Station 130 (Maple) Compressor Upgrade Project

Size: px
Start display at page:

Download "Station 130 (Maple) Compressor Upgrade Project"

Transcription

1 Station 130 (Maple) Compressor Upgrade Project Application August 2012 Supplied to: The Secretary National Energy Board 444 7th Avenue SW Calgary, Alberta T2P 0X8

2 TransCanada Pipelines Limited APPENDIX E1 ENGINEERING AND TECHNICAL DESCRIPTION

3 Page 1 of PROJECT OVERVIEW This Project involves the relocation, refurbishment and installation of two Solar Mars 100 C65 turbo-compressor packages at the existing Maple compressor station (Station 130). The two units will be designated as Unit B1 and B2, and will be permanent units that operate in parallel with the existing European gas turbine Tornado unit, which is currently designated as Unit P. The A plant s reciprocating compressor units currently located at the station are not expected to operate regularly in parallel with the new plant, and are scheduled for deactivation by the end of PRINCIPAL COMPONENTS OF PROJECT The main components of the Project are: one new steel frame compressor building designed to house both Solar Mars 100 turbo compressor packages a skid-mounted control building to contain the motor control centre, station control panel and the uninterruptible power supply a skid-mounted utility building to house the air compressors, air dryers, air bottles and a glycol heating system a skid-mounted auxiliary power unit (APU) building along with an auxiliary generator unit a skid-mounted building used to house the station control panel, supervisory control and data acquisition system and general office space a single dry-type, pad-mounted step-down transformer for the primary incoming electrical feed yard piping, primarily consisting of NPS 42 Grade 483 MPa submerged arc welded (SAW) pipe with a wall thickness of 16 mm Appendix E-2 is a plot plan showing the location of the new components at Station 130. The compressor unit building in the yard, designated as Unit B, is shown as Item 11 on the plot plan. The utility building is labeled as Item 12. The APU building is labeled as Item 13 and the control building is labeled as Item 14. Also depicted on the plot plan are the suction scrubber, the discharge lines leading to the station blowdown, and the station relief lines. 2.1 Relocated Equipment The Project includes the reuse of driver skids from two Solar 90 Mars turbo compressor packages from other TransCanada compressor station sites. These driver skids will be mated to a new C65-2 natural gas compressor. The skids will be

4 Page 2 of 10 completed, refurbished and updated by Solar Turbines to include new dry low emissions controls technology. 3. STANDARDS AND SPECIFICATIONS Name The proposed compressor station unit additions will be designed, constructed and tested in accordance with the provisions of the Onshore Pipelines Regulations, 1999, TransCanada s specifications and the following standards: CSA Z662-11, Oil and Gas Pipelines ASME B , Process Piping CSA Z , Steel Line Pipe CSA Z , Steel Fittings CSA Z , Steel Valves CSA C22.1 Electrical Code, Part 1, Safety Standards for Electrical Installations CSA C22.2 No- 0-M91, General Requirements Canadian Electrical Code, Part II 2007 ASME Boiler and Pressure Vessel Code, Section VIII, Division 1: Pressure Vessels National Building Codes of Canada (2005) and Ontario Building Code (2012) Table 3-1 provides a preliminary list of the TransCanada standards and specifications that will be used for this Project. A final list of applicable standards and specifications will evolve as project planning progresses through detailed design and as individual specifications and procedures are added, updated or replaced to incorporate legislative and regulatory changes, and technological advances. Table 3-1: Preliminary List of TransCanada Standards and Specifications TES-MATL-MD1 Piping System Materials for Pipeline, Compression and Metering Facilities TES-MATL-PV1 Specification for Pressure Vessels TES-FLGE-LD Specification for Carbon Steel Buttwelding Flanges TES-FITG-LD Specification for Carbon Steel Buttwelding Fittings, Grade 290 and Higher EDMS No. Effective Date Rev No. Content Name Dec-02 0 Pipe Apr Pressure Vessel Nov Flange Dec Fitting TES-FITG-EC1 Specification for End Closures Apr Fitting TES-FITG-CIF Specification for Contoured Mar Fitting Insert Fittings (Cdn-US)

5 Page 3 of 10 Name Table 3-1: Preliminary List of TransCanada Standards and Specifications EDMS No. Effective Date Rev No. Content Name TES-FITG-T01 Instrument Tube Fitting, Apr Fitting Instrument Pipe Fitting and Tubing Material Specification TES-PIPE-SAW Specification for Double Sep Pipe Submerged Arc Welded Pipe TES-VALV-LD Specification for Steel Valves Oct Valve TES-VOPR-GH Gas Hydraulic Valve Operator Specification TES-HYDRO-HT1 Primary Test Specs for Hydrostatic Testing New Buried, Pipelines, Compressor Station & Meter Station Piping TES-HYDRO-HT2 Secondary Test Specs for Fully Exposed Pipe, Valves & Piping Assemblies (Hydrostatic or N2 Testing) TES-HYDRO-HTS Hydrostatic Testing Specification TES-WELD-AS Welding of Assemblies and Station Piping TES-NDT-RT Radiographic Examination of Pipeline and Facilities Welds (Cdn) TES-CP-MS Cathodic Protection Materials Specification (Cdn-US) TES-COAT-FBE External Fusion Bond Epoxy for Steel Pipe (Cdn-US) TES-COAT-P1 Paint Systems for Above Ground Facilities (Non-Coastal) (Cdn-US- Mex) Nov-99 0 High Pressure System May Hydrotesting May Hydrotesting May Hydrotesting Apr Joint, Weld Mar Joint, Weld Oct Cathodic Protection Jan Coating, Protection Oct Coating, Protection TES-PROJ-EXC Excavation Specification Jan Excavation TES-DV Excavating, Backfilling and Dec-09 0 Excavation Site Grading

