TransWest Express Project

Size: px
Start display at page:

Download "TransWest Express Project"

Transcription

1 TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation

2 Executive Summary On October 21, 2005 Arizona Public Service Company (APS) announced publicly its intention of exploring the feasibility of constructing two new 500 kv transmission lines from Wyoming (Powder River Basin and nearby high-quality open range wind locations) to northern Arizona to provide Arizona and other states (NM, NV, CA and UT) access to over 6000 MW of coal and wind resources in Wyoming. The new transmission project from Wyoming to Arizona, the TransWest Express Project, is planned to be operational in 2013 and is expected to deliver 3000 MW of power to meet rapid load growth in Arizona and the southwest. The TransWest Express Project has a three-phase implementation plan. These are: Phase 1- Feasibility study Phase 2- Technical study and permitting Phase 3- Implementation APS is sponsoring the feasibility study for the project. The feasibility study entails high level technical and economic analyses. This report details the objective, scope, methodology and the results for the technical part of the feasibility study. This study evaluated six transmission alternatives capable of exporting up to 3000 MW of power from Wyoming to Arizona and the southwest. Alternatives evaluated included three 500 kv AC options (Alternatives A, B and C), a 500 kv DC only alternative (Alternative D), a 500 kv AC/DC hybrid alternative (Alternative E) and a 765 kv AC alternative (Alternative F). Alternative F was designed to serve as sensitivity to Alternative A. The study results demonstrate that each of the transmission alternatives evaluated is feasible and capable of meeting the objective of the project, which is to be able to export up to 3000 MW of power from Wyoming to Arizona and the southwest. The study also revealed that additional facilities or upgrades beyond the basic scope of each alternative are needed in order to export the 3000 MW and meet reliability standards. The study results showed that the electrical performances of Alternatives A, B and C are similar since all the three alternatives originate from the same source with same intermediate connections but slightly different termination points. The critical outages for the three alternatives were found to be the same with the same recommended mitigation plans. However, Alternative A was found to provide a more balanced flow on south of Dave Johnston 500 kv lines compared to B and C. Alternative A also results in relatively lower transmission system losses and has a lower capital cost. All the three alternatives result in inadvertent flow (up to 260 MW) on the existing system. TransWest Express Project, Final Feasibility Study Report-November 2006 i

3 The DC only and the AC/DC hybrid transmission alternatives result in relatively insignificant (about 7 MW) unscheduled flows, lowest transmission system losses, least miles of new transmission lines and lowest capital cost when compared to 500 kv AC alternatives. In particular, Alternative D has transmission system losses of about 186 MW compared to 245 MW for Alternative A, and has a capital cost approximately 55% of that of Alternative A. However, the recommended mitigation plan for the most critical outage for the DC only and the AC/DC hybrid alternatives would require tripping of up to 3000 MW of generation whereas that for the AC alternatives would require tripping of up to 1500 MW of generation. A 765 kv AC transmission alternative is found to compare favorable electrically to 500 kv AC transmission alternative. The difference between the two transmission voltage levels lies in capital cost and transmission losses. Though, transmission system losses for a 765 kv AC alternative (Alternative F) are estimated to be 90 MW while that for a 500 kv AC alternative (Alternative A) is 245 MW, the capital cost for Alternative F is about a billion dollars more than that for Alternative A. This comparison assumed 3000 MW of power schedule for both Alternatives F and A, however, Alternative F could potentially have capacity for up to 5000 MW. TransWest Express Project, Final Feasibility Study Report-November 2006 ii

4 Contents Page Introduction Objective. 2 Scope Transmission Alternatives Alternative A Alternative B Alternative C Alternative D Alternative E...7 Alternative F...8 Base Case Description Modeling of Transmission Alternatives 9 Transmission Schedules Methodology Study Results...13 Analysis and Comparison of Transmission Alternatives Conclusions...23 Appendix A...24 Appendix B...32 Appendix C...39 Appendix D...45 Appendix E...59 TransWest Express Project, Final Feasibility Study Report-November 2006 iii

5 Introduction On October 21, 2005 Arizona Public Service Company (APS) announced publicly its intention of exploring the feasibility of constructing two new 500 kv transmission lines from Wyoming (Powder River Basin and nearby high-quality open range wind locations) to northern Arizona to provide Arizona and other states (NM, NV, CA and UT) access to over 6000 MW of coal and wind resources in Wyoming. The new transmission project from Wyoming to Arizona, the TransWest Express Project (See Figure 1), is planned to be operational in 2013 and is expected to deliver 3000 MW of power to meet rapid load growth in Arizona and the southwest. TransWest Express Project Wyoming All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Substation California Nevada Los Angeles Las Vegas N.Gila Salt Lake City Utah Navajo Arizona Phoenix/ Tucson Four Corners New Mexico Figure 1: TransWest Express Project The TransWest Express Project has a three-phase implementation plan. These are: Phase 1- Feasibility study Phase 2- Technical study and permitting Phase 3- Implementation APS is sponsoring the feasibility study for the project. The feasibility study entails high level technical and economic analyses. This report details the objective, scope and methodology for the technical part of the feasibility study. It provides a high level electrical performances characteristics of the various TransWest Express Project, Final Feasibility Study Report-November

