ATC Planning Zone 3 Generation Integration Screening Study. December, 2018
|
|
- Wesley Miles
- 5 years ago
- Views:
Transcription
1 Page 1 ATC Planning Zone 3 Generation Integration Screening Study December, 2018 ATC voluntarily performed a high level, steady-state screening of transmission facilities in ATC Planning Zone 3, which encompasses the southwestern portion of Wisconsin using the 2028 summer peak model from the Year Assessment. This was done to assist generation developers with the preliminary identification of potential locations where existing transmission facilities may be able to accommodate the addition of new and/or additional generation capacity. All potential locations were screened for single contingency 1, steady-state limitations. The study assumes single/nearby combination locations and does not include any generation presently in the MISO queue. Locations that could not accommodate 100 MW of generation for a single contingency were removed from the tables that were produced through this effort. ATC has not performed any analysis to identify the scope or cost of work to eliminate the limit(s) that were identified for any of the contingencies that were noted. ATC may choose to perform similar screening studies of other portions of its footprint in the future, as system conditions and circumstances warrant. Additional steady state, multiple contingency 2 analysis was performed for all 345 kv locations. Multiple contingency analysis was also performed for all 138 kv and 69 kv locations that appeared to be capable of hosting 100 MW or more of generation under steady-state single contingency conditions. Multiple contingency analyses resulted in reduced generation capacity as compared to single contingency screening. ATC has not performed any analysis to identify the scope or cost of work to eliminate the limit(s) that were identified for any of the contingencies that were noted. ATC s initial screening did not include stability analysis. Since different types of generating units have substantially different stability performance characteristics, a stability analysis would not be generally applicable for this type of screening study. Additionally, the stability analysis would result in different and likely less potential capability than what is depicted in this steady-state screening study. Finally, the study analyzed only one potential generation site at a time and, as such, the are not necessarily additive. Tables that follow below identify the location, screening (rounded to the next lowest 10 MW) and the Zone 3 sub-zone where the existing transmission facility is located. Figure 1 depicts six subzones to aid in identification of applicable locations, as follows: Table 1 illustrates the of the analysis for 345 kv sites. Table 2 and 3 provides the of the analysis for 161 and 138 kv sites respectively where the generation capability appeared to be greater than 100 MW under single contingency conditions. The multiple contingency column is listed as - when there was zero generation capability under multiple contingency conditions. This could occur when there are only two outlets at the site. Table 4 provides the of the analysis for 69 kv sites where the generation capability appeared to be greater than 100 MW under single contingency conditions. The multiple contingency column is listed as - when there was zero generation capability under multiple contingency conditions. This could occur when there are only two outlets at the site. This was a high-level screening study using a single steady-state model and a particular set of assumptions, as described herein. The study listed in the tables below may not be indicative of the that 1 refers to NERC Category P1s and No Load Loss Allowed P2s. 2 Multiple contingency refers to NERC Category P2.1 + P1 and P6s (P1 + P1).