6 Page 4 of FILING MANUAL GUIDANCE 4.1 Compression Table 4-1 provides information identified in the Filing Manual guidance for compression facilities. Table 4-1: Filing Manual Guidance for Compression Filing Guidance Type and power of pumps/compressors Fuel type and source of pumps/compressors MOP, inlet and outlet design pressures Inlet and outlet temperature Station schematic of buildings, relief valves Project Information Two Solar Mars 100 C65 turbo-compressor packages consisting of a Solar Mars T15000S SoLoNox engine (nominal ISO at 11.9 MW) and Solar C65-2 centrifugal compressor. The compressor package employs an aero-derivative gas turbine prime mover, which runs on pipeline quality natural gas. The natural gas is taken from the suction piping and is then filtered and regulated prior to injection into the combustors of the gas turbine. The station operating MOP is 6450 kpag. Inlet and outlet piping is designed to operate at 7240 kpag. Inlet and outlet design temperature -45C to +75C. The compressor building will be designed to withstand loads as defined by the Ontario Building Codes, National Building Code, the Project service loads, and applicable climatic conditions for the area. The compressor building will be a free-standing steel rigid-frame structure, supported by reinforced concrete grade beams and piles and completed with acoustically designed walls and roof. All auxiliary buildings are skid mounted and will be supported on steel driven piles. The buildings are complete with heating and ventilation equipment. The discharge relief valve/blow off valve will be sized for maximum rated flow rate from the compressor at a relief pressure as prescribed by TransCanada s Operating Procedure for Compressor Station Pressure Limits and Settings for the Canadian Mainline System. The design relief set pressure is 6720 kpag. Basic description of surge control system, pressure control and overpressure control Similarly, the suction relief valve/blow off valve will be sized in the same manner and the set pressure will also be 6720 kpag. The recycle (anti-surge) valve is connected downstream of the compressor nozzle and upstream of the compressor discharge valve. The surge control valve is controlled by the unit Program Logic Controller (PLC) so as to ensure sufficient flow is available through the compressor at all times. Under conditions of extremely high head and low flow, the surge valve will open, permitting gas to circle back into the compressor through the recycle piping. The unit PLC will ensure that the anti surge valve will not close the unit valve until the

7 Page 5 of 10 Table 4-1: Filing Manual Guidance for Compression Filing Guidance Project Information compressor has come to a complete stop. Unit discharge pressure is controlled by the unit PLC which provides suitable commands to the compressor package to either slow or shut down the compressor when high pressures are encountered. The maximum set point of the discharge pressure controller is the MOP of 6450 kpag. Basic description of emergency shutdown Description of boilers and pressure vessels System overpressure control is provided by a pressure limiting system and a pressure relieving system. The pressure limiting system consists of a Step-To-Idle (STI) control function to slow down the compressor or a high pressure shut down (HPSD) control setting to shut down the compressor when the discharge pressure reaches 6585 kpag. The pressure relieving system consists of the suction and discharge pressure relief valve/blow off valves. Each relief valve/blow off valve is designed to ensure that the piping pressure will not exceed 6720 kpag under any condition. An emergency shutdown (ESD) pushbutton will be installed at all personnel doors in the compressor building and near the scrubber. Perimeter ESD pushbuttons will be added to all new gates and tied into existing fence ESD. New site ESD pushbutton will be added to the control panel in the relocated control building. ESD pushbuttons will trigger a station ESD. Fire and/or gas detection in new compressor building will also trigger a station ESD. Fire detection in the auxiliary buildings will cause an alarm. The suction scrubber will be designed to handle the design flow. Automatic liquid level control will be performed by the station PLC by actuating pneumatic operated control valves that will drain the scrubber liquids to an aboveground storage tank via an above ground cyclone separator. A local pneumatic (natural gas) supply will be used to provide power gas to the liquid level valves. The scrubber will have a pressure differential gauge, pressure gauge, suction temperature RTD and thermowell. Boilers enclosed in the mechanical skid are expected as part of the glycol heating system for the units. Description of corrosion control elements All new pressure vessels will be built to TransCanada s specification for pressure vessels TES-MATL-PV1 Specification for Pressure Vessels. Active cathodic protection (CP) will be incorporated, as appropriate.

8 Page 6 of Pipe Table 4-2 provides information identified in the Filing Manual guidance for pipe. Table 4-2: Filing Manual Guidance for Yard Piping Additions Filing Guidance High-pressure pipe - outside diameter (OD) Pipe wall thickness (WT) and grade Maximum operating pressure Length Location Burial depth 1067 mm (NPS 42) Project Information Suction and discharge high 16.0 mm WT Grade 483 pressure pipe (NPS 42) Yard Piping (NPS 30) 16.4 mm WT Grade 483 Yard Piping (NPS 24) 9.2 mm WT Grade 483 Yard Piping (NPS 20) 8.2 mm WT Grade 448 Inlet and outlet piping is designed to operate at 7240 kpag. Approximately 250 m of NPS 42, 250 m of NPS 30, 110 m of NPS 24, and 90 m of NPS N and W (approximately 1 km northwest of Vaughan, Ontario) 1.2 m The minimum depth of cover will also comply with all applicable federal, provincial, territorial, municipal and county regulations. Coatings Product carried Description of corrosion control elements External coating fusion bond epoxy (FBE) The proposed facilities will transport sweet natural gas, which meets TransCanada s gas quality specifications, as outlined in the TransCanada tariff. Both aboveground and belowground piping will be coated. Belowground piping will be coated with FBE as per TransCanada s specification TES-COAT-FBE External Fusion Bond Epoxy for Steel Pipe (Cdn-US). Aboveground piping will be coated with paint as per TES-COAT-P1 Paint Systems for Above Ground Facilities (Non-Coastal) (Cdn-Us- Mex). Crossings CP will be provided either by existing TransCanada facilities or the installation of new CP facilities. The requirement for additional CP facilities will be determined during detailed design. A postconstruction CP survey will be conducted to confirm the operation of the CP system and modifications will be made, if necessary. Not applicable.

9 Page 7 of CAPABILITY IMPACT OF THE PROPOSED FACILITIES Table 5-1 provides capability versus requirements information for TransCanada s design season (i.e., peak winter day with loss of critical unit). This table shows that with the new firm contractual requirements of 130,107 GJ/d and without the proposed facilities, system capability would be short by 152 TJ/d. Figures 5-1 and 5-2 are capability flow schematics for the same two conditions, i.e., without and with the proposed facilities. When reading the values on Figure 5-1 and 5-2, note that: The Flow into Station 130 differs from the addition of Barrie Start and Montreal Line Start by the fuel amount listed in the compressor tables at the bottom of each schematic. The Parkway Receipts differs from the Flow into Station 130 by the amount of deliveries at Parkway and between the two points. This value is shown as Parkway to Maple Deliveries. When comparing capability values between Figures 5-1 and 5-2, note the following changes to TransCanada s design since its 2012 Eastern Mainline Expansion application (NEB Filing ID A35884). the installation of the applied for facilities the deactivation of the Station 130 A plant reduces the available power shown in the with facilities schematic the increase in the transient pressure buffer at Parkway by 125 kpa as a result of the impact of the unit additions on transient gas flows in the area the capability shortfall without the proposed facilities (152 TJ/d) is greater than the new contracts (130 TJ/d) because of gas temperature increases at the Parkway receipt point the capability shortfall resulting from the gas temperature increase is also overcome by adding the proposed facilities