6 transmission alternatives evaluated. The report also ranks the alternatives and recommends the most desirable transmission plan, from a technical perspective. This study is performed as a separate, project-specific study that adopted as a starting point the transmission, resource, and other assumptions and plans developed in WECC, STEP, RMATS and other regional planning processes. Study results and data will be made available to other regional planning processes. As part of this study, high level power flow, transient stability and post-transient analyses were initially performed on four different 500 kv AC and DC transmission alternatives capable of exporting 3000 MW of power from Wyoming to Arizona and the southwest. Two additional transmission alternatives including a 765 kv option were subsequently evaluated. Objective This study evaluates the electrical performance of different transmission alternatives, primarily at 500 kv level capable of exporting up to 3000 MW of power from Wyoming to Arizona, New Mexico, Utah, Nevada and California. The transmission alternatives are compared and the most technically desirable plans recommended for further detailed technical and economic evaluation under the Phase 2 of the TransWest Express implementation plan. Scope The scope of the feasibility study included: Performing high level power flow, transient and post-transient studies on all the transmission alternatives under evaluation. Determining need, size and location of series compensation on all the transmission alternatives. Determining need, amount and location of reactive power support to meet reactive margin requirements. Identifying transmission constraints and the associated critical contingencies for each transmission alternative. Quantifying transmission losses for each transmission alternative. Highlighting incremental flows on the major transmission lines and interfaces. High level capital cost estimates for the preferred transmission plans. Demonstrating that the recommended transmission alternative meets the WECC/NERC planning standards. TransWest Express Project, Final Feasibility Study Report-November

7 Demonstrating that the recommended transmission alternative is capable of exporting 3000 MW of power from Wyoming to Arizona and other southwest states subject to the different transmission schedule scenarios defined under the Transmission Schedules section. Transmission Alternatives In this study, several possible scenarios of establishing a new transmission path from Wyoming to Arizona and the southwest were considered. The study focused on 500 kv (AC and DC) transmission alternatives. Four transmission alternatives were initially evaluated, each originating from Dave Johnston substation in Wyoming. Additional alternatives including 765 kv AC is considered. Provided below are the initial four 500 kv transmission alternatives considered. 3. Alternative A This is an AC only alternative and consists of a total of 1824 miles of new 500 kv transmission lines. The transmission lines originate from the newly proposed 500 kv substation at Dave Johnston and terminate at Las Vegas and Northern Arizona with intermediate terminations at Utah and Jim Bridger. Figure 2 provides a geographical depiction of the Alternative. The transmission line configuration is as follows: Two new 500 kv lines from Dave Johnston to Mona (on separate right of ways). One of the 500 kv lines will have connections at Jim Bridger and planned W. Haven Substation in Utah. New 500 kv lines from Mona to Navajo and Crystal. With additional 500 kv line from Navajo to Pinnacle Peak. New 500 kv substations at Dave Johnston, Jim Bridger, W. Haven and Mona. New 500/345 kv transformers at Jim Bridger, W. Haven and Mona. Additional 500/230 kv transformer is modeled at Dave Johnston. Appendix A, Section 1 provides detail transmission line configuration including line and transformer impedances for this alternative. TransWest Express Project, Final Feasibility Study Report-November

8 TransWest Express Project Alterntive A Utah Wyoming Jim Bridge r Dave Johnston Nevada Salt Lake City W. Haven Mona All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Substation California Los Angeles Las Vegas N.Gila Navajo Arizona Moenkopi Phoenix/ Tucson Four Corners New Mexico Figure 2: TransWest Express Project, Transmission Alternative A 3. Alternative B Alternative B is similar in configuration to Alternative A with exception of the termination points which in this case are Crystal (Las Vegas) and Four Corners (Arizona/New Mexico border). This alternative consists of a total 1993 miles of new 500 kv AC transmission lines. The high level transmission configuration is shown in Figure 3, and the detail line/transformer impedance data are located at Appendix A, Section 2. The make up of this alternative are as follows. Two new 500 kv lines from Dave Johnston to Mona (on separate right of ways). One of the 500 kv lines will have connections at Jim Bridger and planned W. Haven Substation in Utah. New 500 kv lines from Mona to Crystal and Four Corners. With additional 500 kv line from Four Corners to Pinnacle Peak. New 500 kv substations at Dave Johnston, Jim Bridger, W. Haven and Mona. New 500/345 kv transformers at Jim Bridger, W. Haven and Mona. Additional 500/230 kv transformer is modeled at Dave Johnston. TransWest Express Project, Final Feasibility Study Report-November

9 TransWest Express Project Alterntive B Utah Wyoming Jim Bridge r Dave Johnston Nevada Salt Lake City W. Haven Mona All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Substation California Los Angeles Las Vegas N.Gila Navajo Arizona Moenkopi Phoenix/ Tucson Four Corners New Mexico Figure 3: TransWest Express Project, Transmission Alternative B 3. Alternative C The total circuit mile for this alternative is approximately 1873 miles. It is an AC only alternative and is configured (see Figure 4) similar to Alternatives A and B. It has termination points at Navajo (Northern Arizona) and Four Corners (Arizona/ New Mexico border). Detailed line/transformer data can be found at Appendix A, Section 3. Below is a summary of the alternative. Two new 500 kv lines from Dave Johnston to Mona (on separate right of ways). One of the 500 kv lines will have connections at Jim Bridger and planned W. Haven Substation in Utah. New 500 kv lines from Mona to Navajo and Four Corners. With additional 500 kv line from Four Corners to Pinnacle Peak. New 500 kv substations at Dave Johnston, Jim Bridger, W. Haven and Mona. New 500/345 kv transformers at Jim Bridger, W. Haven and Mona. Additional 500/230 kv transformer is modeled at Dave Johnston. TransWest Express Project, Final Feasibility Study Report-November

