UNITS (Adopted 1/18/94; Rev. Adopted & Effective 12/12/95)

ELECTRICAL GENERATING STEAM BOILERS, REPLACEMENT UNITS AND NEW UNITS (Adopted 1/18/94; Rev. Adopted & Effective 12/12/95) RULE 69. ELECTRICAL GENERATING STEAM BOILERS, REPLACEMENT UNITS AND NEW UNITS (Adopted 1/18/94; Rev. Adopted & Effective 12/12/95) (a) APPLICABILITY (1) Except as provided in Section (b) or otherwise specified

More information

RULE STATIONARY GAS TURBINES Adopted (Amended , ) INDEX

RULE STATIONARY GAS TURBINES Adopted (Amended , ) INDEX RULE 413 - STATIONARY GAS TURBINES Adopted 04-06-95 (Amended 05-01-97, 03-24-05) INDEX 100 GENERAL 101 PURPOSE 102 APPLICABILITY 110 EXEMPTION - EMERGENCY STANDBY UNITS 111 EXEMPTION - REMOVAL FROM SERVICE

More information

This is a new permit condition titled, "2D.1111 Subpart ZZZZ, Part 63 (Existing Non-Emergency nonblack start CI > 500 brake HP)"

This is a new permit condition titled, 2D.1111 Subpart ZZZZ, Part 63 (Existing Non-Emergency nonblack start CI > 500 brake HP) This is a new permit condition titled, "2D.1111 Subpart ZZZZ, Part 63 (Existing Non-Emergency nonblack start CI > 500 brake HP)" Note to Permit Writer: This condition is for existing engines (commenced

More information

SECTION.1400 NITROGEN OXIDES

SECTION.1400 NITROGEN OXIDES SECTION.1400 NITROGEN OXIDES 15A NCAC 02D.1401 DEFINITIONS (a) For the purpose of this Section, the definitions at G.S 143-212 and G.S. 143-213, and 15A NCAC 02D.0101 shall apply, and in addition the following

More information

ARTICLE AIR POLLUTION CONTROL REGULATIONS AND PROCEDURES

ARTICLE AIR POLLUTION CONTROL REGULATIONS AND PROCEDURES TABLE OF CONTENTS ARTICLE 2.0000 AIR POLLUTION CONTROL REGULATIONS AND PROCEDURES Section 2.1400 Nitrogen Oxides 2.1401 Definitions... 214-01 2.1402 Applicability... 214-04 2.1403 Compliance Schedules...

More information

APPENDIX D. REGULATIONS (excerpts) ON 24-HOUR EMISSION LIMITS: MARYLAND DEPARTMENT OF THE ENVIRONMENT

APPENDIX D. REGULATIONS (excerpts) ON 24-HOUR EMISSION LIMITS: MARYLAND DEPARTMENT OF THE ENVIRONMENT APPENDIX D APPENDIX D REGULATIONS (excerpts) ON 24-HOUR EMISSION LIMITS: MARYLAND DEPARTMENT OF THE ENVIRONMENT DELAWARE DEPARTMENT OF NATURAL RESOURCES AND ENVIRONMENTAL CONTROL NEW JERSEY STATE DEPARTMENT

More information

MARAMA 2015 SCIENCE MEETING JULY 29-30, 2015 RICHMOND, VIRGINIA

MARAMA 2015 SCIENCE MEETING JULY 29-30, 2015 RICHMOND, VIRGINIA Air Permitting of Sources at Natural gas Production, Compression and Processing Facilities MARAMA 2015 SCIENCE MEETING JULY 29-30, 2015 RICHMOND, VIRGINIA Tom Wolf, Governor John Quigley, Secretary Overview

More information

The subject renewal application was received on February 28, 2017 and was determined to be administratively complete on March 9, 2017.

The subject renewal application was received on February 28, 2017 and was determined to be administratively complete on March 9, 2017. COMMONWEAL TH OF PENNSYLVANIA Department of Environmental Protection December 7, 2017 814/332-6940 Fax: 814/332-6117 SUBJECT: TO: FROM: THROUGH: Review of Application for Renewal Title V Permit AUTH ID

More information

RULE 412 STATIONARY INTERNAL COMBUSTION ENGINES LOCATED AT MAJOR STATIONARY SOURCES OF NO X Adopted INDEX

RULE 412 STATIONARY INTERNAL COMBUSTION ENGINES LOCATED AT MAJOR STATIONARY SOURCES OF NO X Adopted INDEX RULE 412 STATIONARY INTERNAL COMBUSTION ENGINES LOCATED AT MAJOR STATIONARY SOURCES OF NO X Adopted 06-01-95 INDEX 100 GENERAL 101 PURPOSE 102 APPLICABILITY 110 EXEMPTION, EMERGENCY STANDBY 111 EXEMPTION,

More information

Part 70 Operating Permit Amendment

Part 70 Operating Permit Amendment Part 70 Operating Permit Amendment Effective Date: February 18, 2016 Facility Name: Scherer Steam-Electric Generating Plant Facility Address 10986 Highway 87 Juliette, Georgia 31046, Monroe County Mailing

