SUMMARY REPORT. 10 Year Transmission System Assessment

Size: px
Start display at page:

Download "SUMMARY REPORT. 10 Year Transmission System Assessment"

Transcription

1 2018 SUMMARY REPORT 10 Year Transmission System Assessment

2 Agility, flexibility needed to plan for Long term transmission planning has always been a complex undertaking, but it was relatively consistent in the days of steady load growth and a stable generation mix. But conditions in the early 21st century are no longer as predictable as they were in the past, adding new challenges to the process. As a transmission only electric utility, we collaborate with our customers to determine needed replacements, expansions and connections to the grid. Recent changes in generation and the energy marketplace have required us to be flexible and agile in our planning to accommodate customer needs. In today s marketplace, our customers expect us to respond quickly. In fall 2017, Foxconn selected Wisconsin for its first U.S. based manufacturing facility for flat screen technology. The Mount Pleasant Tech Interconnection Project was developed to respond to the needs of a facility that would constitute the largest load at a single substation in ATC s service territory. We filed an application in January to build a new substation and associated transmission lines with the Public Service Commission of Wisconsin, which approved the project in July. Construction will start this fall and the project will be in service in late Transmission investments Projections from past and current Transmission System Assessments Specific Network Projects Regional Multi Value Projects $1.4B $1.4B $1.3B $0.7B / $1.0B* $0.5B $0.5B $0.5B $0.5B $0.4B $0.3B Asset Maintenance $1.2B $1.4B $1.4B $1.4B $1.5B Other Capital Categories $0.2B / $0.8B $0.4B / $1.2B $0.4B / $1.2B $0.3B / $0.8B $0.5B / $1.1B Total 10 Year Capital Cost $3.3B / $3.9B $3.7B / $4.5B $3.6B / $4.4B $2.8B / $3.6B $2.8B / $3.4B * The Specific Network Projects range in 2017 reflects the fact that Northern Area Reliability Assessment projects in the 10 Year Assessment project list and in the MISO Transmission Expansion Plan database may be replaced by generation being considered in the Midcontinent Independent System Operator generation queue. 2 AMERICAN TRANSMISSION CO.

3 Minnesota Kingsford Michigan changing energy marketplace Wisconsin De Pere Madison Cottage Grove Illinois Pewaukee Headquarters ATC Offices Upper Michigan Energy Resources Corp., a subsidiary of WEC Energy Group, proposed in early 2017 to add 180 megawatts of generation at two sites in the Upper Peninsula. The project was approved later that year, and construction began immediately. This allowed us to scale back projects identified in our Northern Area Reliability Assessment. UMERC s two plants are located near existing transmission infrastructure and will require two new substations and only a short segment of transmission line to connect the facilities. Generation retirements have a large impact on the transmission grid. We anticipate that more than 30 percent of the coal fired generation in our service territory will be retired by the end of With the retirement of the Kewaunee Nuclear Station in 2013, we canceled a pair of 50 mile, 138 and 345 kv lines that had been in the planning stages for several years the change in generation allowed the need to be satisfied instead with a new substation that went into service this year. The announced closing of the Pleasant Prairie Power Plant in southeastern Wisconsin meant that another transmission connection into northern Illinois was no longer needed, and the Wisconsin Illinois Electric Reliability Project was canceled. We also work with our customers to evaluate cost effective non transmission solutions when examining the condition of our aging assets. Recently, we made the decision to retire a 69 kv line in northeastern Wisconsin that was in poor condition when we determined, with Wisconsin Public Service, that the local distribution company s two substations served by the line could be tied into a nearby rebuilt 138 kv line for about half the cost. These examples demonstrate the dynamic nature of the electric industry today. That s why it s prudent to conduct an annual review of market conditions and transmission needs. Our 10 year forecast calls for a slight decrease in capital expenditures from last year, with $2.8 to $3.4 billion in system improvements. This document contains a summary of ATC s planning initiatives, and an overview of asset renewal and network driven projects in each of our planning zones. For more detailed information, please visit Jim Vespalec Director, Asset Planning & Engineering Ron Snead Vice President, System Planning YEAR ASSESSMENT 3

4 Regional and economic planning ATC is an active participant in a variety of efforts to address regional and inter regional planning initiatives to maintain a reliable grid and capture economic benefits in a dynamic energy marketplace. Policy initiatives to curb greenhouse gas emissions and expand the use of renewable energy continue to evolve, and we work closely with our customers to plan for an electric transmission system that will serve their needs well into the future. MIDCONTINENT INDEPENDENT SYSTEM OPERATOR TRANSMISSION EXPANSION PLANNING MISO planning studies address long and short term issues as well as targeted needs. Long term studies primarily look at value based options that provide economic benefits in the 10 to 20 year horizon. Short term planning is primarily driven by transmission owners reliability and North American Electric Reliability Corporation compliance needs in a five to 10 year period. ATC staff participates in the MISO short term reliability and economic studies in a variety of ways: ensuring accurate project information is included in the MISO database, building and reviewing models, correlating needs identified by MISO analyses with specific ATC projects and participating in various studies and stakeholder forums. MARKET CONSTRAINTS Two of the five narrowly constrained areas identified in the MISO region are associated with ATC, and we continue to track these as well as other constraints. Such tracking assists in planning projects that alleviate congestion within the MISO market. OTHER MISO PLANNING ACTIVITIES Our planning staff participates in various technical and policy discussions and provides future direction for Midwest Transmission Expansion Plan activities. We also are involved in joint planning studies with neighboring regional transmission organizations, including PJM and SPP. MISO and PJM coordinate, conduct and analyze several market efficiency project studies. This analysis is reviewed by an inter regional planning stakeholder advisory committee, which typically examines economic projects that could benefit both Regional Transmission Organizations and qualify for cross border cost sharing. 4 AMERICAN TRANSMISSION CO.

5 Major projects update BADGER COULEE This fall, we expect to energize the 180 mile, 345 kv Badger Coulee transmission line, one of MISO s 17 Multi-Value Projects designed to deliver significant benefits to electric consumers throughout the Upper Midwest. A portion of the project from the Cardinal Substation to the North Madison Substation was placed in service in fall Developed jointly with Xcel Energy, the line will: offset the need for about $190 million in lower-voltage upgrades in western Wisconsin, increase access to the wholesale energy market and provide between $118 million and $700 million in net economic benefits over the life of the line, and establish another pathway for renewable energy into Wisconsin with a connection to key load centers. BAY LAKE The Bay Lake Project is a package of proposals that address the delicate, shifting balance between generation, load and transmission in the northern portion of our service area. The North Appleton Morgan project was placed in service in September 2018, ahead of schedule and under budget. It includes 345 kv and 138 kv lines from our North Appleton Substation in Outagamie County to the Morgan Substation in Oconto County, Wis. Both substations have been expanded and additional work was required at 11 other substations. A new substation, Benson Lake in Marinette County, was placed into service in July It includes a large voltage control device. North Appleton Morgan was approved by the Public Service Commission of Wisconsin in May 2015, with an authorized cost of $328 million. (continued on page 6) YEAR ASSESSMENT 5

6 Major projects update continued The Mount Pleasant Tech Interconnection Project will serve up to 230 MW of load, the largest load connected to a single substation on our system. CARDINAL HICKORY CREEK ATC, ITC Midwest LLC and Dairyland Power Cooperative filed an application in April with the Public Service Commission of Wisconsin for a 102- to 120 mile, 345 kv transmission line connecting Dubuque County, Iowa, to Dane County, Wis. The Cardinal-Hickory Creek Project is another MISO Multi-Value Project. Studies indicate that it will deliver benefits to local communities and the Midwest region by: improving electric system reliability locally and regionally, delivering $23.5 million to $350.1 million in net economic benefits, and connecting to other 345 kv transmission lines in the Upper Midwest and helping to enable 25 gigawatts of cost effective renewable energy to be delivered to communities in the region. If approved by Wisconsin and Iowa regulators, the project is estimated to be in service in SPRING VALLEY NORTH LAKE GENEVA Construction is underway on the $71 million Spring Valley North Lake Geneva Project, which was approved by the Public Service Commission of Wisconsin in spring This project is needed to meet an increase in electric demand in Walworth and Kenosha counties in Wisconsin. The project involves: construction of a new 138 kv transmission line of approximately 23 miles, stretching from the North Lake Geneva Substation in southern Walworth County to the Spring Valley Substation in western Kenosha County, construction of a new 138 kv and 69 kv substation on an ATC owned parcel along Highway 50 in the Town of Wheatland, construction of a new 69 kv transmission line to connect the new substation to the existing Twin Lakes Substation in Twin Lakes, and other power line modifications. The project is expected to be placed into service in AMERICAN TRANSMISSION CO.

