Project #148. Generation Interconnection System Impact Study Report

Size: px
Start display at page:

Download "Project #148. Generation Interconnection System Impact Study Report"

Transcription

1 Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning

2 Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection Service Results kv Interconnection... 4 Definitions... 6 Energy Resource Interconnection Service... 6 Generator and Interconnection Data... 7 Study Parameters... 8 Senior Queue Generator Assumptions... 8 Steady State Power Flow Analysis Method Results kv Interconnection With Project at its full Output Mitigation Transient Stability Analysis Method Results Mitigation QV Analysis QV Analysis Method Results Mitigation Fault Duty Analysis Method Results Mitigation Conclusions Mitigation Next Steps Attachments

3 Executive Summary NorthWestern Energy ( NWE ) has completed the System Impact Study ( SIS ) Project 148 ( Generation Project ) near Columbus Rapelje, MT. NWE studied the Generation Project as an Energy Resource Interconnection Service ( ERIS ). The SIS is an in-depth analysis that examines the response of the transmission system to a variety of system operating conditions. NWE is responsible for maintaining acceptable system reliability, and must be certain that system reliability is maintained with the addition of the Generation Project. NWE uses tolerance levels outlined by FERC, NERC, and/or WECC. The SIS uses the following types of analyses: Steady-State Power Flow Post Transient Steady-State Power Flow Transient Stability Fault Duty Reactive Margin The results of the SIS demonstrate that with all the senior queue projects and associated mitigation in place, the addition of 80 MW interconnected to NWE 100 kv transmission system near Columbus-Rapelje between Project # 137 Point of Interconnection (POI) and Columbus Auto substation as an Energy Resource will not require additional network upgrades except the interconnection itself. The Generation Project may be required to restrict their output to 52.5 MW under certain operating conditions. For an ERIS application there are two basic questions answered in the study. (1) To identify necessary upgrades to allow full output of the proposed Large Generating Facility and (2) Also identify the maximum allowed output, at the time the study is performed, of the interconnecting Large Generating Facility without requiring additional Network Upgrades. The Customer has waived question 1 of the study for their ERIS application which would identify the necessary network upgrade required to interconnect the Generation Project at its full amount. The Customer has only requested answer to question 2 through this study which would identify the maximum allowed output without requiring additional network upgrades. The findings included in this study do not assure the Interconnection Customer that the planned Generation Project will be allowed to operate at full capacity under all operating conditions. NWE cannot guarantee that future studies (i.e. Operational Studies) will not identify additional problems. Energy Resource Interconnection Service Results ERIS allows the Interconnection Customer to connect the Large Generating Facility to the Transmission System and be eligible to deliver the Large Generating Facility s output using the existing firm or non-firm capacity of the Transmission System on an as available basis. ERIS 3

4 does not in and of itself convey any right to deliver electricity to any specific customer or Point of Delivery. 100 kv Interconnection A new 100 kv substation between Project # 137 Point of Interconnection (POI) and Columbus Auto substation, depicted in Attachment A - One Line Diagram, was assumed as the POI for Customer's Project. With no additional network upgrades and with the senior queue projects and their mitigation in place, the Generation Project showed thermal issues if the output of the Project is above 52.5 MW. The study did not show any fault duty or transient stability issue with the Generation Project at its full output. Hence no network upgrades necessary to address short circuit issues associated with interconnection facilities is required. With the senior queue projects and their mitigation in place the study showed an N-0 overload on the Columbus Rapelje 161/100 kv auto transformer with the Generation Project at its full output. The study also showed some N-1 and N-2 overloads with the Generation Project at its full output. Due to these system constraints the Customer will have to limit their total output at the POI to 52.5 MW without additional network upgrades under certain operating conditions. NWE cannot guarantee that future studies will not further restrict generation output. The Customer will also be required to curtail their output for certain N-1 outages. The outages and overloads caused by Customer's project are shown in the "Steady State Power Flow Analysis" section. A high-level non-binding cost estimate to interconnect the Generation Project at 80 MW to NWE's 100 kv transmission system without additional network upgrades is summarized in Table I. Without any additional network upgrades the Customer will have to restrict their output to 52.5 MW under certain operating conditions. As the Customer is interconnecting to one of the critical transmission lines a shoe-fly will be necessary in order to interconnect the Customer. The shoefly will make sure that the Generation Project can be interconnected while keeping the critical 100 kv line in service. The cost of implementing a shoe-fly to interconnect the Customer is also included in the interconnection costs. Table I ERIS kv Interconnection for 80 MW High Level, Non-Binding, Cost Estimate Substation - Interconnection 3,633,000 Transmission 278,785 Relay 660,000 Communications 282,000 Metering 14,000 EMS 10,073 Total $4,877,858 In addition to the cost in Table I, the Interconnection Customer will be responsible for providing the following communications, or if desired, in this case NWE can provide these services for a monthly fee: 1. Telephone circuit to meter 4

