Q217 Generator Interconnection Project

Size: px
Start display at page:

Download "Q217 Generator Interconnection Project"

Transcription

1 Q217 Generator Interconnection System Impact Study APS Contract No By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies, Inc.

2 Q217 SYSTEM IMPACT STUDY TABLE OF CONTENTS EXECUTIVE SUMMARY Study Description and Assumptions Post Case Modeling Dynamic Data Reliability Criteria Power Factor Criteria (Steady State) Power Flow Criteria Transient Stability Criteria Study Methodology Power Factor Requirements Power Flow Post-Transient Transient Stability Results and Findings Reactive Support Power Flow and Post-Transient Analysis Flicker Analysis Transient Stability Analysis Short Circuit / Fault Duty Analysis Results & Findings Summary Cost & Construction Time Estimates Appendix A Power Flow Diagrams Appendix B List of Contingencies Appendix C Transient Stability Data Appendix D Transient Stability Plots LIST OF APPENDICES Page 1

3 EXECUTIVE SUMMARY This section summarizes the System Impact Study (SIS) results for a proposed photovoltaic generation interconnection of 35 MW in the Arizona Public Service (APS) transmission system. Additional specific details of the proposed interconnection s impact on the surrounding transmission system can be found in the Results and Findings section of this report. Disclaimer Nothing in this report constitutes an offer of transmission service or confers upon the Interconnection Customer (IC) any right to receive transmission service. APS and other interconnected utilities may not have the Available Transmission Capacity (ATC) to support the interconnection described in this report. It should also be noted that all results for the SIS are highly dependent upon the assumed topology and timing of new projects in the vicinity of the interconnection, which are subject to change. Background: APS received a valid large generator interconnection request for a proposed interconnection to the Desert Sands 69 kv switchyard. On behalf of, and with the oversight of APS, Utility System Efficiencies, Inc. (USE) performed a SIS under the APS Tariff. The interconnection request was assigned queue position #217. The Applicant has proposed to add solar photo-voltaic generation with a maximum net output of 35 MW, connecting directly to the Desert Sands 69 kv switchyard in the second quarter of A Network & Energy Resource interconnection evaluation was requested. Figure E.1 illustrates this proposed interconnection and the nearby transmission facilities. This SIS used the machine parameters and characteristics provided by the Applicant. Studies consisted of computer-based power flow, post-transient, transient stability, voltage flicker, and short-circuit/fault duty analyses. This study modeled the proposed generation interconnection under anticipated 2014 summer peak conditions. Select contingencies which stressed the transmission system were simulated. Power flow, transient stability, and post-transient results were monitored for APS, WAPA, and other neighboring systems. Flicker was monitored for the buses in the immediate project area. System performance criteria used in the study: The criteria applied in this study are consistent with NERC/WECC Reliability Criteria. For more detailed information on the criteria used for each analysis see section 1.3 Reliability Criteria. The APS Open Access Transmission Tariff (OATT) policy regarding power factor requires all Interconnection Customers, with the exception of wind generators, to maintain an acceptable power factor (typically near unity) at the Point of Interconnection (POI), subject to system conditions. The APS OATT also requires Interconnection Customers to be able to achieve +/ power factor at the POI, with the maximum full-output Var capability available at all outputs. Furthermore, APS requires Interconnection Customers to have dynamic voltage control (operational time of less than 5 seconds) and maintain the voltage as specified by the transmission operator within the limitation of +/ power factor, as long as the is online and generating. If the s equipment is not capable of this type of response, a dynamic reactive device will be required. APS has the right to disconnect the if system conditions dictate the need to do so in order to maintain system reliability. Results: The results of the SIS indicate that the addition of Q217 results in no post-project reliability violations. However, the project as designed is not able to meet the power factor requirements at this time. An additional 5.5 Mvar reactive support is necessary to compensate for losses from the generator terminals to the POI. Page 2

4 Table 1.1 Summary of Interconnection Cost and Lead Times Facility Costs ($000) Timeline (months) Network Upgrades Q217 Trans. Provider s Interconnection Facilities Grand Total The total estimated completion time for interconnecting the Q217 project is months. The long lead time component for this project is getting Right Of Way from the State of Arizona that will be required for the rebuild of up to two miles of an existing APS 69kv line and the routing of the generator interconnection tie line as it gets set to enter the switchyard. Since the requested interconnection date can t be met, APS and the Interconnection Customer must discuss and mutually agree to a new and acceptable projected In-Service Date. The customer requested a Network Resource interconnection and as such an evaluation was made and conclusions are that in the 2014 timeframe, APS would be able to accommodate this project as a Network Resource. However, this evaluation result is only good for the time in which it was performed. APS could sell transmission service over the local facilities at any time which could then result in insufficient transmission to accommodate this project as a Network Resource. Figure E-1. Q217 and Nearby Transmission Facilities Page 3