10 Page 8 of 10 Table 5-1: Capabilities versus Requirements Ontario Triangle (Peak Winter 2013/2014) Peak Winter Contracts Loss of Unit Without With Proposed Facilities (TJ/d) Proposed Facilities (TJ/d) Ontario Triangle Requirements 1. North Bay Short Cut Deliveries Montreal Line Deliveries Barrie Line Deliveries Trans Quebec & Maritimes Deliveries Niagara Line Deliveries Compressor fuel Total Delivery Requirements (1 through 6) Supply Requirements 8. Northern Ontario Line Supply Parkway Requirement (7-8) Parkway Capability 10. Parkway Supply Capability Excess from Parkway 11. Parkway Supply Excess (10-9)

11 Page 9 of 10 Figure 5-1: Capability Schematic (Without Proposed Facilities) To Stn To Stn 136 Barrie Start 24, m 3 /d 917,423 GJ/d Flow into Station , m 3 /d Montreal Line Start 1,928,594 GJ/d 26, m 3 /d 1,009,713 GJ/d Flow Bypassing Stn , m 3 /d Parkway to Maple Deliveries 1,143,439 GJ/d 8, m 3 /d 329,141 GJ/d Parkway Parkway Receipts 59, m 3 /d 2,257,735 GJ/d 6125 kpa From Union Gas To Niagara Domestic m 3 /d 0GJ/d Compressor Station Data in 10 6 m 3 T /d STN MWA MWR P Suc P Dis Ratio Fuel Flow TS/TD 7/22 21/36 7/42 Station 130 Flow Schematic System Capability Peak Winter Day LOU without Facilities Operating Year: 2013/ Page 1/1

12 Page 10 of 10 Figure 5-2: Capability Schematic (With Proposed Facilities) To Stn To Stn 136 Barrie Start 29, m 3 /d 1,126,370 GJ/d Flow into Station , m 3 /d Montreal Line Start 2,089,850 GJ/d 25, m 3 /d 957,424 GJ/d Parkway to Maple Deliveries 8, m 3 /d 329,140 GJ/d Parkway Parkway Receipts 64, m 3 /d 2,418,990 GJ/d 6000 kpa From Union Gas To Niagara Domestic m 3 /d 0GJ/d B Compressor Station Data in 10 6 m 3 T /d STN MWA MWR P Suc P Dis Ratio Fuel Flow TS/TD 13/25 19/38 10/45 Station 130 Flow Schematic System Capability Peak Winter Day LOU with Facilities Operating Year: 2013/ Page 1/1

13 TransCanada Pipelines Limited Appendix E2 Plot Plan Page 1 of 1

TAB B. Hydrotest Summary Report. Piping Specifications and Procedures. Pipe Manufacturers. Order XG-N Application for Leave to Open

TAB B. Hydrotest Summary Report. Piping Specifications and Procedures. Pipe Manufacturers. Order XG-N Application for Leave to Open NOVA Gas Transmission Ltd. Alces River B2 Compressor Station Order XG-N081-026-2015 Application for Leave to Open TAB B Hydrotest Summary Report Piping Specifications and Procedures Pipe Manufacturers

More information

COMPRESSOR STATION OPERATIONS

COMPRESSOR STATION OPERATIONS CONTENTS FIGURES AND TABLES... viii PREFACE... xi ACKNOWLEDGEMENTS... xiii CHAPTER 1. INTRODUCTION... 1 Scope and Outline... 1 Types of Stations... 2 Production Stations... 2 Storage Stations... 3 Transmission

More information

Mercy Hospital of Buffalo Catholic Health System 2 nd Floor Patient Holding Center 3 rd Floor Locker Rooms Shaflucas Architects, PC Project No.

Mercy Hospital of Buffalo Catholic Health System 2 nd Floor Patient Holding Center 3 rd Floor Locker Rooms Shaflucas Architects, PC Project No. SECTION 23 22 13 STEAM AND CONDENSATE PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Ferrostaal Industrieanlagen GmbH - Germany

Ferrostaal Industrieanlagen GmbH - Germany Ferrostaal Industrieanlagen GmbH - Germany Ferrostaal Christof Romania SRL - Romania A Joint Venture of Ferrostaal and the Christof Group OMV PETROM Hurezani Gas Delivery Project Compressor Station Bulbuceni

More information

PUBLIC WORKS AND SERVICES PETROLEUM PRODUCTS DIVISION STANDARD DETAILED DRAWINGS FOR NORTHERN FUEL STORAGE AND DISTRIBUTION FACILITIES

PUBLIC WORKS AND SERVICES PETROLEUM PRODUCTS DIVISION STANDARD DETAILED DRAWINGS FOR NORTHERN FUEL STORAGE AND DISTRIBUTION FACILITIES PUBLIC WORKS AND SERVICES PETROLEUM PRODUCTS DIVISION STANDARD DETAILED DRAWINGS FOR NORTHERN FUEL STORAGE AND DISTRIBUTION FACILITIES 3rd EDITION - 01/2006 Foreword This publication, together with the

More information

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations Code Requirements for ASTs at Motor Vehicle-Dispensing Stations This table compares aboveground storage tank requirements in the 2015 edition of, to the 2015 International Fire Code (). Please note that

More information

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 12/12/2017

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 12/12/2017 Abnormal Operating Conditions Outside of 101.01 Room Abnormal Operating Conditions Inside of 101.02 Room 102.01 Measure Structure-to-Soil Potentials 102.02 Advanced Cathodic Testing 102.03 Active Corrosion/MIC

More information

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS SECTION 221123.13 - DOMESTIC-WATER PACKAGED BOOSTER PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 8/24/2018

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 8/24/2018 Abnormal Operating Conditions Outside of 101.01 Room Abnormal Operating Conditions Inside of 101.02 Room 102.01 Measure Structure-to-Soil Potentials 102.02 Advanced Cathodic Testing 102.03 Active Corrosion/MIC

More information

DRAWING INDEX 1 07/01/2013. Company Project Project Number Location Revision Date

DRAWING INDEX 1 07/01/2013. Company Project Project Number Location Revision Date DRAWING INDEX Company Project Project Number Location Revision Date LEGACY OIL & GAS INC. PIERSON PILINE TO EOG 12069 VARIOUS LSD ISSUED FOR APPROVAL January 4, 2013 Drawing No. Client No. Description