More information

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the

1996, or for which modification is commenced on or before March 16, 1998, shall not exceed the 15A NCAC 02D.1206 HOSPITAL, MEDICAL, AND INFECTIOUS WASTE INCINERATORS (a) Applicability. This Rule applies to any hospital, medical, and infectious waste incinerator (HMIWI), except: (1) any HMIWI required

More information

Permit Holder. Permitted Equipment

Permit Holder. Permitted Equipment Air Quality Registration Stationary Spark Ignition Internal Combustion Engine (Less than 400 Brake Horsepower) Permit No. Project No. Description Date Testing No Plant Number: Under the Direction of the

More information

Appendix K. DOC Conditions

Appendix K. DOC Conditions Appendix K DOC Conditions Mission Rock Energy Center Five (5) GE LM6000-PG-Sprint Combustion Turbine Generators (CTGs) Total = 275 MW Nominal Each CTG is simultaneously subject to the emission limits,

More information

AIR QUALITY PERMIT. 7 Foundation Drive Savannah, Georgia (Chatham County)

AIR QUALITY PERMIT. 7 Foundation Drive Savannah, Georgia (Chatham County) AIR QUALITY PERMIT Permit No. Effective Date April 11, 2016 In accordance with the provisions of the Georgia Air Quality Act, O.C.G.A. Section 12-9-1, et seq and the Rules, Chapter 391-3-1, adopted pursuant

More information

This rule shall apply to any stationary source which is a major source of regulated air pollutants or of hazardous air pollutants.

This rule shall apply to any stationary source which is a major source of regulated air pollutants or of hazardous air pollutants. RULE 2530 FEDERALLY ENFORCEABLE POTENTIAL TO EMIT (Adopted June 15, 1995; Amended April 25, 2002; Amended December 18, 2008, but not in effect until June 10, 2010) 1.0 Purpose The purpose of this rule

More information

State of New Jersey. Department of Environmental Protection Air Quality Permitting

State of New Jersey. Department of Environmental Protection Air Quality Permitting GP021 State of New Jersey Department of Environmental Protection Air Quality Permitting General Permit (GP 021) Combined Heat and Power Combustion Turbine(s) less than or equal to 65 MMBTU per hour This

More information

Streamlining Multiple Applicable Requirements

Streamlining Multiple Applicable Requirements Streamlining Multiple Applicable Requirements What is Streamlining? 1. Streamlining is the process of determining one set of requirements to be incorporated into the Title V permit from among multiple

More information

Industrial, Commercial and Institutional Boilers at Area Source Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary

Industrial, Commercial and Institutional Boilers at Area Source Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary Industrial, Commercial and Institutional Boilers at Area Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary Federal Regulation NESHAP, 40 CFR 63, Subpart JJJJJJ Proposed rule published

More information

Appendix K. Final DOC Conditions

Appendix K. Final DOC Conditions Appendix K Final DOC Conditions Puente Power Project 262 MW (net nominal) GE 7HA.01 Combustion Turbine Generator (CTG) The CTG is simultaneously subject to the emission limits, monitoring requirements,

More information

RULE 4306 BOILERS, STEAM GENERATORS, AND PROCESS HEATERS PHASE 3 (Adopted September 18, 2003; Amended March 17, 2005; Amended October 16, 2008)

RULE 4306 BOILERS, STEAM GENERATORS, AND PROCESS HEATERS PHASE 3 (Adopted September 18, 2003; Amended March 17, 2005; Amended October 16, 2008) RULE 4306 BOILERS, STEAM GENERATORS, AND PROCESS HEATERS PHASE 3 (Adopted September 18, 2003; Amended March 17, 2005; Amended October 16, 2008) 1.0 Purpose The purpose of this rule is to limit emissions

More information

RULE NOX REDUCTIONS FROM MISCELLANEOUS SOURCES (Adopted 12/13/2016)

RULE NOX REDUCTIONS FROM MISCELLANEOUS SOURCES (Adopted 12/13/2016) VENTURA COUNTY AIR POLLUTION CONTROL DISTRICT RULE 74.34 NOX REDUCTIONS FROM MISCELLANEOUS SOURCES (Adopted 12/13/2016) A. Purpose and Applicability The purpose of this rule is to reduce emissions of oxides

More information

GENERAL PLAN APPROVAL AND GENERAL OPERATING PERMIT BAQ-GPA/GP 2 STORAGE TANKS FOR VOLATILE ORGANIC LIQUIDS

GENERAL PLAN APPROVAL AND GENERAL OPERATING PERMIT BAQ-GPA/GP 2 STORAGE TANKS FOR VOLATILE ORGANIC LIQUIDS COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF AIR QUALITY GENERAL PLAN APPROVAL AND GENERAL OPERATING PERMIT BAQ-GPA/GP 2 STORAGE TANKS FOR VOLATILE ORGANIC LIQUIDS GENERAL

More information

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM April 18, 2014 SUBJECT: Cellco Partnership, dba Verizon Wireless 18 Abele Road Bridgeville, PA 15017 Allegheny County Operating Permit No. 0867 TO:

More information

PERMIT TO INSTALL. Table of Contents

PERMIT TO INSTALL. Table of Contents Permit No. 118-18 Page 1 of 23 PERMIT TO INSTALL Table of Contents COMMON ACRONYMS... 2 POLLUTANT / MEASUREMENT ABBREVIATIONS... 3 GENERAL CONDITIONS... 4 EMISSION UNIT SPECIAL CONDITIONS... 6 EMISSION