5 1 Study Description and Assumptions This section of the report provides details pertaining to the power flow case development and an overview of the major study assumptions. All power flow, voltage flicker, transient stability and post-transient study work was completed using General Electric s Positive Sequence Load Flow (GE-PSLF), version 18.0_01. The study used the 2014 Heavy Summer APS detailed planning case sm14#16.sav. This case has undergone review and updates by all of the Arizona utilities for planning purposes. Pre- and post-project base cases were developed. The new generation was offset with the Palo Verde (PV) generation group. Sensitivities were run for the following scenarios. Pre- and Post-project cases were developed for each scenario. 1) Max Yuma Load/Generation pattern 2) 2016 Yuma configuration 3) 2016 Yuma configuration with max Yuma Load/Generation pattern 4) 2016 Yuma configuration with max Yuma Load/Generation pattern and TS8 project 5) 2016 Yuma configuration with max Yuma Load/Generation pattern, TS8 project, and Q43 with max output. 1.1 Post Case Modeling Requestor Q217 was represented in the power flow model as a single 35 MW unit connected to a 0.27 kv bus. A transformer steps the voltage up from 0.27kV to 34.5kV. Another transformer steps the voltage up from 34.5kV to 69kV. The project was connected via a 1.5 mile 69kV line to Desert Sands 69kV switchyard. Figure 1-1 represents the Q217 power flow model. Desert Sands 69 kv 1.5 miles 69 kv R= X= kv R= X= MW +/ MVAR Figure 1-1: Q217 Power Flow Model Power scheduled to Palo Verde Page 4

6 Mesquite generation was reduced to offset the interconnection Power flow diagrams of the transmission system along with the new generation interconnection are provided in Appendix A. Table 1.2 summarizes the case attributes for each scenario. Major Branch Flows Table Case Attributes Pre- Post- Pre- HYL Post- HYL Pre config Post config N.Gila-Gila 69kV Gila-AR FH TP 69kV N.Gila-Mittry 69kV Sanguine-Mittry 69kV Redondo-Sanguine 69kV Foothill Tap-Redondo 69kV Foothill Tap-Foothill 69kV Pacific-N.Gila 69kV Quechan-Pacific 69kV th St-Quechan 69kV Sanguine-SW7 69kV SW7-Ivalon 69kV Araby-AR FH TP 69kV MAB-Araby 69kV S.Oneill-MAB 69kV Waldrip-S.Oneill 69kV Waldrip-Baja 69kV San Luis-Baja 69kV Laguna-San Luis 69kV Yuca W-Laguna 69kV Yuca W-Dupont 69kV Dupont-32nd St 69kV th St-32nd St 69kV Cocopah-32nd St 69kV th St-Cocopah 69kV Riverside-10th St 69kV Riverside-Cocopah 69kV Yucca E-Riverside 69kV Hoodoo Wash-N.Gila 500kV 1,387 1,366 1,054 1,041 1,388 1,367 N.Gila-Imperial Valley 500kV 1,192 1, ,191 1,191 Pilot Knob-Yucca 161kV Gila-Araby TP-W 69kV Araby TP-E-Redondo 69kV Foothills-Araby S 69kV Araby N-Araby TP-W 69kV Araby N-Araby TP-E 69kV Control Area Information AZ Load 19,550 19,550 19,724 19,724 19,550 19,550 AZ Lossess AZ Generation 26,559 26,558 25,934 25,933 26,559 26,558 AZ Exports 6,308 6,308 5,508 5,508 6,308 6,308 Case Page 5

7 Major Branch Flows Pre config/ HYL Post config/ HYL Pre config/ HYL/TS8 Post config/ HYL/TS8 Pre config/ HYL/TS8/Q43 max Post config/ HYL/TS8/Q43 max N.Gila-Gila 69kV Gila-AR FH TP 69kV N.Gila-Mittry 69kV Sanguine-Mittry 69kV Redondo-Sanguine 69kV Foothill Tap-Redondo 69kV Foothill Tap-Foothill 69kV Pacific-N.Gila 69kV Quechan-Pacific 69kV th St-Quechan 69kV Sanguine-SW7 69kV SW7-Ivalon 69kV Araby-AR FH TP 69kV MAB-Araby 69kV S.Oneill-MAB 69kV Waldrip-S.Oneill 69kV Waldrip-Baja 69kV San Luis-Baja 69kV Laguna-San Luis 69kV Yuca W-Laguna 69kV Yuca W-Dupont 69kV Dupont-32nd St 69kV th St-32nd St 69kV Cocopah-32nd St 69kV th St-Cocopah 69kV Riverside-10th St 69kV Riverside-Cocopah 69kV Yucca E-Riverside 69kV Hoodoo Wash-N.Gila 500kV 1,055 1, N.Gila-Imperial Valley 500kV Pilot Knob-Yucca 161kV Gila-Araby TP-W 69kV Araby TP-E-Redondo 69kV Foothills-Araby S 69kV Araby N-Araby TP-W 69kV Araby N-Araby TP-E 69kV Control Area Information AZ Load 19,724 19,724 19,724 19,724 19,749 19,749 AZ Lossess AZ Generation 25,934 25,933 25,932 25,930 26,172 26,171 AZ Exports 5,508 5,508 5,508 5,508 5,718 5,718 Case Page 6

