Northern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008

Size: px
Start display at page:

Download "Northern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008"

Transcription

1 Northern Umbrella Plan and U.P. Capital Projects Update 2008 Transmission Business Briefing October 29,

2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather Falls LINCOLN Alexander Boulder Jct. Hilltop Sherman St. Morrison Ave. Weston White Pine Stone UPSCO GOGEBIC VILAS Ontonagon ONTONAGON Victoria Dam Bruce Crossing Land O Lakes Conover Cranberry St. Germain Pine Highway 8 MARATHON Bunker Hill Wausau Kelly Du Bay PORTAGE Northpoint Hoover Rocky Whiting Ave. Run Plover Coyne Three Lakes RPC Black Brook Hodag Venus Arnott Mass Antigo Watersmeet Twin Lakes LANGLADE WAUPACA Winona FOREST HOUGHTON M-38 Prickett MENOMINEE BARAGA Warden IRON Way Dam Lakehead Hemlock Falls DICKINSON Strawberry Hill Iron River Crystal Falls Sagola Peavy Falls Lincoln Nordic Felch Twin Lakes Randville Michigamme I Harrison Waupaca G Crandon Summit Lk. Aurora St. SHAWANO W. Shawano Badger Caroline Clintonville Werner West Laona Silver Cliff Mountain Florence Bass Lk Armory Pine Grede FLORENCE Big Q Niagara Paper Goodman Cauldron Falls High Falls OUTAGAMIE North Hintz Appleton Ellington F White Lake D CWIS Thunder White Clay E. Shawano Amberg Daves Falls MARINETTE Fox Hill Johnson Falls Sandstone Pound OCONTO Morgan H Greenstone Humboldt Lena Brule Twin Fls Falls Pioneer Roselawn Skygen Plains Champion BROWN Hoist Perch Lake Crivitz McClure See Insert A Cataract MARQUETTE MENOMINEE Alger-Delta Nathan Chalk Hills White Rapids Stiles Howard Velp Mason St. James St. Liberty Eastman Glory Rd. Red Maple C Lost Dauphin Ropes Foundry Pulliam A1 A3 Tower Dr. Preble E Highway V Myst. Hills Powers Grand Rapids KEWAUNEE Arnold Bay De Noc Menominee 30th Ave. 2nd St. Roosevelt Rd. West Marinette GREEN BAY Rosiere CEDAR LINE CLARKSBURG LINE East Krok A2 DOOR Presque Isle Marquette Dead River AuTrain Chatham KI Sawyer Gwinn Cornell Forsyth Chandler Delta West Side Harris Canal National Tilden Insert A Perkins Gladstone Mead Escanaba ALGER DELTA Empire Munising Indian Lake Lakehead LAKE SUPERIOR SCHOOLCRAFT B LAKE MICHIGAN Glen Jenks Manistique Seney Newberry Corr. Facility Engadine Hiawatha Curtis Lakehead Valley Blaney Park Gould City LUCE Lou-Pac Newberry Newberry Village Roberts Rexton Lakehead KEY 345 kv Substation 115 or 138 kv Substation <=69 kv Substation Generation 345 kv Transmission CHIPPEWA Eckerman Hulbert Trout Lake 115 or 138 kv Transmission 69 kv Transmission Proposed Projects MACKINAC Brevort Straits McGulpin Emmet Brimley Pine River Oden To Livingston 2

3 d Projects: A: Plains Stiles 138 kv Rebuild B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild C: Morgan Stiles 138 kv Rebuild D: Morgan White Clay 138 kv Up-rate E: Add 2 nd Plains Transformer (cancelled in Feb. 2008) F: New Werner West 345/138 kv Substation NUP Projects In-progress Projects: G: Cranberry Conover Plains Project H: Morgan Werner West 345 kv Line (including Clintonville Werner West 138 kv) I: Gardner Park Central Wisconsin 345 kv Line (for generator interconnection) 3

4 G. Cranberry-Conover-Plains Project Overview and Status Phase 1 -- Schedule/Status New T-Line (Cranberry - Lakota Rd) placed in service 6/6/08 ROW restoration and related activities underway Phase 2 -- Schedule/Status T-Line rebuilt to Twin Lakes Substation (in-service August 08) T-Line reconstruction underway to new Iron Grove Substation NFS Special Use Permit in Nicolet Forest received NFS Special Use Permit pending for Ottawa Forest Targeting February/March 09 for completion of Phase 2 Phases 3 & 4 -- Schedule/Status T-Line and substation design/procurement underway Easement procurement will begin Q4 08 Construction planned to start March 09 Targeting June 10 for completion of Phases 3 & 4 4