7 FINGER ROAD CANAL The rebuild of a 69 kv line in northeastern Wisconsin, along with associated substation work, was approved by the Wisconsin Public Service Commission in spring 2017 at a cost of $60.7 million. About 55 miles of line on 1950s vintage wood poles between Finger Road Substation and Canal Substation will be rebuilt. The line serves seven distribution substations in northern Kewaunee County and Door County. The project includes: the replacement of 834 wood pole structures, the replacement of line conductor and addition of a fiber optic shield wire, the update at terminal end substations of jumpers, selective bus conductor, and disconnect switches. Construction is scheduled to complete in January MOUNT PLEASANT TECH INTERCONNECTION This project is designed to support Foxconn, which upon completion will be one of the largest manufacturing facilities in the nation with a campus build out anticipated to be approximately 22 million square feet. The initial projected electric usage would be 200 megawatts at this manufacturing facility, with an additional 30 MW of expected economic growth in the surrounding area. The electric load required for Foxconn s operations will be the largest connected to ATC s transmission system at a single substation. The project cost is estimated to be about $117 million and includes: constructing a new 345 /138 kv Mount Pleasant Substation, looping the Racine Pleasant Prairie 345 kv line into the new substation, stringing a new Racine Pleasant Prairie 345 kv circuit in the vacant position on existing structures and looping this new circuit into the new substation, reconfiguring the Racine Substation 345 kv bus, rerouting the Pleasant Prairie and Bain 345 kv line, uprating the Elm Road Racine 345 kv line, and constructing four new 138 kv underground lines (~400 feet) from the Mount Pleasant Substation to serve a customer owned substation. ATC submitted the CPCN application in late January 2018 to the Wisconsin Public Service Commission, which approved the project in July. Construction is underway. All electrical infrastructure has an expected in service date of late MACKINAC MCGULPIN 138 k V SUBMARINE CABLE REPLACEMENT ATC has plans to replace the two 4 mile, 138 kv submarine transmission lines connecting the Upper Peninsula of Michigan to lower Michigan at an estimated cost of $105 million. The Mackinac McGulpin 138 kv submarine cable replacement project was submitted for MISO review in the MTEP18 planning cycle. The project was developed for the following reasons: Two 138 kv submarine circuits were damaged by an anchor strike on April 1, Three working cables have been reconfigured to form one 138 kv circuit. The project will restore the eastern UP to the level of reliability it had before the April 1 event. The integrity of the remaining cables is of concern. The remaining cables contain a mineral oil based dielectric fluid; a submarine cable failure could result in a fluid leak into Lake Michigan and Lake Huron. As proposed, the project is estimated to be in service in (continued on page 8) YEAR ASSESSMENT 7

8 Major projects update continued BAYPORT PIONEER The rebuild of a 69 kv transmission line in northeastern Wisconsin, along with associated substation work, will be submitted to the Wisconsin Public Service Commission in spring 2019 at a cost of $51.7 million. Approximately 22 miles of line on 1910s vintage wood poles running between Bayport Substation and Pioneer Substation will be rebuilt. The line will serve three distribution substations in Brown County and Oconto County. The Bayport Pioneer asset renewal project consists of the following: rebuilding the line between Bayport and Pioneer substations with double circuit structures, stringing both Bayport Pioneer lines, combine, and operate as one line at 138 kv, converting Suamico and Sobieski substations to 138 kv operation, and de energizing the Pulliam Bayport 69 kv section of line. The project is scheduled to be in service in December JUNEAUTOWN INTERCONNECTION The Juneautown Interconnection Project is a 138 kv distribution transmission interconnection needed to meet We Energies growing reliability and economic needs. The cost of the project is estimated to be $34.1 million and includes: a new Juneautown 138 / 13.2 kv gas insulated substation, looping the 138 kv line between Haymarket and Harbor substations to feed the new substation, and routing the new line segments through new underground corridors. An application for a Certificate of Authority was filed with the Public Service Commission of Wisconsin in January 2018 and was approved in August. Construction is scheduled to begin in fall The facilities are scheduled to be in service approximately 12 months after construction begins. 8 AMERICAN TRANSMISSION CO.

9 By focusing on life-cycle cost, our asset management program helps us efficiently maintain and upgrade our older transmission assets. Our progress One of ATC s top priorities has always been electric reliability. With that focus, ATC has strengthened the grid to enable our customers to participate in and reap the benefits of the wholesale energy market. As we continue to use our system wide planning process to effectively and economically improve reliability, more emphasis is being placed on the need to efficiently maintain and upgrade our older assets. Our asset management program is focused on the life cycle management of transmission assets. The objective is to ensure assets perform the required function in a sustainable manner while managing life cycle cost. Coordination of design, commissioning, operation and maintenance is crucial to developing the replacement strategy of the assets. Asset renewal is mainly driven by public and worker safety, regulatory compliance, reliability, condition and operational performance. Our single focus, transmission only business model has produced significant results for our customers over the years. Over the past ten years, we have: upgraded more than 895 miles of transmission line, improved 105 electric substations, built 25 new transmission lines (367 miles) connected 1,980 MW of new generation at 12 sites, Includes 430 MW of renewable generation at 6 sites saved customers millions in reduced energy costs with access to the marketplace and lower line losses, increased import and export capability, and improved transmission reliability. Due in large part to our asset management efforts, ATC consistently achieves better reliability performance than our industry peers in all voltage classes YEAR ASSESSMENT 9

10 What drives the need for transmission system improvements? Early in our operational existence we focused on creating a smooth flowing electrical highway to more reliably serve our customers. This involved finding the logical places in our service area to develop transmission projects. Major, network driven projects accounted for significant investment in our 345 kv system. As we were making our network more interconnected and reliable, we also analyzed the life cycle maintenance of our existing assets, focusing on an asset management strategy to complement and create synergies with our network additions. Today, our effective management of transmission assets complements our planning strategy for electric reliability and economic benefits. In a collaborative process, our asset management and planning teams work with other functional groups and stakeholders to achieve the best solutions to transmission system needs. Asset management staff monitor the system through maintenance and inspection programs to identify issues related to equipment performance or condition. Equipment needing attention is discussed internally and with customers to determine if replacement in kind is required and if other reliability needs exist within the geographic area. Needs are evaluated using various options to determine the best means of maintaining reliability. These discussions with customers occur at 10-Year Assessment stakeholder meetings and MISO System Planning Meetings. COMMON NEEDS THAT DRIVE SYSTEM IMPROVEMENTS INCLUDE: New or retiring generation changes in the generation impact on the transmission system, the location and amount of power flowing as well as system stability Economics greater access to the wholesale energy marketplace provides economic opportunities to utility customers Enhanced NERC reliability standards require a greater degree of redundancy and analysis to assure reliable, resilient operation Public policy renewable energy mandates and pending air quality regulations will affect how the transmission system will be built and used Asset renewal maintaining the system in good operating condition extends its life and improves safety and performance Interconnections changes in how our customers distribute electricity to consumers require new or modified transmission facilities Load changes while overall load growth is low, loads are appearing and disappearing, changing power flows on the system New technologies synchronized phasor measurements, demand side management and distributed energy resources affect how the grid is planned and operated to maintain reliability Communications improvements in communication technology, such as fiber optics, are incorporated to support an ever increasing need to see and control what is happening on the transmission system in real time 10 AMERICAN TRANSMISSION CO.

11 Plans and proposals for the transmission system For planning purposes, ATC s service area is divided into five zones representing distinct geographic or usage areas. Within each zone, we compile and assess transmission system needs. PROJECT CLASSIFICATIONS Network and asset renewal projects have targeted in service dates that are designed to address system limitations and condition needs. The network projects are classified into one of three possible categories Planned, Proposed or Provisional, depending upon the stage of the project. Planned Proposed Provisional Status of ATC Studies complete Studies not complete Studies not complete planning activities Application for Application pending None None regulatory approval or order issued Project status Project in construction Project identified Project is not planning phase or under as preferred necessarily the preferred construction alternative alternative Asset renewal projects generally fall into the Provisional or Planned categories. Project is not necessarily the preferred project alternative YEAR ASSESSMENT 11

12 WOOD JUNEAU LINCOLN ONEIDA MARATHON ADAMS PORTAGE LANGLADE WAUSHARA SHAWANO WAUPACA LAKE NORTH CENTRAL WISCONSIN Zone 1 MARQUETTE GREEN Transmission system characteristics in Zone 1 ATC delivers power in Zone 1 with various transmission facilities including: East west 345 kv line from the Village of Arpin through Stevens Point extending to the Appleton area, 345 kv line extending from Stevens Point, north to Wausau, and east toward Shawano County, 345 kv line extending from Wausau to northeastern Minnesota, 115 kv network in the northern portion of the zone and 138 kv and 69 kv network in the southern portion of the zone. Transmission system limitations in Zone 1 Zone 1 has a few key system performance issues. Low voltages that are a result of potential multiple contingency events will continue to be monitored, high voltages in the northern portion of the zone, and other studies have identified thermal limitations in the northern portion of the zone. The most severe limitations occur during both peak and off peak periods. ELECTRIC SYSTEM OVERVIEW Small increases expected in population, employment Population in Zone 1 is projected to grow at 0.5 percent annually between now and Employment is projected to grow at 0.9 percent annually between now and Marathon County is projected to realize the largest increase in population and employment, while Adams County is projected to have the highest growth rate in population and employment. Electricity usage Peak electric demand typically occurs during the summer months, with some winter peaks appearing in the northern portion of the zone. Primary electricity users in Zone 1 include several large paper mills and food processing plants. Electric load is forecasted to grow approximately 0.4 percent annually through COUNTIES INCLUDED IN ZONE 1 NORTH CENTRAL WISCONSIN Adams Forest (southwestern portion) Fond du Lac (northwestern portion) Green Lake Juneau Langlade Lincoln Marathon Marquette Monroe (eastern portion) Oneida Portage Shawano (western portion) Vernon (eastern portion) Vilas (southern portion) Waupaca Waushara Winnebago (western portion) Wood 12 AMERICAN TRANSMISSION CO.

