Q87 Generation Interconnection
|
|
- Lester William Harrington
- 6 years ago
- Views:
Transcription
1 A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No By Arizona Public Service Company Transmission Planning June 6, 2011
2 FACILITIES STUDY Q87 PROPOSED GENERATION TABLE OF CONTENTS 1. Introduction Study Results Power Flow Voltage Flicker Transient Analysis Post-transient Governor Power Flow Analysis Cost Estimates Summary of Cost and Construction Time Estimates Network Upgrades Transmission Provider s Interconnection Facilities System Reinforcements Power Factor Requirements... 8 LIST OF APPENDICES Appendix A Select Power Flow Plots Appendix B Transient Stability Modeling Appendix C Transient Stability Plots Appendix D Construction Schedule Details Appendix E Cotton Center Substation One-Line Diagram Page 2
3 1. Introduction APS performed this Generator Interconnection Facilities Study (FaS) in response to a valid generator interconnection request by the Interconnection Customer (IC). The IC is listed in APS s Active Generator Interconnection Queue as Queue Position 87. The purpose of this study is to provide cost and construction schedule estimates for the facilities needed to interconnect the IC s proposed 20 MW photovoltaic solar generation facility (Q87) located near Gila Bend, Arizona in Maricopa County. The Point of Interconnection (POI) requested for the FaS is the APS Cotton Center 69kV substation. The proposed Commercial Operation Date for Q87 is December 31, 2011 with generator testing beginning October 1, This IC has already completed a System Impact Study (SIS). The Interconnection Customer has chosen to interconnect as an Energy Resource Interconnection Service (Energy Resource). Delivery of the Q87 output beyond the POI would be on an as-available basis only. The delivery of the Q87 output would be subject to the firm or non-firm transmission capacity that may be available when a transmission service request is made. Nothing in this report constitutes an offer of transmission service or confers upon the Interconnection Customer, any right to receive transmission service. APS may not have the Available Transfer Capability (ATC) to support the Transmission Service for the interconnection described in this report. Figure 1 below shows a general depiction of the 69 kv system around Q87 s proposed POI. Figure 1: Project Location and 69kV System Page 3
4 2. Study Results 2.1. Power Flow Power flow analysis was performed on all pre and post-project power flow cases. The results were compared to determine the impacts caused solely by the addition of the Project and to identify the system reinforcements necessary to mitigate the adverse impacts. These Pre-Project and Post-Project cases were evaluated for Category A (N-0 or all lines in service) conditions. Then approximately 60 Category B and 2 Category C contingencies were applied to the cases. Areas 14 (Arizona) and 73 (WAPA R.M.) were monitored. Voltage results focused on buses at 69 kv and above, as well as all Project buses. Select power flow plots are included in Appendix A. Since the System Impact Study (SIS) was completed for Q87, there are three planned changes that affect the flows near the Project's interconnection: 1) Q31 has delayed its In-Service Date from 2011 to 2013, 2) a 12 kv generator will interconnect to the County Line Substation prior to this Project, and 3) two 12 kv generators will interconnect to the Cotton Center Substation prior to this Project. These planned changes have been modeled and were used in the analysis. The results of the 2011, 2013 and 2014 power flow analyses indicate the Project triggered one new overload in the monitored systems of Arizona and WAPA R.M are shown below. The results are shown below. 