ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

Size: px
Start display at page:

Download "ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study"

Transcription

1 ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016

2 LEGAL NOTICE This document, prepared by ABB Inc, is an account of work sponsored by Public Service Company of New Mexico (PNM). Neither PNM nor ABB Inc. nor any person or persons acting on behalf of either party: (i) makes any warranty or representation, expressed or implied, with respect to the use of any information contained in this report, or that the use of any information, apparatus, method, or process disclosed in this report may not infringe privately owned rights, or (ii) assumes any liabilities with respect to the use of or for damages resulting from the use of any information, apparatus, method, or process disclosed in this document. Prepared for: Public Service of New Mexico (PNM) Report No.: E A-R01 Date: June 27, 2016

3 Power Systems Consulting Technical Report ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Executive Summary: E A-R01 Dept. Date Consulting June 27, 2016 Pages 714 PNM has requested that ABB perform power flow and stability technical studies to increase the power injections on the BA-Blackwater 345 kv line (BB line) to the maximum level of 1000 MW. Previous technical studies of 832 MW power injection on the BB line have shown that a Static VAR Compensator (SVC) at the Guadalupe 345 kv station is necessary to provide the required voltage support to accommodate these power transfers. The 1000 MW BB line power injections requested by PNM for this study are: El Cabo wind farm at Clines Corner: 213 MW Broadview wind farm: 497 MW Taiban Mesa: 200 MW Aragonne Mesa: 90 MW This study includes the Guadalupe SVC rated 250 MVAr capacitive to 100 MVAr inductive. The goal of this study is to determine if additional voltage support is required beyond the planned Guadalupe SVC for the 1000 MW full buildout power injection. Several study tasks were performed to assess the system impact of the extra power injections on the BB line. The conclusions from the study tasks were as follows: Powerflow contingency analysis on the study base case shows that, for the analyzed contingencies, no substantial voltage/thermal violations occurred on the BB line. Acceptable North American Electric Reliability Corporation (NERC) Transmission Planning (TPL) performance is achieved without additional reactive power support. Voltage stability margin analysis (QV analysis) on the study base case and two stress cases demonstrated that, for the analyzed contingencies, positive reactive margin is maintained at Guadalupe. As such, the BB line transfers meet the WECC voltage stability margin criteria. Dynamic simulation on the study base case with selected N-1 and N-2 contingencies shows that, for all studied disturbances, adequate system dynamic performance and adequate post-fault voltage recoveries are achieved. All wind power plants on the BB line are able to ride-through the studied faults. Dynamic simulation of selected N-1 contingencies on a sensitivity case with Blackwater HVDC in service at 15 MW East-to-West showed stable performance. The BB line wind power plants and the Blackwater HVDC are able to ride-through the studied faults The technical studies thus did not identify a need for additional voltage support beyond the Guadalupe SVC for the 1000 MW full buildout scenario. The system was found to meet the NERC TPL criteria and the WECC voltage stability margin criteria. All the wind farms on the ii

4 BB line were found able to ride through the studied faults with adequate post-fault voltage recoveries. However, the limitations of the positive sequence models used in this study cannot guarantee that a synchronous condenser at Blackwater station is not required to insure sufficient short circuit capacity in the full buildout scenario for inverter based generation 1. PSCAD studies (3-phase model) are being performed in a separate study to evaluate whether a synchronous condenser at Blackwater station will be required to support the power injection conditions as stated above. Rev # Revision Date Author Reviewed 1 PNM Comments June 27, 2016 Huimin Li D Dickmander DISTRIBUTION Public Service New Mexico 1 WECC White Paper: Value and Limitations of the Positive Sequence Generic Models of Renewable Energy Systems neric%20model%20limitations%20december% docx&action=default&defaultitemopen=1 iii

5 TABLE OF CONTENTS 1 Introduction PSLF Model Setup STARTING CASE CONDITIONS STUDY CASE SETUP (TASK1A) Broadview Wind Farm Setup El Cabo Wind Farm Setup Guadalupe SVC Setup Blackwater HVDC Setup Power Flow Analysis CONTINGENCY ANALYSIS (TASK 1B) QV ANALYSIS (TASK 1C) QV Analysis Assumptions QV Analysis Results Guadalupe SVC Headroom QV Analysis Conclusions Dynamic Simulations DYNAMIC SIMULATION CONFIGURATIONS AND CASE LIST DYNAMIC SIMULATIONS WITH NOMINAL BB LINE LOAD ANALYSIS (TASK 1D) SENSITIVITY CASE DYNAMIC ANALYSIS (TASK 1E) Conclusions and Recommendations References Appendices...34 APPENDIX A. CONTINGENCY ANALYSIS RESULTS, NOMINAL LOAD ON BB LINE APPENDIX B. DYNAMIC SIMULATION PLOTS APPENDIX C. SENSITIVITY DYNAMIC SIMULATION RESULTS

6 1 Introduction PNM has requested that ABB perform power flow and stability technical studies to increase the power injections on the BA-Blackwater 345 kv line (BB line) to the maximum level of 1000 MW. Previous technical studies of 832 MW power injection on the BB line have shown that a Static VAR Compensator (SVC) at the Guadalupe 345 kv station is necessary to provide the required voltage support to accommodate these power transfers. The models and databases for the recently completed studies serve as the starting point for adding the additional wind resources included in the full buildout scenario. The goal of this study is to determine if additional voltage support is required beyond the planned Guadalupe SVC for the power injection assumptions in Figure 1-1 on PNM s 216-mile, 345 kv transmission path between Blackwater station and the BA station north of Bernalillo, New Mexico. To Four Corners Rio Puerco 345 kv To San Juan Norton 345 kv bus El Cabo 345 kv Iberdrola El Cabo 213 MW Wind Type 3 Gamesha Wind Turbines 34 miles El Cabo 34.5 kv Bus 34.5kV/345 kv transformer El Cabo 345 kv Bus /-100 MVAR svc Tiaban Mesa 200 MW Type 3 GE Wind Turbines Black Water 345 kv Broadview 497 MW Wind Type 4 Siemens Wind Turbines 44 miles Broadview 34.5 kv Bus 34.5 kv/345 kv transformer Broadview 345 kv Bus 6 Miles 54 Miles 31 Miles To West Mesa BA 345 kv To 115 kv System Guadalupe 345 Aragonne 138/345 kv transformer miles 70 Miles Taiban Mesa 345 kv Aragonne 138 kv Bus 4 62 Miles Blackwater Converter Aragonne 138 kv Bus 3 Aragonne 34.5kV/138 kv transformer Aragonne 34.5 kv Bus 2 DSTATCOM Aragonne Mesa 90 MW Type 1 Mitshubishi Wind Turbines Figure 1-1: Study Configuration on the Blackwater-BA 345kV Line Existing Transmission System Interconnection Customer Faclities 5