More information

ENGINEERING STANDARD FOR MACHINERY PIPING

ENGINEERING STANDARD FOR MACHINERY PIPING ENGINEERING STANDARD FOR MACHINERY PIPING CONTENTS : PAGE No. 0. INTRODUCTION... 2 1. SCOPE... 3 2. REFERENCES... 3 3. UNITS... 4 4. PIPING DESIGN FOR MACHINERIES... 4 4.1 General... 4 4.2 Pumps... 5 4.3

More information

CONTENTS. Foreword...iii. 1. Introduction...1

CONTENTS. Foreword...iii. 1. Introduction...1 Installation of Aboveground Storage Systems for Motor-Vehicle Fueling CONTENTS Foreword...iii SECTIONS 1. Introduction...1 1.1 Background...1 1.2 Purpose...1 1.3 Scope...1 1.4 Source...1 1.5 Use of PEI/RP100...1

More information

HPG Range. Direct High-Pressure Gas Valve Actuators. Redefining Flow Control

HPG Range. Direct High-Pressure Gas Valve Actuators. Redefining Flow Control PG Range Direct igh-pressure Gas Valve Actuators Redefining Flow Control Rotork Actuators Quality Controlled Rotork is a global leader in valve actuation technology. We provide a comprehensive range of

More information

Precision Air Drilling Services Equipment Information & Specifications

Precision Air Drilling Services Equipment Information & Specifications Equipment Information & Specifications Joy Super Booster Specifications Joy WB-12 5000 Specifications Page 2 of 10 Table of Contents Joy Super Booster Specifications... 2 Joy WB-12 5000 Specifications...

More information

DCP Midstream Contractor Covered Task List Last updated 7/11/2018

DCP Midstream Contractor Covered Task List Last updated 7/11/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 007 Operate Valves 008 Measurement of Wall Thickness with Ultrasonic Device 009 Movement and/or Relocation of Liquid Pipelines 195.424 011 Inspect,

More information

Dominion Energy Questar Pipeline LLC Contractor Covered Task List Last updated 10/3/2017

Dominion Energy Questar Pipeline LLC Contractor Covered Task List Last updated 10/3/2017 007 Operate Valves 008 Measurement of Wall Thickness with Ultrasonic Device 103 Non-destructive Testing (Other than testing of welds) -- Mag Particle 104 Non-destructive Testing (Other than testing of

More information

PEI/RP Recommended Practices for Installation of Bulk Storage Plants

PEI/RP Recommended Practices for Installation of Bulk Storage Plants PEI/RP800-08 Recommended Practices for Installation of Bulk Storage Plants Recommended Practices for Installation of Bulk Storage Plants CONTENTS Foreword...iii. SECTIONS 1. Introduction Page 1.1 Background...1

More information

Columbia Pipeline Group Contractor Covered Task List Last updated 1/8/2018

Columbia Pipeline Group Contractor Covered Task List Last updated 1/8/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral

More information

Direct Contact Desuperheaters

Direct Contact Desuperheaters Control Description Spirax Sarco direct contact desuperheaters reduce the temperature of superheated steam to produce steam temperatures approaching saturation temperature to cool the superheated steam,

More information

ASMECourseCatalog.

ASMECourseCatalog. ASMECourseCatalog www.energyu.org www.midwestenergy.org ASME Abnormal Operating Conditions... 6 ASME GAS01 Hazards of Natural Gas and Prevention of Accidental Ignition... 6 ASME 0001 Measure Structure-to-Electrolyte

More information

Tennessee Gas Pipeline. Enfield Customer Meeting October 19, 2016

Tennessee Gas Pipeline. Enfield Customer Meeting October 19, 2016 1 Tennessee Gas Pipeline Enfield Customer Meeting October 19, 2016 Agenda Brian Merchant Director, Engineering Gas Control, KMI East Region Ron Besette Director, OPS, Division 10 Office, KMI East Region

More information

SECTION PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY

SECTION PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY SECTION 230533 - PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pressure gages. 2. Pressure gage taps. 3. Thermometers. 4. Thermometer supports. 5. Test plugs. 6. Static pressure

More information

Requirements for Dispensing of Compressed Natural Gas. Yvonne Espinoza, PE Austin Fire Department Engineering Services

Requirements for Dispensing of Compressed Natural Gas. Yvonne Espinoza, PE Austin Fire Department Engineering Services Requirements for Dispensing of Compressed Natural Gas Yvonne Espinoza, PE Austin Fire Department Engineering Services Course Overview Enforcement of code requirements Application of code requirements Hazard

More information

Direct Contact Desuperheaters

Direct Contact Desuperheaters Local regulations may restrict the use of this product to below the conditions quoted. In the interests of development and improvement of the product, we reserve the right to change the specification without

More information

PRESSURE RELIEF / SUSTAINING CONTROL VALVES

PRESSURE RELIEF / SUSTAINING CONTROL VALVES PROJECT NAME LOCATION PRESSURE RELIEF / SUSTAINING CONTROL VALVES INTRODUCTION This specification covers the design, manufacture, and testing of 1 in. (25 mm) through 36 in. (900 mm) Control Valves PART

More information

Boardwalk Pipeline Partners, LP Contractor Covered Task List Last updated 9/17/2018

Boardwalk Pipeline Partners, LP Contractor Covered Task List Last updated 9/17/2018 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral 005 Repair Breakout Tank Overfill Protective Devices 195.428

More information

Please note this is a condensed catalog. For a complete version, contact Velan directly.

Please note this is a condensed catalog. For a complete version, contact Velan directly. Please note this is a condensed catalog. For a complete version, contact Velan directly. VELAN VALVES IN POWER With an installed base covering over 300 nuclear power plants and over 2,000 thermal power

More information

22 Kg/Sq.cm gauge at 55deg C. As per Design Code requirement. 100% requiredfor entire vessel

22 Kg/Sq.cm gauge at 55deg C. As per Design Code requirement. 100% requiredfor entire vessel LPG PRESSURE VESSEL FOR AUTO LPG PURPOSE S.NO. DESCRIPTION 1 Service Propane PARTIES CONFIRMATION 2 Type Underground 3 Design Code ASME - Sec VIII- Div II 4 Capacity (Water) KL 7.5 KL / 10 KL 5 Working

More information

BUREAU OF STANDARDS. Effective Date: 8/19/2016 Section No. 4. Version: 1.2 Procedure No. 3

BUREAU OF STANDARDS. Effective Date: 8/19/2016 Section No. 4. Version: 1.2 Procedure No. 3 BUREAU OF STANDARDS Effective Date: 8/19/2016 Section No. 4 Version: 1.2 Procedure No. 3 TITLE: LP Gas Bulk Plant Final Inspection PURPOSE: This document details the procedures used to conduct a Final