1 Table 2.1: 2011 N-1 Overloads Emergency Monitored Branch Contingency Description Rating (Amps) GILLESPI-COTN CTR 69 kv % Emergency Rating Pre Post N-1 JOJOBA-KYRENE 500KV N-1 PALOVRDE-RUDD 500KV N-1 BUCKEYE 230/69KV XFMR N-1 SADDLE MTN-BUCKEYE 69kV N-1 SADDLEMT-CNTYLINE 69 kv There is an existing plan to upgrade the Cotton Center-Gillespie 69 kv line in 2013 as a network upgrade assigned to a higher queued project: Q63. Unfortunately, due to permitting issues and construction schedules, the earliest In-Service Date for the Cotton Center-Gillespie 69 kv rebuild is Therefore, Q87 will need to phase their project, and will be limited to an output of 5 MW (98% loading) until the rebuild can be completed in In the event that Q63 drops from APS s Interconnection Queue, Q87 will be responsible for all costs associated with rebuilding the Cotton Center-Gillespie 69 kv line. Voltage N-0 The power flow results showed no Project caused N-0 voltage violations. Voltage N-1 and N-2 The power flow results showed no Project caused N-1 or N-2 voltage violations. 1 Though not Project-related, in 2014 the Palo Verde-Delany 500 kv outage causes the case solution to diverge without the applicable SPS, opening the Hassayampa Tap-Hassayampa Pump 230 kv line and/or tripping nearby generation. Detailed discussion is not part of this report. Page 4
5 2.2. Voltage Flicker The results found no Project caused voltage flicker deviations greater than 1.5%. Table 2.2: 2011 Voltage Flicker 100% Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus Volt (pu) Volt (pu) Deviation (%) Volt (pu) Deviation (%) Volt (pu) Deviation (%) Volt (pu) Deviation (%) Q kV % % % % CNTYLINE 69.00kV % % % % AZTEC 69.00kV % % % % HORN 69.00kV % % % % SADDLEMT 69.00kV % % % % BUNYAN 69.00kV % % % % PALOMA 69.00kV % % % % GILABEND 69.00kV % % % % PVNGPUMP 69.00kV % % % % BUCKEYE 69.00kV % % % % 2.3. Transient Analysis The results of the 2011 transient stability analysis indicate the Project did not trigger any transient stability violations. See Appendix B for the Transient Stability Modeling and Appendix C for select Transient Stability Plots Post-transient Governor Power Flow Analysis The results of the 2011 post-transient governor power flow analysis indicate the Project did not trigger any voltage deviation violations. Page 5
6 3. Cost Estimates 3.1. Summary of Cost and Construction Time Estimates Table 3.1 below provides a summary of which costs are considered Network Upgrades and which are Transmission Provider s Interconnection Facilities. The work involved for each category is described in more detail in sections 3.2 and 3.3 below. Table 3.1: Q87 Project Cost Summary Network Transmission Provider's Upgrades Interconnection Facilities Cotton Center 69kV Ring Bus $1,616,000 $201,000 69kV Line Work (GB-GP In & Out) $307,000 - Communications - $70,000 Land Acquisition $15,000 - Subtotal $1,938,000 $271,000 Grand Total $2,209,000 Total Cost for Q87 (if Q86 is In-Service) $1,240,000 The costs shown above in Table 3.1 show the total cost to expand Cotton Center substation assuming Q86 is interconnected (6-element ring instead of 5-element). The specific costs for Q87 would be half of the Network Upgrades ($969k), plus the Q87 Transmission Provider s Interconnection Facilities ($271k). The Interconnection Customer s desired In-Service Date for the Interconnection Facilities is December 31, The provided construction schedule used an estimated start date of May 1, The actual construction start date would occur when the Interconnection Customer provides written authorization to proceed, provided all interconnection agreements and funding arrangements are in place. Table 3.2 below provides a summary of the construction schedules. Additional schedule details can be found in Appendix D. Table 3.2: Construction Time Estimates Facility Schedule Cotton Center 69kV Ring Bus 9 months Cotton Center 69kV Ring Bus (TPIF) 9 months 69kV Line Work (GB-GP In & Out) 7 months Total 9 months *Substation and line rebuild work can be completed in parallel with each other The summary provided in Table 3.2 above shows a total estimated completion time of 9 months from the actual construction start date. Therefore, the desired In-Service Date of December 31, 2011 cannot be met. APS and the Interconnection Customer must therefore discuss and mutually agree to a new and acceptable projected In-Service Date. Please note that the Commercial Page 6