5 New Morgan-Werner West 345kV Line (52.8 Mi) ATC Executive approval ATC Board approval File CPCN application CPCN issued Morgan White Clay, 13.2 Mi Werner West Clintonville, 17.5 Mi Clintonville Highway 22, 7.7 Mi Highway 22 White Clay, 15.4 Mi Werner West SS, 345/138 kv Construction period, ~58% Project in-service 2/05 2/05 3/05 6/06 10/7/07 70% Construction 12/08-4/09 Construction 4/09-10/09 12/06 1/07-12/09 12/09 5

6 New Gardner Park-Central WI 345kV line (51 Mi) ATC Executive approval ATC Board approval File CPCN application CPCN issued Belle Plain Tap Highway 22, 1.1 Mi Caroline Belle Plain Tap, 6.9 Mi Structure 773 Whitcomb, Mi Gardner Park Structure 773, 6.53 Mi Whitcomb Caroline, 16.1 Mi Highway 22 Substation Construction period; ~ 78% Project in-service 2/05 2/05 3/05 6/06 6/07 7/07 4/08 98% 10% 73% 1/07 12/09 December

7 Project Status Summary Project Name Key Need Drivers Projected In-Service Date Projected Cost Status A: Plains Stiles 138 kv Rebuild A1: Plains Amberg A2: Amberg West Marinette Physical condition; transfer capability; solution also results in a more robust parallel path for 2/3 of P-S corridor October 2005 November 2005 $94.3M - - A3: Amberg Stiles October B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild Phase 1 Rebuild Indian Lake Glen Jenks Phase 2 Rebuild as double circuit 138 kv, operate at 69 kv TLR mitigation; voltage support; physical condition; local loadserving in Manistique area; required operating guide that splits the U.P. system August 2004 March 2006 $6.1M $46.2M Phase 3 Convert to 138 kv operation N/A N/A Not part of the Northern Umbrella Plan C: Morgan Stiles 138 kv Rebuild as double circuit Transfer capability May 2006 $8.0M 7

8 Project Status Summary Project Name Key Need Drivers Projected In- Service Date Projected Cost Status D: Morgan White Clay 138 kv uprate (eventual rebuild as part of Element H) Transfer capability March 2005 $0.4M Project. E: Add 2 nd Plains transformer (250 MVA 345/138 kv) Transfer capability Cancelled Cancelled F: New Werner West Substation with 345/138 kv transformer TLR mitigation, system security December 2006 $14.2M Project. G: Cranberry Conover Plains Project Phase 1: New 115 kv Cranberry Conover Transfer capability; Transmission service; Reliability, physical condition See below June 2008 $127.6M - In-service. Energized first week of June 08. Phase 2, 3 & 4: Rebuild 69 kv Conover Plains to 138 kv June Design/procurement activities started. Will design/construct from west to east. H: New Morgan Werner West 345 kv line & Clintonville Werner West 138 kv line Transfer capability, reliability, and network service $139.0M See Page 8 for detailed status. Project under construction and on schedule. I: New Gardner Park Central Wisconsin 345 kv line & Central Wisconsin 345 kv switching station Required for new Weston 4 generation 2009 $124.3M See Page 9 for detailed status. Project under construction and on schedule. 8

9 Northern Umbrella Plan Summary Costs estimated at $560.1 million for all NUP projects $430 million spent on NUP as of September 2008 Of the 9 projects 5 are complete and in-service 3 are under construction 1 has been cancelled Targeting 2010 for completion of all NUP projects 9

10 Other Capital Projects Eastern U.P. Emergency Upgrades d to mitigate risks associated with low Lake Superior water levels Transformer at Hiawatha Substation Transformer at Straits Substation Capacitor Bank at Nine Mile Substation d in ~3 months Cost to construct $6.4 Million 10

11 Other Capital Projects Rebuild of Laurium No. 1 Line Located between Houghton and Calumet Driven by age/condition/reliability and capacity concerns Started construction in September 2007 Placed in service in May 2008 Cost to construct $8.1 million 11

12 Other Capital Projects North Lake Substation Located near Ishpeming Greenfield construction Driven by age/condition/reliability concerns at Cedar Substation Began construction in Fall 2007 Anticipated completion May 2009 Anticipated cost is ~$12 Million 12

13 Other Capital Projects Pine River Substation Located near Rudyard Brownfield construction Driven by age/condition/reliability concerns at existing Pine River Substation Began construction in Fall 2008 Anticipated completion Fall 2009 Anticipated cost is ~$9 Million 13

