TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis
|
|
- Kristin Bates
- 5 years ago
- Views:
Transcription
1 TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018
2 Table of Contents 1. Introduction Project Description and System Topology Plan of Service Planned Operating Date Study Methods Base Case Development Post Transient Power Analysis Post-Transient Voltage Stability Transient Stability Affected Path Stress Test (10% Test) Path Independence Test Generation Drop via Remedial Action Schemes (RAS) Non-Simultaneous Analysis Results Non-Simultaneous Analysis Commercial Operation Buildout Base Case Development Post-Transient Power Analysis Post-Transient Voltage Stability Transient Stability Analysis Non-Simultaneous Analysis Full Buildout Base Case Development Post-Transient Power Analysis Post-Transient Voltage Stability Transient Stability Analysis Affected Path Stress Test Results Commercial Operation Buildout Full Buildout, SWIP-N Included Sensitivity, Full Buildout, Cross-Tie Project Included Path Independence Test Results Test 1: Schedule a Fixed Amount of Power on Project Test 2: Do Not Schedule Power on Project Sensitivity Studies Non-Simultaneous Analysis Full Buildout, Cross-Tie Project Base Case Development Post-Transient Power Analysis Post-Transient Voltage Stability Transient Stability Analysis Study Findings and Conclusions / Recommendations Appendix A Post-Transient and Transient Stability Contingency Lists Appendix B Post-transient Power Study Results Appendix C Voltage Stability Study Results Appendix D Transient Stability Study Results Appendix E Power Plots Appendix F Transient Stability Plots Appendix I Plan of Service Appendix J Schedule/Milestones Appendix K Project Review Group (PRG) Roster Appendix L Approved Study Plan
3 Executive Summary TransWest Express LLC (TransWest) is developing the TransWest Express Transmission Project (TWE Project), a 3,000 MW, transmission project in the western U.S. The TWE Project recently completed Phase 2 of the WECC Path process as a 730-mile, 1,500 MW Stage 1, 600 kv high voltage direct current (HVDC) system between south central Wyoming and southeastern Nevada. The proposed project is now in Phase 3 of the WECC path rating process and the path rating becomes effective upon implementation of the project. An alternative Plan of Service for the TWE Project that would include AC and DC segments (the TWE AC and DC Project) could potentially better meet the project objectives to provide the needed transmission capacity between the Wyoming wind resource areas in the Rocky Mountain region and the existing transmission systems that serve California, Nevada and Arizona. The TWE AC and DC Project includes a 406-mile, 3,000 MW HVDC system terminating at a bus adjacent to the Intermountain substation and a 324-mile, 1, kv AC system from the adjacent Intermountain substation to a Southern terminal in the Eldorado Valley. As shown in Figure 1, the TWE HVDC portion of the Project will extend from south central Wyoming to the Intermountain 345kV substation in Utah. The AC potion of the Project will extend from a new Intermountain 500 kv substation in Utah to southeastern Nevada. The primary use for the TWE Project is to deliver wind generated electricity from Wyoming to markets in the desert southwest. In addition, the TWE AC and DC Project will provide needed transmission capacity between balancing areas in multiple regions including CAISO, WestConnect and NTTG. Figure 1 TWE HVDC Transmission Project 3
4 This report describes the system studies that have been performed to demonstrate a Proposed for 3,000 MW (north-to-south) on the TWE DC Project and a Proposed of 1,500 MW (north-to-south) on the TWE AC Project. Additional WECC Phase 2 studies will be needed to achieve an Accepted of 3,000 MW and 1,500 MW, respectively. Major Findings The results of the system studies described in this report demonstrate that the TWE AC and DC Project does interact with existing WECC path ratings as identified in Section 4 of this report. Therefore, it is recommended that the TransWest Express Project be accepted into Phase 2A of the WECC Path process with the Plan of Service described in Appendix I. Following are key findings of the Comprehensive Progress Report. Both the TWE AC and DC components of the Project will be new WECC Paths since they are independent of all other paths. Study results were positive and did not yield significant planning criteria violations. The Affected Path Stress Test (10% test) results indicate that there are a number of existing WECC paths that will require simultaneous analysis in the WECC Phase 2 studies. Some of the paths indicate that the TWE AC and DC project have a very strong correlation. Loss of the Aeolus TWE-Wyoming No.1 and No.2 500kV lines results in the underlying 230kV system to yield a line that exceeds its thermal limit. A solution for this double line contingency would be to trip the TWE Wyoming 230kV bus from the Platte Latham 230kV line. This opens the path to mitigate the high flow during this contingency. Further discussions with PRG members will be helpful in assessing if there are any issues in coordinating operation of both the IPPDC and TWE DC lines. Furthermore, scheduling and generation tripping at the Intermountain substation should be further explored to determine trip amounts for various levels of flow scheduled to the Intermountain substation. 4
5 1. Introduction This report describes the results of system studies that have been performed to demonstrate a Proposed of 3,000 MW (north to south) for the TWE AC and DC Project Project Description and System Topology The TWE AC and DC Project includes the elements listed in Section 1.2, Plan of Service. The TWE AC and DC Project will initially be interconnected in 2022 to the existing Wyoming 230 kv transmission facilities and the planned 500 kv Gateway West transmission line. In the future, the TWE Project will be interconnected to the Gateway South transmission line. Both Gateway 500 kv transmission lines are planned to be routed immediately adjacent to the TWE Project s Northern Terminal, which have completed Phase 2 of the WECC Project Review Process and have received Accepted s 1. Because the TWE Project may be in service prior to completion of WECC Projects that are pursuing a WECC Phase 2 status, two levels of Project development, referred to as Buildouts, will be considered in this study plan: 1. TWE Project Commercial Operation Buildout: Represents system conditions when the TWE AC and DC Project is planned to be placed into commercial operation prior to other projects. This scenario will assume that the following transmission projects have been placed into commercial operation: a. TWE AC and DC Project b. Gateway West Segment D.2. c. Eldorado Harry Allen 500 kv line d. Delaney-Colorado River 500 kv line 2. TWE Project with Full Buildout: Represents system conditions for the Full buildout. This scenario will assume that the following transmission projects have been placed into commercial operation: a. TWE AC and DC Project b. Gateway West c. Eldorado Harry Allen 500 kv line d. Delaney-Colorado River 500 kv line e. Gateway South (addition to item 1 above) f. North Gila-Imperial Valley #2 Project (addition to item 1 above) g. Southwest Intertie Project North (SWIP-N) consisting of Midpoint to Robinson Summit, 70% series compensated. (addition to item 1 above) A system map and a one-line diagram showing the TWE AC and DC Project Commercial Operation Buildout are provided in Figures 2 and 3. 1 The Gateway West and Gateway South sponsors originally planned to develop the Gateway Projects as double circuit 500 kv lines in two stages. However, the sponsors have elected to remove Stage 2 of these projects from the Project Review Process. Therefore Accepted s will not be sought for Stage 2 of these projects at this time. 5
6 Generation: The system that was studied included 3,280 MW of wind generation connected to the TWE Project Northern Terminal in Wyoming. This generation was dispatched to achieve a flow of 3,000 MW 2 at the TWE Project Northern AC Terminal and 1,500 MW at the TWE Project Southern Terminal. Figure 2 TWE AC and DC Project System Map 2 This assumes 280 MW of losses on the DC line project. 6
7 Figure 3 TWE AC and DC Project System One Line 7
8 1.2. Plan of Service The TransWest Express AC and DC project consists of the following system additions: 1. TWE Northern DC Terminal a. New substation with 500 kv and 230 kv busses 3 located south of Rawlins, Wyoming. approximately 60 miles west of the planned (PacifiCorp) Aeolus substation b. Connected to the Wyoming grid by looping the following lines in and out. (Because the Northern Terminal s proposed location is immediately adjacent to the proposed Gateway South and Gateway West routes, no additional line length was assumed for these loops. A 230 kv switching station will be added to the Platte-Latham 230 kv line with a two mile line connected to the Northern Terminal.) i. An existing 230 kv line between Platte and Latham substations ii. A planned Gateway West project 500 kv (series compensated) line between Aeolus and Anticline substations once this line has been constructed 4 iii. A planned Gateway South project 500 kv (series compensated) line between Aeolus and Clover substations once this line has been constructed 5 c. Two (2) 500/230 kv transformers with an aggregated capacity of approximately 1,000 MW depending on final configuration and studies 6 d. Thyristor-based HVDC converter rated for 3,225 MW at the converter station e. Number of synchronous condensers rated at +300/-150 MVAr needed for each buildout: Commercial Buildout Full Buildout 3000 MW 230/500kV Northern Terminal 3000 MW, 230/500kV Northern Terminal 7 5 f. Approximately +/-150 MVAr STATCOM on the 230 kv bus g. Approximately 1500 MVAr [ MVAr] shunt capacitors and filter banks on the 230 kv bus 2. TWE HVDC Transmission Line a. 406 miles of ±500 kv, 3000 MW bi-pole, HVDC transmission line consisting of 3 conductors of kcmil Athabaska/TW conductor per pole 3. TWE Southern DC Terminal at Intermountain Substation a. Connected to the Intermountain 345 kv bus via two (2) short transmission lines. b. Thyristor-based HVDC converter rated 3,000 MW at the converter station c. Approximately 2400 MVAr [ MVAr] shunt caps and filter banks on 500 kv bus d. Approximately +/-150 MVAr SVC on the 345 kv bus 5. TWE Northern AC Terminal at Intermountain a. New Intermountain 500kV bus. b. Three (3) 500/345 kv transformers with an aggregated capacity of approximately 1,500 MW 3 The 500 kv bus is part of the Gateway Buildout for the TWE Project. The 500 kv bus will not be constructed until Gateway West and/or Gateway South 500 kv lines are placed in service and interconnected to the TWE Project. 4 The 500/230 kv transformers are part of the Gateway Buildout for the TWE Project. These transformers will not be installed until Gateway West and/or Gateway South 500 kv lines are placed in service and interconnected to the TWE Project. 5 See note 3. 6 See note 3. 8
9 6. TWE AC Transmission Line a. 324 miles of 500 kv, AC transmission line consisting of triple bundle of 1590 kcmil Lapwing/TW conductor per pole b. Seventy percent (70%) series compensated line. Series capacitor bank modeled approximately 162 miles from each end of the line. c. 200 MVAr shunt reactor at series compensation location. 7. TWE Southern AC Terminal a. New 500 kv substation located in Eldorado Valley b. Connected to the Nevada grid by interconnecting with the following lines: i. An existing 500 kv line between Mead and Marketplace substations ii. A new 500 kv line from the TWE Project to McCullough substation iii. A new 500 kv line from the TWE Project to Eldorado substation c. Three (3) 500/500 kv phase-shifting transformers with an aggregated capacity of approximately 1,500 MW. d. Four (4) 80 MVAr shunt capacitors at the new TWE-NV 500kV bus Planned Operating Date The plan of service provides for the facilities to be operational by Study Methods 2.1. Base Case Development The TWE Project Commercial Operation Buildout Base Case was developed starting from the WECC 2022HS1a (8/31/2016) planning base case. The TWE AC and DC Project and connected generation were added to the case. Generation in California, Nevada and Arizona was adjusted to accommodate the resources associated with the TWE AC and DC Project. Generation reductions were 1,000 MW in the SCE area, 1750 MW in the LADWP area (1,500 MW of generation was displaced at the Intermountain substation) and 250 MW in the APS area. The TWE Project Full Buildout Base Case was developed starting from the WECC 2026HS1a (4/11/2016) planning base case. The TWE AC and DC Project and connected generation were added to the case. Generation in California, Nevada and Arizona was adjusted to accommodate the resources associated with the TWE AC and DC Project. Generation reductions were 1,000 MW in the SCE area, 1750 MW in the LADWP area (1,050 MW of generation was displaced at the Intermountain substation) and 250 MW in the APS area. The phase-shift transformers at the TWE Southern Project end were adjusted to yield a flow of 1,500 MW in the north to south direction. The phase-shift transformers can be used to adjust flow to the Intermountain 345kV substation. Base cases were developed in both Siemens PSS/E (version ) and GE PSLF (version 21.0_02). Base cases in both programs are needed since PRG members utilize different in run programs during power flow and transient stability simulations. For example, in the LA Basin, the Centralized Grid Capacitor Control algorithm (cgcc.p) EPCL program is utilized, which can result in different reactive margin values with and without the program. Additional details of how each study base case was developed can be found in the Base Case Development of Section 3 in this report. 9