8 1.2 Dynamic Data Appendix C provides the transient stability model used in this study, and the details of these assumptions. Modeling for the new generation utilized machine characteristics provided by the Applicant. Dynamic data file sm14_v2.dyd (developed by APS) was obtained from APS Transmission Planning. A stability plot of the flat run simulation is also provided in Appendix D. 1.3 Reliability Criteria In general, an evaluation of the system reliability investigates the system s thermal loading capability, voltage performance (not too high or low), and transient stability (the system should not oscillate excessively and generators should remain synchronized). The evaluation of these criteria must be conducted for credible emergency conditions, such as loss of a single or double circuit line, a transformer, or a generator. Performance of the transmission system and neighboring Control Areas were measured against the Western Electricity Coordinating Council (WECC) Reliability Standards and the North American Electric Reliability Corporation (NERC) Planning Standards described in the following subsections. The criteria for Category A (TPL-001, All lines in service ), Category B (TPL-002, single element outage), and Category C (TPL-003, multiple element outage) conditions were explicitly applied both internally (within APS system) and to external Control Areas (where appropriate) Power Factor Criteria The study applies APS power factor criteria states that a generator must be capable of providing dynamic reactive support within the range of +/-0.95 power factor at the POI (Steady State) Power Flow Criteria Normal conditions All line loading must be less than 100% of the continuous (normal) thermal ratings. All transformer loading must be less than 100% of the continuous (normal) ratings. Contingency Conditions For any contingency, no transmission element will be loaded above the emergency rating. Depending upon the type of analysis and applied case/sensitivity, applicable criteria for system performance will be identified. In some instances, resulting local circuit overloads and/or voltage deviations may be deemed acceptable per local criteria; as long as the local system s postcontingency performance does not result in cascading outages. Established loading limits and voltage performance for other neighboring utilities will be monitored. deviations at any bus must be no more than 5% for N-1 contingencies and no more than 10% for N Transient Stability Criteria The SIS applies reliability criteria contained within the WECC disturbance-performance table of allowable effects on other systems. Table 1.3 and Figure 1-2 are excerpts from the WECC Reliability Criteria. Page 7

9 Table 1.3 WECC Disturbance-Performance Table of Allowable Effects on Other Systems NERC and WECC Categories A System normal B One element out-of-service C Two or more elements out-of-service D Extreme multipleelement outages Outage Frequency Associated with the Performance Category (outage/year) Not Applicable Transient Dip Standard Not to exceed 25% at load buses or 30% at non-load buses. Not to exceed 20% for more than 20 cycles at load buses. Not to exceed 30% at any bus. Not to exceed 20% for more than 40 cycles at load buses. Minimum Transient Frequency Standard Nothing in addition to NERC Not below 59.6Hz for 6 cycles or more at a load bus. Not below 59.0Hz for 6 cycles or more at a load bus. < Nothing in addition to NERC Post Transient Deviation Standard Not to exceed 5% at any bus. Not to exceed 10% at any bus. Figure 1-2. NERC/WECC Performance Parameters Page 8