14 Other Capital Projects New Alger-Delta T-D Interconnection Located in Marquette County Anticipated completion December 2008 Anticipated cost is ~$900K New UPPCO T-D Interconnection Located in Keweenaw County Anticipated completion April 2009 Anticipated cost is $250K New City of Norway T-D Interconnection Located in Dickinson County Anticipated completion April 2009 Anticipated cost is ~$230K 14

15 Other Capital Projects Asset Renewal (reliability) Breaker/switch/relay replacements Transmission Line Rating Studies Pole replacements (>100 poles at ~ $3M total) New Capacitor Banks (voltage support) Munising (in-service 2008) Ontonagon (in-service 2008) Hiawatha (September 2009) L Anse (September 2009) M-38 (September 2009) Perkins (October 2009) Indian Lake (June 2010) 15

Northern Umbrella Plan Update. December 7, 2007

Northern Umbrella Plan Update. December 7, 2007 Northern Umbrella Plan Update December 7, 2007 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather

More information

Northern Umbrella Plan Update. December 15, 2006

Northern Umbrella Plan Update. December 15, 2006 Northern Umbrella Plan Update December 15, 2006 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Eastom Tomahawk Grandfather Falls Boulder

More information

American Transmission Company LLC Northern Umbrella Plan (NUP) Projects

American Transmission Company LLC Northern Umbrella Plan (NUP) Projects American Transmission Company LLC Northern Umbrella Plan (NUP) Projects February 21, 2006 Agenda Northern Umbrella Plan Individual Project Discussion Summary System Prior to NUP Projects NUP Projects Wien

More information

Northern Umbrella Plan & Projects- Update

Northern Umbrella Plan & Projects- Update Northern Umbrella Plan & Projects- Update November 29, 2007 Jane Petras, ATC General Manager Agenda Overall Northern Umbrella Plan Update Cranberry-Conover-Plains Project: Underground Transmission Line

More information

Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability

Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability, 1/5/4 Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability American Transmission Company, LLC Stephen D.

More information

Capital Project Update Northern Umbrella Plan Update

Capital Project Update Northern Umbrella Plan Update Capital Project Update Northern Umbrella Plan Update Jane Petras General Manager - North Portfolio November 7, 2006 1 Overview Northern Umbrella Plan (9) Network Projects (8) Asset Renewal Transmission

More information

Section IV CHANGES TO THE YEAR ASSESSMENT

Section IV CHANGES TO THE YEAR ASSESSMENT Section IV CHANGES TO THE 2003 10-YEAR ASSESSMENT This section describes the changes made by ATC to certain planned, proposed and provisional transmission projects since the 2003 10-Year Assessment was

More information

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects

More information

Highly Constrained Elements Within ATC Footprint

Highly Constrained Elements Within ATC Footprint Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372

More information

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- -- ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

AMERICAN TRANSMISSION COMPANY

AMERICAN TRANSMISSION COMPANY AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5

More information

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

WHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018

WHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018 di, WHEDA Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits Estimated Maximum Family Income Limits at 30% of HUD Estimated 2018 County Median Income Brown 16,290

More information

Wisconsin Local Employment & Unemployment Estimates Released

Wisconsin Local Employment & Unemployment Estimates Released Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report Northeast Wisconsin/Upper Peninsula Separation 11/14/01 Incident Investigation Report Summary Contact by a high voltage electric transmission line with a tree in northeastern Wisconsin initiated a series

More information

Wisconsin Housing Statistics

Wisconsin Housing Statistics Wisconsin Housing Statistics Monthly Year-to-Date Dec 2018 Dec 2017 % Change Jan-Dec 2018 Jan-Dec 2017 % Change Unit Sales 4,980 5,728-13.1% 82,760 84,594-2.2% Median Price $179,000 $170,000 +5.3% $184,000

More information

Region NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane.

Region NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane. Notes: 1) Costs shown in table are estimated and do not include the 4.44% Administrative Costs; 2) Material Costs includes,, and other Deicing and icing Agents; 3) Equipment Costs are based on $60 per

More information

Region NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand.