More information

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS SECTION 22 1123.13 DOMESTIC-WATER PACKAGED BOOSTER PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Southern Star Central Gas Pipeline Contractor Covered Task List Last updated 8/15/2018

Southern Star Central Gas Pipeline Contractor Covered Task List Last updated 8/15/2018 007 Operate Valves 008 Measurement of Wall Thickness with Ultrasonic Device 018 Inspect Navigable Waterway Crossing 195.412(b) 201 Abnormal Operating Conditions Related to Welding on Pipelines 192.225

More information

SECTION (15444) - DOMESTIC WATER PACKAGED BOOSTER PUMPS

SECTION (15444) - DOMESTIC WATER PACKAGED BOOSTER PUMPS SECTION 22 11 23.13 (15444) - DOMESTIC WATER PACKAGED BOOSTER PUMPS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Packaged Domestic Water Booster Pumps B. Related Sections: 1.02 REFERENCES 1. Section

More information

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations Code Requirements for ASTs at Motor Vehicle-Dispensing Stations This table compares aboveground storage tank requirements in the 2008 edition of NFPA 30A, and the 2006 International Fire Code (IFC). Please

More information

GO Range. Gas-over-Oil Valve Actuators. Redefining Flow Control

GO Range. Gas-over-Oil Valve Actuators. Redefining Flow Control GO Range Gas-over-Oil Valve Actuators Redefining Flow Control Rotork Actuators Quality Controlled Rotork is a global leader in valve actuation technology. We provide a comprehensive range of valve actuators,

More information

Saddle Butte Rockies Midstream LLC Contractor Covered Task List Last updated 12/6/2017

Saddle Butte Rockies Midstream LLC Contractor Covered Task List Last updated 12/6/2017 003 Test Breakout Tank Overfill Protective N/A 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective N/A 195.428 Oral 005 Repair Breakout Tank Overfill Protective N/A 195.428 007 Operate

More information

Enbridge Gas Transmission and Midstream and Enbridge Liquid Pipelines (Express-Platte) Contractor Covered Task List Last updated 8/30/2018

Enbridge Gas Transmission and Midstream and Enbridge Liquid Pipelines (Express-Platte) Contractor Covered Task List Last updated 8/30/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral

More information

GH Hydro Kits. Technical Information. Ref: N

GH Hydro Kits. Technical Information. Ref: N GH Hydro Kits Ref: N-27167 0507 Technical Information Johnson Controls Manufacturing España, S.L. is participating in the EUROVENT Certification Program. Products are as listed in the EUROVENT Directory

More information

Williams Contractor Covered Task List Last updated 11/7/2017

Williams Contractor Covered Task List Last updated 11/7/2017 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral 005 Repair Breakout Tank Overfill Protective Devices 195.428

More information

STANDARDS and SPECIFICATIONS

STANDARDS and SPECIFICATIONS ANSI (American National Standards Institute) ANSI B31.4 - Liquid petroleum transportation piping system. ANSI B31.4 - Gas transmission and distribution piping system. API (American Petroleum Institute)

More information

M A N I T O B A ) Order No. 42/14 ) THE PUBLIC UTILITIES BOARD ACT ) April 23, 2014

M A N I T O B A ) Order No. 42/14 ) THE PUBLIC UTILITIES BOARD ACT ) April 23, 2014 M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) BEFORE: Régis Gosselin, B ès Arts, M.B.A., C.G.A., Chair Larry Soldier, Member Marilyn Kapitany, B.Sc. (Hons.), M.Sc., Member Neil Duboff, B.A. (Hons.),

More information

NOVA Gas Transmission Ltd. Appendix 2: 2013 Facility Status Update (December)

NOVA Gas Transmission Ltd. Appendix 2: 2013 Facility Status Update (December) Appendix 2: Facility Status Update () This section describes the current status of facilities that were applied for, are under construction or have been placed on-stream since the 2012 Annual Plan was

More information

Northern Natural Gas Contractor Covered Task List Last updated 4/26/2018

Northern Natural Gas Contractor Covered Task List Last updated 4/26/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral

More information

COVERED TASK Conduct Cathodic Protection Surveys 1 DESCRIPTION ELEMENTS OF TASK 4 PART QUESTION NOTES ABNORMAL OPERATING CONDITIONS

COVERED TASK Conduct Cathodic Protection Surveys 1 DESCRIPTION ELEMENTS OF TASK 4 PART QUESTION NOTES ABNORMAL OPERATING CONDITIONS COVERED Conduct Cathodic Protection Surveys 1 Annual surveys are conducted for each operator s pipeline system that is under cathodic protection to ensure that the protection is adequate. This task is

More information

FIXED CONE VALVE. The flow is guided by the inner vanes, in order to decrease the vortex and the vibration;

FIXED CONE VALVE. The flow is guided by the inner vanes, in order to decrease the vortex and the vibration; BEI JI NG JOI NTFLOW SYSTEM CO. FI XEDCONEVALVE The Fixed cone Valve is typically operated by a manual, electric or hydraulic actuator mounted above the bevel gear. The bevel gear transmits torque to the

More information

SECTION H3 TRAYMASTER SERIES DEAERATORS

SECTION H3 TRAYMASTER SERIES DEAERATORS SECTION H3 TRAYMASTER SERIES DEAERATORS SAMPLE SPECIFICATIONS PART 1 GENERAL... H3-12 1.1 Packaged Deaerator Specification... H3-12 PART 2 PRODUCTS... H3-12 2.1 Deaerator... H3-12 2.2 Deaerator Vessel...

More information

SECTION VIII. (Sub-section 430) Wastewater Valves and Appurtenances. 1. General thru Gate Valves thru 430-3

SECTION VIII. (Sub-section 430) Wastewater Valves and Appurtenances. 1. General thru Gate Valves thru 430-3 SECTION VIII (Sub-section 430) Wastewater Valves and Appurtenances Article Page 1. General 430-1 thru 430-2 2. Gate Valves 430-2 thru 430-3 3. Plug Valves 430-3 thru 430-4 4. Check Valves 430-4 5. Tapping

More information

Series 500 Valves. Product Catalogue. Series 500 Valves. Series 500 Valves. Catalogue. Edition 10/2012

Series 500 Valves. Product Catalogue. Series 500 Valves. Series 500 Valves. Catalogue. Edition 10/2012 Series 500 Valves Product Catalogue Catalogue Areas Of Activity Waterworks Dorot s valves are especially designed to comply with all the demands of Waterworks systems such as Pressure Management, Low Flow

More information

PRODUCT OVERVIEW. Our BDB (Bolted Body) and BW3 (Fully Welded Body) trunnion-mounted ball valves are designed and manufactured