More information

State of New Jersey. Department of Environmental Protection Division of Air Quality

State of New Jersey. Department of Environmental Protection Division of Air Quality GOP-006 State of New Jersey Department of Environmental Protection Division of Air Quality General Operating Permit (GOP-006) Combined Heat and Power Stationary Spark Ignition Reciprocating Engine(s) less

More information

Air Individual Permit Permit Limits to Avoid NSR

Air Individual Permit Permit Limits to Avoid NSR Air Individual Permit Permit Limits to Avoid NSR 13900128-001 Permittee: Facility name: Shakopee Distributed Generation Shakopee Distributed Generation Vierling Drive E Shakopee, Minnesota 55379 Scott

More information

General Plan Approval and General Operating Permit BAQ-GPA/GP-5 and Proposed Exemption 38. Citizens Advisory Council Meeting March 19, 2013

General Plan Approval and General Operating Permit BAQ-GPA/GP-5 and Proposed Exemption 38. Citizens Advisory Council Meeting March 19, 2013 General Plan Approval and General Operating Permit BAQ-GPA/GP-5 and Proposed Exemption 38 Citizens Advisory Council Meeting March 19, 2013 Headings : White Text 40 pt. Calibri GP-5 General Information

More information

(2) An engine subject to this rule or specifically exempt by Subsection (b)(1) of this rule shall not be subject to Rule 68.

(2) An engine subject to this rule or specifically exempt by Subsection (b)(1) of this rule shall not be subject to Rule 68. RULE 69.4. STATIONARY RECIPROCATING INTERNAL COMBUSTION ENGINES - REASONABLY AVAILABLE CONTROL TECHNOLOGY (Adopted 9/27/94; Rev. Effective11/15/00; Rev. Effective 7/30/03) (a) APPLICABILITY (1) Except

More information

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Mayo Foundation

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Mayo Foundation AIR EMISSION PERMIT NO. 10900008-003 Major Amendment IS ISSUED TO Mayo Foundation SAINT MARYS HOSPITAL 1216 Second Street Southwest Rochester, Olmsted County, Minnesota 55902 The emission units, control

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Cogentrix

AIR EMISSION PERMIT NO IS ISSUED TO. Cogentrix AIR EMISSION PERMIT NO. 16300087-004 IS ISSUED TO Cogentrix 9525 105th Street Court South Cottage Grove, Washington County, MN 55016 The emission units, control equipment and emission stacks at the stationary

More information

AIR EMISSION PERMIT NO Total Facility Oper. Permit - Reissuance IS ISSUED TO. LSPCottage Grove, L.P.

AIR EMISSION PERMIT NO Total Facility Oper. Permit - Reissuance IS ISSUED TO. LSPCottage Grove, L.P. AIR EMISSION PERMIT NO. 16300087-006 Total Facility Oper. Permit - Reissuance IS ISSUED TO LSPCottage Grove, L.P. LSPCOTTAGE GROVE COGENERATION FACILITY 9525 105th Street Court South Cottage Grove, Washington

More information

Applicable Requirements - NSPS Subpart JJJJ

Applicable Requirements - NSPS Subpart JJJJ Facility Name: CO Station 3 Combustion Type: 4SRB Facility HAP Status: Area Fuel Type: Natural gas RICE Owner: RICE Operator: S2C Gathering Co Acme Operating Inc. Use Type: Max. Runtime: Non-emergency

More information

402 LOSS OF EXEMPTION LOW FUEL USAGE 4032 SOURCE TESTING FREQUENCY 4043 SOURCE TESTING PROTOCOL

402 LOSS OF EXEMPTION LOW FUEL USAGE 4032 SOURCE TESTING FREQUENCY 4043 SOURCE TESTING PROTOCOL Attachment 6: Proposed Rule 419, Underline/Strikeout Version RULE 419 NOx FROM MISCELLANEOUS COMBUSTION UNITS Adopted 07-26-18 (Amended XX-XX-18) INDEX 100 GENERAL 101 PURPOSE 102 APPLICABILITY 103 SEVERABILITY

More information

Draft Air Individual Permit Major Amendment

Draft Air Individual Permit Major Amendment Draft Air Individual Permit Major Amendment 14700009-101 Permittee: Facility name: Northern Natural Gas Company - Owatonna Compressor Station Northern Natural Gas Company - Owatonna Compressor Station

More information

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM June 17, 2004 SUBJECT: Review of Application Title V Operating Permit Bellefield Boiler Plant Boundary Street Pittsburgh, PA 15213 RE: Operating Permit

More information

WORKSHOP REPORT. No, the RICE NESHAP applies only to stationary engines as defined in 40 CFR

WORKSHOP REPORT. No, the RICE NESHAP applies only to stationary engines as defined in 40 CFR AIR POLLUTION CONTROL DISTRICT COUNTY OF SAN DIEGO FEDERAL SUBPART ZZZZ NATIONAL EMISSIONS STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR STATIONARY RECIPROCATING INTERNAL COMBUSTION ENGINES WORKSHOP REPORT

More information

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM

ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM ALLEGHENY COUNTY HEALTH DEPARTMENT AIR QUALITY PROGRAM February 2, 2012 SUBJECT: Superior Appalachian Pipeline, LLC Kissick Lane Frazer Township, PA 15084 Allegheny County Installation Permit No. 0837-I001