7 The study steps requested by PNM are outlined below in Table 1-1. Table 1-1: Study Task Outline Task # Study case set up 1a Configure base cases Task description Powerflow study 1b Contingency analysis on the base case without stress conditions 1c QV analysis on the base case without and with stress conditions Dynamic study 1d Dynamic simulation on the base case 1e Sensitivity case with Blackwater at 15 MW E-W This report is arranged as follows to address each of the above tasks: 1. All cases including the starting case, the study base case without/with stress conditions and the sensitivity case are defined in Section Powerflow studies are described in Section 3 as follows: a. In Section 3.1, powerflow contingency studies of the base case, without stress conditions, are performed to determine if contingency performance meets steady state North American Electric Reliability Corporation (NERC) Transmission Planning (TPL) criteria. The focus of the analysis is limited to defining adequate voltage support between BA and Blackwater for the full buildout conditions, and identify overloads or voltage violations. Addressing overloads or voltage violations west of BA is outside the scope of this analysis. b. In Section 3.2, QV analysis is performed on the base case with and without stress conditions to confirm that transfers meet WECC voltage stability margin criteria. 3. Dynamic studies are described in Section 4 as follows: a. In Section 4.1, system configurations and case lists are described. b. In Section 4.2, dynamic simulations are performed on the base case without stress conditions. c. In Section 4.3, dynamic simulations are performed on the sensitivity case with Blackwater in service at 15 MW E-W. 4. Conclusions and recommendations of this study are presented in Section Section 6 and Section 7 list the references and the appendices of the study. 6

8 2 PSLF Model Setup 2.1 Starting Case Conditions This section describes development of based cases from the starting PSLF model from the Broadview study. The starting PSLF model that formed the basis for the studies was the base case developed for prior studies. The system data from PNM were provided in PSLF version 18 format. The following PNM equipment is included in the starting case: Broadview Generation Injection at Blackwater 345 kv: 297 MW Blackwater HVDC: 75 MW E-W Taiban Mesa: 200 MW Aragonne Mesa: 90 MW A total of 662 MW is injected on the BB line in the starting case as shown in Figure

9 Figure 2-1: One-Line for the 297 MW Broadview Case (Input to Present Study) 8

10 2.2 Study Case Setup (Task1a) Starting from the powerflow case presented in Section 2.1, the modifications listed below were made to develop the base case of the full buildout scenario. Add the 200 MW Grady wind farm at Broadview Add the 213 MW El Cabo wind farm at Clines Corner Add the 250/-100 MVAr SVC in service at Guadalupe. Disconnect the HVDC converter at Blackwater The resulting PSLF model developed as the base case for this study shown in Figure 2-2. The case was developed in PSLF version 18 format. In addition to the base case, two stress cases and one sensitivity case were developed, as shown in Figure 2-3 to Figure 2-5: The two stress cases are only for checking the WECC voltage stability margin criteria. The cases are setup by adding stress conditions on the base case. The defined stress conditions include: o Stress condition 1: Increasing each power injection on the BB line by 5.25% (5% stress case) o Stress condition 2: Increasing each power injection on the BB line by 2.56% (2.5% stress case). The sensitivity case is for checking the BB line fault recovery ability with Blackwater HVDC operates at its minimum power level E-W. The case is set up with Blackwater HVDC in service at 15 MW east to west, and with a reduced power level of the Broadview wind farm to keep the total BB line injections the same as the base case. A total of four cases were thus set up for this study to capture the above conditions. All case conditions are summarized in Table

11 Figure 2-2: One-Line for the Study Base Case 10

12 Figure 2-3: One-Line for the 5% Stress Case 11

13 Figure 2-4: One-Line for the 2.5% Stress Case 12

14 Figure 2-5: One-Line for the Sensitivity Case 13

15 Table 2-1: Study Case Conditions EI Cabo 5 EI Cabo 5-1 AM TM Grady, GWECMV1Grady, GWECMV2 BEJN1 BEJN2 BEKW BLW HVDC E-W Guad SVC RioP SVC Total BB Case Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status WTG [MW] Status P [MW] Status Status line MW Usage Starting Case NA 0 NA 0 IN 94 IN 206 NA 0 NA 0 IN 88 IN 89 IN 125 IN 75 OUT IN 677 Task 1a Base Case IN Task 1b, 107 IN 94 IN 206 IN 100 IN 100 IN 88 IN 89 IN 125 OUT 0 IN IN IN 1c and 1d Stress Case 1 IN IN IN IN IN IN IN IN IN OUT 0 IN IN Task 1c Stress Case 2 IN IN IN IN IN IN IN IN IN OUT 0 IN IN Task 1c Sensitivity IN Case 111 IN 107 IN 94 IN 206 IN 92.5 IN 92.5 IN 88 IN 89 IN 125 IN 15 IN IN 1020 Task 1e Notes: NA: not applicable to this case Starting case: Case from PNM Broadview PSLF study (662 MW injections on BB line). Base case: the full buildout scenario with 1000 MW injections on the BB line. Stress case 1: Base case with 5.25% increase on the total BB line MW injection. Stress case 2: Base case with 2.56% increase on the total BB line MW injection. Sensitivity case: Base case with Blackwater HVDC in service at 15 MW E-W schedule, and a 15MW power reduction at the Broadview wind farm. The total BB line injections are thus the same as the base case. Descriptions on each of the tasks are in Table