10 TransWest Express Project Alterntive C Utah Wyoming Jim Bridge r Dave Johnston Nevada Salt Lake City W. Haven Mona All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Substation California Los Angeles Las Vegas N.Gila Navajo Arizona Moenkopi Phoenix/ Tucson Four Corners New Mexico Figure 4: TransWest Express Project, Transmission Alternative C 3. Alternative D This is a two-pole 892-mile, 500 kv DC line from Dave Johnston to Pinnacle Peak. Figure 5 below depicts the geographical configuration of Alternative D. Line /transformer impedance data for this alternative is located at Appendix A, Section 4. Provided below is a summary of the components of this transmission alternative. New 500 kv DC line from Dave Johnston to Pinnacle Peak New 500 kv substation at Dave Johnston New 500 kv converter stations at Dave Johnston and Pinnacle Peak TransWest Express Project, Final Feasibility Study Report-November

11 TransWest Express Project Alterntive D Wyoming Dave Johnston Nevada Utah All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Substation California Los Angeles Las Vegas N.Gila Navajo Arizona Moenkopi Phoenix/ Tucson Four Corners New Mexico Figure 4: TransWest Express Project, Transmission Alternative D 3. Other Alternatives Considered In addition to the four initial alternatives, two other alternatives are considered. These are an AC/DC hybrid alternative (i.e. Alternative E) and a 765 kv level version of Alternative A (i.e. Alternative F). The detailed configurations of these alternatives are as follows. a) Alternative E This alternative comprises of a 512-mile two-pole 500 kv DC line from Dave Johnston to Mona (Utah) and a two 500 kv AC lines originating from Mona and terminating at Crystal (Las Vegas) and Navajo (Northern Arizona). The total transmission circuit length (including the DC portion) is approximately 1318 miles. TransWest Express Project, Final Feasibility Study Report-November

12 The technical detail of this alternative can be found at Appendix A, Section 6. Figure 5 below depicts the geographical configuration of the alternative. TransWest Express Project Alterntive E Wyoming Dave Johnston Utah Nevada Salt Lake City Mona California Las Vegas Navajo Moenkopi Four Corners All Lines are 500 kv TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant Los Ange les N.Gila Arizona Phoenix/ Tucson New Mexico Substation Figure 5: TransWest Express Project, Transmission Alternative E b) Alternative F This 765 kv level alternative is similar in configuration to Alternative A. All the new transmission lines are operated at 765 kv level with exception of Navajo- Pinnacle Peak which is operated at 500 kv level. Alternative F is designed to serve as sensitivity to Alternative A. TransWest Express Project, Final Feasibility Study Report-November

13 Base Case Description The approved WECC 2014 heavy summer peak load (14hs1a) case is used as the starting power flow base case for the feasibility study. This base case is modified to reflect forecasted in-10 heat wave load for Arizona and the southwestern states. New transmission and generation projects that are approved and planned to be online by 2013 in Arizona, Wyoming, Utah and the southwest were modeled. Pre-project case also modeled all transmission projects which are in Phase 2 or 3 of the WECC path rating process. The following projects were included in the pre-project case: STEP short term upgrade project (2006) Harquahala-Devers 500 kv line (2009) Palo Verde TS5 500 kv line (2009) EOR project (2008) Moenkopi-Eldorado series capacitor upgrade (2009) Path 51 upgrade (2009) Hassyampa- Pinal West 500 kv line (2008) VV1 500 kv switching station (2009) Navajo Transmission Project (2010) Pinal West- Browning 500 kv line (2013) TS5-Raceway 500 kv line (2012) Raceway -Pinnacle Peak 500 kv (2010) Hassyampa- N. Gila #2 500 kv line (2012) The post-project cases modeled a total of 3000 MW of new resources at Dave Johnston 500 kv Substation. These resources were scheduled to stress the new transmission lines south of Dave Johnston based on the transmission schedule scenarios provided under Table 1 for each transmission alternative. Modeling of Transmission Alternatives All 500 kv AC alternatives were modeled using MCM Aluminum Conductor Steel Reinforced (ASCR) bundle per phase. The 500 kv AC transmission lines were initially compensated 70%. Transmission lines of circuit length less than 120 miles were compensated at one end. Series compensation was modeled at both ends for transmission lines of circuit length greater than 120 miles, while the total line compensation was maintained at 70%. Shunt reactors were modeled at both ends of a transmission line section. The shunt compensation of the reactors was modeled to be 60% of the respective line charges. TransWest Express Project, Final Feasibility Study Report-November

14 765 kv transmission lines were modeled using MCM ACSR bundle per phase. The 765 kv transmission lines were not series compensated because of loading below surge impedance loading. Shunt reactors were modeled and estimated similarly as the 500 kv transmission lines. DC transmission lines were modeled as a bipole with earth/ground return. Each pole is modeled using MCM ASCR. The DC resistances of the conductors were assumed to be 93.5% of the conductor s AC resistance. Each converter station was equipped with filters and shunt capacitors sized 50% of the transmitted DC power. DC converter and associated transformer losses were estimated to be 1.5% of the total DC power transmitted. Transmission Schedules The following transmission schedules were adhered to in the evaluation of the transmission alternatives. Transmission Transmission Schedules (MW) Alternative Arizona Utah S. Nevada S. California Alternative A Alternative B Alternative C Alternative D Alternative E Alternative F Table 1: TransWest Express Project, Transmission Schedules Methodology The pre-project base case was tested to ensure compliance with WECC/NERC planning standards. The 3000 MW new resource was modeled as coal-fired plants for this feasibility study. The output of the coal plants were injected at the proposed Dave Johnston 500 kv Substation. For each transmission alternative, transfers were made according to transmission schedule scenarios provided under Table 1 until the flow on the new transmission line(s) south of Dave Johnston is 3000 MW or a critical transmission facility limit is reached. The limiting facility and the associated transfer levels were noted for each transmission alternative. The 3000 MW transferred power replaced generators in Arizona (Red Hawk, Mesquite and Harquahala Units), California (Mohave Units), Utah (Hunter Emery Units) and Nevada (Duke Units) according to the transmission schedules provided under Table 1. The generators selected for displacement in Arizona TransWest Express Project, Final Feasibility Study Report-November

