Network. ENMAX Power Corporation Network Planning & Design November 4, 2011

Size: px
Start display at page:

Download "Network. ENMAX Power Corporation Network Planning & Design November 4, 2011"

Transcription

1 Network ENMAX Power Corporation Network Planning & Design November 4, 2011

2 ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground 36 substations Distribution System 2,387km overhead 5,136km underground 64,554 utility poles 48,321 transformers

3 Network Service Boundary

4 ENMAX Network History 1910 Started installing conduit & manholes prior to paving 1912 Substation # 1 built to supply downtown load 1934 City council approves installation of a secondary network 1935 Secondary network started 1937 First 3-phase network transformer installed 1939 Secondary network expanded and 1 st in western Canada

5 ENMAX Network Section Secondary Network supplied via 3 major substations 13kV primary system, 56 feeders 3 voltages available 120/208v general street voltage 277/480v medium density loads 347/600v high density loads Remote Secondary Networks 3 major malls are supplied via secondary Network systems. Consist of 54 transformers with a load of 27 MVA. 25Kv High Voltage System 30 high density buildings supplied with a preferred and alternate 25kV feeder 2 substations supply the downtown 25kV system via 16 feeders. System configured such that a break before make transfer occurs within customer owned switchgear

6 ENMAX Network Fast Facts Secondary Network System Peak load of 230 MVA Service area of 8 square kilometers 875 transformers (500MVA installed capacity) 272 km underground primary HV cables (13.2kV) NO overhead primary 32kM secondary overhead cable 988 utility poles 1549kM underground conduit 653 km secondary system cable 343 street vaults 1300 manholes 410kM 3 rd party communication cable 25kV Downtown System Peak load of 130 MVA 30 major customers 50kM underground primary cables Secondary Spot Networks 3 large shopping malls (Chinook, North Hill and Westbrook) Peak load of 27MVA Supplied via distribution substations

7 What & Why a Secondary Network System Why Designed for high density loads Densely populated area s (impact of a power outage creates large scale socioeconomic impacts) Higher degree of reliability (n-2) is required or expected (Banking & Data centers) Permits equipment outages without impact to customers or switching operations What Composed of multiple transformers interconnected on the low voltage side Multiple primary feeders supplying the transformers Customers are supplied from the low voltage secondary interconnected grid Provides n-2 reliability (loss of any 2 components does not impact service)

8 Reliability Difference Total Outage Minutes Since 1994 #1 Substation 349 minutes Chevron fire (2002) 149 minutes, 26MVA load loss Century Gardens fire (2002) 121 minutes, 25MVA load loss Mission Gas Line (2005) 15 minutes, 23MVA load loss Miscellaneous substation incidents #5 Substation 9 minutes Miscellaneous substation incidents #8 Substation 60 minutes Miscellaneous substation incidents

9 Downtown Secondary Network Sub 8 Sub 5 8 Feeders 8 Feeders 8 Feeders 8 Feeders 13.2kV Q Buss 37 MVA 13.2kV R Buss 18 MVA 13.2kV 13.2kV Teens Buss 23 MVA 13.2kV Twenties Buss 25 MVA K Buss 40 MVA 13.2kV J Buss 32 MVA 8 Feeders 8 Feeders Sub 1 8 Feeders 13.2kV L Buss 44 MVA

10 Secondary Network - Sub 5 Example 138kV West Bus 138kV East Bus Street Grid 13.2kV Bus Street Grid Street Grid Man Hole Street Grid 208V Customer Load STREET VAULT Customer Load STREET VAULT < 1200A Load Customer Load STREET VAULT STREET GRID Secondary voltages tied