10 2 Study Methodology This section summarizes the methods used to derive the power flow, post transient, transient stability and voltage flicker results. Appendix B details the contingencies simulated for the study. 2.1 Power Factor Requirements The APS Open Access Transmission Tariff (OATT) policy regarding power factor requires all Interconnection Customers, with the exception of wind generators, to maintain an acceptable power factor (typically near unity) at the Point of Interconnection (POI), subject to system conditions. The APS OATT also requires Interconnection Customers to be able to achieve +/ power factor at the POI, with the maximum full-output Var capability available at all outputs. Furthermore, APS requires Interconnection Customers to have dynamic voltage control (operational time of less than 5 seconds) and maintain the voltage as specified by the transmission operator within the limitation of +/ power factor, as long as the is online and generating. If the s equipment is not capable of this type of response, a dynamic reactive device will be required. APS has the right to disconnect the from the power grid if system conditions dictate the need to do so in order to maintain system reliability. The method for determining whether or not the generator meets these requirements is to first record the pre-project POI bus voltage. Next, model the generator with zero reactive capabilities at full output. Any shunt devices are turned off. Two synchronous condensers are added to the case with infinite reactive capability. One is at the terminal bus of the unit regulating the bus voltage to 1.0 pu. The other is one bus away from the POI regulating the POI to the pre-project voltage level. The amount of plant losses can be determined by recording the MVAR flow at the POI and adding that to the sum of the synchronous condenser output. Based on the maximum output of the plant, determine the minimum reactive capabilities required to meet the +/-0.95 power factor range. The sum of the two numbers determines the maximum amount of reactive support the project must provide. 2.2 Power Flow Power flow analysis considers a snapshot in time where the transformer tap changers, SVDs and, the phase shifters have not adjusted, and the system swing bus balances the system during each contingency scenario. All power flow analysis was conducted with version 18.0_01 of General Electric s PSLF/PSDS/SCSC software. Power flow results are monitored and reported for APS and other neighboring systems, including WAPA. Traditional power flow analysis is used to evaluate the thermal and voltage performance of the system under Category A (TPL-001, all elements in service) and Category B (TPL-002, N-1, single contingency) conditions. The applicable WECC reliability planning criteria is listed below. Changes in bus voltages from pre- to post-contingency must be less than 5% for single contingencies. All equipment loadings must be below their normal ratings under normal conditions. All equipment loadings must be below their emergency ratings for single contingencies. Depending upon the type of analysis and applied case/sensitivity, applicable criteria for system performance will be identified. In some instances, resulting local circuit overloads and/or voltage deviations may be deemed acceptable per local criteria; as long as the local system s postcontingency performance does not result in cascading outages. Thermal loading is reported when a modeled transmission element is loaded over 98% of its appropriate MVA rating modeled in the power flow database. Page 9

11 Transmission voltage violations for Category A (TPL-001, no contingency) conditions are reported where per unit voltages are less than 0.95 or greater than For Category B outages (TPL-002, N-1) the voltage violations were reported when the post-contingency voltage deviation was greater than 5%. 2.3 Post-Transient Post-transient analysis determines if the voltage deviations at critical buses meet the maximum allowable voltage dip criteria and if any transmission elements exceed their maximum rating for selected Category B (TPL-002, N-1) and Category C (TPL-002, N-2) disturbances. This snapshot focuses on the first few minutes following an outage where the transformer tap changers, the phase shifters, and SVDs have not adjusted, and all of the system generation reacts by governor control to balance the system during each contingency scenario. All loads are modeled as constant power during the Post-Transient time frame. Generator VAR limits will be modeled as a constant single value for each generator since the reactive power capability curve will not be modeled in the power flow program. Alpha min and Gamma min of the PDCI and IPPDC will be adjusted to 5 degrees and 13 degrees, respectively. Shunt capacitors (132 MVAR) at Adelanto and Marketplace will be used if the post-transient voltage deviation exceeds 5% at those buses. 2.4 Transient Stability Transient stability analysis is a time-based simulation that assesses the performance of the power system during (and shortly following) a contingency. Transient stability studies were performed to verify the system stability following a critical fault on the system. Prior to finalization of the power flow and dynamic data set, a flat run is run to ensure true power system behavior is not masked by any remote dynamic modeling anomalies. Transient stability analysis was performed based on WECC Disturbance-Performance Criteria for selected system contingencies. Initial transient stability contingencies are simulated out to 11 seconds to ensure a damped system performance. All simulated faults are assumed to be three-phase. Table 2.1 identifies the breaker clearing times for faults on different voltage levels. Table 2.1 Breaker Clearing Times Level Breaker clearing times 69 kv 7-cycles 115/161 kv 6-cycles 230 kv 5-cycles 500 kv 4-cycles All transient stability simulations were conducted using version 17.0_06 of General Electric s PSLF/PSDS/SCSC software. The Worst Condition Analysis (WCA) tool, available in the PSDS software package, tracks and records the transient stability behavior of all output channels contained within the binary output file of a transient stability simulation. The monitoring of channel output was initiated two cycles after fault clearing, to ensure that all post-fault stability behavior would be captured. System damping was assessed visually with the aid of stability plots. Page 10