15 were chosen to create a stressed base case condition to expose the most transmission constraints south of Navajo and the relative performance differences between the various transmission alternatives with respect to those transmission constraints were evaluated. The initial phase of the study focused on power flow analysis. Subsequent phases of the study examined at high level post-transient voltage and transient stability performances. As part of the power flow study, critical contingencies in Arizona and the southwest were simulated, including the following: Navajo-Crystal 500 kv line South of Navajo 500 kv lines Moenkopi-El Dorado 500 kv line Moenkopi Four Corners 500 kv line Moenkopi Westwing 500 kv line Perkins-Mead 500 kv line Four Corners- Cholla 345 kv line Palo Verde-Westwing 500 kv line Palo Verde Devers 500 kv Harquahala-Devers 500 kv line Hassyampa-N. Gila 500 kv line Palo Verde 2 units outage Navajo 2 units outage The study also focused on outages of the transmission sections of the individual transmission alternatives evaluated. Appendix E depicts the list of all outages simulated. The power flow study is performed and the results analyzed based on the assumption that no single element is loaded above its normal continuous thermal rating under pre-contingency conditions or above its emergency ratings under contingency conditions. The post-transient analysis is conducted and evaluated based on the assumption that the maximum voltage deviations allowed under contingency conditions in the post-transient time frame are 5% for N-1 and 10% for N-2 unless a lower standard has been previously adopted on selected buses. TransWest Express Project, Final Feasibility Study Report-November

16 Transient stability runs are simulated for 20 seconds to ensure the transmission system is stable and adequately damped. System stability is assessed based on damping of the rotor angles and also using WECC/NERC transient voltage dip and transient frequency criteria 1. All outages were simulated using governor power flow tools. Remedial actions for each outage were modeled according to the latest Operating Studies Subcommittee Handbook. 1 WECC transient voltage dip criteria: The transient voltage dip should not exceed 30% at any bus. For transient voltage dips 20% or more, the maximum duration should not exceed 20 cycles for a single contingency or 40 cycles for a double contingency. WECC transient frequency criteria: The minimum transient frequency for a single contingency is 59.6 Hz; if below 59.6 Hz, the duration should not exceed 6 cycles. For double contingencies, the minimum transient frequency is 59.0 Hz; if below 59.0 Hz, the duration should not exceed 6 cycles TransWest Express Project, Final Feasibility Study Report-November

17 Study Results 1. Benchmark Case The pre-project or benchmark case is tested to ensure compliance with WECC/NERC planning standards. Power flow diagram that highlights critical path flows can be found in Appendix B, Section 1. All outages studied yielded a power flow, post-transient and transient solutions. No thermal overload was identified following the outages studied. Bus voltage deviations during post-transient time frame were found to be within established planning limits. Transient voltage and frequency dips were within limits for all the outages studied. 2. Transmission Alternative A Power Flow Study All outages with exception of Dave Johnston-Bridger 500 kv line yielded power flow solution. Summary of the study results can be found in Appendix C, Table C.1. Dave Johnston-Bridger 500 kv line outage is identified as the most critical contingency for this case. Power flow solution for this outage was obtained by adding up to 600 Mvar of voltage support equipment at Dave Johnston Substation. Other potential solution to this outage is an installation of Special Protection System (SPS) to trip up to 750 MW of generation at Dave Johnston. Shiprock 345/230 kv transformer overloads up to 3% following an outage of Navajo-Pinnacle Peak 500 kv line. Replacing the transformer with a higher rated one will resolved the observed overload. Transient Stability Most of the contingencies studied yielded a stable and well-damped transient stability performance. Other critical outages such as Dave Johnston-Bridger 500 kv and Bridger-Mona 500 kv lines however resulted in unstable transient stability performances. An outage of Dave Johnston- Bridger 500 kv line results in transient voltage and frequency dip violations at several load buses. To address this system instability will require tripping up to two of the four generation units (1500 MW generation trip) connected to Dave Johnston following the outage. Similarly, Bridger-Mona 500 kv single line outage resulted in several bus voltage and frequency dip criteria violations. Tripping up to 1500 MW of generation at Dave Johnston will mitigate the observed criteria violations. TransWest Express Project, Final Feasibility Study Report-November

18 An outage of Dave Johnston- Mona 500 kv line also results in transient voltage and frequency dip criteria violations at several load buses. To mitigate this requires an installation of an SPS that will trip one generation unit or 750 MW of generation following the outage. Appendix D, Section 1 depicts the transient voltage and frequency plots for selected critical buses following the outages of Dave Johnston-Mona, Dave Johnston-Bridger and Bridger-Mona 500 kv lines. Post-transient With exception of the outage of Dave Johnston-Bridger 500 kv line, all outages studied yielded solution during post-transient time frame. No posttransient voltage deviation criteria violation was observed for majority of the outages. To achieve post-transient solution without post-transient voltage deviation criteria violation following the outage of Dave Johnston- Bridger 500 kv line will require the installation of up to 800 Mvar voltage support at Dave Johnston. Alternatively, installing an SPS to trip up to 750 MW of generation at Dave Johnston immediately following the outage will facilitate the achievement of post-transient solution and mitigate the observed voltage deviation criteria violation. Post-transient voltage deviation violations were also recorded for outage of Dave Johnston-Mona 500 kv line. To mitigate the recorded violations will require the installation of up to 200 Mvar of voltage support equipment at Bridger substation. Other potential mitigation plan includes tripping up to 750 MW of generation at Dave Johnston via SPS. 3. Transmission Alternative B Power Flow Study Summary of the power flow study is provided in Appendix C, Table C.1. No power flow solution was obtained following Dave Johnston-Bridger 500 kv line outage. Voltage support equipment or generation tripping scheme will be required for a solution to be achieved. Shiprock 345/230 kv transformer overloads by 1% following the outage of Four Corner-Pinnacle Peak 500 kv line. Replacing the existing transformer with a higher rated one will mitigate this overload. Transient Stability Three outages resulted in transient voltage and frequency dip violations at several buses. These outages are Dave Johnston-Bridger 500 kv line, Dave Johnston Mona 500 kv line and Bridger- Mona 500 kv line. TransWest Express Project, Final Feasibility Study Report-November