11 Spot Network North Hill Mall Example Sub - 20 Sub Distribution Feeder: Switchgear Distribution Feeder: A V 21B 7 1A 1A 1B 1B 1A 1B Switchgear Pad-mounted Designed to source spot network from one feeder at a time Upon loss of service to the primary feeder, control system is designed to transfer the spot network to the alternate source via a break-beforemake scheme. Customer Load STREET VAULT Customer Load STREET VAULT Customer Load STREET VAULT Note: Secondary's not tied together like a Street Grid

12 25kV High Voltage Radial System Open Sub 8 X3 feeders X3 feeders Preferred Alternate 25kV Customer Load 25kV Customer Load Preferred Alternate Alternate Preferred 25kV Customer Load 25kV Customer Load Alternate Preferred X3 feeders X3 feeders Sub 5 Open Sub 1

13 Network Servicing & Guidelines

14 Design & Records Tools Cost estimates produced utilizing Storms Design tool Byers MapViewer also used as a locating tool P&D enhanced the tool with the ability to view digital images as part of the records system. Microstation/Byers used for records and construction maps. Bubble system utilized to identify current construction projects Digital Grid used to determine current system status and load profiles for existing infrastructure

15

16

17

18 Network Monitoring System Originally installed in the early 1980 s System designed to monitor equipment status such as transformer load, voltage, power factor protector status (Open or Closed) water level, heat, smoke, temperature sensors SF6 gas pressure in system switches Operational staff utilize system to identify potential safety issues whenever a high voltage cable is de-energized to confirm if potential backfeed conditions exist Provides backup data for Engineering staff to develop Capital Maintenance programs. Assist design staff in identifying if a vault as sufficient capacity for additional customer loading

19 Screen shot of NCS viewer

20 NETWORK Field Pictures

21 Pre-Cast Vault & Installation

22 Street Vault Fancy Top

23 Street Vault Standard Top

24 Street Vault Fancy Top, Brick

25 Street Vault Fancy Top, Cement

26 Pre-Cast Manhole

27 Manhole High Voltage Connections (BLR)

28 Manhole High Voltage Connections (Splice)

29 Emergency Disconnect Switches E.D.D. (Emergency Disconnect Device) - 15kV switchgear which contains SF6 (Sulphurhexaflouride) - increased protection for equipment located inside the customer building - minimize impact of an event in the customer indoor vault on the system - enhanced safety for staff (Kill Push Button to de-energize vault in emergency)

30 25kV SF6 Switches

31 Network Major Office Tower Projects 8 th ave Place 480-volt (2 Indoor Vaults) Encana (The Bow) 600-volt (2 Indoor Vaults)

32 Door Signs on our Customer Owned Vaults

33 Postless Bus I-Beams

34 480 Volt Indoor Vault

35 600V Bus The Bow

36 Secondary HRC Fuse Boxes

37 Customer Service Fuseboards

38 Moles, close up

39 ENMAX Network Section Fibre Optics in the Network

40 Network Fiber Optic History installation of 1st fibre optic cable for Trans Alta Utility Shaw Fibrelink project starts in September and 36kM of backbone fiber installed in 4 months. ENMAX Network section performed all the fiber cable route planning and installation. GT Fiber project started an 12kM of 432 fiber backbone cable installed. ENMAX Network section performed all the fiber cable route planning and installation. Today ENMAX Network system contains over 110 km of fiber optic cable. We have a reputation for high quality work from design to installation.

41 Communication Cable Tagging

42 Network 101 Questions?

43 enmax.com

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems SECTION 9: ELECTRICAL POWER DISTRIBUTION ESE 470 Energy Distribution Systems 2 Introduction The Electrical Grid 3 Three main components to the electrical grid Generation ESE 450 Transmission Transmission

More information

OEB's Appendix 2-B: Fixed Asset Continuity Schedule

OEB's Appendix 2-B: Fixed Asset Continuity Schedule Page 1 of 11 OEB's Appendix 2-B: Fixed Asset Continuity Schedule Table 1: Fixed Asset Continuity Schedule - Actuals 2008 N/A 1805 Land NA 2.2 - (0.0) 2.2 0 - - - - 2.2 CEC 1806 Land Rights 2.0% 1.6 0.1-1.7

