Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Size: px
Start display at page:

Download "Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning."

Transcription

1 A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final Prepared by Utility System Efficiencies, Inc.

2 Q95 SYSTEM IMPACT STUDY TABLE OF CONTENTS EXECUTIVE SUMMARY Study Description and Assumptions Post Project Case Modeling Dynamic Data Reliability Criteria... 7 (Steady State) Power Flow Criteria Transient Stability Criteria Study Methodology Power Flow Post-Transient Transient Stability Results and Findings Power Flow and Post-Transient Analysis Flicker Analysis Transient Stability Analysis Short Circuit / Fault Duty Analysis Results & Findings Summary Cost & Construction Time Estimates LIST OF APPENDICES Appendix A Power Flow Diagrams Appendix B List of Contingencies Appendix C Transient Stability Modeling Appendix D Transient Stability Plots Page 1

3 EXECUTIVE SUMMARY This section summarizes the System Impact Study (SIS) results for a proposed generation interconnection of 20 MW in the Arizona Public Service (APS) system. Additional specific details of the proposed interconnection s impact on the surrounding transmission system can be found in the Results and Findings section of this report. Disclaimer Nothing in this report constitutes an offer of transmission service or confers upon the Interconnection Customer ( IC ) any right to receive transmission service. APS and other interconnected utilities may not have the Available Transmission Capacity to support the interconnection described in this report. It should also be noted that all results for the SIS are highly dependent upon the assumed topology and timing of new projects in the vicinity of the interconnection, which are subject to change. Background: Arizona Public Service Company ( APS ) received a valid small generator interconnection request for a proposed interconnection at Vicksburg Substation. The Applicant elected to bypass the Feasibility Study and proceed directly to the System Impact Study ( SIS ) phase of the Small Generator Interconnection Process ( SGIP ). On behalf of, and with the oversight of APS, Utility System Efficiencies, Inc. ( USE ) performed a SIS under the APS Tariff. The interconnection request was assigned queue position #95. The Applicant has proposed to add solar photo-voltaic generation with a maximum net output of 20MW, connecting to the Vicksburg 69kV bus in the fourth quarter of Figure E.1 illustrates this proposed interconnection and the nearby transmission facilities. Figure E-1. Q95 and Nearby Transmission Facilities This SIS used the machine parameters and characteristics provided by the Applicant. Analyses consisted of computer-based power flow analysis, transient stability analysis, post-transient analysis, voltage flicker analysis, and short circuit/fault duty analysis. This study modeled the proposed generation interconnection under 2012 Summer Peak conditions. Select contingencies which stressed the transmission system were simulated. Power flow, transient stability, and post-transient results were monitored for APS, WAPA, and other neighboring systems. Flicker was monitored for the buses in the immediate project area. System performance criteria used in the study: The criteria applied in this study are consistent with NERC/WECC Reliability Criteria. For more detailed information on the criteria used for each analysis see section 1.3 Reliability Criteria. Page 2

4 Results: The results of the study indicate that the there are two reliability violations caused by the addition of the Q95 project. One is an N-0 condition due to low voltages on the 69kV side of the Eagle Eye 230/69 kv transformer. The other is a voltage flicker concern with a 1.88% deviation as the project reduces its output from 100% to 10%. Both reliability violations can be eliminated by re-building the Salome-Vicksburg 69kV line to 795ACSS. Another mitigation option considered was reduction in plant output. Unfortunately the amount of MW reduction required was outside of the 15% reduction allowed at this phase of the process. In addition the transient stability data model provided by the IC has an error which results in high frequencies at the plant buses. This model will need to be revised so the unit does not trip offline for nearby faults on the transmission system. For the time being the over frequency protection has been disabled to move forward with the interconnection. Prior to the start of construction the IC will need to demonstrate that the new model fixes the problems and does not trip offline for nearby faults. Interconnection cost and timeline estimates are listed on the table below: Table 1.1 Summary of Project Interconnection Cost Facility Costs Timeline Network Upgrades $2,186, Months Q95 Trans. Provider's $1,238, Months Interconnection Facilities Grand Total $3,425, Months As can be seen in Table 1.1 above, the total estimated completion time for interconnecting the Q95 project is 36 to 48 months. Therefore, the desired In-Service Date of fourth quarter of 2012 cannot be met. APS and the Interconnection Customer must therefore discuss and mutually agree to a new and acceptable projected In-Service Date. Page 3