19 Transient voltage and frequency violations associated with the outage of Dave Johnston-Bridger 500 kv line could be mitigated by tripping up to 1500 MW of generation at Dave Johnston following the outage. Installing an SPS to trip up to 750 MW of generation at Dave Johnston will mitigate the transient voltage and frequency dip criteria violations following Dave Johnston-Mona and Bridger Mona 500 kv single line outages. Appendix D, Section 2 shows the transient voltage and frequency plots for selected critical buses following the outages of Dave Johnston-Mona, Dave Johnston-Bridger and Bridger-Mona 500 kv lines. Post-transient No solution was obtained following an outage of Dave Johnston- Bridger 500 kv line. Up to 800 Mvar voltage support will be required for posttransient solution and to remain with the voltage deviation criteria. Alternatively, installing an SPS to trip up to 750 MW of generation at Dave Johnston immediately following the outage will mitigate the observed criteria violation. Post-transient voltage deviation violations were recorded for outage of Dave Johnston-Mona 500 kv line. To mitigate the recorded violations will require the installation of up to 200 Mvar of voltage support equipment at Bridger substation. Other potential mitigation plan includes tripping up to 750 MW of generation at Dave Johnston using SPS. 4. Transmission Alternative C Power Flow study Summary of power flow results can be found at Appendix C, Table C.3. No power flow solution was obtained following Dave Johnston-Bridger 500 kv line outage. 600 Mvar of SVC or generation tripping scheme is required for a solution to be achieved. Moenkopi - RME 500 kv line overloads by 155% following the outage of Navajo-Crystal 500 kv line. This overload exceeds the line s short-term rating by 26%. The observed overload could be mitigated by upgrading the line s series capacitor for higher ampacity. Transient Stability Single line outages of Dave Johnston-Bridger 500 kv line, Dave Johnston- Mona 500 kv line and Bridger-Mona 500 kv line yielded an unstable transmission system performance. Transient voltage and frequency dip criteria violations were recorded at several buses following these outages. TransWest Express Project, Final Feasibility Study Report-November

20 Transient voltage and frequency criteria violations recorded with the outage of Dave Johnston-Bridger 500 kv line could be mitigated by tripping up to 1500 MW of generation at Dave Johnston following the outage. Installing an SPS to trip up to 750 MW of generation at Dave Johnston will mitigate the transient voltage and frequency dip criteria violations following Dave Johnston-Mona and Bridger Mona 500 kv single line outages. Transient voltage and frequency plots for selected critical buses following the outages of Dave Johnston-Mona, Dave Johnston-Bridger and Bridger- Mona 500 kv lines can be found in Appendix D, Section 3. Post-transient No solution was obtained following an outage of Dave Johnston- Bridger 500 kv line. Up to 800 Mvar voltage support will be required for posttransient solution without voltage deviation criteria violation to be achieved. Alternatively, installing an SPS to trip up to 750 MW of generation at Dave Johnston following the outage will mitigate the observed criteria violation. Post-transient voltage deviation violations were recorded for outage of Dave Johnston-Mona 500 kv line. To mitigate the recorded violations will require installing up to 200 Mvar of voltage support equipment at Bridger substation. Other potential mitigation plan includes tripping up to 750 MW of generation at Dave Johnston using SPS. 5. Transmission Alternative D Power Flow Study Appendix C, Table C.4 depicts the summary of the power flow and posttransient study results. Pinnacle Peak-Cactus 230 kv line loads up to 124% under normal operating conditions. Pre-project overload on the line was found to be 10%. Dave Johnston-Pinnacle Peak 500 kv DC bipole outage is the most critical contingency for this alternative. A power flow solution could only be obtained for this outage by tripping all the generators (3000 MW) connected to Dave Johnston. Losing one pole of the DC line will require the tripping of 1500 MW without ramping power onto the remaining pole. An outage of any one of the four Pinnacle Peak 500/230 kv transformers overloads the remaining in-service transformers by 15%. Adding a fifth transformer bank or installing a 500/345 kv transformer at Pinnacle peak will mitigate this overload. TransWest Express Project, Final Feasibility Study Report-November

21 Pinnacle Peak-Reach 230 kv line outage overloads Pinnacle Peak-Cactus 230 kv line by 5%. Re-conductoring of this line will resolve the observed overload. Transient Stability Stable and well damped transient performances were achieved for all outages studied. An outage of Dave Johnston-Pinnacle Peak 500 kv DC line (both poles), following by tripping of all the generators (3000 MW) connected to Dave Johnston yielded a stable transmission system performance during transient conditions. No transient voltage and frequency dip criteria violations were recorded following the outage. An outage of one of the DC poles without ramping power on to the remaining pole yielded a stable transmission system performance. An SPS to trip up to 1500 MW is required to achieve the stable transient solution. Transient voltage and frequency plots for selected critical buses following the Dave Johnston-Pinnacle Peak 500 kv DC bipole outage are located at Appendix D, Section 4. Post-Transient Post-transient solution was achieved for all outages studied. No voltage deviation criteria violation was recorded. 6. Transmission Alternative E Power Flow Study Summary of the power flow and post-transient study results for this alternative can be found at Appendix C, Table C.5. Dave Johnston-Mona 500 kv DC bipole outage is the most critical contingency for this alternative. A power flow solution for this outage could only be achieved by tripping all the generators (3000 MW) connected to Dave Johnston. One pole outage of the DC line will require tripping up to 1500 MW. Navajo-Pinnacle Peak 500 kv line outage overloads Shiprock 345/230 kv transformer by 1%. Replacing the existing transformer with a higher rated one will resolve the observed overload. TransWest Express Project, Final Feasibility Study Report-November