10 2.2. Post Transient Power Analysis Power flow contingencies are modeled with single element (N-1) outages and credible double element (N-2) outages to evaluate the NERC/WECC category P1 through P7 performance. Transmission elements were monitored for thermal and voltage violations Post-Transient Voltage Stability The WECC requires that new rated paths or facilities be increased to 102.5% and 105% of the maximum achievable transfer capability. For adequate reactive margin, 105% cases are required to converge for Category P1 and P3 7 contingencies, while 102.5% cases are required to converge for Category P6 and P7 contingencies. Studies for this analysis also simulated reactive margin for key buses throughout the system, which provides a measure of system adequacy. In addition, reactive margin was calculated for the LADWP Adelanto 500kV bus. Following a P1 contingency, the Adelanto 500kV bus must have 500 MVAr, and following a P7 contingency, the bus must have 250 MVAr Transient Stability Single element (N-1) and double element (N-2) contingencies identified in the study plan were simulated to evaluate transient stability performance. Also, critical contingencies for each path rating were simulated to evaluate transient stability performance Affected Path Stress Test (10% Test) WECC requires a screening test procedure to identify all paths that are potentially affected by the path under study. For the TWE DC contingency and TWE AC contingency, the established WECC paths with a flow increase of 10% or more were identified. The percent increase is based on the affected paths rating Path Independence Test WECC requires two (2) screening tests to be used to determine whether a path is independent of another path. Results of the tests are provided in this report to aid in determining if the TWE AC and DC proposed Project is part of the same path or a subset of an existing Path Generation Drop via Remedial Action Schemes (RAS) For loss of the TransWest Express Project, new Wyoming wind generation and/or gas generation connected to the TWE northern terminal was tripped. 100% of this generation was tripped for a TWE bi-pole contingency and approximately 40% of this generation was tripped for a TWE monopole contingency. 7 The ISO Grid Planning Standards ( April12015_v2.pdf) requires performance for P3 contingency (G-1/N-1) to meet the former Category B performance. 10
11 3. Non-Simultaneous Analysis Results The Non-Simultaneous results were simulated for single and double contingencies listed in Table 3a and 3b of the study plan. A discussion of key outages follows. Loss of the TWE DC Mono-pole (w/ras) Each TWE DC monopole has a continuous overload capacity of 1725 MW (utilizes 15% overload capability of converters) delivered to the southern DC terminal. Therefore, only 1,275 MW of new Wyoming wind generation connected to the TWE northern terminal is tripped for loss of the TWE DC mono-pole. Loss of the TWE DC Bi-pole (w/ras) The following mitigation is needed for loss of the TWE DC Bi-pole: 1. All new Wyoming wind generation at the TWE northern terminal was tripped. 2. The Intermountain (IPPDC) DC flow is ramped back quickly to ensure that there are no issues on the Intermountain Mona No.1 and No.2 345kV lines. 3. Shunt capacitors will need to be switched off-line to alleviate high voltage. Loss of the TWE Intermountain TWE Nevada 500kV line (w/ras) The TWE Project injects 1,500 MW of new Wyoming generation into the TWE 500kV line that interconnects to the AC southern terminal. Loss of this line removes the path to transfer the generation. As a result, the TWE DC flow needs to be reduced by the amount scheduled on the TWE AC line. This reduction in DC flow will require generation tripping at the northern TWE DC terminal. Loss of the Intermountain IPPDC Mono-pole or Bi-pole line (w/ras) With loss of the Intermountain IPPDC mono or bi-pole line, the TWE DC flow would be reduced by the amount that was initially flowing on the IPPDC line(s) prior to tripping. An arming RAS may be needed to determine ramp back and generation tripping amounts prior to an incident. Coordination between the IPPDC and TWE DC systems will be needed. An IPPDC bi-pole outage would require a quicker response. Depending on the amount of Wyoming generation that is needed to be tripped, the TWE DC mono-pole could be tripped (instead of ramping back) for higher flow levels that are scheduled to the Intermountain substation. Loss of the Intermountain Mona No.1 and No.2 345kV lines Post-transient power flow identifies that the IPPDC line may not need to be tripped. Presently, for loss of the Intermountain Mona No.1 and No.2 345kV lines, the Intermountain Gonder 230kV line is tripped, which also results in the IPPDC lines being tripped. For this analysis, the Intermountain Gonder 230 kv line was not tripped, which results in the Intermountain system staying intact. 11
