1 TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY P+ PowerPlus Engineering A Department of STAR Energy Services, LLC
2 TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY CITY OF SHASTA LAKE, CA Prepared by PowerPlus Engineering P+ PowerPlus Engineering A Department of STAR Energy Services, LLC
3 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC Thomas E. Nigon, P. E. 115 S. 5 th Ave., Suite 501 Timothy E. Smith La Crosse, WI Phone: (608) Fax: (608) tnigon@powerpluseng.com July 29, 2011 City Council City of Shasta Lake 1650 Stanton Drive Shasta Lake, CA Attention: Tom Miller Electric Utility Director Dear Council Members: We are pleased to present our Report on the Ten Year Plan which has been prepared for your electric distribution system. This report presents the results of studies made to determine the ten year requirements for your electric system. The report provides recommendations for the development of the electric system to accommodate load growth and improve reliability for the next 10 years. The ten year plan analysis is based on providing electric service to approximately 5,000 customers with a peak load of approximately 23 MW (not including Knauf demand) that is estimated to occur in the next ten years. The majority of recommendations for electric improvements to serve the existing and new loads include rebuilding feeder ties to improve reliability and replacing the substation voltage regulators in Central Valley substation. The estimated investment over the next 10 years is approximately $13.2 million in 2011 dollars. We thank you for allowing us to provide you with professional consulting services. Sincerely, Tom Nigon, P.E.
4 Table of contents, list of tables and figures 1 EXECUTIVE SUMMARY PLANNING CRITERIA General Primary Lines and Distribution Configuration Voltage Levels Loading Limits Equipment Loading Guidelines Substation Equipment Loading During Load Transfer Recloser Loading Single-Phase Line Loading Economic Conductor Size Reliability Environmental Considerations Power Supply Distributed Generation LOAD PROJECTIONS Background Load Forecast Land Use Analysis Design Load and Allocation Substation Load Projection Distribution Feeder Load Projection ANALYSIS OF EXISTING SYSTEM Power Supply and Transmission Distribution General Description Reliability Substations Current System Studies Coordination Study Master Plan Load Forecast Distribution Feeders Feeder capacity and voltage Energy losses EXPLORATORY PLANS Comparison Analysis Assumptions Transmission Options Substation Options Distribution Options RECOMMENDED PLAN General New Transmission Lines Transmission Line Upgrades Shasta Lake Ten Year Plan i
5 6.4 Substations Additions and Upgrades Distribution lines of substations Central Valley Feeder A Distribution Central Valley Feeder B Distribution Central Valley Feeder C Distribution Central Valley Feeder D Distribution Central Valley Feeder E Distribution Central Valley Feeder F Distribution Service Extensions to New Customers Service Upgrades Pole Replacements and System Improvements Overhead Single-Phase and Cable Replacements Fused Cutouts and Arresters Reclosers Capacitors Voltage Regulators Advanced Metering Infrastructure COST ESTIMATE SUMMARY Unit Cost Estimates Distribution Projects Cost Estimate Substation and Transmission Projects Cost Estimate Cost Estimate for Ten-Year Plan CONCLUSION SOURCES USED IN THIS REPORT APPENDIX System Load, Consumer Data and Losses Conductor Loading Tables Cost Estimate for Central Valley No. 1 Transformer System Model Data System Maps Table 1 Economic Conductor Size for 1-Phase Overhead Lines... 7 Table 2 Economic Conductor Size for 3-Phase Overhead Lines... 7 Table 3 Economic Conductor Size for 3-Phase Underground Lines... 8 Table 4 Average Annual SAIFI and SAIDI (minutes) for Six Utilities Table 5 Annual Growth Forecast Table 6 kw Annual Peak Demands and Growth Factors Table 7 Substation Peak kw Demand Ten Year Forecast Table 8 Feeder Loading from Summer 2008 SCADA Table 9 Feeder Demands for Electrical Model Table 10 Average Annual Outage Reliability Indexes Table 11 Outage Comparison with Neighboring Utilities Table 12 Substation Equipment Table 13 Existing and 10-year Substation Loading Table 14 Substation Site Visit Review Summary Table 15 Highest Voltage Drop Location with 10-Year Peak Feeder Loads Table 16 Feeder Voltage with Mt. Gate Load Addition Table 17 Energy Losses 2009 for City of Shasta Lake Table 18 Loss Benchmarks for Rural Electric Shasta Lake Shasta Lake Ten Year Plan ii
6 Table 19 Energy Loss Comparison Table 20 Cost of Losses Table 21 Cost Estimate Rewind CV Table 22 Cost Estimate Replace CV1 with 25/47 MVA Transformer Table 23 Cost Estimate Replace CV1 with 15/25 MVA Transformer Table 24 Secondary Voltage with CV1 Tap at 120, Table 25 Cost Estimate with CV1 Tap to 120,750 volts Table 26 Cost Estimate for Feeder Ties with Mt. Gate Substation Table 27 Feeder Loading with Load Transfer Table 28 Mt. Gate Load Forecast Table 29 Cost Estimate for Substation for Mt. Gate Development Table 30 Cost Estimate to Extend New Feeders for Mt. Gate Development Table 31 Distribution Projects Details Table 32 Maximum Fault Current for Distribution Transformers Table 33: Unit Cost Estimates Table 34 Distribution Project Cost Estimate Table 35 Substation Upgrades Cost Estimate Table 36 Ten-Year Estimate of Equipment Quantity Table 37 Ten-Year Total Cost Summary Table 38: Peak Demand and Energy Use Central Valley Substation Table 39 Energy Purchase, Sales and Losses Central Valley Table 40 Distribution Transformer Loss Estimate Table 41 Overhead Conductor Rating in Amps Table 42 Overhead Conductor Constants for Amp Ratings Table 43 Overhead Secondary Amp Rating Table 44 Underground Secondary Amp Rating Table 45 Underground 15 kv Cable Rating in Amps Table 46 Maximum Current Annealing of No. 2 ACSR Table 47 Maximum Current Annealing of 397 ACSR Table 48 Maximum Current Insulation Damage No. 2 AL Cable Table 49 Maximum Current Insulation Damage 750 AL Cable Figure 1 Feeder Configuration - Underground Distribution... 4 Figure 2 Transformer Failure Model Figure 3 One-Line Diagram Mt. Gate Development Substation Option Figure 4 One-Line Diagram Mt. Gate Development Distribution Option Shasta Lake Ten Year Plan iii