More information

Regulation No. 3 Changes For Internal Combustion Engines. Christine Hoefler November 14, 2012

Regulation No. 3 Changes For Internal Combustion Engines. Christine Hoefler November 14, 2012 Regulation No. 3 Changes For Internal Combustion Engines Christine Hoefler November 14, 2012 Overview Changes to Regulation No. 3 New Source Performance Standard (NSPS) IIII Conflicts with NSPS IIII 2

More information

DRAFT/PROPOSED. AIR EMISSION PERMIT NO Total Facility Operating Permit Reissuance IS ISSUED TO. Hutchinson Utilities Commission

DRAFT/PROPOSED. AIR EMISSION PERMIT NO Total Facility Operating Permit Reissuance IS ISSUED TO. Hutchinson Utilities Commission DRAFT/PROPOSED AIR EMISSION PERMIT NO. 08500034 002 Total Facility Operating Permit Reissuance IS ISSUED TO Hutchinson Utilities Commission Hutchinson Utilities Commission Plant 2 1100 Industrial Boulevard

More information

STATIONARY GAS TURBINE ENGINES - REASONABLY AVAILABLE CONTROL TECHNOLOGY (Adopted & Effective 9/27/94) (Rev. Adopted & Effective 12/16/98)

STATIONARY GAS TURBINE ENGINES - REASONABLY AVAILABLE CONTROL TECHNOLOGY (Adopted & Effective 9/27/94) (Rev. Adopted & Effective 12/16/98) RULE 69.3 STATIONARY GAS TURBINE ENGINES - REASONABLY AVAILABLE CONTROL TECHNOLOGY (Adopted & Effective 9/27/94) (Rev. Adopted & Effective 12/16/98) (a) APPLICABILITY This rule shall apply to any stationary

More information

Draft Air Individual Permit Part 70 Reissuance

Draft Air Individual Permit Part 70 Reissuance Draft Air Individual Permit Part 70 Reissuance 10900008-101 Permittee: Facility name: Mayo Clinic Mayo Clinic Hospital Saint Marys Campus 1216 2nd St SW Rochester, MN 55902-1906 Olmsted County Expiration

More information

RULE 4702 INTERNAL COMBUSTION ENGINES PHASE 2 (Adopted August 21, 2003; Amended June 16, 2005; Amended April 20, 2006; Amended January 18, 2007)

RULE 4702 INTERNAL COMBUSTION ENGINES PHASE 2 (Adopted August 21, 2003; Amended June 16, 2005; Amended April 20, 2006; Amended January 18, 2007) RULE 4702 INTERNAL COMBUSTION ENGINES PHASE 2 (Adopted August 21, 2003; Amended June 16, 2005; Amended April 20, 2006; Amended January 18, 2007) 1.0 Purpose The purpose of this rule is to limit the emissions

More information

PERMIT TO INSTALL. Table of Contents

PERMIT TO INSTALL. Table of Contents Permit No. 206-14 Page 1 of 27 PERMIT TO INSTALL Table of Contents Section Page Alphabetical Listing of Common Abbreviations / Acronyms... 2 General Conditions... 3 Special Conditions... 5 Emission Unit

More information

6/1/2011. NSPS and MACT Standards for Combustion Sources at Utility Authorities What happens when a permit has both federal and state regulations?

6/1/2011. NSPS and MACT Standards for Combustion Sources at Utility Authorities What happens when a permit has both federal and state regulations? Presented by Richard M. Cestone, PE, CHMM Birdsall Services Group For NJEWA Conference May 9, 2011 What happens when a permit has both federal and state regulations? 1 Facilities get confused with Federal

More information

AIR EMISSION PERMIT NO IS ISSUED TO NORTHERN STATES POWER COMPANY

AIR EMISSION PERMIT NO IS ISSUED TO NORTHERN STATES POWER COMPANY AIR EMISSION PERMIT NO. 12300012-002 IS ISSUED TO NORTHERN STATES POWER COMPANY NSP - HIGH BRIDGE GENE 501 Shepard Road St. Paul, Ramsey County, Minnesota 551023004 The emission units, control equipment

More information

2017Compliance Table with methods.xlsx

2017Compliance Table with methods.xlsx University of Michigan Renewable Operating Permit Annual Monitoring/Recordkeeping Compliance Table January 1, 2017 through December 31, 2017 Permit Condition Emission Unit: EU-B0260-06 Boiler 6 at Central

More information

Full Compliance Evaluation Report Off-Site Report

Full Compliance Evaluation Report Off-Site Report STATE OF NEW HAMPSHIRE DEPARTMENT OF ENVIRONMENTAL SERVICES AIR RESOURCES DIVISION Full Compliance Evaluation Report Off-Site Report CONCORD STEAM CORPORATION 105 ½ PLEASANT STREET CONCORD, NH 03302-1377

More information

AIR EMISSION PERMIT NO IS ISSUED TO. St Cloud State University 720 South Fourth Avenue St Cloud, Stearns County, Minnesota 56301