5 1 Study Description and Assumptions This section of the report provides details pertaining to the power flow case development and an overview of the major study assumptions. All power flow, transient, voltage flicker, and post-transient study work was completed using General Electric s Positive Sequence Load Flow (GE-PSLF), version 16.3_02. The study utilized two sets of base cases. For the 2012 power flow analysis, voltage flicker, and posttransient analysis the 2012 Heavy Summer APS detailed planning case sm12#18_q95.sav was used. This case has undergone review and updates by all of the Arizona utilities, for Arizona/regional planning purposes. This case does not have a corresponding dynamic data file so an additional base case was used for the transient stability study. The 2013 Heavy Summer APS detailed planning case sm13#10.sav was used. Similar to the 2012 case this case has undergone review and updates by all of the Arizona utilities, for Arizona/regional planning purposes. The load in this case was scaled to the 2012 level and the 2013 transmission projects were removed. There were no higher queued projects modeled in this study. A pre- and post-project base case was developed. The new generation was offset at the Palo Verde Hub (PV). The additional modifications described below were then used to develop the SIS base cases. All Cases: Base case changes 1) Study base case sm12#18.sav was obtained from APS Transmission Planning. General Changes 2) Changed all isolated/islanded busses from Type 0 to Type -4. Arizona Changes 3) The Palo Verde Devers line model was corrected. The conductor ratings were set to MVA normal and MVA emergency. The series capacitor ratings were set to MVA normal and MVA emergency. 4) Emergency ratings ( % of normal) were added to for selected APS 230/69kV transformers. 5) Emergency ratings of 1225MVA were added to the Four Corners 500/345kV transformer. 6) The Cholla-Saguaro 500kV line ratings were set to 1515MVA normal and 2046MVA emergency. 7) Emergency ratings of 717MVA were added to the Pinnacle Peak 500/230kV transformers. 8) The Yavapai-Verde 230kV line ratings were set to 318MVA normal and 374MVA emergency. 9) The Yavapai-Willow Lake 230kV line ratings were set to 306MVA normal and 354MVA emergency. 10) Moenkopi-Yavapai and Yavapai-Westwing 500kV series capacitors set to 25.7 Ohms each. 11) Pinto-Four Corners 345kV series capacitors were added (28.5 Ohms). 12) Emergency ratings of 750MVA were added to the Cholla 500/345kV transformers. 13) The Shiprock 345/230kV transformer was updated to reflect the recent transformer replacement. The new transformer is rated at 600MVA normal and 720MVA emergency. 14) Various shunt capacitors where switched to increase of lower bus voltages. Page 4

6 All Cases: Stability Base case changes 1) Study base case sm12#10_stab.sav was obtained from APS Transmission Planning. General Changes 2) Changed all isolated/islanded busses from Type 0 to Type -4. Arizona Changes 3) The Palo Verde Devers line model was corrected. The conductor ratings were set to MVA normal and MVA emergency. The series capacitor ratings were set to MVA normal and MVA emergency. 4) Emergency ratings ( % of normal) were added to for selected APS 230/69kV transformers. 5) Emergency ratings of 1225MVA were added to the Four Corners 500/345kV transformer. 6) The Cholla-Saguaro 500kV line ratings were set to 1515MVA normal and 2046MVA emergency. 7) Emergency ratings of 717MVA were added to the Pinnacle Peak 500/230kV transformers. 8) The Yavapai-Verde 230kV line ratings were set to 318MVA normal and 374MVA emergency. 9) The Yavapai-Willow Lake 230kV line ratings were set to 306MVA normal and 354MVA emergency. 10) Moenkopi-Yavapai and Yavapai-Westwing 500kV series capacitors set to 25.7 Ohms each. 11) Pinto-Four Corners 345kV series capacitors were added (28.5 Ohms). 12) Emergency ratings of 750MVA were added to the Cholla 500/345kV transformers. 13) The Shiprock 345/230kV transformer was updated to reflect the recent transformer replacement. The new transformer is rated at 600MVA normal and 720MVA emergency. 14) Remove the Youngs Canyon 345/69kV transformer. 15) Remove the Pinal Central connections, planned in-service date of ) Remove the San Manuel Loop-in to the Apache-Hayden 115kV line. 17) Scale the 2013 load and generation to the 2012 levels. 18) Various shunt capacitors were switched to increase or lower bus voltages. 1.1 Post Project Case Modeling Request #95 consists of 46 units each rated at 0.5 MVA. This was represented in the power flow model as a single 20 MW unit operated with a +/ power factor 1 range (+/-6.6MVAR dynamic capability) connected to a kv bus with a scheduled voltage of 1.03 p.u. A single transformer steps the voltage up from 12.47kV to 69 kv. The project was connected to the Vicksburg 69-kV bus by a 1 mile line. The 5 mile line from the Black Peak Eagle Eye 69 kv line to the Vicksburg bus was upgraded. The project model was provided by the applicant. Figure 1-1 represents the Q95 power flow model. The Utting Vicksburg Tap 69 kv line section is normally open, the addition of the project will mean that the Q95 Utting 69 kv line will be normally open. 1 As specified in the Tariff, Q95 will be required to possess the capability of providing +/ Power Factor at the POI when called upon by APS. Page 5