16 2.2.1 Broadview Wind Farm Setup The Broadview/Grady wind farm includes five sections: BEJN1, BEJN2, BEKW, GWECMV1 and GWECMV2. Type 4 wind turbines are assumed for all five sections. Detailed models of the Broadview wind farm were provided by PNM including: The wind farm collector system Wind turbine generator dynamic models based on the PSLF regc_a, reec_a, and wtgt_a models. The power flow model of each section of the Broadview wind farm is represented by aggregate models. The parameters used for the PSLF models are listed in Table 2-2. Table 2-2: Broadview Wind Farm PSLF Powerflow Model Parameters Parameter BEJN1 BEJN2 BEKW GWECMV1 GWECMV2 Note WTG Pgen [MW] Siemens SWT 2.3 VS Aggregate 497 MW Turbine GSU transformer Aggregate MVA Wind farm main transformer F/T winding kv Turbine GSU transformer R1 34.5/ / / / / Grady data: reference [2] & [3] Other data: Broadview [pu] PSCAD study Turbine GSU transformer X [pu] Wind farm main transformer MVA Wind farm main transformer / / / / /34.5 Grady data: reference [2] & [3] Other data: Broadview H/X winding kv PSCAD study Wind farm main transformer /345 kv R1 [pu] Wind farm main transformer 34.5/345 kv X1 [pu] Collector System Voltage Grady data: reference [kv] [2] & [3] Collector System R1 [pu] [a] Other data: Broadview Collector System X1 [pu] PSCAD study Collector System B1 [pu] kv Line to BV_POI_3-T~1 [b] R1 [pu] 345 kv Line to BV_POI_3-T~1 X1 [pu] 345 kv Line to BV_POI_3-T~1 B1 [pu] Notes: BEKW s high station is Broadview POI [a] Impedance is on the system 100 MVA base. [b] The 345 kv lines referenced above are the three transmission lines between the grouped wind farm sections and the wind farm main 345 kv collector bus (BV_POI_3-T~1). Impedance is on the system 100 MVA base. 15

17 2.2.2 El Cabo Wind Farm Setup The El Cabo wind farm includes two sections. All wind turbines are Type 3 machines. A detailed model of the El Cabo wind farm was supplied by PNM including: The wind farm collector system Wind turbine generator dynamic models based on the PSLF wt3g, wt3e, and wt3t models. The power flow model of each wind farm section is represented by aggregate models. The parameters used for the PSLF models are listed in Table 2-3. Note: Table 2-3: El Cabo Wind Farm PSLF Powerflow Model Parameters Parameter ELCABO 5 ELCABO 5_1 Note WTG Pgen [MW] Aggregate 213 MW at POI Turbine GSU transformer MVA Aggregate Wind farm main transformer F/T winding kv 34.5/ /0.69 Turbine GSU transformer R1 [pu] Turbine GSU transformer X1 [pu] Wind farm main transformer MVA Wind farm main transformer 345/ /34.5 H/X winding kv Reference [4] Wind farm main transformer 34.5/345 kv R1 [pu] Wind farm main transformer 34.5/345 kv X1 [pu] Collector System Voltage [kv] Collector System R1 [pu] [a] Collector System X1 [pu] Collector System B 1[pu] kv Line ELCABO2 ELCABO1 [a] R1 [pu] kv Line ELCABO2 ELCABO1 X1 [pu] kv Line ELCABO2 ELCABO1 B1 [pu] [a] Impedance is based on the system 100 MVA base. Reference [5] 16

18 2.2.3 Guadalupe SVC Setup The Guadalupe SVC is being designed as a duplicate of the Rio Puerco SVC except for the filter bank configuration which will include 5 th and 7 th harmonic filters as compared to the two fifth harmonic filters used at Rio Puerco. The total filter reactive capability will remain at 75 MVAr as with Rio Puerco SVC. For this analysis, the Guadalupe SVC is assumed to comprise the following components: One Thyristor Controlled Reactor (TCR) rated 175 MVAr. One Thyristor Switched Capactor (TSC) rated 175 MVAr. 5th and 7th harmonic filters, totaling 75 MVAr. The maximum capacitive output is attained with the TSCs switched on and the TCR at a zero conduction angle. This results in an admittance of 250 MVAr (including filters) at the SVC terminal bus. The rated inductive output, on the other hand, is attained with the TCR at full absorption and the TSCs switched out, and amounts to an admittance of 100 MVAr (including filters). Rio Puerco SVC controls two Mechanical Switched Capacitors (MSCs) and one Mechanical Switched Reactor (MSR). In this study, it is assumed that there is no MSR and MSC controlled by the Guadalupe SVC. In the power flow, the SVC is represented as a Type 5 Static VAr Device (SVD) with ID v1 and modeled on the high voltage side of the SVC's 345 kv terminal bus since the modeled controls are based on high voltage side measurements. See Figure 2-6 for the network adjacent to Guadalupe. The SVC is connected to the Guadalupe 345 kv station. For the dynamic simulation, the Guadalupe SVC model is converted to a generator model with ID g1 to interface to the user defined control algorithms. An epcl file PrepForDyd_Guad_SVC.p is modified from the similar Rio Puerco version to accomplish this conversion. Control strategies of the Guadalupe SVC are similar to those for Rio Puerco SVC, Reference [6], except that Guadalupe SVC does not need to control external mechanically switched banks. Step response tests for the Guadalupe SVC are presented in Section 4. As comparison step response of the Rio Puerco SVC is also presented. 17