2 Page 2 would be produced via the MISO Tariff Attachment X Generation Interconnection process. System stability, both angular and voltage, were not considered in this screening study. ATC makes no representations, either expressed or implied, that the scope of the interconnection facilities or transmission upgrades required to connect generation at these sites would be minimal, or even feasible. screening do not reflect any possible reductions required for multiple contingencies. The analysis considered 69 kv, 138 kv, 161 kv, and 345 kv nodes in the power flow model, but did not consider actual bus configuration or the existence of buses for constructability at the locations that were studied. Corresponding interconnection facilities and transmission upgrades will be determined by the MISO Tariff Attachment X process. For ATC TYA models, generally generation interconnections are only modeled if there is a signed GIA and generation retirements are only modeled if MISO has completed the associated Attachment Y-1 process. This non-binding, voluntary study is presented for informational purposes only and ATC makes no guarantee or warranty that the information presented herein is accurate or complete Steady-State Analysis Power Flow Assumptions Bay Lake projects in service Kittyhawk substation o Interconnection of J390 units Cardinal-Hickory Creek in service o Addition of Hill Valley substation Bain-Spring Valley-North Lake Geneva project in service Several rebuilds/uprates in the surrounding area T-D Projects in service o Northern Lights o Edgerton o Mt. Pleasant o State Line o Juneautown o Schofield Retirement of the following facilities o Nelson Dewey T32 transformer Bus/Line/Transformer reconfigurations o Lincoln o Racine o Arcadian o Williams Bay o Paddock o Columbia 345/138 transformers o Saukville
3 Page kv Site Table 1: Generation Capability at 345 kv Sites ATC Planning Zone 3 Multiple contingency Hill Valley B Cardinal C North Madison C Columbia D Rockdale E Kittyhawk/J F Paddock F
4 Page kv Site Table 2: Generation Capability at 161 kv Sites ATC Planning Zone 3 Multiple contingency Nelson Dewey B
5 Page 5 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone kv Site Multiple contingency Spring Green A Troy A Wyoming Valley A Albany B Bass Creek B Darlington B Edgerton B Eden B Falcon / Quiltblock B Hillman B Lancaster B Nelson Dewey B North Monroe B Potosi B Verona B American C Blount C Cardinal C Cross Country C Christiana C Colloday Point C Fitchburg C Femrite C Huiskamp C Kegonsa C McFarland C North Madison C Northern Lights C Oak Ridge C Pleasant View C Reiner C Sprecher C Sycamore C Vienna C Yahara River C
6 Page 6 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone 3 (continued) 138 kv Site Multiple contingency ACEC Lewiston D Artesian D Birchwood D Columbia D Dell Creek D Hamilton D Kilbourn D Kirkwood D Loch Mirror D Lake Delton Tap D Nishan D Portage D Rock Springs Tap / Rock Springs D Staff D Trienda D Zobel D Academy E Boxelder/Lakehead Waterloo E Butler Ridge Wind E Cambridge Tap/ Cambridge E Crawfish River E Fox Lake E Friesland E Fountain Prairie E Hubbard E Hustisford E Jefferson E London E Lakehead Cambridge Tap E North Beaver Dam / East Beaver Dam E North Randolph E Rockdale E Rubicon E Stony Brook E Tyranena E
7 Page 7 Table 3: Generation Capability at 138 kv Sites ATC Planning Zone 3 (continued) 138 kv Site Multiple contingency Balsam F Brick Church F Blackhawk F Beloit Gateway F BOC Gas Tap F Bristol/Delevan F Colley Road F Dickinson F Elkhorn F Janesville F Lakehead Delevan Tap / Lakehead F Delevan McCue / Kennedy F Marine F North Lake Geneva F Northwest Beloit F Paddock F RC2 Bradford F RC2 LaPrairie F Rock River F Russell F Sunrise F Southwest Delevan F Townline F Tripp F Viking F Venture Tap / Venture F West Darien F Williams Bay F Wilcox F
8 Page 8 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 Multiple contingency 69 kv Site Boscobel Muni / Boscobel A Bris Bois / Hillside A Gran Grae A Muscoda A Muscoda Industrial Park A Spring Green A Stagecoach A Timberlane Tap A Bass Creek B Brodhead Switching Station B Darlington B East Lincoln Street / Mount Horeb B Eden B Harmony Tap/ Harmony B Hillman / Pioneer / Platteville / Pioneer B Tap / McGregor Idle Hour B La Mar B Monroe Central Tap / Monroe Central B North Monroe B North Stoughton / North Stoughton Tap 1 & B Oregon Red Hawk Tap / Red Hawk B B
9 Page 9 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 (continued) Multiple contingency 69 kv Site Rock Branch B Sheepskin B South Monroe B Spring Grove B Stoughton B Stoughton Muni East Tap / Stoughton Muni East B Sun Valley Tap / Sun Valley B Verona B Air Gas Tap / Air Gas C Burke Tap / Burke C Dane C De Forest C Femrite C Fitchburg C Kegonsa C North Madison C Pheasant Branch C Royster C Sun Prairie C Sycamore C Syene C Tokay C Waunakee C Waunakee Centennial Park C Waunakee Easy Street Tap C West Middleton C West Towne C Artesian / Reedsburg D Baraboo D Columbia D
10 Page 10 Table 4: Generation Capability at 69 kv Sites ATC Planning Zone 3 (continued) 69 kv Site Dam Heights North & South Tap / Dam Heights / Prairie du Sac Plant Multiple contingency D Kilbourn D Kirkwood D Lodi Tap D Merrimac Tap / Merrimac D Okee Tap D Portage Industrial Park / Portage D Poynette Tap / Poynette D Wyocena D Hubbard E North Beaver Dam E North Randolph E Rio E South Beaver Dam E Balsam F Brick Church F Colley Road F East Rockton F Enzyme Bio Systems F Katzenberg F McCue F North Lake Geneva F Park Avenue Tap / Park Avenue F RCEC Clinton F Richmond Road F Sharon Tap F Shaw F Tiger F Town Hall Road Tap F Twin Lakes F
11 Page 11
The physical boundaries of Zone 3 and transmission facilities located in Zone 3 are shown in Figure ZS 24.