7 Utting 69 kv Vicksburg 69 kv N.O. 69 kv kv 20 MW +/-6.6 MVAR Figure 1-1: Q95 Power Flow Model Power scheduled to Palo Verde Red Hawk generation was reduced to offset the interconnection Power flow diagrams of the transmission system along with the new generation interconnection are provided in Appendix A. Table 1.2 summarizes the case attributes for each scenario. Table Case Attributes Pre- Project with Post- Project with mitigation Major Branch Flows Pre- Project Post- Project Pre- Project (Stability) Post- Project (Stability) mitigation Black Peak-Utting 69kV Vicksburg Tap-Utting 69kV Vicksburg Tap-Vicksburg 69kV Salome-Vicksburg Tap 69kV Eagle Eye-Salome 69kV Black Peak 161/69kV Transformer Eagle Eaye 230/69kV Transformer Parker-Eagle Eye 230kV Eagle Eye-Liberty 230kV Bouse-Black Peak 161kV Parker-Bouse 161kV Bouse-Kofa 69kV Q95-Vicksburg 69kV Arizona Area 14 (incl. WALC) AZ Load 19,909 19,909 20,548 20, AZ Lossess AZ Generation 28,109 28,109 29,269 29, AZ Exports 7,510 7,511 7,906 7, Case Page 6

8 1.2 Dynamic Data Appendix C provides the transient stability model used in this study, and the details of these assumptions. Modeling for the new generation utilized machine characteristics provided by the Applicant. A stability plot of the flat run simulation is also provided in Appendix C. Dynamic Data File 1. Dynamic data file stab_2013.dyd (developed by APS) was obtained from APS Transmission Planning. 2. Representation of Q95 model was added. 1.3 Reliability Criteria In general, an evaluation of the system reliability investigates the system s thermal loading capability, voltage performance (not too high or low), and transient stability (the system should not oscillate excessively and generators should remain synchronized). The evaluation of these criteria must be conducted for credible emergency conditions, such as loss of a single or double circuit line, a transformer, or a generator. Performance of the transmission system and neighboring Control Areas were measured against the Western Electricity Coordinating Council (WECC) Reliability Criteria and the North American Electric Reliability Council (NERC) Planning Standards described in the following subsections. The criteria for Category A (normal, All lines in service ) and Category B (single element outage) conditions were explicitly applied both internally (within APS system) and to external Control Areas. (Steady State) Power Flow Criteria Normal conditions All line loading must be less than 100% of the continuous (normal) thermal ratings. All transformer loading must be less than 100% of the continuous (normal) ratings. Contingency Conditions For a single (N-1) contingency, no transmission element will be loaded above the emergency rating. Established loading limits and voltage performance for other neighboring utilities will be monitored. deviations at any bus must be no more than 5% for N-1 contingencies and no more than 10% for N-2. Page 7