AIR EMISSION PERMIT NO IS ISSUED TO. St Cloud State University 720 South Fourth Avenue St Cloud, Stearns County, Minnesota 56301 AIR EMISSION PERMIT NO. 14500026-001 IS ISSUED TO St Cloud State University 720 South Fourth Avenue St Cloud, Stearns County, Minnesota 56301 The emission units, control equipment and emission stacks at

More information

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. July 29, 2016 PERMIT TO INSTALL D

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. July 29, 2016 PERMIT TO INSTALL D MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION July 29, 2016 PERMIT TO INSTALL 222-10D ISSUED TO Yanfeng Global Automotive Interior Systems LOCATED AT 5050 Kendrick Street SE Kentwood,

More information

TITLE DEPARTMENT OF ENVIRONMENTAL MANAGEMENT

TITLE DEPARTMENT OF ENVIRONMENTAL MANAGEMENT 250-RICR-120-05-8 TITLE 250 - DEPARTMENT OF ENVIRONMENTAL MANAGEMENT CHAPTER 120 - AIR RESOURCES SUBCHAPTER 05 - AIR POLLUTION CONTROL PART 8 - Sulfur Content of Fuels 8.1 Purpose The purpose of this regulation

More information

3. Operation of any applicable boiler on any amount of fuel oil shall be prohibited, except as provided in Subsection C.3.

3. Operation of any applicable boiler on any amount of fuel oil shall be prohibited, except as provided in Subsection C.3. VENTURA COUNTY AIR POLLUTION CONTROL DISTRICT RULE 59 - ELECTRICAL POWER GENERATING EQUIPMENT - OXIDES OF NITROGEN EMISSIONS (Adopted 10/6/69, Revised 5/23/72, 7/18/72, 10/31/72, 8/14/79, 12/7/82, 6/4/91,

More information

RICE NESHAP ZZZZ (>500 hp Non-Emergency CI Engines) Altorfer Meeting June 15, 2010

RICE NESHAP ZZZZ (>500 hp Non-Emergency CI Engines) Altorfer Meeting June 15, 2010 RICE NESHAP ZZZZ (>500 hp Non-Emergency CI Engines) Altorfer Meeting June 15, 2010 Discussion Topics Background Important Terms Applicability Compliance Deadlines Emission/Operating Limits Performance/Compliance

More information

AIR EMISSION PERMIT NO IS ISSUED TO INTERSTATE POWER COMPANY

AIR EMISSION PERMIT NO IS ISSUED TO INTERSTATE POWER COMPANY AIR EMISSION PERMIT NO. 09100007-002 IS ISSUED TO INTERSTATE POWER COMPANY INTERSTATE POWER - FOX LAKE STATION County Road 28 Sherburn, Martin County, Minnesota 561710367 The emission units, control equipment

More information

PERMIT TO INSTALL. Table of Contents

PERMIT TO INSTALL. Table of Contents Permit No. 68-12B Page 1 of 16 PERMIT TO INSTALL Table of Contents Section Page Alphabetical Listing of Common Abbreviations / Acronyms... 2 General Conditions... 3 Special Conditions... 5 Emission Unit

More information

Well Pad Operations. Pennsylvania s GP-5A for Sources at Unconventional Natural Gas Well Sites

Well Pad Operations. Pennsylvania s GP-5A for Sources at Unconventional Natural Gas Well Sites Comparison of Pennsylvania Requirements, EPA Rules, and CSSD Requirements for Methane & VOC Emission Reduction for the Oil & Gas Industry Effective August 8, 2018 Air Quality Permit Category No 38 Exemption

More information

DEP7007CC Compliance Certification

DEP7007CC Compliance Certification Commonwealth of Kentucky Natural Resources & Environmental Protection Cabinet Department for Environmental Protection DIVISION FOR AIR QUALITY DEP7007CC Compliance Certification Division Use Only ID# Permit

More information

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 100. AIR POLLUTION CONTROL

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 100. AIR POLLUTION CONTROL TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 100. AIR POLLUTION CONTROL SUBCHAPTER 39. EMISSION OF VOLATILE ORGANIC COMPOUNDS (VOCS) IN NONATTAINMENT AREAS AND FORMER NONATTAINMENT AREAS PART

More information

Tune-up Information. Owners and operators of all biomass-fired and oil-fired area source boilers.

Tune-up Information. Owners and operators of all biomass-fired and oil-fired area source boilers. Tune-up Information National Emission Standards for Hazardous Air Pollutants for Area Sources: Industrial, Commercial, and Institutional Boilers 40 CFR Part 63 Subpart JJJJJJ Who must conduct a tune-up

More information

Permit Holder. Permitted Equipment

Permit Holder. Permitted Equipment Air Quality Registration Stationary Compression Ignition Internal Combustion Engine (Less than 400 Brake Horsepower) Permit No. Project No. Description Date Testing No Plant Number: Under the Direction

More information

STATEMENT OF BASIS. Cherokee Nitrogen LLC Cherokee, Alabama Colbert County Facility Number

STATEMENT OF BASIS. Cherokee Nitrogen LLC Cherokee, Alabama Colbert County Facility Number STATEMENT OF BASIS Cherokee Nitrogen LLC Cherokee, Alabama Colbert County Facility Number 701-0013 Introduction On June 30, 2017, the Department received an application to renew the Title V Major Source

More information

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. May 1, 2015 PERMIT TO INSTALL 4-13B. ISSUED TO Zoetis LLC