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Schedules 1 to 4, Lot B: Extension of the Lessos Substation 1.0 LIGHTNING ARRESTORS 1.1 ZNO lightning arrester, 192 kv rated voltage, 10 ka nominal discharge current 2.0 CAPACITIVE VOLTAGE TRANSFORMER ea. 45 2.1 220 kv capacitive voltage transformer 220/ 3 / 0.11/

More information

Agility in energy Ahead of the challenge, ahead of the change

Agility in energy Ahead of the challenge, ahead of the change European Utility Week Vienna, November 3-5, 2015 Agility in energy Ahead of the challenge, ahead of the change Go-ahead application for existing distribution grids combines availability and efficiency

More information

Power Infrastructure. PowerToGrowPHX.com

Power Infrastructure. PowerToGrowPHX.com Power Infrastructure PowerToGrowPHX.com Electricity 101 Key utility terms Power supply and generation mix Overview of the electric power system Federal and State Regulation Electric Ready Site What information

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

Rex Healthcare Medium Voltage System Presentation APEC 2015 March 15-19, 2015

Rex Healthcare Medium Voltage System Presentation APEC 2015 March 15-19, 2015 Rex Healthcare Medium Voltage System Presentation APEC 2015 March 15-19, 2015 Maximizing the Efficiency of Hospital Distribution Systems Through the Use of Advancing Technology and Design Creativity MISSION:

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

Electric Power Delivery To Big Cities

Electric Power Delivery To Big Cities Problem Definition Electric Power Delivery To Big Cities a) Socio-economic incentives are a major factor in the movement of population to big cities b) Increasing demand of electric power has strained

More information

WINNIPEG HYDRO QUICK FACTS

WINNIPEG HYDRO QUICK FACTS THE OFFER Manitoba Hydro makes the following payments and commitments: Years 1-5 $25 million per annum 6 9 $20 million per annum 10 TH in perpetuity $16 million per annum PLUS $1 million per annum in services*

More information

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS Larry Vogt Manager, Rates Minimum Distribution System What is MDS? MDS is an analysis module of the cost-of-service study in which distribution investment

More information

Customer Requirements Downtown Secondary Network Service

Customer Requirements Downtown Secondary Network Service Application This standard describes the limitations and requirements for receiving service from the Tacoma Power secondary network system within the City of Tacoma downtown core area. In This Standard

More information

Raising the bar. UHV switchgear and components

Raising the bar. UHV switchgear and components Raising the bar UHV switchgear and components Walter Holaus, Michael Lane, Richard Thomas The reliable supply of electrical energy is a backbone of the modern economy. Its ability to operate safely and

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards

More information

Put the Power in Your Hands

Put the Power in Your Hands Put the Power in Your Hands StarlineTrack Busway... STARLINE Track Busway is quickly becoming the industry standard for power distribution systems. Introduced in 1988, this innovative system is a modular,

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning IEEE-PES Chicago Chapter Presentation November 11, 2009 Smart Grid Mike Born Principal Engineer, Capacity Planning Agenda 2 Smart Grid Brief Overview ComEd s Smart Grid Vision and Building Blocks Customer

More information

3.0 Radial Distribution Systems

3.0 Radial Distribution Systems 3.0 Radial Distribution Systems Radial distribution systems (RDS) are the most common design used by electric utilities, and are the least expensive to plan, construct, and maintain. They generally consist

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

SOUTHWEST CALGARY RING ROAD (SWCRR)

SOUTHWEST CALGARY RING ROAD (SWCRR) PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation

More information

High Voltage Pad-mount Transformer

High Voltage Pad-mount Transformer High Voltage Pad-mount Transformer What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT HVPT History In order to reduce its outlay in distribution, Manitoba Hydro

More information

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Original: October 31, 2006 Table of Contents: INTRODUCTION and SCOPE... 3 DEFINITIONS... 3 QUALIFICATIONS FOR AN EXPEDITED

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

COMPANY PROFILE DOLCHE ENGINEERING POWER AND ENERGY. Where you get Unlimited Support!