PRODUCT OVERVIEW. Our BDB (Bolted Body) and BW3 (Fully Welded Body) trunnion-mounted ball valves are designed and manufactured PRODUCT OVERVIEW For over 30 years, FluoroSeal has been manufacturing and customizing a wide range of valves, and accessories for many industries including Oil & Gas, Petrochemical, Chemical, Mining, Pharmaceutical,

More information

Sealweld Sales, Services and Training Saving clients Billions by preventing costly shutdowns and prolonging Valve and Actuator life since 1969

Sealweld Sales, Services and Training Saving clients Billions by preventing costly shutdowns and prolonging Valve and Actuator life since 1969 Sealweld Sales, Services and Training Saving clients Billions by preventing costly shutdowns and prolonging Valve and Actuator life since 1969 Presented By: Ward Hruza Branch Manager Houston, TX Knowledgeable

More information

TransCanada US Contractor Covered Task List Last updated 9/27/2018

TransCanada US Contractor Covered Task List Last updated 9/27/2018 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral 005 Repair Breakout Tank Overfill Protective Devices 195.428

More information

m-csg Ultra-compact Clean Steam Generation System

m-csg Ultra-compact Clean Steam Generation System Local regulations may restrict the use of this product to below the conditions quoted. In the interests of development and improvement of the product, we reserve the right to change the specification without

More information

PRESSURE RELIEF / SURGE ANTICIPATOR CONTROL VALVE

PRESSURE RELIEF / SURGE ANTICIPATOR CONTROL VALVE PROJECT NAME LOCATION PRESSURE RELIEF / SURGE ANTICIPATOR CONTROL VALVE INTRODUCTION This specification covers the design, manufacture, and testing of 2-1/2 in. (65 mm) through 18 in. (450 mm) Control

More information

Dangerous Goods. Transport Tanks

Dangerous Goods. Transport Tanks Dangerous Goods and Rail Safety Dangerous Goods, Rail Safety & 511 A Technical Publication from the Co-ordination and Information Centre Dangerous Goods Transport Tanks July 2017 - 1 - This material is

More information

Reliable Reduction of Chemical Usage in Field Injection Pumps

Reliable Reduction of Chemical Usage in Field Injection Pumps Reliable Reduction of Chemical Usage in Field Injection Pumps Shawn French President, Voodoo Injection Management Ltd. Mark Scantlebury President and CEO, Extreme Telematics Corp. 2 ETC Background ETC

More information

Energy Transfer Partners LP Contractor Covered Task List Last updated 12/10/2018

Energy Transfer Partners LP Contractor Covered Task List Last updated 12/10/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 005

More information

Applications. Compressor-Features The Vilter Advantages. LNG Boil Off Gas Gathering BIO - Gas Digester CO 2 Nitrogen Hydrogen Refrigerant

Applications. Compressor-Features The Vilter Advantages. LNG Boil Off Gas Gathering BIO - Gas Digester CO 2 Nitrogen Hydrogen Refrigerant Parallex TM Slide System - It s the key to part load efficiencies far superior to twin screw compressors. Capacity and volume slides move independently of each other based on load, eliminating over or

More information

CATERPILLAR 3516B DP2 System

CATERPILLAR 3516B DP2 System CATERPILLAR 3516B DP2 System CONTENTS System Overview 3 Offshore Rig or Ship DP2 Package 3 Main Generator Diesel Skid 3 Main Generator Diesel Engines 3 Instrument, Alarms and Automatic Start/Stop System

More information

Features 1. Differential Latch-type, lightweight, dependable

Features 1. Differential Latch-type, lightweight, dependable Bulletin 516 Rev. B Model DDX-SS Deluge Valve (100mm), (150mm) & (200mm) Bulletin 516 Rev. B Features 1. Differential Latch-type, lightweight, dependable construction. 2. Easily trimmed for releasing by:

More information

Horizontal Pre-Piped Bladder Tanks with Proportioner

Horizontal Pre-Piped Bladder Tanks with Proportioner DATA SHEET Horizontal Pre-Piped Bladder Tanks with Proportioner Features Pre-piped configurations with a wide selection of proportioner sizes, including the ANSUL FLOWMAX CL for closed-head sprinkler systems

More information

AUTOMATIC PIG LAUNCHING

AUTOMATIC PIG LAUNCHING AUTOMATIC PIG LAUNCHING Forged Ball Valves 4,000 PSI Production Optimization and Corrosion Mitigation for High Frequency and Remote Pigging Applications SPECIFICATIONS Spec. 6D 0225 Edmonton, AB, Canada

More information

Regional Market Trends Forum April 21, 2016 Hartford, CT. Mike Dirrane Director, Northeast Marketing

Regional Market Trends Forum April 21, 2016 Hartford, CT. Mike Dirrane Director, Northeast Marketing Regional Market Trends Forum April 21, 2016 Hartford, CT Mike Dirrane Director, Northeast Marketing Spectra Energy s Portfolio of Assets Based in Houston, TX with operations in 30 states Transports 15%

More information

Vertical Pre-Piped Bladder Tanks with Proportioner

Vertical Pre-Piped Bladder Tanks with Proportioner DATA SHEET Vertical Pre-Piped Bladder Tanks with Proportioner Features Pre-piped configurations with a wide selection of proportioner sizes, including the ANSUL FLOWMAX CL for closed-head sprinkler systems

More information

VAD Variable Area Desuperheaters

VAD Variable Area Desuperheaters Local regulations may restrict the use of this product to below the conditions quoted. In the interests of development and improvement of the product, we reserve the right to change the specification without

More information

STEAM TURBINE BY-PASS AND STEAM CONDITIONING VALVE

STEAM TURBINE BY-PASS AND STEAM CONDITIONING VALVE STEAM TURBINE BY-PASS AND STEAM CONDITIONING VALVE Benefits Savings of up to US$ 200.000 per year in maintenance costs Production gains due to superior stability of the temperature control Operational

More information

NITIN CORPORATION 402, 4 th Floor, Bezzola Commercial Complex, Sion Trombay Road, Chembur, Mumbai , India.

