1 Northern Umbrella Plan & Projects- Update November 29, 2007 Jane Petras, ATC General Manager
2 Agenda Overall Northern Umbrella Plan Update Cranberry-Conover-Plains Project: Underground Transmission Line Construction Aspen Substation Project: Demolition of Brule Substation Equipment (as time permits)
3 Northern Umbrella Plan 9 network projects in Northern Wisconsin and Upper Michigan Addresses various system issues and needs
4 NUP: Goals & Objectives Increase reliability throughout the U.P. Provide adequate voltage support to portions of Michigan and Wisconsin. Increase transfer capacity across the MI/WI border from 220 MVA to 525 MVA. Reduce or eliminate certain Binding Constraints under MISO Day 2. Provide for additional redundant service paths. Serve existing Transmission Service Requests. Create a more robust transmission grid.
5 System Prior to NUP Projects
6 Northern Umbrella Plan Projects A: Plains Stiles 138 kv Rebuild B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild C: Morgan Stiles 138 kv Rebuild D: Morgan White Clay 138 kv Up-rate E: Add 2 nd Plains Transformer F: New Werner West 345/138 kv Substation G: Cranberry Conover Plains Project H: Morgan Werner West 345 kv Line (including Clintonville Werner West 138 kv) I: New Weston Central Wisconsin 345 kv Line (for generator interconnection)
7 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather Falls LINCOLN Alexander Boulder Jct. Hilltop Sherman St. Morrison Ave. Weston White Pine Stone UPSCO GOGEBIC VILAS Ontonagon ONTONAGON Victoria Dam Bruce Crossing Land O Lakes Conover Cranberry St. Germain Pine Highway 8 MARATHON Bunker Hill Wausau Kelly Du Bay PORTAGE Northpoint Hoover Rocky Whiting Ave. Run Plover Coyne Three Lakes RPC Black Brook Hodag Venus Arnott Mass Antigo Watersmeet Twin Lakes LANGLADE WAUPACA Winona FOREST HOUGHTON M-38 Prickett MENOMINEE BARAGA Warden IRON Way Dam Lakehead Hemlock Falls DICKINSON Strawberry Hill Iron River Crystal Falls Sagola Peavy Falls Lincoln Nordic Felch Twin Lakes Randville Michigamme I Harrison Waupaca G Crandon Summit Lk. Aurora St. SHAWANO W. Shawano Badger Caroline Clintonville Werner West Laona Silver Cliff Mountain Florence Bass Lk Armory Pine Grede FLORENCE Big Q Niagara Paper Goodman Cauldron Falls High Falls OUTAGAMIE North Hintz Appleton Ellington F White Lake D CWIS Thunder White Clay E. Shawano Amberg Daves Falls MARINETTE Fox Hill Johnson Falls Sandstone Pound OCONTO Morgan H Greenstone Humboldt Lena Brule Twin Fls Falls Pioneer Roselawn Skygen Plains Champion BROWN Hoist Perch Lake Crivitz McClure See Insert A Cataract MARQUETTE MENOMINEE Alger-Delta Nathan Chalk Hills White Rapids Stiles Howard Velp Mason St. James St. Liberty Eastman Glory Rd. Red Maple C Lost Dauphin Ropes Foundry Pulliam A1 A3 Tower Dr. Preble E Highway V Myst. Hills Powers Grand Rapids KEWAUNEE Arnold Bay De Noc Menominee 30th Ave. 2nd St. Roosevelt Rd. West Marinette GREEN BAY Rosiere CEDAR LINE CLARKSBURG LINE East Krok A2 DOOR Presque Isle Marquette Dead River AuTrain Chatham KI Sawyer Gwinn Cornell Forsyth Chandler Delta West Side Harris Canal National Tilden Insert A Perkins Gladstone Mead Escanaba ALGER DELTA Empire Munising Indian Lake Lakehead LAKE SUPERIOR SCHOOLCRAFT B LAKE MICHIGAN Glen Jenks Manistique Seney Newberry Corr. Facility Engadine Hiawatha Curtis Lakehead Valley Blaney Park Gould City LUCE Lou-Pac Newberry Newberry Village Roberts Rexton Lakehead KEY 345 kv Substation 115 or 138 kv Substation <=69 kv Substation Generation 345 kv Transmission CHIPPEWA Eckerman Hulbert Trout Lake 115 or 138 kv Transmission 69 kv Transmission Proposed Projects MACKINAC Brevort Straits McGulpin Emmet Brimley Pine River Oden To Livingston
8 Completed Projects A: Plains Stiles 138 kv Rebuild Placed in-service October 2006 Cost = $94.3 million B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild Placed in-service March 2006 Cost = $52.3 million C: Morgan Stiles 138 kv Rebuild Placed in-service May 2006 Cost = $8.0 million D: Morgan White Clay 138 kv Up-rate Placed in-service March 2005 Cost = $0.4 million F: New Werner West 345/138 kv Substation Placed In-service December 2006 Cost = $12.4 million