19 Figure 2-6: Power Flow Data for Guadalupe SVC 18

20 2.2.4 Blackwater HVDC Setup This section only applies to the sensitivity case. Based on Reference [7], an epcl file previously developed by ABB was used to automatically configure the Blackwater filters and transformer taps for the scheduled HVDC power level. In the sensitivity case, the Blackwater HVDC scheduled power level is set at 15 MW E-W. As such, the PNM station is operated as an inverter. For operation at 15 MW, the Blackwater DC voltage is reduced from the nominal 57 kv to around 13 kv as shown in Table 2-4: Table 2-4: Blackwater HVDC PSLF Powerflow Model Parameters Parameters SPS Station PNM Station p_sched [MW] DC voltage [kv] DC Current [ka] AC Filters 2X 26.5 MVAr 3X 26.5 MVAr The resulting powerflow at Blackwater is shown in Figure 2-7. Figure 2-7: Power Flow Data for Blackwater HVDC in Sensitivity Study 19

21 3 Power Flow Analysis 3.1 Contingency Analysis (Task 1b) Contingency analysis was performed on the base case shown in Table 2-1 to confirm that steady state TPL performance criteria are met. The studied contingencies are in Table 3-1: Table 3-1: Contingency List Contingency Name Base N-0 System Intact BA-RP N-1 BA-Rio Puerco 345 kv BA345/115 TX N-1 BA 345/115 kv Transformer BA-NR N-1 BA to Norton 345 kv Contingency Description RP-WM N-1 Rio Puerco West Mesa 345 kv RP-SJ N-1 Rio Puerco San Juan 345 kv RP-FC N-1 Rio Puerco Four Corners 345 kv BAHBALRP N-2 BA 345/115 kv Transformer and BA Rio Puerco 345 kv Line RPWMHL2 N-2 Rio Puerco-West Mesa & West Mesa 345/115 kv Transformer BA-RP-N2 N-2 BA-Rio Puerco 345 kv Double-Circuit Outage The PNM-specific voltage and thermal criteria are listed in Table 3-2: Table 3-2: PNM Voltage and Thermal Criteria Area Conditions Loading Limits Voltage (p.u.) Voltage Drop Application kV and above Artesia 345 kv Normal < Normal Rating Arroyo 345 kv PST source side EPEC (Area 11) PNM (Area 10) Tri- State (zones ) Alamo, Sierra Blanca and Van Horn 69kV % 60 kv to 115 kv % Artesia 345kV Contingency < Emergency Rating % Arroyo 345kV PST source side Alamo, Sierra Blanca and Van Horn 69kV % Hidalgo, Luna, or other 345 kv buses Normal ALIS < Normal Rating kv and above* Contingency N-1 < Emergency Rating ** 6% 46 kv to 115 kv ** 6% 230 kv and above* Contingency N-2 < Emergency Rating ** 10% 46 kv and above* Normal ALIS < Normal Rating All buses Contingency N-1 < Emergency Rating % 69 kv and above except Northeastern NM and Southern NM % 69 kv and above in Northeastern NM and Southern NM Contingency N-2 < Emergency Rating % All buses *Taiban Mesa and Guadalupe 345 kv voltage range is 0.95 p.u. to 1.1 p.u. under normal and contingency conditions. ** Provided operator action can be utilized to adjust voltages back down to

22 The contingency analysis is performed based on the following assumptions: Powerflow contingency analysis focuses on the system condition immediately after the contingency. Fast closed loop controls (FACTS, HVDC) are allowed to regulate, but the mechanically switched devices such as switched capacitors and transformer taps are locked post-contingency. No head room of the Rio Puerco SVC was retained post-contingency. This means that post-contingency output for both the Rio Puerco and Guadalupe SVCs is allowed to move up to the maximum capability. Two 48 MVAr shunts at WESTMS_2 115 and SANDIA_2 115 are switched in precontingency to help the system condition. A total of 4X10 MVAr caps at the El Cabo wind farms are in service pre-contingency. WTGs of El Cabo wind farms are close to their maximum reactive limit in precontingency. Detailed results of the contingency analysis are presented in Appendix A. From the results, it is noticed that: Among all the contingencies, the highest post-contingency Guadalupe SVC susceptance reference is pu (1.0 pu Bref is 100 MVAr at nominal voltage), for the double contingency of both BA-Rio Puerco 345 kv lines. No low voltage violations were identified. Minor high voltage violations occur postcontingency at Broadview 345 kv buses. These high voltages are related to an initial voltage of pu at Broadview 345 kv from the Broadview PSCAD study. This was a result of steady-state voltage and tap conditions from debugging efforts on the Siemens wind turbine models during the Broadview PSCAD study. These violations can be removed by very minor modification to the voltage profile if needed. For the double contingency BA-Rio Puerco 345 kv 1 & 2 : o Overloads are identified on the BA 345/115 kv transformer and the 115 kv systems near the BA 115 kv station. For this double contingency, the RP-BA 345 circuits are both open post-contingency, resulting in increased flow into the 115 kv system at BA. o Overload is identified on the El Cabo to BA 345 KV line. This line is fully loaded pre-contingency, with sight (2%) post-contingency overload. Overall, it can be concluded from the contingency analysis that from the list of the analyzed contingencies, no substantial violations occurred in the monitored areas and zones (Table 3-2). Thus an acceptable TPL performance is achieved. 21