13 YEAR ASSESSMENT 13

14 WOOD JUNEAU LINCOLN ONEIDA MARATHON ADAMS PORTAGE LANGLADE WAUSHARA SHAWANO WAUPACA NORTH CENTRAL WISCONSIN MARQUETTE GREEN LAKE Zone 1 TRANSMISSION PROJECTS IN ZONE 1 The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 1, along with their projected year of completion and the factors driving the need for the projects, are listed below. PROJECT DESCRIPTION IN SERVICE YEAR NEED DRIVER 1 Planned Projects Wild Rose Harrison 69 kv line (Y 19) partial rebuild 2020 Condition and performance 2 Chaffee Creek Lincoln Pump Station 69 kv line (Y 18) rebuild 2021 Condition and performance 3 Wautoma Chaffee Creek 69 kv line (Y 49) rebuild 2021 Condition and performance Additional projects may be found in the full 10 Year Assessment at atc10yearplan.com. SUBSTATION KEY TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY New substation Supports transmission system expansion Substation modifications Upgrades equipment ratings to avert facility overloads Transformer Supports local growth and improves voltage levels Capacitor bank or reactor Relieves low voltages or high voltages T-D interconnection Supports local growth SYSTEM SOLUTIONS KEY 345-kV transmission line 115-, 138- or 161-kV transmission line 69-kV transmission line Rebuilt 115- or 138-kV transmission line Rebuilt 69-kV transmission line 115- or 138-kV transmission line rating upgrade 69-kV transmission line rating upgrade 69 kv 115 kv 138 kv 161 kv 230 kv 345 kv Lines of proposed projects on the map are for illustrative purposes only and do not reflect actual routes. For information on project status and routes, see atc projects.com. 14 AMERICAN TRANSMISSION CO.

15 e Saratoga Wood Plainfield Arrowhead (ALTE) Wildrose Plainfield Sherwood Springwater Sand Lake Wild Wild Cottonville Rose Fountain Rose Pump Sawyer Hancock Valley Wautoma Waushara Hancock Pershing Adams Red Granite Coloma!3 3 Wautoma Coloma Silver Friendship Lake Lincoln Pump Richford (ALTE) Spring STA! 2 Chaffee CreekTaylor Lake Friendship Price Adams Line 61 Turtle Grand Marsh Westfield Lake Mckenna Brooks Winnebago Jackson Crawford Seneca Rusk Vernon Monroe County Gays Mills DPC Bell Center Grant AshlandGolden Sands Wautoma Area Portage Chateau Glen Neenah Creek Oxford Clark T Corners Wien SW STA Stratford McMillan Wildwood (MEWD) Mill Creek Hume Rozellville Auburndale Eastom Tomahawk - Skanawan ATC 115kV SW STR Tomahawk Grandfather Falls Grandfather Falls Hydro Cassel Lincoln Pine (WPS) Maine Hilltop (WPS) Sherman St Sunnyvale Kelly Weston SW YD Morrison Ave Gardner Park Cedar Creek Mosinee Paper Mill Kronen Guenther CWEC Dewey Richfield Arpin Northpoint CWEC Iola Lawn Portage Rudolph Iola Rocky Run Hoover Pittsville Vesper Sigel Amherst Jct Whiting Ave CWEC Sannes Arnott Waupaca Manawa Wood Consulated Okray Lakehead West Water Power Plover Vesper Werner West Wisconsin (rrn) Sheridan Werner Outagamie Rapids Coyne St (ALTE) Harrison Hintz North Ellington Wisconsin Rapids Golden Sands 138kV Hartman Creek White Port Edwards Baker St Waupaca Harrison Lake (WE) Vulcan Chem 69kV Apple Hills Hollywood Grant Saratoga Casaloma Butte Des!1 1 Morts Arrowhead Plainfield Northside Plainfield (ALTE) Wildrose M Neevin Sherwood Tayco Melis Wild Rose Winnebago Badger West Springwater Sand Lake Woodenshoe Cottonville Wild Fountain Hancock Rose Pump Valley Winneconne Warrens Waushara Wautoma Mears Corners Hancock Sunset Point Big Pond Wautoma Spring Bowen St Adams Red Granite Omro Coloma Lake Coloma!3 3 Pearl Ave Silver Oshkosh Tunnel City Necedah Omro Cardinal Lake Ellinwood River Run Industrial North Tomah Glass Tomah Dellwood Richford (ALTE) Lincoln Park Friendship Council Creek Pump Berlin Tomah Chaffee Creek Juneau STA!2 2 Fox River Fitzgerald Industrial Pk Houghton Rock Friendship Aviation Timberwolf Camp Douglas Adams Line 61 Turtle Mckenna Grand Marsh Westfield Lake Ripon Dartford DPC Buckhorn Brooks Ind Park Marquette Dorset DPC New Green Lake Corners Lisbon Castle Rock Quincy Northwest Fond Du Lac North Ripon Hilltop Chateau Ripon Fond Du Sadoff Roeder Metomen Lac West Mauston (ALTE) Montello Rosendale Forest Co Eas Winnebago Neenah Creek Green Lake Mauston Glen Montello Mercury SW STA Oxford Brandon Marine Mar Lyndon Mackford Station Markesan Prairie Fairwater South Fond Koch Oil Du Lac Wind G Union Center SW YD DPC Lyndon Endeavor Alto Roslin Oakfield Wonewoc Station Wisconsin Creek Hillsboro Dells Waupun Forward Wisconsin Muni 1 Lakehead Westside Energy Dells Muni 2 Platt Portage Center Buttern Finnegan Dell Creek Kilbourn Loch Mirror Lewiston Cambria North Friesland Reedsburg Zobel Birchwood Hamilton St Randolph Fox Lake Nishan Trienda (ALTE) Staff Portage Ind Pardeeville Didion Reedsburg Fox Hills Portage Sanborn Cambria Artesian Park Randolph Mayville Lake Delton Manley North Rock Springs Sand Wyocena Beaver Dam Spring Brook Island Caledonia Beaver Dam Horicon Baraboo Rio Pumping 3rd St Ind Park Kirkwood (ALTE) Columbia Station Hubbard Loganville SW YD Center St Beaver Dam East Juneau Skillet Creek Calamus (ALTE) Northside Horicon Merrimac Sauk Doylestown South Richland Columbia Beaver Dam Juneau Downtown Poynette Fall River Fountain Prairie Dodge Juneau Industrial Okee Academy Columbus Richland Hustisford Lodi Muni 1 Ha Arlington Center Maple Street Industrial Columbus Butler Ridge Richland Dam Heights Park Lodi Hampden Columbus (ALTE) Brewer Rubicon Pine South River Ninth Street North Madison (ALTE) Troy Sauk City Sauk City Phillips St 345/138 kv North Madison Oak St Dane Dane Deforest Monroe Marquette Harrison Waupaca Iron Hartman Creek 69kV Harrison North 138kV! 1 Montello Montello Waupaca Roeder Green Lake Green Lake SW STA Markesan Marathon Ackley Groenier Venus Antigo Aurora St Birnamwood Metonga YEAR ASSESSMENT Summit Lake (WPS) Langlade Polar Deer Trail Brooks Corners Forest Menominee Middle Vlg Oconto Mountain Silver Cli Wittenberg CWEC Wittenberg White Cla Whitcomb Shawano East Shawano CWEC Tigerton West Shawano Highway 22 Badger Caroline Cloverleaf Marion Belle Plaine Rosholt Clintonville Rosholt CWEC 15 Hills S YEAR ASSESSMENT 15