9 In-progress Projects E: Add 2 nd Plains Transformer G: Cranberry Conover Plains Project H: Morgan Werner West 345 kv Line (including Clintonville Werner West 138 kv) I: Gardner Park Central Wisconsin 345 kv Line (for generator interconnection)
10 Second Transformer at Plains Substation Scope Add a second 345/138 kv, 250MVA transformer Schedule/Status Project planning in progress (scoping, estimating, etc.) New transformer has been ordered Planned in-service December 2009
11 Cranberry-Conover-Plains: Scope Phase 1: New 15 miles of 115kV line (overhead and underground) from Cranberry to new Lakota Road Substation with modifications at various substations including Conover SS Phase 2: Rebuild 69kV line from Conover SS to Iron River SS to 138kV including new Iron Grove SS Phases 3 and 4: Rebuild 69kV line from Iron River SS to Plains SS to 138kV (single, double and triple circuit configurations) with modifications at various substations including Aspen SS
12 Cranberry Conover Plains Project
13 Cranberry-Conover-Plains: Schedule/Status PSCW approval received November 2006, design/construction in phases Phase 1 OH line, UG line and substation design/procurement activities essential complete New easement acquisition complete except for 3 parcels Construction started Aug. 07 on UG line and in Oct. 07 on SS and OH line Planned in-service June 2008 Phase 2 OH and SS design and procurement activities underway Partial construction (Twin Lakes crossing) 1Q08 Remainder of construction 3Q08 to 1Q09 (with construction complete to Twin Lakes SS in 3Q08) Phase 3 & 4 OH line and substation design/procurement activities will start 1Q08 Construction start 2Q09 Planned in-service June 2010
14 Gardner Park-Central Wisconsin & Morgan- Werner West (GCMW): Scope Gardner Park Central Wisconsin: New approximately 50 miles 345 kv line, new Central Wisconsin 345kV switching station, expansion of Gardner Park substation Morgan Werner West: New 345 kv line approximately 51 miles of 345kV line, expansion work at Morgan, Werner West and Clintonville Substations
15 GCMW Area Map
16 GCMW: Schedule/Status PSCW approval received June 2006 Project being designed/constructed in phases Construction started January 2007 Actual physical work complete = 32% Overall planned in-service date is December 2009
17 NUP: Project Status Summary (Slide 1/2) Project Name Key Need Drivers Projected In-Service Date Projected Cost Status A: Plains Stiles 138 kv Rebuild A1: Plains Amberg A2: Amberg West Marinette Physical condition; transfer capability; solution also results in a more robust parallel path for 2/3 of P-S corridor October 2005 November 2005 $94.3M - - Complete Complete Complete A3: Amberg Stiles October Complete B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild Phase 1 Rebuild Indian Lake Glen Jenks Phase 2 Rebuild as double circuit 138 kv, operate at 69 kv TLR mitigation; voltage support; physical condition; local loadserving in Manistique area; required operating guide that splits the U.P. system August 2004 March 2006 $6.1M $46.2M Complete Complete Complete Phase 3 Convert to 138 kv operation N/A N/A Not part of the Northern Umbrella Plan C: Morgan Stiles 138 kv Rebuild as double circuit Transfer capability May 2006 $8.0M Complete