12 3.1. Non-Simultaneous Analysis Commercial Operation Buildout A non-simultaneous Commercial Operation buildout base case was developed in order to evaluate WECC system reliability. Note, the pre-project base case was evaluated by simulating all power flow contingencies. The developed post-project base case has a TransWest Express flow of 3,000 MW on the DC portion of the Project and 1,500 MW on the AC portion Base Case Development The Non-Simultaneous base case modeled a TWE DC flow of 3,000 MW in the north to south direction and a TWE AC flow of 1,500 MW in the north to south direction. When turning the Intermountain Unit 2 generator and station service load off (displaced with TWE power), the reactive power from Unit 2 was approximately 175 MVAr. As a result, one (1) 175 MVAr shunt capacitor was modeled at the Intermountain 345 kv bus. The following Projects are included in the Commercial Operation buildout base case. Table 1 TWE Project Commercial Operation Buildout New Transmission Facilities No. Project Description 1 TWE DC and AC Project 2 Gateway West Segment D.2 3 Eldorado Harry Allen 500 kv line 4 Colorado River-Delaney 500 kv line The TransWest Express DC path is defined as the sum of flow on the following lines: TWE-INT* TWE-WY 500 kv DC No.1 and No.2 Lines The TransWest Express AC path is defined as the sum of flow on the following lines: TWE-NV* McCullough 500 kv TWE-NV* Marketplace 500 kv TWE-NV* Eldorado 500 kv TWE-NV* Mead 500 kv Note, the asterisk indicates the metering location Post-Transient Power Analysis Power flow results identified that no elements exceeded 100% of their emergency thermal limit. One (1) post-transient voltage violation was identified with inclusion of TWE AC and DC Project. Loss of the TWE DC Bi-Pole (w/ras) (P7) The outage results in voltage levels below 0.9 per unit at the Peterson 230kV buses. Two (2) 6 MVAr shunt capacitors were switched in-service to mitigate voltage levels below 0.9 per unit in the Dillon/Big Grassy 161kV area. However, this did not result in Peterson 230kV bus voltage levels above 0.9 per unit. This contingency may require additional shunt capacitors in this area with quick insertion. Eldorado Lugo 500 kv and Eldorado Mohave 500 kv Lines (P6) The outage modeled as a P7 (N-2) contingency results in a Lugo Victorville 500 kv line (WECC Path 61) flow of 99.6% of its emergency rating. This is an increase of 17% 12
13 compared to the pre-project case. However, this is actually a P6 (N-1-1) contingency, which allows the system to be adjusted after either of the line outages. Overloading of this element has been observed in other WECC path rating studies. The CAISO Transmission Plan identifies upgrades to this line targeted for 12/2018 that will increase the emergency rating by approximately 50%. Completion of these upgrades will eliminate the P7 overload identified in this study. Currently, CAISO is managing this situation by re-dispatching generation following the first outage of the P6 contingency. Prior to the completion of the upgrades, TWE will participate in the current re-dispatch procedure by reducing its schedule to Eldorado substation as required to mitigate the incremental impacts caused by TWE. However, with the TWE project planned for 2022 in-service date, the Lugo-Victorville 500 kv line upgrade is scheduled to be completed prior to TWE project at this time Post-Transient Voltage Stability Cases were created with TWE path flows increased to 105% of the maximum achievable TWE AC (1575 MW) and DC (3150 MW) transfer capability. All contingencies converged, which indicates adequate reactive margin for the system. Appendix C contains tables showing positive reactive margins at the Adelanto 500kV bus for all contingencies. Reactive margins at Adelanto met the special criteria identified in the study plan. Note: Loss of the IPP DC mono-pole results in the lowest reactive margin of 354 MVAr; however, this is with use of the +5% case. Simulating without the +5% flow yields a reactive margin of 806 MVAr, which meets the +500 MVAr requirement for N-1 contingencies Transient Stability Analysis Transient stability study simulations identified that all contingencies studied for these system conditions were damped and conformed to the NERC/WECC Planning Standards. A discussion of key outages follows. Loss of the Intermountain Mona No.1 and No.2 345kV lines Transient stability study simulation with GE identifies Stopped - network failed to converge, which indicates instability for loss of the Intermountain Mona No.1 and No.2 345kV lines. The simulation stops 5 cycles after fault clearing. Figure 4 Transient Stability Plots with PSLF Program 13
14 As a check, the contingency was simulated in the PSS/E platform to determine if both programs yield the same result. The PSS/E simulation runs without convergence issues. Figure 5 Transient Stability Plots with PSS/E Program Observing both plots, there is a large voltage spike after the fault is cleared and the lines are opened. This could be a mathematical issue causing non-convergence in the PSLF program. Another difference relates to modeling of the IPPDC. The IPPDC in the PSLF program has a user written model that is specific to the IPPDC functionality. However, this model is a black box since, the code is encrypted, which does not allow the user to discern switching actions. Only observing the output during simulations does the user get a glimpse of what the user written model is adjusting Intermountain generation is switched. The PSS/E program has a CDC6T model that represents the IPPDC. LADWP was consulted to determine if this is a modeling issue. LADWP is investigating further to determine if the TWE AC and DC Project benefits this contingency. This contingency will be further defined during the WECC Phase 2 studies. In order to get the contingency to simulate, the TWE monopole (1600 MW) was tripped and the IPPDC lines (881 MW each pole) were tripped. Transient stability results are provided in Appendix D and plots are provided in Appendix F. 14
15 3.2. Non-Simultaneous Analysis Full Buildout A non-simultaneous Full buildout base case was developed in order to evaluate WECC system reliability. Note, the pre-project base case was evaluated by simulating all power flow contingencies. The developed post-project base case has a TransWest Express flow of 3,000 MW on the DC portion of the Project and 1,500 MW on the AC portion Base Case Development The Non-Simultaneous base case modeled a TWE DC flow of 3,000 MW in the north to south direction and a TWE AC flow of 1,500 MW in the north to south direction. When turning the Intermountain Unit 2 generator and station service load off (displaced with TWE power), the reactive power from Unit 2 was approximately 70 MVAr. As a result, one (1) 70 MVAr shunt capacitor was modeled at the Intermountain 345 kv bus. The following Projects are included in the Full buildout base case. Table 2 TWE Project with Full Buildout New Transmission Facilities No. Project Description 1 TWE DC and AC Project 2 Gateway West 3 Eldorado Harry Allen 500 kv line 4 Colorado River-Delaney 500 kv line 5 Gateway South 7 North Gila Imperial Valley No.2 Project 8 Southwest Intertie Project (SWIP-N) 8 The TransWest Express DC path is defined as the sum of flow on the following lines: TWE-INT* TWE-WY 500 kv DC No.1 and No.2 Lines The TransWest Express AC path is defined as the sum of flow on the following lines: TWE-NV* McCullough 500 kv TWE-NV* Marketplace 500 kv TWE-NV* Eldorado 500 kv TWE-NV* Mead 500 kv Note, the asterisk indicates the metering location Post-Transient Power Analysis Single and double contingencies listed in Table 3a and 3b of the study plan were simulated for the Non-Simultaneous base case. Power flow results identified that only one (1) contingency results in an element to exceed 100% of its emergency thermal limit. No post-transient voltage violations were identified with inclusion of TWE AC and DC Project. 8 The Cross-Tie Project will be studied as a sensitivity without the SWIP-N Project. Since, there would be congestion with both Projects modeled. 15