7 Operation Date must be within the ten (10) year transmission planning period from the date of the valid Interconnection Request Network Upgrades New solar generation at Cotton Center Substation will be coming online this summer. Due to the addition of this generation, the Cotton Center substation will need to be upgraded from a single tap to an in and out (two 69 kv line breakers). The two solar projects are expected to be In-Service by July 15, The Network Upgrades for the Q87 project consist of expanding APS s Cotton Center 69 kv substation from a 5-element ring bus, to a 6-element ring bus. This expansion also involves rebuilding and relocating some overhead 69 kv and 12 kv lines to bring the Gila Bend-Gillespie 69 kv line in and out of the Cotton Center substation. A one-line of the Cotton Center ring bus can be seen in Appendix E (Network Upgrades shown in red). The new ring bus will require expanding the Cotton Center substation approximately one (1) acre to the south. The costs associated with acquiring the land for the substation expansion are included in the estimates. The Network Upgrade costs shown in Table 3.1 above are considered shared costs, which would be shared with Q86 (assuming Q86 is still interconnecting into the Cotton Center Substation). If more projects interconnect into Cotton Center, each project s share of the Network Upgrades would be recalculated. All of these costs are considered Network Upgrades, which are typically repaid to the Interconnection Customer, per FERC rules, as transmission credits over a maximum of twenty (20) years. The assumptions used for all cost estimates are as follows: Rebuilds are assumed that lines will be rebuilt in existing location Access and lay down yards are not included in the estimate Rough grading costs are not included in the estimate 120 x120 minimum space required for control house (drainage may require additional land) APS will construct, own and operate the facilities in the Cotton Center substation and the portion of 69 kv line from the Cotton Center 69 kv bus up to the first structure outside the substation fence The IC will construct, own and maintain the 69 kv generation tie-line from the first structure outside the switchyard fence to the Q87 site The IC will be responsible for providing a fiber optic communications path from the Q87 facility to the Cotton Center substation All estimates are in 2011 dollars 3.3. Transmission Provider s Interconnection Facilities The Transmission Provider s Interconnection Facilities required for the Q87 project include the necessary switches, breakers, bus work, etc needed to bring the Q87 69 kv generation tie-line into the Cotton Center substation. The facilities are shown in blue in Appendix E. The communication costs are also considered TPIF, which includes all necessary equipment as well as any work to terminate the IC s fiber line from the Q87 site to the Cotton Center substation. These costs are the sole responsibility of the Interconnection Customer, and will not be reimbursed. Page 7
8 4. System Reinforcements The Interconnection Customer has chosen to interconnect as an Energy Resource, with delivery of the Q87 output beyond the POI on an as-available transmission basis only, using firm and non-firm transmission capacity that may be available when a transmission service request is made. The Q87 project triggered the rebuild of the Cotton Center-Gillespie 69 kv line in 2011 (during the SIS), which is a Network Upgrade to the APS Transmission System. Due to permitting and schedule limitations, the rebuild cannot be completed until Therefore, Q87 will need to phase their project, and will be limited to an output of 5 MW until the rebuild can be completed in Power Factor Requirements The APS Open Access Transmission Tariff (OATT) policy regarding power factor requires all Interconnection Customers, with the exception of wind generators, to maintain an acceptable power factor (typically near unity) at the Point of Interconnection (POI), subject to system conditions. The APS OATT also requires Interconnection Customers to be able to achieve +/ power factor at the POI, with the maximum "full-output" VAr capability available at all outputs. Furthermore, APS requires Interconnection Customers to have dynamic voltage control and maintain the voltage as specified by the transmission operator within the limitation of +/ power factor, as long as the Project is online and generating. If the Project s equipment is not capable of this type of response, a dynamic reactive device will be required. APS has the right to disconnect the Project if system conditions dictate the need to do so in order to maintain system reliability. Page 8