18 NUP: Project Status Summary (Slide 2/2) Project Name Key Need Drivers Projected In- Service Date Projected Cost Status D: Morgan White Clay 138 Transfer capability March 2005 $0.4M Project Complete. kv uprate (eventual rebuild as part of Element H) E: Add 2 nd Plains transformer (250 MVA 345/138 kv) Transfer capability 4Q09 $7.3M Transformer ordered, project scope, schedule and cost being defined and planned. F: New Werner West TLR mitigation, system security December 2006 $14.2M Project Complete. Substation with 345/138 kv transformer G: Cranberry Conover Plains Project Phase 1: New 115 kv Cranberry Conover Transfer capability; Transmission service; Reliability, physical condition See below June 2008 $134.6M - Construction started in August Phase 2, 3 & 4: Rebuild 69 kv Conover Plains to 138 kv June Design/procurement activities started. Will design/construct from west to east. H: New Morgan Werner West 345 kv line & Clintonville Werner West 138 kv line Transfer capability, reliability, and network service $132.3M Engineering and ROW activities continuing on Werner West Hwy 22 and Hwy 22 White Clay. Construction has begun on White Clay Morgan with the temporary line complete.. I: New Gardner Park Central Wisconsin 345 kv line & Central Wisconsin 345 kv switching station Required for new Weston 4 generation 2009 $131.5M Engineering and ROW activities continuing on Gardner Park Whitcomb. Construction complete on Belle Plain Tap Hwy 22. and complete on Caroline BPT.
19 Northern Umbrella Plan Summary Current estimated cost for all projects is $575 million Total project spending to date is approximately $294 million (through October 2007) Of the 9 projects 5 are complete and in-service 4 are in various stages of design and construction Construction and completion of all projects is expected in mid-2010
20 QUESTIONS ON NORTHERN UMBRELLA PLAN???
21 CCP Project (Phase 1): Underground 138kV Line Construction Location: approximately 2 miles of the new 15 mile line from Cranberry to Conover adjacent to the Eagle River Union Airport Design: XLPE (cross-linked polyethylene) cable in a concrete duct bank with manholes approximately every 1/3 of a mile, backfilled with sand Route: Mainly within a local paved road with other underground utilities (sewer, water, telephone, natural gas) Cost: $10.9 million Schedule: -- Duct bank/manhole construction started August Expected ductbank/manhole finish December 07 or spring of Cable installation and testing planned March 08
22
23
24 Manholes Pre-cast concrete boxes constructed offsite Manhole inside dimensions are 24 x 8 x 8 Delivered in two sections on flatbed trucks Each section weighs approximately 71,000 pounds Manholes used for pulling and splicing cable
25
26
27 71,000 pound manhole top
28
29 Lowering manhole bottom into hole
30
31 Applying waterproof seal
32
33 Lowering manhole top
34 Applying waterproof seal to manhole collar
35 Duct Bank
36
37 Shoring required due to depth and sand
38 Steel plate required over trench for road crossings
39
40
41 Concrete is poured to encase conduit
42
43 Warning tape buried above concrete
44 Sand - granular material compacted over concrete for heat dissipation
45
46 Shore box is removed for next location
47 QUESTIONS ON CCP UG CONSTRUCTION???
Northern Umbrella Plan Update. December 7, 2007
Northern Umbrella Plan Update December 7, 2007 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather
More informationNorthern Umbrella Plan Update. December 15, 2006
Northern Umbrella Plan Update December 15, 2006 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Eastom Tomahawk Grandfather Falls Boulder
More informationAmerican Transmission Company LLC Northern Umbrella Plan (NUP) Projects
American Transmission Company LLC Northern Umbrella Plan (NUP) Projects February 21, 2006 Agenda Northern Umbrella Plan Individual Project Discussion Summary System Prior to NUP Projects NUP Projects Wien
More informationNorthern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008
Northern Umbrella Plan and U.P. Capital Projects Update 2008 Transmission Business Briefing October 29, 2008 1 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake
More informationNorthern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability
Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability, 1/5/4 Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability American Transmission Company, LLC Stephen D.