5 2. Data channel to NWE SOCC center 3. Ring down circuit to the generation control center For Customer's information, the mitigation required to allow full output of the Generation Project with senior queue projects and their mitigation in place are listed below (a) Install a new 161/100 kv auto transformer at Columbus Rapelje (approximately $1,600,000). (b) Install 9 MVAR of capacitors at Wilsall to satisfy a minimum reactive margin at the Wilsall substation (approximately $360,000). (c) Install an automatic OMS that will curtail Customer's project for certain N-1 outages (approximately $1,000,000). The costs shown above with the mitigation are very high level. The mitigation shown above is dependent on the senior queue projects, hence a restudy would be required if there are changes to the Generation Interconnection queue. This study assumes that all the mitigation required by the senior queue generation interconnection projects are in place. The study results may change if there are changes to the Generation Project s queue position or the mitigation required by the senior queue projects changes, or if there are any changes to the interconnection specifications provided by the Generation Project to NWE. This study results does not constitute a transmission service request ( TSR ). A TSR study would identify how much transmission capacity is available firm or non-firm on an as available basis. 5

6 Definitions Energy Resource Interconnection Service Energy Resource Interconnection Service shall mean an interconnection service that allows the interconnection customer to connect its generating facility to the transmission provider's transmission system to be eligible to deliver the facility's electric output using the existing firm or non-firm capacity of the transmission provider's transmission system on an as available basis. Energy Resource Interconnection Service in and of itself does not convey transmission service. Under Energy Resource Interconnection Service ( ERIS ), the Generation Project will be able to inject power from the facility into and deliver power across NWE s transmission system on an as available basis up to the amount of MW identified in the applicable stability and steady state studies to the extent the upgrades initially required to qualify for ERIS have been constructed. No transmission delivery service from the Generation Project is assured, but the Generation Project may obtain point-to-point transmission service, network integration transmission service, or be used for secondary network transmission service, pursuant to NWE s Tariff, up to the maximum output identified in the stability and steady state studies. In those instances, in order for the Generation Project to obtain the right to deliver or inject energy beyond the facility point of interconnection or to improve its ability to do so, transmission delivery service must be obtained pursuant to the provisions of NWE's Tariff. The Generation Project's ability to inject its output beyond the point of interconnection, therefore, will depend on the existing capacity of NWE's transmission system at such time as a Transmission Service Request ( TSR ) is made that would accommodate such delivery. The provision of firm point-to-point transmission service or network integration transmission service may require the construction of additional network upgrades. 6

7 Generator and Interconnection Data The proposed generator and interconnection data used in the studies was based on the information received from the Interconnection Customer. From the initial application, NWE identified the following project information. Project Name Project 148 Requested MW Output 80 MW at the Point of Interconnection Location On 100 kv line between Project # 137 POI and Columbus Auto Substation. Special Resources/Technology 50 GE 1.6 MW Wind Turbines Proposed Commercial Operation Date December, 2014 Facilities A new 100 kv 3-breaker ring bus substation between Project # 137 POI and Columbus Auto substation. Assumptions o Scheduled Voltage (pu): 1.01 at the Point of Interconnection The generator is assumed to have operational characteristics either through internal or external capabilities to operate throughout a power factor range of.95 leading to.95 lagging at the Point of Interconnection. During the study process, NWE found that if this requirement was not met, system reliability was compromised. 7