16 MICHIGAN S UPPER PENINSULA AND NORTHERN WISCONSIN Zone 2 Transmission system characteristics in Zone 2 ATC delivers power in Zone 2 with various transmission facilities including: Morgan Plains, Plains Arnold, and Arnold Dead River 345 kv lines, Plains Stiles 138 kv double circuit line, Lakota Road Plains 138 kv line, Holmes Old Mead Rd 138 kv line, and 138 kv facilities tying the Upper Peninsula of Michigan to lower Michigan. Transmission system limitations in Zone 2 There are a number of transmission system performance issues in Zone 2, including limited ability to import or export power, generator instability, overloaded lines and equipment, low and high system voltages and chronic limitations to transmission service. Primary drivers of these issues include a mismatch of load to generation in the Upper Peninsula and aging facilities in poor or deteriorated condition. In addition, other ongoing studies, including northern area studies performed by ATC and MISO, have identified several voltage and thermal limitations. The most severe limitations occur during both peak and off peak periods. ELECTRIC SYSTEM OVERVIEW Small increases expected in population, employment Population in Zone 2 is projected to grow about 0.2 percent annually between now and 2027, and employment is expected to grow about 0.8 percent each year in the same time period. Marquette County (Michigan) is projected to realize the largest increase in population and employment. Florence County (Wisconsin) is projected to have the highest growth rate in population while Keweenaw County (Michigan) is projected to have the highest growth rate in employment. Electricity usage Zone 2 typically experiences peak electric demand during the winter months. Ore mining and paper mills are the largest electricity users in the zone. In the recent past, there have been some load reductions in Zone 2. From these reduced levels, electric load is forecasted to increase by 0.4 percent annually through Also, locally generated electricity is declining in the area with smaller, coal fired generators most at risk. This includes generation owned by industry, municipalities and utilities. COUNTIES INCLUDED IN ZONE 2 MICHIGAN S UPPER PENINSULA AND NORTHERN WISCONSIN Alger, Mich. Baraga, Mich. Chippewa, Mich. Delta, Mich. Dickinson, Mich. Florence, Wis. Forest, Wis. (northern portion) Gogebic, Mich. (eastern portion) Houghton, Mich. Iron, Mich. Keweenaw, Mich. Luce, Mich. Mackinac, Mich. Marinette, Wis. (northern portion) Marquette, Mich. Menominee, Mich. (northern portion) Ontonagon, Mich. (eastern portion) Schoolcraft, Mich. Vilas, Wis. (northern portion) 16 AMERICAN TRANSMISSION CO.

17 YEAR ASSESSMENT 17

18 MICHIGAN S UPPER PENINSULA AND NORTHERN WISCONSIN Zone 2 TRANSMISSION PROJECTS IN ZONE 2 The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 2, along with their projected year of completion and the factors driving the need for the projects, are listed on page 19. L a k e S u p erior UPSCO Ontonagon Winona Osceola Boston Elevation St MTU Atlantic Henry St. Portage (UPPCO) (UPPCO) Toivola Donken Houghton Keweenaw Keweenaw SYSTEM SOLUTIONS KEY SUBSTATION KEY New substation Supports transmission system expansion Substation modifications Upgrades equipment ratings to avert facility overloads Transformer Supports local growth and improves voltage levels Capacitor bank Relieves low voltages or high voltages T-D interconnection Supports local growth TRANSMISSION LINE KEY 345-kV transmission line 115-, 138- or 161-kV transmission line 69-kV transmission line Transmission line voltage conversion Rebuilt 115- or 138-kV transmission line Rebuilt 69-kV transmission line 115- or 138-kV transmission line rating upgrade 69-kV transmission line rating upgrade EXISTING TRANSMISSION LINES KEY 69 kv 115 kv 138 kv 161 kv 230 kv 345 kv White Pine Mine hite Vlg gebic Eagle River St Germain Cranberry Clear Lake (WPS) Rhinelander Paper Hodag Highway Eight om Skanawan SW STR oln ine Vilas Pine (WPS) herman St Kelly Morrison Ave Cedar Creek Lake Mine Rockland Mass (UPP) Victoria Hy Ontonagon Land O Lakes Oneida Ackley Marathon Lakota Rd Conover Bruce Crossing Watersmeet Venus 6 Twin Lake Three Lakes Summit Lake (WPS) Langlade Polar Antigo Aurora St Brooks Birnamwood Corners Wittenberg CWEC Wittenberg Whitcomb Metonga Deer Trail Forest Shawano M-38 JH Warden L'anse Baraga Vlg 3 Lakehead Iron River Homer Road Iron Grove Menominee Middle Vlg West Shawano Iron Baraga Florence Crystal Falls Sagola Felch Peavy Randville Nordic Mountain Falls Hy Brule SW STA Michigamme Aspen Falls Hy Twin Falls Florence SW STA Pine Hy Bass Lake Armory Plains Norway Grede Foundries Aragon Kingsford Champion Bluff Metals Niagra View Paper Of Wisconsin Goodman White Clay Way Plant Greenstone Humboldt Mine Perch Lake Lena Oconto Falls Stiles SW STA Pioneer (WPS) Dead River Presq (WE) Isle S Big Bay Marqu North Diese Lake Barnum Huron National Empire Mine Tilden Mich Transmitter Facility Nathan Sawyer Lumber K I Gwinn Forsyt Arnold Watso Watson Powers Amberg White Chalk Hill Hy Benson Lake Rapids Hy Holmes Silver Cliff Marinette Fox Hills SW Grand STA Rapids Hy Ingalls Caldron Falls Hy High Falls Hy Sandstone Thunder Rapids Hy Mountain Crivitz Bay De Noc 30th Ave Pound Peshtigo Sherwood Oconto 5 Marquette Dickinson 2 4 Menomin Sawye SW STA Redwood Industria Brusbay 18 AMERICAN TRANSMISSION CO.

19 PROJECT DESCRIPTION IN SERVICE YEAR NEED DRIVER Planned Projects Munising Blaney Park 69 kv line (Inland) rebuild 2019 Condition and performance J703: Huron Substation, new G T interconnection 2019 G T interconnection J704: Silver River Substation, new G T interconnection 2019 G T interconnection Plains Arnold 138 kv uprate 2019 Network integration transmission service request 5 Proposed Project J711 Silver River Substation, network upgrades 2020 G T interconnection 6 Provisional Projects Lakota Winona 138 kv conversion 2021 Overloads and low voltages 7 Mackinac McGulpin 138 kv submarine cables (9901, 9903), replacement 2021 Condition Additional projects may be found in the full 10 Year Assessment at atc10yearplan.com. ue W YD ette l Sawyer h Timber Munising Products Chatham Alger Forest Lake Shingleton Hiawatha (AD-REA) Alger 1 Schoolcraft Magazine Portage St Hy 3 Mile Sault Pine Grove Luce Brimley Dafter 9 Mile SW STA Raco Eckerman Newberry Vlg Hulbert Seney (UPPCO) Lou Pac Newberry Hulbert Chippewa Tone Seney Newberry Kincheloe (AD-REA) Correctional Trout SW STA Facility Pickford Lake (CEC) Rudyard Pickford Pine River Rockview Engadine Lakehead Rexton Frank Mackinac Talentino Gould City Limeston Hiawatha Lakehead SW STA Curtis Goetzville (ESE) Naubinway Mich Frank Detour Gould City Brevort Blaney Limestone Talentino SW STA Park Quarry Mich Limestone SW STA Loading Dock n Lakehead Indian Lake Perkins Valley (ESE) Rapid Delta Evergreen River Garden Manistique Glen Jenks Mackinac Corners St Ignace Cornell-UP Mackinac Converter Masonville Straits (UPPCO) Chandler Gladstone McGulpin Old Mead Road 7 Mead Paper North Bluff Mead Pump Delta (UPPCO) Escanaba Steam Plant Harris West Side Emmet Cheboygan ee Door Dunn Rd r Michigan St Canal l Sister Bay Egg Harbor L a k e M i c higan Leelanau Charlevoix Antrim Kalkaska Alpena Lines of proposed Montmorency projects on the Otsego map are for illustrative purposes only and do not reflect actual routes. For information on project status and routes, see atc projects.com. Crawford Oscoda Presque Isle Alcona YEAR ASSESSMENT 19

20 SOUTH CENTRAL/SOUTHWEST WISCONSIN AND NORTH CENTRAL ILLINOIS Zone 3 Transmission system characteristics in Zone 3 ATC delivers power in Zone 3 with various transmission facilities including: Columbia North Madison 345 kv lines, Columbia Rockdale 345 kv line, Paddock Rockdale 345 kv line, Paddock Wempletown 345 kv line, Rockdale Wempletown 345 kv line, Rockdale Cardinal 345 kv line, and 138 kv facilities from Nelson Dewey, around the Madison area, and in the northwest and southeast portions of Zone 3. Transmission system limitations in Zone 3 ELECTRIC SYSTEM OVERVIEW Increases expected in population, employment Population in Zone 3 is projected to grow about 0.8 percent annually between now and 2027, and employment is projected to grow about 1.3 percent each year for the same time period. Dane County is projected to realize the largest increase in population and employment. Dane County is also projected to have the highest growth rate in population and employment. Electricity usage Electric load is forecasted to grow approximately 0.7 percent annually through 2028 in Zone 3. In our analysis of Zone 3, we identified a number of transmission facility overloads. These overloads are due to new generation in the Janesville and Darlington areas. In addition, other emerging issues resulting in facility overloads include steady growth in certain areas and different generation dispatches. The most severe limitations occur during both peak and off peak periods. COUNTIES INCLUDED IN ZONE 3 SOUTH CENTRAL/SOUTHWEST WISCONSIN AND NORTH CENTRAL ILLINOIS Columbia Crawford (southern portion) Dane Dodge Grant Green Iowa Lafayette Jefferson Richland Rock Sauk Walworth Winnebago, Ill. (northern portion) 20 AMERICAN TRANSMISSION CO.