September 00 0 Year Assessment www.atc0yearplan.com overview includes the Wisconsin counties of: Columbia Crawford (southern portion) Dane Dodge Grant Green Iowa Lafayette Jefferson Richland Rock Sauk
More informationATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition
TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372
More informationSection III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment
Section III STATUS OF PROJECTS This section identifies transmission projects that were completed in 200, are under construction or are in the approval stage. This section also provides a list of projects
More informationATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --
ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20
More informationState Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009
State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under
More informationMTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014
MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other
More informationAppendix B. Summary of Changes to the Year Assessment
Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from
More informationHighly Constrained Elements Within ATC Footprint
Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market
More informationUtility Provider Phone Number Additional Direction and Notes
Adams-Columbia Electric Cooperative (800) 831-8629 Algoma Utility Commission (920) 487-5556 Arcadia Electric & Water Utility (608) 323-3359 Ext. 23 Argyle Municipal Electric & Water Utility (608) 543-3335
More informationSUMMARY REPORT. 10 Year Transmission System Assessment
2018 SUMMARY REPORT 10 Year Transmission System Assessment Agility, flexibility needed to plan for Long term transmission planning has always been a complex undertaking, but it was relatively consistent
More informationYear Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month
Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,
More informationAMERICAN TRANSMISSION COMPANY
AMERICAN TRANSMISSION COMPANY UPDATE 2003 10-YEAR TRANSMISSION SYSTEM ASSESSMENT March 2004 Table of Contents Page No. Executive Summary...1 Section I ATC s Public Planning Process...5 Introduction...5
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationWisconsin Local Employment & Unemployment Estimates Released
Department of Workforce Development Secretary s Office 201 E. Washington Avenue P.O. Box 7946 Madison, WI 53707 Telephone: (608) 266-3131 Fax: (608) 266-1784 Email: sec@dwd.wisconsin.gov Scott Walker,
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationImpacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities
Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432
More informationLocal Transmission Plan. October 11, 2013 Revised August 25, 2014
Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated
More informationConsulting Agreement Study. Completed for Transmission Customer
Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationSERTP rd Quarter Meeting
2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please
More informationGuide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.
Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationInterconnection Feasibility Study Report GIP-157-FEAS-R2
Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia
More informationWisconsin FDIC Insured Institutions Profitability First Quarter 2017
Wisconsin FDIC Insured Institutions Profitability First Quarter 2017 Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC Quarterly Data used as the source material.»
More informationMinnesota Biennial Transmission. Zone Meeting 8
Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More information7.7 Southeast Zone. Transmission Projects Report Section 7: Needs
7.7 Southeast Zone The following table provides a list of transmission needs identified in the Southeast Zone and the map on the following page shows the location of each item in the table. Southeast Zone
More informationInterconnection Feasibility Study Report GIP-IR373-FEAS-R1
Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia
More informationNorth Oregon Coast Area Study. Adam Lint
North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationVERMONT ELECTRIC POWER COMPANY (VELCO)
TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first
More informationSPS Planning Criteria and Study Methodology
SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability
More informationRENEWABLE ENERGY SUMMIT 2019
RENEWABLE ENERGY SUMMIT 2019 Scaling Up for the Job Ahead 01.17.2019 Monona Terrace and Convention Center Madison, WI SUMMIT Champions Lunch Sponsors SUMMIT Partners Supporting our keynote & panel sessions
More informationMadison BRT Transit Corridor Study Proposed BRT Operations Plans
Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationWisconsin FDIC Insured Institutions Assets Quality First Quarter 2017
Wisconsin FDIC Insured Institutions Quality First 2017 Data compiled by: Data compiled by: Tom Kosanda 630.820.2265 Tom@BankersBenefits.com Data distributed by:» FDIC ly Data used as the source material.»