9 Appendix A Construction Schedule Details Select Power Flow Plots Plot Listing: Page 9
10 Page 10
11 Page 11
12 Page 12
13 Page 13
14 Page 14
15 Appendix B Q87 Transient Stability Modeling Page 15
16 Plant Dynamic Model Data utilizing Emerson PV Inverters Input Parameters: Emerson Inverters Q087 Constant Description From IC rsrc Generator source resistance, pu on plant base 0.00 xsrc Generator source reactance, pu on plant base 0.00 Vratio Ratio of PV array open circuit to peak power voltage 1.25 Iratio Ratio of PV array short circuit to peak power current 1.05 Tdc Inverter DC capacitor bank time constant, sec Itlim Inverter AC thermal current limit, pu on plant base 1.00 Ixlim Inverter AC transient active current limit, pu on plant base 1.45 Iylim Inverter AC transient reactive current limit, pu on plant base 1.00 Kpdc DC voltage regulator proportional gain 7.65 Kidc DC voltage regulator integral gain 0.29 Kpac AC voltage regulator proportional gain 1 Kiac AC voltage regulator integral gain 0.5 QMOD Reactive power mode (0 = constant reactive current, 1 = constant reactive power, 2 = constant power factor, 3 = voltage regulation) TQT Reactive power transducer time constant, sec 0.2 TQR Reactive power regulator time constant, sec 0.4 TSC AC voltage regulator communications delay, sec 1 OV1L Overvoltage trip point #1, pu 1.36 OV1T Overvoltage delay #1, sec OV2L Overvoltage trip point #2, pu 1.20 OV2T Overvoltage delay #2, sec 0.16 OV3L Overvoltage trip point #3, pu 1.10 OV3T Overvoltage delay #3, sec 1.00 UV1L Undervoltage trip point #1, pu 0.50 UVIT Undervoltage delay #l, sec 0.16 UV2L Undervoltage trip point #2, pu 0.88 UV2T Undervoltage delay #2, sec 2.00 OFL Overfrequency trip point, pu 60.5 OFT Overfrequencv delay, sec 1.00 UF1L Underfrequency trip point #1, pu 57.0 UF1T Underfrequency delay #1, sec 0.16 UF2L Underfrequency trip point #2, pu 59.8 UF2T Underfrequency delay #2, sec Page 16
17 Appendix C Q87 Transient Stability Plots Page 17
18 Transient Stability Analysis was run on each of the contingencies listed in the table below. This appendix includes a sampling of the plots that were created, which are highlighted in grey. Plots for the remaining contingencies may be obtained on request. Contingency #77 intentionally trips the Project generation. Contingency # Pre Post!N-0_FLAT_RUN Flat sw has-jjb-slo 3 sw has-ngi-slo 4 sw has-pnw-slo 5 sw jjb-kyr-slo 6 sw kyr-brn-slo 7 sw pvd-rud-slo-ts 8 sw pvd-wwg-1-slo-ts 9 sw pvd-wwg-2-slo-ts 10 sw jjb-gil_1 12 sw jjb-gil-2 13 sw gbd-pan-5c-slo 14 sw rud-pvl_5c_slo 16 sw buk-lib-wsps-5c-slo 17 sw19-rud_500_230_1 19 sw20-rud_500_230_2 20 sw21-rud_500_230_3 21 sw22-rud_500_230_4 22 sw23-gil_500_230_1 23 sw24-kyr_500_230_6 24 sw25-kyr_500_230_7 25 sw27-glb_230_069_1 27 sw28-glb_230_069_2 28 sw30-buk_230_069_1 30 sw31-buk_230_069_2 31 sw32-69-gil-thay-slo 32 sw33-69-thay-why-slo 33 sw34-69-gil-cotn-slo 34a sw34-69-cotn-gillespi-slo 34b sw35-69-gillespi-buck-slo 35 sw36-69-pvngpump-baseline-slo 36 sw37-69-buckeye-watsonw-slo 37 sw39-69-gillwest-pvngpump-slo 39 sw40-69-pvngpump-winter-slo 40 sw41-69-saddlemt-buckeye-slo 41 sw43-69-gil-bun-slo 42 sw44a-69-bunyan-cntyline-slo 43 sw45a-69-cntyline-horn-slo 44 sw46a-69-cntyline-saddlemt-slo 46 sw has-jjb-pnw-dlo 63 sw64-gil-jjb_500_1-2_wsps 64 Gen trip at Detroit-stable sw74-69-aztec-q084-slo 74 sw76-69-cntyline-q085-slo 76 sw77-69-cotn-q086-slo 77 sw78-69-cotn-q087-slo 78 Page 18
19 Page 19
20 Page 20
21 Page 21
22 Page 22
23 Page 23
24 Page 24
25 Page 25
26 Page 26
27 Page 27
28 Page 28
29 Page 29
30 Page 30
31 Page 31
32 Page 32
33 Page 33
34 Page 34
35 Page 35
36 Page 36
37 Page 37
38 Page 38
39 Appendix D Construction Schedule Details Page 39
40 Page 40
41 Appendix E Cotton Center Substation One-Line Diagram Page 41
42 Page 42
Q85 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationQ51 Generation Interconnection
Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.