7 1 EXECUTIVE SUMMARY This plan covers a ten year system planning period for the City of Shasta Lake Electric Utility (Shasta Lake). Shasta Lake is headquartered in Shasta Lake, California. Shasta Lake is a municipal electric utility serving the City of Shasta Lake. The economy of the area is based primarily on commercial and light industry. Employment growth in the area is due to expansion in the retail and services such as tourism. The area has growth from residential developments located within the City of Shasta Lake. Shasta Lake serves the large industrial customer Knauf Insulation. The City of Shasta Lake is expected to have low to moderate growth in electrical use over the next 10 years. This long range plan presented in this report is based on a design load of 23 MW. This demand doesn t include the demand for the Knauf substation which is a dedicated substation for a large industrial customer. This design load is approximately 1.1 times the past peak load and is estimated to occur in approximately 10 years. The proposed distribution plan includes the following recommended improvements over the next 10 years. The list is prioritized by importance and the estimated timing where the lower numbered projects have a higher priority and are estimated to be completed during the initial time period of the ten year planning period: 1. Update the master SCADA 2. Upgrade Central Valley substation with new voltage regulators 3. Provide service extensions for approximately 500 new members 4. Replace 400 poles 5. Upgrade 2.8 miles of existing distribution 6. Upgrade Central Valley substation with an expanded control house and updated relaying 7. Install new feeders and ties when the Mt. Gate development begins and monitor load growth for a possible future new substation 8. Continue to monitor the condition of the Central Valley substation and replace with a new transformer based on the transformer condition and operating concerns 9. Flanagan upgrade will be planned with WAPA and no cost estimate is available at this time so this upgrade is not included in this plan The estimated investment over the next 10 years is approximately $13.2 million in 2011 dollars. This plan does not include a review of the Flanagan 230 to 115 kv substation. This substation is included in the planning process under a separate agreement with WAPA. Shasta Lake Ten Year Plan
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationWisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power
Wisconsin Public Utility Institute June 28, 2017 Minimum Distribution Charges Larry Vogt Director, Rates Mississippi Power 1 Costs of Service vs. Cost Recovery Residential Service Example Assuming that
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationELECTRIC SYSTEM RELIABILITY ANNUAL REPORT
ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT 2016 LIBERTY UTILITIES (CALPECO ELECTRIC) LLC (U 933 E) Prepared for California Public Utilities Commission July 15, 2017 EXECUTIVE SUMMARY The Electric System
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationUtility Distribution Planning 101
Utility Distribution Planning 101 Michael Coddington, National Renewable Energy Laboratory Webinar for National Association of State Utility Consumer Advocates June 5, 2018 1 Webinar Overview Overview
More informationMINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates
MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS Larry Vogt Manager, Rates Minimum Distribution System What is MDS? MDS is an analysis module of the cost-of-service study in which distribution investment
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationIEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning
IEEE-PES Chicago Chapter Presentation November 11, 2009 Smart Grid Mike Born Principal Engineer, Capacity Planning Agenda 2 Smart Grid Brief Overview ComEd s Smart Grid Vision and Building Blocks Customer
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationSECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems
SECTION 9: ELECTRICAL POWER DISTRIBUTION ESE 470 Energy Distribution Systems 2 Introduction The Electrical Grid 3 Three main components to the electrical grid Generation ESE 450 Transmission Transmission
More informationPower Infrastructure. PowerToGrowPHX.com
Power Infrastructure PowerToGrowPHX.com Electricity 101 Key utility terms Power supply and generation mix Overview of the electric power system Federal and State Regulation Electric Ready Site What information
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationSummer Reliability Assessment Report Electric Distribution Companies Perspective
Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationAgility in energy Ahead of the challenge, ahead of the change
European Utility Week Vienna, November 3-5, 2015 Agility in energy Ahead of the challenge, ahead of the change Go-ahead application for existing distribution grids combines availability and efficiency
More informationFeasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation
Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationPREPARED DIRECT TESTIMONY
Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement
More informationHigh Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007
High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationReasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders
Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,
More informationJuly 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative
AMEREN ILLINOIS UTILITIES Stimulus Package July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative Ron Pate Vice President, Regional Operations Jackie Voiles Director, Regulatory
More informationThe Capital Grid Project:
The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System
More informationNew Jersey State Report
New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the
More informationSPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN
SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationWest Station-West Cañon 115 kv Transmission Project
West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationPike County Light & Power Company Summer Reliability Outlook
Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which
More informationEH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map
EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids
More informationSouthern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management
Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements
More informationEMERGING REQUIREMENTS
Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More information2013 ANNUAL PROGRESS REPORT
March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,
More informationFlorida Public Service Commission 2011 Hurricane Season Preparation Briefing
Florida Public Service Commission 2011 Hurricane Season Preparation Briefing OUC The Reliable One May 4, 2011 Byron Knibbs Vice President, Sustainable Services (407) 434-2194 bknibbs@ouc.com 1 Florida
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationTerry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis
Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience
More informationMIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation
MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation David Aldrich Beckwith Electric Company Goals Flatten voltage profile across entire
More informationAn Inside Look at Electric Reliability 2016 Electric Reliability Report
An Inside Look at Electric Reliability 2016 Electric Reliability Report Stockton, Bakersfield, California California November November 6, 2017 3, 2016 Welcome 2 David Meier Senior Manager, Stockton Division
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:
More informationSPP Notification to Construct
February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationDesigning and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues
Designing and Maintaining a Pollution-Resilient Electric Power System Tom McDermott IEEE/PES T&D Conference April 21-24, 2008 Chicago, IL Managing Pollution Issues Define the metrics, and measure them
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationAlameda Point Electric Infrastructure Improvements Public Utilities Board Update May 15, 2017
Alameda Point Electric Infrastructure Improvements Public Utilities Board Update May 15, 2017 Presentation Overview I. Mutual Goals II. Alameda Point Overview III. Incremental Development Process and Project
More informationProposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013
Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation
More informationWelcome. Liberty Utilities Reliability Reporting Workshop. October 3 & 6, 2017
Welcome Liberty Utilities Reliability Reporting Workshop October 3 & 6, 2017 1 Agenda Purpose of Workshops System Overview Key Utility Initiatives Reliability Performance Plans for Reliability Improvements
More informationUniversity of California, San Diego Cal (IT) 2 Technical Assignment #2. Brian Smith
University of California, San Diego Cal (IT) 2 Technical Assignment #2 Brian Smith Advisor: Dr. Moeck 31 October 2005 Brian Smith Lighting/Electrical Option University of California, San Diego Cal (IT)
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationGasoline/Convenience. Powerful Site Assessment Options for the Gas and Convenience Industry
Type of Report Street Location Gasoline/Convenience North Las Vegas Blvd and Cheyenne Ave Las Vegas, NV October 27 City Location Date TABLE OF CONTENTS Description Table of Contents Page Number Executive
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationEV - Smart Grid Integration. March 14, 2012
EV - Smart Grid Integration March 14, 2012 If Thomas Edison were here today 1 Thomas Edison, circa 1910 with his Bailey Electric vehicle. ??? 2 EVs by the Numbers 3 10.6% of new vehicle sales expected
More informationEMERGING REQUIREMENTS
EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic September 24, 2014 1 Reliability Analysis Update 2 AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationTHE THREE VOLTAGE LEVEL DISTRIBUTION USING THE 1000 V LOW VOLTAGE SYSTEM
THE THREE VOLTAGE LEVEL DISTRIBUTION USING THE 1 V LOW VOLTAGE SYSTEM Juha Lohjala. Suur-Savon Sähkö Ltd. Finland. juha.lohjala@sssoy.fi Tero Kaipia, Jukka Lassila, Jarmo Partanen. Lappeenranta University
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationDiane Lindsey CenterPoint Energy SWEDE 2010
Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge
More informationDYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION
DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION INTERIM REPORT AS OF JULY 21, 2016 PRESENTED JULY 21, 2016 1 TABLE OF CONTENTS Section Introduction Advanced Inverter Approach
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationElectrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer
Electrical Transmission System Analysis EE 456 project Team Members Abdulaziz Almarzouqi Hamzah Abeer Due December 14, 2012 Changes: 1. 134MW Wind added 2. N-1 Contingency limits changed to.95-1.05 3.