23 3.2 QV Analysis (Task 1c) QV Analysis Assumptions Steady-state reactive margin analysis (Q-V analysis) was performed at the Guadalupe 345 kv station using the GE-SSTOOLS scripts. For the Q-V analysis, the following assumptions are made: Reactive power injections are defined as the total Q at Guadalupe 345 kv station. This means that the Guadalupe SVC output is taken into account while generating the QV curves and the results. AC voltage at the Q-V test points are varied up to 1.05 pu, using an infinite reactive source at the test point. QV curves are developed only for the Guadalupe 345 kv bus. Rio Puerco SVC is modeled as a Type 5 SVD, and adjustable post-contingency. Base case Q-V curves were developed for all contingencies in Table 3-1 except for BA-Rio Puerco 345 kv Double-Circuit Outage. Q-V curves for single contingencies (Table 3-1) were developed for the 5% stress case (Stress case 1 in Table 2-1). Q-V curves for all double contingencies (Table 3-1) except for BA-Rio Puerco 345 kv Double-Circuit Outage were developed for the 2.5% stress case (Stress case 2 in Table 2-1). For the two stress cases, the Guadalupe SVC is connected pre-contingency and the Guadalupe SVC is modeled as a generator with fixed Q. 4 X 10MVAr El Cabo wind farm shunt caps are in service (total is 10 X 10 MVAr). All available Broadview wind farm shunt reactors (5 X 10MVAr) are in service. The El Cabo wind farm model included for QV analysis is set to 213 MW at the POI. The wind farm aggregate generator MVAr limits are set at the aggregate VAR capability at 213 MW Pgen. This means that when the injection level is below the nominal level, the effective power factor range is increased; when the injection level is above the nominal level, the effective power factor range is decreased. Similar to the El Cabo, the Broadview wind farm aggregate generator MVAr limits are set at the aggregate VAR capability at 497 MW Pgen. WTG VAR capability was provided by Siemens in the Broadview PSLF study. This means that when the injection level is below the nominal level, the effective power factor range is increased; when the injection level is above the nominal level, the effective power factor range is decreased. Table 3-3 summarizes the QV analysis setup. 22

24 3.2.2 QV Analysis Results Table 3-3: QV Analysis Setup QV Cases Contingency Number of QV Curves Base Case N-0, N-1 and N-2 9 Stress Case 1 N-0 and N-1 7 Stress Case 2 N-0 and N-2 3 Results from QV analysis are presented below in the plots of Figures 3-1 through 3-5, and summarized in Table 3-4 to Table 3-6. As illustrated in Figures 3-1 Figure 3-3, the slope of the QV curves for all studied outages on the three system conditions indicates stable system performance for Guadalupe 345 kv station voltages in the normal range of 0.95 pu to 1.05 pu. With increased power injections on BB line, there is a significant decrease in the reactive margin. With the N-0 condition of the three powerflow cases (Base, Stress 1, and Stress 2) taken as an example, and when Guadalupe 345 kv station operates at 0.95 pu voltage: The reserved reactive margin for base case without stress condition is ~92 MVAr 1 ; The reactive margin is decreased to ~67 MVAr 1 if the BB line load is increased by 2.56% of the nominal level; The reactive margin is further decreased to ~38 MVAr 1 if BB line load is increased by 5.25% of the nominal level. 1 Note that remaining headroom on Guadalupe SVC can be added to these values (Section 3.2.3) Figure 3-1: QV Curves at Nominal BB Line Load 23

25 Figure 3-2: QV Curves at % of Nominal Level Figure 3-3: QV Curves at % of Nominal Level 24

26 Table 3-4 to Table 3-6 summarize the reactive margins of studied outages at different system conditions. Table 3-4: Summary of Guadalupe 345 kv Bus QV Analysis at Nominal BB Line Load Configuration N-0, N-1 &N-2 Outages Minimum Reactive Margin Reactive Power Requirements MVAr [1] Guad Voltage [pu] RioP Bsvc[pu] = 1.00 = 1.04 [pu] Nominal Load No Outage Nominal Load BA-Rio Puerco 345 kv Nominal Load BA 345/115 kv Nominal Load BA-Norton 345 kv Nominal Load Rio Puerco-West Mesa 345 kv Nominal Load Rio Puerco-San Juan 345 kv Nominal Load Rio Puerco-Four Corners 345 kv Nominal Load Nominal Load BA-Rio Puerco 345 kv & BA 345/115 kv Rio Puerco-West Mesa 345 kv & West Mesa 345/115kV Notes: [1] A negative number indicates the presence of reactive power reserves while a positive number indicates that reactive power support is required to obtain a stable solution. [2] Q of Rio Puerco SVC at the point of Guadalupe minimum reactive margin (Guadalupe Voltage = 0.91 pu in Table 3-4). Positive number means SVC is delivering VARs to the system. [3] Above two footnotes also apply to Table 3-5 and 3-6. [4] See also Section Table 3-5: Summary of Guadalupe 345 kv Bus QV Analysis at % of Nominal BB Line Load Configuration N-0 & N-1 Outages Minimum Reactive Margin Reactive Power Requirements MVAr Guad Voltage[pu] RioP = 1.00 = 1.04 pu 5.25% Pre-Con Load Increase No Outage % Pre-Con Load Increase BA-Rio Puerco % Pre-Con Load Increase BA 345/115 kv % Pre-Con Load Increase BA-Norton 345 kv % Pre-Con Load Increase Rio Puerco-West Mesa 345 kv % Pre-Con Load Increase Rio Puerco-San Juan 345 kv % Pre-Con Load Increase Rio Puerco-Four Corners 345 kv