12 Parameters Monitored to Evaluate System Stability Performance: Rotor Angle Rotor angle plots provide a measure for determining how the proposed generation unit would swing with respect to other generating units in the area. This information is used to determine if a machine would remain in synchronism or go out-of-step from the rest of the system following a disturbance. Bus Bus voltage plots, in conjunction with the relative rotor angle plots, provide a means of detecting out-of-step conditions. The bus voltage plots are useful in assessing the magnitude and duration of post-disturbance voltage dips and peak-to-peak voltage oscillations. Bus voltage plots also give an indication of system damping and the level to which voltages are expected to recover in the steady state conditions. Bus Frequency Bus frequency plots provide information on magnitude and duration of post-fault frequency swings with the new project(s) in service. These plots indicate the extent of possible overfrequency or under-frequency, which can occur due to an area s imbalance between load and generation. Other plotted Parameters Generator Terminal Generator Rotor Speed 3 Results and Findings This section provides the results obtained by applying the previous assumptions and methodology. It illustrates all findings associated with the power flow, post-transient, transient stability, and voltage flicker. 3.1 Reactive Support The project satisfies the minimum power factor requirement. The project online at 35 MW requires a minimum of +/-11.5 MVAR capability at the POI to meet the +/-0.95 power factor requirement. The calculated plant losses are 6.0 MVAR. The aggregated inverter dynamic capability is +/ MVAR. The resultant capability at the POI is 5.99 MVAR. An additional 5.5 Mvar reactive support is required to meet the APS power factor requirement. A static capacitor bank can be added to compensate for the reactive losses. 3.2 Power Flow and Post-Transient Analysis The power flow and post-transient analysis focuses on high load and generation conditions for summer of The Pre- cases are used as a baseline to measure the impact of the new generation. Contingencies are then applied to the cases. A list of contingencies that were simulated is provided in Appendix B. Power flow plots from the Pre- and Post- cases are included in Appendix A. Thermal Results 2014 Heavy Summer Case Results indicate that there are 2 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Page 11

13 Table 3.1 Thermal Results Monitored Element Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % N-1 Yucca E-Yucca C 69 kv Riverside-Yucca E 69 kv A A A N-1 Gila-Sonora 69 kv San Luis 69/34.5 kv Bank 20 MVA 23.4 MVA MVA Case 1 2 Page 12

14 2014 Heavy Summer Case w/high Yuma Load/Gen Results indicate that there are 8 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Table 3.2 Thermal Results w/high Yuma Generation Monitored Element N-1 Yucca E-Yucca C 69 kv Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % Riverside-Yucca E 69 kv A A A N-1 Foothill-Desert Sands 69 kv Foothill Tap-Redondo 69kV A A A N-1 Waldrip-South O'Neill 69 kv San Luis 69/34.5 kv Bank 20 MVA 20 MVA MVA N-1 North Gila-Gila 69 kv San Luis 69/34.5 kv Bank 20 MVA 21.6 MVA MVA N-1 North Gila 500/69 kv 1 or 2 San Luis 69/34.5 kv Bank 20 MVA 20.1 MVA MVA N-1 Gila-Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.4 MVA MVA N-1 Knob-Pilot Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.6 MVA MVA N-1 Gila-Sonora 69 kv San Luis 69/34.5 kv Bank 20 MVA 29.3 MVA MVA Case Heavy Summer Case w//2016 configuration Results indicate that there is 1 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Table 3.3 Thermal Results w/2016 configuration Monitored Element N-1 Gila-Sonora 69 kv Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % San Luis 69/34.5 kv Bank 20 MVA 23.4 MVA MVA Case 5 6 Page 13

15 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen Results indicate that there are 8 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Table 3.4 Thermal Results w/2016 configuration, High Yuma Generation Monitored Element N-1 North Gila-Gila 69 kv Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % San Luis 69/34.5 kv Bank 20 MVA 20.3 MVA MVA N-1 Gila-Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.1 MVA MVA 99.5 N-1 Knob-Pilot Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.2 MVA MVA N-1 Gila-Sonora 69 kv San Luis 69/34.5 kv Bank 20 MVA 29.3 MVA MVA Case Heavy Summer Case w//2016 configuration, High Yuma Load/Gen, TS8 project Results indicate that there are 8 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Table 3.5 Thermal Results w/2016 configuration, High Yuma Generation, TS8 project Monitored Element N-1 Tenth St-Quechan 69 kv Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 North Gila-Gila 69 kv San Luis 69/34.5 kv Bank 20 MVA 20.8 MVA MVA N-1 Araby Bus Tie San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 North Gila 500/69 kv 1 or 2 San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 Gila-Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.6 MVA MVA N-1 Knob-Pilot Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 21.0 MVA MVA N-1 Pilot Knob-Yucca 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.4 MVA MVA N-1 Gila-Sonora 69 kv San Luis 69/34.5 kv Bank 20 MVA 29.2 MVA MVA Case 9 10 Page 14

16 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen, TS8 project, Q43 full output Results indicate that there are 8 pre-project violations for this scenario. APS is aware of these and has mitigation plans to reduce the flow. The addition of the Q217 project does not exacerbate the violation. Table 3.6 Thermal Results w/2016 configuration, High Yuma Generation, TS8 project, Q43 full output Monitored Element Rating (AMPS/MVA) Pre- Post- Amps/MVA % Amps/MVA % N-1 Tenth St-Quechan 69 kv San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 North Gila-Gila 69 kv San Luis 69/34.5 kv Bank 20 MVA 20.8 MVA MVA N-1 Araby Bus Tie San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 Gila-Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.6 MVA MVA N-1 Knob-Pilot Knob 161 kv San Luis 69/34.5 kv Bank 20 MVA 21.0 MVA MVA N-1 Pilot Knob-Yucca 161 kv San Luis 69/34.5 kv Bank 20 MVA 20.5 MVA MVA N-1 Gila-Sonora 69 kv San Luis 69/34.5 kv Bank 20 MVA 29.2 MVA MVA Case Page 15