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION. May 1, 2015 PERMIT TO INSTALL 4-13B. ISSUED TO Zoetis LLC MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION May 1, 2015 PERMIT TO INSTALL 4-13B ISSUED TO Zoetis LLC LOCATED AT 306 Pitcher Street Kalamazoo, Michigan IN THE COUNTY OF Kalamazoo STATE

More information

AIR QUALITY PERMIT. Kennesaw State University - Marietta Campus

AIR QUALITY PERMIT. Kennesaw State University - Marietta Campus AIR QUALITY PERMIT Permit No. Effective Date February 11, 2016 In accordance with the provisions of the Georgia Air Quality Act, O.C.G.A. Section 12-9-1, et seq and the Rules, Chapter 391-3-1, adopted

More information

MassDEP 310 CMR 7.00 Air Repair Air Pollution Control Amendments Effective March 9, 2018

MassDEP 310 CMR 7.00 Air Repair Air Pollution Control Amendments Effective March 9, 2018 MassDEP 310 CMR 7.00 Air Repair Air Pollution Control Effective March 9, 2018 Massachusetts Chemistry & Technology Alliance November 29, 2018 Key Definitions 310 CMR 7.00 Computation of Time 310 CMR 7.01

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Minnesota Power Division of ALLETE Inc

AIR EMISSION PERMIT NO IS ISSUED TO. Minnesota Power Division of ALLETE Inc AIR EMISSION PERMIT NO. 13700013-006 IS ISSUED TO Minnesota Power Division of ALLETE Inc MINNESOTA POWER - LASKIN ENERGY CENTER 5699 Colby Lake Road Hoyt Lakes, St. Louis County, MN 55750 The emission

More information

3. GENERAL CONDITIONS

3. GENERAL CONDITIONS 2 3. GENERAL CONDITIONS a) This Plan Approval authorizes the construction of a 272 net megawatt waste coal-fired, circulating fluidized bed boiler by Robinson Power Company (RPC), P. O. Box 127, Burgettstown,

More information

Jon Konings Former CEM Coordinator

Jon Konings Former CEM Coordinator Jon Konings Former CEM Coordinator Not covering every detail of these QA topics. There is such a wide variation in the configuration of hardware out there, and I can t cover everything, so I will address

More information

AUTHORITY TO CONSTRUCT

AUTHORITY TO CONSTRUCT ISSUED BY: DATE ISSUED: TBD JORGE DeGUZMAN DATE EXPIRES: TBD ISSUED TO: SACRAMENTO MUNICIPAL UTILITY DISTRICT FINANCING AUTHORITY (SFA) COSUMNES POWER PLANT LOCATION: 14295A CLAY EAST RD., HERALD, CA 95638

More information

Reproduction of Permit Terms and Conditions

Reproduction of Permit Terms and Conditions Page 1 of 92 This version of facility specific terms and conditions was converted from a database format to an HTML file during an upgrade of the Ohio EPA, Division of Air Pollution Control's permitting

More information

; # RECEIVED 8 JUN2/ AH 10= 1% NOx Proposed Rulemaking [38 Pa.B. 1831] Page 1 of 1. Tate, Michele. From: Harris, Andy

; # RECEIVED 8 JUN2/ AH 10= 1% NOx Proposed Rulemaking [38 Pa.B. 1831] Page 1 of 1. Tate, Michele. From: Harris, Andy NOx Proposed Rulemaking [38 Pa.B. 1831] Page 1 of 1 Tate, Michele ; # RECEIVED From: Harris, Andy [Andy_Harris@pghcorning.com] 8 JUN2/ AH 10= 1% Sent: Monday, June 23, 2008 4:08 PM NirpEWWT RCfil IIATAOV

More information

SUPPLEMENT to PERMIT No Woodspecs, Inc. Waterford, Michigan September 6, 2000 GENERAL CONDITIONS

SUPPLEMENT to PERMIT No Woodspecs, Inc. Waterford, Michigan September 6, 2000 GENERAL CONDITIONS SUPPLEMENT to PERMIT No. 165-00 Woodspecs, Inc. Waterford, Michigan GENERAL CONDITIONS 1. Rule 201(1) - The process or process equipment covered by this permit shall not be reconstructed, relocated, altered,

More information

PERMIT TO INSTALL. Table of Contents

PERMIT TO INSTALL. Table of Contents Permit No. 19-18 Page 1 of 49 PERMIT TO INSTALL Table of Contents Section Page Alphabetical Listing of Common Abbreviations / Acronyms... 2 General Conditions... 3 Special Conditions... 5 Emission Unit

More information

AIR EMISSION PERMIT NO IS ISSUED TO. City of Virginia

AIR EMISSION PERMIT NO IS ISSUED TO. City of Virginia AIR EMISSION PERMIT NO. 13700028-003 IS ISSUED TO City of Virginia 620 South 2nd Street Virginia, St. Louis County, Minnesota 55792 The emission units, control equipment and emission stacks at the stationary

More information

FINAL PERMIT APPLICATION REVIEW SUMMARY

FINAL PERMIT APPLICATION REVIEW SUMMARY FINAL PERMIT APPLICATION REVIEW SUMMARY New Hampshire Department of Environmental Services Air Resources Division P.O. Box 95, 29 Hazen Drive Concord, NH 03302-0095 Phone: 603-271-1370 Fax: 603-271-7053