27 Table 3-6: Summary of Guadalupe 345 kv Bus QV Analysis at % of Nominal BB Line Load Configuration N-0 &N-2 Outages Minimum Reactive Margin Reactive Power Requirements MVAr Guad Voltage [pu] RioP = 1.00 = 1.04 pu 2.56% Pre-Con Load Increase No Outage % Pre-Con Load Increase 2.56% Pre-Con Load Increase BA-Rio Puerco 345 kv & BA 345/115 kv Rio Puerco-West Mesa 345 kv & West Mesa 345/115kV Guadalupe SVC Headroom As described earlier, the Guadalupe SVC output is taken into account while generating the QV curves. Unused Guadalupe SVC capacitive VARs can thus be considered as additional reactive reserves, adding to the reactive margin shown in the QV analysis results. The used and remaining (unused) Guadalupe SVC capacitive VARs for each of the QV cases is summarized in Table 3-7: Table 3-7: QV Analysis: Headroom Remaining of Guadalupe SVC QV Cases SVC output (MVAr) SVC Headroom Remaining (MVAr) Base Case Stress Case 1 (5.25% increase) Stress Case 2 (2.56% increase) QV Analysis Conclusions Based on the QV analysis, the following conclusions can be made: Positive reactive margin is seen at Guadalupe 345 kv for all studied contingencies. With increased power injections on BB line, there is a significant decrease in the reactive margin. Pre-contingency VAR support is needed at Guadalupe 345 kv station for stress cases to solve the power flow at high voltage such as 1.05 pu. Rio Puerco SVC shows relatively high capacitive output when Guadalupe voltage is at the low side, especially when the BB line load is at % of the nominal level. 26

28 4 Dynamic Simulations 4.1 Dynamic Simulation Configurations and Case List After the power flow study in Section 3, dynamic cases were run for selected N-1 or N-2 contingencies to help ensure: Adequate system dynamic performance and adequate post-fault voltage recovery. That all the existing wind power plants on The BB line will ride-through the fault. Dynamic simulations were performed on a list of contingencies as shown in Table 4-1: Table 4-1. Dynamics Case List Contingency Name Description 0 N-0 System intact, flat run 1 BA-RP 4-Cycle 3ph fault on BA-RP close to BA 345 kv. Clear BA at 4 Cycles. Clear RP at 6 Cycles 2 BA345/115 TX 4-Cycle 3ph fault at BA 345 kv, trip BA 345/115 kv Transformer at 4 cycles 3 BA-NR 4-Cycle 3ph fault at BA 345 kv, trip the BA- NR 345 kv line at the 4 cycles 4 RP-WM 4-Cycle 3ph fault at RP 345 kv, trip the RP-WM 345 kv line at the 4 cycles 5 RP-SJ 4-Cycle 3ph fault at RP 345 kv, trip the RP-SJ 345 kv line at the 4 cycles 6 RP-FC 4-Cycle 3ph fault at RP 345 kv, trip the RP-FC 345 kv line at the 4 cycles 7 GuadSvcTrp Trip the Guadalupe SVC after 1 second flat run 8 BAHBALRP N-2: 3-Cycle 3ph fault on BA-RP close to BA 345 kv. Clear BA and RP at 4 Cycles. Trip the BA345/115 kv Transformer at 4 cycles. 9 RPWMHL2 N-2: 3-Cycle 3ph fault on WW-RP close to West Mesa 345 kv. Clear WM and RP at 4 Cycles. Trip the WM 345/115 kv Transformer at 4 cycles. 10 BA-RP-N2 N-2: 4-Cycle 3ph fault on BA-RP close to BA 345 kv. Clear BA & RP at 4 Cycles. Trip the BA-RP double cks at 4 cycles. The following assumptions are used for the dynamic simulations: Dispatch as shown in Figure 1-1 (base case in Table 2-1). The Broadview and El Cabo wind farms are represented using collector system models and wind turbine models provided by PNM. As it was mentioned in Section 2.2.3, a duplicate of the Rio Puerco SVC for Guadalupe SVC is used for this study. Since the network strength at Guadalupe is different from Rio Puerco, sensitivity testing on voltage regulator gains for Guadalupe was performed. Three gain settings as listed in Table 4-2 were tested. Table 4-2: Guadalupe SVC Gain Settings Tested Guadalupe SVC Gain setting # Kp Ki

29 The gains for Rio Puerco SVC are 6 and 2300 for the proportional and integral gain respectively. As shown in Table 4-2: For the test gain setting #1, the Guadalupe SVC uses higher Kp but lower Ki as compared to the Rio Puerco SVC. A reduced integral gain was tried in all settings (#1 #2 and #3) as compared to Rio Puerco. In this study, the dynamic simulations described in Section 4.2 and Section 4.3 were performed with three Guadalupe SVC gain settings. It should be noted that the gains set in PSLF study are preliminary, and detailed settings of the SVC gains will need to be confirmed with PSCAD studies as part of the Guadalupe SVC project. 4.2 Dynamic Simulations with Nominal BB Line Load Analysis (Task 1d) For the study base case shown in Figure 2-2, dynamic simulations were run for all contingencies listed in Table 4-1. Three sets of plots corresponding to the three tested Guadalupe SVC gains are available in Appendix B, as Appendices B-1, B-2, and B-3, corresponding to the numberings given in Table 4-2. Step responses of Rio Puerco and Guadalupe SVC are also included in the three parts of Appendix B. The results show that for the base case of the full buildout scenario: With nominal BB line dispatch plus a 250/-100 MVAr SVC at the Guadalupe 345 kv station, system stability is maintained for all studied N-1 and all N-2 contingencies. All the wind power plants on the BB line are able to ride-through the studied faults For certain faults such as BA-Rio Puerco, N-1 and Rio Puerco Four Corner, N-1, oscillations in the reactive power measured at the Guadalupe side of the Guadalupe 345 kv Argonne 138 kv transformer was observed. Investigation of the oscillations indicates that the oscillations originate within the Argonne Mesa wind farm and are not related to the Guadalupe SVC. Guadalupe SVC integral gain is recommended to be lowered to 10% - 20% comparing to the Rio Puerco SVC gain settings. This is due to the weaker network strength at Guadalupe 345 kv station. 4.3 Sensitivity Case Dynamic Analysis (Task 1e) As shown in Table 2-1 and Figure 2-5, the sensitivity case was setup with Blackwater HVDC in service with a 15 MW E-W schedule, which is the minimum power of the Blackwater HVDC. The Broadview wind farm power level was also reduced by 15 MW to hold the total BB line power injection the same as in the study base case. 28