21 YEAR ASSESSMENT 21

22 SOUTH CENTRAL/SOUTHWEST WISCONSIN AND NORTH CENTRAL ILLINOIS Zone 3 TRANSMISSION PROJECTS IN ZONE 3 The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 3, along with their projected year of completion and the factors driving the need for the projects, are listed on page 23. Briggs Road Sauk La Crosse Monroe County Monroe Timberwolf Industrial Pk Dorset Corners Vienna Sun Prairie Waunakee Business Park Mazomanie Industrial Token Creek Division Street Industrial Park Mazomanie Yahara River Colorado Bird St Centennial Wick Drive Park Highway 151 Waunakee SW South STA Sun American Prairie Black Earth Westport Dane Huiskamp Burke Stage Coach SW STA Walnut GIS! Sycamore Reiner Rd Pheasant SW YD West Branch Mendota Gaston Rd Ruskin East Towne Middleton Walnut Royster Sprecher Cross Plains Gateway (MGE) 9 Blount Cottage Grove Cardinal Blackhawk (MGE) Pflaum Pleasant View AGA Gas East Campus Wingra Femrite Tokay McFarland Wally Road Syene Nine! Timberlane West Towne Femrite East 10 Fitchburg 138/69 kv Lincoln St Springs Mount Horeb Colladay Cross Country Oak Ridge Point Kegonsa Verona Vernon! North 8 Stoughton Sun Valley Oregon Iowa Madison Area Hillsboro Camp Douglas DPC New Lisbon Union Center West Mau Wonewoc Jun SYSTEM SOLUTIONS KEY SUBSTATION KEY New substation Supports transmission system expansion Substation modifications Upgrades equipment ratings to avert facility overloads Transformer Supports local growth and improves voltage levels Capacitor bank Relieves low voltages or high voltages T-D interconnection Supports local growth TRANSMISSION LINE KEY 345-kV transmission line 115-, 138- or 161-kV transmission line 69-kV transmission line Rebuilt 115- or 138-kV transmission line Rebuilt 69-kV transmission line 115- or 138-kV transmission line rating upgrade 69-kV transmission line rating upgrade EXISTING TRANSMISSION LINES KEY 69 kv 115 kv 138 kv 161 kv 230 kv 345 kv Lines of proposed projects on the map are for illustrative purposes only and do not reflect actual routes. For information on project status and routes, see atc projects.com. Allamakee Clayton Brisbois Nelson Dewey SW YD Seneca Hillside DPC Gran Grae Gran Grae La Pointe Prairie Du Chien Glen Haven Cassville Crawford DPC Stoneman Wauzeka Bloomington Gays Mills DPC Bell Center Grant Boscobel Muni Boscobel Boscobel Boscobel Muni Eastside Lancaster Distribution Potosi Lancaster Blue River 4 Pioneer(ALTE) Hillman Richland Muscoda Hill Valley Brewer Elmo Richland Center Muscoda Industrial Sub Eden Cuba City Pine River (ALTE) Rewey Richland Avoca Belmont 9 Falcon Lone Rock Iowa Lands End Mineral Point Red Bird Kieler Cuba City South Benton Shullsburg DPC Shullsburg to Dubuque County area Miners Delaware Dubuque 22 AMERICAN TRANSMISSION CO.

23 Wyoming Valley Dodgeville Rock Branch Darlington Spring Green Lafayette DPC Gratiot PROJECT DESCRIPTION IN SERVICE YEAR NEED DRIVER Planned Projects Badger Coulee: Briggs Rd North Madison Cardinal 345 kv line construction Lone Rock Friendship Boscobel Pump STA 69 kv line (Y 124) rebuild 2019 Condition and performance Mckenna Grand Marsh Westfield Lake Portage Staff North Randolph 138 kv lines (X 6), (X 98), rebuild 2020 Condition Dartford Ripon and performance Ind Park Adams Brooks Quincy Sheepskin Stoughton 69 kv line (Y 12) rebuild Green Lake 2021 Condition and performance Troy Arena Wiota Sauk New Hollandale Mazomanie Industrial Wick Drive Blanchardville Jennings Rd SW STA Mazomanie Black Earth Stage Coach SW STA Cross Plains Browntown Forward Dam Heights Wally Road Mount Horeb Dane Green Idle Hour South Monroe Lodi Industrial Park Pleasant View New Glarus Okee Monticello (ALTE) Lodi North Monroe North Madison 345/138 kv Tokay Blacksmith Walnut GIS Syene Brodhead Spring Grove Poynette Blount AGA Gas Wingra Pflaum Femrite Albany (ALTE) Nine Springs Brooklyn Brodhead SW STA REC Orfordville Hampden McFarland Stoughton South Union Townline Vinburn Kegonsa REC Newark Cottage Grove North Stoughton Stoughton Stoughton East Footville Bass Creek Fall River Fountain Prairie Academy Columbus Maple Street (ALTE) Dana Corp Paddock Columbus South Christiana Sheepskin Lakehead Waterloo Rock McCue Boxelder London Russell Traxler Viking Columbus Muni 1 Rockdale Stony Brook Milton Lawns Venture Tripp Rd REC LaPrairie Rock River Turtle Marine Lakehead Cambridge LaMar Sunrise Scot Forge 2 Crawfish River Scot Forge 1 Dodge Jefferson Colley Rd REC Clinton East Beloit Shirland Park Ave Ave REC East Rockton Shaw Fort Atkinson REC Red Hawk Juneau Industrial Jefferson REC Bradford University (WE) Concord SW YD Walworth Sharon Delavan Bluff Creek Hustisford Bristol (ALTE) West Southwest Delavan Williams Darien Bay Brick Church Walworth Butler Ridge Rubicon Cooney Sugar Creek Elkhorn Fond Du Lac Castle Rock DPC Buckhorn 7 Northwest Ripon North Hilltop Chateau Ripon Fond Du Roeder Metomen Lac Sadoff ston (ALTE) Proposed Projects Montello Rosendale Forest Co East Scott St Ledgeview Mauston Winnebago Neenah Creek eau Marquette Green Lake Macy St 8 Northern Lights Substation, Glen new T D interconnection 2020 T D interconnection SW STA Mercury Marine Ohmstead Oxford Brandon Willow Lawn Rienzi Road 9 Cardinal Hickory Creek 345 kv line construction 2023 Reliability, economics and public Martin policy Mackford Rd South Fond Markesan Prairie Fairwater Koch Oil Oakfield Du Lac SW YD Lyndon Provisional Project Station Forward Endeavor Alto Roslin Energy Creekview 10 Cardinal DPC Lyndon Blount 138 kv line construction 2029 Overloads and low voltages Station Wisconsin Center Dells Waupun Wisconsin Muni 1 Lakehead Additional Dells Muni projects 2 Platt may be found in the full 10 Year Assessment at atc10yearplan.com. Waupun Portage Butternut Finnegan Kilbourn Westside Dell Creek Loch Mirror Lewiston Cambria Zobel Hamilton St Staff Friesland Reedsburg Birchwood North Fox Lake Trienda Nishan Randolph (ALTE) Portage Ind Pardeeville Sanborn Cambria Didion Randolph Reedsburg Artesian Fox Hills Portage Park Mayville Lake Delton 6 North Rock Springs Manley Sand Beaver Dam 1 Horicon Spring Brook Rio Pumping Island Beaver Dam Beaver Caledonia Ind Baraboo Columbia Wyocena Station 3rd St Dam East Park Kirkwood (ALTE) SW YD Center St Hubbard Loganville Skillet Creek (ALTE) Columbia Juneau Calamus Northside Horicon Merrimac Doylestown South Beaver Dam Hooterville Sauk City Phillips St East Lincoln St Ninth Street Sauk City Oak St Timberlane Dane West Towne North Madison Cross Country Fitchburg Verona Belleville Oak Ridge Brodhead South Arlington Vienna Sun Prairie Business Park Division Yahara River Street Centennial Park Bird St Token Creek South Waunakee SW Burke Sun Prairie STA American Highway 151 Westport Sycamore Reiner Rd Pheasant SW YD West Branch East Towne Ruskin Middleton Gaston Rd Walnut Royster Cardinal (MGE) Sprecher Monroe Central Sun Valley Brodhead North Colladay Point Oregon Deforest Evansville Muni Brodhead Central Orfordville REC Center REC Fulton Cambridge Saunders Creek REC Harmony Tyranena Janesville General SW YD Whitewater Lakehead Delavan Juneau Downtown Lakehead Pipeline North Lake Geneva Lake Geneva Zenda Cobblestone Hartford Summit Waukesha Mukwonago St Lawrence Washington Bark River Cottonwood (WE) South Lake Geneva Katzenberg Cedar Ridge Wind Generation Arthur Road Merrill Hills Burlington Waukesha Air Liquide Balsam New Holstein SW STA Houghton Rock Adams Line 61 Spring Valley North Lake Geneva 138 kv line construction 2019 Overloads and low voltages, provide network service Turtle Cypress SW YD Esker View I L L I NOIS Stoughton West 7 2 Lakehead Waterloo 2 Edgerton Business Park 2018 Reliability, economics and public policy J390: Kittyhawk Substation, new G T interconnection 2019 G T interconnection J395: Darlington North Monroe 138 kv line (X 49), Uprate 2019 G T interconnection Lakehead Delavan T2 Tiger 23 5 Auburn Glacier Sussex Edgewood Barton Pleasant Valley Racine Kettle Morraine (ALTE) Maple (WE) Tamarack Duplainville Tichigan Mill Rd Kenosha Twin Lakes (ALTE) Richmond Road Germantown SW YD YEAR 10-YEAR ASSESSMENT 23