17 Results 2014 Heavy Summer Case Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.7 Results Pre- Post- Monitored Element % change % change N-1 Laguna-San Luis 69 kv line BAJA % 7.00% BOSE % 7.90% SANLUIS % 8.20% SANLUS % 8.50% MEX TAP % 7.90% WF_EQLD % 6.40% SANLUIS % 8.20% WF_EQLD % 8.00% SNL-WALC % 8.20% BAJA % 7.20% SANLUS % 8.90% CFE TIE % 8.20% N-1 Yucca-Laguna 69 kv line BOSE % 5.80% SANLUIS % 6.00% SANLUS % 5.40% MEX TAP % 5.80% SANLUIS % 5.20% WF_EQLD % 5.90% SNL-WALC % 6.00% LAGUNA % 7.10% LAGUNA % 7.10% LAGUNA % 6.90% SANLUS % 5.70% CFE TIE % 6.00% N-1 Mex Tap-Bose 34.5 kv line MEX TAP % <5% N-1 Gila-Sonora 69 kv line SONORA % 5.70% SNLWALCX % 5.50% Case 1 2 Page 16

18 2014 Heavy Summer Case w/high Yuma Load/Gen Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.8 Thermal Results w/high Yuma Generation Pre- % Monitored Element change N-1 Laguna-San Luis 69 kv line Post- % change BAJA % 8.60% BOSE % 10.40% SANLUIS % 10.60% SNLWALCX % <5% SANLUS % 10.70% MEX TAP % 10.40% WF_EQLD % 8.40% SANLUIS % 10.00% WF_EQLD % 10.50% SNL-WALC % 10.60% BAJA % 9.10% SANLUS % 10.90% CFE TIE % 10.60% N-1 Yucca-Laguna 69 kv line SONORA % 5.80% BAJA % 12.00% BOSE % 15.10% SANLUIS % 15.30% SNLWALCX % 7.60% SANLUS % 14.80% MEX TAP % 15.10% WF_EQLD % 12.60% SANLUIS % 13.80% WF_EQLD % 15.20% SNL-WALC % 15.30% LAGUNA % 18.20% BAJA % 12.70% LAGUNA % 18.40% LAGUNA % 17.10% SANLUS % 15.00% CFE TIE % 15.30% N-1 Mex Tap-Bose 34.5 kv line SANLUIS % -6.10% MEX TAP % -8.00% WF_EQLD % -6.40% WF_EQLD % -7.00% SNL-WALC % -6.10% CFE TIE % -6.10% N-1 Gila-Sonora 69 kv line SONORA % 9.10% SNLWALCX % 8.50% WF_EQLD % 5.10% Case 3 4 Page 17

19 2014 Heavy Summer Case w//2016 configuration Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.9 Results w/2016 configuration Pre- % Monitored Element change N-1 Laguna-San Luis 69 kv line Post- % change BAJA % 7.00% BOSE % 7.90% SANLUIS % 8.20% SANLUS % 8.60% MEX TAP % 7.90% WF_EQLD % 6.40% SANLUIS % 8.20% WF_EQLD % 8.00% SNL-WALC % 8.20% BAJA % 7.20% SANLUS % 8.90% CFE TIE % 8.20% N-1 Yucca-Laguna 69 kv line BOSE % 5.90% SANLUIS % 6.10% SANLUS % 5.50% MEX TAP % 5.90% SANLUIS % 5.30% WF_EQLD % 6.00% SNL-WALC % 6.10% LAGUNA % 7.20% LAGUNA % 7.20% LAGUNA % 7.00% SANLUS % 5.70% CFE TIE % 6.10% N-1 Mex Tap-Bose 34.5 kv line MEX TAP % <5% N-1 Gila-Sonora 69 kv line SONORA % 5.50% SNLWALCX % 5.30% Case 5 6 Page 18