22 Transient Stability Stable and well damped transient performances were achieved for all outages studied with exception of Mona-Navajo and Mona-Crystal 500 kv single line outages. Transient Stability plots for selected critical outages are depicted at Appendix D, Section E. Mona-Navajo 500 kv line outage resulted in unstable transient system performance. To mitigate this unstable condition requires blocking one of the Dave Johnston-Mona 500 kv DC poles and in addition to tripping up to 1500 MW of generation at Dave Johnston. Similarly, an outage of Mona-Crystal 500 kv line will require the blocking of one of the Dave Johnston-Mona DC poles in addition to tripping up to 1500 MW of generation at Dave Johnston in order to achieve a stable transient stability performance without criteria violation. An outage of Dave Johnston-Mona 500 kv DC line (both poles), following by tripping of all the generators (3000 MW) connected to Dave Johnston yielded a stable transmission system performance during transient conditions. No transient voltage and frequency dip criteria violations were recorded following the outage. An outage of one of the DC poles without ramping power on to the remaining pole yielded a stable transmission system performance. An SPS to trip up to 1500 MW is required to achieve the stable transient solution. Post-Transient Post-transient solution was achieved for all outages studied. No voltage deviation criteria violation was recorded. 7. Transmission Alternative F The power flow, transient and post-transient performances for this sensitivity case are similar to the performances achieved using transmission alternative A. Key similarities are: Transmission line, path and interface flows are similar. Dave Johnston-Bridger outage is the most critical outage. Special protection schemes are required in order to achieve stable operation following outages of Dave Johnston-Bridger, Bridger-Mona and Dave-Johnston Mona 500 kv lines. Differences in performance were identified in areas of transmission line losses and the number of series capacitors. TransWest Express Project, Final Feasibility Study Report-November

23 Analysis and Comparison of Transmission Alternatives One of the objectives of this feasibility study is to rank the transmission alternatives evaluated. This section analyses and compares the transmission alternatives based on the following: Electrical performance Miles of transmission lines Number of transformers Number of series capacitors needed Number of shunt reactors Number of shunt capacitors Number of AC/DC converters Transmission losses Unscheduled flows Number of potential SPS required Transmission facilities to be upgraded Incremental flows on major transmission paths High level cost estimates. It is demonstrated in the study that all the alternatives including the 765 kv option are technically feasible in exporting up to 3000 MW of power from Wyoming to Arizona and the southwest. However, an upgrade to existing transmission facilities will be required for any of the alternatives to meet WECC/NERC reliability standard. On electrical performance, the study showed that Alternatives A, B and C exhibit similar electrical performances since all the three alternatives originate from the same source with same intermediate connections but slightly different termination points. Dave Johnston-Bridger 500 kv, Dave-Johnston-Mona 500 kv and Bridger-Mona 500 kv lines were found to be the critical outages for these alternatives. Impact of these outages could be mitigated by installing SPS to trip generation at Dave Johnston. The electrical performance of the 765 kv option (Alternative F) is similar to Alternative A. Flows on the two transmission lines south of Dave Johnston were found to be nearly balanced for the three alternatives. Alternative A, however has a better balanced flow on the two lines south of Mona when compared to B and C. This is because the power angle between Mona and Four Corners is small compared to the angle between Mona and other terminating points such as Crystal and Navajo. A balanced flow on Mona to Four Corners and Mona to Crystal or Navajo could be achieved by installing a phase shifting transformer on the Mona- Four Corners 500 kv line. Unscheduled flow (i.e. flows from the underlying transmission system on to the new transmission lines) is higher for Alternative A than B and C. Thus, Alternative A would result in a better balanced of flows on TransWest Express Project, Final Feasibility Study Report-November

24 parallel lines but has higher unscheduled flows. Alternatives D and E result in relatively lower inadvertent flows compared to A, B and C. The most critical outage for the DC only (Alternative D) or AC/DC hybrid (Alternative E) alternatives is the simultaneous outages of the DC poles. This outage could only be mitigated by tripping all the generators (3000 MW) connected to Dave Johnston. Whilst, Alternative D would require SPS for only the DC line outage where as Alternative E would require SPS for outages of the DC line and any of the line segments south of Mona. Loss of a line segment between Dave Johnston and Mona is the most critical outage for the AC alternatives. The mitigation plan for an outage of these outages would be to trip 1500 MW of generation at Dave Johnston. Table 2 below compares the transmission alternatives based on miles of transmission lines, transmission facilities needed, transmission losses and costs. As can be seen from Table 2, in terms of miles of transmission line to be constructed, Alternative D is the least, requiring 892 miles of new transmission lines and B is the most (1993 miles of new transmission line). Alternative D would require the least number of transmission equipment (such as transformer, shunt capacitors and converters) as part of its plan of service whilst B requires the most. Furthermore it is evident from Table 2 that Alternative D results in relatively lowest increase in WECC transmission system losses (186 MW) compared to the other 500 kv level alternatives. Alternative C has the highest increase in WECC transmission system losses (308 MW). In all, the 765 kv option (Alternative F) recorded the lowest increase in WECC transmission system losses, approximately 90 MW. High level project capital cost estimates were computed for each alternative based on the basic plan of service provided under section Transmission Alternatives. As depicted on Table 2, Alternative D will cost less to implement and F will cost most. It must be noted that the cost estimates provided on Table 2 does not capture the additional facilities or upgrades to the existing system required to meet WECC/NERC reliability standards. TransWest Express Project, Final Feasibility Study Report-November