COMPANY PROFILE DOLCHE ENGINEERING POWER AND ENERGY.   Where you get Unlimited Support! COMPANY PROFILE DOLCHE ENGINEERING POWER AND ENERGY Where you get Unlimited Support! 2016 ABOUT DOLCHE ENGINEERING DOLCHE Engineering is an Ethiopian, domiciled company. The company involved diversified

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc Con Edison s Infrastructure Delivers Energy To New York City And Westchester 3.3 million electric customers 1.1 million gas customers

More information

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION 100 KVA AND LARGER (CONCRETE PADS ONLY) 27.05-01 CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION

More information

AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR

AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR ANGLER SWITCHING DEVICES CONTENTS 1. General 2. Switchgear Types - Switch Disconnector - Disconnector 3. Cubicle Types - Cubicle with Switch Disconnector

More information

LIST OF EDD DESCRIPTION/ SPECIFICATION AS 19 TH OCTOBER 2016

LIST OF EDD DESCRIPTION/ SPECIFICATION AS 19 TH OCTOBER 2016 No Description/ Specification Amendment 1 EDD 1 :2008 11/0.415 kv Distribution Transformer, Oil Filled - 2 ED 2 :1987 The Galvanization of Iron and Steel, Articles Other Than Steel Wire - 3 ED 3 :1979

More information

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000 2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, 44504 143,789 SF on 20.177 ACRES $4,300,000 BUILDING OVERVIEW PARKER HANNIFIN FACILITY GEAR PUMP DIVISION Zoning - Industrial Light Manufacturing 143,789

More information

Switchgear and Distribution Systems for Engineers and Technicians

Switchgear and Distribution Systems for Engineers and Technicians Switchgear and Distribution Systems for Engineers and Technicians WHAT YOU WILL LEARN: How to identify typical characteristics of an industrial distribution system Become familiar with the main components

More information

University of California, San Diego Cal (IT) 2 Technical Assignment #2. Brian Smith

University of California, San Diego Cal (IT) 2 Technical Assignment #2. Brian Smith University of California, San Diego Cal (IT) 2 Technical Assignment #2 Brian Smith Advisor: Dr. Moeck 31 October 2005 Brian Smith Lighting/Electrical Option University of California, San Diego Cal (IT)

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Overhead Utilities Presentation Purpose

Overhead Utilities Presentation Purpose Presentation Purpose At the November 4, 2013 general presentation on the conversion of overhead utilities Council passed the following motion That staff explore cash-in-lieu payments for standard single

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Oncor Electric Delivery Distributed Storage and Microgrid Demonstration Projects

Oncor Electric Delivery Distributed Storage and Microgrid Demonstration Projects Oncor Electric Delivery Distributed Storage and Microgrid Demonstration Projects Nathan Kassees BSEE Maintenance Strategy & Planning Nathaniel.Kassees@Oncor.com 5/8/2015 1 Neighborhood Storage Reliability

More information

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet DRAWING NUMBER INTRODUCTORY INFORMATION Important Notices Underground Plant Protection Information Code Clearances Commercial/Industrial Information Sheet Work Management Customer Projects Engineering

More information

BSCP31 Trading Unit Application for West Burton A&B Power Stations

BSCP31 Trading Unit Application for West Burton A&B Power Stations Attachment 1 BSCP31 Trading Unit Application for West Burton A&B Power Stations Full description of nominated BM Unit(s) (in conjunction with form BSCP31/4.5) West Burton A Power Station comprises: Plant