More informationCapital Project Update Northern Umbrella Plan Update
Capital Project Update Northern Umbrella Plan Update Jane Petras General Manager - North Portfolio November 7, 2006 1 Overview Northern Umbrella Plan (9) Network Projects (8) Asset Renewal Transmission
More informationSection IV CHANGES TO THE YEAR ASSESSMENT
Section IV CHANGES TO THE 2003 10-YEAR ASSESSMENT This section describes the changes made by ATC to certain planned, proposed and provisional transmission projects since the 2003 10-Year Assessment was
More informationSection III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment
Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects
More informationHighly Constrained Elements Within ATC Footprint
Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market
More informationAppendix B. Summary of Changes to the Year Assessment
Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from
More informationATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --
ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20
More informationATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition
TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372
More informationState Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009
State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under
More informationAMERICAN TRANSMISSION COMPANY
AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5
More informationNortheast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report
Northeast Wisconsin/Upper Peninsula Separation 11/14/01 Incident Investigation Report Summary Contact by a high voltage electric transmission line with a tree in northeastern Wisconsin initiated a series
More informationU.P. Energy Summit February 16, 2017
U.P. Energy Summit February 16, 2017 Brett French, External Affairs Manager atcllc.com Overview ATC s Value Proposition Reliability Metrics Project updates Q&A atcllc.com 2 Providing Value to our Customers
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Presque Isle 5, 6, 7, 8, & 9: 344 MW Coal Retirement, Effective 10/15/2014 ATTACHMENT Y STUDY REPORT August 15, 2014 EXECUTIVE SUMMARY Pursuant to the Tariff, an Attachment Y Notification
More informationWisconsin Housing Statistics
Wisconsin Housing Statistics Monthly Year-to-Date Dec 2018 Dec 2017 % Change Jan-Dec 2018 Jan-Dec 2017 % Change Unit Sales 4,980 5,728-13.1% 82,760 84,594-2.2% Median Price $179,000 $170,000 +5.3% $184,000
More informationWHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018
di, WHEDA Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits Estimated Maximum Family Income Limits at 30% of HUD Estimated 2018 County Median Income Brown 16,290
More informationYear Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month
Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,
More informationRegion NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane.
Notes: 1) Costs shown in table are estimated and do not include the 4.44% Administrative Costs; 2) Material Costs includes,, and other Deicing and icing Agents; 3) Equipment Costs are based on $60 per
More informationWisconsin Local Employment & Unemployment Estimates Released
Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,
More informationRegion NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand.
NC per Hours Hours Mat'l Equip Labor Cost to ADAMS 193.2 95.64 76.0 13 28 14 11 4,318 3,474 844 18.0 0 0 76 1147.0 338.0 $1,676 $440 $340 $2,455 $473,350 0.19 IRON 249.56 163.59 192.0 0 47 16 10 7,308
More informationFlowgate 10515, an OTDF flowgate, consists of the following elements:
MAIN Report for NERC Initial Investigation NERC TLR Level 5A Flowgate 10515 Kewaunee 345/138 kv Transformer for the loss of Point Beach-North Appleton 345kV Line October 15 17, 2001 Submitted January 14,
More informationSummary Report. September The Future Grid. 10-Year Transmission System Assessment.
Summary Report September 2012 he Future Grid 10-Year ransmission System Assessment www.atc10yearplan.com Regional and inter-regional planning achieves results ransmission investments solve problems, save
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationDRAFT Design Study Report February 2015 Eagle River Traffic Mitigation Phase 1 MOA Project No Appendix D Utilities
Appendix D Utilities This page intentionally left blank. Utilities There are numerous utilities present within the project area, including natural gas, sewer, water, electric, communications, and street
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationMarket Efficiency Update
Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationTransitways. Chapter 4
4 Transitways Figure 4-1: Hiawatha LRT Train at the Lake Street/Midtown Station The 23 Transportation Policy Plan identifies a network of transitway corridors to be implemented by 23. Transitways recommended
More informationWisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits
Housing and Economic Recovery Act (HERA Special) Income and Rent Limits Income Limits * Housing and Economic Recovery Act (HERA Special) Income Limits for 2013 at 30% Family Size: ONE TWO THREE FOUR FIVE
More informationThe Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.
(Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name
More informationCase 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA
Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationChallenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America
Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Noe Bargas, PE Supervising Senior Civil Engineer Southern
More informationCA-NP-003. Newfoundland Power 2013/2014 General Rate Application Page 1 of 1
Requests for Information CA-NP-003 NP 2013/2014 GRA 1 2 3 4 5 6 Q. [ELG] Please provide the Company s depreciation request based on an ALG calculation procedure rather than the proposed ELG calculation
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationMichigan Commercial Motor Vehicles
June 2016 Revised 10/3/17 2016 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data
More informationWestern Area Power Administration
2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,
More informationSTATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV-- 0 0 TESTIMONY OF DAVID M. CAMPILII,
More informationAgenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan
Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Committee of the Whole December 1, 016 City Council December 19, 016 Agenda Item: Bids for City Project No. 7551 Lift Station No. 17 & 17A Rehabilitation Submitted by:
More informationMTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014
MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other
More informationSouth Dakota 890 Study
South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2
More informationUpdate of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI
Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative
More informationRolling Road (Route 638) Widening Project
Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public
More informationUpper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000
California Butte 6 7 R R Glenn 6 21 15 ** 7,800,306 ** Tehama 6 103 3 1,187,932 Restricted R R California Total 6 18 8,988,238 Illinois Boone 17 7 24 2,977,946 Bureau 17 11 R R Carroll 17 15 22 3,851,694
More informationSERTP rd Quarter Meeting
2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationSUMMARY REPORT. 10 Year Transmission System Assessment
2018 SUMMARY REPORT 10 Year Transmission System Assessment Agility, flexibility needed to plan for Long term transmission planning has always been a complex undertaking, but it was relatively consistent
More informationWelcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In -
Highway Gap New London to Paynesville Welcome Highway Gap New London to Paynesville Open House - Please Sign In - There is no formal presentation, but representatives are available to answer your questions.
More informationTransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal
TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission
More informationMarch 7, Subject: Southern California Edison 2011 Annual Progress Report
March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen
More informationU.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR
U.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR First place photo by Danielle Adams featuring the James L. Oberstar at anchor off Picnic Rocks, a point between the Presque Isle
More informationINFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS
INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure and Transportation Contract Services Branch 1630-215 Garry Street Winnipeg,
More informationWestern Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04
Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch
More informationCommercial assessment (decrease), estimated 24 Month ratio on 5 sales: 2019, 50.68% $(446,645)
Glen Arbor Township Assessing Officers Report - January 2019 Sales Summary 2018: The sales summary reports presented in this document contain estimates intended to facilitate discussion of market trends.