8 Study Parameters In analyzing the Generation Project, NWE utilized PSS/E software to conduct the System Impact Study with the proposed Generation Project. These studies connected the Generation Project to NWE s Transmission System in a computer model to simulate the interaction of the Generation Project with other resources and loads. Two WECC base cases adjusted to include the NWE Transmission System detail representing 2012 light autumn and 2014 heavy summer scenarios were used in this study. Senior Queue Generator Assumptions In addition to existing generators, senior queue resources listed in Table II and the associated mitigation were also considered in this study. Senior queued generation and existing generation dispatch were varied as needed to emulate stress on the system for various scenarios. Table II. Senior Queued Projects Project Number Size (MW) Point of Interconnection Wilsall-Shorey Road 230 kv Line Billings Steam Plant Switchyard Loweth - Two Dot 100 kv line kv line at Chester Rainbow Switchyard Wilsall-Shorey Road 230 kv Line Bradley Creek Substation Bradley Creek - Three Forks S. 100 kv line 61 2 Phillipsburg - Anaconda 25 kv line (total) 69 kv line near Sumatra (9 requests, 5 MW each) kv line approx 5 mi. N of Bradley Creek sub kv line approx 5 mi. N of Bradley Creek sub Near 100 kv Rainbow Switchyard 82 Efficiency Improvement Near 100 kv Rainbow Switchyard Near Livingston City Substation kv line between Loweth and Two Dot at Groveland 100 Efficiency Improvement Near 100 kv Rainbow Switchyard Dutton 69 kv Substation Great Falls 230 kv Switchyard (total) 69 kv line near Sumatra (9 requests, 5 MW each) Two Dot Substation Distribution kv line near Judith Gap South Yellowstone National Park kv line between Harlowton and Broadview kv line West of Geyser kv East of Bole Substation Dry Creek, Montana kv line East of Bole Substation kv line East of Bole Substation 8

9 kV line West of Geyser Mill Creek Substation 100kV Columbus Rapelje Auto Substation Mill Creek Substation 230 kv Switchyard kV line between Harlowton Sub and Broadview Switchyard to 9 miles SSE of Cut Bank, MT kv Interconnection to NWE existing Judith Gap Switchyard kv Interconnection to NWE existing Judith Gap Switchyard kv line between Big Timber City and Livingston City 9

10 Steady State Power Flow Analysis The steady-state power flow analysis examines steady state, system normal, operating conditions with no lines out of service (i.e., N-0 Conditions) and with various lines out of service (i.e., N-1 and N-2 conditions). A power flow simulation is completed before and after the addition of the Generation Project to identify any unacceptable thermal overloads and voltage excursions the project may cause. Method NWE simulated an extensive set of N-1 and N-2 outages. Power flow contingencies were simulated for both operating conditions (2012 light autumn and 2014 heavy summer). The local area contingencies were the primary focus, but major transmission line outages around the NWE system were also studied. Results 100 kv Interconnection With Project at its full Output. N-0: The addition of the Generation Project to NWE s Transmission System under N-0 conditions (all lines in service) causes overloads. The overloads seen in the study are shown in table III below. Table III. N-0 Overloads with the Generation Project at 80 MW Thermal Overloads Base case Outage Element Monitored Element 2012 LA NONE Columbus Rapelje 161/100 kv auto transformer % Loading Before Project % Loading After Project N-1: The addition of the Generation Project to NWE s Transmission System under N-1 conditions (one line out of service) causes thermal overloads. N-2: The addition of the Generation Project to NWE s Transmission System under credible N-2 conditions (two line out of service) causes thermal overloads. Table IV illustrates the N-1 and N-2 thermal overloads caused by the addition of the Generation Project to NWE's 100 kv transmissions system. 10