More information

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear Robert J. Gustin Eaton Fellow Application Engineer, P. E. Southfield, Michigan Definitions Metal-enclosed load interrupter switchgear type ME Metal-enclosed switchgear is defined in ANSI C37.20.3-1987,

More information

Alternatives for meeting the need for transmission improvement described

Alternatives for meeting the need for transmission improvement described Alternatives for meeting the need for transmission improvement described 240 kv Alternative Looped System Southern Alberta Transmission Reinforcement For more information please contact the AESO at 1.888.866.2959,

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

Design Criteria Implementation for the Network Development Plan Hursthill Substation

Design Criteria Implementation for the Network Development Plan Hursthill Substation Design Criteria Implementation for the Network Development Plan Hursthill Substation Presenter : Riaan Swanepoel PRTechEng 1 Introduction The City of Johannesburg is embarking on a new spatial vision for

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER A19 ADMINISTRATIVE REPORT Report Date: July 10, 2007 Author: Chris Darwent Phone No.: 604.873.7358 RTS No.: 6866 VanRIMS No.: 13-1400-20 Meeting Date: July 24, 2007 TO: FROM: SUBJECT:

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

Max value Max life Range from. ($000) (Years) Pole Type

Max value Max life Range from. ($000) (Years) Pole Type Draft Handbook Vector Asset Description 1 Unit Maximum Maximum Life Max value Max life Max Asset Life Max Asset Life Range from Submitters Max Asset Life ($000) SUBTRANSMISSION Concrete Wood Concrete Wood

More information

EDS SUBSTATION LVAC SUPPLIES

EDS SUBSTATION LVAC SUPPLIES Document Number: EDS 08-1112 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1112 SUBSTATION LVAC SUPPLIES The standard details the requirements and options for the provision of LVAC

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category General Title Reference Number PMP 01 (RIC Standard: EP 00 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and

More information

Pretest Module 29 High Voltage Unit 1

Pretest Module 29 High Voltage Unit 1 Pretest Module 29 High Voltage Unit 1 1. Is a person qualified to work on high-voltage installations when this module is completed? 2. What is the code definition of high-voltage? 3. What is the IEEE definition

More information

8DJ. Maintenance-free for lifetime

8DJ. Maintenance-free for lifetime 8DJ Maintenance-free for lifetime Energy Distribution Welcome! Page 2 October 1 st 2008 8DJ Main Applications for Medium-Voltage Switchgear Power generation Power stations G Power transmission High and

More information

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000 2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, 44504 INDUSTRIAL PROPERTY FOR SALE 143,789 SF on 20.177 ACRES $4,300,000 BUILDING OVERVIEW PARKER HANNIFIN FACILITY GEAR PUMP DIVISION Zoning - Industrial

More information

FEBRUARY 14, 2017 Elastimold Solid dielectric switchgear customer presentation

FEBRUARY 14, 2017 Elastimold Solid dielectric switchgear customer presentation FEBRUARY 14, 2017 Elastimold Solid dielectric switchgear customer presentation Elastimold solid dielectric switchgear agenda Compelling value Design principles Product overview Switchgear applications

More information

Pike County Light & Power Company Summer Reliability Outlook

Pike County Light & Power Company Summer Reliability Outlook Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical.1_ UFSS#p A:_. DAVID/ IC, L re Mechanical Civil Protection & Control an LAND& 4^ Transmission & Distribution Telecontrol System Planning

More information

Arc-Flash Mitigation Technologies. Dennis Balickie

Arc-Flash Mitigation Technologies. Dennis Balickie Arc-Flash Mitigation Technologies Dennis Balickie The purpose of the session is to provide an overall understanding of the strategic impact of arc-flash. Special focus is on the tactical means to minimize

More information

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP)

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title High Voltage and 1500 System Earthing References and Definitions Reference Number PDS 02 (RIC Standard: EP 12 00 00 01 SP) Document Control