More information

Prepared for: BP-Husky Refining LLC 4001 Cedar Point Road Oregon, Ohio Prepared by:

Prepared for: BP-Husky Refining LLC 4001 Cedar Point Road Oregon, Ohio Prepared by: BP-HUSKY REFINING LLC REVISION TO FCCU WET GAS COMPRESSOR RECONSTRUCTION PERMIT TO INSTALL (04-01482) TO INCORPORATE FINAL FCCU NO X EMISSIONS LIMITS Prepared for: BP-Husky Refining LLC 4001 Cedar Point

More information

Public Service Company of Colorado THE SOURCE TO WHICH THIS PERMIT APPLIES IS DESCRIBED AND LOCATED AS FOLLOWS:

Public Service Company of Colorado THE SOURCE TO WHICH THIS PERMIT APPLIES IS DESCRIBED AND LOCATED AS FOLLOWS: COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT AIR POLLUTION CONTROL DIVISION TELEPHONE: (303) 692-3150 CONSTRUCTION PERMIT PERMIT NO: 11PB859 DATE ISSUED: JULY 5, 2005 INITIAL APPROVAL Modification

More information

Huntington Power Plant. Notice of Intent. Submitted to the Utah Division of Air Quality And Prepared by

Huntington Power Plant. Notice of Intent. Submitted to the Utah Division of Air Quality And Prepared by Huntington Power Plant Notice of Intent Submitted to the Utah Division of Air Quality And Prepared by 1407 West North Temple Salt Lake City, Utah 84116 April 11, 2008 1.0 Introduction PacifiCorp Energy

More information

Public Service Company of Colorado THE SOURCE TO WHICH THIS PERMIT APPLIES IS DESCRIBED AND LOCATED AS FOLLOWS:

Public Service Company of Colorado THE SOURCE TO WHICH THIS PERMIT APPLIES IS DESCRIBED AND LOCATED AS FOLLOWS: COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT AIR POLLUTION CONTROL DIVISION TELEPHONE: (303) 692-3150 CONSTRUCTION PERMIT PERMIT NO: 04PB1019 DATE ISSUED: JULY 5, 2005 INITIAL APPROVAL ISSUED TO:

More information

PERMIT TO INSTALL. Table of Contents

PERMIT TO INSTALL. Table of Contents Permit No. 1-18 Page 1 of 14 PERMIT TO INSTALL Table of Contents Section Page Alphabetical Listing of Common Abbreviations / Acronyms... 2 General Conditions... 3 Special Conditions... 5 Emission Unit

More information

TABLE B: SUBMITTALS. Fiscal Services 520 Lafayette Road North, St. Paul, Minnesota

TABLE B: SUBMITTALS. Fiscal Services 520 Lafayette Road North, St. Paul, Minnesota TABLE B: SUBMITTALS Table B lists most of the submittals you must provide. Table B is divided into three sections; one-time submittals or notifications, intermittent submittals or notifications and recurring

More information

Variation Notice with introductory note

Variation Notice with introductory note Variation Notice with introductory note Pollution Prevention and Control Regulations 2000 Dudley Energy from Waste Facility MES Environmental Ltd Lister Road Dudley West Midlands DY2 8JT. Variation Notice

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Rochester Public Utilities for Two Standby/Peaking Diesel-Fired Generator Sets

AIR EMISSION PERMIT NO IS ISSUED TO. Rochester Public Utilities for Two Standby/Peaking Diesel-Fired Generator Sets AIR EMISSION PERMIT NO. 10901019-002 IS ISSUED TO Rochester Public Utilities for Two Standby/Peaking Diesel-Fired Generator Sets Rochester Public Utilities 3605 Highway 52 North Rochester, Olmsted County,

More information

Major Amendment December 29, 1999 Total Facility Operating Permit February 12, 1996

Major Amendment December 29, 1999 Total Facility Operating Permit February 12, 1996 AIR EMISSION PERMIT NO. 03700015-001 IS ISSUED TO Northern States Power Company NSP - Inver Hills Generating Plant 3185 117th Street Inver Grove Heights, Dakota County, Minnesota 55077 The emission units,

More information

RULE 2280 PORTABLE EQUIPMENT REGISTRATION (Adopted October 20, 1994; Amended May 16, 1996)

RULE 2280 PORTABLE EQUIPMENT REGISTRATION (Adopted October 20, 1994; Amended May 16, 1996) RULE 2280 PORTABLE EQUIPMENT REGISTRATION (Adopted October 20, 1994; Amended May 16, 1996) 1.0 Purpose The purpose of this rule is to provide an administrative mechanism, and establish standards for registration

More information

August 23,

August 23, RULE 411, NO X FROM BOILERS, PROCESS HEATERS AND STEAM GENERATORS Adopted 02-02-95 (Amended 11/7/96, 01/09/97, 7/22/99, 10/27/05, 8/23/07) INDEX 100 GENERAL 101 PURPOSE 102 APPLICABILITY 110 EXEMPTION

More information

A high level overview of the federal NSPS and NESHAP rules as they apply to owner/operators of internal combustion engines