16 A discussion of key outages follows. Loss of the Aeolus TWE-Wyoming No.1 and No.2 500kV lines The Platte Standpipe 230kV line loads to 101.5% (45% increase in flow) of its emergency thermal rating of 1258 amps (501 MVA). PacifiCorp has a RAS that trips up to 1600 MW of Aeolus area generation for this contingency. However, the case does not have any new Aeolus area generation modeled to trip. As a result, mitigation is required for this contingency. For this multiple contingency outage, P7, the TWE Wyoming 500/230kV transformers could be tripped, opening the path where the power is flowing. Or, the TWE Wyoming to Anticline 500kV line could be tripped to mitigate thermal issue Post-Transient Voltage Stability Cases were created with TWE path flows increased to 105% of the maximum achievable TWE AC (1575 MW) and DC (3150 MW) transfer capability. All contingencies converged, which indicates adequate reactive margin for the system. Appendix C contains tables showing positive reactive margins at the Adelanto 500kV bus for all contingencies. Reactive margins at Adelanto met the special criteria identified in the study plan Transient Stability Analysis Transient stability study simulations identified that all contingencies studied for these system conditions were damped and conformed to the NERC/WECC Planning Standards. A discussion of key outages follows. Loss of the Intermountain Mona No.1 and No.2 345kV lines Transient stability studies identify that the system is not stable. Transient stability study simulation with GE identifies Stopped - network failed to converge, which indicates instability for loss of the Intermountain Mona No.1 and No.2 345kV lines. The simulation stops 5 cycles after fault clearing. Figure 6 Transient Stability Plots with PSLF Program As a check, the contingency was simulated in the PSS/E platform to determine if both programs yield the same result. The PSS/E simulation runs without convergence issues. 16
17 Figure 7 Transient Stability Plots with PSS/E Program Observing both plots, there is a large voltage spike after the fault is cleared and the lines are opened. This could be a mathematical issue causing non-convergence in the PSLF program. Another difference relates to modeling of the IPPDC. The IPPDC in the PSLF program has a user written model that is specific to the IPPDC functionality. However, this model is a black box since, the code is encrypted, which does not allow the user to discern switching actions. Only observing the output during simulations does the user get a glimpse of what the user written model is adjusting Intermountain generation is switched. The PSS/E program has a CDC6T model that represents the IPPDC. LADWP was consulted to determine if this is a modeling issue. LADWP is investigating further to determine if the TWE AC and DC Project benefits this contingency. This contingency will be further defined during the WECC Phase 2 studies. In order to get the contingency to simulate, the TWE monopole (1600 MW) was tripped and the IPPDC lines (881 MW each pole) were tripped. Transient stability results are provided in Appendix D and plots are provided in Appendix F. 17
18 4. Affected Path Stress Test Results The WECC Affected Path Stress Test is used to determine each affected path with loss of the TWE DC Project at full output. Results for the Commercial Operation buildout, Full buildout with the SWIP-N Project and with the Full buildout with the Cross-Tie Project are provided. A simultaneous interaction is identified as a path flow change greater than or equal to 10% of the path rating. Loss of the TWE bipole outage was simulated by the following switching: 1. Block both TWE DC bi-poles 2. Tripped TWE shunt capacitors at both ends of the TWE DC line 3. Trip Wyoming wind generation 4. Tripped one (1) IPPDC Pole and Intermountain shunt capacitors Commercial Operation Buildout Thirty-one (31) simultaneous interactions were observed. Table 3. Non-Simultaneous, Commercial Operation buildout NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 1 ALBERTA - BRITISH COLUMBIA W2E NORTHWEST - CANADA N2S WEST OF CASCADES - NORTH E2W WEST OF CASCADES - SOUTH E2W WEST OF HATWAI E2W MONTANA - NORTHWEST E2W WEST OF BROADVIEW E2W WEST OF COLSTRIP E2W WEST OF CROSSOVER E2W IDAHO - NORTHWEST W2E MIDWAY - LOS BANOS S2N IDAHO - SIERRA N2S BORAH WEST E2W MONTANA - IDAHO N2S BRIDGER WEST E2W PATH C N2S SOUTHWEST OF FOUR CORNERS E2W FOUR CORNERS 345/ PG&E - SPP E2W PACIFICORP/PG&E 115 KV N2S NORTHERN SOUTHERN CA N2S IPP DC LINE N2S INTERMOUNTAIN - MONA 345 KV E2W INTERMOUNTAIN-GONDER 230 KV E2W TOT 1A E2W
19 NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 31 TOT 2A N2S PAVANT, INTRMTN - GONDER 230 KV E2W BONANZA WEST E2W TOT 2B TOT 2C N2S TOT 3 N2S TOT 4A NE2SW TOT 4B SE2NW TOT 5 W2E TOT 7 N2S SYLMAR - SCE N2S IID - SCE E2W SDG&E - CFE S2N WEST OF COLORADO RIVER (WOR) E2W SOUTHERN NEW MEXICO (NM1) N2S NORTHERN NEW MEXICO (NM2) N2S EAST OF COLORADO RIVER (EOR) E2W CHOLLA - PINNACLE PEAK N2S SOUTHERN NAVAJO N2S SILVER PEAK - CONTROL 55 KV E2W CORONADO-SILVER KING-KYRENE N2S BROWNLEE EAST W2E ELDORADO - MEAD 230 KV LINES N2S WALC BLYTHE - SCE BLYTHE 161 KV E2W INYO - CONTROL 115 KV TIE E2W LUGO - VICTORVILLE 500 KV LINE E2W ELDORADO - MCCULLOUGH 500 KV W2E PERKINS-MEAD-MARKETPLACE PACIFIC DC INTERTIE (PDCI) N2S COI N2S SOUTH OF ALLSTON N2S NORTH OF JOHN DAY N2S MIDPOINT - SUMMER LAKE E2W ALTURAS PROJECT N2S CRYSTAL - ALLEN S2N TOT 2B1 N2S TOT 2B2 N2S MONTANA SOUTHEAST S2N SNTI-S.NEVADA TRAN INTERFACE S2N (Imp) TOTBEAST W2E