9 1.3.1 Transient Stability Criteria The SIS applies reliability criteria contained within the WECC disturbance-performance table of allowable effects on other systems. Table 1.3 and Figure 1-2 are excerpts from the WECC Reliability Criteria. Table 1.3 WECC Disturbance-Performance Table of Allowable Effects on Other Systems NERC and WECC Categories A System normal B One element out-of-service C Two or more elements out-of-service D Extreme multipleelement outages Outage Frequency Associated with the Performance Category (outage/year) Not Applicable Transient Dip Standard Not to exceed 25% at load buses or 30% at non-load buses. Not to exceed 20% for more than 20 cycles at load buses. Not to exceed 30% at any bus. Not to exceed 20% for more than 40 cycles at load buses. Minimum Transient Frequency Standard Nothing in addition to NERC Not below 59.6Hz for 6 cycles or more at a load bus. Not below 59.0Hz for 6 cycles or more at a load bus. < Nothing in addition to NERC Post Transient Deviation Standard Not to exceed 5% at any bus. Not to exceed 10% at any bus. Figure 1-2. NERC/WECC Performance Parameters Page 8

10 2 Study Methodology This section summarizes the methods used to derive the power flow, post transient, voltage flicker, and transient stability results. 2.1 Power Flow Power flow analysis considers a snapshot in time where the transformer tap changers and SVD s have had time to adjust, the phase shifters have not adjusted, and the system swing bus balances the system during each contingency scenario. All power flow analysis was conducted with version 16.3_02 of General Electric s PSLF/PSDS/SCSC software. Power flow results were monitored and reported for APS and other neighboring systems, including TEP and SRP. Traditional power flow analysis was used to evaluate the thermal and voltage performance of the system under Category A (all elements in service) and Category B (N-1, single contingency) conditions. The applicable WECC reliability planning criteria is listed below. Changes in bus voltages from pre- to post-contingency must be less than 5% for single contingencies. All equipment loadings must be below their normal ratings under normal conditions. All equipment loadings must be below their emergency ratings for single contingencies. Thermal loading was reported when a modeled transmission element was loaded over 98% of its appropriate MVA rating modeled in the power flow database and when the incremental change in loading, between Pre-Project and Post-Project, exceeded 1%. Transmission voltage violations for Category A (no contingency) conditions were reported where per unit voltages were less than 0.95 or greater than For Category B outages the voltage violations were reported when the post-contingency voltage deviation was greater than 5%. 2.2 Post-Transient Post-transient analysis determines if the voltage deviations at critical buses meet the maximum allowable voltage dip criteria and if any transmission elements exceed their maximum rating for selected Category B and Category C disturbances. This snapshot focuses on the first few minutes following an outage where the transformer tap changers have adjusted, the phase shifters and SVD s have not adjusted, and all of the system generation reacts by governor control to balance the system during each contingency scenario. All loads are modeled as constant power during the Post-Transient time frame. All voltages at distribution substations will be restored to their normal values by the transformer tap changers and other voltage control devices. Generator VAR limits will be modeled as a constant single value for each generator since the reactive power capability curve will not be modeled in the power flow program. Alpha min and Gamma min of the PDCI and IPPDC will be adjusted to 5 degrees and 13 degrees, respectively. Shunt capacitors (132 MVAR) at Adelanto and Marketplace will be used if the post-transient voltage deviation exceeds 5% at those buses. 2.3 Transient Stability Transient stability analysis is a time-based simulation that assesses the performance of the power system during (and shortly following) a contingency. Transient stability studies were performed to verify the system stability following a critical fault on the system. Prior to finalization of the power flow and dynamic Page 9

11 data set, a flat run and bump test were run to ensure true power system behavior was not masked by any remote dynamic modeling anomalies. Transient stability analysis was performed based on WECC Disturbance-Performance Criteria for selected system contingencies. Initial transient stability contingencies were simulated out to 11 seconds to ensure a damped system performance. All simulated faults were assumed to be three-phase. The following table identifies the breaker clearing times for faults on different voltage levels. Level Breaker clearing times 69 kv 7-cycles 115/161 kv 6-cycles 230 kv 5-cycles All transient stability simulations were conducted using version 16.3_02 of General Electric s PSLF/PSDS/SCSC software. The Worst Condition Analysis (WCA) tool, available in the PSDS software package, tracks and records the transient stability behavior of all output channels contained within the binary output file of a transient stability simulation. The monitoring of channel output was initiated two cycles after fault clearing, to ensure that all post-fault stability behavior would be captured. System damping was assessed visually with the aid of stability plots. Parameters Monitored to Evaluate System Stability Performance: Rotor Angle Rotor angle plots provide a measure for determining how the proposed generation unit would swing with respect to other generating units in the area. This information is used to determine if a machine would remain in synchronism or go out-of-step from the rest of the system following a disturbance. Bus Bus voltage plots, in conjunction with the relative rotor angle plots, provide a means of detecting out-of-step conditions. The bus voltage plots are useful in assessing the magnitude and duration of post-disturbance voltage dips and peak-to-peak voltage oscillations. Bus voltage plots also five an indication of system damping and the level to which voltages are expected to recover in the steady state conditions. Bus Frequency Bus frequency plots provide information on magnitude and duration of post-fault frequency swings with the new project(s) in service. These plots indicate the extent of possible overfrequency or under-frequency, which can occur due to an area s imbalance between load and generation. Other plotted Parameters Generator Terminal Generator Rotor Speed Page 10