20 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.10 Volatge Results w/2016 configuration, High Yuma Generation Pre- % Monitored Element change N-1 Laguna-San Luis 69 kv line Post- % change BAJA % 8.50% BOSE % 10.30% SANLUIS % 10.50% SANLUS % 10.60% MEX TAP % 10.30% WF_EQLD % 8.30% SANLUIS % 10.00% WF_EQLD % 10.40% SNL-WALC % 10.50% BAJA % 9.00% SANLUS % 10.80% CFE TIE % 10.50% N-1 Yucca-Laguna 69 kv line SONORA % 5.50% BAJA % 11.80% BOSE % 14.90% SANLUIS % 15.10% SNLWALCX % 7.30% SANLUS % 14.50% MEX TAP % 14.90% WF_EQLD % 12.40% SANLUIS % 13.60% WF_EQLD % 15.00% SNL-WALC % 15.10% LAGUNA % 18.00% BAJA % 12.50% LAGUNA % 18.10% LAGUNA % 16.80% SANLUS % 14.80% CFE TIE % 15.10% N-1 Mex Tap-Bose 34.5 kv line SANLUIS % -6.10% MEX TAP % -8.00% WF_EQLD % -6.40% WF_EQLD % -7.00% SNL-WALC % -6.10% CFE TIE % -6.10% N-1 Gila-Sonora 69 kv line SONORA % 9.10% SNLWALCX % 8.50% WF_EQLD % 5.00% Case 7 8 Page 19

21 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen, TS8 project Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.11 Results w/2016 configuration, High Yuma Generation, TS8 project Pre- % Monitored Element change N-1 Laguna-San Luis 69 kv line Post- % change BAJA % 6.20% BOSE % 7.30% SANLUIS % 7.50% SANLUS % 7.90% MEX TAP % 7.30% WF_EQLD % 5.90% SANLUIS % 7.40% WF_EQLD % 7.40% SNL-WALC % 7.50% BAJA % 6.50% SANLUS % 8.00% CFE TIE % 7.50% N-1 Yucca-Laguna 69 kv line BAJA % 6.90% BOSE % 8.80% SANLUIS % 9.00% SANLUS % 8.60% MEX TAP % 8.80% WF_EQLD % 7.20% SANLUIS % 8.10% WF_EQLD % 8.90% SNL-WALC % 9.00% LAGUNA % 11.20% BAJA % 7.30% LAGUNA % 11.30% LAGUNA % 10.60% SANLUS % 8.80% CFE TIE % 9.00% N-1 Mex Tap-Bose 34.5 kv line SANLUIS % -5.70% MEX TAP % -7.60% WF_EQLD % -6.00% WF_EQLD % -6.60% SNL-WALC % -5.70% CFE TIE % -5.70% N-1 Gila-Sonora 69 kv line SONORA % 8.40% SNLWALCX % 7.90% Case 9 10 Page 20

22 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen, TS8 project, Q43 full output Results indicate that there are both pre-project and post-project voltage violations for multiple contingencies in the Yuma area. This is a known problem to APS planning and mitigation is being assessed. The addition of the Q217 project does not exacerbate the violations. Table 3.12 Results w/2016 configuration, High Yuma Generation, TS8 project, Q43 full output Pre- % Monitored Element change N-1 Laguna-San Luis 69 kv line Post- % change BAJA % 6.20% BOSE % 7.40% SANLUIS % 7.60% SANLUS % 7.90% MEX TAP % 7.40% WF_EQLD % 5.90% SANLUIS % 7.40% WF_EQLD % 7.50% SNL-WALC % 7.60% BAJA % 6.50% SANLUS % 8.10% CFE TIE % 7.60% N-1 Yucca-Laguna 69 kv line BAJA % 7.00% BOSE % 8.90% SANLUIS % 9.10% SANLUS % 8.70% MEX TAP % 8.90% WF_EQLD % 7.20% SANLUIS % 8.20% WF_EQLD % 9.00% SNL-WALC % 9.10% LAGUNA % 11.40% BAJA % 7.40% LAGUNA % 11.40% LAGUNA % 10.70% SANLUS % 8.90% CFE TIE % 9.10% N-1 Mex Tap-Bose 34.5 kv line SANLUIS % -5.70% MEX TAP % -7.60% WF_EQLD % -6.00% WF_EQLD % -6.60% SNL-WALC % -5.70% CFE TIE % -5.70% N-1 Gila-Sonora 69 kv line SONORA % 8.40% SNLWALCX % 7.90% Case Page 21

23 3.3 Flicker Analysis 2014 Heavy Summer Case Results of the voltage flicker analysis indicate that there are no deviations greater than 1.5%. Table 3.13 details the results of the voltage flicker analysis. The greatest flicker is observed at the Foothills 69.0 kv bus with a % decrease with Q217. This occurs as the unit(s) adjusts from 100% to 10% output. Table 3.13 Flicker Results, Q % Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus (pu) (pu) Deviation (pu) Deviation (pu) Deviation (pu) Deviation FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV LAGUNA 69.00kV FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV Page 22