24 NORTHEAST WISCONSIN Zone 4 Transmission system characteristics in Zone 4 ATC delivers power in Zone 4 with various transmission facilities including: four 345 kv lines extending from the Point Beach Nuclear Plant, two 345 kv lines extending from the Edgewater Power Plant to South Fond du Lac and Cedarsauk, two additional 345 kv lines connecting the South Fond du Lac Power Plant to Columbia and Fitzgerald, four 345 kv lines connecting the Gardner Park, Werner West, Morgan, and Plains Substations, four 345 kv lines from North Appleton to Kewaunee, Fox River, Werner West and Fitzgerald, and a 138 kv network throughout the zone. Transmission system limitations in Zone 4 In our analysis of Zone 4, we found high voltages in Calumet County and impending low voltages in Brown County. In addition, other ongoing studies have identified several voltage and thermal limitations. The most severe limitations occur during both peak and off peak periods. ELECTRIC SYSTEM OVERVIEW Increases expected in population, employment Population in Zone 4 is projected to grow at 0.6 percent annually between now and Employment is projected to grow at 1.0 percent annually between now and Brown County is projected to realize the largest increase in population and employment. Calumet County is projected to have the highest growth rate in population and Sheboygan County is projected to have the highest growth rate in employment. Electricity usage Peak electric demand typically occurs during the summer months, although the northern portion of Zone 4 typically experiences nearly equal summer and winter peaks. Paper mills and foundries in and around the Green Bay and Appleton metropolitan areas are some of the largest electricity users in the zone. Electric load is forecasted to grow at approximately 0.3 percent annually through Also, locally generated electricity is declining in the area with smaller, coal fired generators most at risk. This includes generation owned by industries, municipalities and utilities. Several area projects are related to the underlying condition and performance of assets in Zone 4. COUNTIES INCLUDED IN ZONE 4 NORTHEAST WISCONSIN Brown Calumet Dodge (northeastern corner) Door Fond du Lac (eastern portion) Kewaunee Manitowoc Marinette (southern portion) Menominee, Mich. (southern portion) Menominee, Wis. Oconto Outagamie Shawano (eastern portion) Sheboygan Winnebago (eastern portion) 24 AMERICAN TRANSMISSION CO.

25 YEAR ASSESSMENT 25

26 NORTHEAST WISCONSIN Zone 4 TRANSMISSION PROJECTS IN ZONE 4 The most notable planned, proposed and provisional network projects and asset renewal projects in Zone 4, along with their projected year of completion and the factors driving the need for the projects, are listed below. PROJECT DESCRIPTION IN SERVICE YEAR NEED DRIVER 1 Planned Projects Bay Lake: North Appleton Morgan 345 kv and 138 kv line construction 2018 Overloads and low voltages Cedar Ridge Wind Mullet River 138 kv line (X 97) rebuild 2020 Condition and performance Edgewater SS, 345 kv bus reconfiguration 2020 Condition and performance Goodman Caldron Falls 69 kv line (J 88) rebuild 2020 Condition and performance 5 Butte des Morts Sunset Point 138 kv lines (40321), (80952), (A 79), (MCRG21) rebuild 2021 Condition and performance Finger Rd Canal 69 kv line (J 10) rebuild 2021 Condition and performance Ogden St. Bayshore 69 kv line construction 2021 Provide network service Hwy V Oak St 69 kv line (Z 26) rebuild 2022 Condition and performance Proposed Projects Bayport area Pioneer, rebuild as double circuit 138 kv 2021 Condition, performance and provide network service Pioneer Crivitz (E 83/B 2), retire 69 kv and 2022 Condition, performance, reconfigure load to 138 kv and provide network service Additional projects may be found in the full 10 Year Assessment at atc10yearplan.com. New substation Supports transmission system expansion Substation modifications Upgrades equipment ratings to avert facility overloads Transformer Supports local growth and improves voltage levels Capacitor bank or reactor Relieves low voltages or high voltages T-D interconnection Supports local growth SYSTEM SOLUTIONS KEY SUBSTATION KEY TRANSMISSION LINE KEY EXISTING TRANSMISSION LINES KEY 345-kV transmission line 115-, 138- or 161-kV transmission line 69-kV transmission line Transmission line voltage conversion Rebuilt 115- or 138-kV transmission line Rebuilt 69-kV transmission line 115- or 138-kV transmission line rating upgrade 69-kV transmission line rating upgrade 69 kv 115 kv 138 kv 161 kv 230 kv 345 kv 26 AMERICAN TRANSMISSION CO.

27 Metonga Forest Amberg Benson Lake Chalk Hill Hy White Rapids Hy Holmes Menominee Fox Hills Silver Cliff SW STA 4 Caldron Falls Hy Grand Rapids Hy Ingalls Langlade High Falls Hy Thunder High Falls Hy Marinette Sandstone Rapids Hy r Brooks Corners Polar Deer Trail CWEC Tigerton EC Iola Harrison North 138kV Waupaca rrison 9kV Green Lake SW STA Markesan Fountain Valley Waushara d Granite North Friesland Randolph a Randolph Didion Manawa Waupaca Green Lake mbia Shawano White Lake (WE) River Run Fox River Berlin Marion Ripon Dartford Northwest Ind Park Ripon Ripon Mackford Prairie Fox Lake (ALTE) Caroline Fairwater Werner West Hintz Werner Metomen Middle Vlg Brandon Alto Menominee West Shawano East Shawano Highway 22 Badger Cloverleaf Belle Plaine Clintonville Winnebago Winneconne Rosendale Woodenshoe White Clay Lawn Rd Lawn Rd Casaloma Maes Kaukauna Central Butte Des Combined City Morts Locks Limits Lake Park Northside Meadows Neevin Tayco Melissa Mears Corners Omro Sunset Point Industrial Bowen St Omro Park Pearl Ave Oshkosh Ellinwood 12th Progress Fitzgerald Waupun Waupun Westside Dodge Koch Oil Aviation Ellington 5 North Fond Du Lac Sadoff Forest Co East Scott St Ledgeview Macy St Hickory St Mercury Marine Ohmstead Cedar Ridge Willow Lawn Rienzi Wind Generation Road Martin Rd South Oakfield Fond Du Lac SW YD Forward Energy Creekview Center Mayville Mountain Outagamie Butternut 1 North Appleton Apple Hills Oconto Fond Du Lac Morgan Auburn Falls Fox River SW YRD Kaukauna North Calumet Cypress SW YD Pound Pioneer (W PS) Crivitz Stiles SW STA Little Suamico Sobieski Forest Ryan St Junction Glenview Iron Foundry Brillion Iron Works Gravesville Suamico Ford Drive Tecumseh Rd New Holstein New Roosevelt Holstein SW STA Oconto Bayport Maplewood SW STA Howard Pulliam SW YD Velp Ave Mason St 7th St Preble Liberty St Finger Rd SW STA Highway V Ontario Ashland Ave Glory Rd Oak St De Pere Red Maple Rockland (W PS) Lost Dauphin Kettle Morraine (ALTE) 2 Washington Lena 8 Greenleaf 10 9 Esker View Brown Wesmark Branch River St Nazianz Howards Grove Elkhart Lake Plymouth Sub 4 Erdman North Gate Northside Plymouth Plymouth Sub 3 (sfm) 32nd St Muncipal (ALTE) 20th St Riverside (ALTE) Mullet River Sheboygan Bemis Falls Energy North Nicolet Edgewater SW YD Center SW YD Mullet River Monroe St South Sheboygan Falls Lyndon Sheboygan Fredonia Holland Ozaukee Bay De Noc Menominee 30th Ave Wells Scott Paper Co St Ogden St West Marinette Peshtigo SW YD Sherwood L a k e M i c higan Dyckesville Kellnersville Manitowoc Luxemburg Rosiere Kewaunee Booster Brusbay East Krok Kewaunee SW YD Apollo Point Beach SW YD Mishicot Columbus St Shoto Mirro Northeast Rapids Revere Dr Manrap Lakefront SW YD Custer Mpu Plant Dewey Sawyer Michigan St SW STA Redwood First Ave Industrial Canal Algoma Algoma City Algoma South Barnett Beardsley St Door Dunn Rd Mason St Bayport SW STA Egg Harbor Howard Sister Bay Green Bay Area Velp Ave Pulliam SW YD Tower Dr Danz James St Ave SW Van Buren St STA Eastman Ave Henry St Brown 7th St (WPS) Liberty St Preble South Broadway Finger Rd Potts Avenue SW STA Highway V! 8 Glory Ashland Ave Road North Bluestone Glory Rd De Pere Oak St De Pere Nicolet Paper Co Mystery Hills Lines of proposed projects on the map are for illustrative purposes only and do not reflect actual routes. For information on project status and routes, see atc projects.com. # YEAR ASSESSMENT 27