More informationQ217 Generator Interconnection Project
Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationQ95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.
A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final
More informationQ92 Asarco Interconnection
A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationQ137 Generation Interconnection
Q137 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52675 By Arizona Public Service Company Transmission Planning July 28, 2014 Q137 FACILITIES STUDY - TECHNICAL REVIEW
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationQ196 Generation Interconnection
Q196 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52773 By Arizona Public Service Company Transmission Planning April 22, 2015 [Version 1] Q196 FACILITIES STUDY
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationTOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationFeasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection
Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection
More informationHigh Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007
High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services
More informationConsulting Agreement Study. Completed for Transmission Customer
Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationInterconnection Feasibility Study Report GIP-IR373-FEAS-R1
Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia
More informationSYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company
SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-12-0217 8 MW Hydropower Generating Facility POI on the Dallas Creek to South Canal 115kV Line in SW Colorado FINAL REPORT February
More informationInterconnection Feasibility Study Report GIP-369-FEAS-R1
Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power
More informationPUD ELECTRIC SYSTEM INTERCONNECTION
APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures
More informationAPPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation
APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationInterconnection System Impact Study Final Report February 19, 2018
Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen
More informationENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT
ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationProject #94. Generation Interconnection System Impact Study Report Revision
Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationXXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study
XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost
More informationEl Paso Electric Company
Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationSouthern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management
Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationSYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company
SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report
More informationOCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC
OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC
More informationManitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006
Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationFour Corners Queue Transmission Interconnection Study
Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationSYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company
SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section
More informationGuide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.
Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More informationSPS Planning Criteria and Study Methodology
SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationField Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems
Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,
More informationEssential Reliability Services From PV Plants
Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationLarge General Service Time-of-Use Storage Program
Large General Service Time-of-Use Storage Program AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity and are adjacent
More informationAMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationTransmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202
Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision
More informationInterconnection Feasibility Study Report GIP-157-FEAS-R2
Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia
More informationGENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC
GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC Prepared by: Fred Kimsey Geno Price Roger Hurst Steve
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationMerchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.
Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission
More informationXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS
XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page
More informationLLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST
Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville
More informationInterconnection Feasibility Study Report GIP-046-FEAS-R2
Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationSmall Generator Interconnection Program Interconnection Technical Requirements
General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator
More informationEL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV
EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department
More informationDistributed Energy Resources
Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired
More informationHONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD
SCHEDULED ITEM TO: FROM: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD GEORGE F. MORROW, DIRECTOR OF UTILITIES DATE: JANUARY 28, 2013 SUBJECT: APPROVAL OF POWER SALES AGREEMENT ( PSA ) WITH
More informationJEA Distributed Generation Policy Effective April 1, 2018
Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More informationAPPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
More informationImperial Irrigation District Energy Consumers Advisory Committee Agenda Report
Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report 260 TO: FROM: SUBJECT: ECAC Members Jamie Asbury, deputy energy manager, Business/Regulatory Five (5) Generator Interconnection
More informationReactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018
1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory
More informationQ64. Photovoltaic Solar Generation Project Interconnection. Facilities Study. APS Contract No
A subsidiary of Pinnacle West Capital Corporation Q64 Photovoltaic Solar Generation Project Interconnection Facilities Study APS Contract No. 52215 By Arizona Public Service Company Distribution Planning
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More information