More informationTEN YEAR HISTORY OF FALL ENROLLMENTS
TEN YEAR HISTORY OF FALL ENROLLMENTS 2008 2007 F a l l S e m e s t e r 2006 2005 2004 2003 2002 2001 2000 1999 1998 0 50,000 100,000 150,000 200,000 250,000 Number of Students 3 TABLE 1: TEN YEAR HISTORY
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationWestern NY Public Policy Transmission Planning Report
Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017
More informationThe Capital Grid Project:
The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationCPG is pleased to report the following accomplishments this quarter:
MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That
More informationNetwork. ENMAX Power Corporation Network Planning & Design November 4, 2011
Network ENMAX Power Corporation Network Planning & Design November 4, 2011 ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationSub Regional RTEP Committee - Southern. August 19, 2011
Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning
More informationMetrolinx Electrification Project
Metrolinx Electrification Project Metrolinx Contract No. RQQ-2011-PP-032 Metrolinx Project No. 109503 UP EXPRESS UTILITY REPORT Document Reference No. PB 1000 March 28, 2014 Submitted to Submitted by TABLE
More informationKey to Status Fields in the Project List
Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served
More information747 ACRES LAND FOR SALE
747 ACRES LAND FOR SALE 3400 NORTH PONY EXPRESS PARKWAY, EAGLE MOUNTAIN, UTAH 84005 Salt Lake Count y Lehi 73 Sar atoga Spring s Eagle Mountain Blvd g Eagle Mountain Eagle Mountain Blvd Pony Express Pkwy
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and
More informationCTA Capital Construction Update December 12, 2006
Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction
More informationPROJECTS $500K AND OVER FOR 2012
EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)
More informationPacific Gas and Electric Company s 2013 Annual Progress Report
March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake
More informationBEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE
BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE Project Overview and Need The Bemidji-Grand Rapids 230-kV transmission line was fully energized in September of 2012 to improve reliability for the Red River
More information1 GENERAL Project Description Labrador Island Transmission Link (LIL) Language and Units Site Climate Data...
SLI Doc. No. 505573-8600-40EW-0001 02 26-Aug-2014 iii TABLE OF CONTENTS PAGE 1 GENERAL... 1 1.1 Project Description... 2 1.1.1 Labrador Island Transmission Link (LIL)... 3 1.2 Language and Units... 4 1.3
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationSECTION 1 DESCRIPTION OF THE PROPOSED PROJECT
SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT Supplemental Municipal Consultation Filing The Interstate Reliability Project 1. DESCRIPTION OF THE PROPOSED PROJECT The Connecticut Light and Power Company
More informationVERMONT ELECTRIC POWER COMPANY (VELCO)
TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first
More informationBC Hydro System 2011 Annual Progress Report
March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationManitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006
Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationCOMMERCIAL HANDBOOK 2013 EDITION MATANUSKA ELECTRIC ASSOCIATION, INC. PALMER, ALASKA
COMMERCIAL HANDBOOK 2013 EDITION MATANUSKA ELECTRIC ASSOCIATION, INC. PALMER, ALASKA ~ &teauea~. 'l«e. PtUt tjutee a'~ 2929 Pa/mete. Ata414 99645. ~~/7
More informationFORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5
ALANNA GILLIS ACTING COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL
More informationEagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013
Construction of Peña Bridge - March 2013 South Platte River Bridge Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Today s Agenda Project background Schedule Design Systems Rail cars
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationNogales Transmission, L.L.C. and Nogales Frontier Operations, L.L.C., Docket No. EL Second Supplement to Petition for Declaratory Order
Eversheds Sutherland (US) LLP 700 Sixth reet,, Suite 700 ashington, DC 20001-3980 D: +1 202.383.0838 F: +1 202.637.3593 danielfrank@ eversheds-sutherland.com June 30, 2017 Via Electronic Filing Hon. Kimberly
More informationSCHEDULE A. SPEED LIMITS (A part of Section )
SCHEDULE A SPEED LIMITS (A part of Section 340.0003) A traffic and engineering investigation having been made on the following described highways in Brown County, the maximum permissible speed at which
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationMotor Vehicle Use Map
Motor Vehicle Use Map Hiawatha National Forest Sault Ste Marie/St.Ignace Ranger Districts America s Great Outdoors Michigan / United States Department of Agriculture Forest Service Region Motor Vehicle
More informationPlan and Profile for the Black Dog Natural Gas Pipeline Project Docket No. G002/GP
414 Nicollet Mall Minneapolis, MN 55401 March 13, 2017 Daniel P. Wolf Executive Secretary Minnesota Public Utilities Commission 121 7 th Place East, Suite 350 St. Paul, MN 55101 Via Electronic Filing RE:
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationPaleozoic Geology of the Central Upper Peninsula of Michigan
Paleozoic Geology of the Central Upper Peninsula of Michigan August 22-24, 2014 Michigan Basin Geological Society Summer Excursion Led by Drs. Peter Voice and William B. Harrison III Copies of this Guidebook
More information