30 Dynamic simulations were run on the N-0 and N-1 contingencies listed in Table 4-1. Three sets of plots corresponding to the three tested Guadalupe SVC gains are available in Appendix C, as Appendices C-1, C-2, and C-3, corresponding to the numberings given in Table 4-2. Step responses of Rio Puerco and Guadalupe SVC are also included in the three parts of Appendix C. The results show that for the sensitivity case as dispatched in Figure 2-5: System stability is maintained for all studied N-1 contingencies. All the BB line wind power plants and the Blackwater HVDC are able to ride-through the studied faults. For certain faults such as BA-Rio Puerco, N-1 and Rio Puerco Four Corner, N-1, the previously described oscillations in reactive power measured at the Guadalupe side of the Guadalupe 345 kv Argonne 138 kv transformer was observed. Again, these oscillations originate within Aragonne Mesa and are unrelated to the SVC. The sensitivity case resulted in similar conclusions regarding SVC gain: Guadalupe SVC integral gain is recommended to be lowered to 10% - 20% comparing to the Rio Puerco SVC gain settings due to the weaker network strength at Guadalupe 345 kv station. 29

31 5 Conclusions and Recommendations PNM requested ABB to perform power flow and stability technical studies to increase the power injections on the BA-Blackwater 345 kv line (BB line) to the maximum level of 1000 MW. Previous technical studies of 832 MW power injection on the BB line have shown that a Static VAR Compensator (SVC) at the Guadalupe 345 kv station is necessary to provide the required voltage support to accommodate these power transfers. The 1000 MW BB line power injections for this study are: El Cabo wind farm at Clines Corner: 213 MW Broadview wind farm: 497 MW Taiban Mesa: 200 MW Aragonne Mesa: 90 MW The main conclusions from the study are as follows: 1. Powerflow contingency analysis showed that: Among all the contingencies, the highest post-contingency Guadalupe SVC susceptance reference is pu (1.0 pu Bref is 100 MVAr at nominal voltage, the post contingency Guadalupe voltage is about 1.019pu. As such, Qsvc is about 190 MVAr), for the double contingency of both BA-Rio Puerco 345 kv lines. No low voltage violations were identified. Minor high voltage violations occur post-contingency at the Broadview 345 kv station. These high voltages are related to set an initial voltage of pu at Broadview 345 kv based on the Broadview 297 MW PSCAD study. These violations can be ignored by modifying the voltage profile if required. For the double contingency of the BA-Rio Puerco 345 kv lines: o Overloads are identified on the BA 345/115 kv transformer and the 115 kv systems out of the BA 115 kv station. o Overload is identified on the El Cabo-BA 345 KV line. This line is fully loaded pre-contingency, with slight (2%) post-contingency overloads resulting from reduced post-contingency voltages. o A Remedial Action Scheme is planned for this contingency to trip the Taiban Mesa-Blackwater 345 kv line to maintain acceptable system performance, but was not modeled in the analysis. Overall, it can be concluded from the contingency analysis that no substantial violations occurred in the monitored areas and zones (Table 3-2). Thus an acceptable TPL performance is achieved. 2. Voltage stability margin based on QV analysis showed that: 30

32 Positive reactive margin is seen at Guadalupe 345 kv for all studied contingencies. With increased power injections on BB line, there is a significant decrease in the reactive margin but positive reactive margin is maintained for all normal and contingency conditions when the system is stressed 5% beyond the maximum transfer on the line. Additional VAR support is needed at the Guadalupe 345 kv station if voltages of 105% percent of nominal are desired under maximum loading. The Rio Puerco SVC shows relatively high capacitive output when Guadalupe voltage is at the low side. Overall, the QV analysis shows that for the analyzed outages, positive reactive margin is maintained at Guadalupe 345 kv in the voltage range of 0.95 to 1.05 pu. Thus the BB line transfer meets the WECC voltage stability margin criteria. 3. Dynamic simulation on the study base case with selected N-1 and N-2 contingencies showed that: Adequate system dynamic performance and adequate post-fault voltage recoveries are achieved. All the BB line wind power plants are able ride-through the studied faults. 4. Dynamic simulation on a sensitivity case with selected N-1 contingencies demonstrated that: With Blackwater HVDC in service with 15 MW E-W power level, system stability is maintained for all N-1 contingencies. All the BB line wind power plants and the Blackwater HVDC are able to ridethrough the studied faults The PSLF studies thus did not identify a need for additional voltage support beyond the Guadalupe SVC for the 1000 MW full buildout scenario. The system was found to meet the TPL criteria and the WECC voltage stability margin criteria. All the wind farms on the BB line were found able to ride through the studied faults with adequate post-fault voltage recoveries. However, the limitations of the positive sequence models used in this study cannot guarantee that a synchronous condenser at Blackwater station is not required to insure sufficient short 31

33 circuit capacity in the full buildout scenario for inverter based generation 2. PSCAD studies (3- phase model) are being performed in a separate study to evaluate whether a synchronous condenser at Blackwater station will be required to support the power injection conditions as stated above. 2 WECC White Paper: Value and Limitations of the Positive Sequence Generic Models of Renewable Energy Systems r%20generic%20model%20limitations%20december% docx&action=default&defaultit emopen=1 32

34 6 References [1] ITA - Broadview Full Buildout Affected System PSLF Study - Mar clean.pdf, ABB, March, [2] s from Brett Rollow of Pattern Energy, Monday, March 28, 2016 [3] Technical Data_125MVA_HICO, March [4] PNM Wind Data Request_Check List_Iberdrola docx, April [5] from PNM RE_ [External] RE_ Line impedance values for new 345 kv line at El Cabo, April 11, [6] ABB Technical Report E14417_0070_r0, Rio Puerco SVC PSLF Model, August [7] ABB Technical Report 1JNL , Blackwater HVDC Upgrade Project Main Circuit Parameters and Reactive Power Compensation, October,