12 3 Results and Findings This section provides the results obtained by applying the previous assumptions and methodology. It illustrates all findings associated with the power flow, post-transient, voltage flicker, and transient stability analysis. 3.1 Power Flow and Post-Transient Analysis The power flow and post-transient analysis focused on high load and generation conditions for summer of The Pre-Project cases were used as a baseline to measure the impact of the new generation and planned transmission upgrades. Contingencies were then applied to the cases. The list of contingencies simulated is provided in Appendix B. Selected power flow plots from the Pre-Project case under pre-contingency and postcontingency system conditions are included in Appendix A. Thermal Results There were no Pre-Project overloads in the base study scenario. The addition of the project did not cause any new overloads. Due to the normally open circuit between Utting and Vicksburg Tap 69kV loss of any section east of Vicksburg up to and including the Eagle Eye 69/230kV transformer cause the new unit to be tripped off. Results When modeling the project, a low voltage was seen at the Eagle Eye 69kV bus. APS maintains a standard that all 69kV buses connected to the transmission system be operated at 1.03 pu or as close as possible. Addition of the project reduces the voltage at the Eagle Eye 69kV bus to 1.02 pu or less. An attempt was made to increase the voltage by using the Salome 69kV capacitors. Addition of the capacitors caused voltages in the area greater than 1.05 pu. Mitigation for the voltage violation is to re-build the Salome-Vicksburg 69kV line section to 795ACSS. There were no contingency voltage violations due to the addition of the project generator. 3.2 Flicker Analysis flicker analysis was performed on the post-project case. Table 3.1 details the results of the voltage flicker analysis. The greatest flicker is observed at the Eagle Eye 69 kv bus with a 1.88% increase with Q95. This occurs as the unit(s) adjusts from 100% to 10% output. Per APS criteria Flicker on the 69kV system is no to exceed 1% for a change in the plant s output. Table 3.1 Flicker Results, Q95 100% Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus Deviation % Deviation % Deviation % Deviation % BLACK PK 69.00kV UTTING 69.00kV VICKSBRG 69.00kV SALOME 69.00kV EAGLEY W 69.00kV EAGLEYE kV Page 11

13 Mitigation for the violation is to re-build the Salome-Vicksburg 69kV line section to 795ACSS. Table 3.2 details the results of the voltage flicker with the line rebuild. Table 3.2 Flicker Results, Q95 w/mitigation 100% Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus Deviation % Deviation % Deviation % Deviation % BLACK PK 69.00kV UTTING 69.00kV VICKSBRG 69.00kV SALOME 69.00kV EAGLEY W 69.00kV EAGLEYE kV Transient Stability Analysis Twelve (12) transient stability outages were simulated in addition to the Flat Run. All of these transient stability simulations met Western Electricity Coordinating Council (WECC) Disturbance Performance Criteria. As referenced in the Reliability Criteria section of this report, the system should meet the following transient stability performance criteria for a NERC/WECC Category B disturbance (N-1): Transient voltage dip should not be below 25% at any load busses or 30% at any non-load busses at anytime. The duration of a transient voltage dip greater than 20% should not exceed 20 cycles at load busses. The minimum transient frequency should not fall below 59.6 Hz for more than 6 cycles at load busses. Appendix D contains transient stability plots of selected contingencies that provide a representative illustration of the transmission system s Pre-Project and Post-Project voltage response. A problem was identified with the original Q95 transient stability data provided by the applicant. The under-voltage trip setting #1 was set to trip the unit offline for a voltage drop below 0.5pu for longer than 0.02 sec (1.2 cycles). Since the clearing time in the 69kV system is 7 cycles, the unit would trip offline for any contingency near the project. APS recommended changing the delay to 8 cycles and the IC approved the change. The stability plots and results are based on the updated setting. The transient stability data model provided by the IC has an error which results in high frequencies at the plant buses. This model will need to be revised so the unit does not trip offline for nearby faults on the transmission system. For the time being the over frequency protection has been disabled to move forward with the interconnection. Prior to the start of construction the IC will need to demonstrate that the new model fixes the problems and does not trip offline for nearby faults. Page 12