NITIN CORPORATION 402, 4 th Floor, Bezzola Commercial Complex, Sion Trombay Road, Chembur, Mumbai , India. NITIN CORPORATION 402, 4 th Floor, Bezzola Commercial Complex, Sion Trombay Road, Chembur, Mumbai 400071, India. WEB : www.corponit.com E MAIL : nitincorporation@yahoo.com enquiry@corponit.com PH (O) :

More information

Centrifugal Chiller. PF/PFH Size: 063. Replacement Parts List No Revision V 05/2012

Centrifugal Chiller. PF/PFH Size: 063. Replacement Parts List No Revision V 05/2012 Replacement Parts List No. 057113900 Revision V 05/2012 Centrifugal Chiller PF/PFH Size: 063 To find your Daikin McQuay parts distributor, call 1-800-377-2787 or visit www.daikinmcquay.com Contents Parts

More information

Model MTB-ASME Vertical Pre-Piped Bladder Tanks

Model MTB-ASME Vertical Pre-Piped Bladder Tanks DATA SHEET Model MTB-ASME Vertical Pre-Piped Bladder Tanks Features n Pre-piped configurations with a wide selection of proportioner sizes, including the SKUM TPW-150 MK2 for closedhead sprinkler systems

More information

DV-5a Automatic Water Control Valve Single Interlock Preaction Fire Protection Systems 1-1/2 Inch to 8 Inch (DN40 to DN200) General Description

DV-5a Automatic Water Control Valve Single Interlock Preaction Fire Protection Systems 1-1/2 Inch to 8 Inch (DN40 to DN200) General Description Worldwide Contacts www.tyco-fire.com DV-5a Automatic Water Control Valve Single Interlock Preaction Fire Protection Systems 1-1/ Inch to Inch (DN40 to DN00) General Description The TYCO DV-5a Automatic

More information

Series Direct contact, metal-to-metal seating, make the globe valve ideal for most shut-off applications. Features

Series Direct contact, metal-to-metal seating, make the globe valve ideal for most shut-off applications. Features Direct contact, metal-to-metal seating, make the globe valve ideal for most shut-off applications. Features General application Designed for ASME boiler and pressure vessel code, section I applications

More information

Schedule A to the Memorandum of Understanding. Between the Oil and Gas Commission and British Columbia Safety Authority

Schedule A to the Memorandum of Understanding. Between the Oil and Gas Commission and British Columbia Safety Authority Schedule A to the Memorandum of Understanding Between the Oil and Gas Commission and British Columbia Safety Authority Joint Regulation of Pipeline System Unfired Pressure Vessel Clarification of MOU Responsibilities

More information

HYDRAULIC QUARTER TURN ACTUATOR GAS OVER OIL

HYDRAULIC QUARTER TURN ACTUATOR GAS OVER OIL HYDRAULIC QUARTER TURN ACTUATOR GAS OVER OIL series GOOR SERVOVALVE spa Via Quasimodo 27-20010 S.STEFANO TICINO (MI) PHONE: 0039-029748461 FAX: 0039-0297484646 E-mail: servovalve@servovalve.it RTO Rev.

More information

EnLink Midstream Contractor Covered Task List Last updated 11/8/2017

EnLink Midstream Contractor Covered Task List Last updated 11/8/2017 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 005 Repair Breakout Tank Overfill Protective Devices 195.428

More information

.4 Emergency and normal vents and terminations. .1 CAN/CSA-B139-09, Installation Code for Oil Burning Equipment.

.4 Emergency and normal vents and terminations. .1 CAN/CSA-B139-09, Installation Code for Oil Burning Equipment. Shoal Lake Intake Fuel Storage and Delivery System Rehabilitation Page 1 of 10 1. GENERAL 1.1 Scope.1 The following statement generally describes the scope of work covered by this Section. All tank volumes

More information

SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR RUBBER-SEATED BUTTERFLY VALVES 3 INCHES THROUGH 72 INCHES ANSI/AWWA C504 Class 150/250 December 2012

SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR RUBBER-SEATED BUTTERFLY VALVES 3 INCHES THROUGH 72 INCHES ANSI/AWWA C504 Class 150/250 December 2012 SAN ANTONIO WATER SYSTEM SPECIFICATIONS FOR RUBBER-SEATED BUTTERFLY VALVES 3 INCHES THROUGH 72 INCHES ANSI/AWWA C504 Class December 2012 1. SCOPE This product specification covers class rubber-seated butterfly

More information

PBV s Engineering Excellence At Work

PBV s Engineering Excellence At Work PBV s Engineering Excellence At Work The PBV Series 5700/6700 Three-Piece, Side-Entry, Trunnion Ball Valve 2"- 56" ANSI Class 150/300,600,900,1500 & 2500 In Full And Standard Port PBV trunnion ball valves

More information

Noble Energy Contractor Covered Task List Last updated 2/20/2019

Noble Energy Contractor Covered Task List Last updated 2/20/2019 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 005 Repair Breakout Tank Overfill Protective Devices 195.428

More information

General Installation Instructions for Valves and Gates

General Installation Instructions for Valves and Gates General Installation Instructions for Valves and Gates Thank you for your purchase of a Lorenz valve. We appreciate your business! Please read this installation manual and follow recommended safety precautions.

More information

Model MTB-ASME Horizontal Pre-Piped Bladder Tanks

Model MTB-ASME Horizontal Pre-Piped Bladder Tanks DATA SHEET Model MTB-ASME Horizontal Pre-Piped Bladder Tanks Features n Pre-piped configurations with a wide selection of proportioner sizes, including the SKUM TPW-150 MK2 for closedhead sprinkler systems

More information

Chemical Injection Pump. Quick Start Guide. Pump Models P-075-M1/ ALU P-075-M1/ SS CLASS 1 DIV 1

Chemical Injection Pump. Quick Start Guide.   Pump Models P-075-M1/ ALU P-075-M1/ SS CLASS 1 DIV 1 Chemical Injection Pump Quick Start Guide Pump Models P-075-M1/8-1750-12 ALU P-075-M1/8-1750-12-SS CLASS 1 DIV 1 Overview SPEC Chemical Injection Pump - Quick Start Guide SPEC Chemical Injection Pumps

More information

Tank Farm Additional Storage Site Layout

Tank Farm Additional Storage Site Layout MONTREAL TRUDEAU INTERNATIONAL AIRPORT MIFFC Fuel Committee Meeting Montreal Airport Marriott Hotel, June 15, 2017 Tank Farm Additional Storage Site Layout 1 Tank Farm Additional Storage - Construction

More information

Energy Transfer Partners LP Contractor Covered Task List Last updated 3/2/2018

Energy Transfer Partners LP Contractor Covered Task List Last updated 3/2/2018 001 Provide Security for Pipeline Facilities 195.436 Oral 003 Test Breakout Tank Overfill Protective Devices 195.428 Oral 004 Inspect and Calibrate Breakout Tank Overfill Protective Devices 195.428 Oral

More information

Technical Specification

Technical Specification Technical Specification including performance data Project 3 x 9CM25 rev 2. consisting of 3 Caterpillar Diesel Generator sets Type 9CM25 with site output of: 2475 bkw at each engine flywheel rated 750