More informationBusiness Park North Muskegon County, MI
Business Park North Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business Center 800-805-0490
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationSMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014
SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand
More information201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 2 DESCRIPTION OF SERVICE
201 S. Anaheim Blvd. Page No. 3.2.1 A. GENERAL 1. The character of electric service available at any particular location should be ascertained by inquiry at the City's Electrical Engineering Division office.
More informationOverview of State Distributed Generation Interconnection Rules
Overview of State Distributed Generation Interconnection Rules Presentation to EPA CHP Webinar Series June 26, 2008 Wayne Shirley Director The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier,
More informationWholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources
Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationDistribution Line Transformer / Secondary
- T&D Assessment Distribution Line Transformer / Secondary Pacific Gas and Electric Company November 15, 2010 Analysis of Transmission, Distribution Substation & Primary, Transformer & Secondary Impacts
More informationSERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning
SERVICES INNOVATION Montreal Symposium March 29, 2017 Jack Simpson Director, Generation & Capacity Planning UTILITY LANDSCAPE IS CHANGING 2 Innovation CUSTOMER NEEDS ARE CHANGING GREATER RELIABILITY STORM
More informationTABLE OF CONTENTS 1. GENERAL LABOUR COSTS EQUIPMENT COSTS...2
TABLE OF CONTENTS 1. GENERAL...2 2. LABOUR COSTS...2 3. EQUIPMENT COSTS...2 4. DISTRIBUTION MATERIAL COSTS (EDS AND OIL AND GAS FIELD SERVICE MODELS)..3 5. STREET LIGHTING...3 6. TRANSMISSION LINES...3
More informationThe FREEDM System: components, main functions, system control
Short course on the FREEDM System Session L3 The FREEDM System: components, main functions, system control Dr. I. Husain, North Carolina State University Dr. G. T. Heydt, Arizona State University October,
More informationNetwork. ENMAX Power Corporation Network Planning & Design November 4, 2011
Network ENMAX Power Corporation Network Planning & Design November 4, 2011 ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground
More informationGRID INNOVATION CAUCUS CO-CHAIRS
February 16, 2017 GRID INNOVATION CAUCUS CO-CHAIRS REP. JERRY NCNERNEY (D-CA) REP. BOB LATTA (R-OH) 2 WIRES UNIVERSITY Transmission 101: The Fundamentals Of High Voltage Transmission February 16, 2017
More informationInterconnection Feasibility Study Report Request # GI
A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission
More informationThe Benefits of Having a Municipal Electric Utility
The Benefits of Having a Municipal Electric Utility Karen Weeden, Sr. Rate Analyst April 20, 2015 TOPICS Goals of the Municipal Power Advantage Program Financial Benefits Non-financial Benefits MRES Membership
More informationMuskegon Waste Water Treatment Site Muskegon County, MI
Muskegon Waste Water Treatment Site Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business
More informationElectrical Engineering Services Report for Proposed Optenhorst Mixed Use Development, Erf 9209, Paarl
CARSTENS PLASE (PTY) LTD Electrical Engineering Services Report for Proposed Optenhorst Mixed Use Development, Erf 9209, Paarl J24085 REVISION 3 14 March 2018 Electrical Engineering Services Report for
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationSERTP rd Quarter Meeting
2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please
More information