More information

Transformer Technology Seminar HV Collector (Power) Transformers

Transformer Technology Seminar HV Collector (Power) Transformers Pomona, CA, May 24 & 25, 2016 Transformer Technology Seminar HV Collector (Power) Transformers siemens.com/answers Substation for Wind Park Switch Yard HIS, Transformer & MV / Aux Building Page Page 2

More information

FUSES. Safety through quality

FUSES. Safety through quality Safety through quality HH HIGH VOLTAGE Over many decades SIBA has developed a global product line of High Voltage Fuses that are comprehensive for any and all applications. Superior engineering, advanced

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

THE WAY WE MOVE LRT FOR EVERYONE

THE WAY WE MOVE LRT FOR EVERYONE THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an

More information

ABB Next Level Big shift in power attractive opportunities

ABB Next Level Big shift in power attractive opportunities Bernhard Jucker and Claudio Facchin, Capital Markets Day, London, ABB Next Level Big shift in power attractive opportunities Slide 1 Agenda Profitably growing ABB s power business Shifting the center of

More information

SWITCHGEAR DIVISION PRODUCT PROFILES

SWITCHGEAR DIVISION PRODUCT PROFILES SWITCHGEAR DIVISION PRODUCT PROFILES Metal-Enclosed Load-Interrupter Switchgear Product Profiles Three-Phase, Group-Operated Load-Interrupter Switches with Fuses in Single and Multi-Bay Assemblies Manual,

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Cobra-S. Catalog Cobra-S

Cobra-S. Catalog Cobra-S Cobra-S Solid Dielectric, Three Phase Reclosers Providing electronic three phase overcurrent protection for systems rated through 38kV, 800A continuous current, 12.5/16kA symmetrical interrupting Control

More information

Power Voltage Transformers for Air Insulated Substations

Power Voltage Transformers for Air Insulated Substations Power Voltage Transformers for Air Insulated Substations Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the application of a

More information

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power Wisconsin Public Utility Institute June 28, 2017 Minimum Distribution Charges Larry Vogt Director, Rates Mississippi Power 1 Costs of Service vs. Cost Recovery Residential Service Example Assuming that

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment. General Unit substations shall be 500 kva minimum, 1500 kva maximum unless approved otherwise by the University. For the required configuration of University substations see Standard Electrical Detail

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1 Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV April 17, 2009 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956

More information

V03. APTA Multimodal Operations Planning Workshop August Green Line LRT

V03. APTA Multimodal Operations Planning Workshop August Green Line LRT V03 APTA Multimodal Operations Planning Workshop August 2016 Green Line LRT 2 Presentation Outline Past Present Future 3 16/03/2016 RouteAhead Update 4 4 16/03/2016 RouteAhead Update 5 5 16/03/2016 6 6

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Q64. Photovoltaic Solar Generation Project Interconnection. Facilities Study. APS Contract No

Q64. Photovoltaic Solar Generation Project Interconnection. Facilities Study. APS Contract No A subsidiary of Pinnacle West Capital Corporation Q64 Photovoltaic Solar Generation Project Interconnection Facilities Study APS Contract No. 52215 By Arizona Public Service Company Distribution Planning

More information

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Breaker Technology Operational Advantages Development Schedule Dave Richardson, Ph.D.,P.E. Powell Power Electronic

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of September 1, 2015 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff

More information

Modular integrated transportable substation (MITS)

Modular integrated transportable substation (MITS) Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................

More information

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1 Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV May 15, 2013 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956

More information

Local Transmission Plan. Rev. 1: April 2018

Local Transmission Plan. Rev. 1: April 2018 Local Transmission Plan Rev. 1: April 2018 1 Central Hudson s Service Territory Own & Operate approximately 610 miles of 69 kv, 115 kv & 345 kv transmission lines and three 345 kv substations 2 Central

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development

i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development Innovations in Protection and Control in Ecuador Power System March 26-28, 2013 1 ECUADOR - OVERVIEW Location: South America

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information