More information

THOMAS. Unifit Series. Couplings & Flange Adaptors Non Restrained Products PIPE PRODUCTS

THOMAS. Unifit Series. Couplings & Flange Adaptors Non Restrained Products PIPE PRODUCTS THOMAS Couplings & Flange Adaptors Non Restrained Products PIPE PRODUCTS Unifit Series Universal Pipe Couplings and Flange Adaptors for all Rigid Pipe H1 COUPLINGS & FLANGE ADAPTORS - NON RESTRAINED BELLVILLE

More information

McQuay Air-Cooled Reciprocating Chiller ALR

McQuay Air-Cooled Reciprocating Chiller ALR Replacement Parts List No. 057115200 Revision S 07/2015 McQuay Air-Cooled Reciprocating Chiller ALR Sizes 010-185 Vintage D Last Manufactured: 2000 To find your Daikin Applied parts distributor, call 1-800-377-2787

More information

Installation and Service Manual

Installation and Service Manual Solar Production Equipment Corp Chemical Injection Pump Installation and Service Manual Pump Models P-075-M1/8-1750-12 ALU P-075-M1/8-1750-12-SS CLASS 1 DIV 1 Table of Contents Overview... 4 Pump Specifications

More information

Updated: April 1, Releases Reported by Trans Mountain February 2017 (Updated: April 1, 2017)

Updated: April 1, Releases Reported by Trans Mountain February 2017 (Updated: April 1, 2017) Releases Reported by Trans Mountain - 1961- February 2017 (Updated: April 1, 2017) Trans Mountain has a comprehensive safety and preventative maintenance program that includes the protection of stream

More information

ASME B31.8 INTERPRETATIONS VOLUME 13

ASME B31.8 INTERPRETATIONS VOLUME 13 ASME B31.8 INTERPRETATIONS VOLUME 13 Replies to Technical Inquiries July 2001 Through December 2003 Interpretations 13-1 Through 13-8 It has been agreed to publish intepretations issued by the B31 Committee

More information

050040, Республика Казахстан, г. Алматы, Бостандыкский район, проспект Аль Фараби, д.77/7, н.п. 14А, 15-й этаж Телефон/факс:

050040, Республика Казахстан, г. Алматы, Бостандыкский район, проспект Аль Фараби, д.77/7, н.п. 14А, 15-й этаж Телефон/факс: Technical Data Xioms dual FBE Coating System for coating welded pipe joints with a nominal outside diameter of 4" to 48", consists of a semi automatic coating module that is suspended on a side boom or

More information

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107

More information

HPUs Hydraulic Power Units

HPUs Hydraulic Power Units HPUs Hydraulic Power Units DESIGN PHILOSOPHY Shafer has been manufacturing hydraulic power units (HPUs) for over 40 years. The primary industries we serve are natural gas, oil and water. The majority of

More information

LINE SILENCER. Copyright 2009 by PULSCO Incorporated. All rights reserved. Reproduction without permission is prohibited.

LINE SILENCER. Copyright 2009 by PULSCO Incorporated. All rights reserved. Reproduction without permission is prohibited. LINE SILENCER Copyright 2009 by PULSCO Incorporated. All rights reserved. Reproduction without permission is prohibited. PRODUCT GUIDE PULSCO LINE SILENCER TABLE OF CONTENTS DESCRIPTION PAGE PULSCO LINE

More information

HTX-HTH SEPARATORS I&O MANUAL

HTX-HTH SEPARATORS I&O MANUAL INSTALLATION OPERATIONS AND MAINTENANCE HTX-HTH SEPARATORS I&O MANUAL 1365 N. Clovis Avenue Fresno, California 93727 (559) 255-1601 www.lakos.com LS-714B (Rev. 11/17) TABLE OF CONTENTS Table of Contents...

More information

Field Application of Fuel Cells Increasing Energy Security. Jon Rice, Ultra Electronics

Field Application of Fuel Cells Increasing Energy Security. Jon Rice, Ultra Electronics Field Application of Fuel Cells Increasing Energy Security Jon Rice, Ultra Electronics 734-330-3520 Jon.rice@ultra-ami.com Agenda Define typical loads, systems in our market Define challenges in power

More information

Technical Manual Index

Technical Manual Index Technical Manual Index Manuals March 1, 2017 Publication Number CFMI-TP. Nomenclature Version Next CD.512-2A Shop Manual SM.6 - R82 Illustrated Parts Catalog PC.9 R62 Service Bulletins Up to Oct 17, 2016

More information

IBV Series C-LF2 Carbon Steel Inverted Bucket Vertical Steam Trap

IBV Series C-LF2 Carbon Steel Inverted Bucket Vertical Steam Trap Local regulations may restrict the use of this product to below the conditions quoted. In the interests of development and improvement of the product, we reserve the right to change the specification without

More information

RAIMONDI TRUNNION MOUNTED FULLY WELDED BALL VALVE FIGURE 5600

RAIMONDI TRUNNION MOUNTED FULLY WELDED BALL VALVE FIGURE 5600 The ideal valve to minimize any risk of fugitive emissions from flanges in the natural gas and oil industry FEATURES GENERAL APPLICATION The Fig. 5600 valves have been designed for gas transportation and

More information

McQuay Westinghouse. Centrifugal Chiller PF, PFH 063. Last Manufactured: Replacement Parts List No Revision AB 06/2018

McQuay Westinghouse. Centrifugal Chiller PF, PFH 063. Last Manufactured: Replacement Parts List No Revision AB 06/2018 Replacement Parts List No. 57113900 Revision AB 06/2018 McQuay Westinghouse Centrifugal Chiller PF, PFH 063 Last Manufactured: 2002 To find your Daikin Applied parts distributor, call 1-800-377-2787 or

More information

.3 Section Waste Management and Disposal.

.3 Section Waste Management and Disposal. Issued 2005/06/01 Section 16261 Uninterruptible Power Systems Static Page 1 of 10 PART 1 GENERAL 1.1 RELATED SECTIONS.1 Section 01330 Submittal Procedures..2 Section 01780 Closeout Submittals..3 Section

More information

DIFFERENTIAL PRESSURE BATTERY CHARGERS

DIFFERENTIAL PRESSURE BATTERY CHARGERS DIFFERENTIAL PRESSURE BATTERY CHARGERS CONVERTING PIPELINE ENERGY TO BATTERY POWER Free Uninterruptible Power 24/7 ISO 9001:2008 Certified Quality System 10-20 Watt Units Available POWER SYSTEMS 12 or

More information