28 SOUTHEAST WISCONSIN Zone 5 Transmission system characteristics in Zone 5 ATC delivers power in Zone 5 with various transmission facilities including: the southern portion of 345 kv lines from Point Beach and Edgewater, the Saukville, Arcadian, Granville, Oak Creek, and Racine 345 /138 kv substations, the transmission lines emanating from the Oak Creek power plant, 230 kv facilities near Milwaukee, and a significant 138 kv network in the Milwaukee area, a portion of which is underground. Transmission system limitations in Zone 5 Transmission system performance issues in Zone 5 include heavy market flows to and from the south, resulting in high 345 kv and 138 kv line loadings and the need to monitor potential multiple contingency conditions. ELECTRIC SYSTEM OVERVIEW Increases expected in population, employment Population in Zone 5 is projected to grow 0.5 percent annually between now and 2027, and employment is projected to grow 1.1 percent in the same time period. Waukesha County is projected to realize the largest increase in both population and employment. Waukesha County is also projected to have the highest growth rate in employment while Ozaukee County is projected to have the highest growth rate in population. Electricity usage Peak electric demand typically occurs during the summer months. Large industrial loads in the Milwaukee metropolitan area are among the largest electricity users in the zone. Electric load is forecasted to grow approximately 0.7 percent annually through COUNTIES INCLUDED IN ZONE 5 SOUTHEAST WISCONSIN Kenosha Milwaukee Ozaukee Racine Washington Waukesha 28 AMERICAN TRANSMISSION CO.

29 AMERICAN TRANSMISSION CO YEAR ASSESSMENT YEAR ASSESSMENT 29

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects

More information

ATC Planning Zone 3 Generation Integration Screening Study. December, 2018

ATC Planning Zone 3 Generation Integration Screening Study. December, 2018 Page 1 ATC Planning Zone 3 Generation Integration Screening Study December, 2018 ATC voluntarily performed a high level, steady-state screening of transmission facilities in ATC Planning Zone 3, which

More information

Northern Umbrella Plan Update. December 7, 2007

Northern Umbrella Plan Update. December 7, 2007 Northern Umbrella Plan Update December 7, 2007 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather

More information

Northern Umbrella Plan Update. December 15, 2006

Northern Umbrella Plan Update. December 15, 2006 Northern Umbrella Plan Update December 15, 2006 1 System Prior to NUP Projects 2 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Eastom Tomahawk Grandfather Falls Boulder

More information

Northern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008

Northern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008 Northern Umbrella Plan and U.P. Capital Projects Update 2008 Transmission Business Briefing October 29, 2008 1 Northern Umbrella Plan Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake

More information

American Transmission Company LLC Northern Umbrella Plan (NUP) Projects

American Transmission Company LLC Northern Umbrella Plan (NUP) Projects American Transmission Company LLC Northern Umbrella Plan (NUP) Projects February 21, 2006 Agenda Northern Umbrella Plan Individual Project Discussion Summary System Prior to NUP Projects NUP Projects Wien

More information

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372

More information

Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability

Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability, 1/5/4 Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability American Transmission Company, LLC Stephen D.

More information

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- -- ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20

More information

Northern Umbrella Plan & Projects- Update

Northern Umbrella Plan & Projects- Update Northern Umbrella Plan & Projects- Update November 29, 2007 Jane Petras, ATC General Manager Agenda Overall Northern Umbrella Plan Update Cranberry-Conover-Plains Project: Underground Transmission Line

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

Capital Project Update Northern Umbrella Plan Update

Capital Project Update Northern Umbrella Plan Update Capital Project Update Northern Umbrella Plan Update Jane Petras General Manager - North Portfolio November 7, 2006 1 Overview Northern Umbrella Plan (9) Network Projects (8) Asset Renewal Transmission

More information

Highly Constrained Elements Within ATC Footprint

Highly Constrained Elements Within ATC Footprint Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

Wisconsin Local Employment & Unemployment Estimates Released

Wisconsin Local Employment & Unemployment Estimates Released Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,

More information

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014 MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other

More information

The physical boundaries of Zone 3 and transmission facilities located in Zone 3 are shown in Figure ZS 24.

The physical boundaries of Zone 3 and transmission facilities located in Zone 3 are shown in Figure ZS 24. September 00 0 Year Assessment www.atc0yearplan.com overview includes the Wisconsin counties of: Columbia Crawford (southern portion) Dane Dodge Grant Green Iowa Lafayette Jefferson Richland Rock Sauk

More information

WHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018

WHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018 di, WHEDA Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits Estimated Maximum Family Income Limits at 30% of HUD Estimated 2018 County Median Income Brown 16,290

More information

Wisconsin Housing Statistics

Wisconsin Housing Statistics Wisconsin Housing Statistics Monthly Year-to-Date Dec 2018 Dec 2017 % Change Jan-Dec 2018 Jan-Dec 2017 % Change Unit Sales 4,980 5,728-13.1% 82,760 84,594-2.2% Median Price $179,000 $170,000 +5.3% $184,000

More information

10-Year Transmission System Assessment

10-Year Transmission System Assessment An excerpt from AC s 2009 10-Year ransmission System Assessment Proposals to ensure n Electric system reliability n Access to low-cost sources of power n Access to renewable energy www.atc10yearplan.com

More information

Region NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand.

Region NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand. NC per Hours Hours Mat'l Equip Labor Cost to ADAMS 193.2 95.64 76.0 13 28 14 11 4,318 3,474 844 18.0 0 0 76 1147.0 338.0 $1,676 $440 $340 $2,455 $473,350 0.19 IRON 249.56 163.59 192.0 0 47 16 10 7,308

More information

Summary Report. September The Future Grid. 10-Year Transmission System Assessment.

Summary Report. September The Future Grid. 10-Year Transmission System Assessment. Summary Report September 2012 he Future Grid 10-Year ransmission System Assessment www.atc10yearplan.com Regional and inter-regional planning achieves results ransmission investments solve problems, save

More information

Region NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane.

Region NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane. Notes: 1) Costs shown in table are estimated and do not include the 4.44% Administrative Costs; 2) Material Costs includes,, and other Deicing and icing Agents; 3) Equipment Costs are based on $60 per

More information

AMERICAN TRANSMISSION COMPANY

AMERICAN TRANSMISSION COMPANY AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5

More information

Section IV CHANGES TO THE YEAR ASSESSMENT

Section IV CHANGES TO THE YEAR ASSESSMENT Section IV CHANGES TO THE 2003 10-YEAR ASSESSMENT This section describes the changes made by ATC to certain planned, proposed and provisional transmission projects since the 2003 10-Year Assessment was

More information

Wisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits

Wisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits Housing and Economic Recovery Act (HERA Special) Income and Rent Limits Income Limits * Housing and Economic Recovery Act (HERA Special) Income Limits for 2013 at 30% Family Size: ONE TWO THREE FOUR FIVE

More information

Utility Provider Phone Number Additional Direction and Notes

Utility Provider Phone Number Additional Direction and Notes Adams-Columbia Electric Cooperative (800) 831-8629 Algoma Utility Commission (920) 487-5556 Arcadia Electric & Water Utility (608) 323-3359 Ext. 23 Argyle Municipal Electric & Water Utility (608) 543-3335

More information

VERMONT ELECTRIC POWER COMPANY (VELCO)

VERMONT ELECTRIC POWER COMPANY (VELCO) TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000

Upper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000 California Butte 6 7 R R Glenn 6 21 15 ** 7,800,306 ** Tehama 6 103 3 1,187,932 Restricted R R California Total 6 18 8,988,238 Illinois Boone 17 7 24 2,977,946 Bureau 17 11 R R Carroll 17 15 22 3,851,694

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

Wisconsin FDIC Insured Institutions Profitability First Quarter 2017

Wisconsin FDIC Insured Institutions Profitability First Quarter 2017 Wisconsin FDIC Insured Institutions Profitability First Quarter 2017 Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC Quarterly Data used as the source material.»