35 7 Appendices Appendix A. Contingency Analysis Results, nominal load on BB line The voltage and thermal violations can be found in document: Appendix A.xlsx Voltage and thermal violations Appendix B. Dynamic Simulation Plots The dynamic simulation plots can be found in documents: Appendix B-1.pdf DYNAMIC SIMULATION PLOTS WITH GUAD SVC GAIN SETTING 1 Appendix B-2.pdf Dynamic simulation plots with Guad SVC gain setting 2, reduced Ki Appendix B-3.pdf Dynamic simulation plots with Guad SVC gain setting 3, reduced Ki Appendix C. Sensitivity Dynamic Simulation Results The sensitivity dynamic simulation plots can be found in documents: Appendix C-1.pdf Sensitivity case dynamic simulation plots with Guad SVC gain setting 1 Appendix C-2.pdf Sensitivity case dynamic simulation plots with Guad SVC gain setting 2, reduced Ki Appendix C-3.pdf Sensitivity case dynamic simulation plots with Guad SVC gain setting 3, reduced Ki 34

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and ) Cargill Power Markets LLC Transmission Service Study (OASIS # TSR 72608299 and 72827161) Prepared by: Electric Power Research Institute (EPRI) Under contract with: Public Service Company of New Mexico

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study Clean Line Energy Partners, LLC Western Spirit Clean Line 345 kv System Impact Study February, 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for the Clean Line

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY 300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY El Paso Electric Company System Planning August 2006 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY...Page 1 2.0 PURPOSE...Page 7 3.0

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY September 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXX (XXX) of XXXXXXXX by

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) Nazneen Choudhari Department of Electrical Engineering, Solapur University, Solapur Nida N Shaikh Department of Electrical

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transmission Capability (TTC) & Available Transmission Capability (ATC) On The Open Access Same-Time Information System (OASIS)

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom Grid code Compliance and Renewable Energy Projects Mick Barlow, Business Development Director, S&C Electric, United Kingdom Why Grid Codes? Permit the development of and operation of an efficient and economical

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

The Application of Power Electronics to the Alberta Grid

The Application of Power Electronics to the Alberta Grid The Application of Power Electronics to the Alberta Grid Peter Kuffel, Michael Paradis ATCO Electric APIC May 5, 2016 Power Electronics Semiconductor devices used in power transmission systems Types: Thyristor

More information

Overview of Flexible AC Transmission Systems

Overview of Flexible AC Transmission Systems Overview of Flexible AC Transmission Systems What is FACTS? Flexible AC Transmission System (FACTS): Alternating current transmission systems incorporating power electronic-based and other static controllers

More information

Statcom Operation for Wind Power Generator with Improved Transient Stability

Statcom Operation for Wind Power Generator with Improved Transient Stability Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 4, Number 3 (2014), pp. 259-264 Research India Publications http://www.ripublication.com/aeee.htm Statcom Operation for Wind Power

More information

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Transmission Planning using Production Cost Simulation & Power Flow Analysis ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha 1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Generating Unit Model Validation Policy

Generating Unit Model Validation Policy Generating Unit Model Validation Policy approved by WECC BOT WECC Generator Testing Task Force History August 10, 1996 WSCC Outage 4600 Observed COI Power (Dittmer Control Center) Real event 4400 4200

More information

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY . 120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION May 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXXXXXXXX by System Planning at El Paso Electric Company.

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Blackwater 345 kv. Cluster OASIS ID No. POI SIS FacS Location Page No. Table of Contents 1 DISIS # 8 ABQ Feb-18 Central 2

Blackwater 345 kv. Cluster OASIS ID No. POI SIS FacS Location Page No. Table of Contents 1 DISIS # 8 ABQ Feb-18 Central 2 Cluster OASIS ID No. POI SIS FacS Location Page No. Table of Contents DISIS # 8 ABQ Feb-8 Central 2 IA-PNM-26-3 La Ladera 5 kv IA-PNM-27- Route 66 5 kv IA-PNM-27-2 New 23 kv sta on Ambrosia to WM 23 kv

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

Western Electricity Coordinating Council Modeling and Validation Work Group

Western Electricity Coordinating Council Modeling and Validation Work Group Western Electricity Coordinating Council Modeling and Validation Work Group Renewable Energy Modeling Task Force Development of Planning Models dl for Solar PV Systems November 18, 2009 Phoenix, AZ Contact:

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

ECEN 667 Power System Stability Lecture 19: Load Models

ECEN 667 Power System Stability Lecture 19: Load Models ECEN 667 Power System Stability Lecture 19: Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 7 Homework 6 is

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Experiences with Wind Power Plants with Low SCR

Experiences with Wind Power Plants with Low SCR 1 Experiences with Wind Power Plants with Low SCR Lessons learned from the analysis, design and connection of wind power plants to weak electrical grids IEEE PES General Meeting Denver CO, 26 March 2015

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Power System Economics and Market Modeling

Power System Economics and Market Modeling Power System Economics and Market Modeling M5: Security Constrained Optimal Power Flow 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 NERC Load Modeling Activities Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016 Introduction Kickoff January 2016 LMTF webpage Chair: Dmitry Kosterev,

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets ISGT Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System Raju Pandey, A. K. Kori Abstract FACTS devices can be added to power transmission and distribution systems at appropriate

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Electric Power Research Institute, USA 2 ABB, USA

Electric Power Research Institute, USA 2 ABB, USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity

More information

Islanding of 24-bus IEEE Reliability Test System

Islanding of 24-bus IEEE Reliability Test System Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................

More information

Integration of Large Wind Farms into Electric Grids

Integration of Large Wind Farms into Electric Grids Integration of Large Wind Farms into Electric Grids Dr Mohammad AlZoubi Introduction Development WHAT IS NEXT!! Over the next 12 years, Europe must build new power capacity equal to half the current total.

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Experience on Technical Solutions for Grid Integration of Offshore Windfarms Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information