25 Items Transmission Alternatives A B C D E F Miles of transmission lines No. of transformers No. of series capacitors No. of shunt capacitors No. of shunt reactors No. of AC/DC converters No. of Potential SPS Required Increase in WECC system losses (MW) Unscheduled (MW) Facility upgrades required High level cost estimate ($ Million) flows 263 1) Install a 4th 500/230 kv transformer at Pinnacle Peak. 2) Replace Shiprock 345/230 kv transformer 4, ) Install a 4th 500/230 kv transformer at Pinnacle Peak. 2) Replace Shiprock 345/230 kv transformer 1) Install a 4th 500/230 kv transformer bank at Pinnacle Peak. 2) Upgrade the series capacitors on Moenkopi-RME 500 kv line 1) Install 500/345 kv transformer at Pinnacle Peak. 2) Re-conductor Pinnacle Peak- Cactus 230 kv line 1) Replace Shiprock 345/230 kv transformer 1) Install a 4th 500/230 kv transformer at Pinnacle Peak. 2) Replace Shiprock 345/230 kv transformer 4,897 4,589 2,347 3,190 5,338 Table 2: Comparison of Transmission Alternatives TransWest Express Project, Final Feasibility Study Report-November

26 Next, incremental flows on major transmission paths in the southwest are monitored to ascertain how they are impacted by implementing any of the alternatives. Table 3 below compares interface flows for the alternatives and the benchmark case. Transmission Path Flows (MW) Alternatives Navajo South Four Corner West East of River California- Oregon Intertie Benchmark A B C D E F Table 3: Major Transmission Path Flows As can be seen from Table 3, Alternative D off-loads the flow on Navajo South path and Alternative C causes the flow south of Navajo to increase. All the other alternatives have minimal impact on the Navajo south path. Four Corner West path flow is impacted most by Alternative B and C where as Alternatives A, D, E and F have relatively small impacts. Alternative D causes the EOR flow to increase up to 1000 MW where as Alternative B off-loads the path by up to 450 MW. The EOR Path is least impacted by the implementation of Alternative A. All the transmission alternatives evaluated have minimal or no impact on the California Oregon Intertie and thus no potential effect on the operations of both the Pacific DC Intertie and the Palo Verde nuclear plants. TransWest Express Project, Final Feasibility Study Report-November

27 Conclusions The study results demonstrate the feasibility of each of the transmission alternatives capable of meeting the objective of the project, which is to be able to export up to 3000 MW of power from Wyoming to Arizona and the southwest states. The study also revealed that additional facilities or upgrades beyond the basic scope of each alternative are needed in order to export the 3000 MW and meet reliability standards. The study results showed that the electrical performances of Alternatives A, B and C are similar since all the three alternatives originate from the same source with same intermediate connections but slightly different termination points. The critical outages for the three alternatives were found to be the same with the same recommended mitigation plans. However, Alternative A provides a more balanced flow on south of Dave Johnston 500 kv lines compared to B and C. Alternative A also results in relatively lower transmission system losses and lower capital cost. The DC only (Alternative D) and the AC/DC hybrid transmission (Alternative F) alternatives result in relatively least unscheduled flows, lowest increase in system losses, least miles of new transmission lines and the associated capital cost when compared to 500 kv AC alternatives. In particular, Alternative D has transmission system losses of about 186 MW compared to 245 MW for Alternative A, and has a capital cost approximately 55% that of Alternative A. However, DC line outage would result in tripping of up to 3000 MW of generation whereas critical outage for the AC alternatives would require the tripping of 1500 MW of generation. A 765 kv AC transmission alternative is found to compare favorable electrically to 500 kv AC transmission alternative. The difference between the two transmission voltage levels lies in capital cost and transmission losses. Though, transmission system losses for a 765 kv AC alternative (Alternative F) are estimated to be 90 MW while that for a 500 kv AC alternative (Alternative A) is 245 MW, the capital cost for Alternative F is about 1 billion US Dollars more than that for Alternative A. This comparison assumed 3000 MW of power schedule for both the Alternatives F and A, however, Alternative F could potentially have capacity for up to 5000 MW. TransWest Express Project, Final Feasibility Study Report-November

28 Appendix A Section 1: Technical Details - Transmission Alternative A Section 2: Technical Details - Transmission Alternative B Section 3: Technical Details - Transmission Alternative C Section 4: Technical Details - Transmission Alternative D Section 5: Technical Details - Transmission Alternative E Section 6: Technical Details - Transmission Alternative F TransWest Express Project, Final Feasibility Study Report-November

29 Section 1: Technical Details-Transmission Alternative A States Traversed: Wyoming, Utah, Colorado, Nevada and Arizona Line length: Dave Johnston Jim Bridger, approximately 203 miles Jim Bridger West Haven, approximately 202 miles West Haven Mona, approximately 101 miles Dave Johnston Mona, approximately 512 miles Mona Crystal, approximately 340 miles Mona Navajo, approximately 220 miles Navajo Pinnacle Peak, approximately 246 miles TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant TransWest Express Project Alterntive A All Lines are 500 kv Substation California Nevada Los Ange le s Las Vegas N.Gila Utah Salt Lake City 340 mi Navajo 246 mi 101 mi 220 mi Mona Arizona Phoenix/ Tucson Wyoming Jim Bridger 202 mi W. Haven Moenkopi 203 mi 512 mi Four Corners Dave Johnston Total 1824 miles New Mexico Figure A-1: Transmission Alternative A with line lengths Voltage level: 500 kv AC Conductor type: MCM ASCR bundle per phase Line impedance: For up to 150 miles; R= ohm/mile, X=0.530 ohm/mile, B=2.0 Mvar/mile. For transmission lines of length more than 150 miles, R= ohm/mile, X=0.519 ohm/mile, B=2.0 Mvar/mile. Series capacitors: 60% compensation on Mona-Crystal, Compensation on all other new lines modeled at 70%. TransWest Express Project, Final Feasibility Study Report-November