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

The Transmission Lay of the Land

The Transmission Lay of the Land The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 Overview Regional Transmission Organizations Organizations of transmission owners, users,

More information

Ventis Group (630) 820-BANK

Ventis Group (630) 820-BANK Copy Right 2010, Bankers Benefits, Inc. Do not reproduce or forward. For update or copies please e-mail. Ventis Group (630) 820-BANK ++ NPA/ ( + ) Evergreen State Bank Stoughton WI 246.5 2.3 7.4 9.6 5,730

More information

Ventis Group (630) 820- BANK

Ventis Group (630) 820- BANK nd Copy Right 2010, Bankers Benefits, Inc. Do not reproduce or forward. For update or copies please e-mail. Ventis Group (630) 820- BANK Bank Quality Report, 6-30-2010 performing Quality + AbbyBank Abbotsford

More information

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909 Amy C. Monopoli Counsel Regulatory & Legislative Phone: 774-452-4227 amonopoli@itctransco.com May 11, 2017 Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway

More information

Wisconsin FDIC Insured Institutions Assets Quality First Quarter 2017

Wisconsin FDIC Insured Institutions Assets Quality First Quarter 2017 Wisconsin FDIC Insured Institutions Quality First 2017 Data compiled by: Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC ly Data used as the source material.»

More information

Copyright 2012, Bankers Benefits, Inc. Do not reproduce or forward. For update or copies please

Copyright 2012, Bankers Benefits, Inc. Do not reproduce or forward. For update or copies please nd Copyright 2012, Bankers Benefits, Inc. Do not reproduce or forward. For update or copies please e-mail info@bankersbenefits.com. (630) 820- BANK Quality performing Asset Total ++ Total (Tier 1 + ) Banks

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report Northeast Wisconsin/Upper Peninsula Separation 11/14/01 Incident Investigation Report Summary Contact by a high voltage electric transmission line with a tree in northeastern Wisconsin initiated a series

More information

Year in Review - Solar

Year in Review - Solar Year in Review - Solar Meet the Class of 2017 Michael Vickerman RENEW Wisconsin January 18, 2018 Year Solar PV Growth in Wisconsin Cumulative capacity Rate of increase 2015 25 MW 25% 2016 42 MW 68% 2017

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Presque Isle 5, 6, 7, 8, & 9: 344 MW Coal Retirement, Effective 10/15/2014 ATTACHMENT Y STUDY REPORT August 15, 2014 EXECUTIVE SUMMARY Pursuant to the Tariff, an Attachment Y Notification

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) August 2011

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) August 2011 and Data 1/ (pool pounds) Idaho Bear Lake 16 7 4 132,258 Caribou 16 29 R R Franklin 16 41 8 2/ 491,364 2/ Idaho Total 16 12 623,622 Illinois Boone 17 7 29 3,407,324 Carroll 17 15 13 1,586,519 De Kalb 17

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Transitways. Chapter 4

Transitways. Chapter 4 4 Transitways Figure 4-1: Hiawatha LRT Train at the Lake Street/Midtown Station The 23 Transportation Policy Plan identifies a network of transitway corridors to be implemented by 23. Transitways recommended

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) March 2009

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) March 2009 and Data 1/ (pool pounds) Idaho Jerome 16 053 R R Minidoka 16 067 R R Idaho Total 16 R 2/ R 2/ Illinois Boone 17 007 31 3,431,362 Carroll 17 015 10 1,222,809 De Kalb 17 037 9 1,698,362 Jo Daviess 17 085

More information

Wisconsin s Electric Cooperatives: Renewable Energy Policies, Programs & Practices. Craig Harmes, Manager, Business Development

Wisconsin s Electric Cooperatives: Renewable Energy Policies, Programs & Practices. Craig Harmes, Manager, Business Development Wisconsin s Electric Cooperatives: Renewable Energy Policies, Programs & Practices Craig Harmes, Manager, Business Development Electric Cooperative Policies, Programs & Practices: 1. Customer Owned Distributed

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Looking Towards the Future: Advantages of 765-kV Transmission Technology Looking Towards the Future: Advantages of 765-kV Transmission Technology In the electric transmission business, design plays a key role in the efficiency and productivity of the nation s energy delivery

More information

Tri-State December 2013 Board Meeting

Tri-State December 2013 Board Meeting 1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)

More information

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs 7.7 Southeast Zone The following table provides a list of transmission needs identified in the Southeast Zone and the map on the following page shows the location of each item in the table. Southeast Zone

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Introducing ITC Midwest

Introducing ITC Midwest Introducing ITC Midwest Great River Energy s Southern Minnesota Member Cooperatives March 17, 2009 Keith Eyler, Account Rep. Who is ITC? ITC Midwest LLC, a subsidiary of ITC Holdings Corp. (NYSE: ITC),

More information

RENEWABLE ENERGY SUMMIT 2019

RENEWABLE ENERGY SUMMIT 2019 RENEWABLE ENERGY SUMMIT 2019 Scaling Up for the Job Ahead 01.17.2019 Monona Terrace and Convention Center Madison, WI SUMMIT Champions Lunch Sponsors SUMMIT Partners Supporting our keynote & panel sessions

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

WI Ignition Interlock Device Service Centers

WI Ignition Interlock Device Service Centers This table lists all current the service centers and mobile installers for Ignition Interlock Devices approved for use in Wisconsin by WI DOT. Contact the Wisconsin State Patrol s Chemical Test Section

More information

U.P. Energy Summit February 16, 2017

U.P. Energy Summit February 16, 2017 U.P. Energy Summit February 16, 2017 Brett French, External Affairs Manager atcllc.com Overview ATC s Value Proposition Reliability Metrics Project updates Q&A atcllc.com 2 Providing Value to our Customers

More information

Chicago Milwaukee Intercity Passenger Rail Corridor

Chicago Milwaukee Intercity Passenger Rail Corridor Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power Salt Lake County Electrical Plan Task Force October 2009 Douglas N. Bennion, P.E. Vice President Rocky Mountain Power 1 Rocky Mountain Power s Bright History In 1881, Salt Lake City became the fifth city

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE Project Overview and Need The Bemidji-Grand Rapids 230-kV transmission line was fully energized in September of 2012 to improve reliability for the Red River

More information

Fire Station Location Study

Fire Station Location Study Fire Rescue Department Fire Station Location Study March 24, 2015 PRESENTATION OUTLINE BACKGROUND SCOPE OF THE STUDY STUDY METHODOLOGY STUDY COMPONENTS SUMMARY QUESTIONS CURRENT SERVICE LEVEL NUMBER OF

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

Wyoming Energy Projects

Wyoming Energy Projects Wyoming Energy Projects Wyoming Infrastructure Authority Spring Conference March 28-29, 2019 PacifiCorp Overview Two divisions Rocky Mountain Power and Pacific Power 5600 Employees 1.9 million electricity

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) April 2008

Upper Midwest Marketing Area -- F.O. 30 State and County Data 1/ (pool pounds) April 2008 and Data 1/ (pool pounds) Idaho Jerome 16 53 R R Idaho Total 16 R 2/ R 2/ Illinois Boone 17 7 31 3,309,422 Carroll 17 15 5 586,480 De Kalb 17 37 9 1,299,938 Jo Daviess 17 85 39 4,323,059 Kane 17 89 10

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER

More information

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations SPP OVERVIEW Mike Ross Senior Vice President, Government Affairs and Public Relations 1 Our Mission Helping our members work together to keep the lights on today and in the future. 2 NORTH AMERICAN INDEPENDENT

More information

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

AMERICAN ELECTRIC POWER (AEP)

AMERICAN ELECTRIC POWER (AEP) AMERICAN ELECTRIC POWER (AEP) Company Background: AEP is one of the largest electric utilities in the United States, delivering electricity to more than five million customers in 11 states. AEP s service

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN-12-1053 OAH DOCKET NO. 60-2500-30782 REBUTTAL TESTIMONY OF RANDALL PORTER, PE SUBMITTED ON BEHALF OF: WIND ON THE

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information