24 2014 Heavy Summer Case w/high Yuma Load/Gen Results of the voltage flicker analysis indicate that there are no deviations greater than 1.5%. Table 3.14 details the results of the voltage flicker analysis. The greatest flicker is observed at the Foothills 69.0 kv bus with a % decrease with Q217. This occurs as the unit(s) adjusts from 100% to 10% output. Table 3.14 Flicker Results, Q % Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus (pu) (pu) Deviation (pu) Deviation (pu) Deviation (pu) Deviation FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV LAGUNA 69.00kV FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV Page 23

25 2014 Heavy Summer Case w//2016 configuration Results of the voltage flicker analysis indicate that there are no deviations greater than 1.5%. Table 3.15 details the results of the voltage flicker analysis. The greatest flicker is observed at the Foothills 69.0 kv bus with a % decrease with Q217. This occurs as the unit(s) adjusts from 100% to 10% output. Table 3.15 Flicker Results, Q % Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus (pu) (pu) Deviation (pu) Deviation (pu) Deviation (pu) Deviation FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV LAGUNA 69.00kV FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV Page 24

26 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen Results of the voltage flicker analysis indicate that there are no deviations greater than 1.5%. Table 3.16 details the results of the voltage flicker analysis. The greatest flicker is observed at the Foothills 69.0 kv bus with a % decrease with Q217. This occurs as the unit(s) adjusts from 100% to 10% output. Table 3.16 Flicker Results, Q % Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus (pu) (pu) Deviation (pu) Deviation (pu) Deviation (pu) Deviation FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV LAGUNA 69.00kV FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV Page 25

27 2014 Heavy Summer Case w//2016 configuration, High Yuma Load/Gen, TS8 project Results of the voltage flicker analysis indicate that there are no deviations greater than 1.5%. Table 3.17 details the results of the voltage flicker analysis. The greatest flicker is observed at the Foothills 69.0 kv bus with a % decrease with Q217. This occurs as the unit(s) adjusts from 100% to 10% output. Table 3.17 Flicker Results, Q % Generation (base) 10% Generation 30% Generation 60% Generation 90% Generation Bus (pu) (pu) Deviation (pu) Deviation (pu) Deviation (pu) Deviation FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV LAGUNA 69.00kV FOOTHILS 69.00kV N.GILA 69.00kV REDONDO 69.00kV MITTRY 69.00kV ARABY S 69.00kV MAB S 69.00kV SANGUINE 69.00kV GILA 69.00kV SONEILL 69.00kV PACIFIC 69.00kV SW kV QUECHAN 69.00kV WALDRIP 69.00kV SANLUIS 69.00kV Page 26

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Q87 Generation Interconnection

Q87 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No. 52365 By Arizona Public Service Company Transmission Planning

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Reliability Must-Run Analysis th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006

Reliability Must-Run Analysis th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006 Reliability Must-Run Analysis 2006 2015 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006 Outline of Presentation 2006 RMR Study Process Description of network and constraint SIL/MLSC

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Q51 Generation Interconnection

Q51 Generation Interconnection Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.

More information

Q92 Asarco Interconnection

Q92 Asarco Interconnection A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

North Gila Generator Interconnection

North Gila Generator Interconnection A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

Composite Load Model Sensitivity Study

Composite Load Model Sensitivity Study Composite Load Model Sensitivity Study An Analysis of the Sensitivity of WECC Grid Planning Models to Assumptions Regarding the Composition of Loads NERC LMTF Meeting Salt Lake City, UT January 12, 2016

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING GENERATOR INTERCONNECTION REQUEST BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING May 28, 201 Table of Contents 1. Introduction... 6 1.1. Study

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

Q196 Generation Interconnection

Q196 Generation Interconnection Q196 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52773 By Arizona Public Service Company Transmission Planning April 22, 2015 [Version 1] Q196 FACILITIES STUDY

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Generating Unit Model Validation Policy

Generating Unit Model Validation Policy Generating Unit Model Validation Policy approved by WECC BOT WECC Generator Testing Task Force History August 10, 1996 WSCC Outage 4600 Observed COI Power (Dittmer Control Center) Real event 4400 4200

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Q137 Generation Interconnection

Q137 Generation Interconnection Q137 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52675 By Arizona Public Service Company Transmission Planning July 28, 2014 Q137 FACILITIES STUDY - TECHNICAL REVIEW

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

ECEN 667 Power System Stability Lecture 19: Load Models

ECEN 667 Power System Stability Lecture 19: Load Models ECEN 667 Power System Stability Lecture 19: Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 7 Homework 6 is

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Dynamic Scheduling NI A F S NI S. Where:

Dynamic Scheduling NI A F S NI S. Where: Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience SPIDER Modeling Sub-Group DER Modeling, CAISO Experience Irina Green, Modeling Sub-Group Chair Regional Transmission Senior Advisor, California ISO NERC SPIDER Work Group Meeting, January 2019 Presentation

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha 1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information