14 Table 3.3 summarizes the results of the transient stability simulations where instability was noted. Pre-Project Post-Project Contingency 05_12HS_PRE 06_12HS_PST Black Peak-Utting 69kV No Violations No Violations Utting-Vicksburg 69kV No Violations No Violations Vicksburg Tap-Vicksburg 69kV No Violations No Violations Vicksburg Tap-Salome 69kV No Violations No Violations Salome-Eagle Eye 69kV No Violations No Violations Eagle Eye 69/230kV Transformer No Violations No Violations Black Peak 69/161kV No Violations No Violations Transformer Utting-Q95 69kV NA No Violations Q95-Vicksburg 69kV NA No Violations Utting 69/12kV Load Bank No Violations No Violations Vicksburg 69/12kV Load Bank No Violations No Violations Salome 69/12kV Load Bank No Violations No Violations 3.4 Short Circuit / Fault Duty Analysis Short circuit analysis of the proposed generator was performed by the APS Protection Department, using the CAPE program and parameters supplied by the Applicant. Fault duties were calculated for both single-phase to-ground and three-phase faults at substations busses in the immediate surrounding area before and after the proposed generator installation. The results presented here assume a worst-case scenario. Table 3.4 summarizes the results of the Short-Circuit analysis Station Base Case With Q95 Min. Brkr 3 Ph. (ka) X/R Ph-G (ka) X/R 3 Ph. (ka) X/R Ph-G (ka) X/R Rating -ka Q95 69kV NA NA NA NA As Required Black Peak 69kV Eagle Eye 69kV As can be seen from Table 3.4, the interconnection of the project does not cause the existing substation breakers to exceed their minimum rating. 3.5 Results & Findings Summary The results of the study indicate that there are two reliability violations caused by the addition of the Q95 project. One is an N-0 condition due to low voltages on the 69kV side of the Eagle Eye 230/69 kv transformer. The other is a voltage flicker concern with a 1.88% deviation as the project reduces its output from 100% to 10%. Both reliability violations can be eliminated by re-building the Salome-Vicksburg 69kV line to 795ACSS. Another mitigation option considered was reduction in plant output. Unfortunately the amount of MW reduction required was outside of the 15% reduction allowed at this phase of the process. In addition the transient stability data model provided by the IC has an error which results in high frequencies at the plant buses. This model will need to be revised so the unit does not trip offline for nearby faults on the transmission system. For the time being the over frequency protection has been disabled to move forward with the interconnection. Prior to the start of construction the IC will need to demonstrate that the new model fixes the problems and does not trip offline for nearby faults. Page 13

15 4 Cost & Construction Time Estimates The cost estimates represent good faith estimates necessary to interconnect to the system. The nonbinding, good faith cost and time estimates are tabulated below. Assumptions: Land Values will fluctuate based on specific location. Terrain was not considered when estimating line route. R.O.W. = 40 foot width. N.E.P.A. Process estimated at $3,000 per Mile. Access & Lay Down Yards are not included in the Estimate. Private acquisition could be 18 months if condemnation is required. Rough grading costs are not included in the estimate. APS will construct, own and operate the 69kV facilities in the Q95 substation and the portion of 69 kv line from the Q95 69 kv bus up to the Point of Interconnection. All estimates are in 2010 dollars. Table 4.1 Q95 Project Cost Summary Equipment Description Network Upgrades Transmission Provider's Interconnection Facilities Substation Work $86,000 $668, kv Line Work $2,033,884 $565,334 Communications $38,607 $0 Right of Way $28,400 $4,900 Subtotal $2,186,891 $1,238,234 Grand Total $3,425,125 The facilities identified in Table 4.1 above as Transmission Provider s Interconnection Facilities would be the sole cost of the Interconnection Customer. Unlike Network Upgrades, these costs are not reimbursable. Table 4.2 Q95 Construction Time Estimates Facility Schedule Design Construction Substation Work 6 Months 6 Month 69 kv Line Work 8 Months 10 Months Communications 6 Months Right of Way Months Grand Total Months The summary provided in Table 4.2 above shows a total estimated completion time of 36 to 48 months. Therefore, the desired In-Service Date of fourth quarter of 2012 cannot be met. APS and the Interconnection Customer must therefore discuss and mutually agree to a new and acceptable projected In-Service Date. Page 14