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationSummary Report. September The Future Grid. 10-Year Transmission System Assessment.
Summary Report September 2012 he Future Grid 10-Year ransmission System Assessment www.atc10yearplan.com Regional and inter-regional planning achieves results ransmission investments solve problems, save
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationGenerator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85
Generator Interconnection Impact Study Report Richmond County, NC 1402 MW Queue #85, Inc. Introduction The following impact study results are from the Progress Energy Inc., Carolinas (PEC) internal power-flow
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationSERTP rd Quarter Meeting
2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationWestern Area Power Administration
2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationSub Regional RTEP Committee - Southern
Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies
More informationSTATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY
STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN-12-1053 OAH DOCKET NO. 60-2500-30782 REBUTTAL TESTIMONY OF RANDALL PORTER, PE SUBMITTED ON BEHALF OF: WIND ON THE
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationSoutheastern Regional Transmission Planning (SERTP)
Southeastern Regional Transmission Planning (SERTP) December 2014 Regional Transmission Planning Analyses I. Overview of Regional Analyses SERTP sponsors plan and expand the transmission system to reliably
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationAMERICAN ELECTRIC POWER (AEP)
AMERICAN ELECTRIC POWER (AEP) Company Background: AEP is one of the largest electric utilities in the United States, delivering electricity to more than five million customers in 11 states. AEP s service
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South December 18, 2017 Baseline Reliability and Supplemental Projects Second Review 2 Date Project Last Presented: 10/30/2017 SRRTEP Problem Statement: DOM End of Life Criteria
More informationERCOT Independent Review of Houston Import RPG Project
ERCOT Independent Review of Houston Import RPG Project ERCOT System Planning 2014 Electric Reliability Council of Texas, Inc. ERCOT Regional Planning ERCOT Independent Review of Houston Import Project
More informationMTEP13 SPM #2- Central Region. March 25, 2013
MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for
More informationSystem Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado
System Impact Study T-2007-3 Final.doc System Impact Study Report Request # T-2007-3 900 MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado Executive Summary PSCo Transmission
More informationTri-State December 2013 Board Meeting
1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)
More informationBC Hydro System 2011 Annual Progress Report
March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationThe Long-Range Transmission Plan
The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning
More information2018 Annual Progress Report to WECC Pacific Gas and Electric Company
2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,
More informationATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M
of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and
More informationMarket Efficiency Planning Study
Market Efficiency Planning Study West SPM June 12, 2013 SPM : Market Efficiency Planning Study Update March 25, 2012 Market Efficiency Planning Study Recap Objective is to execute an annual structured
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationTOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY
More information2016 SDG&E Grid Assessment Results
2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationJay Caspary Director Research, Development & Tariff Services
Interconnection Seams Study Update CIGRE GOTF October 23, 2017 Jay Caspary Director Research, Development & Tariff Services jcaspary@spp.org 2 Disclaimer This deck includes materials which were presented
More informationManitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006
Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions
More informationR=Right, L=Left, C=Continue, S=Straight, BL= Bear Left, Super 8, 518 Borg Rd Delavan, WI. BR=Bear Right, SS=Stop sign, T=T intersection, Start 6:00 AM
The Swiss Miss 600k R=Right, L=Left, C=Continue, S=Straight, BL= Bear Left, Super 8, 518 Borg Rd Delavan, WI BR=Bear Right, SS=Stop sign, T=T intersection, Start 6:00 AM us=unsigned Section 1 Section 2
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationNew Jersey State Report
New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of
More informationDUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More information