A high level overview of the federal NSPS and NESHAP rules as they apply to owner/operators of internal combustion engines A high level overview of the federal NSPS and NESHAP rules as they apply to owner/operators of internal combustion engines Presented by: Brandon Guillory & Andy Goldberg AWMA October 29, 2009 1 New Source

More information

TIER 3 MOTOR VEHICLE FUEL STANDARDS FOR DENATURED FUEL ETHANOL

TIER 3 MOTOR VEHICLE FUEL STANDARDS FOR DENATURED FUEL ETHANOL 2016 TIER 3 MOTOR VEHICLE FUEL STANDARDS FOR DENATURED FUEL ETHANOL This document was prepared by the Renewable Fuels Association (RFA). The information, though believed to be accurate at the time of publication,

More information

Part 70 Operating Permit Amendment

Part 70 Operating Permit Amendment Part 70 Operating Permit Amendment Permit Amendment No.: 2436-211-0013-V-03-1 Effective Date: July 25, 2014 Facility Name: Facility Address: Mailing Address: Parent/Holding Company: Georgia-Pacific Wood

More information

Overview of Revisions to the Proposed GP-5A and GP-5 and Emissions Discussion

Overview of Revisions to the Proposed GP-5A and GP-5 and Emissions Discussion Overview of Revisions to the Proposed GP-5A and GP-5 and Emissions Discussion Oil and Gas Technical Advisory Board February 14, 2018 Tom Wolf, Governor Patrick McDonnell, Secretary Background All air pollution

More information

Multi-Sector Air Pollutants Regulations (MSAPR) May 2017

Multi-Sector Air Pollutants Regulations (MSAPR) May 2017 Multi-Sector Air Pollutants Regulations (MSAPR) May 2017 Purpose The Multi-Sector Air Pollutants Regulations (MSAPR) came into force on June 17, 2016 This presentation will provide an overview of: MSAPR

More information

(2) ANNUAL HEAT INPUT means the actual amount of heat released by fuels burned in a unit during a calendar year.

(2) ANNUAL HEAT INPUT means the actual amount of heat released by fuels burned in a unit during a calendar year. 1 of 11 8/21/2012 10:19 AM SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT RULE 1146 - EMISSIONS OF OXIDES OF NITROGEN FROM INDUSTRIAL, INSTITUTIONAL, AND COMMERCIAL BOILERS, STEAM GENERATORS, AND PROCESS

More information

ENGINEERING CALCULATION SHEET AIR RESOURCES DIVISION

ENGINEERING CALCULATION SHEET AIR RESOURCES DIVISION SIC Code: 4911 (Energy Production) DATE: 06/17/2005 Page 1 of 6 DATE APPLICATION RECEIVED: March 31, 2004 (Application # FY04-0427) FACILITY DESCRIPTION Pinetree-Bethlehem (the Permittee) operates a 17.1

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Northern Natural Gas Company

AIR EMISSION PERMIT NO IS ISSUED TO. Northern Natural Gas Company AIR EMISSION PERMIT NO. 16300110-001 IS ISSUED TO Northern Natural Gas Company NORTHERN NATURAL GAS - HUGO No Street Address Hugo, Washington County, Minnesota 55038 The emission units and emission stacks

More information

COST EFFECTIVENESS EVALUATION. A. Selective Catalytic Reduction System

COST EFFECTIVENESS EVALUATION. A. Selective Catalytic Reduction System was installed with a Selective Catalytic Reduction (SCR) and is able to comply with a NOx emission limit of 9 ppmv when operating with natural gas and 13 ppmv when operating under diesel fuel. In addition,

More information

US oil production hits 15-year high: DEC 04, 2012

US oil production hits 15-year high: DEC 04, 2012 Setting a New Standard!! US oil production hits 15-year high: DEC 04, 2012 Domestic crude oil production in September hit the highest monthly output since 1998, according to the U.S. Energy Information

More information

RULE BOILERS, STEAM GENERATORS, AND PROCESS HEATERS (Adopted 5/11/93, Revised 6/13/95, 6/13/00, 9/11/12)

RULE BOILERS, STEAM GENERATORS, AND PROCESS HEATERS (Adopted 5/11/93, Revised 6/13/95, 6/13/00, 9/11/12) VENTURA COUNTY AIR POLLUTION CONTROL DISTRICT RULE 74.15.1 - BOILERS, STEAM GENERATORS, AND PROCESS HEATERS (Adopted 5/11/93, Revised 6/13/95, 6/13/00, 9/11/12) A. Applicability The provisions of this

More information

AIR EMISSION PERMIT NO Total Facility Operating Permit - Reissuance IS ISSUED TO. Mayo Foundation

AIR EMISSION PERMIT NO Total Facility Operating Permit - Reissuance IS ISSUED TO. Mayo Foundation AIR EMISSION PERMIT NO. 10900008-004 Total Facility Operating Permit - Reissuance IS ISSUED TO Mayo Foundation St Marys 1216 Southwest 2nd Street Rochester, Olmsted County, MN 55902 The emission units,

More information

ICAPCD RULE APPENDIX C

ICAPCD RULE APPENDIX C There is not a federal policy that establishes maximum cost effectiveness values for NOx RACT. The San Joaquin Valley APCD uses a BARCT threshold of $9,700.00 (California Air Resources Board (CARB), Report

More information