30 Shunt reactors: Modeled at both ends of each transmission line section with shunt compensation equivalent to 60% of respective line section charges. Transformer: Dave Johnston (500/230 kv, 600 MVA, R= p.u, X= p.u), Jim Bridger and Mona (500/345 kv. 672 MVA, R= p.u, X= p.u). Section 2: Technical Details-Transmission Alternative B States Traversed: Wyoming, Utah, Colorado, Nevada and Arizona Line length: Dave Johnston Jim Bridger, approximately 203 miles Jim Bridger West Haven, approximately 202 miles West Haven Mona, approximately 101 miles Dave Johnston Mona, approximately 512 miles Mona Crystal, approximately 340 miles Mona Four Corners, approximately 322 miles Four Corners Pinnacle Peak, approximately 313 miles TransWest Express Project Existing Lines Upgrades Other Planned Projects Power Plant TransWest Express Project Alterntive B All Lines are 500 kv Substation California Nevada Los Ange le s Las Vegas N.Gila Utah Salt Lake City 340 mi Navajo 101 mi Mona Arizona Phoenix/ Tucson Wyoming Jim Bridger 202 mi W. Haven 322 mi Moenkopi 313mi 203 mi 512 mi Four Corners Dave Johnston Total 1993 miles New Mexico Figure A-2: Transmission Alternative B with line lengths TransWest Express Project, Final Feasibility Study Report-November

31 Voltage level: 500 kv AC Conductor type: MCM ASCR bundle per phase Line impedance: For up to 150 miles; R= ohm/mile, X=0.530 ohm/mile, B=2.0 Mvar/mile. For transmission lines of length more than 150 miles, R= ohm/mile, X=0.519 ohm/mile, B=2.0 Mvar/mile. Series capacitors: 45% compensation on Mona-Crystal, Compensation on all other new lines modeled at 70%. Shunt reactors: Modeled at both ends of each transmission line section with shunt compensation equivalent to 60% of respective line section charges. Transformer: Dave Johnston (500/230 kv, 600 MVA, R= p.u, X= p.u), Jim Bridger and Mona (500/345 kv. 672 MVA, R= p.u, X= p.u) Section 3: Technical Details-Transmission Alternative C States Traversed: Wyoming, Utah, Colorado and Arizona Line length: Dave Johnston Jim Bridger, approximately 203 miles Jim Bridger West Haven, approximately 202 miles West Haven Mona, approximately 101 miles Dave Johnston Mona, approximately 512 miles Mona Navajo, approximately 220 miles Mona Four Corners, approximately 322 miles Four Corners Pinnacle Peak, approximately 313 miles TransWest Express Project, Final Feasibility Study Report-November

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Reliability Must-Run Analysis th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006

Reliability Must-Run Analysis th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006 Reliability Must-Run Analysis 2006 2015 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006 Outline of Presentation 2006 RMR Study Process Description of network and constraint SIL/MLSC

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

North Gila Generator Interconnection

North Gila Generator Interconnection A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009

More information

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer Electrical Transmission System Analysis EE 456 project Team Members Abdulaziz Almarzouqi Hamzah Abeer Due December 14, 2012 Changes: 1. 134MW Wind added 2. N-1 Contingency limits changed to.95-1.05 3.

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Dynamic Scheduling NI A F S NI S. Where:

Dynamic Scheduling NI A F S NI S. Where: Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017 Sheffield-Highgate Export Interface SHEI VSPC Quarterly Meeting October 18, 2017 Northern Vermont Export Study Update VELCO is providing information to enable evaluation of potential solutions Incremental

More information

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting Joseph H. Rowley Vice President Project Development 101 Ash Street, HQ14A San Diego, CA 92101-3017 Tel: 619.696.4455 Fax: 619.696.2911 JRowley@SempraGeneration.com December 15, 2009 Ms. Anjali Sheffrin

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

APS and Regional Transmission Systems Overview

APS and Regional Transmission Systems Overview APS and Regional Transmission Systems Overview Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System Overview APS Transmission System Overview Industry

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Electric Power Research Institute, USA 2 ABB, USA

Electric Power Research Institute, USA 2 ABB, USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

Valley - Rainbow Interconnection Project Feasibility Study Report

Valley - Rainbow Interconnection Project Feasibility Study Report Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Arizona Energy Consortium Conference

Arizona Energy Consortium Conference SunZia Southwest Transmission Project SunZia and Potential Impacts of Regionalization Arizona Energy Consortium Conference SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 2018 0 SunZia: 500kV Project delivering

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

EE 456 Design Project

EE 456 Design Project F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...

More information

U.S. System Summary: ARIZONA/SOUTHWEST

U.S. System Summary: ARIZONA/SOUTHWEST U.S. System Summary: ARIZONA/SOUTHWEST Arizona/Southwest High-Speed Rail System (Source: Texas A&M Transportation Institute) The Arizona/Southwest high-speed rail system described in this summary groups

More information

Question Question 1.2-8

Question Question 1.2-8 Question 1.2-7 A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information