Region NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand. NC per Hours Hours Mat'l Equip Labor Cost to ADAMS 193.2 95.64 76.0 13 28 14 11 4,318 3,474 844 18.0 0 0 76 1147.0 338.0 $1,676 $440 $340 $2,455 $473,350 0.19 IRON 249.56 163.59 192.0 0 47 16 10 7,308

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Presque Isle 5, 6, 7, 8, & 9: 344 MW Coal Retirement, Effective 10/15/2014 ATTACHMENT Y STUDY REPORT August 15, 2014 EXECUTIVE SUMMARY Pursuant to the Tariff, an Attachment Y Notification

More information

U.P. Energy Summit February 16, 2017

U.P. Energy Summit February 16, 2017 U.P. Energy Summit February 16, 2017 Brett French, External Affairs Manager atcllc.com Overview ATC s Value Proposition Reliability Metrics Project updates Q&A atcllc.com 2 Providing Value to our Customers

More information

Summary Report. September The Future Grid. 10-Year Transmission System Assessment.

Summary Report. September The Future Grid. 10-Year Transmission System Assessment. Summary Report September 2012 he Future Grid 10-Year ransmission System Assessment www.atc10yearplan.com Regional and inter-regional planning achieves results ransmission investments solve problems, save

More information

Flowgate 10515, an OTDF flowgate, consists of the following elements:

Flowgate 10515, an OTDF flowgate, consists of the following elements: MAIN Report for NERC Initial Investigation NERC TLR Level 5A Flowgate 10515 Kewaunee 345/138 kv Transformer for the loss of Point Beach-North Appleton 345kV Line October 15 17, 2001 Submitted January 14,

More information

Michigan Commercial Motor Vehicles

Michigan Commercial Motor Vehicles June 2016 Revised 10/3/17 2016 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Wisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits

Wisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits Housing and Economic Recovery Act (HERA Special) Income and Rent Limits Income Limits * Housing and Economic Recovery Act (HERA Special) Income Limits for 2013 at 30% Family Size: ONE TWO THREE FOUR FIVE

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

SUMMARY REPORT. 10 Year Transmission System Assessment

SUMMARY REPORT. 10 Year Transmission System Assessment 2018 SUMMARY REPORT 10 Year Transmission System Assessment Agility, flexibility needed to plan for Long term transmission planning has always been a complex undertaking, but it was relatively consistent

More information

U.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR

U.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR U.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR First place photo by Danielle Adams featuring the James L. Oberstar at anchor off Picnic Rocks, a point between the Presque Isle

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014 MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000

Upper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000 California Butte 6 7 R R Glenn 6 21 15 ** 7,800,306 ** Tehama 6 103 3 1,187,932 Restricted R R California Total 6 18 8,988,238 Illinois Boone 17 7 24 2,977,946 Bureau 17 11 R R Carroll 17 15 22 3,851,694

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Transitways. Chapter 4

Transitways. Chapter 4 4 Transitways Figure 4-1: Hiawatha LRT Train at the Lake Street/Midtown Station The 23 Transportation Policy Plan identifies a network of transitway corridors to be implemented by 23. Transitways recommended

More information

VERMONT ELECTRIC POWER COMPANY (VELCO)

VERMONT ELECTRIC POWER COMPANY (VELCO) TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first

More information

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE Project Overview and Need The Bemidji-Grand Rapids 230-kV transmission line was fully energized in September of 2012 to improve reliability for the Red River

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

VEHICLE TYPE CRASH INVOLVEMENT

VEHICLE TYPE CRASH INVOLVEMENT VEHICLE TYPE CRASH INVOLVEMENT TYPES Number Total MOST SEVERE OUTCOME IN CRASH MOST SEVERE OUTCOME IN VEHICLE Motor Vehicles Fatal Crash Injury PDO Fatality in Veh Injury PDO Number Total Passenger Car

More information

Economics of Law Practice in Michigan

Economics of Law Practice in Michigan 20 2014 Attorney Income and Billing Rate Key Findings Report The survey was conducted in May 2014 and requested income and billing rate information for 2013. he State Bar of Michigan Economics of Law Practice

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Ex.-Applicants-Stevenson-22

Ex.-Applicants-Stevenson-22 Mississippi River WAB AS HA W INONA City of Alma WABA SHA 61 Alma Lizzy Pauls Pond City of Buffalo BU FFALO Belvidere Village of Cochrane Lincoln Fountain City Bay 88 Bensel Pond Milton 35 Waumandee Waumandee

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS

INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure and Transportation Contract Services Branch 1630-215 Garry Street Winnipeg,

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, December 8 2016 2000 PACIFICORP PAGE 2 Study Areas for 2016 Findings Reports Southeast, Utah

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

State Bar of Michigan

State Bar of Michigan State Bar of Michigan 2017 Economics of Law Practice Attorney Income and Billing Rate Summary Report Contents Economics of Law Practice in Michigan 2017 Attorney Income and Billing Rate Summary Report

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012 First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

SCHEDULE A. SPEED LIMITS (A part of Section )