20 NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 83 MATL TRANSWEST EXPRESS DC LINE N2S TRANSWEST EXPRESS AC LINE N2S Full Buildout, SWIP-N Included Twenty-six (26) simultaneous interactions were observed. Table 4. Non-Simultaneous, Full buildout, SWIP-N Included NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 1 ALBERTA - BRITISH COLUMBIA W2E NORTHWEST - CANADA N2S WEST OF CASCADES - NORTH E2W WEST OF CASCADES - SOUTH E2W WEST OF HATWAI E2W MONTANA - NORTHWEST E2W WEST OF BROADVIEW E2W WEST OF COLSTRIP E2W WEST OF CROSSOVER E2W IDAHO - NORTHWEST W2E MIDWAY - LOS BANOS S2N IDAHO - SIERRA N2S BORAH WEST E2W MONTANA - IDAHO N2S BRIDGER WEST E2W PATH C N2S SOUTHWEST OF FOUR CORNERS E2W FOUR CORNERS 345/ PG&E - SPP E2W PACIFICORP/PG&E 115 KV N2S NORTHERN SOUTHERN CA N2S IPP DC LINE N2S INTERMOUNTAIN - MONA 345 KV E2W INTERMOUNTAIN-GONDER 230 KV E2W TOT 1A E2W TOT 2A N2S PAVANT, INTRMTN - GONDER 230 KV E2W BONANZA WEST E2W TOT 2B TOT 2C N2S
21 NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 36 TOT 3 N2S TOT 4A NE2SW TOT 4B SE2NW TOT 5 W2E TOT 7 N2S SYLMAR - SCE N2S IID - SCE E2W SDG&E - CFE S2N WEST OF COLORADO RIVER (WOR) E2W SOUTHERN NEW MEXICO (NM1) N2S NORTHERN NEW MEXICO (NM2) N2S EAST OF COLORADO RIVER (EOR) E2W CHOLLA - PINNACLE PEAK N2S SOUTHERN NAVAJO N2S SILVER PEAK - CONTROL 55 KV E2W CORONADO - SILVER KING - KYRENE N2S BROWNLEE EAST W2E ELDORADO - MEAD 230 KV LINES N2S WALC BLYTHE - SCE BLYTHE 161 KV E2W INYO - CONTROL 115 KV TIE E2W LUGO - VICTORVILLE 500 KV LINE E2W ELDORADO - MCCULLOUGH 500 KV W2E PERKINS-MEAD-MARKETPLACE PACIFIC DC INTERTIE (PDCI) N2S COI N2S SOUTH OF ALLSTON N2S NORTH OF JOHN DAY N2S MIDPOINT - SUMMER LAKE E2W ALTURAS PROJECT N2S CRYSTAL - ALLEN S2N TOT 2B1 N2S TOT 2B2 N2S MONTANA SOUTHEAST S2N SNTI-S.NEVADA TRAN INTERFACE S2N (Imp) TOTBEAST W2E MATL TRANSWEST EXPRESS DC LINE N2S TRANSWEST EXPRESS AC LINE N2S * SWIP-North: Mdpt-RobnSumt *
22 4.3. Sensitivity, Full Buildout, Cross-Tie Project Included Twenty-seven (27) simultaneous interactions were observed. Table 5. Non-Simultaneous, Full buildout, Cross-Tie Project Included NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 1 W2E ALBERTA - SASKATCHEWAN W2E NORTHWEST - CANADA N2S WEST OF CASCADES - NORTH E2W WEST OF CASCADES - SOUTH E2W WEST OF HATWAI E2W MONTANA - NORTHWEST E2W WEST OF BROADVIEW E2W WEST OF COLSTRIP E2W WEST OF CROSSOVER E2W IDAHO - NORTHWEST W2E MIDWAY - LOS BANOS S2N IDAHO - SIERRA N2S BORAH WEST E2W MONTANA - IDAHO N2S BRIDGER WEST E2W PATH C N2S SOUTHWEST OF FOUR CORNERS E2W FOUR CORNERS 345/ PG&E - SPP E2W PACIFICORP/PG&E 115 KV INTERCON. N2S NORTHERN - SOUTHERN CALIFORNIA N2S IPP DC LINE N2S INTERMOUNTAIN - MONA 345 KV E2W INTERMOUNTAIN - GONDER 230 KV E2W TOT 1A E2W TOT 2A N2S PAVANT, INTRMTN - GONDER 230 KV E2W BONANZA WEST E2W TOT 2B TOT 2C N2S TOT 3 N2S TOT 4A NE2SW TOT 4B SE2NW TOT 5 W2E TOT 7 N2S SYLMAR - SCE N2S
23 NUM NAME Post-Con 'Direction of + Pre- Con Post- Con Change Percent of Path Path (+) Path (-) 42 IID - SCE E2W SDG&E - CFE S2N WEST OF COLORADO RIVER (WOR) E2W SOUTHERN NEW MEXICO (NM1) N2S NORTHERN NEW MEXICO (NM2) N2S EAST OF COLORADO RIVER (EOR) E2W CHOLLA - PINNACLE PEAK N2S SOUTHERN NAVAJO N2S SILVER PEAK - CONTROL 55 KV E2W CORONADO - SILVER KING - KYRENE N2S BROWNLEE EAST W2E ELDORADO - MEAD 230 KV LINES N2S WALC BLYTHE - SCE BLYTHE 161 KV E2W INYO - CONTROL 115 KV TIE E2W LUGO - VICTORVILLE 500 KV LINE E2W ELDORADO - MCCULLOUGH 500 KV W2E PERKINS - MEAD - MARKETPLACE PACIFIC DC INTERTIE (PDCI) N2S COI N2S SOUTH OF ALLSTON N2S NORTH OF JOHN DAY N2S MIDPOINT - SUMMER LAKE E2W ALTURAS PROJECT N2S CRYSTAL - ALLEN S2N TOT 2B1 N2S TOT 2B2 N2S MONTANA SOUTHEAST S2N SNTI-S.NEVADA TRAN INTERFACE S2N (Imp) TOTBEAST W2E MATL TRANSWEST EXPRESS DC LINE N2S TRANSWEST EXPRESS AC LINE N2S Cross-Tie Project
24 5. Path Independence Test Results Two screening tests were used to determine whether the TWE AC and TWE DC lines are independent of existing paths Test 1: Schedule a Fixed Amount of Power on Project The TWE AC and DC Project was added to the 2020 heavy summer base case. Since, the TWE DC inverters can control the range from 0 to 3,000 MW, it will be a new Path independent of all other paths. Also, since, the TWE AC line has phase-shift transformers that can control the power flow for the full range from 0 to 3,000 MW, it will be a new Path independent of all other paths Test 2: Do Not Schedule Power on Project The TWE AC and DC Project was added to the 2020 heavy summer base case. Since, the TWE DC inverters can control the range from 0 to 3,000 MW, it will be a new Path independent of all other paths. Also, since, the TWE AC line has phase-shift transformers that can control the power flow for the full range from 0 to 3,000 MW, it will be a new Path independent of all other paths. 6. Sensitivity Studies 6.1. Non-Simultaneous Analysis Full Buildout, Cross-Tie Project A non-simultaneous Full buildout base case with the Cross-Tie Project modeled was developed in order to evaluate WECC system reliability. Note, the pre-project base case was evaluated by simulating all power flow contingencies. The developed post-project base case has a TransWest Express flow of 3,000 MW on the DC portion of the Project and 1,500 MW on the AC portion Base Case Development The Non-Simultaneous base case modeled a TWE DC flow of 3,000 MW in the north to south direction and a TWE AC flow of 1,500 MW in the north to south direction. When turning the Intermountain Unit 2 generator and station service load off (displaced with TWE power), the reactive power from Unit 2 was approximately 70 MVAr. As a result, one (1) 70 MVAr shunt capacitor was modeled at the Intermountain 345 kv bus. The following Projects are included in the Full buildout base case. Table 6 TWE Project with Full Buildout New Transmission Facilities No. Project Description 1 TWE DC and AC Project 2 Gateway West 3 Eldorado Harry Allen 500 kv line 4 Colorado River-Delaney 500 kv line 5 Gateway South 7 North Gila Imperial Valley No.2 Project 8 Cross-Tie Project 24