11 Table IV. N-1 and N-2 Thermal Overloads with Generation Project at 80 MW. Thermal Overloads Base case Outage Element Monitored Element % Loading Before Project % Loading After Project at full output 2012LA Chrome 100/50 kv Auto ** ** 2012LA Columbus Rapelje - Project # 137 POI 100 kv line Chrome 100/50 kv Auto ** ** 2012LA Project #137 POI to Project # 148 POI 100 kv line Chrome 100/50 kv Auto ** ** 2012LA Columbus Auto 100/50 kv Auto ** ** 2012LA Columbus Rapelje - Project # 137 POI 100 kv line Columbus Auto 100/50 kv Auto ** ** 2012LA Project #137 POI to Project # 148 POI 100 kv line Columbus Auto 100/50 kv Auto ** ** Chrome 100/50 kv Auto ** ** Columbus Rapelje - Project # 137 POI 100 kv line Chrome 100/50 kv Auto ** ** Project #137 POI to Project # 148 POI 100 kv line Chrome 100/50 kv Auto ** ** Columbus Auto 100/50 kv Auto ** ** Columbus Rapelje - Project # 137 POI 100 kv line Columbus Auto 100/50 kv Auto ** ** Project #137 POI to Project # 148 POI 100 kv line Columbus Auto 100/50 kv Auto ** ** Columbus Auto - Still Water Smelter 100 kv line Columbus Auto 100/50 kv Auto Chrome Junction - Still Water 50 kv line Columbus Auto - Columbus East - Park City 50 kv Line Big Timber 161/50 kv Auto transformer Alkali Creek - Columbus Rapelje 161 kv line Lower Duck Creek - Clyde Park 161 kv line Lower Duck Creek - Big Timber 161 kv line 39% 111% 42% 114% 28% 119% 46% 105% 52% 102% 45% 106% 56% 101% 57% 102% Wilsall - Three Rivers 230 kv line East Gallatin - Bozeman Westside 161 kv line 97% 104% 2012LA Three Rivers - Wilsall 230 kv line + Three Rivers Clyde Park 161 kv line * Monitored Element is a current limiting air-break switch. East Gallatin - Bozeman Westside 161 kv line* 97% 108% ** The overloads on the Monitored Element is a pre-existing issue for which NWE has a planned mitigation. If the Generation Project comes online before the planned mitigation is in place, the Generation Project will have to implement mitigation to alleviate this issue. Mitigation The Generation Project can interconnect 80 MW without additional network upgrades but can only output 52.5 MW under certain operating conditions due to the system constraints shown above. However, the Generation Project along with senior queued projects may be asked to curtail generation in order to relieve thermal overloads for N-1 and N-2 conditions. 11

12 Transient Stability Analysis When a line fault occurs, the protective relaying must respond by opening circuit breakers to remove the affected transmission line from service. This can result in a system disturbance. The credible worst case fault events must be simulated to determine if the transmission system will recover to acceptable steady state operating conditions. Events that were studied include singlephase and three-phase faults causing either single or multiple line outages or generator failures. The dynamic simulations performed for this project include an assortment of events that are intended to provide a robust test of the impact of the Generation Project. The results from the Transient Stability Analysis are designed to reveal: Whether or not regional electric transmission systems remain stable with each event; Whether or not WECC criteria are met for each outage condition; and Identify where problems are located on the Transmission System. Method NWE simulated an extensive set of 500 kv and non-500 kv faults. The term fault refers to a short-circuit between either a single-phase conductor to ground or all three phases. Due to a senior queued project's Transmission Service Request and the Generation Project's Transmission Service Request, the Colstrip 500 kv upgrade project was included in this analysis. Results All of the events simulated remained stable and met WECC criteria. Mitigation No mitigation is required. 12