16 Table 4.3 Q95 Network Upgrade Cost Estimates Equipment Description Cost Estimate Engineering and Design $9,600 Below Grade Construction $0 Above Grade Construction $0 Labor (Steel, Bus, & Equipment) Control/Relay Labor $30,000 Equipment/Relay/RTU/Security $46,400 Steel Structures $0 Land $0 Services/Siting/Permit/Etc 69kV Single Circuit $1,918,298 SA - VB 69kV Line Rebuilt $115,586 2 Communications $38,607 69kV Line Right of Way $28,400 Grand Total $2,186,891 Network Upgrades Estimates: are anticipated to consist of the above listed $2,186,891 shown for construction of Q95, Control, Communications, and Relay Protection Requirements. Network Upgrades are typically repaid to the customer per FERC Rules, as transmission credits and/or repaid within a 20 year period. Table 4.4 Q95 Transmission Provider s Interconnection Facilities Cost Estimates Equipment Description Cost Estimate Engineering and Design $78,000 Below Grade Construction $189,600 Above Grade Construction $49,200 Labor (Steel, Bus, & Equipment) Control/Relay Labor $51,600 Equipment/Relay/RTU/Security $285,600 Steel Structures $14,000 Land $0 Services/Siting/Permit/Etc 69kV Single Circuit $565,334 SA - VB 69kV Line Rebuilt $0 Communications $0 69kV Line Right of Way $4,900 Grand Total $1,238,234 2 The $115,586 estimate represents the cost of advancing the planned Salome tap Vicksburg tap 69kV line rebuilt from 2014 to Page 15

17 Figure 4.1 shows a single line diagram of the build-out for Q95 s interconnection facilities Page 16

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Q92 Asarco Interconnection

Q92 Asarco Interconnection A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Q87 Generation Interconnection

Q87 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No. 52365 By Arizona Public Service Company Transmission Planning

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Composite Load Model Sensitivity Study

Composite Load Model Sensitivity Study Composite Load Model Sensitivity Study An Analysis of the Sensitivity of WECC Grid Planning Models to Assumptions Regarding the Composition of Loads NERC LMTF Meeting Salt Lake City, UT January 12, 2016

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

North Gila Generator Interconnection

North Gila Generator Interconnection A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Q51 Generation Interconnection

Q51 Generation Interconnection Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Four Corners 230kV Generator Interconnections Group

Four Corners 230kV Generator Interconnections Group A subsidiary of Pinnacle West Capital Corporation Four Corners kv Generator Interconnections Group Feasibility Study APS Contract Nos. - By Arizona Public Service Company Transmission Planning September,

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Q137 Generation Interconnection

Q137 Generation Interconnection Q137 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52675 By Arizona Public Service Company Transmission Planning July 28, 2014 Q137 FACILITIES STUDY - TECHNICAL REVIEW

More information

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING GENERATOR INTERCONNECTION REQUEST BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING May 28, 201 Table of Contents 1. Introduction... 6 1.1. Study

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Q196 Generation Interconnection

Q196 Generation Interconnection Q196 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52773 By Arizona Public Service Company Transmission Planning April 22, 2015 [Version 1] Q196 FACILITIES STUDY

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Generating Unit Model Validation Policy

Generating Unit Model Validation Policy Generating Unit Model Validation Policy approved by WECC BOT WECC Generator Testing Task Force History August 10, 1996 WSCC Outage 4600 Observed COI Power (Dittmer Control Center) Real event 4400 4200

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information