25 The TransWest Express DC path is defined as the sum of flow on the following lines: TWE-INT* TWE-WY 500 kv DC No.1 and No.2 Lines The TransWest Express AC path is defined as the sum of flow on the following lines: TWE-NV* McCullough 500 kv TWE-NV* Marketplace 500 kv TWE-NV* Eldorado 500 kv TWE-NV* Mead 500 kv Note, the asterisk indicates the metering location Post-Transient Power Analysis Single and double contingencies listed in Table 3a and 3b of the study plan were simulated for the Non-Simultaneous base case. Power flow results identified that only one (1) contingency results in an element to exceed 100% of its emergency thermal limit. No post-transient voltage violations were identified with inclusion of TWE AC and DC Project. A discussion of key outages follows. Loss of the Aeolus TWE-Wyoming No.1 and No.2 500kV lines The Platte Standpipe 230kV line loads to 104.9% (49% increase in flow) of its emergency thermal rating of 1258 amps (501 MVA). PacifiCorp has a RAS that trips up to 1600 MW of Aeolus area generation for this contingency. However, the case does not have any new Aeolus area generation modeled to trip. As a result, mitigation is required for this contingency. For this multiple contingency outage, P7, the TWE Wyoming 500/230kV transformers could be tripped, opening the path where the power is flowing. Or, the TWE Wyoming to Anticline 500kV line could be tripped to mitigate thermal issue Post-Transient Voltage Stability Cases were created with TWE path flows increased to 105% of the maximum achievable TWE AC (1575 MW) and DC (3150 MW) transfer capability. All contingencies converged, which indicates adequate reactive margin for the system. Appendix C contains tables showing positive reactive margins at the Adelanto 500kV bus for all contingencies. Reactive margins at Adelanto met the special criteria identified in the study plan Transient Stability Analysis Transient stability study simulations identified that all contingencies studied for these system conditions were damped and conformed to the NERC/WECC Planning Standards. A discussion of key outages follows. 25
26 Loss of the Intermountain Mona No.1 and No.2 345kV lines Transient stability studies identify that the system is not stable. Transient stability study simulation with GE identifies Stopped - network failed to converge, which indicates instability for loss of the Intermountain Mona No.1 and No.2 345kV lines. The simulation stops 5 cycles after fault clearing. Figure 8 Transient Stability Plots with PSLF Program As a check, the contingency was simulated in the PSS/E platform to determine if both programs yield the same result. The PSS/E simulation runs without convergence issues. Figure 9 Transient Stability Plots with PSS/E Program 26
27 Observing both plots, there is a large voltage spike after the fault is cleared and the lines are opened. This could be a mathematical issue causing non-convergence in the PSLF program. Another difference relates to modeling of the IPPDC. The IPPDC in the PSLF program has a user written model that is specific to the IPPDC functionality. However, this model is a black box since, the code is encrypted, which does not allow the user to discern switching actions. Only observing the output during simulations does the user get a glimpse of what the user written model is adjusting Intermountain generation is switched. The PSS/E program has a CDC6T model that represents the IPPDC. LADWP was consulted to determine if this is a modeling issue. LADWP is investigating further to determine if the TWE AC and DC Project benefits this contingency. This contingency will be further defined during the WECC Phase 2 studies. In order to get the contingency to simulate, the TWE monopole (1600 MW) was tripped and the IPPDC lines (881 MW each pole) were tripped. Transient stability results are provided in Appendix D and plots are provided in Appendix F. 27
28 7. Study Findings and Conclusions / Recommendations Study results for the TWE AC and DC Project did not yield significant planning criteria violations. In fact, the results were positive indicating that further studies should be conducted to achieve WECC path ratings for both the AC and DC components of this Project. Key observations from the non-simultaneous studies are provided in the following summary. Both the TWE AC and DC components of the Project will be new WECC Paths since they are independent of all other paths. The Affected Path Stress Test (10% test) results indicate that there are number of existing WECC paths that will require further analysis in the WECC Phase 2 studies. Some of the paths indicate that the TWE AC and DC project have a very strong correlation. Based on power flow base case development, when scheduling power flow to the Intermountain 345kV substation, the reactive power consumption increased. As a result, an additional two (2) 160 MVAr shunt capacitors are needed. Loss of the Aeolus TWE-Wyoming No.1 and No.2 500kV lines results in the underlying 230kV system to yield a line that exceeds its thermal limit. A solution for this double line contingency would be to trip the TWE Wyoming 230kV bus from the Platte Latham 230kV line. This opens the path to mitigate the high flow during this contingency. Further discussions with PRG members will be helpful in assessing if there are any issues in coordinating operation of both the IPPDC and TWE DC lines. Furthermore, scheduling and generation tripping at the Intermountain substation should be further explored to determine trip amounts for various levels of flow scheduled to the Intermountain substation. Loss of the Intermountain Mona No.1 and No.2 345kV lines does not converge in the PSLF program for transient stability simulations. The transient stability contingency solves in the PSS/E program. However, PSLF uses a user-written model and PSS/E uses a generic CDC6T model. Need to further investigate to determine if this a numerical issue, or truly a transient instability. For this study, the TWE DC monopole and the IPPDC bi-pole was tripped for this contingency to yield a transient stability converged simulation. Based on these study results, the TransWest Express AC and DC Project does interact with a number of existing WECC path ratings. Therefore, it is recommended that the TransWest Express AC and DC Project be accepted into Phase 2A of the WECC Path process with the Plan of Service described in Appendix I. 28
TransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationTOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY
More informationSDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report
SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationAPPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
More informationTransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal
TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationConsulting Agreement Study. Completed for Transmission Customer
Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...
More informationRocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationCITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS
CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationChapter 7: Transmission
Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key Findings... 1 Background... 1 Northwest Transmission Planning... 6 SUMMARY OF KEY FINDINGS For a number of years
More informationSupplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications
Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen
More informationWestConnect TTC/ATC Workshop. Joint CCPG-SSPG-SWAT Meeting NOVEMBER 16, 2017
WestConnect /ATC Workshop Joint CCPG-SSPG-SWAT Meeting NOVEMBER 16, 2017 WestConnect /ATC Workshop WestConnect /ATC Workshop Participants CCPG SSPG SWAT BEPC* NVE APS PRPA* SMUD EPE TRI-STATE TANC LADWP
More informationNorthernLights HVDC Project
WECC COMPREHENSIVE PROGRESS REPORT December 4, 2008 Prepared for TransCanada by Ben Williams TABLE OF CONTENTS EXECUTIVE SUMMARY... III 1.0 BACKGROUND & INTRODUCTION... 1 1.1 BACKGROUND... 1 1.2 INTRODUCTION...
More informationQ217 Generator Interconnection Project
Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationValley - Rainbow Interconnection Project Feasibility Study Report
Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationDecision on the ISO Transmission Plan
Decision on the 2013-2014 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 19-20, 2014 Approving the plan means approving
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationInterconnection System Impact Study Final Report February 19, 2018
Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationMoving Renewable Energy to the User
Moving Renewable Energy to the User Bob Wilson, Energy Systems Engineer, REWilson@IEEE.org May 17, 2008 Outline Objectives & Legislation Moving megawatts Large pipe dreams Power electronics at the RE plant
More informationWECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report
WECC Regional Planning Review Canada/Pacific Northwest Northern California Transmission Line Project Technical Analysis Committee Report November 1, 2007 Table of Content Summary...1 SECTION 1 SECTION
More informationTransmission Planning. WECC 2014 Progress Report. March 14, 2014
Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission
More informationCalifornia Independent. System Operator. Market Overview and Design Construct
California Independent Market Overview and Design Construct Kyle Hoffman 916-608-1127 khoffman@caiso.com The ISO Vision Preferred Provider of Superior Electric Transmission Services Ensure reliable transmission
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationEvaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection
Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationMidway/Monument Area TTC Study
Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny
More informationQ95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.
A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationVerde Transmission, LLC. Verde Project. System Impact Study Report
Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationWestern Area Power Administration Sierra Nevada Region
Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,
More informationEl PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS
El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationTransCanyon Cross-Tie Transmission Project
TransCanyon Cross-Tie Transmission Project Cross-Tie Phase I Progress Report Supplemental Simultaneous Analysis Final Report Revision 1.1 August 2017 Table of Contents 2 Page Executive Summary -------------------------------------------------------------------------------------------
More information2012 LOCAL TRANSMISSION PLAN:
Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study
ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationDate: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah
TRANSMISSION PLANNING Craig Quist Director of Area/Transmission Planning East PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84116 (801)220-4264 PH (801)220-2842 FAX Date: March 15,
More informationDynamic Scheduling NI A F S NI S. Where:
Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationFour Corners 230kV Generator Interconnections Group
A subsidiary of Pinnacle West Capital Corporation Four Corners kv Generator Interconnections Group Feasibility Study APS Contract Nos. - By Arizona Public Service Company Transmission Planning September,
More informationNorth Gila Generator Interconnection
A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009
More informationSDG&E Valley-Rainbow Project
SDG&E Valley-Rainbow Project Presentation to Grid Reliability/Operations Committee Steven Mavis ISO Grid Planning Department May 24, 2000 1 Background SDG&E s 1999 Expansion Plan for 2000-2004 indicated
More informationProcess Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.
Process Timeline Legend Problem Area that have been resolved Recurring Areas from previous System Assessment New Areas Area Bubbles Flows Modeled for One-Year Heavy Winter Peak Conditions Base Case Conditions
More informationTable of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure
No. 6930 Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationLoad Modeling for Power System Studies
Load Modeling for Power System Studies WECC Load Modeling Task Force Dmitry Kosterev Bonneville Power Administration Transmission Planning Timescale of Interest Our primary interest is the fast dynamic
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationTransmission Planning using Production Cost Simulation & Power Flow Analysis
ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL
More informationLarge Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project
Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationGENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED
DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE
More informationTransCanyon Cross-Tie Transmission Project
TransCanyon Cross-Tie Transmission Project WECC Path Rating Studies and Comprehensive Progress Report (Phase 1) Final Report Revision 1.0 July 2017 1 Table of Contents Page Executive Summary ----------------------------------------------------------------------------------
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More information2013 ANNUAL PROGRESS REPORT
Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationWestern Area Power Administration Sierra Nevada Region
Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,
More informationMarch 7, Subject: Southern California Edison 2011 Annual Progress Report
March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen
More informationFour Corners Queue Transmission Interconnection Study
Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationManaging California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station
Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center
More informationSPS Planning Criteria and Study Methodology
SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationAPPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation
APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed
More informationSecond Report of the Tehachapi Collaborative Study Group
Development Plan for the Phased Expansion of Electric Power Transmission Facilities in the Tehachapi Wind Resource Area Second Report of the Tehachapi Collaborative Study Group Volume 2: Appendices California
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationMerchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.
Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationCargill Power Markets LLC Transmission Service Study (OASIS # TSR and )
Cargill Power Markets LLC Transmission Service Study (OASIS # TSR 72608299 and 72827161) Prepared by: Electric Power Research Institute (EPRI) Under contract with: Public Service Company of New Mexico
More informationEL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV
EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department
More informationBurlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study
Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study
More informationAPPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems
2016-2017 ISO Transmission Plan March 17, 2017 APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems California ISO/MID G-1 2016-2017 ISO Transmission Plan March 17, 2017 Intentionally
More informationWestern Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04
Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch
More informationTargeted Application of STATCOM Technology in the Distribution Zone
Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More informationWest Station-West Cañon 115 kv Transmission Project
West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon
More informationAPS and Regional Transmission Systems Overview
APS and Regional Transmission Systems Overview Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System Overview APS Transmission System Overview Industry
More informationFeasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection
Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection
More informationSMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014
SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More information