13 QV Analysis The SIS examined the reactive margin at critical buses on NWE s Transmission System. In addition, the QV reactive margin identifies potential voltage collapse issues under maximum operating conditions. This analysis includes the addition of the Generation Project. QV Analysis QV analysis is used to determine the reactive power injection required at predefined bus in order to correct the bus voltage to the required value. The curve is obtained through a series of AC load flow calculations. The voltage at a predefined bus can be calculated for a series of power flows as the reactive load is increased in steps. The point where the power flow becomes nonconvergent is the point where voltage collapse occurs. Method QV curves were obtained for the Wilsall 161 kv bus using the QV analysis tools in PSS/E. These curves were obtained before and after the addition of the Generation Project, and include N-1 contingencies used in the "Steady State Power Flow Analysis." The result is a series of QV curves for each bus, which are used to determine the reactive power margin. The Generation Project is modeled at 52.5 MW with all senior queue projects and their mitigation requirements. Results With the Generation Project modeled at 52.5 MW, the amount of reactive power required to maintain a voltage range of 0.90 p.u to 1.05 p.u. at the Wilsall 161 kv bus after the loss of the Shorey Rd to the Project #54 POI 230 kv line is sufficient. The QV curve for the outage mentioned above with Generation MW 80 MW is shown in Attachment B. Mitigation No mitigation is required by the Generation Project to interconnect 80 MW. Network mitigation will be required in order for the Generation Project to output the full amount of the request under certain operating conditions. 13

14 Fault Duty Analysis When a fault occurs on a power line, protective relaying equipment detects the fault current flowing and signals the associated circuit breakers to open. When the circuit breakers open, they must be capable of interrupting the fault current. If the magnitude of the fault current exceeds the interrupt rating of the circuit breakers, the fault may not be cleared, and damage to system equipment and voltage collapse may result. Method To perform a fault duty analysis, busses at or near the POI of the Generation Project are faulted in a PSS/E model to determine the magnitude of fault current anticipated with the Generation Project in service. The results of this analysis determine whether standard circuit breaker fault duty ratings would be exceeded with the addition of the Generation Project. Results The fault current contributed by the Generation Project is negligible and the fault duty at the buses near the POI does not change very much. The breakers in the area are capable of interrupting the fault current. Mitigation No mitigation is required. 14

15 Conclusions The results of the SIS demonstrate that with all the senior queue projects and associated mitigation in place, the addition of 80 MW interconnected to the 100 kv transmission system between Project # 137 POI and Columbus Auto substation as a Energy Resource Network Resource is feasible without additional network mitigation provided the Generation Project will restrict its output to 52.5 MW under certain operating conditions. The SIS study showed that the Customer can interconnect the full 80 MW but will have to restrict their output to 52.5 MW under certain operating conditions without additional network mitigation other than the interconnection. Mitigation No mitigation is required to interconnect full 80 MW provided the Generation Project will restrict its output to 52.5 MW under certain operating conditions. Network upgrades will be required if the Customer would like to output at 80 MW which is the full amount of the interconnection request. A restudy of this SIS will be required if there are changes to the senior queue generation projects. Next Steps NWE will be scheduling a meeting to discuss the findings of the SIS with the Interconnection Customer. If, after the meeting, the Interconnection Customer wishes to continue with the project, the Generation Project must designate either ERIS or NRIS. A Facility Study specific to the project will then be carried out to determine the final details of the interconnection. This study does not constitute a request for transmission service. The study examined the physics of the electrical system and does not imply that you will receive any transmission required to deliver the generation output to load. You must follow the procedures described in the transmission tariff available on ( to request and/or receive transmission service. Attachments Attachment A Project 148 One line Diagram Attachment B QV Curves 15

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2 Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Pennask and Shinnish Creek Wind Project Report No: T&S Planning 2014 072 December 2014 DRAFT British Columbia Hydro and Power Authority British Columbia Hydro and Power

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

EE 456 Design Project

EE 456 Design Project F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study XXXX Kokish River Hydroelectric Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY,

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING GENERATOR INTERCONNECTION REQUEST BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING May 28, 201 Table of Contents 1. Introduction... 6 1.1. Study

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information