SCHEDULE A. SPEED LIMITS (A part of Section ) SCHEDULE A SPEED LIMITS (A part of Section 340.0003) A traffic and engineering investigation having been made on the following described highways in Brown County, the maximum permissible speed at which

More information

Project Description - 1 -

Project Description - 1 - Project Description The Mother Ann Lee Hydroelectric Station is located at Lock and Dam 7 on the Kentucky River. This dam is part of a system of 14 lock and dams installed on the Kentucky River between

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant

More information

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016 Public Service Company of Colorado Transmission Projects Status CCPG August 18, 2016 1 Transmission Ownership Colorado 2016 Generation Additions/Reductions Name Interconnection Owner Net MW Type ISD Zuni

More information

TEN YEAR HISTORY OF FALL ENROLLMENTS

TEN YEAR HISTORY OF FALL ENROLLMENTS TEN YEAR HISTORY OF FALL ENROLLMENTS 2008 2007 F a l l S e m e s t e r 2006 2005 2004 2003 2002 2001 2000 1999 1998 0 50,000 100,000 150,000 200,000 250,000 Number of Students 3 TABLE 1: TEN YEAR HISTORY

More information

Monitoring Bank Erosion On the Missouri River, Lower Brule Reservation

Monitoring Bank Erosion On the Missouri River, Lower Brule Reservation Monitoring Bank Erosion On the Missouri River, Lower Brule Reservation A cooperative study between the Lower Brule Sioux Tribe s Environmental Protection Office and the U.S. Geological Survey, with assistance

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (OCTOBER 2016) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

747 ACRES LAND FOR SALE

747 ACRES LAND FOR SALE 747 ACRES LAND FOR SALE 3400 NORTH PONY EXPRESS PARKWAY, EAGLE MOUNTAIN, UTAH 84005 Salt Lake Count y Lehi 73 Sar atoga Spring s Eagle Mountain Blvd g Eagle Mountain Eagle Mountain Blvd Pony Express Pkwy

More information

CREATING CONNECTIONS IN WATERLOO REGION

CREATING CONNECTIONS IN WATERLOO REGION CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

National Grid s 2018 Local Transmission Plan

National Grid s 2018 Local Transmission Plan National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016 Public Service Company of Colorado Transmission Projects Status CCPG May 5, 2016 1 Transmission Ownership Colorado 2016 Transmission Planning Drivers Load Service / Near-Term (1-5 years) TPL Studies (5

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) August 2011

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) August 2011 and Data 1/ (pool pounds) Idaho Bear Lake 16 7 4 132,258 Caribou 16 29 R R Franklin 16 41 8 2/ 491,364 2/ Idaho Total 16 12 623,622 Illinois Boone 17 7 29 3,407,324 Carroll 17 15 13 1,586,519 De Kalb 17

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative

More information

2017 BIA Transportation Projects Wisconsin Tribes

2017 BIA Transportation Projects Wisconsin Tribes 2017 BIA Transportation Projects Wisconsin Tribes Contracting Process Tribal Transportation Program Funds and Contract Authority at Tribe Work directly with each respective Tribe since they solicit and

More information

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES Revision 10 August 11, 2017 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed

More information

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012 Hurricane Sandy Preparations, Response & Recovery Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012 Topics Storm Preparation Sequence of Events Infrastructure Status Operations

More information

July 25, Karla Bailey Asset Management & Engineering Manager Thunder Bay Hydro 34 Cumberland St N, Thunder Bay, ON P7A 4L4. Dear Ms.

July 25, Karla Bailey Asset Management & Engineering Manager Thunder Bay Hydro 34 Cumberland St N, Thunder Bay, ON P7A 4L4. Dear Ms. 483 Bay Street Tel: (416) 345-5420 13 th Floor, North Tower Fax: (416) 345-4141 Toronto, ON, M5G 2P5 ajay.garg@hydroone.com www.hydroone.com July 25, 2016 Karla Bailey Asset Management & Engineering Manager

More information

10-Year Transmission System Assessment

10-Year Transmission System Assessment An excerpt from AC s 2009 10-Year ransmission System Assessment Proposals to ensure n Electric system reliability n Access to low-cost sources of power n Access to renewable energy www.atc10yearplan.com

More information

Paleozoic Geology of the Central Upper Peninsula of Michigan

Paleozoic Geology of the Central Upper Peninsula of Michigan Paleozoic Geology of the Central Upper Peninsula of Michigan August 22-24, 2014 Michigan Basin Geological Society Summer Excursion Led by Drs. Peter Voice and William B. Harrison III Copies of this Guidebook

More information